Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Adaption as per Standard School Building Plans Duly Approved by DPWH-CO Approved Budget by C
P
(13) Equipment to be u
(12) Technical Personnel Required: Con
1 - Civil Engineer
1 - Construction Foreman
10 - Mason
8 - Carpenter
25 - Labor Drill
Truc
SPT
UNIT TOTAL
PRICE AMOUNT
3,414.70 6,829.40
12,761.40 127,614.00
60,999.52 60,999.52
5,995.22 107,913.96
78,248.10 78,248.10
21.37 53,272.80
1,077.46 52,623.03
1,080.74 194,047.01
2,936.27 5,725,721.12
9,299.59 11,623,422.38
403.80 12,083.75
500.00 2,866.48
1,407.28 752,139.39
1,366.09 2,285,160.02
110.77 1,873,001.56
1,123,241.60 1,123,241.60
286.31 572,474.49
154.24 14,806.60
163.63 12,566.60
296.06 35,526.60
375.41 27,404.60
59.04 1,771.32
55.04 1,981.32
87.72 1,578.88
98.06 784.44
47.36 852.44
55.51 1,776.44
65.04 780.44
66.36 1,194.44
170.09 2,041.10
215.15 1,290.88
85.04 2,040.88
105.06 1,680.88
390.07 4,680.88
610.44 2,441.76
248.39 4,471.10
422.79 3,805.10
625.15 11,252.64
275.22 3,302.64
440.44 2,642.64
142.11 3,410.64
288.17 5,186.97
595.66 2,382.64
195.15 3,512.64
400.44 2,402.64
320.15 5,762.64
385.14 9,243.30
470.17 11,283.96
115.07 2,071.32
149.11 1,789.32
140.04 5,041.32
270.17 3,241.98
320.97 4,172.64
394.26 3,942.64
127.09 3,812.64
8,889.58 151,122.80
937.01 16,866.16
790.44 1,580.88
962.21 28,866.16
184.73 16,625.72
846.97 197,093.82
5,049.34 287,812.33
928.29 23,782.71
1,398.29 95,139.45
341.70 21,526.92
482.70 10,619.34
472.17 59,492.80
656.05 608,298.79
1,029.23 534,784.26
971.88 188,269.31
56.33 96,348.84
313.89 692,823.85
217.26 913,959.13
136.07 24,493.20
156.85 7,842.64
207.09 3,727.65
12.43 1,305.66
37.14 1,262.88
16.68 900.66
22.02 528.44
81.08 648.66
25.12 3,391.76
33.33 1,299.88
45.03 180.11
5.18 2,281.32
118.09 1,180.88
150.15 900.88
43.16 4,531.76
42.69 5,762.64
118.09 590.44
3,273.77 49,106.60
4,085.68 30,642.60
7,303.67 13,146.60
178.43 3,211.76
205.04 9,841.76
410.29 2,461.76
151.72 5,461.76
207.37 9,331.76
7,802.20 7,802.20
910.87 153,026.40
735.92 8,831.00
4,870.18 317,048.52
29,475,345.99
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
Bureau : Plans/Design Section
Region : Caraga - Region XIII
District/City : Agusan del Sur
INDIVIDUAL PROGRAM OF WORK
cy 2017 beff-batch3, completion of sbp Date:
5) Name/Location of Project: (7) Source of Funds :
CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
UNDER BASIC EDUCATIONAL FACILITIES FUND (BEFF) - BATCH 3
@ Agusan del Sur National High School, San Francisco, Agusan del Sur
Site/Location 1
(10) Project Description: (11) Calendar Days to C
(11-a) Original Project A
(11-b) Buffer Fund Req
Additional Foundati
Adaption as per Standard School Building Plans Duly Approved by DPWH-CO Approved Budget by C
P
(13) Equipment to be u
(12) Technical Personnel Required: Con
1 - Civil Engineer
1 - Construction Foreman
10 - Mason
8 - Carpenter
25 - Labor Drill
Truc
SPT
UNIT TOTAL
PRICE AMOUNT
3,414.70 6,829.40
12,761.40 127,614.00
60,999.52 60,999.52
5,995.22 107,913.96
78,248.10 78,248.10
21.37 53,272.80
1,077.46 52,623.03
1,080.74 194,047.01
2,936.27 5,725,721.12
9,299.59 11,623,422.38
403.80 12,083.75
500.00 2,866.48
1,407.28 752,139.39
1,366.09 2,285,160.02
110.77 1,873,001.56
1,123,241.60 1,123,241.60
286.31 572,474.49
154.24 14,806.60
163.63 12,566.60
296.06 35,526.60
375.41 27,404.60
59.04 1,771.32
55.04 1,981.32
87.72 1,578.88
98.06 784.44
47.36 852.44
55.51 1,776.44
65.04 780.44
66.36 1,194.44
170.09 2,041.10
215.15 1,290.88
85.04 2,040.88
105.06 1,680.88
390.07 4,680.88
610.44 2,441.76
248.39 4,471.10
422.79 3,805.10
625.15 11,252.64
275.22 3,302.64
440.44 2,642.64
142.11 3,410.64
288.17 5,186.97
595.66 2,382.64
195.15 3,512.64
400.44 2,402.64
320.15 5,762.64
385.14 9,243.30
470.17 11,283.96
115.07 2,071.32
149.11 1,789.32
140.04 5,041.32
270.17 3,241.98
320.97 4,172.64
394.26 3,942.64
127.09 3,812.64
8,889.58 151,122.80
937.01 16,866.16
790.44 1,580.88
962.21 28,866.16
184.73 16,625.72
846.97 197,093.82
5,049.34 287,812.33
928.29 23,782.71
1,398.29 95,139.45
341.70 21,526.92
482.70 10,619.34
472.17 59,492.80
656.05 608,298.79
1,029.23 534,784.26
971.88 188,269.31
56.33 96,348.84
313.89 692,823.85
217.26 913,959.13
136.07 24,493.20
156.85 7,842.64
207.09 3,727.65
12.43 1,305.66
37.14 1,262.88
16.68 900.66
22.02 528.44
81.08 648.66
25.12 3,391.76
33.33 1,299.88
45.03 180.11
5.18 2,281.32
118.09 1,180.88
150.15 900.88
43.16 4,531.76
42.69 5,762.64
118.09 590.44
3,273.77 49,106.60
4,085.68 30,642.60
7,303.67 13,146.60
178.43 3,211.76
205.04 9,841.76
410.29 2,461.76
151.72 5,461.76
207.37 9,331.76
7,802.20 7,802.20
910.87 153,026.40
735.92 8,831.00
4,870.18 317,048.52
29,475,345.99
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
Bureau : Plans/Design Section
Region : Caraga - Region XIII
District/City : Agusan del Sur
INDIVIDUAL PROGRAM OF WORK
cy 2017 beff-batch3, completion of sbp Date:
5) Name/Location of Project: (7) Source of Funds :
CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
UNDER BASIC EDUCATIONAL FACILITIES FUND (BEFF) - BATCH 3
@ Agusan del Sur National High School, San Francisco, Agusan del Sur
Site/Location 2
(10) Project Description: (11) Calendar Days to C
(11-a) Appropriation:
(11-b) Buffer Fund Req
Additional Foundati
Adaption as per Standard School Building Plans Duly Approved by DPWH-CO Approved Budget by C
PH
(13) Equipment to be u
(12) Technical Personnel Required: Concr
1 - Civil Engineer C
1 - Construction Foreman
10 - Mason
8- Carpenter
25 - Labor Drill R
Truck
SPT &
UNIT TOTAL
PRICE AMOUNT
3,414.70 6,829.40
12,761.40 127,614.00
60,999.52 60,999.52
5,995.22 107,913.96
78,248.10 78,248.10
21.37 53,272.80
1,077.46 52,623.03
1,080.74 194,047.01
2,936.27 5,725,721.12
9,299.59 11,623,422.38
403.80 12,083.75
500.00 2,866.48
1,407.28 752,139.39
1,366.09 2,285,160.02
110.77 1,873,001.56
1,123,241.60 1,123,241.60
286.31 572,474.49
154.24 14,806.60
163.63 12,566.60
296.06 35,526.60
375.41 27,404.60
59.04 1,771.32
55.04 1,981.32
87.72 1,578.88
98.06 784.44
47.36 852.44
55.51 1,776.44
65.04 780.44
66.36 1,194.44
170.09 2,041.10
215.15 1,290.88
85.04 2,040.88
105.06 1,680.88
390.07 4,680.88
610.44 2,441.76
248.39 4,471.10
422.79 3,805.10
625.15 11,252.64
275.22 3,302.64
440.44 2,642.64
142.11 3,410.64
288.17 5,186.97
595.66 2,382.64
195.15 3,512.64
400.44 2,402.64
320.15 5,762.64
385.14 9,243.30
470.17 11,283.96
115.07 2,071.32
149.11 1,789.32
140.04 5,041.32
270.17 3,241.98
320.97 4,172.64
394.26 3,942.64
127.09 3,812.64
8,889.58 151,122.80
937.01 16,866.16
790.44 1,580.88
962.21 28,866.16
184.73 16,625.72
846.97 197,093.82
5,049.34 287,812.33
928.29 23,782.71
1,398.29 95,139.45
341.70 21,526.92
482.70 10,619.34
472.17 59,492.80
656.05 608,298.79
1,029.23 534,784.26
971.88 188,269.31
56.33 96,348.84
313.89 692,823.85
217.26 913,959.13
136.07 24,493.20
156.85 7,842.64
207.09 3,727.65
12.43 1,305.66
37.14 1,262.88
16.68 900.66
22.02 528.44
81.08 648.66
25.12 3,391.76
33.33 1,299.88
45.03 180.11
5.18 2,281.32
118.09 1,180.88
150.15 900.88
43.16 4,531.76
42.69 5,762.64
118.09 590.44
3,273.77 49,106.60
4,085.68 30,642.60
7,303.67 13,146.60
178.43 3,211.76
205.04 9,841.76
410.29 2,461.76
151.72 5,461.76
207.37 9,331.76
7,802.20 7,802.20
910.87 153,026.40
735.92 8,831.00
4,870.18 317,048.52
29,475,345.99
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
Bureau : Plans/Design Section
Region : Caraga - Region XIII
District/City : Agusan del Sur
INDIVIDUAL PROGRAM OF WORK
cy 2017 beff-batch3, completion of sbp Date:
5) Name/Location of Project: (7) Source of Funds :
CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
UNDER BASIC EDUCATIONAL FACILITIES FUND (BEFF) - BATCH 3
@ Agusan del Sur National High School, San Francisco, Agusan del Sur
Site/Location 3
(10) Project Description: (11) Calendar Days to C
(11-a) Appropriation:
(11-b) Buffer Fund Req
Additional Foundati
Adaption as per Standard School Building Plans Duly Approved by DPWH-CO Approved Budget by C
PH
(13) Equipment to be u
(12) Technical Personnel Required: Concr
1 - Civil Engineer C
1 - Construction Foreman
10 - Mason
8- Carpenter
25 - Labor Drill R
Truck
SPT &
UNIT TOTAL
PRICE AMOUNT
3,414.70 6,829.40
12,761.40 127,614.00
60,999.52 60,999.52
5,995.22 107,913.96
78,248.10 78,248.10
21.37 53,272.80
1,077.46 52,623.03
1,080.74 194,047.01
2,936.27 5,725,721.12
9,299.59 11,623,422.38
403.80 12,083.75
500.00 2,866.48
1,407.28 752,139.39
1,366.09 2,285,160.02
110.77 1,873,001.56
1,123,241.60 1,123,241.60
286.31 572,474.49
154.24 14,806.60
163.63 12,566.60
296.06 35,526.60
375.41 27,404.60
59.04 1,771.32
55.04 1,981.32
87.72 1,578.88
98.06 784.44
47.36 852.44
55.51 1,776.44
65.04 780.44
66.36 1,194.44
170.09 2,041.10
215.15 1,290.88
85.04 2,040.88
105.06 1,680.88
390.07 4,680.88
610.44 2,441.76
248.39 4,471.10
422.79 3,805.10
625.15 11,252.64
275.22 3,302.64
440.44 2,642.64
142.11 3,410.64
288.17 5,186.97
595.66 2,382.64
195.15 3,512.64
400.44 2,402.64
320.15 5,762.64
385.14 9,243.30
470.17 11,283.96
115.07 2,071.32
149.11 1,789.32
140.04 5,041.32
270.17 3,241.98
320.97 4,172.64
394.26 3,942.64
127.09 3,812.64
8,889.58 151,122.80
937.01 16,866.16
790.44 1,580.88
962.21 28,866.16
184.73 16,625.72
846.97 197,093.82
5,049.34 287,812.33
928.29 23,782.71
1,398.29 95,139.45
341.70 21,526.92
482.70 10,619.34
472.17 59,492.80
656.05 608,298.79
1,029.23 534,784.26
971.88 188,269.31
56.33 96,348.84
313.89 692,823.85
217.26 913,959.13
136.07 24,493.20
156.85 7,842.64
207.09 3,727.65
12.43 1,305.66
37.14 1,262.88
16.68 900.66
22.02 528.44
81.08 648.66
25.12 3,391.76
33.33 1,299.88
45.03 180.11
5.18 2,281.32
118.09 1,180.88
150.15 900.88
43.16 4,531.76
42.69 5,762.64
118.09 590.44
3,273.77 49,106.60
4,085.68 30,642.60
7,303.67 13,146.60
178.43 3,211.76
205.04 9,841.76
410.29 2,461.76
151.72 5,461.76
207.37 9,331.76
7,802.20 7,802.20
910.87 153,026.40
735.92 8,831.00
4,870.18 317,048.52
29,475,345.99
BREAKDOWN OF ESTIMATED EXPENDITURES % OF TOTAL
(15) I. ESTIMATED CONTRACT COST
B. ESTIMATED DIRECT COST
1 Mobilization / Demobilization 0.18
2. Materials 60.55
1.1 Supply/Delivery
3. Labor 12.06
2.1 Direct Cost
2.2 Leaves
2.3 Medicare
2.4 State Insurance
C. INDIRECT COST:
2. Profit 4.23
60,999.52
21,098,500.08
4,201,403.22
4,114,443.16
1,760,454.16
1,473,767.30
1,635,478.37
34,345,045.81
348,434.81
150,000.00
498,434.81
34,843,480.62
Superintendent
PHP 6,503,230.62
BREAKDOWN OF ESTIMATED EXPENDITURES % OF TOTAL
(15) I. ESTIMATED CONTRACT COST
B. ESTIMATED DIRECT COST
1 Mobilization / Demobilization 0.18
2. Materials 60.55
1.1 Supply/Delivery
3. Labor 12.06
2.1 Direct Cost
2.2 Leaves
2.3 Medicare
2.4 State Insurance
C. INDIRECT COST:
2. Profit 4.23
60,999.52
21,098,500.08
4,201,403.22
4,114,443.16
1,760,454.16
1,473,767.30
1,635,478.37
34,345,045.81
348,434.81
150,000.00
498,434.81
34,843,480.62
Superintendent
PHP 6,503,230.62
BREAKDOWN OF ESTIMATED EXPENDITURES % OF TOTAL
(15) I. ESTIMATED CONTRACT COST
B. ESTIMATED DIRECT COST
1 Mobilization / Demobilization 0.18
2. Materials 60.55
1.1 Supply/Delivery
3. Labor 12.06
2.1 Direct Cost
2.2 Leaves
2.3 Medicare
2.4 State Insurance
C. INDIRECT COST:
2. Profit 4.23
60,999.52
21,098,500.08
4,201,403.22
4,114,443.16
1,760,454.16
1,473,767.30
1,635,478.37
34,345,045.81
348,434.81
150,000.00
498,434.81
34,843,480.62
Superintendent
#REF!
