600 BPM Individual Equipment shipment schedule:

Eqquipment Name OEM Shipment Date Reached at CTG port Reached at Site FAT Remarks

Krones Block with Krones-Germany 04.01.18 09.02.18 24.02.18 Done-Vedio Confirmed


Mixprocessor & Labeller Avilable
Warmer Jieh-Hong-Taiwan 05.01.18 23.01.18 12.02.18 Done Confirmed
Done-Vedio
Pack conveyor Beeta-India 25.12.18 25.01.18 05.02.18 Confirmed
Avilable
Done-Vedio
S/Wrapping SMI-Italy 31.12.17 04.02.18 19.02.18 Confirmed
Avilable
Palletizer SIPA-Italy 10.01.18 20.02.18 05.03.18 Done Confirmed
HP Compressor AF-Belgium 29.12.117 10.02.18 24.02.18 Done Confirmed
LP Compressor Compare-England 07.01.18 08.02.18 22.02.18 Done Confirmed
Beverages Chiller Trane-France 08.12.17 18.01.18 04.02.18 Done Confirmed

300 BPM HF PET Line Individual Equipment shipment schedule:

Eqquipment Name OEM Shipment Date Reached at CTG port Reached at Site FAT Remarks
Name of Company : Transcom Bevarage Limited
Plant Location : Bagherbazar, Joydevpur, Gazipur

Work Schdule of 600 BPM CSD Pet Line + 300 BPM HF Line Incliding Approx. Budget
A. 600 BPM Line Appliances
Eqquipment Name Starting Ending Approx. cost to
Date Date excute
each specified
Job

Krones Block (Blow Moulding+ Filler)


Unloading M/C & Placed as actual location 24.02.18 100000
BlowMoulding Chiller unloading & Placed as per Drawing 25.02.18 25.02.18 100000
Chilled Water Supply & Return Line C/W insulation for Blow Moulding Chiller 26.02.18 08.03.18
HP Air Line 750000
26.02.18 05.03.18
LP air Line for (Filler +Mix Processor+Labeller+ Plalletiser) 1125000
26.02.18 08.03.18
Co2 Pipe Line for Filler+ Mix Processor 26.02.18 03.02.18 500000
Steel Structure of New AHU-10000 CFM 01.03.18 15.03.18 437292
10000 CFM AHU Installation 16.03.18 16.03.18 50000
Ducting C/W Insulation for Supply Cooling Air 01.03.18 15.03.18 1080000
Refrigeration Piping for New AHU 01.03.18 15.03.18 750000
Air Terminal Installation both for HF & Blow Moulding Room 16.03.18 16.03.18 115200
Mixprocessor of Krones 24.02.18
Unloading M/C & Placed as actual location
25.02.18 25.02.18 100000
Chilled Water Piping Work (Supply+ Return) C/ W insulation of Mix Processor 26.02.18 5.03.018 750000
Cooling Water Pipe Line for Vaccum Pump 26.02.18 18.03.18 125000
SS Piping Line from Syrup Tank to Mix Processor 26.02.18 05.03.18 300000
CIP Piping line from Filler to Syrup Tank 26.02.18 07.03.18 300000
Beverages Chiller
Bevarage Chiller Foundation Base
Unloading M/C & Placed at actual location 05.02.18 05.02.18 100000
Cooling Tower Foundation Base 06.02.18 06.02.18
Cooling Tower installation for Bevarage Chiller including piping to chiller 07.02.18 14.02.18 300000
Make Up Water Piping for Cooling Tower 15.02.18 17.02.18 250000
Interconnecting Pipe Line in between Pump & Chiller 08.02.18 24.02.18 1545150
Buffer Tank 25.01.18 15.02.18 1000000
HP Compressor

Unloading M/C & Placed at actual location 24.02.18 75000


Cooling Tower Base
Cooling Tower Installation 25.02.18 28.05.18 30000
Supply & Return Line from Cooling Tower 26.02.18 08.03.18 2500000
LP Compressor
Unloading M/C & Placed at actual location 23.02.18 23.02.18
Interconnecting Pipe Line in between compressor,drier and header 24.02.18 28.02.18 100000
Warmer
Unloading M/C & Placed at actual location 12.02.18 30000
Steam Line from Boiler Header to Warmer 12.02.18 22.02.18 150000
Cholorine Line to warmer 15.02.18
15.02.18 225000
Labeller 24.02.18
Unloading M/C & Placed at actual location 25.02.18 25.02.18 50000
S/Wrapping
19.02.18
Unloading M/C & Placed at actual location 20.02.18 20.02.18 50000
Palletizer 05.03.18 05.03.18
Unloading M/C & Placed at actual location 05.03.18 05.03.18 50000
Modification Work
Modification Work of Syrup System 18.02.18 10.03.18 500000
Modification Work of CIP System 15.02.18 22.02.18
200000
Modification Work of WTP System 07.02.18 28.02.18
B. Utility Appliances
Bore Well
3000000
Boiler
Boiler Foundation Base

Unloading M/C & Placed at actual location 01.02.18 100000


Diesel Oil Piping from storage tank to boiler burner 02.02.18 08.02.18 300000
Inetrconnecting pipe line in between Feed Water Tank, Softener & Boiler 02.02.18 08.02.18 200000
Diesel Generator
Connecting Pipe Line 22.01.18 30.01.18 150000
Supply & Febrication Chimney 25.01.18 10.02.18
Ductng Work for removing exhaust air from radiator 300000
01.02.18 01.02.18
Diesel Tank + Diesel Tank Platform 1000000
03.01.18 1000000
B. 300 BPM HF Line Appliances

RFC & S/Sleeve 25.03.18


Unloading M/C & Placed as actual location 26.03.18 26.03.18 100000
Warmer Modification 25.04.18 15.05.18 500000
Syrup system 02.03.18
Unloading M/C & Placed as actual location 03.03.18 03.03.18
Utility Line like Water, Air & steam 04.03.18 25.03.18 3000000
Homoginizer 05.03.18
Unloading M/C & Placed as actual location 05.03.18 05.03.18 50000
Utility Line 06.03.18 20.03.18 750000
Pasturizer
Unloading M/C & Placed as actual location
Utility Line 1000000
Safety Sector
Fire Protection System 6000000