Sei sulla pagina 1di 129

VALORIZACION DE AVANCE FISICO Nº 03 MARZO-ABRIL 2010 - II ETAPA

DEL 01/03/2010 AL 09/04/2010


OBRA : "MEJORAMIENTO DE PISTAS Y VEREDAS DE AV. JOSE OLAYA TRAMO : AV. GIRALDEZ - PROLONG. PUNO RESIDENTE : ING. MIRIAM VILLAFUERTE PACHE

CODIGO : 15-036-074-2063804-2164992-0086 SUPERVISOR : ING. JORGE CHUCOS DE LA CRUZ


: PAVIMENTACION FLEXIBLE
CLIENTE : MUNICIPALIDAD PROVINCIAL DE HUANCAYO

Departamento : JUNIN Provincia : HUANCAYO Distrito : HUANCAYO Fecha de Presentacion :13 de Abril del 2010
PRESUPUESTO REFERENCIAL AVANCES
ITEM DESCRIPCION Unidad Metrado Precio Parcial MES ANTERIOR MES ACTUAL ACUMULADO
METRADO VALORIZA. S/. % METRADO VALORIZ. S/. % METRADO VALORIZ. S/. %
01.00 OBRAS PROVISIONALES
01.01 ALMACEN Y CASETA DE GUARDIANIA MES 0.25 437.84 109.46 0.25 109.46 100.00 0.00 0.00 0.00 0.25 109.46 100.00
01.02 CARTEL DE IDENTIFICACION DE OBRA UND 0.25 1,902.11 475.53 0.00 0.00 0.00 0.25 475.53 100.00 0.25 475.53 100.00
02.00 OBRAS PRELIMINARES
02.01 TRAZO Y REPLANTEO M2 1,904.10 0.87 1,656.57 1904.10 1656.57 100.00 0.00 0.00 0.00 1904.10 1656.57 100.00
02.02 TRAZO Y REPLANTEO DURANTE LA EJECUCION M2 1,904.08 0.85 1,618.47 1626.09 1382.18 85.40 277.99 236.29 14.60 1904.08 1618.47 100.00
02.03 ROTURA DE VEREDAS M3 0.48 42.58 20.44 0.48 20.44 100.00 0.00 0.00 0.00 0.48 20.44 100.00
03.00 EXPLANACIONES
03.01 MOVIMIENTO DE TIERRAS
03.01.01 CORTE DE TERRENO DE SUB RASANTE M3 1,149.87 5.09 5,852.84 1083.27 5513.84 94.21 66.60 338.99 5.79 1149.87 5852.84 100.00
03.01.02 CORTE PARA MEJORAM. DE SUB BASE M3 46.08 5.08 234.09 46.08 234.09 100.00 0.00 0.00 0.00 46.08 234.09 100.00
03.01.03 CORTE DE TERRENO MANUAL M3 59.80 21.45 1,282.71 59.80 1282.71 100.00 0.00 0.00 0.00 59.80 1282.71 100.00
03.01.04 EXCAVACION MANUAL PARA CUNETA M3 18.29 21.45 392.32 0.00 0.00 0.00 18.29 392.32 100.00 18.29 392.32 100.00
03.01.05 EXCAVACION MANUAL PARA SARDINEL M3 28.17 21.45 604.25 28.17 604.25 100.00 0.00 0.00 0.00 28.17 604.25 100.00
03.01.06 EXCAVACION MANUAL EN BADEN M3 4.73 21.04 99.52 0.00 0.00 0.00 4.73 99.52 100.00 4.73 99.52 100.00
03.02 ELIMINACION DE MATERIAL EXCEDENTE
03.02.01 ACARREO INTERNO DE MATERIAL M3 133.80 17.94 2,400.37 133.80 2400.37 100.00 0.00 0.00 0.00 133.80 2400.37 100.00
03.02.02 CARGUIO (ELIM.DE MATERIAL EXCEDENTE) M3 1,568.94 3.63 5,695.25 1568.94 5695.25 100.00 0.00 0.00 0.00 1568.94 5695.25 100.00
03.02.03 TRANSPORTE (ELIM. MAT. EXCEDENTE) M3 1,568.94 5.70 8,942.96 1568.94 8942.96 100.00 0.00 0.00 0.00 1568.94 8942.96 100.00
03.02.04 ESCARIFICADO PERFILADO/COMPACTADO M2 1,421.70 2.28 3,241.48 1421.70 3241.48 100.00 0.00 0.00 0.00 1421.70 3241.48 100.00
04.00 PAVIMENTOS
04.01 MEJORAMIENTO DE SUB RASANTE
04.01.01 EXTRACCION DE MATERIAL P/MEJ. SUB RASANTE M3 305.70 7.42 2,268.27 305.70 2268.29 100.00 0.00 0.00 0.00 305.70 2268.29 100.00
04.01.02 SELECCION DE MATERIAL P/ MEJ DE SUB RASANTE M3 251.00 4.68 1,174.68 251.00 1174.68 100.00 0.00 0.00 0.00 251.00 1174.68 100.00
04.01.03 CARGUIO DE (MEJ. S-R) M3 251.00 3.83 961.33 251.00 961.33 100.00 0.00 0.00 0.00 251.00 961.33 100.00
04.01.04 TRANSPORTE (MEJ. S-R) M3 251.00 5.70 1,430.70 251.00 1430.70 100.00 0.00 0.00 0.00 251.00 1430.70 100.00
04.01.05 EXT. RIEGO Y COMPC. P/MEJ DE SUB RASANTE M2 1,165.00 2.18 2,539.70 1165.00 2539.70 100.00 0.00 0.00 0.00 1165.00 2539.70 100.00
04.02 SUB BASE GRANULAR
04.02.01 EXTRACCION DE MATERIAL PARA SUB BASE M3 398.08 7.41 2,949.77 398.08 2949.77 100.00 0.00 0.00 0.00 398.08 2949.77 100.00
04.02.02 SELECCION DE MATERIAL P/ SUB BASE GRANULAR M3 369.64 4.68 1,729.92 365.00 1708.20 98.74 4.64 21.72 1.26 369.64 1729.92 100.00
04.02.03 CARGUIO DE S-B M3 369.64 3.92 1,448.99 315.00 1234.80 85.22 54.64 214.19 14.78 369.64 1448.99 100.00
04.02.04 TRANSPORTE DE S.B. M3 369.64 5.70 2,106.95 315.00 1795.50 85.22 54.64 311.45 14.78 369.64 2106.95 100.00
04.02.05 EXT. RIEGO Y COMPC. DE SUB BASE E= 0.20m. M2 1,421.70 2.31 3,284.13 1195.00 2760.45 84.05 226.70 523.68 15.95 1421.70 3284.13 100.00
04.03 BASE GRANULAR
04.03.01 EXTRACCION DE MATERIAL PARA BASE M3 471.44 7.41 3,493.37 430.00 3186.30 91.21 41.44 307.07 8.79 471.44 3493.37 100.00
04.03.02 SELECCION DE MATERIAL P/ BASE GRANULAR M3 437.76 4.68 2,048.72 345.00 1614.60 78.81 92.76 434.12 21.19 437.76 2048.72 100.00
04.03.03 CARGUIO DE B. M3 437.76 3.92 1,716.02 345.00 1352.40 78.81 92.76 363.62 21.19 437.76 1716.02 100.00
04.03.04 TRANSPORTE DE B. M3 437.76 5.70 2,495.23 345.00 1966.50 78.81 92.76 528.73 21.19 437.76 2495.23 100.00
04.03.05 EXT. RIEGO Y COMPC. DE BASE E= 0.20m. M2 1,421.70 2.32 3,298.34 75.00 174.00 5.28 1346.70 3124.34 94.72 1421.70 3298.34 100.00
04.04 CARPETA ASFALTICA
04.04.01 IMPRIMACION ASFALTICA M2 1,097.20 5.46 5,990.71 0.00 0.00 0.00 608.48 3322.30 55.46 608.48 3322.30 55.46
04.04.02 CARPETA ASFALTICA EN CALIENTE E= 3" M2 1,097.20 52.36 57,449.39 0.00 0.00 0.00 608.48 31860.01 55.46 608.48 31860.01 55.46
05.00 DRENAJE
05.01 ENCOFRADO Y DESENCOFRADO DE CUNETAS M2 45.72 36.99 1,691.18 0.66 24.41 1.44 15.00 554.85 32.81 15.66 579.26 34.25
05.02 CUNETAS CONCRETO F'C=175 KG/CM2 M3 61.23 281.43 17,231.96 0.26 73.17 0.42 16.40 4615.45 26.78 16.66 4688.62 27.21
06.00 BADEN
06.01 BADEN CONCRETO F'C=210 KG/CM2 M3 4.73 285.88 1,352.21 0.00 0.00 0.00 4.73 1352.21 100.00 4.73 1352.21 100.00
06.02 BADEN ENCOFRADO Y DESENCOFRADO M2 3.94 36.99 145.74 0.00 0.00 0.00 3.94 145.74 100.00 3.94 145.74 100.00
07.00 SARDINEL INEXPUESTO
07.01 SARDINEL INEXP. CONCRETO F'C=210 KG/CM2 M3 3.43 298.61 1,024.23 0.00 0.00 0.00 0.86 256.80 25.07 0.86 256.80 25.07
07.02 SARDINEL INEXP. ENCOFRADO Y DESENCOFRADO M2 6.86 26.86 184.26 0.00 0.00 6.86 184.26 100.00 6.86 184.26 100.00
08.00 ACERA PEATONAL
08.01 SARDINEL EXPUESTO
08.01.01 SARDINEL EXP. ENCOFRADO Y DESENCOFRADO M2 170.63 30.13 5,141.08 170.63 5141.08 100.00 0.00 0.00 0.00 170.63 5141.08 100.00
08.01.02 SARDINEL EXP. CONCRETO F'C=175 KG/CM2 M3 25.59 270.17 6,913.65 22.47 6070.72 87.81 0.00 0.00 0.00 22.47 6070.72 87.81
VEREDAS
08.02.01 REFINE Y NIVELACION M2 524.00 1.41 738.84 336.80 474.89 64.27 0.00 0.00 0.00 336.80 474.89 64.27
08.02.02 RELLENO Y COMPACTADO DE VEREDA M2 524.00 4.60 2,410.40 405.50 1865.30 77.39 0.00 0.00 0.00 405.50 1865.30 77.39
08.02.03 VEREDA ENCOFRADO Y DESENCOFRADO M2 12.57 29.31 368.43 12.57 368.43 100.00 0.00 0.00 0.00 12.57 368.43 100.00
08.02.04 VEREDAS CONCRETO F'C=175 KG/CM2 M2 524.00 29.26 15,332.24 341.78 10000.48 65.23 0.00 0.00 0.00 341.78 10000.48 65.23
9.00 RAMPAS
9.01 ENCOFRADO Y DESENCOFRADO RAMPA M2 2.31 31.63 73.07 0.96 30.36 41.56 0.00 0.00 0.00 0.96 30.36 41.56
9.02 RAMPA CONCRETO F'C=175 KG/CM2 M2 10.80 29.88 322.70 2.80 83.66 25.93 2.60 77.69 24.07 5.40 161.35 50.00
10.00 JUNTAS
10.01 RELLENO DE JUNTAS M 179.09 1.96 351.02 0.00 0.00 0.00 179.09 351.02 100.00 179.09 351.02 100.00
11.00 AREAS VERDES
11.01 SUMINISTRO DE TIERRA AGRICOLA M3 72.30 33.76 2,440.85 72.30 2440.85 100.00 0.00 0.00 0.00 72.30 2440.85 100.00
11.02 COLOCACION DE GRASS M2 241.00 10.20 2,458.20 241.00 2458.20 100.00 0.00 0.00 0.00 241.00 2458.20 100.00
11.03 COLOCACION DE PLANTONES UND 20.00 16.79 335.80 10.00 167.90 50.00 10.00 167.90 50.00 20.00 335.80 100.00
12.00 SEÑALIZACION
12.01 SEÑALIZACION HORIZONTAL
12.01.01 PINTURA LINEAL EN BORDE DE VIA M 228.62 3.97 907.62 0.00 0.00 0.00 228.62 907.62 100.00 228.62 907.62 100.00
12.01.02 PINTURA LINEAL CONTINUA EN EJE DE VIA M 95.70 3.90 373.23 0.00 0.00 0.00 95.70 373.23 100.00 95.70 373.23 100.00
12.01.03 PINTURA LINEAL DISCONTINUA EN EJE DE VIA M 191.00 3.24 618.84 0.00 0.00 0.00 191.00 618.84 100.00 191.00 618.84 100.00
12.01.04 PINTURA DE SIMBOLOS Y FLECHAS M2 12.00 12.69 152.28 0.00 0.00 0.00 12.00 152.28 100.00 12.00 152.28 100.00
12.02 SEÑALIZACION VERTICAL
12.02.01 SEÑALES TIPO R (90cM x 60cm) UND 1.00 384.08 384.08 0.00 0.00 0.00 1.00 384.08 100.00 1.00 384.08 100.00
12.02.02 SEÑALES TIPO F UND 1.00 358.52 358.52 0.00 0.00 0.00 1.00 358.52 100.00 1.00 358.52 100.00
13.00 EQUIPAMIENTO
13.01 MOVILIARIO URBANO UND 3.00 545.16 1,635.48 3.00 1635.48 100.00 0.00 0.00 0.00 3.00 1635.48 100.00
13.02 SUMINISTRO Y COLOCACION DE TACHOS DE BASURA UND 2.00 399.03 798.06 0.00 0.00 0.00 2.00 798.06 100.00 2.00 798.06 100.00
14.00 RECONEXIONES
14.01 RECONEXIONES DE PUNTOS DE AGUA PTO 6.00 13.99 83.94 6.00 83.94 100.00 0.00 0.00 0.00 6.00 83.94 100.00
14.02 RECONEXION DE CAJA MEDIDOR DE AGUA PTO 6.00 12.96 77.76 6.00 77.76 100.00 0.00 0.00 0.00 6.00 77.76 100.00
14.03 RECONEXION DE INSTALACIONES DE DESAGUE PTO 6.00 17.56 105.36 6.00 105.36 100.00 0.00 0.00 0.00 6.00 105.36 100.00
14.04 RECONEXION DE CAJA DE REGISTRO DE DESAGUE PTO 6.00 11.31 67.86 6.00 67.86 100.00 0.00 0.00 0.00 6.00 67.86 100.00
15.00 VARIOS
15.01 LIMPIEZA FINAL DE OBRA M2 2,000.00 0.66 1,320.00 0.00 0.00 0.00 2000.00 1320.00 100.00 2000.00 1320.00 100.00

DESAGUE PLUVIAL

01.00 TRABAJOS PRELIMINARES


01.01 TRAZO NIVELES Y REPLANTEO DE ZANJA M 395.00 0.56 221.20 395.00 221.20 100.00 0.00 0.00 0.00 395.00 221.20 100.00
02.00 MOVIMIENTO DE TIERRAS

02.01 EXCAVACIONES
02.01.01 EXCAVACION PARA BUZONES M3 32.63 21.45 699.91 32.63 699.91 100.00 0.00 0.00 0.00 32.63 699.91 100.00
02.01.02 EXCAVACION DE ZANJAS - MANUAL M 471.20 15.02 7,077.42 471.20 7077.42 100.00 0.00 0.00 0.00 471.20 7077.42 100.00
02.01.03 EXCAVACION PARA SUMIDEROS M3 7.83 28.75 225.11 4.05 116.44 51.72 3.78 108.68 48.28 7.83 225.11 100.00
02.01.04 REFINE Y NIVELACION EN ZANJAS M 471.20 1.85 871.72 466.10 862.29 98.92 5.10 9.44 1.08 471.20 871.72 100.00
02.02 CAMAS DE APOYO
02.02.01 PREPARACION DE CAMAS DE APOYO M 471.20 4.61 2,172.23 411.40 1896.55 87.31 39.00 179.79 8.28 450.40 2076.34 95.59
02.03 RELLENOS
02.03.01 EXTRACCION DE MAT. P/RELLENO M3 230.89 6.39 1,475.39 230.89 1475.39 100.00 0.00 0.00 0.00 230.89 1475.39 100.00
02.03.02 SELECCIÓN DE MATERIAL P/RELLENO M3 214.40 3.42 733.25 150.00 513.00 69.96 0.00 0.00 0.00 150.00 513.00 69.96
02.03.03 CARGUIO P/ RELLENO M3 214.40 4.16 891.90 150.00 624.00 69.96 0.00 0.00 0.00 150.00 624.00 69.96
02.03.04 TRANSPORTE P/ RELLENO M3 214.40 5.52 1,183.49 150.00 828.00 69.96 0.00 0.00 0.00 150.00 828.00 69.96
02.03.05 RELLENO Y COMPACTADO DE ZANJA M 471.20 14.97 7,053.86 434.40 6502.97 92.19 36.80 550.90 7.81 471.20 7053.86 100.00
02.04 ELIMINACION DE MATERIAL EXCEDENTE
02.04.01 ACARREO INTERNO DE MATERIAL M3 48.55 13.46 653.48 48.55 653.48 100.00 0.00 0.00 0.00 48.55 653.48 100.00
02.04.02 CARGUIO (ELIM. MAT. EXCEDENTE) M3 48.55 3.92 190.32 48.55 190.32 100.00 0.00 0.00 0.00 48.55 190.32 100.00
02.04.03 TRANSPORTE (ELIM. MAT. EXCEDENTE) M3 48.55 5.70 276.74 48.55 276.74 100.00 0.00 0.00 0.00 48.55 276.74 100.00
03.00 OBRAS DE CONCRETO ARMADO
03.01 CONSTRUCCION DE BUZONES
03.01.01 CONSTRUCCION DE BUZON H =1..50m UND 4.00 1159.37 4,637.48 2.20 2550.61 55.00 1.00 1159.37 25.00 3.20 3709.98 80.00
03.01.02 CONSTRUCCION DE BUZON H =1.70m UND 5.00 1,066.12 5,330.60 4.80 5117.38 96.00 0.20 213.22 4.00 5.00 5330.60 100.00
03.01.03 DADOS DE CONCRETO F'C= 140KG/CM² UND 18.00 63.27 1,138.86 11.00 695.97 61.11 4.00 253.08 22.22 15.00 949.05 83.33
03.02 ENCIMADO DE BUZONES
03.02.01 CONST. ENCIM.BUZON H= 0.45m. S.M.yTAPA UND 1.00 344.68 344.68 0.00 0.00 0.00 1.00 344.68 100.00 1.00 344.68 100.00
03.02.02 DADOS DE CONCRETO F'C= 140KG/CM² UND 5.00 63.27 316.35 3.00 189.81 60.00 1.00 63.27 20.00 4.00 253.08 80.00
03.03 SUMIDEROS
03.03.01 CONSTRUCCION DE SUMIDERO UND 6.00 423.36 2,540.16 3.00 1270.08 50.00 0.00 0.00 0.00 3.00 1270.08 50.00
03.03.02 CONSTRUCCION DE CAJA RECEPTOR UND 6.00 60.58 363.48 3.00 181.74 50.00 0.00 0.00 0.00 3.00 181.74 50.00
04.00 SUMINISTRO Y TENDIDO DE TUBERIA
04.01 TENDIDO DE TUBERIA UPVC U/F S-25 D=12" M 395.00 70.77 27,954.15 395.00 27954.15 100.00 0.00 0.00 0.00 395.00 27954.15 100.00
04.02 TENDIDO DE TUBERIA UPVC U/F S-25 D=10" M 22.20 54.39 1,207.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.03 TENDIDO DE TUBERIA UPVC U/F S-25 D=8" M 54.00 42.40 2,289.60 20.00 848.00 37.04 0.00 0.00 0.00 20.00 848.00 37.04
04.04 SUMINISTRO Y COLOCACION DE ACCESORIOS UND 6.00 15.35 92.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.00 PRUEBA HIDRAULICA
05.01 PRUEBA A ZANJA TAPADA P/TUBERIA M 471.20 1.17 551.30 412.00 482.04 87.44 0.00 0.00 0.00 412.00 482.04 87.44
06.00 CARPINTERIA METALICA
06.01 VENTANA DE SUMIDERO 0.70x0.80M UND 6.00 93.49 560.94 3.00 280.47 50.00 0.00 0.00 0.00 3.00 280.47 50.00
06.02 REJILLA DE CAJA UND 6.00 114.81 688.86 3.00 344.43 50.00 0.00 0.00 0.00 3.00 344.43 50.00
COSTO DIRECTO 01 PAVIMENTACION FLEXIBLE 194411.37 89370.68 45.97% 55172.43 28.38% 144543.11 74.35%
COSTO DIRECTO 02 DESAGUE PLUVIAL 71742.04 61852.38 86.21% 2882.42 4.02% 64734.80 90.23%
SUB TOTAL 266153.41 151223.06 58054.85 209277.91
GASTOS GENERALES 7% 18630.74 10585.61 4063.84 14649.45
UTILIDADES 5% 13307.67 7561.15 2902.74 10463.90
SUB TOTAL 298091.82 169369.83 65021.44 234391.26
IMPUESTO IGV 19 % 56637.45 32180.27 12354.07 44534.34
TOTAL GENERAL 354729.27 201550.09 56.82% 77375.51 21.81% 278925.60 78.63%

AVANCE FISICO % VALORIZACION S/.


MES ANTER. 56.82% 201550.09
DEL MES 21.81% 77375.51
ACUMULADO 78.63% 278925.60
21.37%
VALORIZACION DE DEDUCTIVOS FINAL - 2010 - II ETAPA
OBRA : "MEJORAMIENTO DE PISTAS Y VEREDAS DE AV. JOSE OLAYA TRAMO : AV. GIRALDEZ - PROLONG. PUNO RESIDENTE : ING. MIRIAM VILLAFUERTE PACHE
CODIGO : 15-036-074-2063804-2164992-0086 SUPERVISOR : ING. JORGE CHUCOS DE LA CRUZ
: PAVIMENTACION FLEXIBLE
CLIENTE : MUNICIPALIDAD PROVINCIAL DE HUANCAYO

Departamento : JUNIN Provincia : HUANCAYO Distrito : HUANCAYO Fecha de Presentacion :


PRESUPUESTO REFERENCIAL AVANCES
ITEM DESCRIPCION Unidad Metrado Precio Parcial MES ANTERIOR MES ACTUAL ACUMULADO

METRADO VALORIZA. S/. % METRADO VALORIZ. S/. % METRADO VALORIZ. S/. %


04.04 CARPETA ASFALTICA
04.04.01 IMPRIMACION ASFALTICA M2 488.72 5.46 2,668.41 0.00 0.00 0.00 488.72 2668.41 100.00 488.72 2668.41 100.00
04.04.02 CARPETA ASFALTICA EN CALIENTE E= 3" M2 488.72 52.36 25,589.38 0.00 0.00 0.00 488.72 25589.38 100.00 488.72 25589.38 100.00
05.00 DRENAJE
05.01 ENCOFRADO Y DESENCOFRADO DE CUNETAS M2 30.06 36.99 1,111.92 0.00 0.00 0.00 30.06 1111.92 100.00 30.06 1111.92 100.00
05.02 CUNETAS CONCRETO F'C=175 KG/CM2 M3 44.57 281.43 12,543.34 0.00 0.00 0.00 44.57 12543.34 100.00 44.57 12543.34 100.00
07.00 SARDINEL INEXPUESTO
07.01 SARDINEL INEXP. CONCRETO F'C=210 KG/CM2 M3 2.57 298.61 767.43 0.00 0.00 0.00 2.57 767.43 100.00 2.57 767.43 100.00
08.00 ACERA PEATONAL
08.01 SARDINEL EXPUESTO
08.01.02 SARDINEL EXP. CONCRETO F'C=175 KG/CM2 M3 3.12 270.17 842.93 0.00 0.00 0.00 3.12 842.93 100.00 3.12 842.93 100.00
VEREDAS
08.02.01 REFINE Y NIVELACION M2 187.20 1.41 263.95 0.00 0.00 0.00 187.20 263.95 100.00 187.20 263.95 100.00
08.02.02 RELLENO Y COMPACTADO DE VEREDA M2 118.50 4.60 545.10 0.00 0.00 0.00 118.50 545.10 100.00 118.50 545.10 100.00
08.02.04 VEREDAS CONCRETO F'C=175 KG/CM2 M2 182.22 29.26 5,331.76 0.00 0.00 0.00 182.22 5331.76 100.00 182.22 5331.76 100.00
9.00 RAMPAS
9.01 ENCOFRADO Y DESENCOFRADO RAMPA M2 1.35 31.63 42.70 0.00 0.00 0.00 1.35 42.70 100.00 1.35 42.70 100.00
9.02 RAMPA CONCRETO F'C=175 KG/CM2 M2 5.40 29.88 161.35 0.00 0.00 0.00 5.40 161.35 100.00 5.40 161.35 100.00
02.02 CAMAS DE APOYO
02.02.01 PREPARACION DE CAMAS DE APOYO M 20.80 4.61 95.89 0.00 0.00 0.00 20.80 95.89 100.00 20.80 95.89 100.00
02.03 RELLENOS
02.03.02 SELECCIÓN DE MATERIAL P/RELLENO M3 64.40 3.42 220.25 0.00 0.00 0.00 64.40 220.25 100.00 64.40 220.25 100.00
02.03.03 CARGUIO P/ RELLENO M3 64.40 4.16 267.90 0.00 0.00 0.00 64.40 267.90 100.00 64.40 267.90 100.00
02.03.04 TRANSPORTE P/ RELLENO M3 64.40 5.52 355.49 0.00 0.00 0.00 64.40 355.49 100.00 64.40 355.49 100.00
03.00 OBRAS DE CONCRETO ARMADO
03.01 CONSTRUCCION DE BUZONES
03.01.01 CONSTRUCCION DE BUZON H =1..50m UND 0.80 1159.37 927.50 0.00 0.00 0.00 0.80 927.50 100.00 0.80 927.50 100.00
03.01.03 DADOS DE CONCRETO F'C= 140KG/CM² UND 3.00 63.27 189.81 0.00 0.00 0.00 3.00 189.81 100.00 3.00 189.81 100.00
03.02 ENCIMADO DE BUZONES
03.02.02 DADOS DE CONCRETO F'C= 140KG/CM² UND 1.00 63.27 63.27 0.00 0.00 0.00 1.00 63.27 100.00 1.00 63.27 100.00
03.03 SUMIDEROS
03.03.01 CONSTRUCCION DE SUMIDERO UND 3.00 423.36 1,270.08 0.00 0.00 0.00 3.00 1270.08 100.00 3.00 1270.08 100.00
03.03.02 CONSTRUCCION DE CAJA RECEPTOR UND 3.00 60.58 181.74 0.00 0.00 0.00 3.00 181.74 100.00 3.00 181.74 100.00
04.00 SUMINISTRO Y TENDIDO DE TUBERIA
04.02 TENDIDO DE TUBERIA UPVC U/F S-25 D=10" M 22.20 54.39 1,207.46 0.00 0.00 0.00 22.20 1207.46 100.00 22.20 1207.46 100.00
04.03 TENDIDO DE TUBERIA UPVC U/F S-25 D=8" M 34.00 42.40 1,441.60 0.00 0.00 0.00 34.00 1441.60 100.00 34.00 1441.60 100.00
04.04 SUMINISTRO Y COLOCACION DE ACCESORIOS UND 6.00 15.35 92.10 0.00 0.00 0.00 6.00 92.10 100.00 6.00 92.10 100.00
05.00 PRUEBA HIDRAULICA
05.01 PRUEBA A ZANJA TAPADA P/TUBERIA M 59.20 1.17 69.26 0.00 0.00 0.00 59.20 69.26 100.00 59.20 69.26 100.00
06.00 CARPINTERIA METALICA
06.01 VENTANA DE SUMIDERO 0.70x0.80M UND 3.00 93.49 280.47 0.00 0.00 0.00 3.00 280.47 100.00 3.00 280.47 100.00
06.02 REJILLA DE CAJA UND 3.00 114.81 344.43 0.00 0.00 0.00 3.00 344.43 100.00 3.00 344.43 100.00
COSTO DIRECTO 01 PAVIMENTACION FLEXIBLE 49868.28 0.00 0.00% 49868.26 25.65% 49868.26 100.00%
COSTO DIRECTO 02 DESAGUE PLUVIAL 7007.24 0.00 0.00% 7007.25 9.77% 7007.25 100.00%
SUB TOTAL 56875.52 0.00 56875.51 56875.51
GASTOS GENERALES 7% 3981.29 0.00 3981.29 3981.29
UTILIDADES 5% 2843.78 0.00 2843.78 2843.78
SUB TOTAL 63700.58 0.00 63700.57 63700.57
IMPUESTO IGV 19 % 12103.11 0.00 12103.11 12103.11
TOTAL GENERAL 75803.70 0.00 0.00% 75803.68 21.37% 75803.68 21.37%

AVANCE FISICO % VALORIZACION S/.


MES ANTER. 0.00% 0.00
DEL MES 21.37% 75803.68
ACUMULADO 21.37% 75803.68
RIAM VILLAFUERTE PACHECO

RGE CHUCOS DE LA CRUZ

3 de Abril del 2010


SALDO

METRADO VALORIZ. S/. %

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

0.00 -0.02 0.00


0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

488.72 2668.41 44.54


488.72 25589.38 44.54

30.06 1111.92 65.75


44.57 12543.34 72.79

0.00 0.00
0.00 0.00 0.00

2.57 767.43 74.93


0.00 0.00

0.00 0.00 0.00


3.12 842.93 12.19

187.20 263.95 35.73


118.50 545.10 22.61
0.00 0.00 0.00
182.22 5331.76 34.77

1.35 42.70 58.44


5.40 161.35 50.00

0.00 0.00 0.00

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

0.00 0.00 0.00


0.00 0.00 0.00

0.00 0.00 0.00


0.00 0.00 0.00

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

0.00 0.00 0.00

0.00 0.00 0.00

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

20.80 95.89 4.41

0.00 0.00 0.00


64.40 220.25 30.04
64.40 267.90 30.04
64.40 355.49 30.04
0.00 0.00 0.00

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00

0.80 927.50 20.00


0.00 0.00 0.00
3.00 189.81 16.67

0.00 0.00 0.00


1.00 63.27 20.00
0.00 0.00
3.00 1270.08 50.00
3.00 181.74 50.00

0.00 0.00 0.00


22.20 1207.46 100.00
34.00 1441.60 62.96
6.00 92.10 100.00

59.20 69.26 12.56

3.00 280.47 50.00


3.00 344.43 50.00
49868.24 25.65%
7007.25 9.77%
56875.49
3981.28
2843.77
63700.54
12103.10
75803.65 21.37%

RIAM VILLAFUERTE PACHECO


RGE CHUCOS DE LA CRUZ

SALDO

METRADO VALORIZ. S/. %

0.00 0.00 0.00


0.00 0.00 0.00

0.00 0.00 0.00


0.00 0.00 0.00

0.00 0.00 0.00

0.00 0.00 0.00

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

0.00 0.00 0.00

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00

0.00 0.00 0.00


0.00 0.00 0.00

0.00 0.00 0.00

0.00 0.00 0.00


0.00 0.00 0.00

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00

0.00 0.00 0.00

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00%
0.00 0.00%
0.00
0.00
0.00
0.00
0.00
0.00 0.00%
VALORIZACION DE AVANCE FISICO Nº 01 FEBRERO 2010 - II ETAPA
DEL15/02/2010 AL 20/02/2010
OBRA : "MEJORAMIENTO DE PISTAS Y VEREDAS DE AV. JOSE OLAYA TRAMO : AV. GIRALDEZ - PROLONG. PUNO RESIDENTE : ING. MIRIAM VILLAFUERTE PACHECO

CODIGO : 15-036-074-2063804-2164992-0086 SUPERVISOR : ING. JORGE CHUCOS DE LA CRUZ


: PAVIMENTACION FLEXIBLE
CLIENTE : MUNICIPALIDAD PROVINCIAL DE HUANCAYO

Departamento : JUNIN Provincia : HUANCAYO Distrito : HUANCAYO Fecha de Presentacion :20de Febrero del 2010
PRESUPUESTO REFERENCIAL AVANCES
ITEM DESCRIPCION Unidad Metrado Precio Parcial MES ANTERIOR SEMANA III ACUMULADO
METRADO VALORIZA. S/. % METRADO VALORIZ. S/. % METRADO VALORIZ. S/. %
01.00 OBRAS PROVISIONALES
01.01 ALMACEN Y CASETA DE GUARDIANIA MES 0.25 437.84 109.46 0.25 109.46 100.00 0.00 0.00 0.00 0.25 109.46 100.00
01.02 CARTEL DE IDENTIFICACION DE OBRA UND 0.25 1,902.11 475.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.00 OBRAS PRELIMINARES
02.01 TRAZO Y REPLANTEO M2 1,904.10 0.87 1,656.57 1904.10 1656.57 100.00 0.00 0.00 0.00 1904.10 1656.57 100.00
02.02 TRAZO Y REPLANTEO DURANTE LA EJECUCION M2 1,904.08 0.85 1,618.47 1626.09 1382.18 85.40 0.00 0.00 0.00 1626.09 1382.18 85.40
02.03 ROTURA DE VEREDAS M3 0.48 42.58 20.44 0.48 20.44 100.00 0.00 0.00 0.00 0.48 20.44 100.00
03.00 EXPLANACIONES
03.01 MOVIMIENTO DE TIERRAS
03.01.01 CORTE DE TERRENO DE SUB RASANTE M3 1,149.87 5.09 5,852.84 933.67 4752.38 81.20 149.60 761.46 13.01 1083.27 5513.84 94.21
03.01.02 CORTE PARA MEJORAM. DE SUB BASE M3 46.08 5.08 234.09 46.08 234.09 100.00 0.00 0.00 0.00 46.08 234.09 100.00
03.01.03 CORTE DE TERRENO MANUAL M3 59.80 21.45 1,282.71 59.80 1282.71 100.00 0.00 0.00 0.00 59.80 1282.71 100.00
03.01.04 EXCAVACION MANUAL PARA CUNETA M3 18.29 21.45 392.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.01.05 EXCAVACION MANUAL PARA SARDINEL M3 28.17 21.45 604.25 28.17 604.25 100.00 0.00 0.00 0.00 28.17 604.25 100.00
03.01.06 EXCAVACION MANUAL EN BADEN M3 4.73 21.04 99.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.02 ELIMINACION DE MATERIAL EXCEDENTE
03.02.01 ACARREO INTERNO DE MATERIAL M3 133.80 17.94 2,400.37 133.80 2400.37 100.00 0.00 0.00 0.00 133.80 2400.37 100.00
03.02.02 CARGUIO (ELIM.DE MATERIAL EXCEDENTE) M3 1,568.94 3.63 5,695.25 1568.94 5695.25 100.00 0.00 0.00 0.00 1568.94 5695.25 100.00
03.02.03 TRANSPORTE (ELIM. MAT. EXCEDENTE) M3 1,568.94 5.70 8,942.96 1568.94 8942.96 100.00 0.00 0.00 0.00 1568.94 8942.96 100.00
03.02.04 ESCARIFICADO PERFILADO/COMPACTADO M2 1,421.70 2.28 3,241.48 1421.70 3241.48 100.00 0.00 0.00 0.00 1421.70 3241.48 100.00
04.00 PAVIMENTOS
04.01 MEJORAMIENTO DE SUB RASANTE
04.01.01 EXTRACCION DE MATERIAL P/MEJ. SUB RASANTE M3 305.70 7.42 2,268.27 305.70 2268.27 100.00 0.00 0.00 0.00 305.70 2268.27 100.00
04.01.02 SELECCION DE MATERIAL P/ MEJ DE SUB RASANTE M3 251.00 4.68 1,174.68 251.00 1174.68 100.00 0.00 0.00 0.00 251.00 1174.68 100.00
04.01.03 CARGUIO DE (MEJ. S-R) M3 251.00 3.83 961.33 251.00 961.33 100.00 0.00 0.00 0.00 251.00 961.33 100.00
04.01.04 TRANSPORTE (MEJ. S-R) M3 251.00 5.70 1,430.70 251.00 1430.70 100.00 0.00 0.00 0.00 251.00 1430.70 100.00
04.01.05 EXT. RIEGO Y COMPC. P/MEJ DE SUB RASANTE M2 1,165.00 2.18 2,539.70 1165.00 2539.70 100.00 0.00 0.00 0.00 1165.00 2539.70 100.00
04.02 SUB BASE GRANULAR
04.02.01 EXTRACCION DE MATERIAL PARA SUB BASE M3 398.08 7.41 2,949.77 398.08 2949.77 100.00 0.00 0.00 0.00 398.08 2949.77 100.00
04.02.02 SELECCION DE MATERIAL P/ SUB BASE GRANULAR M3 369.64 4.68 1,729.92 365.00 1708.20 98.74 0.00 0.00 0.00 365.00 1708.20 98.74
04.02.03 CARGUIO DE S-B M3 369.64 3.92 1,448.99 315.00 1234.80 85.22 0.00 0.00 0.00 315.00 1234.80 85.22
04.02.04 TRANSPORTE DE S.B. M3 369.64 5.70 2,106.95 315.00 1795.50 85.22 0.00 0.00 0.00 315.00 1795.50 85.22
04.02.05 EXT. RIEGO Y COMPC. DE SUB BASE E= 0.20m. M2 1,421.70 2.31 3,284.13 1195.00 2760.45 84.05 0.00 0.00 0.00 1195.00 2760.45 84.05
04.03 BASE GRANULAR
04.03.01 EXTRACCION DE MATERIAL PARA BASE M3 471.44 7.41 3,493.37 230.00 1704.30 48.79 200.00 1482.00 42.42 430.00 3186.30 91.21
04.03.02 SELECCION DE MATERIAL P/ BASE GRANULAR M3 437.76 4.68 2,048.72 150.00 702.00 34.27 195.00 912.60 44.54 345.00 1614.60 78.81
04.03.03 CARGUIO DE B. M3 437.76 3.92 1,716.02 195.00 764.40 44.54 150.00 588.00 34.27 345.00 1352.40 78.81
04.03.04 TRANSPORTE DE B. M3 437.76 5.70 2,495.23 195.00 1111.50 44.54 150.00 855.00 34.27 345.00 1966.50 78.81
VALORIZACION DE AVANCE FISICO Nº 01 FEBRERO 2010 - II ETAPA
DEL15/02/2010 AL 20/02/2010
OBRA : "MEJORAMIENTO DE PISTAS Y VEREDAS DE AV. JOSE OLAYA TRAMO : AV. GIRALDEZ - PROLONG. PUNO RESIDENTE : ING. MIRIAM VILLAFUERTE PACHECO