BREAKDOWN OF ESTIMATED EXPENDITURES % OF TOTAL
(15) I. ESTIMATED CONTRACT COST
B. ESTIMATED DIRECT COST
1 Mobilization / Demobilization 0.18
2. Materials 60.55
1.1 Supply/Delivery
3. Labor 12.06
2.1 Direct Cost
2.2 Leaves
2.3 Medicare
2.4 State Insurance
C. INDIRECT COST:
2. Profit 4.23
60,999.52
21,098,500.08
4,201,403.22
4,114,443.16
1,760,454.16
1,473,767.30
1,635,478.37
34,345,045.81
348,434.81
150,000.00
498,434.81
34,843,480.62
PHP 6,503,230.62
BREAKDOWN OF ESTIMATED EXPENDITURES % OF TOTAL
(15) I. ESTIMATED CONTRACT COST
B. ESTIMATED DIRECT COST
1 Mobilization / Demobilization 0.18
2. Materials 60.55
1.1 Supply/Delivery
3. Labor 12.06
2.1 Direct Cost
2.2 Leaves
2.3 Medicare
2.4 State Insurance
C. INDIRECT COST:
2. Profit 4.23
60,999.52
21,098,500.08
4,201,403.22
4,114,443.16
1,760,454.16
1,473,767.30
1,635,478.37
34,345,045.81
348,434.81
150,000.00
498,434.81
34,843,480.62
PHP 6,503,230.62
BREAKDOWN OF ESTIMATED EXPENDITURES % OF TOTAL
(15) I. ESTIMATED CONTRACT COST
B. ESTIMATED DIRECT COST
1 Mobilization / Demobilization 0.18
2. Materials 60.55
1.1 Supply/Delivery
3. Labor 12.06
2.1 Direct Cost
2.2 Leaves
2.3 Medicare
2.4 State Insurance
C. INDIRECT COST:
2. Profit 4.23
60,999.52
21,098,500.08
4,201,403.22
4,114,443.16
1,760,454.16
1,473,767.30
1,635,478.37
34,345,045.81
348,434.81
150,000.00
498,434.81
34,843,480.62
#REF!
APPROVED BUDGET FOR THE CONTRACT
CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
UNDER BASIC EDUCATIONAL FACILITIES FUND (BEFF) - BATCH 3
@ Agusan del Sur National High School, San Francisco, Agusan del Sur
Site/Location 1
MARK-UP IN % TOTAL MARK - UP
ESTIMATED
SCOPE OF WORKS % UNIT QTY. UNIT PRICE
DIRECT COST PRO
OCM %
FIT
Item 1002(6) b3 PPR-C Pipes 0.01% piece 12.00 149.11 1,789.32 6.00% 5.00% 11.00%
Item 1002(6) b4 PPR-C Pipes 0.02% piece 36.00 140.04 5,041.32 6.00% 5.00% 11.00%
Item 1002(6) c2 PPR-C Pipes 0.01% piece 12.00 270.17 3,241.98 6.00% 5.00% 11.00%
Item 1002(7) c3 PPR-C Pipes 0.01% piece 13.00 320.97 4,172.64 6.00% 5.00% 11.00%
Item 1002(6) c4 PPR-C Pipes 0.01% piece 10.00 394.26 3,942.64 6.00% 5.00% 11.00%
Item 1002(6) g2 PPR-C Pipes 0.01% piece 30.00 127.09 3,812.64 6.00% 5.00% 11.00%
Item 1002(2) - Plumbing Fixtures 0.51% set 17.00 8,889.58 151,122.80 6.00% 5.00% 11.00%
Item 1004(2) a - Rough Hardwares 0.06% set 18.00 937.01 16,866.16 6.00% 5.00% 11.00%
Item 1004(2) d - Finishing Hardwares 0.01% set 2.00 790.44 1,580.88 6.00% 5.00% 11.00%
Item 1004(2) e - Finishing Hardwares 0.10% set 30.00 962.21 28,866.16 6.00% 5.00% 11.00%
Item 1004(2) g - Finishing Hardwares 0.06% set 90.00 184.73 16,625.72 6.00% 5.00% 11.00%
Item 1009(1) a - Jalousie Windows (Jalouplus eqiuv.) 0.67% sq mt 232.70 846.97 197,093.82 6.00% 5.00% 11.00%
Item 1010(1) - Frames 0.98% set 57.00 5,049.34 287,812.33 6.00% 5.00% 11.00%
Item 1010(2) a - Doors 0.08% sq. mts. 25.62 928.29 23,782.71 6.00% 5.00% 11.00%
Item 1010(2) b - Doors 0.32% sq. mts. 68.04 1,398.29 95,139.45 6.00% 5.00% 11.00%
Item 1013(2) a - Fabricated Metal Roofing Accessory 0.07% ln mt 63.00 341.70 21,526.92 6.00% 5.00% 11.00%
Item 1013(2) b - Fabricated Metal Roofing Accessory 0.04% ln mt 22.00 482.70 10,619.34 6.00% 5.00% 11.00%
Item 1013(2) c - Fabricated Metal Roofing Accessory 0.20% ln mts 126.00 472.17 59,492.80 6.00% 5.00% 11.00%
Item 1014(1) a1 - Prepainted Metal Sheets 2.06% sq mt 927.21 656.05 608,298.79 6.00% 5.00% 11.00%
Item 1018(1) - Glazed Tiles and Trims 1.81% sq mt. 519.60 1,029.23 534,784.26 6.00% 5.00% 11.00%
Item 1018(2) - UnGlazed Tiles 0.64% sq mt. 193.72 971.88 188,269.31 6.00% 5.00% 11.00%
Item 1021(1)a - Cement Floor Finish 0.33% sq.mt 1,710.45 56.33 96,348.84 6.00% 5.00% 11.00%
Item 1027(1) - Cement Plaster Finish 2.35% sq.mt 2,207.24 313.89 692,823.85 6.00% 5.00% 11.00%
Item 1032(1) - Painting Works 3.10% sq.mt 4,206.74 217.26 913,959.13 6.00% 5.00% 11.00%
D Electrical
Item 1100(1) a2 - Rigid Steel Conduit (RSC) 0.08% length 180.00 136.07 24,493.20 6.00% 5.00% 11.00%
Item 1100(1) a3 - Rigid Steel Conduit (RSC) 0.03% length 50.00 156.85 7,842.64 6.00% 5.00% 11.00%
Item 1100(1) a5 - Rigid Steel Conduit (RSC) 0.01% length 18.00 207.09 3,727.65 6.00% 5.00% 11.00%
Item 1100(1) d2 - Conduit Coupling (RSC) 0.00% pcs 105.00 12.43 1,305.66 6.00% 5.00% 11.00%
Item 1100(1) d3 - Conduit Coupling (RSC) 0.00% pcs 34.00 37.14 1,262.88 6.00% 5.00% 11.00%
Item 1100(2) a2 - Locknut & Bushing (RSC) 0.00% pcs 54.00 16.68 900.66 6.00% 5.00% 11.00%
Item 1100(2) a3 - Locknut & Bushing (RSC) 0.00% pcs 24.00 22.02 528.44 6.00% 5.00% 11.00%
Item 1100(1) d4 - Conduit Coupling (RSC) 0.00% pcs 8.00 81.08 648.66 6.00% 5.00% 11.00%
Item 1100(4) d1 - Conduit Coupling (RSC) 0.01% pcs 135.00 25.12 3,391.76 6.00% 5.00% 11.00%
Item 1100(4) d2 - Conduit Coupling (RSC) 0.00% pcs 39.00 33.33 1,299.88 6.00% 5.00% 11.00%
Item 1100(4) d4 - Conduit Coupling (RSC) 0.00% pcs 4.00 45.03 180.11 6.00% 5.00% 11.00%
Item 1100(6) - Conduit Clamp 0.01% pcs 440.00 5.18 2,281.32 6.00% 5.00% 11.00%
Item 1100(8) b - G. I. Wire 0.00% kls 10.00 118.09 1,180.88 6.00% 5.00% 11.00%
Item 1100(12) - PVC Solvent Cement 0.00% Can 6.00 150.15 900.88 6.00% 5.00% 11.00%
Item 1100(14) - Octagonal Junction Box 0.02% Piece 105.00 43.16 4,531.76 6.00% 5.00% 11.00%
Item 1100(15) - Utility Box 0.02% Piece 135.00 42.69 5,762.64 6.00% 5.00% 11.00%
Item 1100(22) - Grounding Rod Copperweld 0.00% length 5.00 118.09 590.44 6.00% 5.00% 11.00%
Item 1101(1) a2 - Electrical Wire 0.17% rolls 15.00 3,273.77 49,106.60 6.00% 5.00% 11.00%
Item 1101(1) a3 - Wires and Wiring Devices 0.10% rolls 7.50 4,085.68 30,642.60 6.00% 5.00% 11.00%
Item 1101(1) a4 - Wires and Wiring Devices 0.04% rolls 1.80 7,303.67 13,146.60 6.00% 5.00% 11.00%
Item 1101(2) - Tumbler Switch Single Pole 0.01% pcs 18.00 178.43 3,211.76 6.00% 5.00% 11.00%
Item 1101(3) - Tumbler Switch 0.03% pcs 48.00 205.04 9,841.76 6.00% 5.00% 11.00%
Item 1101(4) - Tumbler Switch 0.01% pcs 6.00 410.29 2,461.76 6.00% 5.00% 11.00%
Item 1101(5) - Tumbler Switch 0.02% pcs 36.00 151.72 5,461.76 6.00% 5.00% 11.00%
Item 1101(6) - Duplex Convenience Receptacle 0.03% set 45.00 207.37 9,331.76 6.00% 5.00% 11.00%
Item 1102(1) - Panel Boards Safety Switch Type 0.03% set 1.00 7,802.20 7,802.20 6.00% 5.00% 11.00%
Item 1103(1) a4 - Fluorescent lighting Fixture 0.52% set 168.00 910.87 153,026.40 6.00% 5.00% 11.00%
Item 1103(2) a1 - Porcelain Keyless Receptacle case w/ 18w softone bulb 0.03% set 12.00 735.92 8,831.00 6.00% 5.00% 11.00%
Item 1208(2) b1 GI Pipe Railings 1.08% mts 65.10 4,870.18 317,048.52 6.00% 5.00% 11.00%
ARK - UP
VAT TOTAL
INDIRECT TOTAL COST UNIT COST
VALUE COST
5.00%
Approved by :
MARCELINO M. OPERARIO
er District Engineer
APPROVED BUDGET FOR THE CONTRACT
CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
UNDER BASIC EDUCATIONAL FACILITIES FUND (BEFF) - BATCH 3
@ Agusan del Sur National High School, San Francisco, Agusan del Sur
Site/Location 2
MARK-UP IN % TOTAL MARK - UP
ESTIMATED
SCOPE OF WORKS % UNIT QTY. UNIT PRICE
DIRECT COST PRO
OCM %
FIT
Item 1002(6) b3 PPR-C Pipes 0.01% piece 12.00 149.11 1,789.32 6.00% 5.00% 11.00%
Item 1002(6) b4 PPR-C Pipes 0.02% piece 36.00 140.04 5,041.32 6.00% 5.00% 11.00%
Item 1002(6) c2 PPR-C Pipes 0.01% piece 12.00 270.17 3,241.98 6.00% 5.00% 11.00%
Item 1002(7) c3 PPR-C Pipes 0.01% piece 13.00 320.97 4,172.64 6.00% 5.00% 11.00%
Item 1002(6) c4 PPR-C Pipes 0.01% piece 10.00 394.26 3,942.64 6.00% 5.00% 11.00%
Item 1002(6) g2 PPR-C Pipes 0.01% piece 30.00 127.09 3,812.64 6.00% 5.00% 11.00%
Item 1002(2) - Plumbing Fixtures 0.51% set 17.00 8,889.58 151,122.80 6.00% 5.00% 11.00%
Item 1004(2) a - Rough Hardwares 0.06% set 18.00 937.01 16,866.16 6.00% 5.00% 11.00%
Item 1004(2) d - Finishing Hardwares 0.01% set 2.00 790.44 1,580.88 6.00% 5.00% 11.00%
Item 1004(2) e - Finishing Hardwares 0.10% set 30.00 962.21 28,866.16 6.00% 5.00% 11.00%
Item 1004(2) g - Finishing Hardwares 0.06% set 90.00 184.73 16,625.72 6.00% 5.00% 11.00%
Item 1009(1) a - Jalousie Windows (Jalouplus eqiuv.) 0.67% sq mt 232.70 846.97 197,093.82 6.00% 5.00% 11.00%
Item 1010(1) - Frames 0.98% set 57.00 5,049.34 287,812.33 6.00% 5.00% 11.00%
Item 1010(2) a - Doors 0.08% sq. mts. 25.62 928.29 23,782.71 6.00% 5.00% 11.00%
Item 1010(2) b - Doors 0.32% sq. mts. 68.04 1,398.29 95,139.45 6.00% 5.00% 11.00%
Item 1013(2) a - Fabricated Metal Roofing Accessory 0.07% ln mt 63.00 341.70 21,526.92 6.00% 5.00% 11.00%
Item 1013(2) b - Fabricated Metal Roofing Accessory 0.04% ln mt 22.00 482.70 10,619.34 6.00% 5.00% 11.00%
Item 1013(2) c - Fabricated Metal Roofing Accessory 0.20% ln mts 126.00 472.17 59,492.80 6.00% 5.00% 11.00%
Item 1014(1) a1 - Prepainted Metal Sheets 2.06% sq mt 927.21 656.05 608,298.79 6.00% 5.00% 11.00%
Item 1018(1) - Glazed Tiles and Trims 1.81% sq mt. 519.60 1,029.23 534,784.26 6.00% 5.00% 11.00%
Item 1018(2) - UnGlazed Tiles 0.64% sq mt. 193.72 971.88 188,269.31 6.00% 5.00% 11.00%
Item 1021(1)a - Cement Floor Finish 0.33% sq.mt 1,710.45 56.33 96,348.84 6.00% 5.00% 11.00%
Item 1027(1) - Cement Plaster Finish 2.35% sq.mt 2,207.24 313.89 692,823.85 6.00% 5.00% 11.00%
Item 1032(1) - Painting Works 3.10% sq.mt 4,206.74 217.26 913,959.13 6.00% 5.00% 11.00%
D Electrical
Item 1100(1) a2 - Rigid Steel Conduit (RSC) 0.08% length 180.00 136.07 24,493.20 6.00% 5.00% 11.00%
Item 1100(1) a3 - Rigid Steel Conduit (RSC) 0.03% length 50.00 156.85 7,842.64 6.00% 5.00% 11.00%
Item 1100(1) a5 - Rigid Steel Conduit (RSC) 0.01% length 18.00 207.09 3,727.65 6.00% 5.00% 11.00%
Item 1100(1) d2 - Conduit Coupling (RSC) 0.00% pcs 105.00 12.43 1,305.66 6.00% 5.00% 11.00%
Item 1100(1) d3 - Conduit Coupling (RSC) 0.00% pcs 34.00 37.14 1,262.88 6.00% 5.00% 11.00%
Item 1100(2) a2 - Locknut & Bushing (RSC) 0.00% pcs 54.00 16.68 900.66 6.00% 5.00% 11.00%
Item 1100(2) a3 - Locknut & Bushing (RSC) 0.00% pcs 24.00 22.02 528.44 6.00% 5.00% 11.00%
Item 1100(1) d4 - Conduit Coupling (RSC) 0.00% pcs 8.00 81.08 648.66 6.00% 5.00% 11.00%
Item 1100(4) d1 - Conduit Coupling (RSC) 0.01% pcs 135.00 25.12 3,391.76 6.00% 5.00% 11.00%
Item 1100(4) d2 - Conduit Coupling (RSC) 0.00% pcs 39.00 33.33 1,299.88 6.00% 5.00% 11.00%
Item 1100(4) d4 - Conduit Coupling (RSC) 0.00% pcs 4.00 45.03 180.11 6.00% 5.00% 11.00%
Item 1100(6) - Conduit Clamp 0.01% pcs 440.00 5.18 2,281.32 6.00% 5.00% 11.00%
Item 1100(8) b - G. I. Wire 0.00% kls 10.00 118.09 1,180.88 6.00% 5.00% 11.00%
Item 1100(12) - PVC Solvent Cement 0.00% Can 6.00 150.15 900.88 6.00% 5.00% 11.00%
