Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
DETAILED ESTIMATE FOR THE PROPOSED NEW CONSTRUCTION OF RESIDENTIAL BUILDING (GR
FLOOR ).
OWNER :
add
Total
3 P.C.C 1:5:10 mix for foundation , 40mm metal graded including materials & labour charges etc.
Foundation
allround 1 16.92 1.10 0.15
f/r steps 2 1.42 1.60 0.15
Basement -bulding all 1 4.77 2.77 0.10
add
Total
4 R.C.C 1:2:4 for Beam, sunshade, loft, roof, using tor steel rods
&mild steel including materials & labour charges etc.
Foundation
PB allround 1 16.92 0.30 0.10
W-SILL SLAB 2 1.68 0.23 0.05
LL ALLROUND 1 16.92 0.23 0.15
W,D-SUNSHAD 4 1.68 0.60 0.06
LOFT 1 3.00 0.45 0.08
ROOF SLAB 1 5.46 3.46 0.10
add
Page 1 of 28
DETAILED ESTIMATE
QTY REMARK
22.71
1.36
0.43
24.50 Cu.m
re river sand including materials & labour charges etc.
22.71
0.68
10.57
33.96
2.79
5.29
3.50
11.59
22.37
0.43
22.80 Cu.m
etal graded including materials & labour charges etc.
2.79
0.68
1.32
0.11
4.90 Cu.m
0.51
0.04
0.58
0.25
0.10
1.89
0.03
Page 2 of 28
Total
5 CENTERING & SCAFFOLDING WORK using tor steel rods
&mild steel including materials & labour charges etc.
w-sill slab 2 1.68 0.05
lb allround inside 1 16.00 0.15
lb allround out side 1 17.84 0.15
lb-w-bottom 2 1.22 0.23
lb-md-bottom 1 1.22 0.23
lb-d1-bottom 1 0.91 0.23
w-sunshad-bottom 2 1.68 0.60
w-sunshad-3sides 2 2.88 0.08
d-sunshad-bottom 2 1.68 0.60
d-sunshad-3sides 2 2.88 0.08
loft bottom 1 3.00 0.45
loft 1side 1 3.00 0.08
ROOF SLAB 1 5.00 3.00
roOF SLAB 4sides 1 17.84 0.10
add
Total
REINFORCEMENT WORK
PB 1 0.51 60.00
SILL SLAB+LB+LOFT+SUNSHAD 1 0.98 60.00
ROOF SLAB 1 1.89 80.00
ADD
R.R. WORK
Foundation
allround-F1 1 16.92 0.68 0.46
allround-F2 1 16.92 0.45 0.46
allround-F2 1 16.92 0.45 0.80
add
Total
Brick work in c.m. 1:5 IN FOUNDATION with chamber bricks for erials & labour charges etc.
Foundation
STEPS 1 2 1.50 1.22 0.15
STEPS 2 2 1.25 1.22 0.15
STEPS 3 2 1.00 1.22 0.15
STEPS 4 2 0.75 1.22 0.15
STEPS5 2 0.50 1.22 0.15
STEPS 6 2 0.25 1.22 0.15
add
Page 3 of 28
3.40 Cu.m
0.17
2.40
2.68
0.56
0.28
0.21
2.02
0.43
2.02
0.43
1.35
0.23
15.00
1.78
29.55
0.50
0.23
0.73
28.82
0.58
29.40 Cu.m
30.60
58.80
151.20
5.40
246.00 KG
5.29
3.50
6.09
0.21
15.10 Cu.m
with chamber bricks for erials & labour charges etc.
0.55
0.46
0.37
0.27
0.18
0.09
0.08
Page 4 of 28
Total
6 Brick work in c.m. 1:5 with chamber bricks for superstructure including materials & labour charges etc.
Ground floor -
ALLROUND 1 16.92 0.23 3.05
parapet wall all round 1 16.92 0.23 1.22
add
Total
6 DPC
Ground floor -
ALLROUND 1 16.92 0.23
add
Total
7 Plastering for all walls C.M 1:5 mix, 12mm thick thorouly inner &
outer including materials & labour charges etc
inner wall allround 1 16.00 3.05
outer wall 1 17.84 4.37
parapet inner 1 16.00 1.22
parapet top 1 16.92 0.23
STEPS 1 side 4 1.50 0.15
STEPS 2 4 1.25 0.15
STEPS 3 4 1.00 0.15
STEPS 4 4 0.75 0.15
STEPS5 4 0.50 0.15
STEPS 6 4 0.25 0.15
steps 2 2.40 1.22
add
Total
8 Plastering for ceiling in C.M 1:3 mix 10mm thick including materials & labour charges etc.
Ground floor
Roof slab
- building 1 5.00 3.00
Loft bottom+top+side 1 3.00 0.98
Page 5 of 28
2.00 Cu.m
s for superstructure including materials & labour charges etc.