CODIGO : 15-036-074-2063804-2164992-0086 SUPERVISOR : ING. JORGE CHUCOS DE LA CRUZ


: PAVIMENTACION FLEXIBLE
CLIENTE : MUNICIPALIDAD PROVINCIAL DE HUANCAYO

Departamento : JUNIN Provincia : HUANCAYO Distrito : HUANCAYO Fecha de Presentacion :20de Febrero del 2010
PRESUPUESTO REFERENCIAL AVANCES
ITEM DESCRIPCION Unidad Metrado Precio Parcial MES ANTERIOR SEMANA III ACUMULADO
METRADO VALORIZA. S/. % METRADO VALORIZ. S/. % METRADO VALORIZ. S/. %
04.03.05 EXT. RIEGO Y COMPC. DE BASE E= 0.20m. M2 1,421.70 2.32 3,298.34 75.00 174.00 5.28 0.00 0.00 0.00 75.00 174.00 5.28
04.04 CARPETA ASFALTICA
04.04.01 IMPRIMACION ASFALTICA M2 1,097.20 5.46 5,990.71 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.04.02 CARPETA ASFALTICA EN CALIENTE E= 3" M2 1,097.20 52.36 57,449.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.00 DRENAJE
05.01 ENCOFRADO Y DESENCOFRADO DE CUNETAS M2 45.72 36.99 1,691.18 0.00 0.00 0.00 0.66 24.41 1.44 0.66 24.41 1.44
05.02 CUNETAS CONCRETO F'C=175 KG/CM2 M3 61.23 281.43 17,231.96 0.00 0.00 0.00 0.26 73.17 0.42 0.26 73.17 0.42
06.00 BADEN
06.01 BADEN CONCRETO F'C=210 KG/CM2 M3 4.73 285.88 1,352.21 0.00 0.00 0.00 0.00 0.00
06.02 BADEN ENCOFRADO Y DESENCOFRADO M2 3.94 36.99 145.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.00 SARDINEL INEXPUESTO
07.01 SARDINEL INEXP. CONCRETO F'C=210 KG/CM2 M3 3.43 298.61 1,024.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.02 SARDINEL INEXP. ENCOFRADO Y DESENCOFRADO M2 6.86 26.86 184.26 0.00 0.00 0.00 0.00 0.00
08.00 ACERA PEATONAL
08.01 SARDINEL EXPUESTO
08.01.01 SARDINEL EXP. ENCOFRADO Y DESENCOFRADO M2 170.63 30.13 5,141.08 170.63 5141.08 100.00 0.00 0.00 0.00 170.63 5141.08 100.00
08.01.02 SARDINEL EXP. CONCRETO F'C=175 KG/CM2 M3 25.59 270.17 6,913.65 22.34 6035.60 87.30 0.13 35.12 0.51 22.47 6070.72 87.81
VEREDAS
08.02.01 REFINE Y NIVELACION M2 524.00 1.41 738.84 336.80 474.89 64.27 0.00 0.00 0.00 336.80 474.89 64.27
08.02.02 RELLENO Y COMPACTADO DE VEREDA M2 524.00 4.60 2,410.40 405.50 1865.30 77.39 0.00 0.00 0.00 405.50 1865.30 77.39
08.02.03 VEREDA ENCOFRADO Y DESENCOFRADO M2 12.57 29.31 368.43 12.57 368.43 100.00 0.00 0.00 0.00 12.57 368.43 100.00
08.02.04 VEREDAS CONCRETO F'C=175 KG/CM2 M2 524.00 29.26 15,332.24 341.78 10000.48 65.23 0.00 0.00 0.00 341.78 10000.48 65.23
9.00 RAMPAS
9.01 ENCOFRADO Y DESENCOFRADO RAMPA M2 2.31 31.63 73.07 0.96 30.36 41.56 0.00 0.00 0.00 0.96 30.36 41.56
9.02 RAMPA CONCRETO F'C=175 KG/CM2 M2 10.80 29.88 322.70 2.80 83.66 25.93 0.00 0.00 0.00 2.80 83.66 25.93
10.00 JUNTAS
10.01 RELLENO DE JUNTAS M 179.09 1.96 351.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.00 AREAS VERDES
11.01 SUMINISTRO DE TIERRA AGRICOLA M3 72.30 33.76 2,440.85 45.77 1545.20 63.31 26.53 895.65 36.69 72.30 2440.85 100.00
11.02 COLOCACION DE GRASS M2 241.00 10.20 2,458.20 102.04 1040.81 42.34 138.96 1417.39 57.66 241.00 2458.20 100.00
11.03 COLOCACION DE PLANTONES UND 20.00 16.79 335.80 10.00 167.90 50.00 0.00 0.00 0.00 10.00 167.90 50.00
12.00 SEÑALIZACION
12.01 SEÑALIZACION HORIZONTAL
12.01.01 PINTURA LINEAL EN BORDE DE VIA M 228.62 3.97 907.62 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12.01.02 PINTURA LINEAL CONTINUA EN EJE DE VIA M 95.70 3.90 373.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12.01.03 PINTURA LINEAL DISCONTINUA EN EJE DE VIA M 191.00 3.24 618.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12.01.04 PINTURA DE SIMBOLOS Y FLECHAS M2 12.00 12.69 152.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12.02 SEÑALIZACION VERTICAL
VALORIZACION DE AVANCE FISICO Nº 01 FEBRERO 2010 - II ETAPA
DEL15/02/2010 AL 20/02/2010
OBRA : "MEJORAMIENTO DE PISTAS Y VEREDAS DE AV. JOSE OLAYA TRAMO : AV. GIRALDEZ - PROLONG. PUNO RESIDENTE : ING. MIRIAM VILLAFUERTE PACHECO

CODIGO : 15-036-074-2063804-2164992-0086 SUPERVISOR : ING. JORGE CHUCOS DE LA CRUZ


: PAVIMENTACION FLEXIBLE
CLIENTE : MUNICIPALIDAD PROVINCIAL DE HUANCAYO

Departamento : JUNIN Provincia : HUANCAYO Distrito : HUANCAYO Fecha de Presentacion :20de Febrero del 2010
PRESUPUESTO REFERENCIAL AVANCES
ITEM DESCRIPCION Unidad Metrado Precio Parcial MES ANTERIOR SEMANA III ACUMULADO
METRADO VALORIZA. S/. % METRADO VALORIZ. S/. % METRADO VALORIZ. S/. %
12.02.01 SEÑALES TIPO R (90cM x 60cm) UND 1.00 384.08 384.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12.02.02 SEÑALES TIPO F UND 1.00 358.52 358.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.00 EQUIPAMIENTO
13.01 MOVILIARIO URBANO UND 3.00 545.16 1,635.48 3.00 1635.48 100.00 0.00 0.00 0.00 3.00 1635.48 100.00
13.02 SUMINISTRO Y COLOCACION DE TACHOS DE BASURA UND 2.00 399.03 798.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
14.00 RECONEXIONES
14.01 RECONEXIONES DE PUNTOS DE AGUA PTO 6.00 13.99 83.94 6.00 83.94 100.00 0.00 0.00 0.00 6.00 83.94 100.00
14.02 RECONEXION DE CAJA MEDIDOR DE AGUA PTO 6.00 12.96 77.76 6.00 77.76 100.00 0.00 0.00 0.00 6.00 77.76 100.00
14.03 RECONEXION DE INSTALACIONES DE DESAGUE PTO 6.00 17.56 105.36 6.00 105.36 100.00 0.00 0.00 0.00 6.00 105.36 100.00
14.04 RECONEXION DE CAJA DE REGISTRO DE DESAGUE PTO 6.00 11.31 67.86 6.00 67.86 100.00 0.00 0.00 0.00 6.00 67.86 100.00
15.00 VARIOS
15.01 LIMPIEZA FINAL DE OBRA M2 2,000.00 0.66 1,320.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

DESAGUE PLUVIAL

01.00 TRABAJOS PRELIMINARES


01.01 TRAZO NIVELES Y REPLANTEO DE ZANJA M 395.00 0.56 221.20 395.00 221.20 100.00 0.00 0.00 0.00 395.00 221.20 100.00
02.00 MOVIMIENTO DE TIERRAS

02.01 EXCAVACIONES
02.01.01 EXCAVACION PARA BUZONES M3 32.63 21.45 699.91 32.63 699.91 100.00 0.00 0.00 0.00 32.63 699.91 100.00
02.01.02 EXCAVACION DE ZANJAS - MANUAL M 471.20 15.02 7,077.42 471.20 7077.42 100.00 0.00 0.00 0.00 471.20 7077.42 100.00
02.01.03 EXCAVACION PARA SUMIDEROS M3 7.83 28.75 225.11 4.05 116.44 51.72 0.00 0.00 0.00 4.05 116.44 51.72
02.01.04 REFINE Y NIVELACION EN ZANJAS M 471.20 1.85 871.72 466.10 862.29 98.92 0.00 0.00 0.00 466.10 862.29 98.92
02.02 CAMAS DE APOYO
02.02.01 PREPARACION DE CAMAS DE APOYO M 471.20 4.61 2,172.23 411.40 1896.55 87.31 0.00 0.00 0.00 411.40 1896.55 87.31
02.03 RELLENOS
02.03.01 EXTRACCION DE MAT. P/RELLENO M3 230.89 6.39 1,475.39 230.89 1475.39 100.00 0.00 0.00 0.00 230.89 1475.39 100.00
02.03.02 SELECCIÓN DE MATERIAL P/RELLENO M3 214.40 3.42 733.25 150.00 513.00 69.96 0.00 0.00 0.00 150.00 513.00 69.96
02.03.03 CARGUIO P/ RELLENO M3 214.40 4.16 891.90 150.00 624.00 69.96 0.00 0.00 0.00 150.00 624.00 69.96
02.03.04 TRANSPORTE P/ RELLENO M3 214.40 5.52 1,183.49 150.00 828.00 69.96 0.00 0.00 0.00 150.00 828.00 69.96
02.03.05 RELLENO Y COMPACTADO DE ZANJA M 471.20 14.97 7,053.86 434.40 6502.97 92.19 0.00 0.00 0.00 434.40 6502.97 92.19
02.04 ELIMINACION DE MATERIAL EXCEDENTE
02.04.01 ACARREO INTERNO DE MATERIAL M3 48.55 13.46 653.48 48.55 653.48 100.00 0.00 0.00 0.00 48.55 653.48 100.00
02.04.02 CARGUIO (ELIM. MAT. EXCEDENTE) M3 48.55 3.92 190.32 48.55 190.32 100.00 0.00 0.00 0.00 48.55 190.32 100.00
02.04.03 TRANSPORTE (ELIM. MAT. EXCEDENTE) M3 48.55 5.70 276.74 48.55 276.74 100.00 0.00 0.00 0.00 48.55 276.74 100.00
03.00 OBRAS DE CONCRETO ARMADO
03.01 CONSTRUCCION DE BUZONES
VALORIZACION DE AVANCE FISICO Nº 01 FEBRERO 2010 - II ETAPA
DEL15/02/2010 AL 20/02/2010
OBRA : "MEJORAMIENTO DE PISTAS Y VEREDAS DE AV. JOSE OLAYA TRAMO : AV. GIRALDEZ - PROLONG. PUNO RESIDENTE : ING. MIRIAM VILLAFUERTE PACHECO

CODIGO : 15-036-074-2063804-2164992-0086 SUPERVISOR : ING. JORGE CHUCOS DE LA CRUZ


: PAVIMENTACION FLEXIBLE
CLIENTE : MUNICIPALIDAD PROVINCIAL DE HUANCAYO

Departamento : JUNIN Provincia : HUANCAYO Distrito : HUANCAYO Fecha de Presentacion :20de Febrero del 2010
PRESUPUESTO REFERENCIAL AVANCES
ITEM DESCRIPCION Unidad Metrado Precio Parcial MES ANTERIOR SEMANA III ACUMULADO
METRADO VALORIZA. S/. % METRADO VALORIZ. S/. % METRADO VALORIZ. S/. %
03.01.01 CONSTRUCCION DE BUZON H =1..50m UND 4.00 1159.37 4,637.48 1.50 1739.06 37.50 0.70 811.56 17.50 2.20 2550.61 55.00
03.01.02 CONSTRUCCION DE BUZON H =1.70m UND 5.00 1,066.12 5,330.60 4.45 4744.23 89.00 0.35 373.14 7.00 4.80 5117.38 96.00
03.01.03 DADOS DE CONCRETO F'C= 140KG/CM² UND 18.00 63.27 1,138.86 11.00 695.97 61.11 0.00 0.00 0.00 11.00 695.97 61.11
03.02 ENCIMADO DE BUZONES
03.02.01 CONST. ENCIM.BUZON H= 0.45m. S.M.yTAPA UND 1.00 344.68 344.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.02.02 DADOS DE CONCRETO F'C= 140KG/CM² UND 5.00 63.27 316.35 3.00 189.81 60.00 0.00 0.00 0.00 3.00 189.81 60.00
03.03 SUMIDEROS
03.03.01 CONSTRUCCION DE SUMIDERO UND 6.00 423.36 2,540.16 3.00 1270.08 50.00 0.00 0.00 0.00 3.00 1270.08 50.00
03.03.02 CONSTRUCCION DE CAJA RECEPTOR UND 6.00 60.58 363.48 3.00 181.74 50.00 0.00 0.00 0.00 3.00 181.74 50.00
04.00 SUMINISTRO Y TENDIDO DE TUBERIA
04.01 TENDIDO DE TUBERIA UPVC U/F S-25 D=12" M 395.00 70.77 27,954.15 395.00 27954.15 100.00 0.00 0.00 0.00 395.00 27954.15 100.00
04.02 TENDIDO DE TUBERIA UPVC U/F S-25 D=10" M 22.20 54.39 1,207.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.03 TENDIDO DE TUBERIA UPVC U/F S-25 D=8" M 54.00 42.40 2,289.60 20.00 848.00 37.04 0.00 0.00 0.00 20.00 848.00 37.04
04.04 SUMINISTRO Y COLOCACION DE ACCESORIOS UND 6.00 15.35 92.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.00 PRUEBA HIDRAULICA
05.01 PRUEBA A ZANJA TAPADA P/TUBERIA M 471.20 1.17 551.30 412.00 482.04 87.44 0.00 0.00 0.00 412.00 482.04 87.44
06.00 CARPINTERIA METALICA
06.01 VENTANA DE SUMIDERO 0.70x0.80M UND 6.00 93.49 560.94 3.00 280.47 50.00 0.00 0.00 0.00 3.00 280.47 50.00
06.02 REJILLA DE CAJA UND 6.00 114.81 688.86 3.00 344.43 50.00 0.00 0.00 0.00 3.00 344.43 50.00
COSTO DIRECTO 01 PAVIMENTACION FLEXIBLE 194411.37 82325.84 42.35% 7044.82 3.62% 89370.65 45.97%
COSTO DIRECTO 02 DESAGUE PLUVIAL 71742.04 60667.68 84.56% 1184.70 1.65% 61852.38 86.21%
SUB TOTAL 266153.41 142993.52 8229.52 151223.04
GASTOS GENERALES 7% 18630.74 10009.55 576.07 10585.61
UTILIDADES 5% 13307.67 7149.68 411.48 7561.15
SUB TOTAL 298091.82 160152.74 9217.06 169369.80
IMPUESTO IGV 19 % 56637.45 30429.02 1751.24 32180.26
TOTAL GENERAL 354729.27 190581.76 53.73% 10968.30 3.09% 201550.06 56.82%

AVANCE FISICO % VALORIZACION S/.


MES ANTER. 53.73% 190581.76
DE LA SEMANA 3.09% 10968.30
ACUMULADO 56.82% 201550.06
IAM VILLAFUERTE PACHECO

RGE CHUCOS DE LA CRUZ

0de Febrero del 2010


SALDO

METRADO VALORIZ. S/. %

0.00 0.00 0.00


0.25 475.53 100.00
0.00 0.00
0.00 0.00 0.00
277.99 236.29 14.60
0.00 0.00 0.00

66.60 338.99 5.79


0.00 0.00 0.00
0.00 0.00 0.00
18.29 392.32 100.00
0.00 0.00 0.00
4.73 99.52 100.00

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

0.00 0.00 0.00


4.64 21.72 1.26
54.64 214.19 14.78
54.64 311.45 14.78
226.70 523.68 15.95

41.44 307.07 8.79


92.76 434.12 21.19
92.76 363.62 21.19
92.76 528.73 21.19
IAM VILLAFUERTE PACHECO

RGE CHUCOS DE LA CRUZ

0de Febrero del 2010


SALDO

METRADO VALORIZ. S/. %


1346.70 3124.34 94.72

1097.20 5990.71 100.00


1097.20 57449.39 100.00

45.06 1666.77 98.56


60.97 17158.79 99.58

4.73 1352.21
3.94 145.74 100.00

3.43 1024.23 100.00


6.86 184.26

0.00 0.00 0.00


3.12 842.93 12.19
0.00 0.00
187.20 263.95 35.73
118.50 545.10 22.61
0.00 0.00 0.00
182.22 5331.76 34.77

1.35 42.70 58.44


8.00 239.04 74.07

179.09 351.02 100.00

0.00 0.00 0.00


0.00 0.00 0.00
10.00 167.90 50.00

228.62 907.62 100.00


95.70 373.23 100.00
191.00 618.84 100.00
12.00 152.28 100.00
IAM VILLAFUERTE PACHECO

RGE CHUCOS DE LA CRUZ

0de Febrero del 2010


SALDO

METRADO VALORIZ. S/. %


1.00 384.08 100.00
1.00 358.52 100.00

0.00 0.00 0.00


2.00 798.06 100.00

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

2000.00 1320.00 100.00

0.00 0.00 0.00

0.00 0.00 0.00


0.00 0.00 0.00
3.78 108.68 48.28
5.10 9.43 1.08

59.80 275.68 12.69

0.00 0.00 0.00


64.40 220.25 30.04
64.40 267.90 30.04
64.40 355.49 30.04
36.80 550.90 7.81

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00
IAM VILLAFUERTE PACHECO

RGE CHUCOS DE LA CRUZ

0de Febrero del 2010


SALDO

METRADO VALORIZ. S/. %


1.80 2086.87 45.00
0.20 213.22 4.00
7.00 442.89 38.89

1.00 344.68 100.00


2.00 126.54 40.00
0.00 0.00
3.00 1270.08 50.00
3.00 181.74 50.00

0.00 0.00 0.00


22.20 1207.46 100.00
34.00 1441.60 62.96
6.00 92.10 100.00

59.20 69.26 12.56

3.00 280.47 50.00


3.00 344.43 50.00
105040.70 54.03%
9889.67 13.79%
114930.36
8045.13
5746.52
128722.00
24457.18
153179.19 43.18%
VALORIZACION DE AVANCE FISICO Nº 02 FEBRERO 2010 - II ETAPA
DEL 01/02/2010 AL 28/02/2010
OBRA : "MEJORAMIENTO DE PISTAS Y VEREDAS DE AV. JOSE OLAYA TRAMO : AV. GIRALDEZ - PROLONG. PUNO RESIDENTE : ING. MIRIAM VILLAFUERTE PACHECO

CODIGO : 15-036-074-2063804-2164992-0086 SUPERVISOR : ING. JORGE CHUCOS DE LA CRUZ


: PAVIMENTACION FLEXIBLE
CLIENTE : MUNICIPALIDAD PROVINCIAL DE HUANCAYO

Departamento : JUNIN Provincia : HUANCAYO Distrito : HUANCAYO Fecha de Presentacion :03de Marzo del 2010
PRESUPUESTO REFERENCIAL AVANCES
ITEM DESCRIPCION Unidad Metrado Precio Parcial MES ANTERIOR MES ACTUAL ACUMULADO
METRADO VALORIZA. S/. % METRADO VALORIZ. S/. % METRADO VALORIZ. S/. %
01.00 OBRAS PROVISIONALES
01.01 ALMACEN Y CASETA DE GUARDIANIA MES 0.25 437.84 109.46 0.25 109.46 100.00 0.00 0.00 0.00 0.25 109.46 100.00
01.02 CARTEL DE IDENTIFICACION DE OBRA UND 0.25 1,902.11 475.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.00 OBRAS PRELIMINARES
02.01 TRAZO Y REPLANTEO M2 1,904.10 0.87 1,656.57 1904.10 1656.57 100.00 0.00 0.00 0.00 1904.10 1656.57 100.00
02.02 TRAZO Y REPLANTEO DURANTE LA EJECUCION M2 1,904.08 0.85 1,618.47 856.09 727.68 44.96 770.00 654.50 40.44 1626.09 1382.18 85.40
02.03 ROTURA DE VEREDAS M3 0.48 42.58 20.44 0.48 20.44 100.00 0.00 0.00 0.00 0.48 20.44 100.00
03.00 EXPLANACIONES
03.01 MOVIMIENTO DE TIERRAS
03.01.01 CORTE DE TERRENO DE SUB RASANTE M3 1,149.87 5.09 5,852.84 916.22 4663.56 79.68 167.05 850.28 14.53 1083.27 5513.84 94.21
03.01.02 CORTE PARA MEJORAM. DE SUB BASE M3 46.08 5.08 234.09 46.08 234.09 100.00 0.00 0.00 0.00 46.08 234.09 100.00
03.01.03 CORTE DE TERRENO MANUAL M3 59.80 21.45 1,282.71 59.80 1282.71 100.00 0.00 0.00 0.00 59.80 1282.71 100.00
03.01.04 EXCAVACION MANUAL PARA CUNETA M3 18.29 21.45 392.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.01.05 EXCAVACION MANUAL PARA SARDINEL M3 28.17 21.45 604.25 12.53 268.77 44.48 15.64 335.48 55.52 28.17 604.25 100.00
03.01.06 EXCAVACION MANUAL EN BADEN M3 4.73 21.04 99.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.02 ELIMINACION DE MATERIAL EXCEDENTE
03.02.01 ACARREO INTERNO DE MATERIAL M3 133.80 17.94 2,400.37 133.80 2400.37 100.00 0.00 0.00 0.00 133.80 2400.37 100.00
03.02.02 CARGUIO (ELIM.DE MATERIAL EXCEDENTE) M3 1,568.94 3.63 5,695.25 1460.00 5299.80 93.06 108.94 395.45 6.94 1568.94 5695.25 100.00
03.02.03 TRANSPORTE (ELIM. MAT. EXCEDENTE) M3 1,568.94 5.70 8,942.96 1460.00 8322.00 93.06 108.94 620.96 6.94 1568.94 8942.96 100.00
03.02.04 ESCARIFICADO PERFILADO/COMPACTADO M2 1,421.70 2.28 3,241.48 1421.70 3241.48 100.00 0.00 0.00 0.00 1421.70 3241.48 100.00
04.00 PAVIMENTOS
04.01 MEJORAMIENTO DE SUB RASANTE
04.01.01 EXTRACCION DE MATERIAL P/MEJ. SUB RASANTE M3 305.70 7.42 2,268.27 305.70 2268.29 100.00 0.00 0.00 0.00 305.70 2268.29 100.00
04.01.02 SELECCION DE MATERIAL P/ MEJ DE SUB RASANTE M3 251.00 4.68 1,174.68 251.00 1174.68 100.00 0.00 0.00 0.00 251.00 1174.68 100.00
04.01.03 CARGUIO DE (MEJ. S-R) M3 251.00 3.83 961.33 251.00 961.33 100.00 0.00 0.00 0.00 251.00 961.33 100.00
04.01.04 TRANSPORTE (MEJ. S-R) M3 251.00 5.70 1,430.70 251.00 1430.70 100.00 0.00 0.00 0.00 251.00 1430.70 100.00
04.01.05 EXT. RIEGO Y COMPC. P/MEJ DE SUB RASANTE M2 1,165.00 2.18 2,539.70 60.80 132.54 5.22 1104.20 2407.16 94.78 1165.00 2539.70 100.00
04.02 SUB BASE GRANULAR
04.02.01 EXTRACCION DE MATERIAL PARA SUB BASE M3 398.08 7.41 2,949.77 398.08 2949.77 100.00 0.00 0.00 0.00 398.08 2949.77 100.00
04.02.02 SELECCION DE MATERIAL P/ SUB BASE GRANULAR M3 369.64 4.68 1,729.92 365.00 1708.20 98.74 0.00 0.00 0.00 365.00 1708.20 98.74
04.02.03 CARGUIO DE S-B M3 369.64 3.92 1,448.99 270.00 1058.40 73.04 45.00 176.40 12.17 315.00 1234.80 85.22
04.02.04 TRANSPORTE DE S.B. M3 369.64 5.70 2,106.95 270.00 1539.00 73.04 45.00 256.50 12.17 315.00 1795.50 85.22
04.02.05 EXT. RIEGO Y COMPC. DE SUB BASE E= 0.20m. M2 1,421.70 2.31 3,284.13 30.00 69.30 2.11 1165.00 2691.15 81.94 1195.00 2760.45 84.05
04.03 BASE GRANULAR
04.03.01 EXTRACCION DE MATERIAL PARA BASE M3 471.44 7.41 3,493.37 0.00 0.00 0.00 430.00 3186.30 91.21 430.00 3186.30 91.21
04.03.02 SELECCION DE MATERIAL P/ BASE GRANULAR M3 437.76 4.68 2,048.72 0.00 0.00 0.00 345.00 1614.60 78.81 345.00 1614.60 78.81
04.03.03 CARGUIO DE B. M3 437.76 3.92 1,716.02 0.00 0.00 0.00 345.00 1352.40 78.81 345.00 1352.40 78.81
04.03.04 TRANSPORTE DE B. M3 437.76 5.70 2,495.23 0.00 0.00 0.00 345.00 1966.50 78.81 345.00 1966.50 78.81
VALORIZACION DE AVANCE FISICO Nº 02 FEBRERO 2010 - II ETAPA
DEL 01/02/2010 AL 28/02/2010
OBRA : "MEJORAMIENTO DE PISTAS Y VEREDAS DE AV. JOSE OLAYA TRAMO : AV. GIRALDEZ - PROLONG. PUNO RESIDENTE : ING. MIRIAM VILLAFUERTE PACHECO

CODIGO : 15-036-074-2063804-2164992-0086 SUPERVISOR : ING. JORGE CHUCOS DE LA CRUZ


: PAVIMENTACION FLEXIBLE
CLIENTE : MUNICIPALIDAD PROVINCIAL DE HUANCAYO

Departamento : JUNIN Provincia : HUANCAYO Distrito : HUANCAYO Fecha de Presentacion :03de Marzo del 2010
PRESUPUESTO REFERENCIAL AVANCES
ITEM DESCRIPCION Unidad Metrado Precio Parcial MES ANTERIOR MES ACTUAL ACUMULADO
METRADO VALORIZA. S/. % METRADO VALORIZ. S/. % METRADO VALORIZ. S/. %
04.03.05 EXT. RIEGO Y COMPC. DE BASE E= 0.20m. M2 1,421.70 2.32 3,298.34 0.00 0.00 0.00 75.00 174.00 5.28 75.00 174.00 5.28
04.04 CARPETA ASFALTICA
04.04.01 IMPRIMACION ASFALTICA M2 1,097.20 5.46 5,990.71 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.04.02 CARPETA ASFALTICA EN CALIENTE E= 3" M2 1,097.20 52.36 57,449.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.00 DRENAJE
05.01 ENCOFRADO Y DESENCOFRADO DE CUNETAS M2 45.72 36.99 1,691.18 0.00 0.00 0.00 0.66 24.41 1.44 0.66 24.41 1.44
05.02 CUNETAS CONCRETO F'C=175 KG/CM2 M3 61.23 281.43 17,231.96 0.00 0.00 0.00 0.26 73.17 0.42 0.26 73.17 0.42
06.00 BADEN
06.01 BADEN CONCRETO F'C=210 KG/CM2 M3 4.73 285.88 1,352.21 0.00 0.00 0.00 0.00 0.00
06.02 BADEN ENCOFRADO Y DESENCOFRADO M2 3.94 36.99 145.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.00 SARDINEL INEXPUESTO
07.01 SARDINEL INEXP. CONCRETO F'C=210 KG/CM2 M3 3.43 298.61 1,024.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.02 SARDINEL INEXP. ENCOFRADO Y DESENCOFRADO M2 6.86 26.86 184.26 0.00 0.00 0.00 0.00 0.00
08.00 ACERA PEATONAL
08.01 SARDINEL EXPUESTO
08.01.01 SARDINEL EXP. ENCOFRADO Y DESENCOFRADO M2 170.63 30.13 5,141.08 78.68 2370.63 46.11 91.95 2770.45 53.89 170.63 5141.08 100.00
08.01.02 SARDINEL EXP. CONCRETO F'C=175 KG/CM2 M3 25.59 270.17 6,913.65 13.97 3774.27 54.59 8.50 2296.45 33.22 22.47 6070.72 87.81
VEREDAS
08.02.01 REFINE Y NIVELACION M2 524.00 1.41 738.84 336.80 474.89 64.27 0.00 0.00 0.00 336.80 474.89 64.27
08.02.02 RELLENO Y COMPACTADO DE VEREDA M2 524.00 4.60 2,410.40 405.50 1865.30 77.39 0.00 0.00 0.00 405.50 1865.30 77.39
08.02.03 VEREDA ENCOFRADO Y DESENCOFRADO M2 12.57 29.31 368.43 12.57 368.43 100.00 0.00 0.00 0.00 12.57 368.43 100.00
08.02.04 VEREDAS CONCRETO F'C=175 KG/CM2 M2 524.00 29.26 15,332.24 275.39 8057.91 52.56 66.39 1942.57 12.67 341.78 10000.48 65.23
9.00 RAMPAS
9.01 ENCOFRADO Y DESENCOFRADO RAMPA M2 2.31 31.63 73.07 0.48 15.18 20.78 0.48 15.18 20.78 0.96 30.36 41.56
9.02 RAMPA CONCRETO F'C=175 KG/CM2 M2 10.80 29.88 322.70 1.40 41.83 12.96 1.40 41.83 12.96 2.80 83.66 25.93
10.00 JUNTAS
10.01 RELLENO DE JUNTAS M 179.09 1.96 351.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.00 AREAS VERDES
11.01 SUMINISTRO DE TIERRA AGRICOLA M3 72.30 33.76 2,440.85 0.00 0.00 0.00 72.30 2440.85 100.00 72.30 2440.85 100.00
11.02 COLOCACION DE GRASS M2 241.00 10.20 2,458.20 0.00 0.00 0.00 241.00 2458.20 100.00 241.00 2458.20 100.00
11.03 COLOCACION DE PLANTONES UND 20.00 16.79 335.80 0.00 0.00 0.00 10.00 167.90 50.00 10.00 167.90 50.00
12.00 SEÑALIZACION
12.01 SEÑALIZACION HORIZONTAL
12.01.01 PINTURA LINEAL EN BORDE DE VIA M 228.62 3.97 907.62 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12.01.02 PINTURA LINEAL CONTINUA EN EJE DE VIA M 95.70 3.90 373.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12.01.03 PINTURA LINEAL DISCONTINUA EN EJE DE VIA M 191.00 3.24 618.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12.01.04 PINTURA DE SIMBOLOS Y FLECHAS M2 12.00 12.69 152.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12.02 SEÑALIZACION VERTICAL
VALORIZACION DE AVANCE FISICO Nº 02 FEBRERO 2010 - II ETAPA
DEL 01/02/2010 AL 28/02/2010
OBRA : "MEJORAMIENTO DE PISTAS Y VEREDAS DE AV. JOSE OLAYA TRAMO : AV. GIRALDEZ - PROLONG. PUNO RESIDENTE : ING. MIRIAM VILLAFUERTE PACHECO

CODIGO : 15-036-074-2063804-2164992-0086 SUPERVISOR : ING. JORGE CHUCOS DE LA CRUZ


: PAVIMENTACION FLEXIBLE
CLIENTE : MUNICIPALIDAD PROVINCIAL DE HUANCAYO

Departamento : JUNIN Provincia : HUANCAYO Distrito : HUANCAYO Fecha de Presentacion :03de Marzo del 2010
PRESUPUESTO REFERENCIAL AVANCES
ITEM DESCRIPCION Unidad Metrado Precio Parcial MES ANTERIOR MES ACTUAL ACUMULADO
METRADO VALORIZA. S/. % METRADO VALORIZ. S/. % METRADO VALORIZ. S/. %
12.02.01 SEÑALES TIPO R (90cM x 60cm) UND 1.00 384.08 384.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12.02.02 SEÑALES TIPO F UND 1.00 358.52 358.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.00 EQUIPAMIENTO
13.01 MOVILIARIO URBANO UND 3.00 545.16 1,635.48 2.00 1090.32 66.67 1.00 545.16 33.33 3.00 1635.48 100.00
13.02 SUMINISTRO Y COLOCACION DE TACHOS DE BASURA UND 2.00 399.03 798.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
14.00 RECONEXIONES
14.01 RECONEXIONES DE PUNTOS DE AGUA PTO 6.00 13.99 83.94 6.00 83.94 100.00 0.00 0.00 0.00 6.00 83.94 100.00
14.02 RECONEXION DE CAJA MEDIDOR DE AGUA PTO 6.00 12.96 77.76 6.00 77.76 100.00 0.00 0.00 0.00 6.00 77.76 100.00
14.03 RECONEXION DE INSTALACIONES DE DESAGUE PTO 6.00 17.56 105.36 6.00 105.36 100.00 0.00 0.00 0.00 6.00 105.36 100.00
14.04 RECONEXION DE CAJA DE REGISTRO DE DESAGUE PTO 6.00 11.31 67.86 6.00 67.86 100.00 0.00 0.00 0.00 6.00 67.86 100.00
15.00 VARIOS
15.01 LIMPIEZA FINAL DE OBRA M2 2,000.00 0.66 1,320.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