Item 1100(14) - Octagonal Junction Box 0.02% Piece 105.00 43.16 4,531.76 6.00% 5.00% 11.00%
Item 1100(15) - Utility Box 0.02% Piece 135.00 42.69 5,762.64 6.00% 5.00% 11.00%
Item 1100(22) - Grounding Rod Copperweld 0.00% length 5.00 118.09 590.44 6.00% 5.00% 11.00%
Item 1101(1) a2 - Electrical Wire 0.17% rolls 15.00 3,273.77 49,106.60 6.00% 5.00% 11.00%
Item 1101(1) a3 - Wires and Wiring Devices 0.10% rolls 7.50 4,085.68 30,642.60 6.00% 5.00% 11.00%
Item 1101(1) a4 - Wires and Wiring Devices 0.04% rolls 1.80 7,303.67 13,146.60 6.00% 5.00% 11.00%
Item 1101(2) - Tumbler Switch Single Pole 0.01% pcs 18.00 178.43 3,211.76 6.00% 5.00% 11.00%
Item 1101(3) - Tumbler Switch 0.03% pcs 48.00 205.04 9,841.76 6.00% 5.00% 11.00%
Item 1101(4) - Tumbler Switch 0.01% pcs 6.00 410.29 2,461.76 6.00% 5.00% 11.00%
Item 1101(5) - Tumbler Switch 0.02% pcs 36.00 151.72 5,461.76 6.00% 5.00% 11.00%
Item 1101(6) - Duplex Convenience Receptacle 0.03% set 45.00 207.37 9,331.76 6.00% 5.00% 11.00%
Item 1102(1) - Panel Boards Safety Switch Type 0.03% set 1.00 7,802.20 7,802.20 6.00% 5.00% 11.00%
Item 1103(1) a4 - Fluorescent lighting Fixture 0.52% set 168.00 910.87 153,026.40 6.00% 5.00% 11.00%
Item 1103(2) a1 - Porcelain Keyless Receptacle case w/ 18w softone bulb 0.03% set 12.00 735.92 8,831.00 6.00% 5.00% 11.00%
Item 1208(2) b1 GI Pipe Railings 1.08% mts 65.10 4,870.18 317,048.52 6.00% 5.00% 11.00%
ARK - UP
VAT TOTAL
INDIRECT TOTAL COST UNIT COST
VALUE COST
5.00%
Approved by :
MARCELINO M. OPERARIO
er District Engineer
APPROVED BUDGET FOR THE CONTRACT
CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
UNDER BASIC EDUCATIONAL FACILITIES FUND (BEFF) - BATCH 3
@ Agusan del Sur National High School, San Francisco, Agusan del Sur
Site/Location 3
MARK-UP IN % TOTAL MARK - UP
ESTIMATED
SCOPE OF WORKS % UNIT QTY. UNIT PRICE
DIRECT COST PRO
OCM %
FIT
Item 1002(6) b3 PPR-C Pipes 0.01% piece 12.00 149.11 1,789.32 6.00% 5.00% 11.00%
Item 1002(6) b4 PPR-C Pipes 0.02% piece 36.00 140.04 5,041.32 6.00% 5.00% 11.00%
Item 1002(6) c2 PPR-C Pipes 0.01% piece 12.00 270.17 3,241.98 6.00% 5.00% 11.00%
Item 1002(7) c3 PPR-C Pipes 0.01% piece 13.00 320.97 4,172.64 6.00% 5.00% 11.00%
Item 1002(6) c4 PPR-C Pipes 0.01% piece 10.00 394.26 3,942.64 6.00% 5.00% 11.00%
Item 1002(6) g2 PPR-C Pipes 0.01% piece 30.00 127.09 3,812.64 6.00% 5.00% 11.00%
Item 1002(2) - Plumbing Fixtures 0.51% set 17.00 8,889.58 151,122.80 6.00% 5.00% 11.00%
Item 1004(2) a - Rough Hardwares 0.06% set 18.00 937.01 16,866.16 6.00% 5.00% 11.00%
Item 1004(2) d - Finishing Hardwares 0.01% set 2.00 790.44 1,580.88 6.00% 5.00% 11.00%
Item 1004(2) e - Finishing Hardwares 0.10% set 30.00 962.21 28,866.16 6.00% 5.00% 11.00%
Item 1004(2) g - Finishing Hardwares 0.06% set 90.00 184.73 16,625.72 6.00% 5.00% 11.00%
Item 1009(1) a - Jalousie Windows (Jalouplus eqiuv.) 0.67% sq mt 232.70 846.97 197,093.82 6.00% 5.00% 11.00%
Item 1010(1) - Frames 0.98% set 57.00 5,049.34 287,812.33 6.00% 5.00% 11.00%
Item 1010(2) a - Doors 0.08% sq. mts. 25.62 928.29 23,782.71 6.00% 5.00% 11.00%
Item 1010(2) b - Doors 0.32% sq. mts. 68.04 1,398.29 95,139.45 6.00% 5.00% 11.00%
Item 1013(2) a - Fabricated Metal Roofing Accessory 0.07% ln mt 63.00 341.70 21,526.92 6.00% 5.00% 11.00%
Item 1013(2) b - Fabricated Metal Roofing Accessory 0.04% ln mt 22.00 482.70 10,619.34 6.00% 5.00% 11.00%
Item 1013(2) c - Fabricated Metal Roofing Accessory 0.20% ln mts 126.00 472.17 59,492.80 6.00% 5.00% 11.00%
Item 1014(1) a1 - Prepainted Metal Sheets 2.06% sq mt 927.21 656.05 608,298.79 6.00% 5.00% 11.00%
Item 1018(1) - Glazed Tiles and Trims 1.81% sq mt. 519.60 1,029.23 534,784.26 6.00% 5.00% 11.00%
Item 1018(2) - UnGlazed Tiles 0.64% sq mt. 193.72 971.88 188,269.31 6.00% 5.00% 11.00%
Item 1021(1)a - Cement Floor Finish 0.33% sq.mt 1,710.45 56.33 96,348.84 6.00% 5.00% 11.00%
Item 1027(1) - Cement Plaster Finish 2.35% sq.mt 2,207.24 313.89 692,823.85 6.00% 5.00% 11.00%
Item 1032(1) - Painting Works 3.10% sq.mt 4,206.74 217.26 913,959.13 6.00% 5.00% 11.00%
D Electrical
Item 1100(1) a2 - Rigid Steel Conduit (RSC) 0.08% length 180.00 136.07 24,493.20 6.00% 5.00% 11.00%
Item 1100(1) a3 - Rigid Steel Conduit (RSC) 0.03% length 50.00 156.85 7,842.64 6.00% 5.00% 11.00%
Item 1100(1) a5 - Rigid Steel Conduit (RSC) 0.01% length 18.00 207.09 3,727.65 6.00% 5.00% 11.00%
Item 1100(1) d2 - Conduit Coupling (RSC) 0.00% pcs 105.00 12.43 1,305.66 6.00% 5.00% 11.00%
Item 1100(1) d3 - Conduit Coupling (RSC) 0.00% pcs 34.00 37.14 1,262.88 6.00% 5.00% 11.00%
Item 1100(2) a2 - Locknut & Bushing (RSC) 0.00% pcs 54.00 16.68 900.66 6.00% 5.00% 11.00%
Item 1100(2) a3 - Locknut & Bushing (RSC) 0.00% pcs 24.00 22.02 528.44 6.00% 5.00% 11.00%
Item 1100(1) d4 - Conduit Coupling (RSC) 0.00% pcs 8.00 81.08 648.66 6.00% 5.00% 11.00%
Item 1100(4) d1 - Conduit Coupling (RSC) 0.01% pcs 135.00 25.12 3,391.76 6.00% 5.00% 11.00%
Item 1100(4) d2 - Conduit Coupling (RSC) 0.00% pcs 39.00 33.33 1,299.88 6.00% 5.00% 11.00%
Item 1100(4) d4 - Conduit Coupling (RSC) 0.00% pcs 4.00 45.03 180.11 6.00% 5.00% 11.00%
Item 1100(6) - Conduit Clamp 0.01% pcs 440.00 5.18 2,281.32 6.00% 5.00% 11.00%
Item 1100(8) b - G. I. Wire 0.00% kls 10.00 118.09 1,180.88 6.00% 5.00% 11.00%
Item 1100(12) - PVC Solvent Cement 0.00% Can 6.00 150.15 900.88 6.00% 5.00% 11.00%
Item 1100(14) - Octagonal Junction Box 0.02% Piece 105.00 43.16 4,531.76 6.00% 5.00% 11.00%
Item 1100(15) - Utility Box 0.02% Piece 135.00 42.69 5,762.64 6.00% 5.00% 11.00%
Item 1100(22) - Grounding Rod Copperweld 0.00% length 5.00 118.09 590.44 6.00% 5.00% 11.00%
Item 1101(1) a2 - Electrical Wire 0.17% rolls 15.00 3,273.77 49,106.60 6.00% 5.00% 11.00%
Item 1101(1) a3 - Wires and Wiring Devices 0.10% rolls 7.50 4,085.68 30,642.60 6.00% 5.00% 11.00%
Item 1101(1) a4 - Wires and Wiring Devices 0.04% rolls 1.80 7,303.67 13,146.60 6.00% 5.00% 11.00%
Item 1101(2) - Tumbler Switch Single Pole 0.01% pcs 18.00 178.43 3,211.76 6.00% 5.00% 11.00%
Item 1101(3) - Tumbler Switch 0.03% pcs 48.00 205.04 9,841.76 6.00% 5.00% 11.00%
Item 1101(4) - Tumbler Switch 0.01% pcs 6.00 410.29 2,461.76 6.00% 5.00% 11.00%
Item 1101(5) - Tumbler Switch 0.02% pcs 36.00 151.72 5,461.76 6.00% 5.00% 11.00%
Item 1101(6) - Duplex Convenience Receptacle 0.03% set 45.00 207.37 9,331.76 6.00% 5.00% 11.00%
Item 1102(1) - Panel Boards Safety Switch Type 0.03% set 1.00 7,802.20 7,802.20 6.00% 5.00% 11.00%
Item 1103(1) a4 - Fluorescent lighting Fixture 0.52% set 168.00 910.87 153,026.40 6.00% 5.00% 11.00%
Item 1103(2) a1 - Porcelain Keyless Receptacle case w/ 18w softone bulb 0.03% set 12.00 735.92 8,831.00 6.00% 5.00% 11.00%
Item 1208(2) b1 GI Pipe Railings 1.08% mts 65.10 4,870.18 317,048.52 6.00% 5.00% 11.00%
ARK - UP
VAT TOTAL
INDIRECT TOTAL COST UNIT COST
VALUE COST
5.00%
Approved by :
MARCELINO M. OPERARIO
er District Engineer
Unit Price Analysis
UNIT COST
HOOL BUILDING
TOTAL COST
1,615.00
140.00
706.00
2,500.00
4,961.00
Total
Cost
577.20
1,291.20
1,868.40
Total
Cost
-
6,829.40
700.01
7,529.41
3,764.71
Unit Price Analysis
NONE
UNIT COST
OOMS SCHOOL BUILDING
TOTAL COST
1,630.00
8,800.00
8,880.00
816.00
8,568.00
5,920.00
4,920.00
6,240.00
45,774.00
Total
Cost
45,000.00
36,840.00
81,840.00
Total
Cost
-
127,614.00
13,080.44
140,694.44
14,069.44
Unit Price Analysis
NONE
NONE
UNIT COST
OMS SCHOOL BUILDING
m3/hr.
TOTAL COST
0.00
Total
Cost
6,497.07
54,502.45
60,999.52
Total
Cost
0.00
60,999.52
10,095.42
71,094.94
71,094.94
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : SPL - 1 Blackboard
COST SHEET ID : Other General Requirements
QUANTITY : 18.00 set PRODUCTION RATE :
NUMBER OF HOURS :
NONE
UNIT COST
SCHOOL BUILDING
TOTAL COST
10,395.00
11,700.00
14,400.00
17,280.00
8,640.00
13,500.00
10,800.00
1,440.00
1,350.00
89,505.00
Total
Cost
2,308.80
5,770.56
10,329.60
18,408.96
Total
Cost
107,913.96
17,859.76
125,773.72
6,987.43
Unit Price Analysis
JOB : Construction of 3sty-18cl School Building Projects
PAY ITEMS : Item 407-4 Piling
COST SHEET ID : Concrete Structures
QUANTITY : 1,950.00 ln mts. PRODUCTION RATE :
NUMBER OF HOURS :
A) MATERIALS : COST/UNIT UNIT QUANTITY
MICRO PILE:
195 pcs x 200mm dia x 10000mm lm 1,950.00
per L.M.
UNIT COST
3.00 mts/hour
3,475.00 114.68
47.00 593.42
150.00 0.90
21.27
730.27
1,424,020.47
Hourly Total
Rate Cost
72.15 72.15
60.11 300.55
40.35 242.10
60.11 60.11
40.35 80.70
755.61
491,146.50
Hourly Total
Rate Cost
3,932.00 2,909.68
1,427.00 1,355.65
351.50 14.06
219.75 8.79
173.00 86.50
280.00 140.00
123.38 61.69
1,065.00 532.50
391.00 195.50
320.00 76.80
559.00 134.16
543.00 271.50
75.56
5,862.39
3,810,554.15
5,725,721.12
343,543.27
286,286.06
317,777.52
947,606.85
6,673,327.97
3,422.22
Unit Price Analysis
NONE
NONE
UNIT COST
S SCHOOL BUILDING
m3/hr.
TOTAL COST
0.00
Total
Cost
7,070.70
71,177.40
78,248.10
Total
Cost
0.00
78,248.10
12,950.06
91,198.16
91,198.16
Unit Price Analysis
NONE
NONE
UNIT COST
SCHOOL BUILDING
m3/hr.
TOTAL COST
0.00
Total
Cost
8,080.80
45,192.00
53,272.80
Total
Cost
0.00
53,272.80
8,816.65
62,089.45
24.91
Unit Price Analysis
UNIT COST
OOL BUILDING
m3/hr.
41.39
TOTAL COST
39,616.27
39,616.27
Total
Cost
2,986.28
10,020.48
13,006.75
Total
Cost
52,623.03
8,709.11
61,332.14
1,255.78
Unit Price Analysis
NONE
UNIT COST
SCHOOL BUILDING
m3/hr.
TOTAL COST
127,285.01
127,285.01
Total
Cost
8,658.00
58,104.00
66,762.00
Total
Cost
0.00
194,047.01
32,114.78
226,161.79
1,259.60
Unit Price Analysis
Footings
Portland Cement bags 2,444.44 263.09
Sand cu.m. 134.31 741.66
Gravel - 3/4" cu.m. 268.62 811.14
20mm dia x 6mts kgs. 12,992.56 45.12
#16 G.I. Tie Wire kgs. 227.55 100.00
Columns
Portland Cement bags 1,221.57 263.09
Sand cu.m. 67.12 741.66
Gravel - 3/4" cu.m. 134.24 811.14
25mm dia x 6mts,20mm dia x 6mts,16mm dia x 6mts kgs. 60,386.90 45.12
12mm dia x 6mts,10mm dia x 6mts
#16 G.I. Tie Wire kgs. 586.44 100.00
Tie Beam
Portland Cement bags 479.80 263.09
Sand cu.m. 26.36 741.66
Gravel - 3/4" cu.m. 52.73 811.14
20mm dia x 6mts,16mm dia x 6mts kgs. 9,221.58 45.12
12mm dia x 6mts,10mm dia x 6mts
#16 G.I. Tie Wire kgs. 152.49 100.00
Slab on Fill
Portland Cement bags 544.64 263.09
Sand cu.m. 29.93 741.66
Gravel - 3/4" cu.m. 59.85 811.14
10mm dia x 6mts kgs. 2,229.92 45.12
#16 G.I. Tie Wire kgs. 29.71 100.00
Septic Tank
Portland Cement bags 123.08 263.09
Sand cu.m. 6.76 741.66
Gravel - 3/4" cu.m. 13.53 811.14
12mm dia x 6mts,10mm dia x 6mts kgs. 372.72 45.12
#16 G.I. Tie Wire kgs. 0.57 100.00
m3/hr.
