VICINITY PLAN:
PROJECT SITE
MAKKAH
PLANT NORTH= Y MAKKAH
REAL NORTH

MYAS
GRID MYAS
MAKKAH GRID

GRID
MYAS PLANT EAST=X
REAL EAST

19 GUARD ROOM 1

GUARD ROOM 2 19

21 GREEN AREA 21 GREEN AREA


28 GREEN AREA
MASTER KEY PLAN:
21 GREEN AREA

PROJECT SITE

07
ADMINISTRATION
18

ROAD 1
WEIGHING BRIDGES
ROAD 12

CHEC / IGCC

21 GREEN AREA 21 GREEN AREA


ROAD 16

ROAD 1A
RESRECO
SOLB STEEL

ROAD 18

13
PRAYER AREA

ASPHALT
KEY PLAN:
21
THIS BUILDING

21 GREEN AREA 21 GREEN AREA

SLOPE 15% SLOPE 15% SLOPE 15% SLOPE 15%

SLOPE 15% SLOPE 15% SLOPE 15% SLOPE 15%

SLOPE 15% SLOPE 15% SLOPE 15% SLOPE 15%

08
SLOPE 15% SLOPE 15% SLOPE 15% SLOPE 15% SLOPE 15% SLOPE 15% FACILITY AREA AND CANTEEN

SLOPE 15% 03 SLOPE 15% SLOPE 15% SLOPE 15% SLOPE 15%
03 SLOPE 15%

03 WHITE SUGAR 01
WHITE SUGAR 02
PAKING STATION
SLOPE 15% SLOPE 15% SLOPE 15% SLOPE 15% SLOPE 15% SLOPE 15%

SLOPE 15% SLOPE 15% SLOPE 15% SLOPE 15%

SLOPE 15% SLOPE 15% 21


SLOPE 15% SLOPE 15% SLOPE 15% SLOPE 15%

21 GREEN AREA

21

GREEN AREA
FLOOR FINISH TYPES
CODITIONING SILOS 14
ASPHALT
INTERLOCK
GRASS

20B SLOPE 10% SLOPE 10% SLOPE 10%


20C

SLOPE 14% SLOPE 14%

SLOPE 10% SLOPE 10% SLOPE 10%

SLOPE 14% SLOPE 14%

SLOPE 10% SLOPE 10% SLOPE 10%


GENERAL NOTES:
04
WORKSHOP
SLOPE 15% SLOPE 15%
1) ALL DIMENSIONS ARE IN MILLIMETERS & LEVELS IN METERS UNLESS OTHERWISE SPECIFIED.
SLOPE 14% SLOPE 14%
SLOPE 10% SLOPE 10% SLOPE 10% SLOPE 15% SLOPE 15%
2) ALL LEVELS INDICATED ARE FINISHED FLOOR LEVELS UNLESS OTHERWISE INDICATED.
SLOPE 15%

09
SLOPE 15%
3) THIS DRAWING TO BE READ IN CONJUNCTION WITH RELEVANT ARCHITECTURAL & SPECIFICATION'S THE
SLOPE 10% SLOPE 10% SLOPE 10% STORE BUILDING
SLOPE 15% SLOPE 15%
CONTRACTOR SHALL COORDINATE THESE DRAWINGS AND REPORT IF ANY DISCREPANCY FOR CLARIFICATION
1
FUTUR PROCESS BUILDING 02
01
SLOPE 10% SLOPE 10% SLOPE 10% SLOPE 15% SLOPE 15% BEFORE PROCEEDING WITH THE WORK INVOLVED.
SLOPE 14% SLOPE 14%
PROCESS BUILDING 01
4) ALL MATERIALS SHOULD BE APPROVED BEFORE STARTING.
20A
5) CONTRACTOR HAS TO SUBMIT SHOP DRAWINGS WITH DETAILS AND SAMPLES FOR APPROVAL PRIOR OF
EXECUTION OF WORK.
SLOPE 14% SLOPE 14%

AIR COMPRESSOR STATION

SLOPE 15% SLOPE 15%


11
22 GREEN AREA
1500
SLOPE 14% SLOPE 14%

01 04/08/2017 BIA AS PER R.C. COMMENTS

00 01/02/2017 BIA FIRST EDITION

SLOPE 15% SLOPE 15%


10
CO2 STATION
REV. NO DATE BY DESCRIPTION APPROVED BY.

KINGDOM OF SAUDI ARABIA


SLOPE 100% SLOPE 100%
SLOPE 100% SLOPE 100%

17 ROYAL COMMISSION FOR JUBAIL & YANBU


20D BOILERS

DIRECTORATE GENERAL FOR YANBU PROJECT


SLOPE 100% SLOPE 100% 17
SLOPE 100% SLOPE 100%
POWER HOUSE

PROJECT : ALREEF SUGAR REFINERY CO. (JSC)


SLOPE 100% SLOPE 100%
SLOPE 100% SLOPE 100%

ALREEF SUGAR REFINERY CO. (JSC)


SLOPE 100% SLOPE 100% SLOPE 100% SLOPE 100% 20E 39
WATER TANK

FIRE WATER PUMPS 12


DRAWING TITLE :
02
RAW SUGAR STORAGE 02
02
RAW SUGAR STORAGE 01
06
500

SITE PLAN
FUEL TANKS

SLOPE 100% SLOPE 100% SLOPE 100% SLOPE 100%

16
SEA WATER TREATMENT STATION

SLOPE 100% SLOPE 100% SLOPE 100% SLOPE 100%


EPC CONTRACTOR & DESIGNER:
BIOMASS INDUSTRIES ASSOCIATES
Address: Avenue de la bourse, Lac2 Immeuble El wafa ,
SLOPE 100%
SLOPE 100% SLOPE 100%
SLOPE 100%
Bureau N°B2, 2ème étage 1053 Tunis/Tunisie
Tel: +216 71 190 184
Fax: +216 71 190 184
Email: info@bia-industries.com
BIOMASS INDUSTRIES ASSOCIATES
15
05
MASTE WATER TREATMENT

MOLASSE TANKS

SLOPE 100%
SLOPE 100% SLOPE 100%
SLOPE 100%
DESIGNED BY : BIA
20F
COSMOS-E BIOMASS INDUSTRIES ASSOCIATES

E
ENGINEERS & CONSULTANT

REVIEWED BY : COSMOS
CIVIL & STEEL CONSULTANT
Engineers & Consultants

ROAD 18 DESIGNED BY: ALTORATH ENGINEERING CONSULTANTS


CONSULTING ENGINEERS & PROJECT MANAGERS

SHE

RD
WA
IKH

A
DRAWN BY :
H

E
K
AL C
I FA E X ELL EN

I
IF TR
C

AIC

DE

E
C
Net I
CHECKED BY :

ME

M
NA
SY

T
ST A
NE M EG

ILA UQ DE
SECT.MANAGER : YT
ABU DHABI TEL:+970-2-6775900 FAX: +971-2-6788620 P.O.BOX4644

IF
METSY
ISO

ITR EC
9001:2000
WEB.SITE: WWW.MAZROUEIGROUP.COM
DIRECTOR : VINCOTTE
INTERNATIONAL
AIB

E-MAIL: ALTORATH@MAZROUEIGROUP.COM
SITE PLAN A/E APPROVAL : WBS.NO : DRAWING NO : AR-A1-000-005
AR-A1-000-005 AR-A1-000-005 SCALE: N.T.S
R/C APPROVAL : CONT.NO :

DATE : JULY 2017 SCALE : 1/100 REVISION NO : 01 AR-A1-000-005 OF 12