DESAGUE PLUVIAL

01.00 TRABAJOS PRELIMINARES


01.01 TRAZO NIVELES Y REPLANTEO DE ZANJA M 395.00 0.56 221.20 395.00 221.20 100.00 0.00 0.00 0.00 395.00 221.20 100.00
02.00 MOVIMIENTO DE TIERRAS

02.01 EXCAVACIONES
02.01.01 EXCAVACION PARA BUZONES M3 32.63 21.45 699.91 32.63 699.91 100.00 0.00 0.00 0.00 32.63 699.91 100.00
02.01.02 EXCAVACION DE ZANJAS - MANUAL M 471.20 15.02 7,077.42 409.40 6149.19 86.88 61.80 928.24 13.12 471.20 7077.42 100.00
02.01.03 EXCAVACION PARA SUMIDEROS M3 7.83 28.75 225.11 2.70 77.63 34.48 1.35 38.81 17.24 4.05 116.44 51.72
02.01.04 REFINE Y NIVELACION EN ZANJAS M 471.20 1.85 871.72 463.10 856.74 98.28 3.00 5.55 0.64 466.10 862.29 98.92
02.02 CAMAS DE APOYO
02.02.01 PREPARACION DE CAMAS DE APOYO M 471.20 4.61 2,172.23 408.40 1882.72 86.67 3.00 13.83 0.64 411.40 1896.55 87.31
02.03 RELLENOS
02.03.01 EXTRACCION DE MAT. P/RELLENO M3 230.89 6.39 1,475.39 230.89 1475.39 100.00 0.00 0.00 0.00 230.89 1475.39 100.00
02.03.02 SELECCIÓN DE MATERIAL P/RELLENO M3 214.40 3.42 733.25 150.00 513.00 69.96 0.00 0.00 0.00 150.00 513.00 69.96
02.03.03 CARGUIO P/ RELLENO M3 214.40 4.16 891.90 150.00 624.00 69.96 0.00 0.00 0.00 150.00 624.00 69.96
02.03.04 TRANSPORTE P/ RELLENO M3 214.40 5.52 1,183.49 150.00 828.00 69.96 0.00 0.00 0.00 150.00 828.00 69.96
02.03.05 RELLENO Y COMPACTADO DE ZANJA M 471.20 14.97 7,053.86 431.40 6458.06 91.55 3.00 44.91 0.64 434.40 6502.97 92.19
02.04 ELIMINACION DE MATERIAL EXCEDENTE
02.04.01 ACARREO INTERNO DE MATERIAL M3 48.55 13.46 653.48 48.55 653.48 100.00 0.00 0.00 0.00 48.55 653.48 100.00
02.04.02 CARGUIO (ELIM. MAT. EXCEDENTE) M3 48.55 3.92 190.32 48.55 190.32 100.00 0.00 0.00 0.00 48.55 190.32 100.00
02.04.03 TRANSPORTE (ELIM. MAT. EXCEDENTE) M3 48.55 5.70 276.74 48.55 276.74 100.00 0.00 0.00 0.00 48.55 276.74 100.00
03.00 OBRAS DE CONCRETO ARMADO
03.01 CONSTRUCCION DE BUZONES
VALORIZACION DE AVANCE FISICO Nº 02 FEBRERO 2010 - II ETAPA
DEL 01/02/2010 AL 28/02/2010
OBRA : "MEJORAMIENTO DE PISTAS Y VEREDAS DE AV. JOSE OLAYA TRAMO : AV. GIRALDEZ - PROLONG. PUNO RESIDENTE : ING. MIRIAM VILLAFUERTE PACHECO

CODIGO : 15-036-074-2063804-2164992-0086 SUPERVISOR : ING. JORGE CHUCOS DE LA CRUZ


: PAVIMENTACION FLEXIBLE
CLIENTE : MUNICIPALIDAD PROVINCIAL DE HUANCAYO

Departamento : JUNIN Provincia : HUANCAYO Distrito : HUANCAYO Fecha de Presentacion :03de Marzo del 2010
PRESUPUESTO REFERENCIAL AVANCES
ITEM DESCRIPCION Unidad Metrado Precio Parcial MES ANTERIOR MES ACTUAL ACUMULADO
METRADO VALORIZA. S/. % METRADO VALORIZ. S/. % METRADO VALORIZ. S/. %
03.01.01 CONSTRUCCION DE BUZON H =1..50m UND 4.00 1159.37 4,637.48 1.50 1739.06 37.50 0.70 811.56 17.50 2.20 2550.61 55.00
03.01.02 CONSTRUCCION DE BUZON H =1.70m UND 5.00 1,066.12 5,330.60 4.35 4637.62 87.00 0.45 479.75 9.00 4.80 5117.38 96.00
03.01.03 DADOS DE CONCRETO F'C= 140KG/CM² UND 18.00 63.27 1,138.86 11.00 695.97 61.11 0.00 0.00 0.00 11.00 695.97 61.11
03.02 ENCIMADO DE BUZONES
03.02.01 CONST. ENCIM.BUZON H= 0.45m. S.M.yTAPA UND 1.00 344.68 344.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.02.02 DADOS DE CONCRETO F'C= 140KG/CM² UND 5.00 63.27 316.35 2.00 126.54 40.00 1.00 63.27 20.00 3.00 189.81 60.00
03.03 SUMIDEROS
03.03.01 CONSTRUCCION DE SUMIDERO UND 6.00 423.36 2,540.16 2.00 846.72 33.33 1.00 423.36 16.67 3.00 1270.08 50.00
03.03.02 CONSTRUCCION DE CAJA RECEPTOR UND 6.00 60.58 363.48 2.00 121.16 33.33 1.00 60.58 16.67 3.00 181.74 50.00
04.00 SUMINISTRO Y TENDIDO DE TUBERIA
04.01 TENDIDO DE TUBERIA UPVC U/F S-25 D=12" M 395.00 70.77 27,954.15 395.00 27954.15 100.00 0.00 0.00 0.00 395.00 27954.15 100.00
04.02 TENDIDO DE TUBERIA UPVC U/F S-25 D=10" M 22.20 54.39 1,207.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.03 TENDIDO DE TUBERIA UPVC U/F S-25 D=8" M 54.00 42.40 2,289.60 17.00 720.80 31.48 3.00 127.20 5.56 20.00 848.00 37.04
04.04 SUMINISTRO Y COLOCACION DE ACCESORIOS UND 6.00 15.35 92.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.00 PRUEBA HIDRAULICA
05.01 PRUEBA A ZANJA TAPADA P/TUBERIA M 471.20 1.17 551.30 412.00 482.04 87.44 0.00 0.00 0.00 412.00 482.04 87.44
06.00 CARPINTERIA METALICA
06.01 VENTANA DE SUMIDERO 0.70x0.80M UND 6.00 93.49 560.94 2.00 186.98 33.33 1.00 93.49 16.67 3.00 280.47 50.00
06.02 REJILLA DE CAJA UND 6.00 114.81 688.86 2.00 229.62 33.33 1.00 114.81 16.67 3.00 344.43 50.00
COSTO DIRECTO 01 PAVIMENTACION FLEXIBLE 194411.37 59912.82 30.82% 29457.86 15.15% 89370.68 45.97%
COSTO DIRECTO 02 DESAGUE PLUVIAL 71742.04 58647.02 81.75% 3205.36 4.47% 61852.38 86.21%
SUB TOTAL 266153.41 118559.84 32663.22 151223.06
GASTOS GENERALES 7% 18630.74 8299.19 2286.43 10585.61
UTILIDADES 5% 13307.67 5927.99 1633.16 7561.15
SUB TOTAL 298091.82 132787.02 36582.80 169369.83
IMPUESTO IGV 19 % 56637.45 25229.53 6950.73 32180.27
TOTAL GENERAL 354729.27 158016.56 44.55% 43533.54 12.27% 201550.09 56.82%

AVANCE FISICO % VALORIZACION S/.


MES ANTER. 44.55% 158016.56
DEL MES 12.27% 43533.54
ACUMULADO 56.82% 201550.09
IAM VILLAFUERTE PACHECO

RGE CHUCOS DE LA CRUZ

3de Marzo del 2010


SALDO

METRADO VALORIZ. S/. %

0.00 0.00 0.00


0.25 475.53 100.00
0.00 0.00
0.00 0.00 0.00
277.99 236.29 14.60
0.00 0.00 0.00

66.60 338.99 5.79


0.00 0.00 0.00
0.00 0.00 0.00
18.29 392.32 100.00
0.00 0.00 0.00
4.73 99.52 100.00

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

0.00 -0.02 0.00


0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

0.00 0.00 0.00


4.64 21.72 1.26
54.64 214.19 14.78
54.64 311.45 14.78
226.70 523.68 15.95

41.44 307.07 8.79


92.76 434.12 21.19
92.76 363.62 21.19
92.76 528.73 21.19
IAM VILLAFUERTE PACHECO

RGE CHUCOS DE LA CRUZ

3de Marzo del 2010


SALDO

METRADO VALORIZ. S/. %


1346.70 3124.34 94.72

1097.20 5990.71 100.00


1097.20 57449.39 100.00

45.06 1666.77 98.56


60.97 17158.79 99.58

4.73 1352.21
3.94 145.74 100.00

3.43 1024.23 100.00


6.86 184.26

0.00 0.00 0.00


3.12 842.93 12.19
0.00 0.00
187.20 263.95 35.73
118.50 545.10 22.61
0.00 0.00 0.00
182.22 5331.76 34.77

1.35 42.70 58.44


8.00 239.04 74.07

179.09 351.02 100.00

0.00 0.00 0.00


0.00 0.00 0.00
10.00 167.90 50.00

228.62 907.62 100.00


95.70 373.23 100.00
191.00 618.84 100.00
12.00 152.28 100.00
IAM VILLAFUERTE PACHECO

RGE CHUCOS DE LA CRUZ

3de Marzo del 2010


SALDO

METRADO VALORIZ. S/. %


1.00 384.08 100.00
1.00 358.52 100.00

0.00 0.00 0.00


2.00 798.06 100.00

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

2000.00 1320.00 100.00

0.00 0.00 0.00

0.00 0.00 0.00


0.00 0.00 0.00
3.78 108.68 48.28
5.10 9.43 1.08

59.80 275.68 12.69

0.00 0.00 0.00


64.40 220.25 30.04
64.40 267.90 30.04
64.40 355.49 30.04
36.80 550.90 7.81

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00
IAM VILLAFUERTE PACHECO

RGE CHUCOS DE LA CRUZ

3de Marzo del 2010


SALDO

METRADO VALORIZ. S/. %


1.80 2086.87 45.00
0.20 213.22 4.00
7.00 442.89 38.89

1.00 344.68 100.00


2.00 126.54 40.00
0.00 0.00
3.00 1270.08 50.00
3.00 181.74 50.00

0.00 0.00 0.00


22.20 1207.46 100.00
34.00 1441.60 62.96
6.00 92.10 100.00

59.20 69.26 12.56

3.00 280.47 50.00


3.00 344.43 50.00
105040.67 54.03%
9889.67 13.79%
114930.34
8045.12
5746.52
128721.98
24457.18
153179.16 43.18%
VALORIZACION DE AVANCE FISICO Nº 01 FEBRERO 2010 - II ETAPA
DEL15/02/2010 AL 20/02/2010
OBRA : "MEJORAMIENTO DE PISTAS Y VEREDAS DE AV. JOSE OLAYA TRAMO : AV. GIRALDEZ - PROLONG. PUNO RESIDENTE : ING. MIRIAM VILLAFUERTE PACHECO

CODIGO : 15-036-074-2063804-2164992-0086 SUPERVISOR : ING. JORGE CHUCOS DE LA CRUZ


: PAVIMENTACION FLEXIBLE
CLIENTE : MUNICIPALIDAD PROVINCIAL DE HUANCAYO

Departamento : JUNIN Provincia : HUANCAYO Distrito : HUANCAYO Fecha de Presentacion :20de Febrero del 2010
PRESUPUESTO REFERENCIAL AVANCES
ITEM DESCRIPCION Unidad Metrado Precio Parcial MES ANTERIOR SEMANA III ACUMULADO
METRADO VALORIZA. S/. % METRADO VALORIZ. S/. % METRADO VALORIZ. S/. %
01.00 OBRAS PROVISIONALES
01.01 ALMACEN Y CASETA DE GUARDIANIA MES 0.25 437.84 109.46 0.25 109.46 100.00 0.00 0.00 0.00 0.25 109.46 100.00
01.02 CARTEL DE IDENTIFICACION DE OBRA UND 0.25 1,902.11 475.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.00 OBRAS PRELIMINARES
02.01 TRAZO Y REPLANTEO M2 1,904.10 0.87 1,656.57 1904.10 1656.57 100.00 0.00 0.00 0.00 1904.10 1656.57 100.00
02.02 TRAZO Y REPLANTEO DURANTE LA EJECUCION M2 1,904.08 0.85 1,618.47 1626.09 1382.18 85.40 0.00 0.00 0.00 1626.09 1382.18 85.40
02.03 ROTURA DE VEREDAS M3 0.48 42.58 20.44 0.48 20.44 100.00 0.00 0.00 0.00 0.48 20.44 100.00
03.00 EXPLANACIONES
03.01 MOVIMIENTO DE TIERRAS
03.01.01 CORTE DE TERRENO DE SUB RASANTE M3 1,149.87 5.09 5,852.84 933.67 4752.38 81.20 0.00 0.00 0.00 933.67 4752.38 81.20
03.01.02 CORTE PARA MEJORAM. DE SUB BASE M3 46.08 5.08 234.09 46.08 234.09 100.00 0.00 0.00 0.00 46.08 234.09 100.00
03.01.03 CORTE DE TERRENO MANUAL M3 59.80 21.45 1,282.71 59.80 1282.71 100.00 0.00 0.00 0.00 59.80 1282.71 100.00
03.01.04 EXCAVACION MANUAL PARA CUNETA M3 18.29 21.45 392.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.01.05 EXCAVACION MANUAL PARA SARDINEL M3 28.17 21.45 604.25 28.17 604.25 100.00 0.00 0.00 0.00 28.17 604.25 100.00
03.01.06 EXCAVACION MANUAL EN BADEN M3 4.73 21.04 99.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.02 ELIMINACION DE MATERIAL EXCEDENTE
03.02.01 ACARREO INTERNO DE MATERIAL M3 133.80 17.94 2,400.37 133.80 2400.37 100.00 0.00 0.00 0.00 133.80 2400.37 100.00
03.02.02 CARGUIO (ELIM.DE MATERIAL EXCEDENTE) M3 1,568.94 3.63 5,695.25 1568.94 5695.25 100.00 0.00 0.00 0.00 1568.94 5695.25 100.00
03.02.03 TRANSPORTE (ELIM. MAT. EXCEDENTE) M3 1,568.94 5.70 8,942.96 1568.94 8942.96 100.00 0.00 0.00 0.00 1568.94 8942.96 100.00
03.02.04 ESCARIFICADO PERFILADO/COMPACTADO M2 1,421.70 2.28 3,241.48 1421.70 3241.48 100.00 0.00 0.00 0.00 1421.70 3241.48 100.00
04.00 PAVIMENTOS
04.01 MEJORAMIENTO DE SUB RASANTE
04.01.01 EXTRACCION DE MATERIAL P/MEJ. SUB RASANTE M3 305.70 7.42 2,268.27 305.70 2268.27 100.00 0.00 0.00 0.00 305.70 2268.27 100.00
04.01.02 SELECCION DE MATERIAL P/ MEJ DE SUB RASANTE M3 251.00 4.68 1,174.68 251.00 1174.68 100.00 0.00 0.00 0.00 251.00 1174.68 100.00
04.01.03 CARGUIO DE (MEJ. S-R) M3 251.00 3.83 961.33 251.00 961.33 100.00 0.00 0.00 0.00 251.00 961.33 100.00
04.01.04 TRANSPORTE (MEJ. S-R) M3 251.00 5.70 1,430.70 251.00 1430.70 100.00 0.00 0.00 0.00 251.00 1430.70 100.00
04.01.05 EXT. RIEGO Y COMPC. P/MEJ DE SUB RASANTE M2 1,165.00 2.18 2,539.70 1165.00 2539.70 100.00 0.00 0.00 0.00 1165.00 2539.70 100.00
04.02 SUB BASE GRANULAR
04.02.01 EXTRACCION DE MATERIAL PARA SUB BASE M3 398.08 7.41 2,949.77 398.08 2949.77 100.00 0.00 0.00 0.00 398.08 2949.77 100.00
04.02.02 SELECCION DE MATERIAL P/ SUB BASE GRANULAR M3 369.64 4.68 1,729.92 365.00 1708.20 98.74 0.00 0.00 0.00 365.00 1708.20 98.74
04.02.03 CARGUIO DE S-B M3 369.64 3.92 1,448.99 315.00 1234.80 85.22 0.00 0.00 0.00 315.00 1234.80 85.22
04.02.04 TRANSPORTE DE S.B. M3 369.64 5.70 2,106.95 315.00 1795.50 85.22 0.00 0.00 0.00 315.00 1795.50 85.22
04.02.05 EXT. RIEGO Y COMPC. DE SUB BASE E= 0.20m. M2 1,421.70 2.31 3,284.13 1195.00 2760.45 84.05 0.00 0.00 0.00 1195.00 2760.45 84.05
04.03 BASE GRANULAR
04.03.01 EXTRACCION DE MATERIAL PARA BASE M3 471.44 7.41 3,493.37 230.00 1704.30 48.79 0.00 0.00 0.00 230.00 1704.30 48.79
04.03.02 SELECCION DE MATERIAL P/ BASE GRANULAR M3 437.76 4.68 2,048.72 150.00 702.00 34.27 0.00 0.00 0.00 150.00 702.00 34.27
04.03.03 CARGUIO DE B. M3 437.76 3.92 1,716.02 195.00 764.40 44.54 0.00 0.00 0.00 195.00 764.40 44.54
04.03.04 TRANSPORTE DE B. M3 437.76 5.70 2,495.23 195.00 1111.50 44.54 0.00 0.00 0.00 195.00 1111.50 44.54
VALORIZACION DE AVANCE FISICO Nº 01 FEBRERO 2010 - II ETAPA
DEL15/02/2010 AL 20/02/2010
OBRA : "MEJORAMIENTO DE PISTAS Y VEREDAS DE AV. JOSE OLAYA TRAMO : AV. GIRALDEZ - PROLONG. PUNO RESIDENTE : ING. MIRIAM VILLAFUERTE PACHECO

CODIGO : 15-036-074-2063804-2164992-0086 SUPERVISOR : ING. JORGE CHUCOS DE LA CRUZ


: PAVIMENTACION FLEXIBLE
CLIENTE : MUNICIPALIDAD PROVINCIAL DE HUANCAYO

Departamento : JUNIN Provincia : HUANCAYO Distrito : HUANCAYO Fecha de Presentacion :20de Febrero del 2010
PRESUPUESTO REFERENCIAL AVANCES
ITEM DESCRIPCION Unidad Metrado Precio Parcial MES ANTERIOR SEMANA III ACUMULADO
METRADO VALORIZA. S/. % METRADO VALORIZ. S/. % METRADO VALORIZ. S/. %
04.03.05 EXT. RIEGO Y COMPC. DE BASE E= 0.20m. M2 1,421.70 2.32 3,298.34 75.00 174.00 5.28 0.00 0.00 0.00 75.00 174.00 5.28
04.04 CARPETA ASFALTICA
04.04.01 IMPRIMACION ASFALTICA M2 1,097.20 5.46 5,990.71 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.04.02 CARPETA ASFALTICA EN CALIENTE E= 3" M2 1,097.20 52.36 57,449.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.00 DRENAJE
05.01 ENCOFRADO Y DESENCOFRADO DE CUNETAS M2 45.72 36.99 1,691.18 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.02 CUNETAS CONCRETO F'C=175 KG/CM2 M3 61.23 281.43 17,231.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.00 BADEN
06.01 BADEN CONCRETO F'C=210 KG/CM2 M3 4.73 285.88 1,352.21 0.00 0.00 0.00 0.00 0.00
06.02 BADEN ENCOFRADO Y DESENCOFRADO M2 3.94 36.99 145.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.00 SARDINEL INEXPUESTO
07.01 SARDINEL INEXP. CONCRETO F'C=210 KG/CM2 M3 3.43 298.61 1,024.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.02 SARDINEL INEXP. ENCOFRADO Y DESENCOFRADO M2 6.86 26.86 184.26 0.00 0.00 0.00 0.00 0.00
08.00 ACERA PEATONAL
08.01 SARDINEL EXPUESTO
08.01.01 SARDINEL EXP. ENCOFRADO Y DESENCOFRADO M2 170.63 30.13 5,141.08 170.63 5141.08 100.00 0.00 0.00 0.00 170.63 5141.08 100.00
08.01.02 SARDINEL EXP. CONCRETO F'C=175 KG/CM2 M3 25.59 270.17 6,913.65 22.34 6035.60 87.30 0.00 0.00 0.00 22.34 6035.60 87.30
VEREDAS
08.02.01 REFINE Y NIVELACION M2 524.00 1.41 738.84 336.80 474.89 64.27 0.00 0.00 0.00 336.80 474.89 64.27
08.02.02 RELLENO Y COMPACTADO DE VEREDA M2 524.00 4.60 2,410.40 405.50 1865.30 77.39 0.00 0.00 0.00 405.50 1865.30 77.39
08.02.03 VEREDA ENCOFRADO Y DESENCOFRADO M2 12.57 29.31 368.43 12.57 368.43 100.00 0.00 0.00 0.00 12.57 368.43 100.00
08.02.04 VEREDAS CONCRETO F'C=175 KG/CM2 M2 524.00 29.26 15,332.24 341.78 10000.48 65.23 0.00 0.00 0.00 341.78 10000.48 65.23
9.00 RAMPAS
9.01 ENCOFRADO Y DESENCOFRADO RAMPA M2 2.31 31.63 73.07 0.96 30.36 41.56 0.00 0.00 0.00 0.96 30.36 41.56
9.02 RAMPA CONCRETO F'C=175 KG/CM2 M2 10.80 29.88 322.70 2.80 83.66 25.93 0.00 0.00 0.00 2.80 83.66 25.93
10.00 JUNTAS
10.01 RELLENO DE JUNTAS M 179.09 1.96 351.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.00 AREAS VERDES
11.01 SUMINISTRO DE TIERRA AGRICOLA M3 72.30 33.76 2,440.85 15.16 511.80 20.97 30.61 1033.39 42.34 45.77 1545.20 63.31
11.02 COLOCACION DE GRASS M2 241.00 10.20 2,458.20 0.00 0.00 0.00 102.04 1040.81 42.34 102.04 1040.81 42.34
11.03 COLOCACION DE PLANTONES UND 20.00 16.79 335.80 0.00 0.00 0.00 18.00 302.22 90.00 18.00 302.22 90.00
12.00 SEÑALIZACION
12.01 SEÑALIZACION HORIZONTAL
12.01.01 PINTURA LINEAL EN BORDE DE VIA M 228.62 3.97 907.62 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12.01.02 PINTURA LINEAL CONTINUA EN EJE DE VIA M 95.70 3.90 373.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12.01.03 PINTURA LINEAL DISCONTINUA EN EJE DE VIA M 191.00 3.24 618.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12.01.04 PINTURA DE SIMBOLOS Y FLECHAS M2 12.00 12.69 152.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12.02 SEÑALIZACION VERTICAL
VALORIZACION DE AVANCE FISICO Nº 01 FEBRERO 2010 - II ETAPA
DEL15/02/2010 AL 20/02/2010
OBRA : "MEJORAMIENTO DE PISTAS Y VEREDAS DE AV. JOSE OLAYA TRAMO : AV. GIRALDEZ - PROLONG. PUNO RESIDENTE : ING. MIRIAM VILLAFUERTE PACHECO

CODIGO : 15-036-074-2063804-2164992-0086 SUPERVISOR : ING. JORGE CHUCOS DE LA CRUZ


: PAVIMENTACION FLEXIBLE
CLIENTE : MUNICIPALIDAD PROVINCIAL DE HUANCAYO

Departamento : JUNIN Provincia : HUANCAYO Distrito : HUANCAYO Fecha de Presentacion :20de Febrero del 2010
PRESUPUESTO REFERENCIAL AVANCES
ITEM DESCRIPCION Unidad Metrado Precio Parcial MES ANTERIOR SEMANA III ACUMULADO
METRADO VALORIZA. S/. % METRADO VALORIZ. S/. % METRADO VALORIZ. S/. %
12.02.01 SEÑALES TIPO R (90cM x 60cm) UND 1.00 384.08 384.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12.02.02 SEÑALES TIPO F UND 1.00 358.52 358.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.00 EQUIPAMIENTO
13.01 MOVILIARIO URBANO UND 3.00 545.16 1,635.48 2.50 1362.90 83.33 0.50 272.58 16.67 3.00 1635.48 100.00
13.02 SUMINISTRO Y COLOCACION DE TACHOS DE BASURA UND 2.00 399.03 798.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
14.00 RECONEXIONES
14.01 RECONEXIONES DE PUNTOS DE AGUA PTO 6.00 13.99 83.94 6.00 83.94 100.00 0.00 0.00 0.00 6.00 83.94 100.00
14.02 RECONEXION DE CAJA MEDIDOR DE AGUA PTO 6.00 12.96 77.76 6.00 77.76 100.00 0.00 0.00 0.00 6.00 77.76 100.00
14.03 RECONEXION DE INSTALACIONES DE DESAGUE PTO 6.00 17.56 105.36 6.00 105.36 100.00 0.00 0.00 0.00 6.00 105.36 100.00
14.04 RECONEXION DE CAJA DE REGISTRO DE DESAGUE PTO 6.00 11.31 67.86 6.00 67.86 100.00 0.00 0.00 0.00 6.00 67.86 100.00
15.00 VARIOS
15.01 LIMPIEZA FINAL DE OBRA M2 2,000.00 0.66 1,320.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

DESAGUE PLUVIAL

01.00 TRABAJOS PRELIMINARES


01.01 TRAZO NIVELES Y REPLANTEO DE ZANJA M 395.00 0.56 221.20 395.00 221.20 100.00 0.00 0.00 0.00 395.00 221.20 100.00
02.00 MOVIMIENTO DE TIERRAS

02.01 EXCAVACIONES
02.01.01 EXCAVACION PARA BUZONES M3 32.63 21.45 699.91 32.63 699.91 100.00 0.00 0.00 0.00 32.63 699.91 100.00
02.01.02 EXCAVACION DE ZANJAS - MANUAL M 471.20 15.02 7,077.42 531.80 7987.64 112.86 0.00 0.00 0.00 531.80 7987.64 112.86
02.01.03 EXCAVACION PARA SUMIDEROS M3 7.83 28.75 225.11 4.05 116.44 51.72 0.00 0.00 0.00 4.05 116.44 51.72
02.01.04 REFINE Y NIVELACION EN ZANJAS M 471.20 1.85 871.72 466.10 862.29 98.92 0.00 0.00 0.00 466.10 862.29 98.92
02.02 CAMAS DE APOYO
02.02.01 PREPARACION DE CAMAS DE APOYO M 471.20 4.61 2,172.23 411.40 1896.55 87.31 0.00 0.00 0.00 411.40 1896.55 87.31
02.03 RELLENOS
02.03.01 EXTRACCION DE MAT. P/RELLENO M3 230.89 6.39 1,475.39 230.89 1475.39 100.00 0.00 0.00 0.00 230.89 1475.39 100.00
02.03.02 SELECCIÓN DE MATERIAL P/RELLENO M3 214.40 3.42 733.25 150.00 513.00 69.96 0.00 0.00 0.00 150.00 513.00 69.96
02.03.03 CARGUIO P/ RELLENO M3 214.40 4.16 891.90 150.00 624.00 69.96 0.00 0.00 0.00 150.00 624.00 69.96
02.03.04 TRANSPORTE P/ RELLENO M3 214.40 5.52 1,183.49 150.00 828.00 69.96 0.00 0.00 0.00 150.00 828.00 69.96
02.03.05 RELLENO Y COMPACTADO DE ZANJA M 471.20 14.97 7,053.86 434.40 6502.97 92.19 0.00 0.00 0.00 434.40 6502.97 92.19
02.04 ELIMINACION DE MATERIAL EXCEDENTE
02.04.01 ACARREO INTERNO DE MATERIAL M3 48.55 13.46 653.48 48.55 653.48 100.00 0.00 0.00 0.00 48.55 653.48 100.00
02.04.02 CARGUIO (ELIM. MAT. EXCEDENTE) M3 48.55 3.92 190.32 48.55 190.32 100.00 0.00 0.00 0.00 48.55 190.32 100.00
02.04.03 TRANSPORTE (ELIM. MAT. EXCEDENTE) M3 48.55 5.70 276.74 48.55 276.74 100.00 0.00 0.00 0.00 48.55 276.74 100.00
03.00 OBRAS DE CONCRETO ARMADO
03.01 CONSTRUCCION DE BUZONES
VALORIZACION DE AVANCE FISICO Nº 01 FEBRERO 2010 - II ETAPA
DEL15/02/2010 AL 20/02/2010
OBRA : "MEJORAMIENTO DE PISTAS Y VEREDAS DE AV. JOSE OLAYA TRAMO : AV. GIRALDEZ - PROLONG. PUNO RESIDENTE : ING. MIRIAM VILLAFUERTE PACHECO

CODIGO : 15-036-074-2063804-2164992-0086 SUPERVISOR : ING. JORGE CHUCOS DE LA CRUZ


: PAVIMENTACION FLEXIBLE
CLIENTE : MUNICIPALIDAD PROVINCIAL DE HUANCAYO

Departamento : JUNIN Provincia : HUANCAYO Distrito : HUANCAYO Fecha de Presentacion :20de Febrero del 2010
PRESUPUESTO REFERENCIAL AVANCES
ITEM DESCRIPCION Unidad Metrado Precio Parcial MES ANTERIOR SEMANA III ACUMULADO
METRADO VALORIZA. S/. % METRADO VALORIZ. S/. % METRADO VALORIZ. S/. %
03.01.01 CONSTRUCCION DE BUZON H =1..50m UND 4.00 1159.37 4,637.48 1.85 2144.83 46.25 0.70 811.56 17.50 2.55 2956.39 63.75
03.01.02 CONSTRUCCION DE BUZON H =1.70m UND 5.00 1,066.12 5,330.60 4.45 4744.23 89.00 0.00 0.00 0.00 4.45 4744.23 89.00
03.01.03 DADOS DE CONCRETO F'C= 140KG/CM² UND 18.00 63.27 1,138.86 11.00 695.97 61.11 0.00 0.00 0.00 11.00 695.97 61.11
03.02 ENCIMADO DE BUZONES
03.02.01 CONST. ENCIM.BUZON H= 0.45m. S.M.yTAPA UND 1.00 344.68 344.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.02.02 DADOS DE CONCRETO F'C= 140KG/CM² UND 5.00 63.27 316.35 3.00 189.81 60.00 0.00 0.00 0.00 3.00 189.81 60.00
03.03 SUMIDEROS
03.03.01 CONSTRUCCION DE SUMIDERO UND 6.00 423.36 2,540.16 3.00 1270.08 50.00 0.00 0.00 0.00 3.00 1270.08 50.00
03.03.02 CONSTRUCCION DE CAJA RECEPTOR UND 6.00 60.58 363.48 3.00 181.74 50.00 0.00 0.00 0.00 3.00 181.74 50.00
04.00 SUMINISTRO Y TENDIDO DE TUBERIA
04.01 TENDIDO DE TUBERIA UPVC U/F S-25 D=12" M 395.00 70.77 27,954.15 395.00 27954.15 100.00 0.00 0.00 0.00 395.00 27954.15 100.00
04.02 TENDIDO DE TUBERIA UPVC U/F S-25 D=10" M 22.20 54.39 1,207.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.03 TENDIDO DE TUBERIA UPVC U/F S-25 D=8" M 54.00 42.40 2,289.60 20.00 848.00 37.04 0.00 0.00 0.00 20.00 848.00 37.04
04.04 SUMINISTRO Y COLOCACION DE ACCESORIOS UND 6.00 15.35 92.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.00 PRUEBA HIDRAULICA
05.01 PRUEBA A ZANJA TAPADA P/TUBERIA M 471.20 1.17 551.30 412.00 482.04 87.44 0.00 0.00 0.00 412.00 482.04 87.44
06.00 CARPINTERIA METALICA
06.01 VENTANA DE SUMIDERO 0.70x0.80M UND 6.00 93.49 560.94 3.00 280.47 50.00 0.00 0.00 0.00 3.00 280.47 50.00
06.02 REJILLA DE CAJA UND 6.00 114.81 688.86 3.00 344.43 50.00 0.00 0.00 0.00 3.00 344.43 50.00
COSTO DIRECTO 01 PAVIMENTACION FLEXIBLE 194411.37 79811.16 41.05% 2649.00 1.36% 82460.16 42.42%
COSTO DIRECTO 02 DESAGUE PLUVIAL 71742.04 61983.67 86.40% 811.56 1.13% 62795.23 87.53%
SUB TOTAL 266153.41 141794.83 3460.56 145255.39
GASTOS GENERALES 7% 18630.74 9925.64 242.24 10167.88
UTILIDADES 5% 13307.67 7089.74 173.03 7262.77
SUB TOTAL 298091.82 158810.21 3875.83 162686.04
IMPUESTO IGV 19 % 56637.45 30173.94 736.41 30910.35
TOTAL GENERAL 354729.27 188984.15 53.28% 4612.24 1.30% 193596.38 54.58%

AVANCE FISICO % VALORIZACION S/.