TOTAL COST
643,108.49
99,612.89
217,889.50
586,254.35
22,754.72
321,382.61
49,779.86
108,886.60
2,724,796.20
58,643.77
126,229.97
19,552.12
42,767.57
416,098.82
15,249.06
143,288.08
22,194.30
48,546.97
100,619.13
2,971.13
280,758.44
43,487.47
95,122.86
1,437,019.07
46,616.60
246,699.69
38,212.01
83,583.52
770,710.71
26,318.49
87,145.96
13,498.28
29,525.64
225,996.92
10,014.79
80,772.82
12,511.13
27,366.38
48,106.67
267.17
33,148.98
5,134.54
11,231.10
33,379.82
361.94
32,381.67
5,015.69
10,971.13
16,817.80
57.36
9,522,860.80
Total
Cost
82,828.20
552,050.24
276,025.12
694,827.00
276,025.12
1,881,755.68
Total
Cost
127,888.26
17,198.42
29,773.27
43,945.96
218,805.91
11,623,422.38
1,923,676.40
13,547,098.78
10,838.67
Unit Price Analysis
NONE
UNIT COST
S SCHOOL BUILDING
TOTAL COST
9,875.25
9,875.25
Total
Cost
2,208.50
2,208.50
Total
Cost
0.00
12,083.75
1,999.86
14,083.62
470.63
Unit Price Analysis
NONE
UNIT COST
S SCHOOL BUILDING
TOTAL COST
1,891.89
1,891.89
Total
Cost
974.59
974.59
Total
Cost
0.00
2,866.48
474.40
3,340.88
582.75
Unit Price Analysis
UNIT COST
MS SCHOOL BUILDING
m2./hr.
TOTAL COST
63,960.00
73,399.70
272,718.69
133,417.12
2,511.99
546,007.50
Total
Cost
23,088.00
76,940.80
77,472.00
19,235.20
196,736.00
Total
Cost
9,395.89
9,395.89
752,139.39
124,479.07
876,618.46
1,640.18
Unit Price Analysis
m2./hr.
TOTAL COST
205,908.00
275,217.94
1,230,691.77
288,880.88
7,862.04
2,008,560.64
Total
Cost
30,591.60
101,946.56
119,758.80
25,486.64
247,192.00
Total
Cost
29,407.38
29,407.38
2,285,160.02
378,193.98
2,663,354.01
1,592.18
Unit Price Analysis
Steel Trusses
2< - 50mm x 50mm x 6mm x 6.0m Angle Bar kgs 3,812.46 75.23
2< - 50mm x 50mm x 4.5mm x 6.0m Angle Bar kgs 1,782.14 75.23
Gusset Plate - 1.2 x 2.4 x 6mm
0.25 x 0.35 x 6mm kgs 857.22 75.23
Base & Buckle Plate 1.2 x 2.4 x 12mm
0.45 x 0.45 x 12mm kgs 612.14 75.23
Anchor Bolts w/ N & W
4-16mm x 350mm Long Bolts kgs 246.32 110.23
Steel LC - Purlins
150mm x 65mm x 20mm x 2.5mm kgs 8,024.94 75.23
Steel Channel (Fascia Frame)
100mm x 50mm x 12mm x 1.2mm kgs 296.00 75.23
Bottom Strut
150mm x 50mm x 20mm x 2mm pcs 234.00 75.23
Long Clip Angle w/ N & W
65mm x 65mm x 6mm angle bar kgs 115.21 75.23
Angular Bar - press @ top of roofing sheet edges
40mm x 40mm x 6mm angle bar kgs 116.95 75.23
Shelf Angle
100mm x 100mm x 4.5mm bent plate kgs 162.78 75.23
6mm Spider legs anchor set 28.42 2.50
Blind Rivets set 2,500.00 1.50
TurnBuckle w/ hookend
16mm dia x Std. Turnbuckle pcs. 28.00 185.00
16mm dia x Cross Bracing Bar kgs. 309.48 47.12
Sag Rod
12mm dia x Nuts & Washers pcs 1,469.16 80.00
J-Bolt w/ cyclonic washer
6mm J-bolt w/ felt and cyclonic washer pcs 9,900.00 10.00
Purlins Connection
4- 12mm dia bolts x Nuts & Washers pcs 924.00 2.50
125mm x 125mm x 4mm x 50mm bent plate kgs 340.00 75.23
*** Welding Rod @ 20 kls kls 9.00 3,000.00
*** Red Lead gals. 8.00 655.00
***
UNIT COST
kgs./hr.
TOTAL COST
286,820.77
134,075.16
64,490.81
46,053.13
27,152.91
603,736.34
22,268.82
17,604.41
8,667.60
8,798.59
12,246.17
3,750.00
5,180.00
14,583.60
117,532.80
99,000.00
2,310.00
25,579.29
27,000.00
5,240.00
1,532,090.38
Total
Cost
31,168.80
103,870.08
174,312.00
309,350.88
Total
Cost
29,106.00
2,454.30
31,560.30
1,873,001.56
309,981.76
2,182,983.32
129.10
Unit Price Analysis
JOB : Construction of One(1)-Storey TechVoc Workshop/Laboratory Building (Batch 6)
PAY ITEMS : Item 1044(1) - Forms and Falsework
COST SHEET ID : Masonry Works
QUANTITY : 1.00 ls PRODUCTION RATE :
, NUMBER OF HOURS :
UNIT COST
m2./hr.
TOTAL COST
300,000.00
250,000.00
300,000.00
250,000.00
1,100,000.00
Total
Cost
6,926.40
23,241.60
23,241.60
Total
Cost
-
1,123,241.60
185,896.48
1,309,138.08
1,309,138.08
Unit Price Analysis
NONE
UNIT COST
CHOOL BUILDING
sq m/hr
TOTAL COST
312,421.88
10,174.20
55,517.33
7,694.62
48,457.50
7,298.44
24,300.00
12,463.13
733.13
1,800.00
3,000.00
4,000.00
6,000.00
1,872.00
375.00
1,350.00
497,457.21
Total
Cost
15,007.20
75,017.28
75,017.28
Total
Cost
0.00
572,474.49
94,744.53
667,219.02
333.69
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1001(1) a5 Pipe
COST SHEET ID : Storm Drainage and Sewerage System
QUANTITY : 96.00 meter PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
UILDING
N RATE :
HOURS :
350.00 11,200.00
11,200.00
Hourly Total
Rate Cost
60.11 3,606.60
3,606.60
Hourly Total
Rate Cost
14,806.60
888.40
740.33
821.77
2,450.49
17,257.09
179.76
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1001(1) a6 Pipe
COST SHEET ID : Storm Drainage and Sewerage System
QUANTITY : 76.80 meter PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
UILDING
N RATE :
HOURS :
350.00 8,960.00
8,960.00
Hourly Total
Rate Cost
60.11 3,606.60
3,606.60
Hourly Total
Rate Cost
12,566.60
754.00
628.33
697.45
2,079.77
14,646.37
190.71
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1001(1) a7 Pipe
COST SHEET ID : Storm Drainage and Sewerage System
QUANTITY : 120.00 meter PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
UILDING
N RATE :
HOURS :
798.00 31,920.00
31,920.00
Hourly Total
Rate Cost
60.11 3,606.60
3,606.60
Hourly Total
Rate Cost
35,526.60
2,131.60
1,776.33
1,971.73
5,879.65
41,406.25
345.05
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1001(1) a8 Pipe
COST SHEET ID : Storm Drainage and Sewerage System
QUANTITY : 73.00 meter PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
UILDING
N RATE :
HOURS :
978.00 23,798.00
23,798.00
Hourly Total
Rate Cost
60.11 3,606.60
3,606.60
Hourly Total
Rate Cost
27,404.60
1,644.28
1,370.23
1,520.96
4,535.46
31,940.06
437.54
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1001(2) a1 Fittings
COST SHEET ID : Storm Drainage and Sewerage System
QUANTITY : 30.00 each PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
UILDING
N RATE :
HOURS :
35.00 1,050.00
1,050.00
Hourly Total
Rate Cost
60.11 721.32
721.32
Hourly Total
Rate Cost
1,771.32
106.28
88.57
98.31
293.15
2,064.47
68.82
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1001(2) a2 Fittings
COST SHEET ID : Storm Drainage and Sewerage System
QUANTITY : 36.00 each PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
UILDING
N RATE :
HOURS :
35.00 1,260.00
1,260.00
Hourly Total
Rate Cost
60.11 721.32
721.32
Hourly Total
Rate Cost
1,981.32
118.88
99.07
109.96
327.91
2,309.23
64.15
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1001(2) a3 Fittings
COST SHEET ID : Storm Drainage and Sewerage System
QUANTITY : 18.00 each PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
UILDING
N RATE :
HOURS :
61.00 1,098.00
1,098.00
Hourly Total
Rate Cost
60.11 480.88
480.88
Hourly Total
Rate Cost
1,578.88
94.73
78.94
87.63
261.30
1,840.18
102.23
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1001(2) a4 Fittings
COST SHEET ID : Storm Drainage and Sewerage System
QUANTITY : 8.00 each PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
UILDING
N RATE :
HOURS :
68.00 544.00
544.00
Hourly Total
Rate Cost
60.11 240.44
240.44
Hourly Total
Rate Cost
784.44
47.07
39.22
43.54
129.82
914.26
114.28
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1001(2) b1 Fittings
COST SHEET ID : Storm Drainage and Sewerage System
QUANTITY : 18.00 each PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
UILDING
N RATE :
HOURS :
34.00 612.00
612.00
Hourly Total
Rate Cost
60.11 240.44
240.44
Hourly Total
Rate Cost
852.44
51.15
42.62
47.31
141.08
993.52
55.20
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1001(2) b2 Fittings
COST SHEET ID : Storm Drainage and Sewerage System
QUANTITY : 32.00 each PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
UILDING
N RATE :
HOURS :
48.00 1,536.00
1,536.00
Hourly Total
Rate Cost
60.11 240.44
240.44
Hourly Total
Rate Cost
1,776.44
106.59
88.82
98.59
294.00
2,070.44
64.70
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1001(2) c1 Fittings
COST SHEET ID : Storm Drainage and Sewerage System
QUANTITY : 12.00 each PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
UILDING
N RATE :
HOURS :
45.00 540.00
540.00
Hourly Total
Rate Cost
60.11 240.44
240.44
Hourly Total
Rate Cost
780.44
46.83
39.02
43.31
129.16
909.60
75.80
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1001(2) c2 Fittings
COST SHEET ID : Storm Drainage and Sewerage System
QUANTITY : 18.00 each PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
UILDING
N RATE :
HOURS :
53.00 954.00
954.00
Hourly Total
Rate Cost
60.11 240.44
240.44
Hourly Total
Rate Cost
1,194.44
71.67
59.72
66.29
197.68
1,392.12
77.34
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1001(2) c3 Fittings
COST SHEET ID : Storm Drainage and Sewerage System
QUANTITY : 12.00 each PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
UILDING
N RATE :
HOURS :
120.00 1,440.00
1,440.00
Hourly Total
Rate Cost
60.11 601.10
601.10
Hourly Total
Rate Cost
2,041.10
122.47
102.06
113.28
337.80
2,378.90
198.24
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1001(2) c4 Fittings
COST SHEET ID : Storm Drainage and Sewerage System
QUANTITY : 6.00 each PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
UILDING
N RATE :
HOURS :
135.00 810.00
810.00
Hourly Total
Rate Cost
60.11 480.88
480.88
Hourly Total
Rate Cost
1,290.88
77.45
64.54
71.64
213.64
1,504.52
250.75
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1001(2) d1 Fittings
COST SHEET ID : Storm Drainage and Sewerage System
QUANTITY : 24.00 each PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
UILDING
N RATE :
HOURS :
65.00 1,560.00
1,560.00
Hourly Total
Rate Cost
60.11 480.88
480.88
Hourly Total
Rate Cost
2,040.88
122.45
102.04
113.27
337.77
2,378.65
99.11
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1001(2) d2 Fittings
COST SHEET ID : Storm Drainage and Sewerage System
QUANTITY : 16.00 each PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
UILDING
N RATE :
HOURS :
75.00 1,200.00
1,200.00
Hourly Total
Rate Cost
60.11 480.88
480.88
Hourly Total
Rate Cost
1,680.88
100.85
84.04
93.29
278.19
1,959.07
122.44
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1001(2) d3 Fittings
COST SHEET ID : Storm Drainage and Sewerage System
QUANTITY : 12.00 each PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
UILDING
N RATE :
HOURS :
350.00 4,200.00
4,200.00
Hourly Total
Rate Cost
60.11 480.88
480.88
Hourly Total
Rate Cost
4,680.88
280.85
234.04
259.79
774.69
5,455.57
454.63
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1001(2) d4 Fittings
COST SHEET ID : Storm Drainage and Sewerage System
QUANTITY : 4.00 each PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
UILDING
N RATE :
HOURS :
370.00 1,480.00
1,480.00
Hourly Total
Rate Cost
60.11 961.76
961.76
Hourly Total
Rate Cost
2,441.76
146.51
122.09
135.52
404.11
2,845.87
711.47
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1001(2) e1 Fittings
COST SHEET ID : Storm Drainage and Sewerage System
QUANTITY : 18.00 each PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
UILDING
N RATE :
HOURS :
215.00 3,870.00
3,870.00
Hourly Total
Rate Cost
60.11 601.10
601.10
Hourly Total
Rate Cost
4,471.10
268.27
223.56
248.15
739.97
5,211.07
289.50
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1001(2) e2 Fittings
COST SHEET ID : Storm Drainage and Sewerage System
QUANTITY : 9.00 each PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
UILDING
N RATE :
HOURS :
356.00 3,204.00
3,204.00
Hourly Total
Rate Cost
60.11 601.10
601.10
Hourly Total
Rate Cost
3,805.10
228.31
