Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Assignment 2
1. Overview
This assessment is designed to test your achievement of selected learning objectives of Modules 6 to
9. In particular, the assignment involves estimation of urban design discharges, reservoir routing and
water balance. It is intended to reinforce and extend your knowledge on urban hydrology, using a
residential subdivision located in Townsville as a case study.
1|Pa g e
ENV3105 Hydrology 2012
Major system check. The subdivision is situated near the Townsville Airport. Use the following
information:
1. The road kerbs are vertical and are 200mm high, 300mm gutter width with a 1:30 crossfall.
The street in the subdivision will have a 10m wide carriageway with a single crossfall of 1:30
(ie no central crown).
2. The street has a 20m wide road reserve. Adopt 80% impervious for the road reserve.
3. The area upstream of the subdivision (‘tributary area’ on the plan) is public open space and
will not be developed. Runoff from this area needs to be allowed for in the hydrologic
calculations.
4. The proposed lots will be developed to ‘urban residential – low density’ with an expected %
impervious within the lot area of 55%.
5. For partial area calculations, assume a critical duration of 5 minutes
6. The minimum travel time to a pit is 5 minutes with a maximum of 20 minutes.
7. The minimum longitudinal grade of grass swales and catch drains is 0.5%.
8. Gutter flows in the street are not to exceed 3.3m for the Minor system. The maximum flow
depth at the road kerb during the Major storm is not to exceed 0.35m to contain flooding to
within the road reserve.
9. Select a gully pit as required based on the 2400 to 4800 mm lintel range. Include an
appropriate blockage factor for the gully pits.
10. Unless otherwise defined, the drainage design will be in accordance to the Queensland Urban
Drainage Manual (QUDM)
11. The capacity of field inlets shall be estimated based on QUDM 7.05.4
12. Undertake the Major design flow checks for the roadway at Pits 1B, 1D and 1E.
The lot areas have been predetermined and are provided in Table 2.
2|Pa g e
ENV3105 Hydrology 2012
Sheet Hints
1 For the purpose of the assignment, it is acceptable to scale off lengths and areas based on
the layout plan (Figure 1). After marking the subcatchment boundaries, the areas can be
determined by any of several methods. These methods include 1) manually overlying a
grid over the plan and counting the grid squares (an inaccurate method), 2) using a
planimeter available for oncampus students by contacting Clinton Caudell (Technical
Officer – Spatial Science), 3) importing the plan into a GIS or CAD package and using the
area computation features of this software. Road slope can be estimated from the road
surface levels (Table 1) and distances scaled off Figure 1. Make sure that you have
allowed for drainage of the road reserve, the upstream public open space and developed
lots in the pit discharge computations. Lots draining to the same pit can be grouped
together in the calculations. Provide partial area checks at all pits. QUDM 4.06 provides
guidance on determination of flow travel times – refer to QUDM 4.06.7 for estimation of
travel time along open drains and swales. Flows to some pits include different types of
flowpaths (eg overland + catch drain), so define each flowpath component on the
‘remarks’ column of Sheet 1.
2 As for Sheet 1, the longest travel time is used to determine the full area design discharge.
3 Remember the roadway has a single, one-way cross fall to the kerb. It is acceptable to
scale up the CA values based on the frequency factor ratio F100/F2– this will simplify the
calculations
3|Pa g e
ENV3105 Hydrology 2012
peak 100 year ARI discharge from the proposed development catchment (including the public open
space) to at least the ‘pre-developed’ peak 100 year ARI discharge.
For the purpose of analysis, the proposed basin has the following characteristics:
1. The basin floor is rectangular (28m x 17m) and is assumed to be level (a floor slope draining
to Pit 1F would be required, but assume this to be zero)
2. The internal batters of the basin are 4H:1V
3. The basin is drained by Pit 1F, which also acts as a surcharge pit if the Minor system pipe
capacity is exceeded.
4. The basin can overflow to the street, controlled by a broadcrested weir with a crest level 1.2m
above the basin floor level. The weir crest length is 4m.
5. The maximum flow depth over the weir should not exceed 0.25m in the Major storm.
The scope of Part B is to undertake a hydrologic analysis to answer the following questions:
Q1. What is the estimated 100 year ARI peak discharge for the pre-developed catchment,
assuming that it is rural with no urban development?
Q2. What is the estimated 100 year ARI peak discharge for the developed catchment at the basin
site?
Q3. Is the proposed basin adequate to achieve the desired peak discharge reduction?
Q4. Do you think the inflow discharge that you used is the critical duration for the detention basin
(i.e the duration that gives the largest outflow from the basin)? What approach would you use
to obtain a better estimate of the critical duration?
Questions Hints
Q1 Assume the catchment outlet is at Pit 1F. Some redrawing of the catchment boundary is
required to define the ‘pre-developed’ catchment (as the proposed development as
modified flow paths due to catch drains and lots). QUDM 4.06.11 has guidance on rural
time of concentration. However, for reasons of consistency use the same overland time of
concentration methods adopted in Part A. Note the differences in the time of
concentration associated with the QUDM 4.06.11 recommended methods.
Q2 For simplicity, assume that Pit 1F is fully blocked, the Minor pipe system has adequate
capacity to handle discharges up to 2 year ARI – so the basin receives road surface flow
only and the only basin outlet is the weir.
Q3 Use reservoir routing to make the assessment. This requires adopting an inflow
hydrograph to use in the analysis. Assume that the hydrograph has a symmetrical
triangular shape. To define the hydrograph, round off the time of concentration estimate
to the nearest minute – this will simplify your computations. Interpolation of data within
the storage curve is preferred to obtain more accurate results, rather than using Excel
‘look-up’ functions.
Q4 A discussion on critical duration can be found on page 115, Study Book.
4|Pa g e
ENV3105 Hydrology 2012
Questions Hints
Q1 Account for the runoff contributions from both impervious and pervious areas within the
residential catchment. Consider how the runoff coefficient may change with the amount
of rainfall.
5|Pa g e
ENV3105 Hydrology 2012
Q2 Consider how more sophisticated methods could be used and how the simplistic
assumptions may impact on the results.
5. Submission
Your submission for Assignment 2 should include:
A report that documents the hydrological analyses that have completed. A marking scheme is
provided as Table 5. Use this marking scheme to check that you have addressed the full
scope of the work. If an element of the assignment has not been documented in the file
report than no marks will be given for that element. For reasons of consistency, a report
template (ENV3105Report2Template.docx) must be downloaded from Study Desk and used
to report your work. Complete each section of the report.
Part of the available marks has been allocated to reward reporting that is well set out and easy to
follow. Submissions that are untidy and/or poorly structured and thus difficult to assess will attract
less marks for this element.
Electronic submission of this assignment is required. One ZIP file will be accepted containing:
1. A single Office Word document based on the template provided (rename the file based on the
convention below)
2. A single EXCEL spreadsheet
The following filename convention shall be used: *Ass2.zip, *Ass2.docx and *Ass2.xlsx, where * is
your student number.
6. Marking Scheme
Table 6: Assignment 2 Marking Scheme
6|Pa g e
ENV3105 Hydrology 2012
7|Pa g e