MES ANTER. 53.28% 188984.15
DE LA SEMANA 1.30% 4612.24
ACUMULADO 54.58% 193596.38
IAM VILLAFUERTE PACHECO

RGE CHUCOS DE LA CRUZ

0de Febrero del 2010


SALDO

METRADO VALORIZ. S/. %

0.00 0.00 0.00


0.25 475.53 100.00
0.00 0.00
0.00 0.00 0.00
277.99 236.29 14.60
0.00 0.00 0.00

216.20 1100.46 18.80


0.00 0.00 0.00
0.00 0.00 0.00
18.29 392.32 100.00
0.00 0.00 0.00
4.73 99.52 100.00

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

0.00 0.00 0.00


4.64 21.72 1.26
54.64 214.19 14.78
54.64 311.45 14.78
226.70 523.68 15.95

241.44 1789.07 51.21


287.76 1346.72 65.73
242.76 951.62 55.46
242.76 1383.73 55.46
IAM VILLAFUERTE PACHECO

RGE CHUCOS DE LA CRUZ

0de Febrero del 2010


SALDO

METRADO VALORIZ. S/. %


1346.70 3124.34 94.72

1097.20 5990.71 100.00


1097.20 57449.39 100.00

45.72 1691.18 100.00


61.23 17231.96 100.00

4.73 1352.21
3.94 145.74 100.00

3.43 1024.23 100.00


6.86 184.26

0.00 0.00 0.00


3.25 878.05 12.70
0.00 0.00
187.20 263.95 35.73
118.50 545.10 22.61
0.00 0.00 0.00
182.22 5331.76 34.77

1.35 42.70 58.44


8.00 239.04 74.07

179.09 351.02 100.00

26.53 895.65 36.69


138.96 1417.39 57.66
2.00 33.58 10.00

228.62 907.62 100.00


95.70 373.23 100.00
191.00 618.84 100.00
12.00 152.28 100.00
IAM VILLAFUERTE PACHECO

RGE CHUCOS DE LA CRUZ

0de Febrero del 2010


SALDO

METRADO VALORIZ. S/. %


1.00 384.08 100.00
1.00 358.52 100.00

0.00 0.00 0.00


2.00 798.06 100.00

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

2000.00 1320.00 100.00

0.00 0.00 0.00

0.00 0.00 0.00


-60.60 -910.21 -12.86
3.78 108.68 48.28
5.10 9.43 1.08

59.80 275.68 12.69

0.00 0.00 0.00


64.40 220.25 30.04
64.40 267.90 30.04
64.40 355.49 30.04
36.80 550.90 7.81

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00
IAM VILLAFUERTE PACHECO

RGE CHUCOS DE LA CRUZ

0de Febrero del 2010


SALDO

METRADO VALORIZ. S/. %


1.45 1681.09 36.25
0.55 586.37 11.00
7.00 442.89 38.89

1.00 344.68 100.00


2.00 126.54 40.00
0.00 0.00
3.00 1270.08 50.00
3.00 181.74 50.00

0.00 0.00 0.00


22.20 1207.46 100.00
34.00 1441.60 62.96
6.00 92.10 100.00

59.20 69.26 12.56

3.00 280.47 50.00


3.00 344.43 50.00
111951.19 57.58%
8946.82 12.47%
120898.01
8462.86
6044.90
135405.77
25727.10
161132.86 45.42%
VALORIZACION DE AVANCE FISICO Nº 01 FEBRERO 2010 - II ETAPA
DEL 01/02/2010 AL06/02/2010
OBRA : "MEJORAMIENTO DE PISTAS Y VEREDAS DE AV. JOSE OLAYA TRAMO : AV. GIRALDEZ - PROLONG. PUNO RESIDENTE : ING. MIRIAM VILLAFUERTE PACHECO

CODIGO : 15-036-074-2063804-2164992-0086 SUPERVISOR : ING. JORGE CHUCOS DE LA CRUZ


: PAVIMENTACION FLEXIBLE
CLIENTE : MUNICIPALIDAD PROVINCIAL DE HUANCAYO

Departamento : JUNIN Provincia : HUANCAYO Distrito : HUANCAYO Fecha de Presentacion :06de Febrero del 2010
PRESUPUESTO REFERENCIAL AVANCES
ITEM DESCRIPCION Unidad Metrado Precio Parcial MES ANTERIOR SEMANA II ACUMULADO
METRADO VALORIZA. S/. % METRADO VALORIZ. S/. % METRADO VALORIZ. S/. %
01.00 OBRAS PROVISIONALES
01.01 ALMACEN Y CASETA DE GUARDIANIA MES 0.25 437.84 109.46 0.25 109.46 100.00 0.00 0.00 0.00 0.25 109.46 100.00
01.02 CARTEL DE IDENTIFICACION DE OBRA UND 0.25 1,902.11 475.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.00 OBRAS PRELIMINARES
02.01 TRAZO Y REPLANTEO M2 1,904.10 0.87 1,656.57 1904.10 1656.57 100.00 0.00 0.00 0.00 1904.10 1656.57 100.00
02.02 TRAZO Y REPLANTEO DURANTE LA EJECUCION M2 1,904.08 0.85 1,618.47 1456.09 1237.68 76.47 170.00 144.50 8.93 1626.09 1382.18 85.40
02.03 ROTURA DE VEREDAS M3 0.48 42.58 20.44 0.48 20.44 100.00 0.00 0.00 0.00 0.48 20.44 100.00
03.00 EXPLANACIONES
03.01 MOVIMIENTO DE TIERRAS
03.01.01 CORTE DE TERRENO DE SUB RASANTE M3 1,149.87 5.09 5,852.84 933.67 4752.38 81.20 0.00 0.00 0.00 933.67 4752.38 81.20
03.01.02 CORTE PARA MEJORAM. DE SUB BASE M3 46.08 5.08 234.09 46.08 234.09 100.00 0.00 0.00 0.00 46.08 234.09 100.00
03.01.03 CORTE DE TERRENO MANUAL M3 59.80 21.45 1,282.71 59.80 1282.71 100.00 0.00 0.00 0.00 59.80 1282.71 100.00
03.01.04 EXCAVACION MANUAL PARA CUNETA M3 18.29 21.45 392.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.01.05 EXCAVACION MANUAL PARA SARDINEL M3 28.17 21.45 604.25 17.97 385.46 63.79 10.20 218.79 36.21 28.17 604.25 100.00
03.01.06 EXCAVACION MANUAL EN BADEN M3 4.73 21.04 99.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.02 ELIMINACION DE MATERIAL EXCEDENTE
03.02.01 ACARREO INTERNO DE MATERIAL M3 133.80 17.94 2,400.37 133.80 2400.37 100.00 0.00 0.00 0.00 133.80 2400.37 100.00
03.02.02 CARGUIO (ELIM.DE MATERIAL EXCEDENTE) M3 1,568.94 3.63 5,695.25 1535.00 5572.05 97.84 33.94 123.20 2.16 1568.94 5695.25 100.00
03.02.03 TRANSPORTE (ELIM. MAT. EXCEDENTE) M3 1,568.94 5.70 8,942.96 1535.00 8749.50 97.84 33.94 193.46 2.16 1568.94 8942.96 100.00
03.02.04 ESCARIFICADO PERFILADO/COMPACTADO M2 1,421.70 2.28 3,241.48 1421.70 3241.48 100.00 0.00 0.00 0.00 1421.70 3241.48 100.00
04.00 PAVIMENTOS
04.01 MEJORAMIENTO DE SUB RASANTE
04.01.01 EXTRACCION DE MATERIAL P/MEJ. SUB RASANTE M3 305.70 7.42 2,268.27 305.70 2268.27 100.00 0.00 0.00 0.00 305.70 2268.27 100.00
04.01.02 SELECCION DE MATERIAL P/ MEJ DE SUB RASANTE M3 251.00 4.68 1,174.68 251.00 1174.68 100.00 0.00 0.00 0.00 251.00 1174.68 100.00
04.01.03 CARGUIO DE (MEJ. S-R) M3 251.00 3.83 961.33 251.00 961.33 100.00 0.00 0.00 0.00 251.00 961.33 100.00
04.01.04 TRANSPORTE (MEJ. S-R) M3 251.00 5.70 1,430.70 251.00 1430.70 100.00 0.00 0.00 0.00 251.00 1430.70 100.00
04.01.05 EXT. RIEGO Y COMPC. P/MEJ DE SUB RASANTE M2 1,165.00 2.18 2,539.70 1165.00 2539.70 100.00 0.00 0.00 0.00 1165.00 2539.70 100.00
04.02 SUB BASE GRANULAR
04.02.01 EXTRACCION DE MATERIAL PARA SUB BASE M3 398.08 7.41 2,949.77 398.08 2949.77 100.00 0.00 0.00 0.00 398.08 2949.77 100.00
04.02.02 SELECCION DE MATERIAL P/ SUB BASE GRANULAR M3 369.64 4.68 1,729.92 365.00 1708.20 98.74 0.00 0.00 0.00 365.00 1708.20 98.74
04.02.03 CARGUIO DE S-B M3 369.64 3.92 1,448.99 315.00 1234.80 85.22 0.00 0.00 0.00 315.00 1234.80 85.22
04.02.04 TRANSPORTE DE S.B. M3 369.64 5.70 2,106.95 315.00 1795.50 85.22 0.00 0.00 0.00 315.00 1795.50 85.22
04.02.05 EXT. RIEGO Y COMPC. DE SUB BASE E= 0.20m. M2 1,421.70 2.31 3,284.13 1195.00 2760.45 84.05 0.00 0.00 0.00 1195.00 2760.45 84.05
04.03 BASE GRANULAR
04.03.01 EXTRACCION DE MATERIAL PARA BASE M3 471.44 7.41 3,493.37 230.00 1704.30 48.79 0.00 0.00 0.00 230.00 1704.30 48.79
04.03.02 SELECCION DE MATERIAL P/ BASE GRANULAR M3 437.76 4.68 2,048.72 150.00 702.00 34.27 0.00 0.00 0.00 150.00 702.00 34.27
04.03.03 CARGUIO DE B. M3 437.76 3.92 1,716.02 150.00 588.00 34.27 45.00 176.40 10.28 195.00 764.40 44.54
04.03.04 TRANSPORTE DE B. M3 437.76 5.70 2,495.23 150.00 855.00 34.27 45.00 256.50 10.28 195.00 1111.50 44.54
VALORIZACION DE AVANCE FISICO Nº 01 FEBRERO 2010 - II ETAPA
DEL 01/02/2010 AL06/02/2010
OBRA : "MEJORAMIENTO DE PISTAS Y VEREDAS DE AV. JOSE OLAYA TRAMO : AV. GIRALDEZ - PROLONG. PUNO RESIDENTE : ING. MIRIAM VILLAFUERTE PACHECO

CODIGO : 15-036-074-2063804-2164992-0086 SUPERVISOR : ING. JORGE CHUCOS DE LA CRUZ


: PAVIMENTACION FLEXIBLE
CLIENTE : MUNICIPALIDAD PROVINCIAL DE HUANCAYO

Departamento : JUNIN Provincia : HUANCAYO Distrito : HUANCAYO Fecha de Presentacion :06de Febrero del 2010
PRESUPUESTO REFERENCIAL AVANCES
ITEM DESCRIPCION Unidad Metrado Precio Parcial MES ANTERIOR SEMANA II ACUMULADO
METRADO VALORIZA. S/. % METRADO VALORIZ. S/. % METRADO VALORIZ. S/. %
04.03.05 EXT. RIEGO Y COMPC. DE BASE E= 0.20m. M2 1,421.70 2.32 3,298.34 0.00 0.00 0.00 75.00 174.00 5.28 75.00 174.00 5.28
04.04 CARPETA ASFALTICA
04.04.01 IMPRIMACION ASFALTICA M2 1,097.20 5.46 5,990.71 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.04.02 CARPETA ASFALTICA EN CALIENTE E= 3" M2 1,097.20 52.36 57,449.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.00 DRENAJE
05.01 ENCOFRADO Y DESENCOFRADO DE CUNETAS M2 45.72 36.99 1,691.18 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.02 CUNETAS CONCRETO F'C=175 KG/CM2 M3 61.23 281.43 17,231.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.00 BADEN
06.01 BADEN CONCRETO F'C=210 KG/CM2 M3 4.73 285.88 1,352.21 0.00 0.00 0.00 0.00 0.00
06.02 BADEN ENCOFRADO Y DESENCOFRADO M2 3.94 36.99 145.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.00 SARDINEL INEXPUESTO
07.01 SARDINEL INEXP. CONCRETO F'C=210 KG/CM2 M3 3.43 298.61 1,024.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.02 SARDINEL INEXP. ENCOFRADO Y DESENCOFRADO M2 6.86 26.86 184.26 0.00 0.00 0.00 0.00 0.00
08.00 ACERA PEATONAL
08.01 SARDINEL EXPUESTO
08.01.01 SARDINEL EXP. ENCOFRADO Y DESENCOFRADO M2 170.63 30.13 5,141.08 126.85 3821.99 74.34 43.78 1319.09 25.66 170.63 5141.08 100.00
08.01.02 SARDINEL EXP. CONCRETO F'C=175 KG/CM2 M3 25.59 270.17 6,913.65 15.69 4238.97 61.31 6.65 1796.63 25.99 22.34 6035.60 87.30
VEREDAS
08.02.01 REFINE Y NIVELACION M2 524.00 1.41 738.84 336.80 474.89 64.27 0.00 0.00 0.00 336.80 474.89 64.27
08.02.02 RELLENO Y COMPACTADO DE VEREDA M2 524.00 4.60 2,410.40 405.50 1865.30 77.39 0.00 0.00 0.00 405.50 1865.30 77.39
08.02.03 VEREDA ENCOFRADO Y DESENCOFRADO M2 12.57 29.31 368.43 12.57 368.43 100.00 0.00 0.00 0.00 12.57 368.43 100.00
08.02.04 VEREDAS CONCRETO F'C=175 KG/CM2 M2 524.00 29.26 15,332.24 341.78 10000.48 65.23 0.00 0.00 0.00 341.78 10000.48 65.23
9.00 RAMPAS
9.01 ENCOFRADO Y DESENCOFRADO RAMPA M2 2.31 31.63 73.07 0.96 30.36 41.56 0.00 0.00 0.00 0.96 30.36 41.56
9.02 RAMPA CONCRETO F'C=175 KG/CM2 M2 10.80 29.88 322.70 2.80 83.66 25.93 0.00 0.00 0.00 2.80 83.66 25.93
10.00 JUNTAS
10.01 RELLENO DE JUNTAS M 179.09 1.96 351.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.00 AREAS VERDES
11.01 SUMINISTRO DE TIERRA AGRICOLA M3 72.30 33.76 2,440.85 0.00 0.00 0.00 15.16 511.80 20.97 15.16 511.80 20.97
11.02 COLOCACION DE GRASS M2 241.00 10.20 2,458.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03 COLOCACION DE PLANTONES UND 20.00 16.79 335.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12.00 SEÑALIZACION
12.01 SEÑALIZACION HORIZONTAL
12.01.01 PINTURA LINEAL EN BORDE DE VIA M 228.62 3.97 907.62 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12.01.02 PINTURA LINEAL CONTINUA EN EJE DE VIA M 95.70 3.90 373.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12.01.03 PINTURA LINEAL DISCONTINUA EN EJE DE VIA M 191.00 3.24 618.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12.01.04 PINTURA DE SIMBOLOS Y FLECHAS M2 12.00 12.69 152.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12.02 SEÑALIZACION VERTICAL
VALORIZACION DE AVANCE FISICO Nº 01 FEBRERO 2010 - II ETAPA
DEL 01/02/2010 AL06/02/2010
OBRA : "MEJORAMIENTO DE PISTAS Y VEREDAS DE AV. JOSE OLAYA TRAMO : AV. GIRALDEZ - PROLONG. PUNO RESIDENTE : ING. MIRIAM VILLAFUERTE PACHECO

CODIGO : 15-036-074-2063804-2164992-0086 SUPERVISOR : ING. JORGE CHUCOS DE LA CRUZ


: PAVIMENTACION FLEXIBLE
CLIENTE : MUNICIPALIDAD PROVINCIAL DE HUANCAYO

Departamento : JUNIN Provincia : HUANCAYO Distrito : HUANCAYO Fecha de Presentacion :06de Febrero del 2010
PRESUPUESTO REFERENCIAL AVANCES
ITEM DESCRIPCION Unidad Metrado Precio Parcial MES ANTERIOR SEMANA II ACUMULADO
METRADO VALORIZA. S/. % METRADO VALORIZ. S/. % METRADO VALORIZ. S/. %
12.02.01 SEÑALES TIPO R (90cM x 60cm) UND 1.00 384.08 384.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12.02.02 SEÑALES TIPO F UND 1.00 358.52 358.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.00 EQUIPAMIENTO
13.01 MOVILIARIO URBANO UND 3.00 545.16 1,635.48 2.00 1090.32 66.67 0.50 272.58 16.67 2.50 1362.90 83.33
13.02 SUMINISTRO Y COLOCACION DE TACHOS DE BASURA UND 2.00 399.03 798.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
14.00 RECONEXIONES
14.01 RECONEXIONES DE PUNTOS DE AGUA PTO 6.00 13.99 83.94 6.00 83.94 100.00 0.00 0.00 0.00 6.00 83.94 100.00
14.02 RECONEXION DE CAJA MEDIDOR DE AGUA PTO 6.00 12.96 77.76 6.00 77.76 100.00 0.00 0.00 0.00 6.00 77.76 100.00
14.03 RECONEXION DE INSTALACIONES DE DESAGUE PTO 6.00 17.56 105.36 6.00 105.36 100.00 0.00 0.00 0.00 6.00 105.36 100.00
14.04 RECONEXION DE CAJA DE REGISTRO DE DESAGUE PTO 6.00 11.31 67.86 6.00 67.86 100.00 0.00 0.00 0.00 6.00 67.86 100.00
15.00 VARIOS
15.01 LIMPIEZA FINAL DE OBRA M2 2,000.00 0.66 1,320.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

DESAGUE PLUVIAL

01.00 TRABAJOS PRELIMINARES


01.01 TRAZO NIVELES Y REPLANTEO DE ZANJA M 395.00 0.56 221.20 395.00 221.20 100.00 0.00 0.00 0.00 395.00 221.20 100.00
02.00 MOVIMIENTO DE TIERRAS

02.01 EXCAVACIONES
02.01.01 EXCAVACION PARA BUZONES M3 32.63 21.45 699.91 32.63 699.91 100.00 0.00 0.00 0.00 32.63 699.91 100.00
02.01.02 EXCAVACION DE ZANJAS - MANUAL M 471.20 15.02 7,077.42 531.80 7987.64 112.86 0.00 0.00 0.00 531.80 7987.64 112.86
02.01.03 EXCAVACION PARA SUMIDEROS M3 7.83 28.75 225.11 4.05 116.44 51.72 0.00 0.00 0.00 4.05 116.44 51.72
02.01.04 REFINE Y NIVELACION EN ZANJAS M 471.20 1.85 871.72 466.10 862.29 98.92 0.00 0.00 0.00 466.10 862.29 98.92
02.02 CAMAS DE APOYO
02.02.01 PREPARACION DE CAMAS DE APOYO M 471.20 4.61 2,172.23 411.40 1896.55 87.31 0.00 0.00 0.00 411.40 1896.55 87.31
02.03 RELLENOS
02.03.01 EXTRACCION DE MAT. P/RELLENO M3 230.89 6.39 1,475.39 230.89 1475.39 100.00 0.00 0.00 0.00 230.89 1475.39 100.00
02.03.02 SELECCIÓN DE MATERIAL P/RELLENO M3 214.40 3.42 733.25 150.00 513.00 69.96 0.00 0.00 0.00 150.00 513.00 69.96
02.03.03 CARGUIO P/ RELLENO M3 214.40 4.16 891.90 150.00 624.00 69.96 0.00 0.00 0.00 150.00 624.00 69.96
02.03.04 TRANSPORTE P/ RELLENO M3 214.40 5.52 1,183.49 150.00 828.00 69.96 0.00 0.00 0.00 150.00 828.00 69.96
02.03.05 RELLENO Y COMPACTADO DE ZANJA M 471.20 14.97 7,053.86 434.40 6502.97 92.19 0.00 0.00 0.00 434.40 6502.97 92.19
02.04 ELIMINACION DE MATERIAL EXCEDENTE
02.04.01 ACARREO INTERNO DE MATERIAL M3 48.55 13.46 653.48 48.55 653.48 100.00 0.00 0.00 0.00 48.55 653.48 100.00
02.04.02 CARGUIO (ELIM. MAT. EXCEDENTE) M3 48.55 3.92 190.32 48.55 190.32 100.00 0.00 0.00 0.00 48.55 190.32 100.00
02.04.03 TRANSPORTE (ELIM. MAT. EXCEDENTE) M3 48.55 5.70 276.74 48.55 276.74 100.00 0.00 0.00 0.00 48.55 276.74 100.00
03.00 OBRAS DE CONCRETO ARMADO
03.01 CONSTRUCCION DE BUZONES
VALORIZACION DE AVANCE FISICO Nº 01 FEBRERO 2010 - II ETAPA
DEL 01/02/2010 AL06/02/2010
OBRA : "MEJORAMIENTO DE PISTAS Y VEREDAS DE AV. JOSE OLAYA TRAMO : AV. GIRALDEZ - PROLONG. PUNO RESIDENTE : ING. MIRIAM VILLAFUERTE PACHECO

CODIGO : 15-036-074-2063804-2164992-0086 SUPERVISOR : ING. JORGE CHUCOS DE LA CRUZ


: PAVIMENTACION FLEXIBLE
CLIENTE : MUNICIPALIDAD PROVINCIAL DE HUANCAYO

Departamento : JUNIN Provincia : HUANCAYO Distrito : HUANCAYO Fecha de Presentacion :06de Febrero del 2010
PRESUPUESTO REFERENCIAL AVANCES
ITEM DESCRIPCION Unidad Metrado Precio Parcial MES ANTERIOR SEMANA II ACUMULADO
METRADO VALORIZA. S/. % METRADO VALORIZ. S/. % METRADO VALORIZ. S/. %
03.01.01 CONSTRUCCION DE BUZON H =1..50m UND 4.00 1159.37 4,637.48 1.85 2144.83 46.25 0.00 0.00 0.00 1.85 2144.83 46.25
03.01.02 CONSTRUCCION DE BUZON H =1.70m UND 5.00 1,066.12 5,330.60 4.35 4637.62 87.00 0.10 106.61 2.00 4.45 4744.23 89.00
03.01.03 DADOS DE CONCRETO F'C= 140KG/CM² UND 18.00 63.27 1,138.86 11.00 695.97 61.11 0.00 0.00 0.00 11.00 695.97 61.11
03.02 ENCIMADO DE BUZONES
03.02.01 CONST. ENCIM.BUZON H= 0.45m. S.M.yTAPA UND 1.00 344.68 344.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.02.02 DADOS DE CONCRETO F'C= 140KG/CM² UND 5.00 63.27 316.35 3.00 189.81 60.00 0.00 0.00 0.00 3.00 189.81 60.00
03.03 SUMIDEROS
03.03.01 CONSTRUCCION DE SUMIDERO UND 6.00 423.36 2,540.16 3.00 1270.08 50.00 0.00 0.00 0.00 3.00 1270.08 50.00
03.03.02 CONSTRUCCION DE CAJA RECEPTOR UND 6.00 60.58 363.48 3.00 181.74 50.00 0.00 0.00 0.00 3.00 181.74 50.00
04.00 SUMINISTRO Y TENDIDO DE TUBERIA
04.01 TENDIDO DE TUBERIA UPVC U/F S-25 D=12" M 395.00 70.77 27,954.15 395.00 27954.15 100.00 0.00 0.00 0.00 395.00 27954.15 100.00
04.02 TENDIDO DE TUBERIA UPVC U/F S-25 D=10" M 22.20 54.39 1,207.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.03 TENDIDO DE TUBERIA UPVC U/F S-25 D=8" M 54.00 42.40 2,289.60 20.00 848.00 37.04 0.00 0.00 0.00 20.00 848.00 37.04
04.04 SUMINISTRO Y COLOCACION DE ACCESORIOS UND 6.00 15.35 92.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.00 PRUEBA HIDRAULICA
05.01 PRUEBA A ZANJA TAPADA P/TUBERIA M 471.20 1.17 551.30 412.00 482.04 87.44 0.00 0.00 0.00 412.00 482.04 87.44
06.00 CARPINTERIA METALICA
06.01 VENTANA DE SUMIDERO 0.70x0.80M UND 6.00 93.49 560.94 3.00 280.47 50.00 0.00 0.00 0.00 3.00 280.47 50.00
06.02 REJILLA DE CAJA UND 6.00 114.81 688.86 3.00 344.43 50.00 0.00 0.00 0.00 3.00 344.43 50.00
COSTO DIRECTO 01 PAVIMENTACION FLEXIBLE 194411.37 74624.20 38.38% 5186.95 2.67% 79811.16 41.05%
COSTO DIRECTO 02 DESAGUE PLUVIAL 71742.04 61877.06 86.25% 106.61 0.15% 61983.67 86.40%
SUB TOTAL 266153.41 136501.26 5293.57 141794.83
GASTOS GENERALES 7% 18630.74 9555.09 370.55 9925.64
UTILIDADES 5% 13307.67 6825.06 264.68 7089.74
SUB TOTAL 298091.82 152881.41 5928.79 158810.21
IMPUESTO IGV 19 % 56637.45 29047.47 1126.47 30173.94
TOTAL GENERAL 354729.27 181928.88 51.29% 7055.26 1.99% 188984.15 53.28%

AVANCE FISICO % VALORIZACION S/.


MES ANTER. 51.29% 181928.88
DE LA SEMANA 1.99% 7055.26
ACUMULADO 53.28% 188984.15
IAM VILLAFUERTE PACHECO

RGE CHUCOS DE LA CRUZ

6de Febrero del 2010


SALDO

METRADO VALORIZ. S/. %

0.00 0.00 0.00


0.25 475.53 100.00
0.00 0.00
0.00 0.00 0.00
277.99 236.29 14.60
0.00 0.00 0.00

216.20 1100.46 18.80


0.00 0.00 0.00
0.00 0.00 0.00
18.29 392.32 100.00
0.00 0.00 0.00
4.73 99.52 100.00

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

0.00 0.00 0.00


4.64 21.72 1.26
54.64 214.19 14.78
54.64 311.45 14.78
226.70 523.68 15.95

241.44 1789.07 51.21


287.76 1346.72 65.73
242.76 951.62 55.46
242.76 1383.73 55.46
IAM VILLAFUERTE PACHECO

RGE CHUCOS DE LA CRUZ

6de Febrero del 2010


SALDO

METRADO VALORIZ. S/. %


1346.70 3124.34 94.72

1097.20 5990.71 100.00


1097.20 57449.39 100.00

45.72 1691.18 100.00


61.23 17231.96 100.00

4.73 1352.21
3.94 145.74 100.00

3.43 1024.23 100.00


6.86 184.26

0.00 0.00 0.00


3.25 878.05 12.70
0.00 0.00
187.20 263.95 35.73
118.50 545.10 22.61
0.00 0.00 0.00
182.22 5331.76 34.77

1.35 42.70 58.44


8.00 239.04 74.07

179.09 351.02 100.00

57.14 1929.05 79.03


241.00 2458.20 100.00
20.00 335.80 100.00

228.62 907.62 100.00


95.70 373.23 100.00
191.00 618.84 100.00
12.00 152.28 100.00
IAM VILLAFUERTE PACHECO

RGE CHUCOS DE LA CRUZ

6de Febrero del 2010


SALDO

METRADO VALORIZ. S/. %


1.00 384.08 100.00
1.00 358.52 100.00

0.50 272.58 16.67


2.00 798.06 100.00

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

2000.00 1320.00 100.00

0.00 0.00 0.00

0.00 0.00 0.00


-60.60 -910.21 -12.86
3.78 108.68 48.28
5.10 9.43 1.08

59.80 275.68 12.69

0.00 0.00 0.00


64.40 220.25 30.04
64.40 267.90 30.04
64.40 355.49 30.04
36.80 550.90 7.81

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00
IAM VILLAFUERTE PACHECO

RGE CHUCOS DE LA CRUZ

6de Febrero del 2010


SALDO

METRADO VALORIZ. S/. %


2.15 2492.65 53.75
0.55 586.37 11.00
7.00 442.89 38.89

1.00 344.68 100.00


2.00 126.54 40.00
0.00 0.00
3.00 1270.08 50.00
3.00 181.74 50.00

0.00 0.00 0.00


22.20 1207.46 100.00
34.00 1441.60 62.96
6.00 92.10 100.00

59.20 69.26 12.56

3.00 280.47 50.00


3.00 344.43 50.00
114600.19 58.95%
9758.38 13.60%
124358.57
8705.10
6217.93
139281.60
26463.50
165745.10 46.72%
VALORIZACION DE AVANCE FISICO Nº 01 FEBRERO 2010 - II ETAPA
DEL 02/01/2010 AL 30/01/2010
OBRA : "MEJORAMIENTO DE PISTAS Y VEREDAS DE AV. JOSE OLAYA TRAMO : AV. GIRALDEZ - PROLONG. PUNO RESIDENTE : ING. MIRIAM VILLAFUERTE PACHECO

CODIGO : 15-036-074-2063804-2164992-0086 SUPERVISOR : ING. JORGE CHUCOS DE LA CRUZ


: PAVIMENTACION FLEXIBLE
CLIENTE : MUNICIPALIDAD PROVINCIAL DE HUANCAYO

Departamento : JUNIN Provincia : HUANCAYO Distrito : HUANCAYO Fecha de Presentacion :06de Febrero del 2010
PRESUPUESTO REFERENCIAL AVANCES
ITEM DESCRIPCION Unidad Metrado Precio Parcial MES ANTERIOR SEMANA I ACUMULADO
METRADO VALORIZA. S/. % METRADO VALORIZ. S/. % METRADO VALORIZ. S/. %
01.00 OBRAS PROVISIONALES
01.01 ALMACEN Y CASETA DE GUARDIANIA MES 0.25 437.84 109.46 0.25 109.46 100.00 0.00 0.00 0.00 0.25 109.46 100.00
01.02 CARTEL DE IDENTIFICACION DE OBRA UND 0.25 1,902.11 475.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.00 OBRAS PRELIMINARES
02.01 TRAZO Y REPLANTEO M2 1,904.10 0.87 1,656.57 1904.10 1656.57 100.00 0.00 0.00 0.00 1904.10 1656.57 100.00
02.02 TRAZO Y REPLANTEO DURANTE LA EJECUCION M2 1,904.08 0.85 1,618.47 856.09 727.68 44.96 600.00 510.00 31.51 1456.09 1237.68 76.47
02.03 ROTURA DE VEREDAS M3 0.48 42.58 20.44 0.48 20.44 100.00 0.00 0.00 0.00 0.48 20.44 100.00
03.00 EXPLANACIONES
03.01 MOVIMIENTO DE TIERRAS
03.01.01 CORTE DE TERRENO DE SUB RASANTE M3 1,149.87 5.09 5,852.84 916.22 4663.56 79.68 17.45 88.82 1.52 933.67 4752.38 81.20
03.01.02 CORTE PARA MEJORAM. DE SUB BASE M3 46.08 5.08 234.09 46.08 234.09 100.00 0.00 0.00 0.00 46.08 234.09 100.00
03.01.03 CORTE DE TERRENO MANUAL M3 59.80 21.45 1,282.71 59.80 1282.71 100.00 0.00 0.00 0.00 59.80 1282.71 100.00
03.01.04 EXCAVACION MANUAL PARA CUNETA M3 18.29 21.45 392.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.01.05 EXCAVACION MANUAL PARA SARDINEL M3 28.17 21.45 604.25 12.53 268.77 44.48 5.44 116.69 19.31 17.97 385.46 63.79
03.01.06 EXCAVACION MANUAL EN BADEN M3 4.73 21.04 99.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.02 ELIMINACION DE MATERIAL EXCEDENTE
03.02.01 ACARREO INTERNO DE MATERIAL M3 133.80 17.94 2,400.37 133.80 2400.37 100.00 0.00 0.00 0.00 133.80 2400.37 100.00
03.02.02 CARGUIO (ELIM.DE MATERIAL EXCEDENTE) M3 1,568.94 3.63 5,695.25 1460.00 5299.80 93.06 75.00 272.25 4.78 1535.00 5572.05 97.84
03.02.03 TRANSPORTE (ELIM. MAT. EXCEDENTE) M3 1,568.94 5.70 8,942.96 1460.00 8322.00 93.06 75.00 427.50 4.78 1535.00 8749.50 97.84
03.02.04 ESCARIFICADO PERFILADO/COMPACTADO M2 1,421.70 2.28 3,241.48 1421.70 3241.48 100.00 0.00 0.00 0.00 1421.70 3241.48 100.00
04.00 PAVIMENTOS
04.01 MEJORAMIENTO DE SUB RASANTE
04.01.01 EXTRACCION DE MATERIAL P/MEJ. SUB RASANTE M3 305.70 7.42 2,268.27 305.70 2268.29 100.00 0.00 0.00 0.00 305.70 2268.29 100.00
04.01.02 SELECCION DE MATERIAL P/ MEJ DE SUB RASANTE M3 251.00 4.68 1,174.68 251.00 1174.68 100.00 0.00 0.00 0.00 251.00 1174.68 100.00
04.01.03 CARGUIO DE (MEJ. S-R) M3 251.00 3.83 961.33 251.00 961.33 100.00 0.00 0.00 0.00 251.00 961.33 100.00
04.01.04 TRANSPORTE (MEJ. S-R) M3 251.00 5.70 1,430.70 251.00 1430.70 100.00 0.00 0.00 0.00 251.00 1430.70 100.00
04.01.05 EXT. RIEGO Y COMPC. P/MEJ DE SUB RASANTE M2 1,165.00 2.18 2,539.70 60.80 132.54 5.22 1104.20 2407.16 94.78 1165.00 2539.70 100.00
04.02 SUB BASE GRANULAR
04.02.01 EXTRACCION DE MATERIAL PARA SUB BASE M3 398.08 7.41 2,949.77 398.08 2949.77 100.00 0.00 0.00 0.00 398.08 2949.77 100.00
04.02.02 SELECCION DE MATERIAL P/ SUB BASE GRANULAR M3 369.64 4.68 1,729.92 365.00 1708.20 98.74 0.00 0.00 0.00 365.00 1708.20 98.74
04.02.03 CARGUIO DE S-B M3 369.64 3.92 1,448.99 270.00 1058.40 73.04 45.00 176.40 12.17 315.00 1234.80 85.22
04.02.04 TRANSPORTE DE S.B. M3 369.64 5.70 2,106.95 270.00 1539.00 73.04 45.00 256.50 12.17 315.00 1795.50 85.22
04.02.05 EXT. RIEGO Y COMPC. DE SUB BASE E= 0.20m. M2 1,421.70 2.31 3,284.13 30.00 69.30 2.11 1165.00 2691.15 81.94 1195.00 2760.45 84.05
04.03 BASE GRANULAR
04.03.01 EXTRACCION DE MATERIAL PARA BASE M3 471.44 7.41 3,493.37 0.00 0.00 0.00 230.00 1704.30 48.79 230.00 1704.30 48.79
04.03.02 SELECCION DE MATERIAL P/ BASE GRANULAR M3 437.76 4.68 2,048.72 0.00 0.00 0.00 150.00 702.00 34.27 150.00 702.00 34.27
04.03.03 CARGUIO DE B. M3 437.76 3.92 1,716.02 0.00 0.00 0.00 150.00 588.00 34.27 150.00 588.00 34.27
04.03.04 TRANSPORTE DE B. M3 437.76 5.70 2,495.23 0.00 0.00 0.00 150.00 855.00 34.27 150.00 855.00 34.27
VALORIZACION DE AVANCE FISICO Nº 01 FEBRERO 2010 - II ETAPA
DEL 02/01/2010 AL 30/01/2010
OBRA : "MEJORAMIENTO DE PISTAS Y VEREDAS DE AV. JOSE OLAYA TRAMO : AV. GIRALDEZ - PROLONG. PUNO RESIDENTE : ING. MIRIAM VILLAFUERTE PACHECO