190.26
211.18
629.74
4,434.84
492.76
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1001(2) e3 Fittings
COST SHEET ID : Storm Drainage and Sewerage System
QUANTITY : 18.00 each PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
UILDING
N RATE :
HOURS :
545.00 9,810.00
9,810.00
Hourly Total
Rate Cost
60.11 1,442.64
1,442.64
Hourly Total
Rate Cost
11,252.64
675.16
562.63
624.52
1,862.31
13,114.95
728.61
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1001(2) f1 Fittings
COST SHEET ID : Storm Drainage and Sewerage System
QUANTITY : 12.00 each PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
UILDING
N RATE :
HOURS :
155.00 1,860.00
1,860.00
Hourly Total
Rate Cost
60.11 1,442.64
1,442.64
Hourly Total
Rate Cost
3,302.64
198.16
165.13
183.30
546.59
3,849.23
320.77
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1001(2) f3 Fittings
COST SHEET ID : Storm Drainage and Sewerage System
QUANTITY : 6.00 each PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
UILDING
N RATE :
HOURS :
200.00 1,200.00
1,200.00
Hourly Total
Rate Cost
60.11 1,442.64
1,442.64
Hourly Total
Rate Cost
2,642.64
158.56
132.13
146.67
437.36
3,080.00
513.33
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1001(2) g1 Fittings
COST SHEET ID : Storm Drainage and Sewerage System
QUANTITY : 24.00 each PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
UILDING
N RATE :
HOURS :
82.00 1,968.00
1,968.00
Hourly Total
Rate Cost
60.11 1,442.64
1,442.64
Hourly Total
Rate Cost
3,410.64
204.64
170.53
189.29
564.46
3,975.10
165.63
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1001(2) g3 Fittings
COST SHEET ID : Storm Drainage and Sewerage System
QUANTITY : 18.00 each PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
UILDING
N RATE :
HOURS :
198.00 3,564.00
3,564.00
Hourly Total
Rate Cost
60.11 1,622.97
1,622.97
Hourly Total
Rate Cost
5,186.97
311.22
259.35
287.88
858.44
6,045.41
335.86
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1001(2) g4 Fittings
COST SHEET ID : Storm Drainage and Sewerage System
QUANTITY : 4.00 each PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
UILDING
N RATE :
HOURS :
235.00 940.00
940.00
Hourly Total
Rate Cost
60.11 1,442.64
1,442.64
Hourly Total
Rate Cost
2,382.64
142.96
119.13
132.24
394.33
2,776.97
694.24
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1001(2) i2 Fittings
COST SHEET ID : Storm Drainage and Sewerage System
QUANTITY : 18.00 each PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
UILDING
N RATE :
HOURS :
115.00 2,070.00
2,070.00
Hourly Total
Rate Cost
60.11 1,442.64
1,442.64
Hourly Total
Rate Cost
3,512.64
210.76
175.63
194.95
581.34
4,093.98
227.44
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1001(2) l2 Fittings
COST SHEET ID : Storm Drainage and Sewerage System
QUANTITY : 6.00 each PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
UILDING
N RATE :
HOURS :
160.00 960.00
960.00
Hourly Total
Rate Cost
60.11 1,442.64
1,442.64
Hourly Total
Rate Cost
2,402.64
144.16
120.13
133.35
397.64
2,800.28
466.71
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1002(5) b1 PPR-C Pipes
COST SHEET ID : Plumbing
QUANTITY : 18.00 piece PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
UILDING
N RATE :
HOURS :
240.00 4,320.00
4,320.00
Hourly Total
Rate Cost
60.11 1,442.64
1,442.64
Hourly Total
Rate Cost
5,762.64
345.76
288.13
319.83
953.72
6,716.36
373.13
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1002(5) c2 PPR-C Pipes
COST SHEET ID : Plumbing
QUANTITY : 24.00 piece PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
UILDING
N RATE :
HOURS :
310.00 7,440.00
7,440.00
Hourly Total
Rate Cost
60.11 1,803.30
1,803.30
Hourly Total
Rate Cost
9,243.30
554.60
462.17
513.00
1,529.77
10,773.07
448.88
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1002(5) d3 PPR-C Pipes
COST SHEET ID : Plumbing
QUANTITY : 24.00 piece PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
UILDING
N RATE :
HOURS :
380.00 9,120.00
9,120.00
Hourly Total
Rate Cost
60.11 2,163.96
2,163.96
Hourly Total
Rate Cost
11,283.96
677.04
564.20
626.26
1,867.50
13,151.46
547.98
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1002(6) b2 PPR-C Pipes
COST SHEET ID : Plumbing
QUANTITY : 18.00 piece PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
UILDING
N RATE :
HOURS :
75.00 1,350.00
1,350.00
Hourly Total
Rate Cost
60.11 721.32
721.32
Hourly Total
Rate Cost
2,071.32
124.28
103.57
114.96
342.80
2,414.12
134.12
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1002(6) b3 PPR-C Pipes
COST SHEET ID : Plumbing
QUANTITY : 12.00 piece PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
UILDING
N RATE :
HOURS :
89.00 1,068.00
1,068.00
Hourly Total
Rate Cost
60.11 721.32
721.32
Hourly Total
Rate Cost
1,789.32
107.36
89.47
99.31
296.13
2,085.45
173.79
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1002(6) b4 PPR-C Pipes
COST SHEET ID : Plumbing
QUANTITY : 36.00 piece PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
UILDING
N RATE :
HOURS :
120.00 4,320.00
4,320.00
Hourly Total
Rate Cost
60.11 721.32
721.32
Hourly Total
Rate Cost
5,041.32
302.48
252.07
279.79
834.34
5,875.66
163.21
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1002(6) c2 PPR-C Pipes
COST SHEET ID : Plumbing
QUANTITY : 12.00 piece PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
UILDING
N RATE :
HOURS :
180.00 2,160.00
2,160.00
Hourly Total
Rate Cost
60.11 1,081.98
1,081.98
Hourly Total
Rate Cost
3,241.98
194.52
162.10
179.93
536.55
3,778.53
314.88
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1002(7) c3 PPR-C Pipes
COST SHEET ID : Plumbing
QUANTITY : 13.00 piece PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
UILDING
N RATE :
HOURS :
210.00 2,730.00
2,730.00
Hourly Total
Rate Cost
60.11 1,442.64
1,442.64
Hourly Total
Rate Cost
4,172.64
250.36
208.63
231.58
690.57
4,863.21
374.09
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1002(6) c4 PPR-C Pipes
COST SHEET ID : Plumbing
QUANTITY : 10.00 piece PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
UILDING
N RATE :
HOURS :
250.00 2,500.00
2,500.00
Hourly Total
Rate Cost
60.11 1,442.64
1,442.64
Hourly Total
Rate Cost
3,942.64
236.56
197.13
218.82
652.51
4,595.15
459.51
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1002(6) g2 PPR-C Pipes
COST SHEET ID : Plumbing
QUANTITY : 30.00 piece PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
UILDING
N RATE :
HOURS :
79.00 2,370.00
2,370.00
Hourly Total
Rate Cost
60.11 1,442.64
1,442.64
Hourly Total
Rate Cost
3,812.64
228.76
190.63
211.60
630.99
4,443.63
148.12
Unit Price Analysis
Water Closet (6.0 gpf) w/ complete accy set & assy. set 15.00 6,000.00
Lavatory w/ complete accy set & assy. set 2.00 5,500.00
Soap & Paper Holder set 15.00 650.00
sink faucet pcs 18.00 250.00
Solvent cement can 12.00 380.00
Teflon tape pcs 20.00 15.00
Stainless Steel Floor Drain pcs 12.00 180.00
NONE
UNIT COST
OL BUILDING
TOTAL COST
90,000.00
11,000.00
9,750.00
4,500.00
4,560.00
300.00
2,160.00
122,270.00
Total
Cost
28,852.80
28,852.80
Total
Cost
151,122.80
25,010.82
176,133.62
10,360.80
Unit Price Analysis
UNIT COST
set/hr
TOTAL COST
13,500.00
13,500.00
Total
Cost
3,366.16
3,366.16
Total
Cost
-
16,866.16
2,791.35
19,657.51
1,092.08
Unit Price Analysis
UNIT COST
set/hr
TOTAL COST
1,100.00
1,100.00
Total
Cost
480.88
480.88
Total
Cost
-
1,580.88
261.64
1,842.52
921.26
Unit Price Analysis
UNIT COST
set/hr
TOTAL COST
25,500.00
25,500.00
Total
Cost
3,366.16
3,366.16
Total
Cost
-
28,866.16
4,777.35
33,643.51
1,121.45
Unit Price Analysis
UNIT COST
set/hr
TOTAL COST
13,500.00
13,500.00
Total
Cost
3,125.72
3,125.72
Total
Cost
-
16,625.72
2,751.56
19,377.28
215.30
Unit Price Analysis
UNIT COST
m2/hr.
215.47
TOTAL COST
79,560.00
18,360.00
44,553.60
10,281.60
4,961.28
522.24
158,238.72
Total
Cost
38,855.10
38,855.10
Total
Cost
-
197,093.82
32,619.03
229,712.85
987.15
Unit Price Analysis
Ground Floor
Window Jamb w/ Transom - (W1), (W2),(W3),(W4)
96 - 2" x 6" x 5' bd ft 480.00
54 - 2" x 6" x 6' bd ft 324.00
36 - 2" x 6" x 8' bd ft 288.00
2nd & 3rd Floor
Window Jamb w/ Transom - (W1), (W2),(W3),(W4)
192 - 2" x 6" x 5' bd ft 960.00
92 - 2" x 6" x 6' bd ft 552.00
72 - 2" x 6" x 8' bd ft 576.00
UNIT COST
OOL BUILDING
set/hr.
680.00 24,480.00
50.00 10,800.00
50.00 28,800.00
-
-
50.00 600.00
50.00 2,800.00
-
-
50.00 900.00
50.00 4,200.00
50.00 800.00
50.00 1,333.33
50.00 24,000.00
50.00 16,200.00
50.00 14,400.00
50.00 48,000.00
50.00 27,600.00
50.00 28,800.00
233,713.33
Hourly Total
Rate Cost
60.11 54,099.00
54,099.00
Hourly Total
Rate Cost
-
287,812.33
17,268.74
14,390.62
15,973.58
47,632.94
335,445.27
5,885.00
Unit Price Analysis
UNIT COST
OOL BUILDING
1.08 sq.mts/hr.
23.72
650.00 2,769.00
650.00 6,552.00
650.00 6,084.00
650.00 1,248.00
16,653.00
Hourly Total
Rate Cost
60.11 7,129.71
7,129.71
Hourly Total
Rate Cost
-
23,782.71
1,426.96
1,189.14
1,319.94
3,936.04
27,718.75
1,081.92
Unit Price Analysis
UNIT COST
OOL BUILDING
1.08 sq.mts/hr.
63.00
1,120.00 76,204.80
76,204.80
Hourly Total
Rate Cost
60.11 18,934.65
18,934.65
Hourly Total
Rate Cost
-
95,139.45
5,708.37
4,756.97
5,280.24
15,745.58
110,885.03
1,629.70
Unit Price Analysis
UNIT COST
L BUILDING
2.08 ln m/hr.
HOURS : 30.29
255.00 16,065.00
16,065.00
Hourly Total
Rate Cost
60.11 5,461.92
5,461.92
Hourly Total
Rate Cost
-
21,526.92
1,291.62
1,076.35
1,194.74
3,562.70
25,089.62
398.25
Unit Price Analysis
UNIT COST
L BUILDING
2.08 ln m/hr.
HOURS : 10.58
396.00 8,712.00
8,712.00
Hourly Total
Rate Cost
60.11 1,907.34
1,907.34
Hourly Total
Rate Cost
-
10,619.34
637.16
530.97
589.37
1,757.50
12,376.84
562.58
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1013(2) c - Fabricated Metal Roofing Accessory
COST SHEET ID : Corrugated Metal Roofing
QUANTITY : 126.00 ln mts PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
UILDING
N RATE :
HOURS :
434.00 54,684.00
54,684.00
Hourly Total
Rate Cost
60.11 4,808.80
4,808.80
Hourly Total
Rate Cost
59,492.80
3,569.57
2,974.64
3,301.85
9,846.06
69,338.86
550.31
Unit Price Analysis
UNIT COST
L BUILDING
2.08 sq m/hr.
HOURS : 445.77
480.00 445,060.00
7.50 74,250.00
580.00 2,900.00
145.00 1,015.00
523,225.00
Hourly Total
Rate Cost
60.11 80,386.29
80,386.29
Hourly Total
Rate Cost
31.25 4,687.50
4,687.50
608,298.79
36,497.93
30,414.94
33,760.58
100,673.45
708,972.24
764.63
Unit Price Analysis
UNIT COST
m2/hr.
138.56
TOTAL COST
324,750.00
112,500.00
3,750.00
36,504.00
477,504.00
Total
Cost
49,972.66
49,972.66
Total
Cost
7,307.60
7,307.60
534,784.26
88,506.80
623,291.06
1,199.57
Unit Price Analysis
Ceramic Tiles
unGlazed - 0.20m x 0.20m pcs. 4,843.00 30.00
Tile Grout bags 12.00 125.00
Adhesive Cement bags 86.00 234.00
UNIT COST
m2/hr.
51.66
TOTAL COST
145,290.00
1,500.00
20,124.00
166,914.00
Total
Cost
18,630.88
18,630.88
Total
Cost
2,724.43
2,724.43
188,269.31
31,158.57
219,427.88
1,132.73
Unit Price Analysis
NONE
UNIT COST
OL BUILDING
m2./hr.
480.46
TOTAL COST
64,800.35
12,794.17
77,594.52
Total
Cost
18,754.32
18,754.32
Total
Cost
0.00
96,348.84
15,945.73
112,294.57
65.65
Unit Price Analysis
NONE
UNIT COST
L BUILDING
m2./hr.
TOTAL COST
138,854.41
549,761.74
688,616.15
Total
Cost
4,207.70
4,207.70
Total
Cost
0.00
692,823.85
114,662.35
807,486.19
365.84
Unit Price Analysis
note: for the exterior and interior paint finish, pls. refer to DepEd's approved color
NONE
UNIT COST
OL BUILDING
m2./hr.