11.87
4.75
16.62
0.59
0.44
0.77
0.58
2.38
14.24
0.26
14.50 Cu.m
3.89 SQ.M
0.11
4.00 SQ.M
48.80
77.96
19.52
3.89
0.90
0.75
0.60
0.45
0.30
0.15
5.86
159.18
2.56
1.91
3.34
7.82
151.36
3.64
155.00 Sq.m
15.00
2.93
Page 6 of 28
Sunshad bottom +top+front 4 1.68 1.25
Sunshad l/r side 8 0.60 0.08
add
Total
Page 7 of 28
8.40
0.36
0.81
27.50 Sq.m
Page 8 of 28
9 Tiles flooring using materials & labour charges etc.
Ground floor
- building all 1 5.00 3.00
add
Total
10 Weathering course concrete including materials & labour charges etc.
- building all 1 5.00 3.00 0.08
- building allround 1 16.00 0.20 0.08
add
Total
10 Weathering course tiles including materials & labour charges etc.
- building all 1 5.00 3.00
- building allround 1 16.00 0.20
add
Total
11 White wash for Inner & Outer including materials & labour charges etc.
plastering wall inner + outer
plastering ceilling
11 colour wash for Inner & Outer including materials & labour charges etc.
plastering wall inner + outer
18 Grill works
Page 9 of 28
15.00
0.5
15.50 Sq.m
1.20
0.26
0.04
1.50 Cu.m
15.00
3.20
0.40
18.60 Sq.m
155.00
27.50
182.50 Sq.m
155.00 Sq.m
L.S
L.S
L.S
L.S
L.S
L.S
L.S
Page 10 of 28
20 Miscellaneous items of work
ENGINEER
Page 11 of 28
L.S
L.S
ENGINEER
Page 12 of 28
DETAILED ESTIMATE
DETAILED ESTIMATE FOR THE PROPOSED NEW CONSTRUCTION OF RESIDENTIAL BUILDING (GROUN
OWNER :
add
Total
3 P.C.C 1:5:10 mix for foundation , 40mm metal graded including materials & labour charges etc.
Foundation 4 1.20 1.20 0.10
PB1 2 5.00 0.40 0.10
PB2 2 3.00 0.40 0.10
f/r steps 2 1.42 1.60 0.15
Basement -FLOORING PCC 1 5.00 3.00 0.10
add
Total
4 R.C.C 1:2:4 for Beam, sunshade, loft, roof, using tor steel rods
&mild steel including materials & labour charges etc.
Foundation 4 1.00 1.00 0.40
COLUMN 4 0.23 0.23 4.65
PB1 2 5.00 0.23 0.45
PB2 2 3.00 0.23 0.30
W-SILL SLAB 2 1.68 0.23 0.05
Page 13 of 28
DETAILED ESTIMATE
QTY REMARK
7.03
1.61
0.81
1.36
0.43
11.24 Cu.m
re river sand including materials & labour charges etc.
7.03
0.40
0.24
0.68
12.00
20.35
0.58
1.60
0.13
2.30
18.05
0.45
18.50 Cu.m
etal graded including materials & labour charges etc.
0.58
0.40
0.24
0.68
1.50
0.10
3.50 Cu.m
1.60
0.98
1.04
0.41
0.04
Page 14 of 28
CLB-MD1 1 1.68 0.23 0.15
CLB-D1 1 1.37 0.23 0.15
CL for loft 1 3.46 0.23 0.15
CLB-W 2 1.68 0.23 0.15
W,D-SUNSHAD 4 1.68 0.60 0.06
LOFT 1 3.46 0.45 0.08
ROOF BEAM1 2 5.00 0.23 0.45
ROOF BEAM2 2 3.00 0.23 0.30
ROOF SLAB 1 5.00 3.00 0.10
add
Total
4 DUMMY CONCRETE 1:3:6
&mild steel including materials & labour charges etc.