CODIGO : 15-036-074-2063804-2164992-0086 SUPERVISOR : ING. JORGE CHUCOS DE LA CRUZ


: PAVIMENTACION FLEXIBLE
CLIENTE : MUNICIPALIDAD PROVINCIAL DE HUANCAYO

Departamento : JUNIN Provincia : HUANCAYO Distrito : HUANCAYO Fecha de Presentacion :06de Febrero del 2010
PRESUPUESTO REFERENCIAL AVANCES
ITEM DESCRIPCION Unidad Metrado Precio Parcial MES ANTERIOR SEMANA I ACUMULADO
METRADO VALORIZA. S/. % METRADO VALORIZ. S/. % METRADO VALORIZ. S/. %
04.03.05 EXT. RIEGO Y COMPC. DE BASE E= 0.20m. M2 1,421.70 2.32 3,298.34 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.04 CARPETA ASFALTICA
04.04.01 IMPRIMACION ASFALTICA M2 1,097.20 5.46 5,990.71 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.04.02 CARPETA ASFALTICA EN CALIENTE E= 3" M2 1,097.20 52.36 57,449.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.00 DRENAJE
05.01 ENCOFRADO Y DESENCOFRADO DE CUNETAS M2 45.72 36.99 1,691.18 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.02 CUNETAS CONCRETO F'C=175 KG/CM2 M3 61.23 281.43 17,231.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.00 BADEN
06.01 BADEN CONCRETO F'C=210 KG/CM2 M3 4.73 285.88 1,352.21 0.00 0.00 0.00 0.00 0.00
06.02 BADEN ENCOFRADO Y DESENCOFRADO M2 3.94 36.99 145.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.00 SARDINEL INEXPUESTO
07.01 SARDINEL INEXP. CONCRETO F'C=210 KG/CM2 M3 3.43 298.61 1,024.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.02 SARDINEL INEXP. ENCOFRADO Y DESENCOFRADO M2 6.86 26.86 184.26 0.00 0.00 0.00 0.00 0.00
08.00 ACERA PEATONAL
08.01 SARDINEL EXPUESTO
08.01.01 SARDINEL EXP. ENCOFRADO Y DESENCOFRADO M2 170.63 30.13 5,141.08 78.68 2370.63 46.11 48.17 1451.36 28.23 126.85 3821.99 74.34
08.01.02 SARDINEL EXP. CONCRETO F'C=175 KG/CM2 M3 25.59 270.17 6,913.65 13.97 3774.27 54.59 1.72 464.69 6.72 15.69 4238.97 61.31
VEREDAS
08.02.01 REFINE Y NIVELACION M2 524.00 1.41 738.84 336.80 474.89 64.27 0.00 0.00 0.00 336.80 474.89 64.27
08.02.02 RELLENO Y COMPACTADO DE VEREDA M2 524.00 4.60 2,410.40 405.50 1865.30 77.39 0.00 0.00 0.00 405.50 1865.30 77.39
08.02.03 VEREDA ENCOFRADO Y DESENCOFRADO M2 12.57 29.31 368.43 12.57 368.43 100.00 0.00 0.00 0.00 12.57 368.43 100.00
08.02.04 VEREDAS CONCRETO F'C=175 KG/CM2 M2 524.00 29.26 15,332.24 275.39 8057.91 52.56 66.39 1942.57 12.67 341.78 10000.48 65.23
9.00 RAMPAS
9.01 ENCOFRADO Y DESENCOFRADO RAMPA M2 2.31 31.63 73.07 0.48 15.18 20.78 0.48 15.18 20.78 0.96 30.36 41.56
9.02 RAMPA CONCRETO F'C=175 KG/CM2 M2 10.80 29.88 322.70 1.40 41.83 12.96 1.40 41.83 12.96 2.80 83.66 25.93
10.00 JUNTAS
10.01 RELLENO DE JUNTAS M 179.09 1.96 351.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.00 AREAS VERDES
11.01 SUMINISTRO DE TIERRA AGRICOLA M3 72.30 33.76 2,440.85 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02 COLOCACION DE GRASS M2 241.00 10.20 2,458.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03 COLOCACION DE PLANTONES UND 20.00 16.79 335.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12.00 SEÑALIZACION
12.01 SEÑALIZACION HORIZONTAL
12.01.01 PINTURA LINEAL EN BORDE DE VIA M 228.62 3.97 907.62 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12.01.02 PINTURA LINEAL CONTINUA EN EJE DE VIA M 95.70 3.90 373.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12.01.03 PINTURA LINEAL DISCONTINUA EN EJE DE VIA M 191.00 3.24 618.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12.01.04 PINTURA DE SIMBOLOS Y FLECHAS M2 12.00 12.69 152.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12.02 SEÑALIZACION VERTICAL
VALORIZACION DE AVANCE FISICO Nº 01 FEBRERO 2010 - II ETAPA
DEL 02/01/2010 AL 30/01/2010
OBRA : "MEJORAMIENTO DE PISTAS Y VEREDAS DE AV. JOSE OLAYA TRAMO : AV. GIRALDEZ - PROLONG. PUNO RESIDENTE : ING. MIRIAM VILLAFUERTE PACHECO

CODIGO : 15-036-074-2063804-2164992-0086 SUPERVISOR : ING. JORGE CHUCOS DE LA CRUZ


: PAVIMENTACION FLEXIBLE
CLIENTE : MUNICIPALIDAD PROVINCIAL DE HUANCAYO

Departamento : JUNIN Provincia : HUANCAYO Distrito : HUANCAYO Fecha de Presentacion :06de Febrero del 2010
PRESUPUESTO REFERENCIAL AVANCES
ITEM DESCRIPCION Unidad Metrado Precio Parcial MES ANTERIOR SEMANA I ACUMULADO
METRADO VALORIZA. S/. % METRADO VALORIZ. S/. % METRADO VALORIZ. S/. %
12.02.01 SEÑALES TIPO R (90cM x 60cm) UND 1.00 384.08 384.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12.02.02 SEÑALES TIPO F UND 1.00 358.52 358.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.00 EQUIPAMIENTO
13.01 MOVILIARIO URBANO UND 3.00 545.16 1,635.48 2.00 1090.32 66.67 0.00 0.00 0.00 2.00 1090.32 66.67
13.02 SUMINISTRO Y COLOCACION DE TACHOS DE BASURA UND 2.00 399.03 798.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
14.00 RECONEXIONES
14.01 RECONEXIONES DE PUNTOS DE AGUA PTO 6.00 13.99 83.94 6.00 83.94 100.00 0.00 0.00 0.00 6.00 83.94 100.00
14.02 RECONEXION DE CAJA MEDIDOR DE AGUA PTO 6.00 12.96 77.76 6.00 77.76 100.00 0.00 0.00 0.00 6.00 77.76 100.00
14.03 RECONEXION DE INSTALACIONES DE DESAGUE PTO 6.00 17.56 105.36 6.00 105.36 100.00 0.00 0.00 0.00 6.00 105.36 100.00
14.04 RECONEXION DE CAJA DE REGISTRO DE DESAGUE PTO 6.00 11.31 67.86 6.00 67.86 100.00 0.00 0.00 0.00 6.00 67.86 100.00
15.00 VARIOS
15.01 LIMPIEZA FINAL DE OBRA M2 2,000.00 0.66 1,320.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

DESAGUE PLUVIAL

01.00 TRABAJOS PRELIMINARES


01.01 TRAZO NIVELES Y REPLANTEO DE ZANJA M 395.00 0.56 221.20 395.00 221.20 100.00 0.00 0.00 0.00 395.00 221.20 100.00
02.00 MOVIMIENTO DE TIERRAS

02.01 EXCAVACIONES
02.01.01 EXCAVACION PARA BUZONES M3 32.63 21.45 699.91 32.63 699.91 100.00 0.00 0.00 0.00 32.63 699.91 100.00
02.01.02 EXCAVACION DE ZANJAS - MANUAL M 471.20 15.02 7,077.42 471.20 7077.42 100.00 3.00 45.06 0.64 474.20 7122.48 100.64
02.01.03 EXCAVACION PARA SUMIDEROS M3 7.83 28.75 225.11 2.70 77.63 34.48 1.35 38.81 17.24 4.05 116.44 51.72
02.01.04 REFINE Y NIVELACION EN ZANJAS M 471.20 1.85 871.72 463.10 856.74 98.28 3.00 5.55 0.64 466.10 862.29 98.92
02.02 CAMAS DE APOYO
02.02.01 PREPARACION DE CAMAS DE APOYO M 471.20 4.61 2,172.23 471.20 2172.23 100.00 3.00 13.83 0.64 474.20 2186.06 100.64
02.03 RELLENOS
02.03.01 EXTRACCION DE MAT. P/RELLENO M3 230.89 6.39 1,475.39 230.89 1475.39 100.00 0.00 0.00 0.00 230.89 1475.39 100.00
02.03.02 SELECCIÓN DE MATERIAL P/RELLENO M3 214.40 3.42 733.25 150.00 513.00 69.96 0.00 0.00 0.00 150.00 513.00 69.96
02.03.03 CARGUIO P/ RELLENO M3 214.40 4.16 891.90 150.00 624.00 69.96 0.00 0.00 0.00 150.00 624.00 69.96
02.03.04 TRANSPORTE P/ RELLENO M3 214.40 5.52 1,183.49 150.00 828.00 69.96 0.00 0.00 0.00 150.00 828.00 69.96
02.03.05 RELLENO Y COMPACTADO DE ZANJA M 471.20 14.97 7,053.86 431.40 6458.06 91.55 3.00 44.91 0.64 434.40 6502.97 92.19
02.04 ELIMINACION DE MATERIAL EXCEDENTE
02.04.01 ACARREO INTERNO DE MATERIAL M3 48.55 13.46 653.48 48.55 653.48 100.00 0.00 0.00 0.00 48.55 653.48 100.00
02.04.02 CARGUIO (ELIM. MAT. EXCEDENTE) M3 48.55 3.92 190.32 48.55 190.32 100.00 0.00 0.00 0.00 48.55 190.32 100.00
02.04.03 TRANSPORTE (ELIM. MAT. EXCEDENTE) M3 48.55 5.70 276.74 48.55 276.74 100.00 0.00 0.00 0.00 48.55 276.74 100.00
03.00 OBRAS DE CONCRETO ARMADO
03.01 CONSTRUCCION DE BUZONES
VALORIZACION DE AVANCE FISICO Nº 01 FEBRERO 2010 - II ETAPA
DEL 02/01/2010 AL 30/01/2010
OBRA : "MEJORAMIENTO DE PISTAS Y VEREDAS DE AV. JOSE OLAYA TRAMO : AV. GIRALDEZ - PROLONG. PUNO RESIDENTE : ING. MIRIAM VILLAFUERTE PACHECO

CODIGO : 15-036-074-2063804-2164992-0086 SUPERVISOR : ING. JORGE CHUCOS DE LA CRUZ


: PAVIMENTACION FLEXIBLE
CLIENTE : MUNICIPALIDAD PROVINCIAL DE HUANCAYO

Departamento : JUNIN Provincia : HUANCAYO Distrito : HUANCAYO Fecha de Presentacion :06de Febrero del 2010
PRESUPUESTO REFERENCIAL AVANCES
ITEM DESCRIPCION Unidad Metrado Precio Parcial MES ANTERIOR SEMANA I ACUMULADO
METRADO VALORIZA. S/. % METRADO VALORIZ. S/. % METRADO VALORIZ. S/. %
03.01.01 CONSTRUCCION DE BUZON H =1..50m UND 4.00 1159.37 4,637.48 1.50 1739.06 37.50 0.35 405.78 8.75 1.85 2144.83 46.25
03.01.02 CONSTRUCCION DE BUZON H =1.70m UND 5.00 1,066.12 5,330.60 4.35 4637.62 87.00 0.00 0.00 0.00 4.35 4637.62 87.00
03.01.03 DADOS DE CONCRETO F'C= 140KG/CM² UND 18.00 63.27 1,138.86 11.00 695.97 61.11 0.00 0.00 0.00 11.00 695.97 61.11
03.02 ENCIMADO DE BUZONES
03.02.01 CONST. ENCIM.BUZON H= 0.45m. S.M.yTAPA UND 1.00 344.68 344.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.02.02 DADOS DE CONCRETO F'C= 140KG/CM² UND 5.00 63.27 316.35 2.00 126.54 40.00 1.00 63.27 20.00 3.00 189.81 60.00
03.03 SUMIDEROS
03.03.01 CONSTRUCCION DE SUMIDERO UND 6.00 423.36 2,540.16 2.00 846.72 33.33 1.00 423.36 16.67 3.00 1270.08 50.00
03.03.02 CONSTRUCCION DE CAJA RECEPTOR UND 6.00 60.58 363.48 2.00 121.16 33.33 1.00 60.58 16.67 3.00 181.74 50.00
04.00 SUMINISTRO Y TENDIDO DE TUBERIA
04.01 TENDIDO DE TUBERIA UPVC U/F S-25 D=12" M 395.00 70.77 27,954.15 395.00 27954.15 100.00 0.00 0.00 0.00 395.00 27954.15 100.00
04.02 TENDIDO DE TUBERIA UPVC U/F S-25 D=10" M 22.20 54.39 1,207.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.03 TENDIDO DE TUBERIA UPVC U/F S-25 D=8" M 54.00 42.40 2,289.60 17.00 720.80 31.48 3.00 127.20 5.56 20.00 848.00 37.04
04.04 SUMINISTRO Y COLOCACION DE ACCESORIOS UND 6.00 15.35 92.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.00 PRUEBA HIDRAULICA
05.01 PRUEBA A ZANJA TAPADA P/TUBERIA M 471.20 1.17 551.30 412.00 482.04 87.44 0.00 0.00 0.00 412.00 482.04 87.44
06.00 CARPINTERIA METALICA
06.01 VENTANA DE SUMIDERO 0.70x0.80M UND 6.00 93.49 560.94 2.00 186.98 33.33 1.00 93.49 16.67 3.00 280.47 50.00
06.02 REJILLA DE CAJA UND 6.00 114.81 688.86 2.00 229.62 33.33 1.00 114.81 16.67 3.00 344.43 50.00
COSTO DIRECTO 01 PAVIMENTACION FLEXIBLE 194411.37 59912.82 30.82% 14711.40 7.57% 74624.22 38.38%
COSTO DIRECTO 02 DESAGUE PLUVIAL 71742.04 59864.77 83.44% 1436.65 2.00% 61301.42 85.45%
SUB TOTAL 266153.41 119777.58 16148.06 135925.64
GASTOS GENERALES 7% 18630.74 8384.43 1130.36 9514.79
UTILIDADES 5% 13307.67 5988.88 807.40 6796.28
SUB TOTAL 298091.82 134150.89 18085.82 152236.72
IMPUESTO IGV 19 % 56637.45 25488.67 3436.31 28924.98
TOTAL GENERAL 354729.27 159639.57 45.00% 21522.13 6.07% 181161.70 51.07%

AVANCE FISICO % VALORIZACION S/.


MES ANTER. 45.00% 159639.57
DE LA SEMANA 6.07% 21522.13
ACUMULADO 51.07% 181161.70
IAM VILLAFUERTE PACHECO

RGE CHUCOS DE LA CRUZ

6de Febrero del 2010


SALDO

METRADO VALORIZ. S/. %

0.00 0.00 0.00


0.25 475.53 100.00
0.00 0.00
0.00 0.00 0.00
447.99 380.79 23.53
0.00 0.00 0.00

216.20 1100.46 18.80


0.00 0.00 0.00
0.00 0.00 0.00
18.29 392.32 100.00
10.20 218.79 36.21
4.73 99.52 100.00

0.00 0.00 0.00


33.94 123.20 2.16
33.94 193.46 2.16
0.00 0.00 0.00

0.00 -0.02 0.00


0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

0.00 0.00 0.00


4.64 21.72 1.26
54.64 214.19 14.78
54.64 311.45 14.78
226.70 523.68 15.95

241.44 1789.07 51.21


287.76 1346.72 65.73
287.76 1128.02 65.73
287.76 1640.23 65.73
IAM VILLAFUERTE PACHECO

RGE CHUCOS DE LA CRUZ

6de Febrero del 2010


SALDO

METRADO VALORIZ. S/. %


1421.70 3298.34 100.00

1097.20 5990.71 100.00


1097.20 57449.39 100.00

45.72 1691.18 100.00


61.23 17231.96 100.00

4.73 1352.21
3.94 145.74 100.00

3.43 1024.23 100.00


6.86 184.26

43.78 1319.09 25.66


9.90 2674.68 38.69
0.00 0.00
187.20 263.95 35.73
118.50 545.10 22.61
0.00 0.00 0.00
182.22 5331.76 34.77

1.35 42.70 58.44


8.00 239.04 74.07

179.09 351.02 100.00

72.30 2440.85 100.00


241.00 2458.20 100.00
20.00 335.80 100.00

228.62 907.62 100.00


95.70 373.23 100.00
191.00 618.84 100.00
12.00 152.28 100.00
IAM VILLAFUERTE PACHECO

RGE CHUCOS DE LA CRUZ

6de Febrero del 2010


SALDO

METRADO VALORIZ. S/. %


1.00 384.08 100.00
1.00 358.52 100.00

1.00 545.16 33.33


2.00 798.06 100.00

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

2000.00 1320.00 100.00

0.00 0.00 0.00

0.00 0.00 0.00


-3.00 -45.06 -0.64
3.78 108.68 48.28
5.10 9.43 1.08

-3.00 -13.83 -0.64

0.00 0.00 0.00


64.40 220.25 30.04
64.40 267.90 30.04
64.40 355.49 30.04
36.80 550.90 7.81

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00
IAM VILLAFUERTE PACHECO

RGE CHUCOS DE LA CRUZ

6de Febrero del 2010


SALDO

METRADO VALORIZ. S/. %


2.15 2492.65 53.75
0.65 692.98 13.00
7.00 442.89 38.89

1.00 344.68 100.00


2.00 126.54 40.00
0.00 0.00
3.00 1270.08 50.00
3.00 181.74 50.00

0.00 0.00 0.00


22.20 1207.46 100.00
34.00 1441.60 62.96
6.00 92.10 100.00

59.20 69.26 12.56

3.00 280.47 50.00


3.00 344.43 50.00
119787.12 61.62%
10440.63 14.55%
130227.76
9115.94
6511.39
145855.09
27712.47
173567.55 48.93%
AVANCE FISICO DIARIO DE OBRA MAYO - 2009
OBRA: MEJORAMIENTO PISTA Y VEREDAS AV. JOSE OLAYA I ETAPA TRAMO: (PROLG. PUNO - AV. CENTENARIO)

PAVIMENTO
ALMACEN Y
CASETA DE
PARTIDA MOVILIZACION Y CARTEL DE
TRAZO Y
CORTE DE TERRENO CORTE DE TERRENO CORTE DE
TRAZO Y REPLANTEO ROTURA DE
GUARD.
DESMOVILIZAC. DE IDENTIFIC. DE C/MAQUINARIA HASTA C/MAQUINARIA TERRENO
REPLANTEO DURANTE LA VEREDAS
EQUIPO OBRA S-R MEJORAMIENTO MANUAL
EJECUCION

FECHA 01.01 01.02 01.03 02.01 02.02 02.03 03.01.01 03.01.02 03.01.03
5/11/2009 3600.00 8.22 7.20
5/12/2009
5/13/2009 3200.00 18.90
5/14/2009 5.40
5/15/2009 18.90
5/16/2009 492.00
5/17/2009
5/18/2009 624.00 5.40
5/19/2009 6.29
5/20/2009
5/21/2009 7.20
5/22/2009 821.00
5/23/2009 377.00
5/24/2009
5/25/2009 5.40
5/26/2009
5/27/2009
5/28/2009 3.60
5/29/2009
5/30/2009 1.80
5/31/2009 0.70

EJECUTADO DEL MES 0.70 0.00 0.00 6800.00 0.00 8.22 2314.00 0.00 80.09
EJEC. ANTERIOR #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
EJEC. ACUMULADO #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
PROGRAMADO 2.50 1.00 1.00 8436.68 8436.68 8.22 3308.71 628.48 196.86
SALDO 1.80 1.00 1.00 1636.68 8436.68 0.00 994.71 628.48 116.77
AVANCE FISICO DIARIO DE OBRA MAYO - 2009
OBRA: MEJORAMIENTO PISTA Y VEREDAS AV. JOSE OLAYA I ETAPA TRAMO: (PROLG. PUNO - AV. CENTENARIO)

PAVIMENTO

CARGUIO SELECCION DE
EXCAVACION EXCAVACION ACARREO ESCARIFICADO EXTRACCION DE
EXCAVACION (ELIMINACION DE TRANSPORTE (ELIM. MATERIAL P/ MEJ CARGUIO DE TRANSPORTE (MEJ.
MANUAL PARA MANUAL PARA INTERNO DE PERFILADO/COMPACT MATERIAL P/MEJ. SUB
MANUAL EN BADEN MATERIAL MAT. EXCEDENTE) DE SUB (MEJ. S-R) S-R)
CUNETA SARDINEL MATERIAL ADO RASANTE
EXCEDENTE) RASANTE

03.01.04 03.01.05 03.01.06 03.02.01 03.02.02 03.02.03 03.02.04 04.01.01 04.01.02 04.01.03 04.01.04

288.00 288.00

480.00 480.00

465.00 465.00

650.00 650.00

165.00 165.00

40.00 40.00

0.00 0.00 0.00 106.79 2088.00 2088.00 0.00 0.00 0.00 0.00 0.00
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
61.23 98.85 15.91 458.10 5182.73 5182.73 6014.35 1355.14 1258.35 1258.35 1258.35
61.23 98.85 15.91 351.31 3094.73 3094.73 6014.35 1355.14 1258.35 1258.35 1258.35
FORMULA DE CARGUÍO

2884 (DEBE SER IGUAL A CELDA O39)

DIFERENCIA DE 796 M3
AVANCE FISICO DIARIO DE OBRA MAYO - 2009
OBRA: MEJORAMIENTO PISTA Y VEREDAS AV. JOSE OLAYA I ETAPA TRAMO: (PROLG. PUNO - AV. CENTENARIO)

PAVIMENTO

EXT. RIEGO Y COMPC. EXTRACCION DE SELECCION DE EXT. RIEGO Y EXTRACCION DE SELECCION DE


TRANSPORTE DE
P/MEJ DE SUB MATERIAL PARA MATERIAL P/ SUB BASE CARGUIO DE S-B COMPC. DE SUB MATERIAL PARA MATERIAL P/ BASE CARGUIO DE B. TRANSPORTE DE B.
S.B.
RASANTE SUB BASE GRANULAR BASE E= 0.20m. BASE GRANULAR

04.01.05 04.02.01 04.02.02 04.02.03 04.02.04 04.02.05 04.03.01 04.03.02 04.03.03 04.03.04

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
2688.00 1684.02 1563.73 1563.73 1563.73 6014.35 1897.28 1761.76 1761.76 1761.76
2688.00 1684.02 1563.73 1563.73 1563.73 6014.35 1897.28 1761.76 1761.76 1761.76
AVANCE FISICO DE OBRA DIARIO - MAYO 20
OLG. PUNO - AV. CENTENARIO) OBRA: MEJORAMIENTO PISTA Y VEREDAS AV. JOSE OLAYA I ETAPA TRAM

ENCOFRADO Y ENCOFRADO Y BADEN SARDINEL INEXP. SARDINEL INEXP.


EXT. RIEGO Y COMPC. IMPRIMACION CARPETA ASFALTICA EN CUNETAS CONCRETO
DESENCOFRADO DE DESENCOFRADO DE CONCRETO ENCOFRADO Y CONCRETO
DE BASE E= 0.20m. ASFALTICA CALIENTE E= 3" F'C=175 KG/CM2
CUNETAS BADEN F'C=210 KG/CM2 DESENCOFRADO F'C=210 KG/CM2

04.03.05 04.04.01 04.04.02 05.01 05.02 06.01 06.02 07.01 07.02

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00


#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
6014.35 5702.62 5702.62 153.07 61.23 15.91 13.26 16.06 26.76
6014.35 5702.62 5702.62 153.07 61.23 15.91 13.26 16.06 26.76
DE OBRA DIARIO - MAYO 2009
EDAS AV. JOSE OLAYA I ETAPA TRAMO: (PROLG. PUNO - AV. CENTENARIO) OBRA: MEJORAMIENTO PISTA Y VER

PAVIMENTO

SARDINEL EXP. SARDINEL EXP. RELLENO Y VEREDAS RAMPA SUMINISTRO DE


REFINE Y VEREDA ENCOFRADO Y ENCOFRADO Y RELLENO DE
ENCOFRADO Y CONCRETO F'C=175 COMPACTADO DE CONCRETO CONCRETO TIERRA
NIVELACION DESENCOFRADO DESENCOFRADO RAMPA JUNTAS
DESENCOFRADO KG/CM2 VEREDA F'C=175 KG/CM2 F'C=175 KG/CM2 AGRICOLA

09.01.01 09.01.02 09.02.01 09.02.02 09.02.03 09.02.04 10.01 10.02 12.01 13.01

126.00 126.00

54.00 54.00

0.00 0.00 180.00 180.00 0.00 0.00 0.00 0.00 0.00 0.00
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
668.62 100.29 1523.30 1523.30 1523.30 42.10 5.01 23.40 599.54 274.00
668.62 100.29 1343.30 1343.30 1523.30 42.10 5.01 23.40 599.54 274.00
AVANCE FISICO DE OBRA DIARIO - MAYO 2009
A: MEJORAMIENTO PISTA Y VEREDAS AV. JOSE OLAYA I ETAPA TRAMO: (PROLG. PUNO - AV. CENTENARIO)

PAVIMENTO

PINTURA LINEAL PINTURA LINEAL


COLOCACION DE COLOCACION DE PINTURA LINEAL EN PINTURA DE PINTURA ZONAL CRUCE SEÑALES TIPO R
CONTINUA EN EJE DISCONTINUA EN EJE SEÑALES TIPO P SEÑALES TIPO F
GRASS PLANTONES BORDE DE VIA SIMBOLOS Y FLECHAS PEATONAL (90cM x 60cm)
DE VIA DE VIA

13.02 13.03 14.01.01 14.01.02 14.01.03 14.01.04 14.01.05 14.02.01 14.02.02 14.02.03

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
915.61 150.00 502.59 250.99 502.59 16.00 200.00 2.00 1.00 4.00
915.61 150.00 502.59 250.99 502.59 16.00 200.00 2.00 1.00 4.00
AVANCE FISICO DE OBRA DIARIO - MAYO 2009
OBRA: MEJORAMIENTO PISTA Y VEREDAS AV. JOSE OLAYA I ETAPA TRAMO: (PROLG. PUNO - AV. CENTENARIO)

DESAGUE PLUVIAL

SUMINISTRO Y RECONEXION DE RECONEXION DE CAJA TRAZO NIVELES Y


MOVILIARIO RECONEXIONES DE RECONEXION DE CAJA LIMPIEZA FINAL EXCAVACION PARA EXCAVACION DE
COLOCACION DE INSTALACIONES DE DE REGISTRO DE REPLANTEO DE
URBANO PUNTOS DE AGUA MEDIDOR DE AGUA DE OBRA BUZONES ZANJAS - MANUAL
TACHOS DE BASURA DESAGUE DESAGUE ZANJA

16.01 16.02 17.01 17.02 17.03 17.04 18.01 01.01 02.01.01 02.01.02

54.00 20
20
14

3.00 2.00 2.00


4.00
2.00

14.00 1.99 14.00


1.99

1.99
1.99

0.00 0.00 9.00 0.00 2.00 2.00 0.00 68.00 7.96 68.00
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
4.00 4.00 41.00 41.00 41.00 41.00 7200.00 360.00 27.88 575.94
4.00 4.00 32.00 41.00 39.00 39.00 7200.00 292.00 19.92 507.94
AVANCE FISICO DE OBRA DIARIO - MAYO 2009
OBRA: MEJORAMIENTO PISTA Y VEREDAS AV. JOSE OLAYA I ETAPA TRAMO: (PROLG. PUNO - AV. CENTENARIO)

AGUE PLUVIAL DESAGUE PLUVIAL

REFINE Y SELECCIÓN DE RELLENO Y ACARREO


EXCAVACION PARA PREPARACION DE EXTRACCION DE CARGUIO P/ TRANSPORTE P/ CARGUIO (ELIM. TRANSPORTE (ELIM.
NIVELACION EN MATERIAL COMPACTADO DE INTERNO DE
SUMIDEROS CAMAS DE APOYO MAT. P/RELLENO RELLENO RELLENO MAT. EXCEDENTE) MAT. EXCEDENTE)
ZANJAS P/RELLENO ZANJA MATERIAL

02.01.03 02.01.04 02.02.01 02.03.01 02.03.02 02.03.03 02.03.04 02.03.05 02.04.01 02.04.02 02.04.03

54.00 54.00
14.00 14.00

0.00 68.00 68.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
16.97 575.94 575.94 282.21 262.05 262.05 262.05 575.94 53.81 53.81 53.81
16.97 507.94 507.94 282.21 262.05 262.05 262.05 575.94 53.81 53.81 53.81
AVANCE FISICO DE OBRA DIARIO - MAYO 2009
OBRA: MEJORAMIENTO PISTA Y VEREDAS AV. JOSE OLAYA I ETAPA TRAMO: (PROLG. PUNO - AV. CENTENARIO)

DESAGUE PLUVIAL
CONSTRUC.
CONSTRUCCION DE CONSTRUCCION DE CONSTRUCCION DE DADOS DE DADOS DE TENDIDO DE TENDIDO DE
ENCIMADO CONSTRUCCION DE CONSTRUCCION DE
BUZON H BUZON H BUZON H CONCRETO F'C= CONCRETO F'C= TUBERIA UPVC TUBERIA UPVC
BUZON H= 0.45m. SUMIDERO CAJA RECEPTOR
=1.200m =1.40m =1.50m 140KG/CM² 140KG/CM² U/F S-25 D=12" U/F S-25 D=10"
S.M.yTAPA

03.01.01 03.01.02 03.01.03 03.01.04 03.02.01 03.02.02 03.03.01 03.03.02 04.01 04.02

14.00
0.60 0.60 3.00

0.60 0.60 0.00 0.00 0.00 3.00 0.00 0.00 0.00 14.00
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
1.00 1.00 5.00 18.00 1.00 5.00 13.00 13.00 350.84 103.00
0.40 0.40 5.00 18.00 1.00 2.00 13.00 13.00 350.84 89.00
DIARIO - MAYO 2009
OLG. PUNO - AV. CENTENARIO)

DESAGUE PLUVIAL

TENDIDO DE SUMINISTRO Y PRUEBA A ZANJA VENTANA DE


TUBERIA UPVC COLOCACION DE TAPADA SUMIDERO REJILLA DE CAJA
U/F S-25 D=8" ACCESORIOS P/TUBERIA 0.70x0.80M

04.03 04.04 05.01 06.01 06.02

54.00

68.00

54.00 0.00 68.00 0.00 0.00


#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
122.10 33.00 575.94 13.00 13.00
68.10 33.00 507.94 13.00 13.00
VALORIZACION DE AVANCE FISICO Nº 02 ENERO 2010 - II ETAPA
DEL 02/01/2010 AL 30/01/2010
OBRA : "MEJORAMIENTO DE PISTAS Y VEREDAS DE AV. JOSE OLAYA TRAMO : AV. GIRALDEZ - PROLONG. PUNO RESIDENTE : ING. MIRIAM VILLAFUERTE PAC

CODIGO : 15-036-074-2063804-2164992-190 SUPERVISOR : ING. JORGE CHUCOS DE LA C


: PAVIMENTACION FLEXIBLE
CLIENTE : MUNICIPALIDAD PROVINCIAL DE HUANCAYO 46.26
Departamento : JUNIN Provincia : HUANCAYO Distrito : HUANCAYO Fecha de Presentacion :01 de Febrero del 2010
PRESUPUESTO REFERENCIAL AVANCES
ITEM DESCRIPCION Unidad Metrado Precio Parcial MES ANTERIOR SEMANA II ACUMULADO
METRADO VALORIZA. S/. % METRADO VALORIZ. S/. % METRADO VALORIZ. S/. %
01.00 OBRAS PROVISIONALES
01.01 TRAZO Y REPLANTEO M2 100.00 1.29 129.00 0.00 0.00 0.00 100.00 129.00 100.00 100.00 129.00 100.00
01.02 TRAZO Y REPLANTEO DURANTE LA EJECUCION M2 50.00 1.29 64.50 0.00 0.00 0.00 50.00 64.50 100.00 50.00 64.50 100.00
02.00 DEMOLICIONES
02.01 DEMOLICION DE MURO DE TAPIA M2 33.31 5.45 181.54 0.00 0.00 0.00 33.31 181.54 100.00 33.31 181.54 100.00
02.02 DEMOLICION DE MURO DE ADOBE M2 139.65 3.63 506.93 0.00 0.00 0.00 139.65 506.93 100.00 139.65 506.93 100.00
02.03 DEMOLICION DE PISOS M2 2.65 12.57 33.31 0.00 0.00 0.00 2.65 33.31 100.00 2.65 33.31 100.00
03.00 DESMONTAJE
03.01 DESMONTAJE DE PUERTAS UND 6.00 4.93 29.58 0.00 0.00 0.00 6.00 29.58 100.00 6.00 29.58 100.00
03.02 DESMONTAJE DE VENTANAS UND 2.00 7.61 15.22 0.00 0.00 0.00 2.00 15.22 100.00 2.00 15.22 100.00
03.03 DESMONTAJE DE TECHO DE TEJA M2 76.10 1.51 114.91 0.00 0.00 0.00 76.10 114.91 100.00 76.10 114.91 100.00
03.04 DESMONTAJE DE MEDIDOR DE ENERGIA ELEC. UND 1.00 4.39 4.39 0.00 0.00 0.00 1.00 4.39 100.00 1.00 4.39 100.00
03.05 DESMONTAJE DE CIELO RASO DE TRIPLAY M2 50.00 0.42 21.00 0.00 0.00 0.00 50.00 21.00 100.00 50.00 21.00 100.00
03.06 DESMONTAJE DE PISOS DE MADERA M2 12.60 1.91 24.07 0.00 0.00 0.00 12.60 24.07 100.00 12.60 24.07 100.00
04.00 REPOSICION
04.01 REPOSICION DE PUERTAS UND 2.00 20.28 40.56 0.00 0.00 0.00 2.00 40.56 100.00 2.00 40.56 100.00
04.02 REPOSICION DE VENTANAS UND 20.28 0.00 0.00 0.00 0.00 0.00
04.03 REPOSICION DE TECHO DE TEJA M2 14.24 1.90 27.06 0.00 0.00 0.00 14.24 27.06 100.00 14.24 27.06 100.00
04.04 REPOSICION DE TECHO DE CALAMINA M2 1.77 0.00 0.00 0.00 0.00 0.00
04.05 REPOSICION DE MEDIDOR DE ENERGIA ELECT. UND 1.00 62.32 62.32 0.00 0.00 0.00 1.00 62.32 100.00 1.00 62.32 100.00
04.06 REPOSICION DE CIELO RASO DE TRIPLAY M2 25.40 0.00 0.00 0.00 0.00 0.00
05.00 MOVIMIENTO DE TIERRAS
05.01 CIMIENTOS
05.01.01 EXCAVACION DE ZANJAS PARA CIMIENTO DE M3 12.65 15.86 200.63 0.00 0.00 0.00 12.65 200.63 100.00 12.65 200.63 100.00
MURO DE ADOBE Y/O TAPIA
05.02 ELIMINACION DE MATERIAL EXCEDENTE
05.02.01 ACARREO INTERNO DE MATERIAL EXCED. D=30 m M3 9.20 12.28 112.98 0.00 0.00 0.00 9.20 112.98 100.00 9.20 112.98 100.00
05.02.02 CARGUIO ELIM. MATERIAL EXCEDENTE M3 3.63 0.00 0.00 0.00 0.00 0.00
05.02.03 TRANSPORTE ELIM. MATERIAL EXCEDENTE M3 5.70 0.00 0.00 0.00 0.00 0.00
06.00 CIMENTACION
06.01 CIMENTACION DE PIEDRA Y BARRO `PARA MURO M3 12.65 81.89 1,035.91 0.00 0.00 0.00 12.65 1035.91 100.00 12.65 1035.91 100.00
DE ADOBE Y/O TAPIA
07.00 MUROS Y TABIQUES
07.01 REPOSICON DE MURO DE ADOBE Y/O TAPIA M3 93.48 19.63 1,835.01 0.00 0.00 0.00 93.48 1835.01 100.00 93.48 1835.01 100.00
08.00 REVOQUES Y ENLUCIDOS
08.01 TARRAJEO CON CEMENTO Y ARENA M2 1.00 27.83 27.83 0.00 0.00 0.00 1.00 27.83 100.00 1.00 27.83 100.00
08.02 ENLUCIDO DE MUROS CON YESO M2 14.08 31.81 447.88 0.00 0.00 0.00 14.08 447.88 100.00 14.08 447.88 100.00
09.00 PISOS Y PAVIMENTOS
VALORIZACION DE AVANCE FISICO Nº 02 ENERO 2010 - II ETAPA
DEL 02/01/2010 AL 30/01/2010
OBRA : "MEJORAMIENTO DE PISTAS Y VEREDAS DE AV. JOSE OLAYA TRAMO : AV. GIRALDEZ - PROLONG. PUNO RESIDENTE : ING. MIRIAM VILLAFUERTE PAC

CODIGO : 15-036-074-2063804-2164992-190 SUPERVISOR : ING. JORGE CHUCOS DE LA C


: PAVIMENTACION FLEXIBLE
CLIENTE : MUNICIPALIDAD PROVINCIAL DE HUANCAYO 46.26
Departamento : JUNIN Provincia : HUANCAYO Distrito : HUANCAYO Fecha de Presentacion :01 de Febrero del 2010
PRESUPUESTO REFERENCIAL AVANCES
ITEM DESCRIPCION Unidad Metrado Precio Parcial MES ANTERIOR SEMANA II ACUMULADO
METRADO VALORIZA. S/. % METRADO VALORIZ. S/. % METRADO VALORIZ. S/. %
09.01 FALSO PISO DE CONCRETO E= 4" M2 16.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.02 PISO DE CEMENTO PULIDO M3 24.81 0.00 0.00 0.00 0.00 0.00 0.00 0.00
COSTO DIRECTO 03 ALINEAMIENTO 4914.62 0.00 0.00% 4914.62 100.00% 4914.62 100.00%
SUB TOTAL 4914.62 0.00 4914.62 4914.62
GASTOS GENERALES 7% 344.02 0.00 344.02 344.02
UTILIDADES 5% 245.73 0.00 245.73 245.73
SUB TOTAL 5504.38 0.00 5504.38 5504.38
IMPUESTO IGV 19 % 1045.83 0.00 1045.83 1045.83
TOTAL GENERAL 6550.21 0.00 0.00% 6550.21 1.85% 6550.21 1.85%

AVANCE FISICO % VALORIZACION S/.