120.19
TOTAL COST
127,324.00
127,324.00
119,366.25
127,324.00
78,876.38
36,458.41
7,800.00
16,344.00
103,196.59
10,500.00
3,750.00
11,200.00
769,463.62
Total
Cost
144,495.51
144,495.51
Total
Cost
0.00
913,959.13
151,260.24
1,065,219.36
253.22
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1100(1) a2 - Rigid Steel Conduit (RSC)
COST SHEET ID : Conduits, Boxes and Fittings
QUANTITY : 180.00 length PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
TOTAL COST
17,280.00
17,280.00
Total
Cost
7,213.20
7,213.20
Total
Cost
24,493.20
4,053.62
28,546.82
158.59
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1100(1) a3 - Rigid Steel Conduit (RSC)
COST SHEET ID : Conduits, Boxes and Fittings
QUANTITY : 50.00 length PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
TOTAL COST
6,400.00
6,400.00
Total
Cost
1,442.64
1,442.64
Total
Cost
7,842.64
1,297.96
9,140.60
182.81
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1100(1) a5 - Rigid Steel Conduit (RSC)
COST SHEET ID : Conduits, Boxes and Fittings
QUANTITY : 18.00 length PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
TOTAL COST
2,826.00
2,826.00
Total
Cost
901.65
901.65
Total
Cost
3,727.65
616.93
4,344.58
241.37
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1100(1) d2 - Conduit Coupling (RSC)
COST SHEET ID : Conduits, Boxes and Fittings
QUANTITY : 105.00 pcs PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
TOTAL COST
945.00
945.00
Total
Cost
360.66
360.66
Total
Cost
1,305.66
216.09
1,521.75
14.49
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1100(1) d3 - Conduit Coupling (RSC)
COST SHEET ID : Conduits, Boxes and Fittings
QUANTITY : 34.00 pcs PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
TOTAL COST
782.00
782.00
Total
Cost
480.88
480.88
Total
Cost
1,262.88
209.01
1,471.89
43.29
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1100(2) a2 - Locknut & Bushing (RSC)
COST SHEET ID : Conduits, Boxes and Fittings
QUANTITY : 54.00 pcs PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
TOTAL COST
540.00
540.00
Total
Cost
360.66
360.66
Total
Cost
900.66
149.06
1,049.72
19.44
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1100(2) a3 - Locknut & Bushing (RSC)
COST SHEET ID : Conduits, Boxes and Fittings
QUANTITY : 24.00 pcs PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
TOTAL COST
288.00
288.00
Total
Cost
240.44
240.44
Total
Cost
528.44
87.46
615.90
25.66
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1100(1) d4 - Conduit Coupling (RSC)
COST SHEET ID : Conduits, Boxes and Fittings
QUANTITY : 8.00 pcs PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
TOTAL COST
288.00
288.00
Total
Cost
360.66
360.66
Total
Cost
648.66
107.35
756.01
94.50
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1100(4) d1 - Conduit Coupling (RSC)
COST SHEET ID : Conduits, Boxes and Fittings
QUANTITY : 135.00 pcs PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
TOTAL COST
2,430.00
2,430.00
Total
Cost
961.76
961.76
Total
Cost
3,391.76
561.34
3,953.10
29.28
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1100(4) d2 - Conduit Coupling (RSC)
COST SHEET ID : Conduits, Boxes and Fittings
QUANTITY : 39.00 pcs PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
TOTAL COST
819.00
819.00
Total
Cost
480.88
480.88
Total
Cost
1,299.88
215.13
1,515.01
38.85
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1100(4) d4 - Conduit Coupling (RSC)
COST SHEET ID : Conduits, Boxes and Fittings
QUANTITY : 4.00 pcs PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
TOTAL COST
120.00
120.00
Total
Cost
60.11
60.11
Total
Cost
180.11
29.81
209.92
52.48
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1100(6) - Conduit Clamp
COST SHEET ID : Conduits, Boxes and Fittings
QUANTITY : 440.00 Piece PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
TOTAL COST
960.00
600.00
1,560.00
Total
Cost
721.32
721.32
Total
Cost
2,281.32
377.56
2,658.88
6.04
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1100(8) b - G. I. Wire
COST SHEET ID : Conduits, Boxes and Fittings
QUANTITY : 10.00 kls PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
TOTAL COST
700.00
700.00
Total
Cost
480.88
480.88
Total
Cost
1,180.88
195.44
1,376.32
137.63
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1100(12) - PVC Solvent Cement
COST SHEET ID : Conduits, Boxes and Fittings
QUANTITY : 6.00 Can PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
TOTAL COST
420.00
420.00
Total
Cost
480.88
480.88
Total
Cost
900.88
149.10
1,049.98
175.00
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1100(14) - Octagonal Junction Box
COST SHEET ID : Conduits, Boxes and Fittings
QUANTITY : 105.00 Piece PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
TOTAL COST
3,570.00
3,570.00
Total
Cost
961.76
961.76
Total
Cost
4,531.76
750.01
5,281.77
50.30
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1100(15) - Utility Box
COST SHEET ID : Conduits, Boxes and Fittings
QUANTITY : 135.00 Piece PRODUCTION RATE :
, NUMBER OF HOURS :
NONE
UNIT COST
TOTAL COST
4,320.00
4,320.00
Total
Cost
1,442.64
1,442.64
Total
Cost
5,762.64
953.72
6,716.36
49.75
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1100(22) - Grounding Rod Copperweld
COST SHEET ID : Conduits, Boxes and Fittings
QUANTITY : 5.00 length PRODUCTION RATE :
, NUMBER OF HOURS :
Electrician 2 2.00
NONE
UNIT COST
HOOL BUILDING
N RATE :
HOURS :
70.00 350.00
350.00
Hourly Total
Rate Cost
60.11 240.44
240.44
Hourly Total
Rate Cost
590.44
35.43
29.52
32.77
97.72
688.16
137.63
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1101(1) a2 - Electrical Wire
COST SHEET ID : Wires and Wiring Devices
QUANTITY : 15.00 rolls PRODUCTION RATE :
, NUMBER OF HOURS :
Electrician 2 30.00
NONE
UNIT COST
LDING
N RATE :
HOURS :
2,800.00 42,000.00
3,500.00 3,500.00
45,500.00
Hourly Total
Rate Cost
60.11 3,606.60
3,606.60
Hourly Total
Rate Cost
49,106.60
2,946.40
2,455.33
2,725.42
8,127.14
57,233.74
3,815.58
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1101(1) a3 - Wires and Wiring Devices
COST SHEET ID : Electrical Works
QUANTITY : 7.50 rolls PRODUCTION RATE :
, NUMBER OF HOURS :
Electrician 2 30.00
NONE
UNIT COST
LDING
N RATE :
HOURS :
36.00 27,000.00
36.00 36.00
27,036.00
Hourly Total
Rate Cost
60.11 3,606.60
3,606.60
Hourly Total
Rate Cost
30,642.60
1,838.56
1,532.13
1,700.66
5,071.35
35,713.95
4,761.86
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1101(1) a4 - Wires and Wiring Devices
COST SHEET ID : Electrical Works
QUANTITY : 1.80 rolls PRODUCTION RATE :
, NUMBER OF HOURS :
Electrician 2 30.00
NONE
UNIT COST
LDING
N RATE :
HOURS :
53.00 9,540.00
9,540.00
Hourly Total
Rate Cost
60.11 3,606.60
3,606.60
Hourly Total
Rate Cost
13,146.60
788.80
657.33
729.64
2,175.76
15,322.36
8,512.42
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1101(2) - Tumbler Switch Single Pole
COST SHEET ID : Wires and Wiring Devices
QUANTITY : 18.00 pcs PRODUCTION RATE :
, NUMBER OF HOURS :
Electrician 2 8.00
NONE
UNIT COST
LDING
N RATE :
HOURS :
125.00 2,250.00
2,250.00
Hourly Total
Rate Cost
60.11 961.76
961.76
Hourly Total
Rate Cost
3,211.76
192.71
160.59
178.25
531.55
3,743.31
207.96
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1101(3) - Tumbler Switch
COST SHEET ID : Wires and Wiring Devices
QUANTITY : 48.00 pcs PRODUCTION RATE :
, NUMBER OF HOURS :
Electrician 2 8.00
NONE
UNIT COST
LDING
N RATE :
HOURS :
185.00 8,880.00
8,880.00
Hourly Total
Rate Cost
60.11 961.76
961.76
Hourly Total
Rate Cost
9,841.76
590.51
492.09
546.22
1,628.81
11,470.57
238.97
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1101(4) - Tumbler Switch
COST SHEET ID : Wires and Wiring Devices
QUANTITY : 6.00 pcs PRODUCTION RATE :
, NUMBER OF HOURS :
Electrician 2 8.00
NONE
UNIT COST
LDING
N RATE :
HOURS :
250.00 1,500.00
1,500.00
Hourly Total
Rate Cost
60.11 961.76
961.76
Hourly Total
Rate Cost
2,461.76
147.71
123.09
136.63
407.42
2,869.18
478.20
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1101(5) - Tumbler Switch
COST SHEET ID : Wires and Wiring Devices
QUANTITY : 36.00 pcs PRODUCTION RATE :
, NUMBER OF HOURS :
Electrician 2 8.00
NONE
UNIT COST
LDING
N RATE :
HOURS :
125.00 4,500.00
4,500.00
Hourly Total
Rate Cost
60.11 961.76
961.76
Hourly Total
Rate Cost
5,461.76
327.71
273.09
303.13
903.92
6,365.68
176.82
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1101(6) - Duplex Convenience Receptacle
COST SHEET ID : Wires and Wiring Devices
QUANTITY : 45.00 set PRODUCTION RATE :
, NUMBER OF HOURS :
Electrician 2 8.00
NONE
UNIT COST
BUILDING
N RATE :
HOURS :
180.00 6,480.00
210.00 1,890.00
8,370.00
Hourly Total
Rate Cost
60.11 961.76
961.76
Hourly Total
Rate Cost
9,331.76
559.91
466.59
517.91
1,544.41
10,876.17
241.69
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1102(1) - Panel Boards Safety Switch Type
COST SHEET ID : Power Load Center, Swicthgear and Panel Boards
QUANTITY : 1.00 set PRODUCTION RATE :
, NUMBER OF HOURS :
Panel Board DP
Main : 125AT, 2p, 100AF, 240V
Branches : 2-15AT, to 30AT, 2P, 240V (Plug in type) set 1.00
Circuit Breaker
15 ACB, 20 ACB, 30 ACB to 100ACB set 1.00
NONE
UNIT COST
HOOL BUILDING
3,100.00 3,100.00
3,500.00 3,500.00
6,600.00
Hourly Total
Rate Cost
60.11 1,202.20
1,202.20
Hourly Total
Rate Cost
7,802.20
468.13
390.11
433.02
1,291.26
9,093.46
9,093.46
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1103(1) a4 - Fluorescent lighting Fixture
COST SHEET ID : Lighting Fixture
QUANTITY : 168.00 set PRODUCTION RATE :
, NUMBER OF HOURS :
1 x 36w Flourescent Lamp fixtures w/ box type case set 60.00 546.00
2 x 36w Flourescent Lamp fixtures w/ box type case set 108.00 980.00
NONE
UNIT COST
TOTAL COST
32,760.00
105,840.00
138,600.00
Total
Cost
14,426.40
14,426.40
Total
Cost
153,026.40
25,325.87
178,352.27
1,061.62
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1103(2) a1 - Porcelain Keyless Receptacle case w/ 18w softone bulb
COST SHEET ID : Lighting Fixture
QUANTITY : 12.00 set PRODUCTION RATE :
, NUMBER OF HOURS :
Porcelain Keyless Receptacle case w/ 18w softone bulb set 12.00 235.00
NONE
UNIT COST
TOTAL COST
2,820.00
2,820.00
Total
Cost
6,011.00
6,011.00
Total
Cost
8,831.00
1,461.53
10,292.53
857.71
Unit Price Analysis
JOB : CONSTRUCTION OF THREE(3) STOREY - EIGHTEEN(18) CLASSROOMS SCHOOL BUILDING
PAY ITEMS : Item 1208(2) b1 GI Pipe Railings
COST SHEET ID : Miscellaneous Hardwares
QUANTITY : 65.10 mts PRODUCTION RATE :
, NUMBER OF HOURS :
Corridor Handrail
G.I Pipe x 3m - sch. 40
50mm dia x hand railings mts 34.80
19mm dia x Square bar baluster kgs 1,122.40
Stairway railings
G.I Pipe x 3m - sch. 40
50mm dia x hand railings mts 11.50
19mm dia x Square bar baluster kgs 708.58
PWD Handrail Stainless
Stainless Steel Pipe x 3m -
38mm dia x hand railings mts 2.00
Ramp railings
G.I Pipe x 3m - sch. 40
38mm dia x hand railings mts 9.13
38mm dia x Railings support mts 7.67
Stair Nosing
25mm x 25mm x 2mm Angle bar kgs 134.40
12mm x 12mm x 2mm Flat bar strap kgs 11.20
Welding Rod kls 12.00
Welding Rod for Stainless Steel Pipe kls 4.00
NONE
UNIT COST
UILDING
N RATE :
HOURS :
2,312.50 80,475.00
45.00 50,508.00
2,312.50 26,593.75
45.00 31,885.92
-
-
3,260.00 6,520.00
-
-
1,850.00 16,896.67
1,850.00 14,183.33
-
75.23 10,111.25
75.23 842.60
150.00 1,800.00
1,275.00 5,100.00
-
244,916.52
Hourly Total
Rate Cost
60.11 72,132.00
72,132.00
Hourly Total
Rate Cost
317,048.52
19,022.91
15,852.43
17,596.19
52,471.53
369,520.05
5,676.19
Materials Price Data
Price Unit Hauling
Aluminum Cladding Panel 4mm x 1200mm x 2400mm 2,200.00 sq.m
Assorted C.W. Nails 75.00 kgs.
CHB - 4" x 8" x 16" 10.00 pc.
CHB - 6" x 8" x 16" 12.00 pc.
Stone Masonry 660.00 cu.m
Coco lumber 19.00 bd.ft
Lumber Good 45.00 bd.ft
Red or White Lau-an 50.00 bd.ft
Yakal 80.00 bd.ft
STEEL BARS
Reinforcing Steel Bars 45.00 kgs.
Structural Steel Angular Bar (A36) 75.00 kgs.
Anchor Bolts with Nuts & Washer 110.00 kgs.
Machine Bolts with Nuts & Washer 130.00 kgs.
Steel Deck 550.00 kgs.
Roofing Materials
Pre-painted Metal Roofing Sheet GA. 26 (Long span) 494.00 sq.m
Corrugated Roofing sheets GA. 26 480.00 sq.m
Pre-painted Gutter GA. 24 434.00 ln m
Pre-painted Flashing GA. 24 396.00 ln.m
Pre-painted Ridge Roll GA. 24 250.00 ln.m
Roof Ventilators 1,000.00 set
Painting Materials
Paint Tinting Color 400.00 ltr.
Paint Enamel 908.00 gal.
Paint Latex Gloss 908.00 gal.
Paint latex Semi Gloss 908.00 gal.
Paint Red Lead 800.00 gal.
Thinner Paint 500.00 gal.
Thinner Lacquer 650.00 gal.
Concrete Neutralizer 110.00 ltr.
Brush Paint (101mm) 150.00 pc
Brush Roller (152mm) 180.00 pc
Sand Paper 1,600.00 roll
Solignum (Termite Control) Clear 1,200.00 lrt
Plumbing Works
Water Closet Including Fittings and Accy. 7,500.00 set
Lavatory Including Fittings and Accy. 6,550.00 set
Urinals Including Fittings and Accy. 8,500.00 set
Shower Head with Valve 1,200.00 set
Soap Holder 650.00 set
Kitchen Sink 3,800.00 set
Floor Drain 180.00 set
Paper Holder 480.00 set
Mirror 650.00 sq.ft
Solvent Cement 380.00 can
Tefflon Tape 30.00 roll
Gate Valve 25mm dia. 650.00 pc
Water Meter 1,800.00 pc
Cylindrical Water Tank (500 gals) 18,000.00 set
PVC Pipe (101mm dia.) 798.00 pc
PVC Pipe (76mm dia.) 650.00 pc
PVC Pipe (50mm dia.) 350.00 pc
PVC Pipe 45 deg. (3mm Bend x 101mm) 61.00 pc
PVC Pipe 45 deg. (3mm Bend x 76mm) 40.00 pc
PVC Pipe 45 deg. (3mm Bend x 50mm) 35.00 pc
PVC Pipe 87 deg. (6mm Bend x 101mm) 82.00 pc
PVC Pipe 87 deg. (6mm Bend x 76mm) 55.00 pc
PVC Pipe 87 deg. (6mm Bend x 50mm) 34.00 pc
PVC Pipe 45 deg. Single Branch, WYE (50mm x 50mm) 82.00 pc
PVC Pipe 45 deg. Single Branch, WYE (101mm x 50mm) 198.00 pc
PVC Pipe 45 deg. Single Branch, WYE (101mm x 76mm) 235.00 pc
PVC Pipe 45 deg. Single Branch, WYE (101mm x 101mm) 250.00 pc
PVC P-Trap w/ Plug & Sealing Ring(101mm) 545.00 pc
PVC P-Trap w/ Plug & Sealing Ring(76mm) 385.00 pc
PVC P-Trap w/ Plug & Sealing Ring(50mm) 215.00 pc
PVC Clean Out w/ Plug & Sealing Ring(101mm) 120.00 pc
PVC Clean Out w/ Plug & Sealing Ring(76mm) 75.00 pc
PVC Clean Out w/ Plug & Sealing Ring(50mm) 45.00 pc
Electrical Works
Service Entrance Cap (19mm dia.) 100.00 pc
Eletrical Rigid Steel Conduit (19mm dia.) 504.00 pc
Bushing and Locknut (19mm) 10.00 pc
PVC Conduit Pipe (3m x 19mm dia.) 96.00 pc
Octagonal Junction Box Type guage #16(101mmx101mmx53mm) 34.00 pc
Utility Box guage # 16 (50mmx101mmx53mm) Deep Type 32.00 pc
Eletrical Wires THWN / THHN 2.0 mm2 30.00 mtr
Eletrical Wires THWN / THHN 3.5 mm2 35.00 mtr
Eletrical Wires THWN / THHN 5.5 mm2 40.00 mtr
Single gang Switch 100.00 set
Two-gang Switch 146.00 set
Three-gang Switch 320.00 set
Duplex Convenience Outlet 195.00 set
Telephone Outlet RJ 45 242.00 set
Polarized 3-prongs (ACU Outlet) 472.00 set
Eclosed Air Circuit Breaker 100AF, 3P, 220V,70AT 1,600.00 set
Eclosed Air Circuit Breaker 50AF, 3P, 220V,40AT 1,312.00 set
Eclosed Air Circuit Breaker 50AF, 2P, 220V,40AT 1,240.00 set
Electrical Tape 38.00 pc
Panel Board & Cabinets (Enclosed 60AMP,2 PST) 1,627.00 set
1 x 20 W Box Type FLF 451.00 set
1 x 40 W Troofer Type Aluminum Louver Recess 1,500.00 set
6" dia. Pinlinght with 18W 220 V CFL 567.00 set
Air Conditioner Window Type 1.0 HP 220V 19,587.00 unit
Air Conditioner Window Type 1.5 HP 220V 23,450.00 unit
878.51
878.51
878.51
264.51
828.51
828.51
828.51
25,000.00
1,450.00
100.00
65.00
900.00
2,000.00
45.00
75.00
110.00
130.00
550.00
388.00
765.00
606.00
1,152.00
-
1,850.00
2,771.00
8,000.00
494.00
480.00
434.00
396.00
250.00
1,000.00
400.00
908.00
908.00
908.00
800.00
500.00
650.00
110.00
150.00
180.00
1,600.00
1,200.00
7,500.00
6,550.00
8,500.00
1,200.00
650.00
3,800.00
180.00
480.00
650.00
380.00
30.00
650.00
1,800.00
18,000.00
798.00
650.00
350.00
61.00
40.00
35.00
82.00
55.00
34.00
82.00
198.00
235.00
250.00
545.00
385.00
215.00
120.00
75.00
45.00
-
-
100.00
504.00
10.00
96.00
34.00
32.00
30.00
35.00
40.00
100.00
146.00
320.00
195.00
242.00
472.00
1,600.00
1,312.00
1,240.00
38.00
1,627.00
451.00
1,500.00
567.00
19,587.00
23,450.00
Materials
price w/ Hauling Cost
GI Pipe - 38mm dia 2,312.50 2,312.50
Assorted C.W. Nails 75.00
CHB - 4" x 8" x 16" 10.00
CHB - 6" x 8" x 16" 12.00
Fiber Cement Board - 1/4" x 4' x 8' 450.00 0.62 450.62
Coco lumber 19.00
Gravel - 3/4" 650.00 811.14 811.14
Gravel - 3/4" - 2" 650.00 811.14 811.14
Gravel/Earth Fill 650.00 708.91 708.91
Marine Plywood - 1/4" x 4' x 8' 388.00
Marine Plywood - 1/2" x 4' x 8' 765.00
Portland Cement 260.00 3.09 263.09
Reinforcing Def. Steel Bars 45.00 0.12 45.12
Reinforcing Pln. Steel Bars 47.00 0.12 47.12
Sand 600.00 741.66 741.66
Screened Sand 600.00 741.66 741.66
Mixed Sand & Gravel w/ Boulders 600.00 783.83 783.83
Stainless Steel Pipe & Tubular 75mm dia ssp & 50mm x 100mm tubular 25,000.00
Tarpaulin w/ printed signs ready for installation 4"x8" 1,450.00
Washed Sand 600.00 741.66 741.66
#16 G.I. Tie Wire 100.00
Embankment 633.00 708.91 708.91
Concrete Nail 150.00
Roofing Sheets 494.00 2.91 496.91
Structural Angular 75.00 0.23 75.23
Anchor Bolt w/ n&w 110.00 0.23 110.23
CHB-4 10.00 0.17 10.17
CHB-6 12.00 0.25 12.25
Carpenter 60.11
Construction Foreman 72.15
Electrician 60.11
Installer/Skilled Laborer 60.11
Laborer 40.35
Mason 60.11
Safety Officer (Part Time) 245.00
Skilled Laborer 60.11
Steelman 60.11
Tiles Setter/Skilled Laborer 60.11
Welder 60.11
Description Operated Hourly Rate
owned?
