Project
Management
IMMEDIATE
ACTIVITY DESCRIPTION
PREDECESSORS
A Build internal components —
B Modify roof and floor —
C Construct collection stack A
D Pour concrete and install frame B
E Build high-temperature burner C
F Install control system C
G Install air pollution device D, E
H Inspect and test F, G
A C F
Build Internal Construct Install Control
Components Collection Stack System
E H
Start Build Burner Inspect Finish
and Test
B D G
Modify Roof Pour Concrete Install Pollution
and Floor and Install Frame Device
Probability of 1 in 100
of a Occurring
Probability
Probability of 1 in 100
of b Occurring
Activity Time
Most Most Most
Optimistic Likely Pessimistic
Time Time Time
(a) (m) (b)
a + 4m + b
t=
6
• To compute the dispersion or variance of activity
completion time
2
b – a
Variance =
6
MOST EXPECTED
OPTIMISTIC, LIKELY, PESSIMISTIC, TIME, VARIANCE,
ACTIVITY a m b t = [(a + 4m + b)/6] [(b – a)/6]2
A 1 2 3 2 4/36
B 2 3 4 3 4/36
C 1 2 3 2 4/36
D 2 4 6 4 16/36
E 1 4 7 4 36/36
F 1 2 9 3 64/36
G 3 4 11 5 64/36
H 1 2 3 2 4/36
25
A 2 C 2 F 3
E 4 H 2
Start Finish
B 3 D 4 G 5
A t=2
ES = 0 EF = 0 + 2 = 2
Start
B t=3
ES = 0 EF = 0 + 3 = 3
A 2 C 2 F 3
0 2 2 4 4 7
E 4 H 2
Start 4 8 13 15 Finish
B 3 D 4 G 5
0 3 3 7 8 13
A 2 C 2 F 3
0 2 2 4 4 7
E 4 H 2
Start 4 8 13 15 Finish
B 3 D 4 G 5
0 3 3 7 8 13
A 2 C 2 F 3
0 2 2 4 4 7
0 2 2 4 10 13
E 4 H 2
Start 4 8 13 15 Finish
4 8 13 15
B 3 D 4 G 5
0 3 3 7 8 13
1 4 4 8 8 13
A 2 C 2 F 3
0 2 2 4 4 7
0 2 2 4 10 13
E 4 H 2
Start 4 8 13 15 Finish
4 8 13 15
B 3 D 4 G 5
0 3 3 7 8 13
1 4 4 8 8 13
15 Weeks
Expected Completion Time
Probability
(T ≤ 16 Weeks)
Is 71.6%
15 16 Time
Weeks Weeks
D
Activity
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Copyright ©2015 Pearson Education, Inc. Week 11 – 45
Budgeting for General Foundry
TABLE 11.5 – Activity Cost for General Foundry, Inc.
WEEK
ACTIVITY 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 TOTAL
A 11 11 22
B 10 10 10 30
C 13 13 26
D 12 12 12 12 48
E 14 14 14 14 56
F 10 10 10 30
G 16 16 16 16 16 80
H 8 8 16
308
Total to date 21 42 65 90 126 162 198 212 228 244 260 276 292 300 308
WEEK
ACTIVITY 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 TOTAL
A 11 11 22
B 10 10 10 30
C 13 13 26
D 12 12 12 12 48
E 14 14 14 14 56
F 10 10 10 30
G 16 16 16 16 16 80
H 8 8 16
308
Total to date 11 32 55 78 104 130 156 182 198 214 240 266 292 300 308
200,000 –
Budget Using
150,000 – Latest Start
Times, LS
100,000 –
50,000 –
0– | | | | | | | | | | | | | | |
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Weeks
VALUE OF
TOTAL WORK ACTIVITY
BUDGETED PERCENT OF COMPLETED ACTUAL DIFFERENCE
ACTIVITY COST ($) COMPLETION ($) COST ($) ($)
A 22,000 100 22,000 20,000 –2,000
B 30,000 100 30,000 36,000 6,000
C 26,000 100 26,000 26,000 0
D 48,000 10 4,800 6,000 1,200
E 56,000 20 11,200 20,000 8,800
F 30,000 20 6,000 4,000 –2,000
G 80,000 0 0 0 0
H 16,000 0 0 0 0
Total 100,000 112,000 12,000
Overrun
Copyright ©2015 Pearson Education, Inc. 11 – 53
Project Crashing
• Projects will sometimes have deadlines that
are impossible to meet using normal
procedures
• By using exceptional methods it may be
possible to finish the project in less time
• Costs usually increase
• Reducing a project’s completion time is called
crashing
Activity
Cost
Crash
$30,000 —
Normal
Normal —
Cost
| | |
1 2 3 Time (Weeks)
Crash Time Normal Time
Copyright ©2015 Pearson Education, Inc. 11 – 60
Other Topics in Project
Management
• Subprojects
– For extremely large projects, an activity may be made of
several smaller subactivities
• Milestones
– Major events in a project are often referred to as milestones
• Resource Leveling
– Adjusts the activity start away from the early start so that
resource utilization is more evenly distributed over time
• Software
– Numerous project management software packages
– Most of these create PERT charts and Gantt charts and can
be used to develop budget schedules, adjust future start
times, and level resource utilization