MES ANTER. 0.00% 0.00
DE LA SEMANA 1.85% 6550.21
ACUMULADO 1.85% 6550.21
M VILLAFUERTE PACHECO

GE CHUCOS DE LA CRUZ

e Febrero del 2010


SALDO

METRADO VALORIZ. S/. %

0.00 0.00 0.00


0.00 0.00 0.00

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

0.00 0.00 0.00


0.00 0.00
0.00 0.00 0.00
0.00 0.00
0.00 0.00 0.00
0.00 0.00

0.00 0.00 0.00

0.00 0.00 0.00


0.00 0.00
0.00 0.00

0.00 0.00 0.00

0.00 0.00 0.00

0.00 0.00 0.00


0.00 0.00 0.00
M VILLAFUERTE PACHECO

GE CHUCOS DE LA CRUZ

e Febrero del 2010


SALDO

METRADO VALORIZ. S/. %


0.00 0.00
0.00 0.00
0.00 0.00%
0.00
0.00
0.00
0.00
0.00
0.00 0.00%
VALORIZACION DE AVANCE FISICO Nº 02 ENERO 2010 - II ETAPA
DEL 18/01/2010 AL 23/01/2010
OBRA : "MEJORAMIENTO DE PISTAS Y VEREDAS DE AV. JOSE OLAYA TRAMO : AV. GIRALDEZ - PROLONG. PUNO RESIDENTE : ING. MIRIAM VILLAFUERTE PACHECO

CODIGO : 15-036-074-2063804-2164992-0086 SUPERVISOR : ING. JORGE CHUCOS DE LA CRUZ


: ALINEAMIENTO
CLIENTE : MUNICIPALIDAD PROVINCIAL DE HUANCAYO 46.26
Departamento : JUNIN Provincia : HUANCAYO Distrito : HUANCAYO Fecha de Presentacion :23 de Enero del 2010
PRESUPUESTO REFERENCIAL AVANCES
ITEM DESCRIPCION Unidad Metrado Precio Parcial MES ANTERIOR SEMANA II ACUMULADO
METRADO VALORIZA. S/. % METRADO VALORIZ. S/. % METRADO VALORIZ. S/. %
01.00 TRABAJOS PRELIMINARES
01.01 TRAZO Y REPLANTEO MES 0.25 437.84 109.46 0.25 109.46 100.00 0.00 0.00 0.00 0.25 109.46 100.00
01.02 CARTEL DE IDENTIFICACION DE OBRA UND 0.25 1,902.11 475.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.00 OBRAS PRELIMINARES
02.01 TRAZO Y REPLANTEO M2 1,904.10 0.87 1,656.57 1904.10 1656.57 100.00 0.00 0.00 1904.10 1656.57 100.00
02.02 TRAZO Y REPLANTEO DURANTE LA EJECUCION M2 1,904.08 0.85 1,618.47 400.00 340.00 21.01 354.20 301.07 18.60 754.20 641.07 39.61
02.03 ROTURA DE VEREDAS M3 0.48 42.58 20.44 0.48 20.44 100.00 0.00 0.00 0.00 0.48 20.44 100.00
03.00 EXPLANACIONES
03.01 MOVIMIENTO DE TIERRAS
03.01.01 CORTE DE TERRENO DE SUB RASANTE M3 1,149.87 5.09 5,852.84 801.72 4080.75 69.72 114.50 582.81 9.96 916.22 4663.56 79.68
03.01.02 CORTE PARA MEJORAM. DE SUB BASE M3 46.08 5.08 234.09 46.08 234.09 100.00 0.00 0.00 0.00 46.08 234.09 100.00
03.01.03 CORTE DE TERRENO MANUAL M3 59.80 21.45 1,282.71 32.24 691.55 53.91 27.56 591.16 46.09 59.80 1282.71 100.00
03.01.04 EXCAVACION MANUAL PARA CUNETA M3 18.29 21.45 392.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.01.05 EXCAVACION MANUAL PARA SARDINEL M3 28.17 21.45 604.25 7.20 154.44 25.56 0.00 0.00 0.00 7.20 154.44 25.56
03.01.06 EXCAVACION MANUAL EN BADEN M3 4.73 21.04 99.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.02 ELIMINACION DE MATERIAL EXCEDENTE
03.02.01 ACARREO INTERNO DE MATERIAL M3 133.80 17.94 2,400.37 133.80 2400.37 100.00 0.00 0.00 133.80 2400.37 100.00
03.02.02 CARGUIO (ELIM.DE MATERIAL EXCEDENTE) M3 1,568.94 3.63 5,695.25 965.00 3502.95 61.51 360.00 1306.80 22.95 1325.00 4809.75 84.45
03.02.03 TRANSPORTE (ELIM. MAT. EXCEDENTE) M3 1,568.94 5.70 8,942.96 965.00 5500.50 61.51 360.00 2052.00 22.95 1325.00 7552.50 84.45
03.02.04 ESCARIFICADO PERFILADO/COMPACTADO M2 1,421.70 2.28 3,241.48 1168.00 2663.04 82.16 253.70 578.44 17.84 1421.70 3241.48 100.00
04.00 PAVIMENTOS
04.01 MEJORAMIENTO DE SUB RASANTE
04.01.01 EXTRACCION DE MATERIAL P/MEJ. SUB RASANTE M3 305.70 7.42 2,268.27 240.00 1780.80 78.51 65.70 487.49 21.49 305.70 2268.29 100.00
04.01.02 SELECCION DE MATERIAL P/ MEJ DE SUB RASANTE M3 251.00 4.68 1,174.68 251.00 1174.68 100.00 0.00 0.00 0.00 251.00 1174.68 100.00
04.01.03 CARGUIO DE (MEJ. S-R) M3 251.00 3.83 961.33 251.00 961.33 100.00 0.00 0.00 0.00 251.00 961.33 100.00
04.01.04 TRANSPORTE (MEJ. S-R) M3 251.00 5.70 1,430.70 251.00 1430.70 100.00 0.00 0.00 0.00 251.00 1430.70 100.00
04.01.05 EXT. RIEGO Y COMPC. P/MEJ DE SUB RASANTE M2 1,165.00 2.18 2,539.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02 SUB BASE GRANULAR
04.02.01 EXTRACCION DE MATERIAL PARA SUB BASE M3 398.08 7.41 2,949.77 350.00 2593.50 87.92 48.08 356.27 12.08 398.08 2949.77 100.00
04.02.02 SELECCION DE MATERIAL P/ SUB BASE GRANULAR M3 369.64 4.68 1,729.92 0.00 0.00 0.00 120.00 561.60 32.46 120.00 561.60 32.46
04.02.03 CARGUIO DE S-B M3 369.64 3.92 1,448.99 0.00 0.00 0.00 120.00 470.40 32.46 120.00 470.40 32.46
04.02.04 TRANSPORTE DE S.B. M3 369.64 5.70 2,106.95 0.00 0.00 0.00 120.00 684.00 32.46 120.00 684.00 32.46
04.02.05 EXT. RIEGO Y COMPC. DE SUB BASE E= 0.20m. M2 1,421.70 2.31 3,284.13 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.03 BASE GRANULAR
04.03.01 EXTRACCION DE MATERIAL PARA BASE M3 471.44 7.41 3,493.37 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.03.02 SELECCION DE MATERIAL P/ BASE GRANULAR M3 437.76 4.68 2,048.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.03.03 CARGUIO DE B. M3 437.76 3.92 1,716.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.03.04 TRANSPORTE DE B. M3 437.76 5.70 2,495.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
VALORIZACION DE AVANCE FISICO Nº 02 ENERO 2010 - II ETAPA
DEL 18/01/2010 AL 23/01/2010
OBRA : "MEJORAMIENTO DE PISTAS Y VEREDAS DE AV. JOSE OLAYA TRAMO : AV. GIRALDEZ - PROLONG. PUNO RESIDENTE : ING. MIRIAM VILLAFUERTE PACHECO

CODIGO : 15-036-074-2063804-2164992-0086 SUPERVISOR : ING. JORGE CHUCOS DE LA CRUZ


: ALINEAMIENTO
CLIENTE : MUNICIPALIDAD PROVINCIAL DE HUANCAYO 46.26
Departamento : JUNIN Provincia : HUANCAYO Distrito : HUANCAYO Fecha de Presentacion :23 de Enero del 2010
PRESUPUESTO REFERENCIAL AVANCES
ITEM DESCRIPCION Unidad Metrado Precio Parcial MES ANTERIOR SEMANA II ACUMULADO
METRADO VALORIZA. S/. % METRADO VALORIZ. S/. % METRADO VALORIZ. S/. %
04.03.05 EXT. RIEGO Y COMPC. DE BASE E= 0.20m. M2 1,421.70 2.32 3,298.34 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.04 CARPETA ASFALTICA
04.04.01 IMPRIMACION ASFALTICA M2 1,097.20 5.46 5,990.71 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.04.02 CARPETA ASFALTICA EN CALIENTE E= 3" M2 1,097.20 52.36 57,449.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.00 DRENAJE
05.01 ENCOFRADO Y DESENCOFRADO DE CUNETAS M2 45.72 36.99 1,691.18 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.02 CUNETAS CONCRETO F'C=175 KG/CM2 M3 61.23 281.43 17,231.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.00 BADEN
06.01 BADEN CONCRETO F'C=210 KG/CM2 M3 4.73 285.88 1,352.21 0.00 0.00 0.00 0.00 0.00 0.00
06.02 BADEN ENCOFRADO Y DESENCOFRADO M2 3.94 36.99 145.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.00 SARDINEL INEXPUESTO
07.01 SARDINEL INEXP. CONCRETO F'C=210 KG/CM2 M3 3.43 298.61 1,024.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.02 SARDINEL INEXP. ENCOFRADO Y DESENCOFRADO M2 6.86 26.86 184.26 0.00 0.00 0.00 0.00 0.00 0.00
08.00 ACERA PEATONAL
08.01 SARDINEL EXPUESTO
08.01.01 SARDINEL EXP. ENCOFRADO Y DESENCOFRADO M2 170.63 30.13 5,141.08 57.60 1735.49 33.76 0.00 0.00 0.00 57.60 1735.49 33.76
08.01.02 SARDINEL EXP. CONCRETO F'C=175 KG/CM2 M3 25.59 270.17 6,913.65 8.64 2334.27 33.76 0.00 0.00 0.00 8.64 2334.27 33.76
VEREDAS
08.02.01 REFINE Y NIVELACION M2 524.00 1.41 738.84 312.08 440.03 59.56 0.00 0.00 312.08 440.03 59.56
08.02.02 RELLENO Y COMPACTADO DE VEREDA M2 524.00 4.60 2,410.40 380.78 1751.59 72.67 0.00 0.00 380.78 1751.59 72.67
08.02.03 VEREDA ENCOFRADO Y DESENCOFRADO M2 12.57 29.31 368.43 7.93 232.43 63.09 0.00 0.00 0.00 7.93 232.43 63.09
08.02.04 VEREDAS CONCRETO F'C=175 KG/CM2 M2 524.00 29.26 15,332.24 203.24 5946.80 38.79 0.00 0.00 0.00 203.24 5946.80 38.79
9.00 RAMPAS
9.01 ENCOFRADO Y DESENCOFRADO RAMPA M2 2.31 31.63 73.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
9.02 RAMPA CONCRETO F'C=175 KG/CM2 M2 10.80 29.88 322.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.00 JUNTAS
10.01 RELLENO DE JUNTAS M 179.09 1.96 351.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.00 AREAS VERDES
11.01 SUMINISTRO DE TIERRA AGRICOLA M3 72.30 33.76 2,440.85 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02 COLOCACION DE GRASS M2 241.00 10.20 2,458.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03 COLOCACION DE PLANTONES UND 20.00 16.79 335.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12.00 SEÑALIZACION
12.01 SEÑALIZACION HORIZONTAL
12.01.01 PINTURA LINEAL EN BORDE DE VIA M 228.62 3.97 907.62 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12.01.02 PINTURA LINEAL CONTINUA EN EJE DE VIA M 95.70 3.90 373.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12.01.03 PINTURA LINEAL DISCONTINUA EN EJE DE VIA M 191.00 3.24 618.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12.01.04 PINTURA DE SIMBOLOS Y FLECHAS M2 12.00 12.69 152.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12.02 SEÑALIZACION VERTICAL
VALORIZACION DE AVANCE FISICO Nº 02 ENERO 2010 - II ETAPA
DEL 18/01/2010 AL 23/01/2010
OBRA : "MEJORAMIENTO DE PISTAS Y VEREDAS DE AV. JOSE OLAYA TRAMO : AV. GIRALDEZ - PROLONG. PUNO RESIDENTE : ING. MIRIAM VILLAFUERTE PACHECO

CODIGO : 15-036-074-2063804-2164992-0086 SUPERVISOR : ING. JORGE CHUCOS DE LA CRUZ


: ALINEAMIENTO
CLIENTE : MUNICIPALIDAD PROVINCIAL DE HUANCAYO 46.26
Departamento : JUNIN Provincia : HUANCAYO Distrito : HUANCAYO Fecha de Presentacion :23 de Enero del 2010
PRESUPUESTO REFERENCIAL AVANCES
ITEM DESCRIPCION Unidad Metrado Precio Parcial MES ANTERIOR SEMANA II ACUMULADO
METRADO VALORIZA. S/. % METRADO VALORIZ. S/. % METRADO VALORIZ. S/. %
12.02.01 SEÑALES TIPO R (90cM x 60cm) UND 1.00 384.08 384.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12.02.02 SEÑALES TIPO F UND 1.00 358.52 358.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.00 EQUIPAMIENTO
13.01 MOVILIARIO URBANO UND 3.00 545.16 1,635.48 0.00 0.00 0.00 1.00 545.16 33.33 1.00 545.16 33.33
13.02 SUMINISTRO Y COLOCACION DE TACHOS DE BASURA UND 2.00 399.03 798.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
14.00 RECONEXIONES
14.01 RECONEXIONES DE PUNTOS DE AGUA PTO 6.00 13.99 83.94 5.00 69.95 83.33 1.00 13.99 16.67 6.00 83.94 100.00
14.02 RECONEXION DE CAJA MEDIDOR DE AGUA PTO 6.00 12.96 77.76 5.00 64.80 83.33 1.00 12.96 16.67 6.00 77.76 100.00
14.03 RECONEXION DE INSTALACIONES DE DESAGUE PTO 6.00 17.56 105.36 6.00 105.36 100.00 0.00 0.00 0.00 6.00 105.36 100.00
14.04 RECONEXION DE CAJA DE REGISTRO DE DESAGUE PTO 6.00 11.31 67.86 6.00 67.86 100.00 0.00 0.00 0.00 6.00 67.86 100.00
15.00 VARIOS
15.01 LIMPIEZA FINAL DE OBRA M2 2,000.00 0.66 1,320.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

DESAGUE PLUVIAL

01.00 TRABAJOS PRELIMINARES


01.01 TRAZO NIVELES Y REPLANTEO DE ZANJA M 395.00 0.56 221.20 352.00 197.12 89.11 43.00 24.08 10.89 395.00 221.20 100.00
02.00 MOVIMIENTO DE TIERRAS

02.01 EXCAVACIONES
02.01.01 EXCAVACION PARA BUZONES M3 32.63 21.45 699.91 32.63 699.91 100.00 0.00 0.00 0.00 32.63 699.91 100.00
02.01.02 EXCAVACION DE ZANJAS - MANUAL M 471.20 15.02 7,077.42 357.60 5371.15 75.89 51.80 778.04 10.99 409.40 6149.19 86.88
02.01.03 EXCAVACION PARA SUMIDEROS M3 7.83 28.75 225.11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.01.04 REFINE Y NIVELACION EN ZANJAS M 471.20 1.85 871.72 411.30 760.91 87.29 51.80 95.83 10.99 463.10 856.74 98.28
02.02 CAMAS DE APOYO
02.02.01 PREPARACION DE CAMAS DE APOYO M 471.20 4.61 2,172.23 356.60 1643.93 75.68 51.80 238.80 10.99 408.40 1882.72 86.67
02.03 RELLENOS
02.03.01 EXTRACCION DE MAT. P/RELLENO M3 230.89 6.39 1,475.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.03.02 SELECCIÓN DE MATERIAL P/RELLENO M3 214.40 3.42 733.25 150.00 513.00 69.96 0.00 0.00 0.00 150.00 513.00 69.96
02.03.03 CARGUIO P/ RELLENO M3 214.40 4.16 891.90 150.00 624.00 69.96 0.00 0.00 0.00 150.00 624.00 69.96
02.03.04 TRANSPORTE P/ RELLENO M3 214.40 5.52 1,183.49 150.00 828.00 69.96 0.00 0.00 0.00 150.00 828.00 69.96
02.03.05 RELLENO Y COMPACTADO DE ZANJA M 471.20 14.97 7,053.86 379.60 5682.61 80.56 51.80 775.45 10.99 431.40 6458.06 91.55
02.04 ELIMINACION DE MATERIAL EXCEDENTE
02.04.01 ACARREO INTERNO DE MATERIAL M3 48.55 13.46 653.48 48.55 653.48 100.00 0.00 0.00 0.00 48.55 653.48 100.00
02.04.02 CARGUIO (ELIM. MAT. EXCEDENTE) M3 48.55 3.92 190.32 48.55 190.32 100.00 0.00 0.00 0.00 48.55 190.32 100.00
02.04.03 TRANSPORTE (ELIM. MAT. EXCEDENTE) M3 48.55 5.70 276.74 48.55 276.74 100.00 0.00 0.00 0.00 48.55 276.74 100.00
03.00 OBRAS DE CONCRETO ARMADO
03.01 CONSTRUCCION DE BUZONES
VALORIZACION DE AVANCE FISICO Nº 02 ENERO 2010 - II ETAPA
DEL 18/01/2010 AL 23/01/2010
OBRA : "MEJORAMIENTO DE PISTAS Y VEREDAS DE AV. JOSE OLAYA TRAMO : AV. GIRALDEZ - PROLONG. PUNO RESIDENTE : ING. MIRIAM VILLAFUERTE PACHECO

CODIGO : 15-036-074-2063804-2164992-0086 SUPERVISOR : ING. JORGE CHUCOS DE LA CRUZ


: ALINEAMIENTO
CLIENTE : MUNICIPALIDAD PROVINCIAL DE HUANCAYO 46.26
Departamento : JUNIN Provincia : HUANCAYO Distrito : HUANCAYO Fecha de Presentacion :23 de Enero del 2010
PRESUPUESTO REFERENCIAL AVANCES
ITEM DESCRIPCION Unidad Metrado Precio Parcial MES ANTERIOR SEMANA II ACUMULADO
METRADO VALORIZA. S/. % METRADO VALORIZ. S/. % METRADO VALORIZ. S/. %
03.01.01 CONSTRUCCION DE BUZON H =1..50m UND 4.00 1159.37 4,637.48 1.50 1739.06 37.50 0.00 0.00 0.00 1.50 1739.06 37.50
03.01.02 CONSTRUCCION DE BUZON H =1.70m UND 5.00 1,066.12 5,330.60 4.35 4637.62 87.00 0.00 0.00 4.35 4637.62 87.00
03.01.03 DADOS DE CONCRETO F'C= 140KG/CM² UND 18.00 63.27 1,138.86 7.00 442.89 38.89 4.00 253.08 22.22 11.00 695.97 61.11
03.02 ENCIMADO DE BUZONES
03.02.01 CONST. ENCIM.BUZON H= 0.45m. S.M.yTAPA UND 1.00 344.68 344.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.02.02 DADOS DE CONCRETO F'C= 140KG/CM² UND 5.00 63.27 316.35 2.00 126.54 40.00 0.00 0.00 0.00 2.00 126.54 40.00
03.03 SUMIDEROS
03.03.01 CONSTRUCCION DE SUMIDERO UND 6.00 423.36 2,540.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.03.02 CONSTRUCCION DE CAJA RECEPTOR UND 6.00 60.58 363.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.00 SUMINISTRO Y TENDIDO DE TUBERIA
04.01 TENDIDO DE TUBERIA UPVC U/F S-25 D=12" M 395.00 70.77 27,954.15 360.20 25491.35 91.19 34.80 2462.80 8.81 395.00 27954.15 100.00
04.02 TENDIDO DE TUBERIA UPVC U/F S-25 D=10" M 22.20 54.39 1,207.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.03 TENDIDO DE TUBERIA UPVC U/F S-25 D=8" M 54.00 42.40 2,289.60 0.00 0.00 0.00 17.00 720.80 31.48 17.00 720.80 31.48
04.04 SUMINISTRO Y COLOCACION DE ACCESORIOS UND 6.00 15.35 92.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.00 PRUEBA HIDRAULICA
05.01 PRUEBA A ZANJA TAPADA P/TUBERIA M 471.20 1.17 551.30 145.30 170.00 30.84 51.80 60.61 10.99 197.10 230.61 41.83
06.00 CARPINTERIA METALICA
06.01 VENTANA DE SUMIDERO 0.70x0.80M UND 6.00 93.49 560.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.02 REJILLA DE CAJA UND 6.00 114.81 688.86 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
COSTO DIRECTO 01 PAVIMENTACION FLEXIBLE 194411.37 42043.74 21.63% 8544.15 4.39% 50587.89 26.02%
COSTO DIRECTO 02 DESAGUE PLUVIAL 71742.04 50048.62 69.76% 5409.47 7.54% 55458.10 77.30%
SUB TOTAL 266153.41 92092.37 13953.62 106045.99
GASTOS GENERALES 7% 18630.74 6446.47 976.75 7423.22
UTILIDADES 5% 13307.67 4604.62 697.68 5302.30
SUB TOTAL 298091.82 103143.45 15628.06 118771.51
IMPUESTO IGV 19 % 56637.45 19597.26 2969.33 22566.59
TOTAL GENERAL 354729.27 122740.71 34.60% 18597.39 5.24% 141338.10 39.84%

AVANCE FISICO % VALORIZACION S/.


MES ANTER. 34.60% 122740.71
DE LA SEMANA 5.24% 18597.39
ACUMULADO 39.84% 141338.10
IAM VILLAFUERTE PACHECO

RGE CHUCOS DE LA CRUZ

3 de Enero del 2010


SALDO

METRADO VALORIZ. S/. %

0.00 0.00 0.00


0.25 475.53 100.00
0.00 0.00
0.00 0.00 0.00
1149.88 977.40 60.39
0.00 0.00 0.00

233.65 1189.28 20.32


0.00 0.00 0.00
0.00 0.00 0.00
18.29 392.32 100.00
20.97 449.81 74.44
4.73 99.52 100.00

0.00 0.00 0.00


243.94 885.50 15.55
243.94 1390.46 15.55
0.00 0.00 0.00

0.00 -0.02 0.00


0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
1165.00 2539.70 100.00

0.00 0.00 0.00


249.64 1168.32 67.54
249.64 978.59 67.54
249.64 1422.95 67.54
1421.70 3284.13 100.00

471.44 3493.37 100.00


437.76 2048.72 100.00
437.76 1716.02 100.00
437.76 2495.23 100.00
IAM VILLAFUERTE PACHECO

RGE CHUCOS DE LA CRUZ

3 de Enero del 2010


SALDO

METRADO VALORIZ. S/. %


1421.70 3298.34 100.00

1097.20 5990.71 100.00


1097.20 57449.39 100.00

45.72 1691.18 100.00


61.23 17231.96 100.00

4.73 1352.21
3.94 145.74 100.00

3.43 1024.23 100.00


6.86 184.26

113.03 3405.59 66.24


16.95 4579.38 66.24
0.00 0.00
211.92 298.81 40.44
143.22 658.81 27.33
4.64 136.00 36.91
320.76 9385.44 61.21

2.31 73.07 100.00


10.80 322.70 100.00

179.09 351.02 100.00

72.30 2440.85 100.00


241.00 2458.20 100.00
20.00 335.80 100.00

228.62 907.62 100.00


95.70 373.23 100.00
191.00 618.84 100.00
12.00 152.28 100.00
IAM VILLAFUERTE PACHECO

RGE CHUCOS DE LA CRUZ

3 de Enero del 2010


SALDO

METRADO VALORIZ. S/. %


1.00 384.08 100.00
1.00 358.52 100.00

2.00 1090.32 66.67


2.00 798.06 100.00

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

2000.00 1320.00 100.00

0.00 0.00 0.00

0.00 0.00 0.00


61.80 928.24 13.12
7.83 225.11 100.00
8.10 14.99 1.72

62.80 289.51 13.33

230.89 1475.39 100.00


64.40 220.25 30.04
64.40 267.90 30.04
64.40 355.49 30.04
39.80 595.81 8.45

0.00 0.00 0.00


0.00 0.00 0.00
0.00 0.00 0.00
IAM VILLAFUERTE PACHECO

RGE CHUCOS DE LA CRUZ

3 de Enero del 2010


SALDO

METRADO VALORIZ. S/. %


2.50 2898.43 62.50
0.65 692.98 13.00
7.00 442.89 38.89

1.00 344.68 100.00


3.00 189.81 60.00
0.00 0.00
6.00 2540.16 100.00
6.00 363.48 100.00

0.00 0.00 0.00


22.20 1207.46 100.00
37.00 1568.80 68.52
6.00 92.10 100.00

274.10 320.70 58.17

6.00 560.94 100.00


6.00 688.86 100.00
143823.45 73.98%
16283.95 22.70%
160107.41
11207.52
8005.37
179320.29
34070.86
213391.15 60.16%
VALORIZACION DE AVANCE FISICO Nº 02 DICIEMBRE 2009 - II ETAPA
DEL 1/12/2009 AL 30/12/2009
OBRA : "MEJORAMIENTO DE PISTAS Y VEREDAS DE AV. JOSE OLAYA TRAMO : AV. GIRALDEZ - PROLONG. PUNO RESIDENTE : ING. MIRIAM VILLAFUERTE PACHE

CODIGO : 15-036-074-2063804-2164992-190 SUPERVISOR : ING. JORGE CHUCOS DE LA CRU


: PAVIMENTACION FLEXIBLE
CLIENTE : MUNICIPALIDAD PROVINCIAL DE HUANCAYO

Departamento : JUNIN Provincia : HUANCAYO Distrito : HUANCAYO Fecha de Presentacion :01 de Diciembre del 2009
PRESUPUESTO REFERENCIAL AVANCES
ITEM DESCRIPCION Unidad Metrado Precio Parcial ANTERIOR NOVIEMBRE ACTUAL DICIEMBRE ACUMULADO
METRADO VALORIZA. S/. % METRADO VALORIZ. S/. % METRADO VALORIZ. S/. %
01.00 OBRAS PROVISIONALES
01.01 ALMACEN Y CASETA DE GUARDIANIA MES 0.25 437.84 109.46 0.10 43.78 40.00 0.00 0.00 0.00 0.10 43.78 40.00
01.02 CARTEL DE IDENTIFICACION DE OBRA UND 0.25 1,902.11 475.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.00 OBRAS PRELIMINARES 0.00
02.01 TRAZO Y REPLANTEO M2 1,904.10 0.87 1,656.57 1000.00 870.00 52.52 0.00 0.00 0.00 1000.00 870.00 52.52
02.02 TRAZO Y REPLANTEO DURANTE LA EJECUCION M2 1,904.08 0.85 1,618.47 400.00 340.00 21.01 0.00 0.00 0.00 400.00 340.00 21.01
02.03 ROTURA DE VEREDAS M3 0.48 42.58 20.44 0.48 20.44 100.00 0.00 0.00 0.00 0.48 20.44 100.00
03.00 EXPLANACIONES
03.01 MOVIMIENTO DE TIERRAS
03.01.01 CORTE DE TERRENO DE SUB RASANTE M3 1,149.87 5.09 5,852.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.01.02 CORTE PARA MEJORAM. DE SUB BASE M3 46.08 5.08 234.09 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.01.03 CORTE DE TERRENO MANUAL M3 59.80 21.45 1,282.71 25.76 552.55 43.08 0.00 0.00 0.00 25.76 552.55 43.08
03.01.04 EXCAVACION MANUAL PARA CUNETA M3 18.29 21.45 392.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.01.05 EXCAVACION MANUAL PARA SARDINEL M3 28.17 21.45 604.25 2.34 50.19 8.31 0.00 0.00 0.00 2.34 50.19 8.31
03.01.06 EXCAVACION MANUAL EN BADEN M3 4.73 21.04 99.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.02 ELIMINACION DE MATERIAL EXCEDENTE
03.02.01 ACARREO INTERNO DE MATERIAL M3 133.80 17.94 2,400.37 33.68 604.22 25.17 0.00 0.00 0.00 33.68 604.22 25.17
03.02.02 CARGUIO (ELIM.DE MATERIAL EXCEDENTE) M3 1,568.94 3.63 5,695.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.02.03 TRANSPORTE (ELIM. MAT. EXCEDENTE) M3 1,568.94 5.70 8,942.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.02.04 ESCARIFICADO PERFILADO/COMPACTADO M2 1,421.70 2.28 3,241.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.00 PAVIMENTOS
04.01 MEJORAMIENTO DE SUB RASANTE 0.00
04.01.01 EXTRACCION DE MATERIAL P/MEJ. SUB RASANTE M3 305.70 7.42 2,268.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.01.02 SELECCION DE MATERIAL P/ MEJ DE SUB RASANTE M3 251.00 4.68 1,174.68 0.00 0.00 0.00 251.00 1174.68 100.00 251.00 1174.68 100.00
04.01.03 CARGUIO DE (MEJ. S-R) M3 251.00 3.83 961.33 0.00 0.00 0.00 251.00 961.33 100.00 251.00 961.33 100.00
04.01.04 TRANSPORTE (MEJ. S-R) M3 251.00 5.70 1,430.70 0.00 0.00 0.00 251.00 1430.70 100.00 251.00 1430.70 100.00
04.01.05 EXT. RIEGO Y COMPC. P/MEJ DE SUB RASANTE M2 1,165.00 2.18 2,539.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02 SUB BASE GRANULAR
04.02.01 EXTRACCION DE MATERIAL PARA SUB BASE M3 398.08 7.41 2,949.77 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02.02 SELECCION DE MATERIAL P/ SUB BASE GRANULAR M3 369.64 4.68 1,729.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02.03 CARGUIO DE S-B M3 369.64 3.92 1,448.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02.04 TRANSPORTE DE S.B. M3 369.64 5.70 2,106.95 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02.05 EXT. RIEGO Y COMPC. DE SUB BASE E= 0.20m. M2 1,421.70 2.31 3,284.13 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.03 BASE GRANULAR
04.03.01 EXTRACCION DE MATERIAL PARA BASE M3 471.44 7.41 3,493.37 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.03.02 SELECCION DE MATERIAL P/ BASE GRANULAR M3 437.76 4.68 2,048.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.03.03 CARGUIO DE B. M3 437.76 3.92 1,716.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.03.04 TRANSPORTE DE B. M3 437.76 5.70 2,495.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
VALORIZACION DE AVANCE FISICO Nº 02 DICIEMBRE 2009 - II ETAPA
DEL 1/12/2009 AL 30/12/2009
OBRA : "MEJORAMIENTO DE PISTAS Y VEREDAS DE AV. JOSE OLAYA TRAMO : AV. GIRALDEZ - PROLONG. PUNO RESIDENTE : ING. MIRIAM VILLAFUERTE PACHE

CODIGO : 15-036-074-2063804-2164992-190 SUPERVISOR : ING. JORGE CHUCOS DE LA CRU


: PAVIMENTACION FLEXIBLE
CLIENTE : MUNICIPALIDAD PROVINCIAL DE HUANCAYO

Departamento : JUNIN Provincia : HUANCAYO Distrito : HUANCAYO Fecha de Presentacion :01 de Diciembre del 2009
PRESUPUESTO REFERENCIAL AVANCES
ITEM DESCRIPCION Unidad Metrado Precio Parcial ANTERIOR NOVIEMBRE ACTUAL DICIEMBRE ACUMULADO
METRADO VALORIZA. S/. % METRADO VALORIZ. S/. % METRADO VALORIZ. S/. %
04.03.05 EXT. RIEGO Y COMPC. DE BASE E= 0.20m. M2 1,421.70 2.32 3,298.34 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.04 CARPETA ASFALTICA
04.04.01 IMPRIMACION ASFALTICA M2 1,097.20 5.46 5,990.71 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.04.02 CARPETA ASFALTICA EN CALIENTE E= 3" M2 1,097.20 52.36 57,449.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.00 DRENAJE
05.01 ENCOFRADO Y DESENCOFRADO DE CUNETAS M2 45.72 36.99 1,691.18 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.02 CUNETAS CONCRETO F'C=175 KG/CM2 M3 61.23 281.43 17,231.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.00 BADEN
06.01 BADEN CONCRETO F'C=210 KG/CM2 M3 4.73 285.88 1,352.21 0.00 0.00
06.02 BADEN ENCOFRADO Y DESENCOFRADO M2 3.94 36.99 145.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.00 SARDINEL INEXPUESTO
07.01 SARDINEL INEXP. CONCRETO F'C=210 KG/CM2 M3 3.43 298.61 1,024.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.02 SARDINEL INEXP. ENCOFRADO Y DESENCOFRADO M2 6.86 26.86 184.26 0.00 0.00
08.00 ACERA PEATONAL
08.01 SARDINEL EXPUESTO
08.01.01 SARDINEL EXP. ENCOFRADO Y DESENCOFRADO M2 170.63 30.13 5,141.08 15.60 470.03 9.14 0.00 0.00 0.00 15.60 470.03 9.14
08.01.02 SARDINEL EXP. CONCRETO F'C=175 KG/CM2 M3 25.59 270.17 6,913.65 2.34 632.20 9.14 0.00 0.00 0.00 2.34 632.20 9.14
VEREDAS 0.00
08.02.01 REFINE Y NIVELACION M2 524.00 1.41 738.84 64.35 90.73 12.28 0.00 0.00 0.00 64.35 90.73 12.28
08.02.02 RELLENO Y COMPACTADO DE VEREDA M2 524.00 4.60 2,410.40 64.35 296.01 12.28 0.00 0.00 0.00 64.35 296.01 12.28
08.02.03 VEREDA ENCOFRADO Y DESENCOFRADO M2 12.57 29.31 368.43 2.15 63.02 17.10 0.00 0.00 0.00 2.15 63.02 17.10
08.02.04 VEREDAS CONCRETO F'C=175 KG/CM2 M2 524.00 29.26 15,332.24 64.35 1882.88 12.28 0.00 0.00 0.00 64.35 1882.88 12.28
9.00 RAMPAS
9.01 ENCOFRADO Y DESENCOFRADO RAMPA M2 2.31 31.63 73.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
9.02 RAMPA CONCRETO F'C=175 KG/CM2 M2 10.80 29.88 322.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.00 JUNTAS
10.01 RELLENO DE JUNTAS M 179.09 1.96 351.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.00 AREAS VERDES
11.01 SUMINISTRO DE TIERRA AGRICOLA M3 72.30 33.76 2,440.85 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02 COLOCACION DE GRASS M2 241.00 10.20 2,458.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.03 COLOCACION DE PLANTONES UND 20.00 16.79 335.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12.00 SEÑALIZACION
12.01 SEÑALIZACION HORIZONTAL
12.01.01 PINTURA LINEAL EN BORDE DE VIA M 228.62 3.97 907.62 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12.01.02 PINTURA LINEAL CONTINUA EN EJE DE VIA M 95.70 3.90 373.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12.01.03 PINTURA LINEAL DISCONTINUA EN EJE DE VIA M 191.00 3.24 618.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12.01.04 PINTURA DE SIMBOLOS Y FLECHAS M2 12.00 12.69 152.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12.02 SEÑALIZACION VERTICAL
VALORIZACION DE AVANCE FISICO Nº 02 DICIEMBRE 2009 - II ETAPA
DEL 1/12/2009 AL 30/12/2009
OBRA : "MEJORAMIENTO DE PISTAS Y VEREDAS DE AV. JOSE OLAYA TRAMO : AV. GIRALDEZ - PROLONG. PUNO RESIDENTE : ING. MIRIAM VILLAFUERTE PACHE