9,117.04 1,139.63 9,117.04
7,488.00 6 liter/hour 749.00 5,992.00
10,792.00 8 liter/hour 1,079.00 8,632.00
12,296.00 9 liter/hour 1,229.00 9,832.00
6,720.00 5 liter/hour 672.00 5,376.00
16,599.60 12 liter/hour 1,659.15 13,273.20
1,758.00 219.75 1,758.00
2,812.00 351.50 2,812.00
9,664.24 351.50 2,812.00
18,392.00 13 liter/hour 1,839.00 14,712.00
8,816.00 13 liter/hour
Quarry Source : Simulao River, Sta. Maria, Trento, Agusan del Sur
Hauling distance: 47.00 kms.
where:
Conc. Pavement = 40.00 kms. ; Gravel Maintained = 5.00 kms. ; Gravel Poorly Maintained 2.00
Hauling Assumption:
Concrete Gravel ( Maintained ) Gravel (Poorl
Speed empty: 55 kph 35 kph 25
Speed loaded: 35 kph 30 kph 15
Balance Fleet;
1 Payloader 4.00 days
9 Dumptruck 4.00 days
I. Direct Cost
A.Equipment
C.Materials Cost
1,000.00 cu.m. @ Php 296.83 =
(Poorly M )
kph
kph
min.
min.
days
55,456.00
389,376.00
Php 444,832.00
Php 296,832.00
Name of Project Construction of Standard Two-Storey eighteen Classrooms SchoolBuilding -
under Basic Educational Facilities Find (BEFF) - Batch 3
Location @ Agusan del Sur NHS, San Francisco, ADS
Limits
Quarry Source : Simulao River, Sta. Maria, Trento, Agusan del Sur
Hauling distance: 47.00 kms.
where:
Conc. Pavement = 40.00 kms. ; Gravel Maintained = 5.00 kms. ; Gravel Poorly Maintained =
I. Direct Cost
A.Equipment
1 unit Payloader for 9.00 days @
1 unit Bulldozer for 5.50 days @
1 unit Screen for 9.00 days @
C.Materials Cost
1,000.00 cu.m. @
13,864.00 = 124,776.00
18,392.00 = 101,156.00
100.00 = 900.00
226,832.00
70.00 = 70,000.00
70,000.00
296,832.00
296.83 /cu.m.
Name of Project Construction of Standard Two-Storey eighteen Classrooms SchoolBuilding -
under Basic Educational Facilities Find (BEFF) - Batch 3
Location @ Agusan del Sur NHS, San Francisco, ADS
Limits
DESCRIPTION: Gravel
Quantity : 1,000.00 cu.m.
30% Passing
Volume 3,333.33 cu.m.
Quarry Source : Simulao River, Sta. Maria, Trento, Agusan del Sur
Hauling distance: 47.00 kms.
where:
Conc. Pavement = 40.00 kms. ; Gravel Maintained = 5.00 kms. ; Gravel Poorly Maintained = 2.00
Hauling Assumption:
Concrete Gravel ( Maintained ) Gravel (Poorly M
Speed empty: 55 kph 35 kph 25
Speed loaded: 35 kph 30 kph 15
Balance Fleet;
1 Payloader 4.00 days
9 Dumptruck 4.00 days
I. Direct Cost
A.Equipment
C.Materials Cost
1,000.00 cu.m. @ Php 366.31 =
oorly M )
kph
kph
min.
min.
days
55,456.00
389,376.00
Php 444,832.00
Php 366,312.00
Name of Project Construction of Standard Two-Storey eighteen Classrooms SchoolBuilding -
under Basic Educational Facilities Find (BEFF) - Batch 3
Location @ Agusan del Sur NHS, San Francisco, ADS
Limits
Quarry Source : Simulao River, Sta. Maria, Trento, Agusan del Sur
Hauling distance: 47.00 kms.
where:
Conc. Pavement = 40.00 kms. ; Gravel Maintained = 5.00 kms. ; Gravel Poorly Maintained = 2.00
I. Direct Cost
A.Equipment
1 unit Payloader for 12.00 days @ 13,864.00 =
1 unit Bulldozer for 7.00 days @ 18,392.00 =
1 unit Screen for 12.00 days @ 100.00 =
C.Materials Cost
1,000.00 cu.m. @ 70.00 =
days
days
166,368.00
128,744.00
1,200.00
296,312.00
70,000.00
70,000.00
Name of Project Construction of Standard Two-Storey eighteen Classrooms SchoolBuilding -
under Basic Educational Facilities Find (BEFF) - Batch 3
Location @ Agusan del Sur NHS, San Francisco, ADS
Limits K1355+560 - K1355+660
DESCRIPTION: Embankment
Quantity : 1,000.00 cu.m.
Quarry Source : Simulao River, Sta. Maria, Trento, Agusan del Sur
Hauling distance: 47.00 kms.
where:
Conc. Pavement = 40.00 kms. ; Gravel Maintained = 5.00 kms. ; Gravel Poorly Maintained = 2.00
Hauling Assumption:
Concrete Gravel ( Maintained ) Gravel (P
Speed empty: 55 kph 35 kph 25
Speed loaded: 35 kph 30 kph 15
Balance Fleet;
1 Payloader 4.00 days
7 Dumptruck 4.00 days
I. Direct Cost
A.Equipment
C.Materials Cost
1,000.00 cu.m. @ Php 350.61 =
Poorly M )
kph
kph
min.
min.
days
55,456.00
302,848.00
Php 358,304.00
Php 350,607.20
Name of Project Construction of Standard Two-Storey eighteen Classrooms SchoolBuilding -
under Basic Educational Facilities Find (BEFF) - Batch 3
Location @ Agusan del Sur NHS, San Francisco, ADS
Limits
Quarry Source : Simulao River, Sta. Maria, Trento, Agusan del Sur
Hauling distance: 47.00 kms.
where:
Conc. Pavement = 40.00 kms. ; Gravel Maintained = 5.00 kms. ; Gravel Poorly Maintained =
20% Passing
Bulldozer Capability for Quarrying = 480.00 cu.m./day
= 1,000.00 / 480.00 = 2.08 days say
Manual labor cap. for pick-up & stock-piling = 1.50 cu.m.. / m.d.
= 1,000.00 cu.m. / ( 1.50 cu.m./m.d. ) x 14.00 Laborer ) =
say
I. Direct Cost
A.Equipment
1 unit Bulldozer for 2.50 days @ 18,392.00
B. Labor
1 Construction Foreman for 48.00 days @ 577.20
14 Laborers for 48.00 days @ 322.80
C.Materials Cost
1,000.00 cu.m. @ 60.00
2.50 days
47.62 days
48.00 days
= 45,980.00
= 27,705.60
= 216,921.60
244,627.20
= 60,000.00
60,000.00
/cu.m.
Name of Project Construction of Standard Two-Storey eighteen Classrooms SchoolBuilding -
under Basic Educational Facilities Find (BEFF) - Batch 3
Location @ Agusan del Sur NHS, San Francisco, ADS
Limits
DESCRIPTION: Boulders
Quantity : 1,000.00 cu.m.
where:
Conc. Pavement = 30.00 kms. ; Gravel Maintained = 37.00 kms. ; Gravel Poorly Maintained = 0.00
Hauling Assumption:
Concrete Gravel ( Maintained ) Gravel (Poorly M
Speed empty: 55 kph 35 kph 25
Speed loaded: 35 kph 30 kph 15
Balance Fleet;
1 Payloader 2.50 days
14 Dumptruck 2.50 days
I. Direct Cost
A.Equipment
C.Materials Cost
1,000.00 cu.m. @ Php 370.61 =
Poorly M )
kph
kph
min.
min.
days
34,660.00
378,560.00
Php 413,220.00
Php 370,607.20
Name of Project REPAIR / MAINTENANCE OF ROADSLIP ALONG BUTUAN CITY - TALACOGON - LORETO - VERUELA - ST
(S00440MN)
Location OSMEÑA, LA PAZ, AGUSAN DEL SUR
Limits K1355+560 - K1355+660
where:
Conc. Pavement = 30.00 kms. ; Gravel Maintained = 37.00 kms. ; Gravel Poorly Maintained =
20% Passing
Bulldozer Capability for Quarrying = 480.00 cu.m./day
= 1,000.00 / 480.00 = 2.08 days say
Manual labor cap. for pick-up & stock-piling = 1.50 cu.m.. / m.d.
= 1,000.00 cu.m. / ( 1.50 cu.m./m.d. ) x 14.00 Laborer ) =
say
I. Direct Cost
A.Equipment
1 unit Bulldozer for 2.50 days @ 18,392.00
B. Labor
1 Construction Foreman for 48.00 days @ 577.20
14 Laborers for 48.00 days @ 322.80
C.Materials Cost
1,000.00 cu.m. @ 80.00
0.00 kms.
2.50 days
47.62 days
48.00 days
= 45,980.00
= 27,705.60
= 216,921.60
244,627.20
= 80,000.00
80,000.00
/cu.m.
RSB Hauling Cost from DPWH ADS II DEO to Project Site
Hauling Dist. ; = 5 kms. Conc. = 5 kms. Gravel M. = 0 kms. Gravel P.M. = 0 kms
Hauling Assumption;
Concrete Gravel ( Maintained ) Gravel (Poorly M )
Speed empty : 55 kph 35 kph 25 kph
Speed loaded: 35 kph 30 kph 15 kph
I. Direct Cost
B.Equipment
Hauling Dist. ; = 10 kms. Conc. = 10 kms. Gravel M. = 0 kms. Gravel P.M. = 0 kms
Hauling Assumption;
Concrete Gravel ( Maintained ) Gravel (Poorly M )
Speed empty : 55 kph 35 kph 25 kph
Speed loaded: 35 kph 30 kph 15 kph
I. Direct Cost
B.Equipment
Hauling Dist. ; = 10 kms. Conc. = 10 kms. Gravel M. = 0 kms. Gravel P.M. = 0 kms
Hauling Assumption;
Concrete Gravel ( Maintained ) Gravel (Poorly M )
Speed empty : 55 kph 35 kph 25 kph
Speed loaded: 35 kph 30 kph 15 kph
I. Direct Cost
B.Equipment
Hauling Dist. ; = 80 kms. Conc. = 80 kms. Gravel M. = 0 kms. Gravel P.M. = 0 kms
Hauling Assumption;
Concrete Gravel ( Maintained ) Gravel (Poorly M )
Speed empty : 55 kph 35 kph 25 kph
Speed loaded: 35 kph 30 kph 15 kph
I. Direct Cost
B.Equipment
Hauling Dist. ; = 10 kms. Conc. = 10 kms. Gravel M. = 0 kms. Gravel P.M. = 0 kms
Hauling Assumption;
Concrete Gravel ( Maintained ) Gravel (Poorly M )
Speed empty : 55 kph 35 kph 25 kph
Speed loaded: 35 kph 30 kph 15 kph
I. Direct Cost
B.Equipment
Hauling Dist. ; = 5 kms. Conc. = 5 kms. Gravel M. = 0 kms. Gravel P.M. = 0 kms
Hauling Assumption;
Concrete Gravel ( Maintained ) Gravel (Poorly M )
Speed empty : 55 kph 35 kph 25 kph
Speed loaded: 35 kph 30 kph 15 kph
I. Direct Cost
B.Equipment
Hauling Dist. ; = 5 kms. Conc. = 5 kms. Gravel M. = 0 kms. Gravel P.M. = 0 kms
Hauling Assumption;
Concrete Gravel ( Maintained ) Gravel (Poorly M )
Speed empty : 55 kph 35 kph 25 kph
Speed loaded: 35 kph 30 kph 15 kph
I. Direct Cost
B.Equipment
EXECUTIVE SUMMARY 1
DESCRIPTION QUANTITY
RSB # 16 G.I. Tie PORTLAND SAND
CEMENT
(kgs.) (kgs.) (bags) (cu.m.)
EXECUTIVE SUMMARY 2
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
DESCRIPTION UNIT
EXCAVATION: cu.m.
BACKFILL : cu.m.
EMBANKMENT: cu.m.
WINDOWS sq.m.
JAMB bd ft
DOORS sq.m.
JAMB bd ft
CARPENTRY WORKS
Ceiling Panel pcs
angle - 20mmx20mmx3mm pcs
19mmx50mmx0.8mmx5mm pcs
12mmx38mmx0.6mmx5mm pcs
adjustment spring or clip & rod joiner pcs
preformed wire clip pcs
blind rivets - 1/8" x 1/2" pcs
Ceiling Ventillation - 0.30m x 1.1750m bd ft
wire screen sq mts
Fascia Board - 12mm x 1.20mm x 2.40mm ficem pcs
tekscrew pcs
CWN klg.
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
concrete klg.
ROOF AND FRAMING WORKS
Roofing sq mts
area sq mts
gutter l.m.
ridge roll l.m.
end-flushing l.m.