COLUMN 4 0.23 0.23 1.22
add
Total
5 CENTERING & SCAFFOLDING WORK using tor steel rods
&mild steel including materials & labour charges etc.
Foundation 4 4.00 0.40
COLUMN 4 0.92 4.65
PB1 4 5.00 0.45
PB2 4 3.00 0.30
W-SILL SLAB 4 1.68 0.05
CLB-MD1-bottom 1 1.22 0.23
CLB-MD1-side 2 1.68 0.15
CLB-D1-bottom 1 0.91 0.23
CLB-D1-side 2 1.37 0.15
CLB-W-bottom 1 1.22 0.23
CLB-W-side 2 1.68 0.15
W,D-SUNSHAD-bottom 4 1.68 0.60
W,D-SUNSHAD-frent face 4 1.68 0.05
W,D-SUNSHAD-side 8 0.60 0.08
LOFT-w-bottom 1 1.22 0.23
LOFT- cl-side 2 3.00 0.15
LOFT- bottom 1 3.00 0.45
LOFT- f+l+r side 1 4.36 0.08
ROOF BEAM1-bottom 2 5.00 0.23
ROOF BEAM1-inner side 2 5.00 0.35
ROOF BEAM1-outre side 2 5.00 0.45
ROOF BEAM2-bottom 2 3.00 0.23
ROOF BEAM2-inner side 2 3.00 0.20
ROOF BEAM2-outre side 2 3.00 0.30
ROOF SLAB-bottom 1 5.00 3.00
dummy column 4 0.92 1.22
Page 15 of 28
0.06
0.05
0.12
0.12
0.25
0.12
1.04
0.41
1.50
0.00
7.73 Cu.m
0.26
0.04
0.30 Cu.m
6.40
17.11
9.00
3.60
0.34
0.28
0.50
0.21
0.41
0.28
0.50
4.03
0.34
0.36
0.28
0.90
1.35
0.33
2.30
3.50
4.50
1.38
1.20
1.80
15.00
4.49
80.39
0.41
Page 16 of 28
D/F column-pb joint-3m 4 0.23 0.30
D/F column-rb joint-5m 4 0.23 0.45
D/F column-rb joint-3m 4 0.23 0.30
D/F SUNSHAD SIDE 4 1.68 0.08
D/F LOFT SIDE 1 3.00 0.08
add
Total
6 REINFORCEMENT WORK
Foundation 1 1.60 60.00
column 1 0.98 210.00
PB 1 1.45 60.00
ROOF beam 1 1.45 180.00
ROOF SLAB 1 1.50 80.00
SILL SLAB+LB+LOFT+SUNSHAD 1 0.75 60.00
binding wire 1
ADD
7 Brick work in c.m. 1:5 IN FOUNDATION with chamber bricks for erials & labour charges etc.
Foundation
STEPS 1 2 1.50 1.22 0.15
STEPS 2 2 1.25 1.22 0.15
STEPS 3 2 1.00 1.22 0.15
STEPS 4 2 0.75 1.22 0.15
STEPS5 2 0.50 1.22 0.15
STEPS 6 2 0.25 1.22 0.15
add
Total
6 Brick work in c.m. 1:5 with chamber bricks for superstructure including materials & labour charges etc.
Ground floor -
ALLROUND 1 16.92 0.23 3.05
parapet wall all round 1 16.92 0.23 1.22
add
Total
6 DPC
Ground floor -
ALLROUND 1 16.92 0.23
add
Page 17 of 28
0.28
0.41
0.28
0.50
0.23
2.11
78.28
0.58
78.86 SQ.M
96.00
205.80
87.00
261.00
120.00
45.00
5.74
9.26
528.00 KG
with chamber bricks for erials & labour charges etc.
0.55
0.46
0.37
0.27
0.18
0.09
0.08
2.00 Cu.m
s for superstructure including materials & labour charges etc.