CODIGO : 15-036-074-2063804-2164992-190 SUPERVISOR : ING. JORGE CHUCOS DE LA CRU


: PAVIMENTACION FLEXIBLE
CLIENTE : MUNICIPALIDAD PROVINCIAL DE HUANCAYO

Departamento : JUNIN Provincia : HUANCAYO Distrito : HUANCAYO Fecha de Presentacion :01 de Diciembre del 2009
PRESUPUESTO REFERENCIAL AVANCES
ITEM DESCRIPCION Unidad Metrado Precio Parcial ANTERIOR NOVIEMBRE ACTUAL DICIEMBRE ACUMULADO
METRADO VALORIZA. S/. % METRADO VALORIZ. S/. % METRADO VALORIZ. S/. %
12.02.01 SEÑALES TIPO R (90cM x 60cm) UND 1.00 384.08 384.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12.02.02 SEÑALES TIPO F UND 1.00 358.52 358.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.00 EQUIPAMIENTO
13.01 MOVILIARIO URBANO UND 3.00 545.16 1,635.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13.02 SUMINISTRO Y COLOCACION DE TACHOS DE BASURA UND 2.00 399.03 798.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
14.00 RECONEXIONES
14.01 RECONEXIONES DE PUNTOS DE AGUA PTO 6.00 13.99 83.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
14.02 RECONEXION DE CAJA MEDIDOR DE AGUA PTO 6.00 12.96 77.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
14.03 RECONEXION DE INSTALACIONES DE DESAGUE PTO 6.00 17.56 105.36 0.00 0.00 0.00 6.00 105.36 100.00 6.00 105.36 100.00
14.04 RECONEXION DE CAJA DE REGISTRO DE DESAGUE PTO 6.00 11.31 67.86 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.00 VARIOS
15.01 LIMPIEZA FINAL DE OBRA M2 2,000.00 0.66 1,320.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

DESAGUE PLUVIAL

01.00 TRABAJOS PRELIMINARES


01.01 TRAZO NIVELES Y REPLANTEO DE ZANJA M 395.00 0.56 221.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.00 MOVIMIENTO DE TIERRAS

02.01 EXCAVACIONES
02.01.01 EXCAVACION PARA BUZONES M3 32.63 21.45 699.91 0.00 0.00 0.00 32.63 699.91 100.00 32.63 699.91 100.00
02.01.02 EXCAVACION DE ZANJAS - MANUAL M 471.20 15.02 7,077.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.01.03 EXCAVACION PARA SUMIDEROS M3 7.83 28.75 225.11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.01.04 REFINE Y NIVELACION EN ZANJAS M 471.20 1.85 871.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.02 CAMAS DE APOYO
02.02.01 PREPARACION DE CAMAS DE APOYO M 471.20 4.61 2,172.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.03 RELLENOS
02.03.01 EXTRACCION DE MAT. P/RELLENO M3 230.89 6.39 1,475.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.03.02 SELECCIÓN DE MATERIAL P/RELLENO M3 214.40 3.42 733.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.03.03 CARGUIO P/ RELLENO M3 214.40 4.16 891.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.03.04 TRANSPORTE P/ RELLENO M3 214.40 5.52 1,183.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.03.05 RELLENO Y COMPACTADO DE ZANJA M 471.20 14.97 7,053.86 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.04 ELIMINACION DE MATERIAL EXCEDENTE
02.04.01 ACARREO INTERNO DE MATERIAL M3 48.55 13.46 653.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.04.02 CARGUIO (ELIM. MAT. EXCEDENTE) M3 48.55 3.92 190.32 0.00 0.00 0.00 48.55 190.32 100.00 48.55 190.32 100.00
02.04.03 TRANSPORTE (ELIM. MAT. EXCEDENTE) M3 48.55 5.70 276.74 0.00 0.00 0.00 48.55 276.74 100.00 48.55 276.74 100.00
03.00 OBRAS DE CONCRETO ARMADO
03.01 CONSTRUCCION DE BUZONES
VALORIZACION DE AVANCE FISICO Nº 02 DICIEMBRE 2009 - II ETAPA
DEL 1/12/2009 AL 30/12/2009
OBRA : "MEJORAMIENTO DE PISTAS Y VEREDAS DE AV. JOSE OLAYA TRAMO : AV. GIRALDEZ - PROLONG. PUNO RESIDENTE : ING. MIRIAM VILLAFUERTE PACHE

CODIGO : 15-036-074-2063804-2164992-190 SUPERVISOR : ING. JORGE CHUCOS DE LA CRU


: PAVIMENTACION FLEXIBLE
CLIENTE : MUNICIPALIDAD PROVINCIAL DE HUANCAYO

Departamento : JUNIN Provincia : HUANCAYO Distrito : HUANCAYO Fecha de Presentacion :01 de Diciembre del 2009
PRESUPUESTO REFERENCIAL AVANCES
ITEM DESCRIPCION Unidad Metrado Precio Parcial ANTERIOR NOVIEMBRE ACTUAL DICIEMBRE ACUMULADO
METRADO VALORIZA. S/. % METRADO VALORIZ. S/. % METRADO VALORIZ. S/. %
03.01.01 CONSTRUCCION DE BUZON H =1..50m UND 4.00 1159.37 4,637.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.01.02 CONSTRUCCION DE BUZON H =1.70m UND 5.00 1,066.12 5,330.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.01.03 DADOS DE CONCRETO F'C= 140KG/CM² UND 18.00 63.27 1,138.86 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.02 ENCIMADO DE BUZONES
03.02.01 CONST. ENCIM.BUZON H= 0.45m. S.M.yTAPA UND 1.00 344.68 344.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.02.02 DADOS DE CONCRETO F'C= 140KG/CM² UND 5.00 63.27 316.35 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.03 SUMIDEROS 0.00
03.03.01 CONSTRUCCION DE SUMIDERO UND 6.00 423.36 2,540.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.03.02 CONSTRUCCION DE CAJA RECEPTOR UND 6.00 60.58 363.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.00 SUMINISTRO Y TENDIDO DE TUBERIA
04.01 TENDIDO DE TUBERIA UPVC U/F S-25 D=12" M 395.00 70.77 27,954.15 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02 TENDIDO DE TUBERIA UPVC U/F S-25 D=10" M 22.20 54.39 1,207.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.03 TENDIDO DE TUBERIA UPVC U/F S-25 D=8" M 54.00 42.40 2,289.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.04 SUMINISTRO Y COLOCACION DE ACCESORIOS UND 6.00 15.35 92.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.00 PRUEBA HIDRAULICA
05.01 PRUEBA A ZANJA TAPADA P/TUBERIA M 471.20 1.17 551.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.00 CARPINTERIA METALICA
06.01 VENTANA DE SUMIDERO 0.70x0.80M UND 6.00 93.49 560.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.02 REJILLA DE CAJA UND 6.00 114.81 688.86 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
COSTO DIRECTO 01 PAVIMENTACION FLEXIBLE 194411.37 5916.05 3.04% 3672.07 1.89% 9588.12 4.93%
COSTO DIRECTO 02 DESAGUE PLUVIAL 71742.04 0.00 0.00% 1166.96 1.63% 1166.96 1.63%
SUB TOTAL 266153.41 5916.05 4839.03 10755.09
GASTOS GENERALES 7% 18630.74 414.12 338.73 752.86
UTILIDADES 5% 13307.67 295.80 241.95 537.75
SUB TOTAL 298091.82 6625.98 5419.72 12045.70
IMPUESTO IGV 19 % 56637.45 1258.94 1029.75 2288.68
TOTAL GENERAL 354729.27 7884.92 2.22% 6449.47 1.82% 14334.38 4.04%

AVANCE FISICO % VALORIZACION S/.


MES ANTER. 2.22% 7884.92
DEL MES 1.82% 6449.47
ACUMULADO 4.04% 14334.38
AM VILLAFUERTE PACHECO

GE CHUCOS DE LA CRUZ

de Diciembre del 2009


SALDO

METRADO VALORIZ. S/. %

0.15 65.68 60.00


0.25 475.53 100.00
0.00 0.00
904.10 786.57 47.48
1504.08 1278.47 78.99
0.00 0.00 0.00

1149.87 5852.84 100.00


46.08 234.09 100.00
34.04 730.16 56.92
18.29 392.32 100.00
25.83 554.05 91.69
4.73 99.52 100.00

100.12 1796.15 74.83


1568.94 5695.25 100.00
1568.94 8942.96 100.00
1421.70 3241.48 100.00

305.70 2268.27 100.00


0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
1165.00 2539.70 100.00

398.08 2949.77 100.00


369.64 1729.92 100.00
369.64 1448.99 100.00
369.64 2106.95 100.00
1421.70 3284.13 100.00

471.44 3493.37 100.00


437.76 2048.72 100.00
437.76 1716.02 100.00
437.76 2495.23 100.00
AM VILLAFUERTE PACHECO

GE CHUCOS DE LA CRUZ

de Diciembre del 2009


SALDO

METRADO VALORIZ. S/. %


1421.70 3298.34 100.00

1097.20 5990.71 100.00


1097.20 57449.39 100.00

45.72 1691.18 100.00


61.23 17231.96 100.00

4.73 1352.21
3.94 145.74 100.00

3.43 1024.23 100.00


6.86 184.26

155.03 4671.05 90.86


23.25 6281.45 90.86
0.00 0.00
459.65 648.11 87.72
459.65 2114.39 87.72
10.42 305.41 82.90
459.65 13449.36 87.72

2.31 73.07 100.00


10.80 322.70 100.00

179.09 351.02 100.00

72.30 2440.85 100.00


241.00 2458.20 100.00
20.00 335.80 100.00

228.62 907.62 100.00


95.70 373.23 100.00
191.00 618.84 100.00
12.00 152.28 100.00
AM VILLAFUERTE PACHECO

GE CHUCOS DE LA CRUZ

de Diciembre del 2009


SALDO

METRADO VALORIZ. S/. %


1.00 384.08 100.00
1.00 358.52 100.00

3.00 1635.48 100.00


2.00 798.06 100.00

6.00 83.94 100.00


6.00 77.76 100.00
0.00 0.00 0.00
6.00 67.86 100.00

2000.00 1320.00 100.00

395.00 221.20 100.00

0.00 0.00 0.00


471.20 7077.42 100.00
7.83 225.11 100.00
471.20 871.72 100.00

471.20 2172.23 100.00

230.89 1475.39 100.00


214.40 733.25 100.00
214.40 891.90 100.00
214.40 1183.49 100.00
471.20 7053.86 100.00

48.55 653.48 100.00


0.00 0.00 0.00
0.00 0.00 0.00
AM VILLAFUERTE PACHECO

GE CHUCOS DE LA CRUZ

de Diciembre del 2009


SALDO

METRADO VALORIZ. S/. %


4.00 4637.48 100.00
5.00 5330.60 100.00
18.00 1138.86 100.00

1.00 344.68 100.00


5.00 316.35 100.00
0.00 0.00
6.00 2540.16 100.00
6.00 363.48 100.00

395.00 27954.15 100.00


22.20 1207.46 100.00
54.00 2289.60 100.00
6.00 92.10 100.00

471.20 551.30 100.00

6.00 560.94 100.00


6.00 688.86 100.00
184823.22 95.07%
70575.08 98.37%
255398.31
17877.88
12769.92
286046.11
54348.76
340394.87 95.96%
VALORIZACION DE AVA

OBRA : "MEJORAMIENTO DE PISTAS Y VEREDAS DE AV. JOSE OLAYA TRAMO : JR. LOS ANGELES -AV. SAN AGUSTIN
CODIGO : 15-036-074-2063804-2164992-190
: PAVIMENTACION FLEXIBLE
CLIENTE : MUNICIPALIDAD PROVINCIAL DE HUANCAYO

Departamento : JUNIN
PRESUPUESTO REFERENCIAL
ITEM DESCRIPCION Unidad Metrado

01.00 OBRAS PROVISIONALES


01.01 ALMACEN Y CASETA DE GUARDIANIA MES 2.50
02.00 OBRAS PRELIMINARES
02.01 TRAZO Y REPLANTEO M2 103.76
02.02 TRAZO Y REPLANTEO DURANTE LA EJECUCION M2 103.76
03.00 EXPLANACIONES
03.01 MOVIMIENTO DE TIERRAS
03.01.01 CORTE DE TERRENO C/MAQUINARIA HASTA S - R M3 62.26
03.01.02 CORTE DE TERRENO MANUAL M3 79.40
03.01.04 EXCAVACION MANUAL PARA CUNETA M3 1.00
03.01.05 EXCAVACION MANUAL PARA SARDINEL M3 3.35
03.01.06 EXCAVACION MANUAL EN BADEN M3 5.38
EXCAVACION MANUAL EN JARDINERIA M3 273.61
03.02 ELIMINACION DE MATERIAL EXCEDENTE
03.02.01 ACARREO INTERNO DE MATERIAL M3 435.28
03.02.02 CARGUIO (ELIM.DE MATERIAL EXCEDENTE) M3 510.00
03.02.03 TRANSPORTE (ELIM. MAT. EXCEDENTE) M3 510.00
03.02.04 ESCARIFICADO PERFILADO/COMPACTADO M2 103.76
04.00 PAVIMENTOS
04.01 MEJORAMIENTO DE SUB RASANTE
04.01.01 EXTRACCION DE MATERIAL P/MEJ. SUB RASANTE M3 29.05
04.01.02 SELECCION DE MATERIAL P/ MEJ DE SUB RASANTE M3 26.98
04.01.03 CARGUIO DE (MEJ. S-R) M3 26.98
04.01.04 TRANSPORTE (MEJ. S-R) M3 26.98
04.01.05 EXT. RIEGO Y COMPC. P/MEJ DE SUB RASANTE M2 103.76
04.02 SUB BASE GRANULAR
04.02.01 EXTRACCION DE MATERIAL PARA SUB BASE M3 29.05
04.02.02 SELECCION DE MATERIAL P/ SUB BASE GRANULAR M3 26.98
04.02.03 CARGUIO DE S-B M3 26.98
04.02.04 TRANSPORTE DE S.B. M3 26.98
04.02.05 EXT. RIEGO Y COMPC. DE SUB BASE E= 0.20m. M2 103.76
04.03 BASE GRANULAR
04.03.01 EXTRACCION DE MATERIAL PARA BASE M3 33.74
04.03.02 SELECCION DE MATERIAL P/ BASE GRANULAR 31.34
04.03.03 CARGUIO DE B. M3 31.34
04.03.04 TRANSPORTE DE B. M3 31.34
04.03.05 EXT. RIEGO Y COMPC. DE BASE E= 0.20m. M2 103.76
04.04 CARPETA ASFALTICA
04.04.01 IMPRIMACION ASFALTICA M2 78.00
04.04.02 CARPETA ASFALTICA EN CALIENTE E= 3" M2 78.00
05.00 DRENAJE
05.01 ENCOFRADO Y DESENCOFRADO DE CUNETAS M2 6.40
05.02 CUNETAS CONCRETO F'C=175 KG/CM2 M3 2.56
06.00 BADEN
06.01 ENCOFRADO Y DESENCOFRADO DE BADEN M2 4.48
06.02 BADEN CONCRETO F'C=210 KG/CM2 M3 5.38
07.00 SARDINEL INEXPUESTO
07.01 SARDINEL INEXP. ENCOFRADO Y DESENCOFRADO M2 1.60
07.02 SARDINEL INEXP. CONCRETO F'C=210 KG/CM2 M3 0.96
09.00 ACERA PEATONAL
09.01 SARDINEL EXPUESTO
09.01.01 SARDINEL EXP. ENCOFRADO Y DESENCOFRADO M2 15.93
09.01.02 SARDINEL EXP. CONCRETO F'C=175 KG/CM2 M3 2.39
09.02 VEREDAS
09.02.01 REFINE Y NIVELACION M2 79.00
09.02.02 RELLENO Y COMPACTADO DE VEREDA M2 79.00
09.02.03 VEREDAS CONCRETO F'C=175 KG/CM2 M2 79.00
09.02.04 VEREDA ENCOFRADO Y DESENCOFRADO M2 1.41
10.00 RAMPAS
10.01 ENCOFRADO Y DESENCOFRADO RAMPA M2 0.77
10.02 RAMPA CONCRETO F'C=175 KG/CM2 M2 3.60
12.00 JUNTAS
12.01 RELLENO DE JUNTAS M 14.06
14.00 SEÑALIZACION
14.01 SEÑALIZACION HORIZONTAL
14.01.01 PINTURA LINEAL EN BORDE DE VIA M 24.40
14.01.02 PINTURA LINEAL CONTINUA EN EJE DE VIA M 12.20
14.01.03 PINTURA LINEAL DISCONTINUA EN EJE DE VIA M 12.20
14.01.04 PINTURA DE SIMBOLOS Y FLECHAS M2 2.00
14.01.05 PINTURA ZONAL CRUCE PEATONAL M2 126.00
17.00 RECONEXIONES
17.01 RECONEXIONES DE PUNTOS DE AGUA PTO 6.00
17.02 RECONEXION DE CAJA MEDIDOR DE AGUA PTO 6.00
14.03 RECONEXION DE INSTALACIONES DE DESAGUE PTO 6.00
14.04 RECONEXION DE CAJA DE REGISTRO DE DESAGUE PTO 6.00

18.00 VARIOS
18.01 LIMPIEZA FINAL DE OBRA M2 103.76
METRADOS ADICIONALES
02.00 MOVIMIENTO DE TIERRAS
02.01 EXCAVACIONES
02.01.01 EXCAVACION PARA BUZONES M3 23.90
02.01.02 EXCAVACION DE ZANJAS - MANUAL M 104.98
02.01.04 REFINE Y NIVELACION EN ZANJAS M 104.98
02.02 CAMAS DE APOYO
02.02.01 PREPARACION DE CAMAS DE APOYO M 104.98
02.03 RELLENOS
02.03.01 EXTRACCION DE MAT. P/RELLENO M3 30.86
02.03.02 SELECCIÓN DE MATERIAL P/RELLENO M3 28.66
02.03.03 CARGUIO P/ RELLENO M3 28.66
02.03.04 TRANSPORTE P/ RELLENO M3 28.66
02.03.05 RELLENO Y COMPACTADO DE ZANJA M 104.98
02.04 ELIMINACION DE MATERIAL EXCEDENTE
02.04.01 ACARREO INTERNO DE MATERIAL M3 28.66
02.04.02 CARGUIO (ELIM. MAT. EXCEDENTE) M3 28.66
02.04.03 TRANSPORTE (ELIM. MAT. EXCEDENTE) M3 28.66
03.00 OBRAS DE CONCRETO ARMADO
03.02 ENCIMADO DE BUZONES
03.02.01 CONST. ENCIM.BUZON H= 0.45m. S.M.yTAPA UND 6.00
04.00 SUMINISTRO Y TENDIDO DE TUBERIA
04.02 TENDIDO DE TUBERIA UPVC U/F S-25 D=8" M 10.00
05.00 PRUEBA HIDRAULICA
05.01 PRUEBA A ZANJA TAPADA P/TUBERIA M 10.00
COSTO DIRECTO 01 PAVIMENTACION FLEXIBLE
COSTO DIRECTO 02 DESAGUE PLUVIAL
SUB TOTAL
IMPUESTO IGV 19 %
TOTAL GENERAL
LORIZACION DE AVANCE FISICO Nº06 POR MAYORES METRADOS DICIEMBRE 2

DEL 01/10/2009 AL 31/10/2009


LOS ANGELES -AV. SAN AGUSTIN

Provincia : HUANCAYO Distrito :


PRESUPUESTO REFERENCIAL AVANCES

Precio Parcial MES NOVIEMBRE MES DICIEMBRE

METRADO VALORIZA. S/. % METRADO VALORIZ. S/.

437.84 1,094.60 2.50 1094.60 100.00 0.85 372.16

0.87 90.27 103.76 90.27 100.00 0.00 0.00


0.85 88.20 103.76 88.20 100.00 0.00 0.00

5.09 316.90 62.26 316.90 100.00 0.00 0.00


21.45 1,703.13 79.40 1703.13 100.00 0.00 0.00
21.45 21.45 1.00 21.45 100.00 0.00 0.00
21.45 71.86 3.35 71.86 100.00 0.00 0.00
21.04 113.20 4.18 87.95 77.70 0.00 0.00
21.45 5,868.93 273.61 5868.93 100.00

17.94 7,808.92 435.28 7808.92 100.00 0.00 0.00


3.63 1,851.30 510.00 1851.30 100.00 0.00 0.00
5.70 2,907.00 510.00 2907.00 100.00 0.00 0.00
2.28 236.57 103.76 236.57 100.00 0.00 0.00

7.42 215.55 29.05 215.55 100.00 0.00 0.00


4.68 126.27 26.98 126.27 100.00 459.00 2148.12
3.83 103.33 26.98 103.33 100.00 439.00 1681.37
5.70 153.79 26.98 153.79 100.00 439.00 2502.30
2.18 226.20 103.76 226.20 100.00 0.00 0.00
0.00
7.41 215.26 29.05 215.26 100.00 0.00 0.00
4.68 126.27 26.98 126.27 100.00 0.00 0.00
3.92 105.76 26.98 105.76 100.00 0.00 0.00
5.70 153.79 26.98 153.79 100.00 0.00 0.00
2.31 239.69 103.76 239.69 100.00 0.00 0.00
0.00
7.41 250.01 33.74 250.01 100.00 0.00 0.00
4.68 146.67 31.34 146.67 100.00 0.00 0.00
3.92 122.85 31.34 122.85 100.00 0.00 0.00
5.70 178.64 31.34 178.64 100.00 0.00 0.00
2.32 240.72 103.76 240.72 100.00 0.00 0.00
0.00
5.46 425.88 0.00 0.00 0.00 0.00 0.00
52.36 4,084.08 0.00 0.00 0.00 0.00 0.00
0.00
36.99 236.74 6.40 236.74 100.00 0.00 0.00
281.43 720.46 2.56 720.46 100.00 0.00 0.00
0.00
36.99 165.72 3.48 128.73 77.68 0.00
285.88 1,538.03 4.18 1194.98 77.70 0.00
0.00 0.00
26.86 42.98 1.60 42.98 100.00 0.00 0.00
298.61 286.67 0.96 286.67 100.00 0.00 0.00
0.00
0.00
30.13 479.97 15.93 479.97 100.00 0.00 0.00
270.17 645.71 2.39 645.71 100.00 0.00 0.00
0.00
1.41 111.39 79.00 111.39 100.00 0.00 0.00
4.60 363.40 79.00 363.40 100.00 0.00 0.00
29.26 2,311.54 79.00 2311.54 100.00 0.00 0.00
29.31 41.33 1.41 41.33 100.00 0.00 0.00
0.00
31.63 24.36 0.77 24.36 100.00 0.00 0.00
29.88 107.57 3.60 107.57 100.00 0.00 0.00
0.00
1.96 27.56 0.00 0.00 0.00 0.00 0.00
0.00
0.00
3.97 96.87 0.00 0.00 0.00 0.00 0.00
3.90 47.58 0.00 0.00 0.00 0.00 0.00
3.24 39.53 0.00 0.00 0.00 0.00 0.00
12.69 25.38 0.00 0.00 0.00 0.00 0.00
21.20 2,671.20 0.00 0.00 0.00 0.00 0.00
0.00
13.99 83.94 6.00 83.94 100.00 0.00 0.00
12.96 77.76 6.00 77.76 100.00 0.00 0.00
17.56 105.36 0.00 0.00 0.00 3.00 52.68
11.31 67.86 0.00 0.00 0.00 0.00 0.00

0.00
0.66 68.48 0.00 0.00 0.00 0.00 0.00

21.45 512.66 23.90 512.66 100.00 2.82 60.49


15.02 1,576.80 104.98 1576.80 100.00 0.00 0.00
1.85 194.21 104.98 194.21 100.00 0.00 0.00

4.61 483.96 104.98 483.96 100.00 0.00 0.00


6.39 197.20 30.86 197.20 100.00 0.00 0.00
3.42 98.02 28.66 98.02 100.00 0.00 0.00
4.16 119.23 28.66 119.23 100.00 0.00 0.00
5.52 158.20 28.66 158.20 100.00 0.00 0.00
14.97 1,571.55 104.98 1571.55 100.00 0.00 0.00

13.46 385.76 28.66 385.76 100.00 0.00 0.00


3.92 112.35 28.66 112.35 100.00 1.45 5.68
5.70 163.36 28.66 163.36 100.00 1.45 8.27

344.68 2,068.08 6.00 2068.08 100.00 0.00 0.00

54.39 543.90 10.00 543.90 100.00 0.00 0.00

1.17 11.70 10.00 11.70 100.00 0.00 0.00


39674.45 31609.38 4.12% 6756.63
8196.99 8196.97 9.72% 74.44
47871.44 39806.35 6831.07
9095.57 7563.21 1297.90
56967.009911 47369.55 4.68% 8128.98

AVANCE FISICO % VALORIZACION S/.


MES NOV. 4.68% 47369.55
MES DIC. 14.27% 8128.98
ACUMULADO 4.79% 48514.50
OS DICIEMBRE 2009

RESIDENTE : ING. MIRIAM VILLAFUERTE PACHECO


SUPERVISOR : ING. YUDITH BACA ARANA

HUANCAYO Fecha de Presentacion :01 de Noviembre del 2009


AVANCES SALDO

S DICIEMBRE ACUMULADO

% METRADO VALORIZ. S/. % METRADO VALORIZ. S/. %

34.00 3.35 1466.76 134.00 -0.85 -372.16 -34.00

0.00 103.76 90.27 100.00 0.00 0.00 0.00


0.00 103.76 88.20 100.00 0.00 0.00 0.00

0.00 62.26 316.90 100.00 0.00 0.00 0.00


0.00 79.40 1703.13 100.00 0.00 0.00 0.00
0.00 1.00 21.45 100.00 0.00 0.00 0.00
0.00 3.35 71.86 100.00 0.00 0.00 0.00
0.00 4.18 87.95 77.70 1.20 25.25 22.30

0.00 435.28 7808.92 100.00 0.00 0.00 0.00


0.00 510.00 1851.30 100.00 0.00 0.00 0.00
0.00 510.00 2907.00 100.00 0.00 0.00 0.00
0.00 103.76 236.57 100.00 0.00 0.00 0.00

0.00 29.05 215.55 100.00 0.00 0.00 0.00


1701.26 485.98 2274.39 1801.26 -459.00 -2148.12 -1701.26
1627.13 465.98 1784.70 1727.13 -439.00 -1681.37 -1627.13
1627.13 465.98 2656.09 1727.13 -439.00 -2502.30 -1627.13
0.00 103.76 226.20 100.00 0.00 0.00 0.00

0.00 29.05 215.26 100.00 0.00 0.00 0.00


0.00 26.98 126.27 100.00 0.00 0.00 0.00
0.00 26.98 105.76 100.00 0.00 0.00 0.00
0.00 26.98 153.79 100.00 0.00 0.00 0.00
0.00 103.76 239.69 100.00 0.00 0.00 0.00

0.00 33.74 250.01 100.00 0.00 0.00 0.00


0.00 31.34 146.67 100.00 0.00 0.00 0.00
0.00 31.34 122.85 100.00 0.00 0.00 0.00
0.00 31.34 178.64 100.00 0.00 0.00 0.00
0.00 103.76 240.72 100.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 78.00 425.88 100.00
0.00 0.00 0.00 0.00 78.00 4084.08 100.00

0.00 6.40 236.74 100.00 0.00 0.00 0.00


0.00 2.56 720.46 100.00 0.00 0.00 0.00

0.00 3.48 128.73 77.68 1.00 36.99 22.32


0.00 4.18 1194.98 77.70 1.20 343.06 22.30
0.00
0.00 1.60 42.98 100.00 0.00 0.00 0.00
0.00 0.96 286.67 100.00 0.00 0.00 0.00

0.00 15.93 479.97 100.00 0.00 0.00 0.00


0.00 2.39 645.71 100.00 0.00 0.00 0.00

0.00 79.00 111.39 100.00 0.00 0.00 0.00


0.00 79.00 363.40 100.00 0.00 0.00 0.00
0.00 79.00 2311.54 100.00 0.00 0.00 0.00
0.00 1.41 41.33 100.00 0.00 0.00 0.00

0.00 0.77 24.36 100.00 0.00 0.00 0.00


0.00 3.60 107.57 100.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 14.06 27.56 100.00

0.00 0.00 0.00 0.00 24.40 96.87 100.00


0.00 0.00 0.00 0.00 12.20 47.58 100.00
0.00 0.00 0.00 0.00 12.20 39.53 100.00
0.00 0.00 0.00 0.00 2.00 25.38 100.00
0.00 0.00 0.00 0.00 126.00 2671.20 100.00

0.00 6.00 83.94 100.00 0.00 0.00 0.00


0.00 6.00 77.76 100.00 0.00 0.00 0.00
50.00 3.00 52.68 50.00 3.00 52.68 50.00
0.00 0.00 0.00 0.00 6.00 67.86 100.00

0.00 0.00 0.00 0.00 103.76 68.48 100.00

11.80 26.72 573.14 111.80 -2.82 -60.49 -11.80


0.00 104.98 1576.80 100.00 0.00 0.00 0.00
0.00 104.98 194.21 100.00 0.00 0.00 0.00

0.00 104.98 483.96 100.00 0.00 0.00 0.00


0.00 30.86 197.20 100.00 0.00 0.00 0.00
0.00 28.66 98.02 100.00 0.00 0.00 0.00
0.00 28.66 119.23 100.00 0.00 0.00 0.00
0.00 28.66 158.20 100.00 0.00 0.00 0.00
0.00 104.98 1571.55 100.00 0.00 0.00 0.00

0.00 28.66 385.76 100.00 0.00 0.00 0.00


5.06 30.11 118.03 105.06 -1.45 -5.68 -5.06
5.06 30.11 171.63 105.06 -1.45 -8.27 -5.06

0.00 6.00 2068.08 100.00 0.00 0.00 0.00

0.00 10.00 543.90 100.00 0.00 0.00 0.00

0.00 10.00 11.70 100.00 0.00 0.00 0.00


0.88% 32497.08 4.24% 1308.45 0.17%
0.09% 8271.41 9.81% -74.44 -0.09%
40768.49 1234.01
7746.01 234.46
0.80% 48514.50 4.79% 1468.47 0.14%
766762.558
84295.5848
851058.143
161701.047
1012759.19
RIZACION DE AVANCE FISICO Nº 01 ALINEAMIENTO ENERO 2010 - II ETAPA
DEL 02/01/2010 AL 16/01/2010
OBRA : "MEJORAMIENTO DE PISTAS Y VEREDAS DE AV. JOSE OLAYA TRAMO : AV. GIRALDEZ - PROLONG. PUNO
CODIGO : 15-036-074-2063804-2164992-190

CLIENTE : MUNICIPALIDAD PROVINCIAL DE HUANCAYO

Departamento : JUNIN Provincia :