11.87
4.75
16.62
0.59
0.44
0.77
0.58
2.38
14.24
0.26
14.50 Cu.m
3.89 SQ.M
0.11
Page 18 of 28
Total
7 Plastering for all walls C.M 1:5 mix, 12mm thick thorouly inner &
outer including materials & labour charges etc
inner wall allround 1 16.00 3.05
outer wall 1 17.84 4.37
parapet inner 1 16.00 1.22
parapet top 1 16.92 0.23
STEPS 1 side 4 1.50 0.15
STEPS 2 4 1.25 0.15
STEPS 3 4 1.00 0.15
STEPS 4 4 0.75 0.15
STEPS5 4 0.50 0.15
STEPS 6 4 0.25 0.15
steps 2 2.40 1.22
add
Total
8 Plastering for ceiling in C.M 1:3 mix 10mm thick including materials & labour charges etc.
Ground floor
Roof slab
- building 1 5.00 3.00
Loft bottom+top+side 1 3.00 0.98
Sunshad bottom +top+front 4 1.68 1.25
Sunshad l/r side 8 0.60 0.08
add
Total
Page 19 of 28
4.00 SQ.M
48.80
77.96
19.52
3.89
0.90
0.75
0.60
0.45
0.30
0.15
5.86
159.18
2.56
1.91
3.34
7.82
151.36
3.64
155.00 Sq.m
15.00
2.93
8.40
0.36
0.81
27.50 Sq.m
Page 20 of 28
9 Tiles flooring using materials & labour charges etc.
Ground floor
- building all 1 5.00 3.00
add
Total
10 Weathering course concrete including materials & labour charges etc.
- building all 1 5.00 3.00 0.08
- building allround 1 16.00 0.20 0.08
add
Total
10 Weathering course tiles including materials & labour charges etc.
- building all 1 5.00 3.00
- building allround 1 16.00 0.20
add
Total
11 White wash for Inner & Outer including materials & labour charges etc.
plastering wall inner + outer
plastering ceilling
11 colour wash for Inner & Outer including materials & labour charges etc.
plastering wall inner + outer
18 Grill works
Page 21 of 28
15.00
0.5
15.50 Sq.m
1.20
0.26
0.04
1.50 Cu.m
15.00
3.20
0.40
18.60 Sq.m
155.00
27.50
182.50 Sq.m
155.00 Sq.m
L.S
L.S
L.S
L.S
L.S
L.S
L.S
Page 22 of 28
20 Miscellaneous items of work
ENGINEER
Page 23 of 28
L.S
L.S
ENGINEER
Page 24 of 28
ABSTRACT ESTIMATE
ABSTRACT ESTIMATE FOR THE PROPOSED NEW CONSTRUCTION OF RESIDENTIAL BUILDING (GR
FLOOR)
OWNER :
ESTIMATE AMOUNT:-
4
R.C.C lintel,sunshade,loft,R.C.C ROOF1:2:4mix,+Steel 32.00 13500.00 Cu.m
5 R.C.C dummy column 1:3:6 mix,+Steel 1.00 7000.00 Cu.m
6 Brick work in super structure c.m. 1:5 mix 45.00 2300.00 Cu.m
7 Plastering for all walls Inner & outer in c.m 1:5 410.00 110.00 Sq.m
8 Plastering for Ceiling in C.M 1:3 mix 120.00 130.00 Sq.m
9 Tiles flooring finish 43.00 600.00 Sq.m
10 Weathering course arrangements 5.00 2300.00 Cu.m
11 White wash and colour wash inner and outer L.S
12 Doors & Windows Wood work arrangements L.S
13 Electrical work arrangements L.S
14 Plumbing work arrangements L.S
15 Septic tank work arrangements L.S
16 Bore work arrangements L.S
17 Cupboard work arrangements L.S
Page 1 of 28
18 Grill works L.S
19 Elevation item of work L.S
20 Miscellaneous items of work L.S
TOTAL
ENGINEER
Page 2 of 28
ATE
Rs. 9,00,000
25,000.00
14,820.00
23,100.00
432,000.00
7,000.00
103,500.00
45,100.00
15,600.00
25,800.00
11,500.00
35,000.00
40,000.00
45,000.00
25,000.00
35,000.00
0.00
5,000.00
Page 3 of 28
5,000.00
0.00
6,580.00
900,000.00
Page 4 of 28