PRESUPUESTO REFERENCIAL
ITEM DESCRIPCION Unidad Metrado Precio Parcial

02.00 OBRAS PRELIMINARES


02.01 TRAZO Y REPLANTEO M2 1,904.10 0.87 1,656.57
02.02 TRAZO Y REPLANTEO DURANTE LA EJECUCION M2 1,904.08 0.85 1,618.47
02.03 ROTURA DE VEREDAS M3 0.48 42.58 20.44
03.00 EXPLANACIONES
03.01 MOVIMIENTO DE TIERRAS
03.01.01 CORTE DE TERRENO DE SUB RASANTE M3 1,149.87 5.09 5,852.84
03.01.02 CORTE PARA MEJORAM. DE SUB BASE M3 46.08 5.08 234.09
03.01.03 CORTE DE TERRENO MANUAL M3 59.80 21.45 1,282.71
03.01.04 EXCAVACION MANUAL PARA CUNETA M3 18.29 21.45 392.32
03.01.05 EXCAVACION MANUAL PARA SARDINEL M3 28.17 21.45 604.25
03.01.06 EXCAVACION MANUAL EN BADEN M3 4.73 21.04 99.52
03.02 ELIMINACION DE MATERIAL EXCEDENTE
03.02.01 ACARREO INTERNO DE MATERIAL M3 133.80 17.94 2,400.37
03.02.02 CARGUIO (ELIM.DE MATERIAL EXCEDENTE) M3 1,568.94 3.63 5,695.25
03.02.03 TRANSPORTE (ELIM. MAT. EXCEDENTE) M3 1,568.94 5.70 8,942.96
03.02.04 ESCARIFICADO PERFILADO/COMPACTADO M2 1,421.70 2.28 3,241.48
04.00 PAVIMENTOS
04.01 MEJORAMIENTO DE SUB RASANTE
04.01.01 EXTRACCION DE MATERIAL P/MEJ. SUB RASANTE M3 305.70 7.42 2,268.27
04.01.02 SELECCION DE MATERIAL P/ MEJ DE SUB RASANTE M3 251.00 4.68 1,174.68
04.01.03 CARGUIO DE (MEJ. S-R) M3 251.00 3.83 961.33
04.01.04 TRANSPORTE (MEJ. S-R) M3 251.00 5.70 1,430.70
04.01.05 EXT. RIEGO Y COMPC. P/MEJ DE SUB RASANTE M2 1,165.00 2.18 2,539.70
04.02 SUB BASE GRANULAR
04.02.01 EXTRACCION DE MATERIAL PARA SUB BASE M3 398.08 7.41 2,949.77
04.02.02 SELECCION DE MATERIAL P/ SUB BASE GRANULAR M3 369.64 4.68 1,729.92
04.02.03 CARGUIO DE S-B M3 369.64 3.92 1,448.99
04.02.04 TRANSPORTE DE S.B. M3 369.64 5.70 2,106.95
04.02.05 EXT. RIEGO Y COMPC. DE SUB BASE E= 0.20m. M2 1,421.70 2.31 3,284.13
04.03 BASE GRANULAR
04.03.01 EXTRACCION DE MATERIAL PARA BASE M3 471.44 7.41 3,493.37
04.03.02 SELECCION DE MATERIAL P/ BASE GRANULAR M3 437.76 4.68 2,048.72
04.03.03 CARGUIO DE B. M3 437.76 3.92 1,716.02
04.03.04 TRANSPORTE DE B. M3 437.76 5.70 2,495.23
04.03.05 EXT. RIEGO Y COMPC. DE BASE E= 0.20m. M2 1,421.70 2.32 3,298.34
04.04 CARPETA ASFALTICA
04.04.01 IMPRIMACION ASFALTICA M2 1,097.20 5.46 5,990.71
04.04.02 CARPETA ASFALTICA EN CALIENTE E= 3" M2 1,097.20 52.36 57,449.39
05.00 DRENAJE
05.01 ENCOFRADO Y DESENCOFRADO DE CUNETAS M2 45.72 36.99 1,691.18
05.02 CUNETAS CONCRETO F'C=175 KG/CM2 M3 61.23 281.43 17,231.96
06.00 BADEN
06.01 BADEN CONCRETO F'C=210 KG/CM2 M3 4.73 285.88 1,352.21
06.02 BADEN ENCOFRADO Y DESENCOFRADO M2 3.94 36.99 145.74
07.00 SARDINEL INEXPUESTO
07.01 SARDINEL INEXP. CONCRETO F'C=210 KG/CM2 M3 3.43 298.61 1,024.23
07.02 SARDINEL INEXP. ENCOFRADO Y DESENCOFRADO M2 6.86 26.86 184.26
08.00 ACERA PEATONAL
08.01 SARDINEL EXPUESTO
08.01.01 SARDINEL EXP. ENCOFRADO Y DESENCOFRADO M2 170.63 30.13 5,141.08
08.01.02 SARDINEL EXP. CONCRETO F'C=175 KG/CM2 M3 25.59 270.17 6,913.65
VEREDAS
08.02.01 REFINE Y NIVELACION M2 524.00 1.41 738.84
08.02.02 RELLENO Y COMPACTADO DE VEREDA M2 524.00 4.60 2,410.40
08.02.03 VEREDA ENCOFRADO Y DESENCOFRADO M2 12.57 29.31 368.43
08.02.04 VEREDAS CONCRETO F'C=175 KG/CM2 M2 524.00 29.26 15,332.24
9.00 RAMPAS
9.01 ENCOFRADO Y DESENCOFRADO RAMPA M2 2.31 31.63 73.07
9.02 RAMPA CONCRETO F'C=175 KG/CM2 M2 10.80 29.88 322.70
10.00 JUNTAS
10.01 RELLENO DE JUNTAS M 179.09 1.96 351.02
11.00 AREAS VERDES
11.01 SUMINISTRO DE TIERRA AGRICOLA M3 72.30 33.76 2,440.85
11.02 COLOCACION DE GRASS M2 241.00 10.20 2,458.20
11.03 COLOCACION DE PLANTONES UND 20.00 16.79 335.80
12.00 SEÑALIZACION
12.01 SEÑALIZACION HORIZONTAL
12.01.01 PINTURA LINEAL EN BORDE DE VIA M 228.62 3.97 907.62
12.01.02 PINTURA LINEAL CONTINUA EN EJE DE VIA M 95.70 3.90 373.23
12.01.03 PINTURA LINEAL DISCONTINUA EN EJE DE VIA M 191.00 3.24 618.84
12.01.04 PINTURA DE SIMBOLOS Y FLECHAS M2 12.00 12.69 152.28
12.02 SEÑALIZACION VERTICAL
12.02.01 SEÑALES TIPO R (90cM x 60cm) UND 1.00 384.08 384.08
12.02.02 SEÑALES TIPO F UND 1.00 358.52 358.52
13.00 EQUIPAMIENTO
13.01 MOVILIARIO URBANO UND 3.00 545.16 1,635.48
13.02 SUMINISTRO Y COLOCACION DE TACHOS DE BASURA UND 2.00 399.03 798.06
14.00 RECONEXIONES
14.01 RECONEXIONES DE PUNTOS DE AGUA PTO 6.00 13.99 83.94
14.02 RECONEXION DE CAJA MEDIDOR DE AGUA PTO 6.00 12.96 77.76
14.03 RECONEXION DE INSTALACIONES DE DESAGUE PTO 6.00 17.56 105.36
14.04 RECONEXION DE CAJA DE REGISTRO DE DESAGUE PTO 6.00 11.31 67.86
15.00 VARIOS
15.01 LIMPIEZA FINAL DE OBRA M2 2,000.00 0.66 1,320.00
DESAGUE PLUVIAL
01.00 TRABAJOS PRELIMINARES
01.01 TRAZO NIVELES Y REPLANTEO DE ZANJA M 395.00 0.56 221.20
02.00 MOVIMIENTO DE TIERRAS
02.01 EXCAVACIONES
02.01.01 EXCAVACION PARA BUZONES M3 32.63 21.45 699.91
02.01.02 EXCAVACION DE ZANJAS - MANUAL M 471.20 15.02 7,077.42
02.01.03 EXCAVACION PARA SUMIDEROS M3 7.83 28.75 225.11
02.01.04 REFINE Y NIVELACION EN ZANJAS M 471.20 1.85 871.72
02.02 CAMAS DE APOYO
02.02.01 PREPARACION DE CAMAS DE APOYO M 471.20 4.61 2,172.23
02.03 RELLENOS
02.03.01 EXTRACCION DE MAT. P/RELLENO M3 230.89 6.39 1,475.39
02.03.02 SELECCIÓN DE MATERIAL P/RELLENO M3 214.40 3.42 733.25
02.03.03 CARGUIO P/ RELLENO M3 214.40 4.16 891.90
02.03.04 TRANSPORTE P/ RELLENO M3 214.40 5.52 1,183.49
02.03.05 RELLENO Y COMPACTADO DE ZANJA M 471.20 14.97 7,053.86
02.04 ELIMINACION DE MATERIAL EXCEDENTE
02.04.01 ACARREO INTERNO DE MATERIAL M3 48.55 13.46 653.48
02.04.02 CARGUIO (ELIM. MAT. EXCEDENTE) M3 48.55 3.92 190.32
02.04.03 TRANSPORTE (ELIM. MAT. EXCEDENTE) M3 48.55 5.70 276.74
03.00 OBRAS DE CONCRETO ARMADO
03.01 CONSTRUCCION DE BUZONES
03.01.01 CONSTRUCCION DE BUZON H =1..50m UND 4.00 1159.37 4,637.48
03.01.02 CONSTRUCCION DE BUZON H =1.70m UND 5.00 1,066.12 5,330.60
03.01.03 DADOS DE CONCRETO F'C= 140KG/CM² UND 18.00 63.27 1,138.86
03.02 ENCIMADO DE BUZONES
03.02.01 CONST. ENCIM.BUZON H= 0.45m. S.M.yTAPA UND 1.00 344.68 344.68
03.02.02 DADOS DE CONCRETO F'C= 140KG/CM² UND 5.00 63.27 316.35
03.03 SUMIDEROS
03.03.01 CONSTRUCCION DE SUMIDERO UND 6.00 423.36 2,540.16
03.03.02 CONSTRUCCION DE CAJA RECEPTOR UND 6.00 60.58 363.48
04.00 SUMINISTRO Y TENDIDO DE TUBERIA
04.01 TENDIDO DE TUBERIA UPVC U/F S-25 D=12" M 395.00 70.77 27,954.15
04.02 TENDIDO DE TUBERIA UPVC U/F S-25 D=10" M 22.20 54.39 1,207.46
04.03 TENDIDO DE TUBERIA UPVC U/F S-25 D=8" M 54.00 42.40 2,289.60
04.04 SUMINISTRO Y COLOCACION DE ACCESORIOS UND 6.00 15.35 92.10
05.00 PRUEBA HIDRAULICA
05.01 PRUEBA A ZANJA TAPADA P/TUBERIA M 471.20 1.17 551.30
06.00 CARPINTERIA METALICA
06.01 VENTANA DE SUMIDERO 0.70x0.80M UND 6.00 93.49 560.94
06.02 REJILLA DE CAJA UND 6.00 114.81 688.86
: AV. GIRALDEZ - PROLONG. PUNO
AVANCE FISICO DIARIO DE OBRA DICIEM
OBRA: MEJORAMIENTO PISTA Y VEREDAS AV. JOSE OLAYA TRAMO: (PROLONG. PUNO - AV. GIRALDEZ)
PAVIMENTO

TERRENO MANUAL
IDENTIFICAC. DE

C/MAQUINARIA

MANUAL PARA
PARTIDA

GUARDIANIA.

DURANTE LA

EXCAVACION
REPLANTEO

REPLANTEO

HASTA S - R
ALMACEN Y

ROTURA DE
EJECUCION
CARTEL DE
CASETA DE

MEJORAM.
C/MAQUIN.
CORTE DE
CORTE DE

CORTE DE
TERRENO

TERRENO
VEREDAS
TRAZO Y

TRAZO Y

CUNETA
OBRA
FECHA 01.01 1.02 02.01 02.02 02.03 03.01.01 03.01.02 03.01.03 03.01.04

12/1/2009 0.03
12/2/2009 0.03 1.03
12/3/2009 0.03 5.45
12/4/2009 0.03
12/5/2009 0.03 10.20
12/6/2009 0.03
12/7/2009 0.03 100.00
12/8/2009 0.03
12/9/2009 0.03
12/10/2009 0.03
12/11/2009 0.03
12/12/2009 0.03
12/13/2009 0.03
12/14/2009 0.03 153.00
12/15/2009 0.03
12/16/2009 0.03
12/17/2009 0.03 409.60 46.08
12/18/2009 0.03
12/19/2009 0.03
12/20/2009 0.03
12/21/2009 0.03
12/22/2009 0.03
12/23/2009 0.03
12/24/2009 0.03
12/25/2009 0.03
12/26/2009 0.03
12/27/2009 0.03
12/28/2009 0.03
12/29/2009 0.03 120.00
12/30/2009 0.03
12/31/2009 0.03

EJECUTADO DEL MES 1.00 0.00 0.00 0.00 0.00 792.80 46.08 6.48 0.00
EJEC. ANTERIOR 0.10 0.00 1000.00 400.00 0.48 0.00 0.00 25.76 0.00
EJEC. ACUMULADO 1.10 0.00 1000.00 400.00 0.48 792.80 46.08 32.24 0.00
PROGRAMADO 0.25 0.25 1904.10 1904.08 0.48 1149.87 46.08 59.80 18.29
SALDO -0.85 0.25 904.10 1504.08 0.00 357.07 0.00 27.56 18.29
O DE OBRA DICIEMBRE - 2009
AV. GIRALDEZ)
PAVIMENTO

CARGUIO DE (MEJ.
DE SUB RASANTE
MATERIAL P/ MEJ
(ELIMINACION DE

MATERIAL P/MEJ.
EXTRACCION DE
ESCARIFICADO

SELECCION DE
MANUAL PARA

SUB RASANTE
COMPACTADO
TRANSPORTE
EXCAVACION

EXCAVACION

EXCEDENTE)

EXCEDENTE)
INTERNO DE

PERFILADO/
MANUAL EN

(ELIM. MAT.
SARDINEL

MATERIAL

MATERIAL
ACARREO

CARGUIO
BADEN

S-R)
03.01.05 03.01.06 03.02.01 03.02.02 03.02.03 03.02.04 04.01.01 04.01.02 04.01.03

2.88 4.70
1.98 8.92
30.00
12.24

260.00 260.00

50.00

120.00 120.00

1168.00

120.00 120.00

210.00 210.00
240.00

180.00 180.00

120.00 120 150.00 150.00


28.00 120.00 120.00

4.86 0.00 53.86 620.00 620.00 1168.00 240.00 710.00 690.00


0.00 0.00 30.87 0.00 0.00 0.00 0.00 0.00 0.00
4.86 0.00 84.73 620.00 620.00 1168.00 240.00 710.00 690.00
28.17 4.73 133.80 1568.94 1568.94 1421.70 64.51 545.77 545.77
23.31 4.73 49.07 948.94 948.94 253.70 -175.49 -164.23 -144.23
AVANCE FISICO DIARIO DE OBRA DICI
OBRA: MEJORAMIENTO PISTA Y VEREDAS AV. JOSE OLAYA TRAMO: (AV. GIRALDEZ - PROLONGACION PUNO)
PAVIMENTO

CARGUIO DE S-B
COMPC. P/MEJ DE

BASE E= 0.20m.
BASE GRANULAR
MATERIAL P/ SUB

TRANSPORTE DE
EXTRACCION DE

EXTRACCION DE
MATERIAL PARA

MATERIAL PARA
COMPC. DE SUB
SELECCION DE
SUB RASANTE
PARTIDA

TRANSPORTE

EXT. RIEGO Y

EXT. RIEGO Y
SUB BASE
(MEJ. S-R)

BASE
S.B.
FECHA 04.01.04 04.01.05 04.02.01 04.02.02 04.02.03 04.02.04 04.02.05 04.03.01

12/1/2009
12/2/2009
12/3/2009
12/4/2009 30.00
12/5/2009
12/6/2009
12/7/2009
12/8/2009
12/9/2009
12/10/2009
12/11/2009
12/12/2009
12/13/2009
12/14/2009
12/15/2009
12/16/2009
12/17/2009
12/18/2009
12/19/2009 120.00
12/20/2009
12/21/2009 210.00
12/22/2009
12/23/2009 350.00
12/24/2009
12/25/2009
12/26/2009 180.00
12/27/2009
12/28/2009 150.00
12/29/2009
12/30/2009
12/31/2009

EJECUTADO DEL MES 690.00 0.00 350.00 0.00 0.00 0.00 0.00 0.00
EJEC. ANTERIOR 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
EJEC. ACUMULADO 690.00 0.00 350.00 0.00 0.00 0.00 0.00 0.00
PROGRAMADO 545.77 64.51 398.08 369.64 369.64 369.64 1421.70 471.44
-144.23 64.51 48.08 369.64 369.64 369.64 1421.70 471.44
AVANCE FISICO DIARIO DE OBRA NOV
OBRA: MEJORAMIENTO PISTA Y VEREDAS AV. JOSE OLAYA TRAMO: (JR. LOS ANGELES - AV. SAN AGUSTIN)
PAVIMENTO

EXT. RIEGO Y COMPC. DE SUB BASE


EXTRACCION DE MATERIAL PARA

EXTRACCION DE MATERIAL PARA


SELECCION DE MATERIAL P/ SUB
EXT. RIEGO Y COMPC. P/MEJ DE
TRANSPORTE (MEJ. S-R)

PARTIDA

TRANSPORTE DE S.B.
CARGUIO DE S-B
BASE GRANULAR
SUB RASANTE

E= 0.20m.
SUB BASE

BASE
FECHA 04.01.04 04.01.05 04.02.01 04.02.02 04.02.03 04.02.04 04.02.05 04.03.01

11/23/2009
11/24/2009
11/25/2009
11/26/2009
11/27/2009
11/28/2009
11/29/2009
11/30/2009

EJECUTADO DEL MES 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
EJEC. ANTERIOR 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
EJEC. ACUMULADO 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
PROGRAMADO 545.77 64.51 398.08 369.64 369.64 369.64 1421.70 471.44
545.77 64.51 398.08 369.64 369.64 369.64 1421.70 471.44
RIO DE OBRA DICIEMBRE - 2009
OLONGACION PUNO)
PAVIMENTO

BADEN CONCRETO
CONCRETO F'C=175
BASE GRANULAR

COMPC. DE BASE
TRANSPORTE DE

E=

DESENCOF. DE
DESENCOF. DE
CARGUIO DE B.
SELECCION DE

ENCOFRADO Y

ENCOFRADO Y
ASFALTICA EN
IMPRIMACION

F'C=210 KG/CM2
EXT. RIEGO Y
MATERIAL P/

ASFALTICA

CALIENTE
CARPETA

CUNETAS

CUNETAS
E= 0.20m.

BADEN
KG/CM2
3"
B.

04.03.02 04.03.03 04.03.04 04.03.05 04.04.01 04.04.02 05.01 05.02 6.01 6.02

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
437.76 437.76 437.76 1421.70 1097.20 1097.20 45.72 61.23 4.73 3.94
437.76 437.76 437.76 1421.70 1097.20 1097.20 45.72 61.23 4.73 3.94
IO DE OBRA NOVIEMBRE - 2009
AV. SAN AGUSTIN)
PAVIMENTO

CUNETAS CONCRETO F'C=175 KG/CM2


SELECCION DE MATERIAL P/ BASE

CARPETA ASFALTICA EN CALIENTE


EXT. RIEGO Y COMPC. DE BASE E=

BADEN CONCRETO F'C=210 KG/CM2


ENCOFRADO Y DESENCOF. DE

ENCOFRADO Y DESENCOF. DE
IMPRIMACION ASFALTICA
TRANSPORTE DE B.
CARGUIO DE B.
GRANULAR

CUNETAS
E= 3"

BADEN
0.20m.

04.03.02 04.03.03 04.03.04 04.03.05 04.04.01 04.04.02 05.01 05.02 6.01 6.02

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
437.76 437.76 437.76 1421.70 1097.20 1097.20 45.72 61.23 4.73 3.94
437.76 437.76 437.76 1421.70 1097.20 1097.20 45.72 61.23 4.73 3.94
AVANCE FISICO DIARIO DE OBRA DICIEMB
OBRA: MEJORAMIENTO PISTA Y VEREDAS AV. JOSE OLAYA TRAMO: (PROLONG. PUNO - AV. GIRALDEZ)

CONCRETO F'C=210

CONCRETO F'C=175
CONCRETO F'C=175

COMPACTADO DE
SARDINEL INEXP.

INEXP.ENCOF. Y

SARDINEL EXP.

SARDINEL EXP.
ENCOFRADO Y

ENCOFRADO Y
PARTIDA

NIVELACION
DESENCOF.

DESENCOF.
RELLENO Y
DESENCOF
SARDINEL

VEREDAS
REFINE Y

VEREDA
VEREDA
KG/CM2

KG/CM2

KG/CM2
FECHA 07.01 07.02 08.01.01 08.01.02 08.02.01 08.02.02 08.02.03 08.02.04

12/1/2009
12/2/2009 19.20 2.88 80.48 80.48 2.64 80.48
12/3/2009
12/4/2009 13.20 1.98 54.45 54.45 1.82 54.45
12/5/2009 68.70
12/6/2009
12/7/2009 9.60 1.44 54.00 54.00 1.32 3.96
12/8/2009
12/9/2009 48.00 48.00
12/10/2009
12/11/2009
12/12/2009
12/13/2009
12/14/2009
12/15/2009
12/16/2009
12/17/2009
12/18/2009
12/19/2009
12/20/2009
12/21/2009
12/22/2009
12/23/2009
12/24/2009
12/25/2009
12/26/2009
12/27/2009
12/28/2009
12/29/2009
12/30/2009
12/31/2009

EJECUTADO DEL MES 0.00 0.00 42.00 6.30 236.93 305.63 5.78 138.89
0.00 0.00 0.00 15.60 2.34 64.35 64.35 64.35 2.15
EJEC. ACUMULADO 0.00 0.00 57.60 8.64 301.28 369.98 70.13 141.04
PROGRAMADO 3.43 6.86 170.63 25.59 524.00 524.00 12.57 524.00
3.43 6.86 113.03 16.95 222.72 154.02 -57.56 382.96

FALTA VERE 80.6


AVANCE FISICO DIARIO DE OBRA NOVIEMB
OBRA: MEJORAMIENTO PISTA Y VEREDAS AV. JOSE OLAYA TRAMO: (PROLONG. PUNO - AV. GIRALDEZ)

SARDINEL INEXP. CONCRETO F'C=210

VEREDAS CONCRETO F'C=175 KG/CM2

VEREDA ENCOFRADO Y DESENCOF.


SARDINEL EXP. CONCRETO F'C=175
SARDINEL EXP. ENCOFRADO Y

RELLENO Y COMPACTADO DE
SARDINEL INEXP.ENCOF. Y
PARTIDA

REFINE Y NIVELACION
DESENCOF.
DESENCOF

VEREDA
KG/CM2

KG/CM2
FECHA 07.01 07.02 08.01.01 08.01.02 08.02.01 08.02.02 08.02.03 08.02.04

11/23/2009
11/24/2009
11/25/2009
11/26/2009
11/27/2009
11/28/2009
11/29/2009
11/30/2009

EJECUTADO DEL MES 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
EJEC. ACUMULADO 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
PROGRAMADO 3.43 6.86 170.63 25.59 524.00 524.00 12.57 524.00
3.43 6.86 170.63 25.59 524.00 524.00 12.57 524.00
DE OBRA DICIEMBRE - 2009
AV. GIRALDEZ) RAMPA CONCRETO

TIERRA AGRICOLA

CONTINUA EN EJE
EN BORDE DE VIA

DISCONTINUA EN
COLOCACION DE

COLOCACION DE
DESENCOFRADO

PINTURA LINEAL

PINTURA LINEAL

PINTURA LINEAL
SUMINISTRO DE
ENCOFRADO Y

F'C=175 KG/CM2

RELLENO DE

PLANTONES

EJE DE VIA
JUNTAS
RAMPA

GRASS

DE VIA
9.01 9.02 10.01 11.01 11.02 11.03 12.01.01 12.01.02 12.01.03

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2.31 10.80 179.09 72.30 241.00 20.00 228.62 95.70 191.00
2.31 10.80 179.09 72.30 241.00 20.00 228.62 95.70 191.00
DE OBRA NOVIEMBRE - 2009
AV. GIRALDEZ)

PINTURA LINEAL CONTINUA EN EJE


SUMINISTRO DE TIERRA AGRICOLA

PINTURA LINEAL EN BORDE DE VIA

PINTURA LINEAL DISCONTINUA EN


RAMPA CONCRETO F'C=175 KG/CM2
ENCOFRADO Y DESENCOFRADO

COLOCACION DE PLANTONES
COLOCACION DE GRASS
RELLENO DE JUNTAS

EJE DE VIA
RAMPA

DE VIA
9.01 19.02 10.01 11.01 11.02 11.03 12.01.01 12.01.02 12.01.03

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2.31 10.80 179.09 72.30 241.00 20.00 228.62 95.70 191.00
2.31 10.80 179.09 72.30 241.00 20.00 228.62 95.70 191.00
AVANCE FISICO DIARIO DE OBRA DICIEMBR
OBRA: MEJORAMIENTO PISTA Y VEREDAS AV. JOSE OLAYA TRAMO: (PROLONG. PUNO - AV. GIRALDEZ)
PAVIMENTO

(90cM x 60cm)

CAJA MEDIDOR DE
COLOCACION DE

RECONEXION DE

RECONEXION DE

RECONEXION DE
SEÑALES TIPO R

SEÑALES TIPO F

INSTALACIONES
RECONEXIONES
DE PUNTOS DE
SUMINISTRO Y
PARTIDA

REGISTRO DE
DE DESAGUE
SIMBOLOS Y
PINTURA DE

MOVILIARIO

TACHOS DE

DESAGUE
FLECHAS

URBANO

CAJA DE
BASURA

AGUA

AGUA
FECHA 12.01.04 12.02.01 12.02.02 13.01 13.02 14.01 14.02 14.03 14.04

12/1/2009 3.00 3.00 4.00 4.00


12/2/2009
12/3/2009
12/4/2009
12/5/2009
12/6/2009
12/7/2009
12/8/2009
12/9/2009
12/10/2009
12/11/2009 2.00 2.00
12/12/2009
12/13/2009
12/14/2009
12/15/2009
12/16/2009
12/17/2009
12/18/2009 3.00
12/19/2009
12/20/2009
12/21/2009
12/22/2009 2.00 2.00
12/23/2009
12/24/2009
12/25/2009
12/26/2009
12/27/2009
12/28/2009
12/29/2009
12/30/2009
12/31/2009

EJECUTADO DEL MES 0.00 0.00 0.00 0.00 0.00 5.00 5.00 9.00 6.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
EJEC. ACUMULADO 0.00 0.00 0.00 0.00 0.00 5.00 5.00 9.00 6.00
PROGRAMADO 12.00 1.00 1.00 3.00 2.00 6.00 6.00 6.00 6.00
12.00 1.00 1.00 3.00 2.00 1.00 1.00 -3.00 0.00
AVANCE FISICO DIARIO DE OBRA NOVIEMBR
OBRA: MEJORAMIENTO PISTA Y VEREDAS AV. JOSE OLAYA TRAMO: (JR. LOS ANGELES - AV. SAN AGUSTIN)
PAVIMENTO

PINTURA DE SIMBOLOS Y FLECHAS

RECONEXION DE INSTALACIONES
RECONEXION DE CAJA MEDIDOR
(90cM x

SUMINISTRO Y COLOCACION DE

RECONEXIONES DE PUNTOS DE

RECONEXION DE CAJA DE
REGISTRO DE DESAGUE
PARTIDA

MOVILIARIO URBANO

TACHOS DE BASURA
SEÑALES TIPO R

SEÑALES TIPO F

DE DESAGUE
DE AGUA
AGUA
60cm)

FECHA 12.01.04 12.02.01 12.02.03 13.01 13.02 14.01 14.02 14.03 14.04

11/23/2009
11/24/2009
11/25/2009
11/26/2009
11/27/2009
11/28/2009
11/29/2009
11/30/2009

EJECUTADO DEL MES 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
EJEC. ACUMULADO 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
PROGRAMADO 12.00 1.00 1.00 3.00 2.00 6.00 6.00 6.00 6.00
12.00 1.00 1.00 3.00 2.00 6.00 6.00 6.00 6.00
OBRA DICIEMBRE - 2009
GIRALDEZ) OBRA: MEJORAMIENTO PISTA Y VERE
DESAGUE PLUVIAL

EXCAVACION PARA

EXCAVACION PARA
LIMPIEZA FINAL DE

ZANJAS - MANUAL

CAMAS DE APOYO
PREPARACION DE
TRAZO NIVELES Y

EXCAVACION DE

NIVELACION EN
REPLANTEO DE

PARTIDA

SUMIDEROS
BUZONES

REFINE Y

ZANJAS
ZANJA
OBRA

15.01 01.01 02.01.01 02.01.02 02.01.03 02.01.04 02.02.01 FECHA


12/1/2009
12/2/2009
12/3/2009
12/4/2009
12/5/2009
12/6/2009
12/7/2009
12/8/2009
60.00 2.12 30.00 12/9/2009
62.00 25.00 12/10/2009
50.00 12/11/2009
9.60 12/12/2009
12/13/2009
60.00 69.6 12/14/2009
10.00 12/15/2009
25.00 50.00 12/16/2009
54.00 12/17/2009
12/18/2009
12/19/2009
12/20/2009
72.00 1.18 36.00 12/21/2009
41.00 3.00 12/22/2009
73.30 0.7 31.65 72.00 12/23/2009
36.65 12/24/2009
12/25/2009
4.95 12/26/2009
12/27/2009
44.70 22.35 73.30 73.30 12/28/2009
72.00 72.00 12/29/2009
30.00 15.20 12/30/2009
10.00 4.15 47.50 12/31/2009

0.00 352.00 35.45 357.60 0.00 327.30 271.90 EJECUTADO DEL MES
0.00 0.00 0.00 0.00 0.00 0.00 0.00 EJEC. ANTERIOR
0.00 352.00 35.45 357.60 0.00 327.30 271.90 EJEC. ACUMULADO
2000.00 395.00 32.63 471.20 7.83 471.20 471.20 PROGRAMADO
2000.00 43.00 -2.82 113.60 7.83 143.90 199.30
OBRA NOVIEMBRE - 2009
SAN AGUSTIN) OBRA: MEJORAMIENTO PISTA Y VERE
DESAGUE PLUVIAL

EXCAVACION DE ZANJAS - MANUAL


TRAZO NIVELES Y REPLANTEO DE

REFINE Y NIVELACION EN ZANJAS


EXCAVACION PARA SUMIDEROS
EXCAVACION PARA BUZONES

PREPARACION DE CAMAS DE
LIMPIEZA FINAL DE OBRA

PARTIDA

APOYO
ZANJA

15.01 01.01 02.01.01 02.01.02 02.01.03 02.01.04 02.02.01 FECHA


11/23/2009
11/24/2009
11/25/2009
11/26/2009
11/27/2009
11/28/2009
11/29/2009
11/30/2009

0.00 0.00 0.00 0.00 0.00 0.00 0.00 EJECUTADO DEL MES
0.00 0.00 0.00 0.00 0.00 0.00 0.00 EJEC. ANTERIOR
0.00 0.00 0.00 0.00 0.00 0.00 0.00 EJEC. ACUMULADO
2000.00 395.00 32.63 471.20 7.83 471.20 471.20 PROGRAMADO
2000.00 395.00 32.63 471.20 7.83 471.20 471.20
AVANCE FISICO DIARIO DE OBRA DICIEMBRE - 2009
JORAMIENTO PISTA Y VEREDAS AV. JOSE OLAYA TRAMO: (PROLONG. PUNO - AV. GIRALDEZ)
DESAGUE PLUVIAL

MAT. EXCEDENTE)
COMPACTADO DE
EXTRACCION DE
MAT. P/RELLENO

CONSTRUCCION
CONSTRUCCION
TRANSPORTE P/

CARGUIO (ELIM.
SELECCIÓN DE

H =1.70m
H =1.500m
TRANSPORTE

EXCEDENTE)
INTERNO DE
CARGUIO P/
P/RELLENO

RELLENO Y

(ELIM. MAT.

DE BUZON

DE BUZON
MATERIAL

MATERIAL
ACARREO
RELLENO

RELLENO

ZANJA
02.03.01 02.03.02 02.03.03 02.03.04 02.03.05 02.04.01 02.04.02 02.04.03 03.01.01 03.01.02

45.00 45.00 45.00

69.60 2.00
15.00 15.00 15.00 0.75

36.00
50.00

30.00 30.00 30.00


3.00

48.55 50.00 50.00 0.75

30 30.00 30.00

30 30 30
36.7
36.00 0.6

0.00 150.00 150.00 150.00 231.30 48.55 50.00 50.00 1.50 2.60
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 150.00 150.00 150.00 231.30 48.55 50.00 50.00 1.50 2.60
230.89 214.40 214.40 214.40 471.20 48.55 48.55 48.55 4.00 5.00
230.89 64.40 64.40 64.40 239.90 0.00 -1.45 -1.45 2.50 2.40
AVANCE FISICO DIARIO DE OBRA NOVIEMBRE- 2009
JORAMIENTO PISTA Y VEREDAS AV. JOSE OLAYA TRAMO: (JR. LOS ANGELES - AV. SAN AGUSTIN)
DESAGUE PLUVIAL

CARGUIO (ELIM. MAT. EXCEDENTE)


ACARREO INTERNO DE MATERIAL
EXTRACCION DE MAT. P/RELLENO

RELLENO Y COMPACTADO DE

CONSTRUCCION DE BUZON

CONSTRUCCION DE BUZON
TRANSPORTE P/ RELLENO
SELECCIÓN DE MATERIAL

TRANSPORTE (ELIM. MAT.


CARGUIO P/ RELLENO

H =1.70m
H =1.500m
EXCEDENTE)
P/RELLENO

ZANJA

02.03.01 02.03.02 02.03.03 02.03.04 02.03.05 02.04.01 02.04.02 02.04.03 03.01.01 03.01.02

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
230.89 214.40 214.40 214.40 471.20 48.55 48.55 48.55 4.00 5.00
230.89 214.40 214.40 214.40 471.20 48.55 48.55 48.55 4.00 5.00
IEMBRE - 2009 AVANCE FISICO DIARIO DE OBRA DIC

VIAL DESA

TUBERIA UPVC U/F

TUBERIA UPVC U/F


ENCIMADO BUZON

CAJA RECEPTOR
CONSTRUC. DE

CONSTRUC. DE
CONCRETO F'C=

CONCRETO F'C=
PARTIDA

S-25 D=10"
S-25 D=12"
TENDIDO DE

TENDIDO DE
CONSTRUC.

SUMIDERO
140KG/CM²

140KG/CM²
DADOS DE

DADOS DE
S.M.yTAPA
H= 0.45m.

03.01.03 03.02.01 03.02.02 03.03.01 03.03.02 04.01 FECHA 04.02

12/1/2009
12/2/2009
12/3/2009
12/4/2009
12/5/2009
12/6/2009
2.00 3.6 12/7/2009
12/8/2009
12/9/2009
12/10/2009
12/11/2009
12/12/2009
12/13/2009
69.6 12/14/2009
3.00 12/15/2009
1.00 12/16/2009
54.00 12/17/2009
12/18/2009
12/19/2009
12/20/2009
12/21/2009
3.00 12/22/2009
12/23/2009
12/24/2009
12/25/2009
12/26/2009
12/27/2009
73.30 12/28/2009
72.00 12/29/2009
3 12/30/2009
12/31/2009

7.00 0.00 2.00 0.00 0.00 275.50 EJECUTADO DEL MES 0.00
0.00 0.00 0.00 0.00 0.00 0.00 EJEC. ANTERIOR 0.00
7.00 0.00 2.00 0.00 0.00 275.50 EJEC. ACUMULADO 0.00
18.00 1.00 5.00 6.00 6.00 395.00 PROGRAMADO 22.20
11.00 1.00 3.00 6.00 6.00 119.50 22.20
VIEMBRE- 2009 AVANCE FISICO DIARIO DE OBRA NO
)
VIAL DESA
CONSTRUC. ENCIMADO BUZON H=

CONSTRUC. DE CAJA RECEPTOR

TENDIDO DE TUBERIA UPVC U/F

TENDIDO DE TUBERIA UPVC U/F


CONSTRUC. DE SUMIDERO
DADOS DE CONCRETO F'C=

DADOS DE CONCRETO F'C=

PARTIDA
0.45m. S.M.yTAPA
140KG/CM²

140KG/CM²

S-25 D=12"

S-25 D=10"
03.01.03 03.02.01 03.02.02 03.03.01 03.03.02 04.01 FECHA 04.02

11/23/2009
11/24/2009
11/25/2009
11/26/2009
11/27/2009
11/28/2009
11/29/2009
11/30/2009

0.00 0.00 0.00 0.00 0.00 0.00 EJECUTADO DEL MES 0.00
0.00 0.00 0.00 0.00 0.00 0.00 EJEC. ANTERIOR 0.00
0.00 0.00 0.00 0.00 0.00 0.00 EJEC. ACUMULADO 0.00
18.00 1.00 5.00 6.00 6.00 395.00 PROGRAMADO 22.20
18.00 1.00 5.00 6.00 6.00 395.00 22.20
DIARIO DE OBRA DICIEMBRE-2009

DESAGUE PLUVIAL
TUBERIA UPVC U/F

REJILLA DE CAJA
PRUEBA A ZANJA
COLOCACION DE
SUMINISTRO Y

ACCESORIOS

VENTANA DE
TENDIDO DE

S-25 D=8"

P/TUBERIA

SUMIDERO
0.70x0.80M
TAPADA

04.03 04.04 05.01 06.01 06.02

0.00 0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
54.00 6.00 471.20 6.00 6.00
54.00 6.00 471.20 6.00 6.00
DIARIO DE OBRA NOVIEMBRE- 2009

DESAGUE PLUVIAL

VENTANA DE SUMIDERO 0.70x0.80M


SUMINISTRO Y COLOCACION DE
TENDIDO DE TUBERIA UPVC U/F

PRUEBA A ZANJA TAPADA

REJILLA DE CAJA
ACCESORIOS

P/TUBERIA
S-25 D=8"

04.03 04.04 05.01 06.01 06.02

0.00 0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
54.00 6.00 471.20 6.00 6.00
54.00 6.00 471.20 6.00 6.00

Potrebbero piacerti anche