J-Bolt pcs
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
@ top F-2
No. of Pcs. Bar length Total Length (m) Unit wt. (kgs./m)
Bar ø (mm)
X 20.00 20.00 3.50 70.00 1.01
Y 20.00 20.00 3.50 70.00 1.01
CF - 1 8,742.16 CF - 1
F-2 4,250.40 F-2
Total RSB for footing = 12,992.56 Total #16 G.I. Tie =
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
COLUMN
C-1
No. of Pcs. Bar length Total Length (m) Unit wt. (kgs./m)
Bar ø
FDN TO GF
25.00 12.00 2.10 25.20 3.85
12.00 21.00 3.90 81.90 0.89
GF TO 2F
25.00 4.00 4.17 16.66 3.85
20.00 8.00 4.17 33.32 1.01
12.00 24.00 3.90 93.60 0.89
12.00 36.00 3.90 140.40 0.89
2F TO 3F
20.00 12.00 3.84 46.08 1.01
12.00 22.00 3.90 85.80 0.89
12.00 32.00 3.90 124.80 0.89
3F TO ROOF
20.00 12.00 3.84 46.08 1.01
12.00 22.00 3.90 85.80 0.89
12.00 32.00 3.90 124.80 0.89
C-2
No. of Pcs. Bar length Total Length (m) Unit wt. (kgs./m)
Bar ø
FDN TO GF
25.00 12.00 2.10 25.20 3.85
12.00 21.00 6.00 126.00 0.89
GF TO 2F
25.00 12.00 4.17 49.98 3.85
12.00 24.00 5.64 135.36 0.89
12.00 36.00 5.64 203.04 0.89
2F TO 3F
25.00 12.00 3.84 46.08 3.85
12.00 22.00 5.40 118.80 0.89
12.00 32.00 5.40 172.80 0.89
3F TO ROOF
25.00 12.00 3.84 46.08 3.85
12.00 22.00 4.40 96.80 0.89
12.00 32.00 4.40 140.80 0.89
C-3
No. of Pcs. Bar length Total Length (m) Unit wt. (kgs./m)
Bar ø
FDN TO GF
25.00 12.00 2.45 29.40 3.85
12.00 21.00 5.74 120.54 0.89
GF TO 2F
25.00 12.00 4.17 49.98 3.85
12.00 24.00 5.40 129.60 0.89
12.00 36.00 5.40 194.40 0.89
2F TO 3F
25.00 12.00 3.84 46.08 3.85
12.00 22.00 5.40 118.80 0.89
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
3F TO ROOF
25.00 12.00 3.84 46.08 3.85
12.00 22.00 4.40 96.80 0.89
12.00 32.00 4.40 140.80 0.89
DC - 1
No. of Pcs. Bar length Total Length (m) Unit wt. (kgs./m)
Bar ø
FDN TO GF
16.00 4.00 1.95 7.80 1.01
10.00 11.00 0.70 7.70 0.62
GF TO 2F
16.00 4.00 1.95 7.80 1.01
10.00 11.00 0.70 7.70 0.62
PC - 1
No. of Pcs. Bar length Total Length (m) Unit wt. (kgs./m)
Bar ø
FDN TO GF
16.00 4.00 2.85 11.40 1.01
10.00 17.00 1.00 17.00 0.62
TIE BEAM TB 1
No. of Pcs. Bar length Total Length (m) Unit wt. (kgs./m)
Bar ø
TB 2
No. of Pcs. Bar length Total Length (m) Unit wt. (kgs./m)
Bar ø
TB 3
No. of Pcs. Bar length Total Length (m) Unit wt. (kgs./m)
Bar ø
FB 1
No. of Pcs. Bar length Total Length (m) Unit wt. (kgs./m)
Bar ø
FDN
16.00 2.00 4.85 9.70 1.01
16.00 1.00 2.25 2.25 1.01
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
STB 1
No. of Pcs. Bar length Total Length (m) Unit wt. (kgs./m)
Bar ø
FDN TO GF
16.00 2.00 3.35 6.70 1.01
16.00 1.00 1.68 1.68 1.01
16.00 2.00 1.30 2.60 1.01
16.00 2.00 3.35 6.70 1.01
10.00 30.00 1.30 39.00 0.62
STB 2
No. of Pcs. Bar length Total Length (m) Unit wt. (kgs./m)
Bar ø
FDN TO GF
16.00 2.00 3.35 6.70 1.01
16.00 2.00 1.68 3.35 1.01
16.00 2.00 2.25 4.50 1.01
16.00 2.00 3.35 6.70 1.01
10.00 30.00 1.30 39.00 0.62
TB 1 1,159.85 TB 1
TB 2 3,153.06 TB 2
TB 3 4,422.11 TB 3
FB 1 136.80 FB 1
STB 1 167.64 STB 1
RC SLAB STB 2 182.12 STB 2
Total RSB for footing = 9,221.58 Total #16 G.I. Tie =
SLAB @ ground
No. of Pcs. Bar length Total Length (m) Unit wt. (kgs./m)
Bar ø
GF
10.00 29.00 63.35 1,837.15 0.62
10.00 181.00 9.85 1,782.85 0.62
bend1
cut1
2F & 3F SLAB 3 two slab @ 4.5mts
bend1a 10.00 7.00 9.70 67.90 0.62
cut1a 10.00 7.00 4.50 31.50 0.62
@ 2.5mts
temperature/straight 2.00 10.00 12.00 5.70 68.40 0.62
10.00 12.00 5.70 68.40 0.62
temperature/straight 2.00 @ 4.5mts
10.00 7.00 9.70 67.90 0.62
@ 2.5mts
3.00 10.00 12.00 5.70 68.40 0.62
bend1
cut1
2F & 3F SLAB 4 two slab @ 4.5mts
bend1a 10.00 7.00 9.70 67.90 0.62
cut1a 10.00 7.00 4.50 31.50 0.62
@ 2.5mts
temperature/straight 2.00 10.00 12.00 5.70 68.40 0.62
10.00 12.00 5.70 68.40 0.62
temperature/straight 2.00 @ 4.5mts
10.00 7.00 9.70 67.90 0.62
@ 2.5mts
3.00 10.00 12.00 5.70 68.40 0.62
bend1
cut1
2F & 3F SLAB 5 two slab @ 4.5mts
bend1a 10.00 14.00 9.70 135.80 0.62
cut1a 10.00 14.00 4.50 63.00 0.62
@ 3.15mts
temperature/straight 2.00 10.00 12.00 7.00 84.00 0.62
10.00 12.00 7.00 84.00 0.62
temperature/straight 2.00 @ 4.5mts
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
bend1
cut1
2F & 3F SLAB 6 two slab @ 3.75mts
bend1a 10.00 4.00 8.20 32.80 0.62
cut1a 10.00 4.00 3.75 15.00 0.62
@ 1.5mts
temperature/straight 2.00 10.00 10.00 3.70 37.00 0.62
10.00 10.00 3.70 37.00 0.62
temperature/straight 2.00 @ 3.75mts
10.00 10.00 8.20 82.00 0.62
@ 1.5mts
3.00 10.00 4.00 3.70 14.80 0.62
SLAB 1 10,372.45
SLAB 2 9,934.85
SLAB 3 7,522.10
SLAB 4 1,253.68
SLAB 5 1,986.97
SLAB 6 777.15
Total RSB for Slabs = 31,847.20 Total #16 G.I. Tie =
G-2
No. of Pcs. Bar length Total Length (m) Unit wt. (kgs./m)
Bar ø
G-3
No. of Pcs. Bar length Total Length (m) Unit wt. (kgs./m)
Bar ø
G-4
No. of Pcs. Bar length Total Length (m) Unit wt. (kgs./m)
Bar ø
G-5
No. of Pcs. Bar length Total Length (m) Unit wt. (kgs./m)
Bar ø
G-6
No. of Pcs. Bar length Total Length (m) Unit wt. (kgs./m)
Bar ø
20.00 3.00 2.85 8.55 1.01
20.00 1.00 1.60 1.60 1.01
20.00 3.00 2.85 8.55 1.01
10.00 20.00 1.70 34.00 0.62
G-7
No. of Pcs. Bar length Total Length (m) Unit wt. (kgs./m)
Bar ø
25.00 2.00 7.35 14.70 3.85
25.00 3.00 3.85 11.55 3.85
25.00 2.00 3.85 7.70 3.85
25.00 2.00 7.35 14.70 3.85
10.00 56.00 1.90 106.40 0.62
G-8
No. of Pcs. Bar length Total Length (m) Unit wt. (kgs./m)
Bar ø
B-1
No. of Pcs. Bar length Total Length (m) Unit wt. (kgs./m)
Bar ø
B-2
No. of Pcs. Bar length Total Length (m) Unit wt. (kgs./m)
Bar ø
B-3
No. of Pcs. Bar length Total Length (m) Unit wt. (kgs./m)
Bar ø
- G-1 814.23
G-2 918.95
G-3 918.95
G-4 78.47
G-5 251.51
RAMP G-6 518.29
G-7 506.08
G-8 3,080.19
B-1 1,243.16
B-2 120.87
B-3 89.54
Total RSB for Slabs = 8,540.24 Total #16 G.I. Tie =
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
RAMP
No. of Pcs. Bar length Total Length (m) Unit wt. (kgs./m)
Bar ø
RAMP 59.70
Total RSB for Slabs = 59.70 Total #16 G.I. Tie =
CONCRETE STAIR
No. of Pcs. Bar length Total Length (m) Unit wt. (kgs./m)
Bar ø
SUNBREAKER
No. of Pcs. Bar length Total Length (m) Unit wt. (kgs./m)
Bar ø
SUNBREAKER 680.06
Total RSB for Slabs = 680.06 Total #16 G.I. Tie =
PUBLIC WORKS AND HIGHWAYS
UTIVE SUMMARY 1
QUANTITY
GRAVEL CHB
(cu.m.)
268.62
134.24
52.73
59.85
117.27
103.04
36.40
12.15
1.70
33.74
6,396.00
17,159.00
13.53
UTIVE SUMMARY 2
PUBLIC WORKS AND HIGHWAYS
QUANTITY REMARKS
17,833.00
34.80
48.40
2.00
9.13
7.67
130.00
2,492.54
997.31
48.84
179.55
232.70
3,158.00
91.74
1,004.67
694.27
328.20
578.31
66.91
2,692.08
1,459.69
16,200.00
260.00
15.60
16.29
260.67
18.00
PUBLIC WORKS AND HIGHWAYS
12.00
927.21
693.00
126.00
63.00
22.00
9,900.00
PUBLIC WORKS AND HIGHWAYS
@ FOOTING ONLY
Total Wt. (kgs.) Remarks
@ FOOTING ONLY
Total Wt. (kgs.) Remarks
159.62
67.92
227.55
PUBLIC WORKS AND HIGHWAYS
@ COLUMN ONLY
Total Wt. (kgs.) Remarks
@ COLUMN ONLY
Total Wt. (kgs.) Remarks
153.45 Ties
436.53
@ COLUMN ONLY
Total Wt. (kgs.) Remarks
0.77
192.57
192.57
192.57
7.97
0.77
586.44
PUBLIC WORKS AND HIGHWAYS
@ TB ONLY
Total Wt. (kgs.) Remarks
@ TB ONLY
Total Wt. (kgs.) Remarks
@ TB ONLY
Total Wt. (kgs.) Remarks
@ FB ONLY
Total Wt. (kgs.) Remarks
@ Stair
Total Wt. (kgs.) Remarks
1.36
(Note:1kg of #16 G.I. tie is equal to 53m)
1.36
@ TB ONLY
Total Wt. (kgs.) Remarks
13.25
71.32
64.19
1.02
1.36
1.36
152.49
1,131.68 X Bars
1,098.24 Y Bars
2,229.92
2,229.92 kgs.
29.71
(Note:1kg of #16 G.I. tie is equal to 53m)
29.71
107.55 temperature/straight
113.84 temperature/straight
432.19
10,372.45 kgs.
153.65
(Note:1kg of #16 G.I. tie is equal to 53m)
153.65
107.55 temperature/straight
113.84 temperature/straight
413.95
PUBLIC WORKS AND HIGHWAYS
9,934.85 kgs.
135.71
(Note:1kg of #16 G.I. tie is equal to 53m)
135.71
83.65 temperature/straight
84.27 temperature/straight
313.42
7,522.10 kgs.
112.89
(Note:1kg of #16 G.I. tie is equal to 53m)
112.89
83.65 temperature/straight
84.27 temperature/straight
313.42
1,253.68 kgs.
18.82
(Note:1kg of #16 G.I. tie is equal to 53m)
18.82
167.31 temperature/straight
103.49 temperature/straight
496.74
1,986.97 kgs.
34.51
(Note:1kg of #16 G.I. tie is equal to 53m)
34.51
101.02 temperature/straight
18.23 temperature/straight
194.29
777.15 kgs.
10.60
(Note:1kg of #16 G.I. tie is equal to 53m)
10.60
PUBLIC WORKS AND HIGHWAYS
153.65
135.71
112.89
18.82
34.51
10.60
466.17 -
918.95 kgs.
22.82
(Note:1kg of #16 G.I. tie is equal to 53m)
33.26 Ties
60.44
120.87 kgs.
2.04
(Note:1kg of #16 G.I. tie is equal to 53m)
17.12
22.82
22.82
1.58
6.34
10.30
5.71
31.38
9.78
2.04
1.70
131.59
PUBLIC WORKS AND HIGHWAYS
0.22
0.22
2.67
2.67
3.40
3.40
DETAILED ESTIMATE FOR RSB
Project Name: CONSTRUCTION OF THREE STOREY EIGHTEEN CLASSROOM SCHOOL BUILDING
Project Location : SAN FRANCISCO, ADS
G-2
No. of Pcs. Bar length Total Length (m) Unit wt. (kgs./m) Total Wt. (kgs.)
Bar ø
G-3
No. of Pcs. Bar length Total Length (m) Unit wt. (kgs./m) Total Wt. (kgs.)
Bar ø
G-4
No. of Pcs. Bar length Total Length (m) Unit wt. (kgs./m) Total Wt. (kgs.)
Bar ø
G-6
No. of Pcs. Bar length Total Length (m) Unit wt. (kgs./m) Total Wt. (kgs.)
Bar ø
G-7
No. of Pcs. Bar length Total Length (m) Unit wt. (kgs./m) Total Wt. (kgs.)
Bar ø
G-8
No. of Pcs. Bar length Total Length (m) Unit wt. (kgs./m) Total Wt. (kgs.)
Bar ø
B-1
No. of Pcs. Bar length Total Length (m) Unit wt. (kgs./m) Total Wt. (kgs.)
Bar ø
B-2
No. of Pcs. Bar length Total Length (m) Unit wt. (kgs./m) Total Wt. (kgs.)
Bar ø
B-3
No. of Pcs. Bar length Total Length (m) Unit wt. (kgs./m) Total Wt. (kgs.)
Bar ø
ROOF BEAM RG - 1
No. of Pcs. Bar length Total Length (m) Unit wt. (kgs./m) Total Wt. (kgs.)
Bar ø
RG - 3
No. of Pcs. Bar length Total Length (m) Unit wt. (kgs./m) Total Wt. (kgs.)
Bar ø
RG - 4a
No. of Pcs. Bar length Total Length (m) Unit wt. (kgs./m) Total Wt. (kgs.)
Bar ø
RG - 4b
No. of Pcs. Bar length Total Length (m) Unit wt. (kgs./m) Total Wt. (kgs.)
Bar ø
Remarks
Top Bars
Cut Bars-top
Cut Bars-bottom
Bottom Bars
Ties
kgs.
(Note:1kg of #16 G.I. tie is equal to 53m)
Remarks
Top Bars
Cut Bars-top
Cut Bars-bottom
Bottom Bars
Ties
kgs.
(Note:1kg of #16 G.I. tie is equal to 53m)
Remarks
Top Bars
Cut Bars-top
Cut Bars-bottom
Bottom Bars
Ties
kgs.
(Note:1kg of #16 G.I. tie is equal to 53m)
Remarks
Top Bars
Cut Bars-top
Bottom Bars
Ties
kgs.
(Note:1kg of #16 G.I. tie is equal to 53m)
Remarks
Top Bars
Cut Bars-top
Cut Bars-bottom
Bottom Bars
Ties
kgs.
(Note:1kg of #16 G.I. tie is equal to 53m)
Remarks
Top Bars
Cut Bars-top
Bottom Bars
Ties
kgs.
(Note:1kg of #16 G.I. tie is equal to 53m)
Remarks
Top Bars
Cut Bars-top
Cut Bars-bottom
Bottom Bars
Ties
kgs.
(Note:1kg of #16 G.I. tie is equal to 53m)
Remarks
Top Bars
Cut Bars-top
Cut Bars-bottom
Bottom Bars
Ties
kgs.
(Note:1kg of #16 G.I. tie is equal to 53m)
Remarks
Top Bars
Bottom Bars
Ties
kgs.
(Note:1kg of #16 G.I. tie is equal to 53m)
Remarks
Top Bars
Cut Bars-bottom
Bottom Bars
Ties
kgs.
(Note:1kg of #16 G.I. tie is equal to 53m)
Remarks
Top Bars
Bottom Bars
Ties
kgs.
(Note:1kg of #16 G.I. tie is equal to 53m)
Remarks
Top Bars
Cut Bars-top
Cut Bars-bottom
Bottom Bars
Ties
kgs.
(Note:1kg of #16 G.I. tie is equal to 53m)
Remarks
Top Bars
Cut Bars-top
Cut Bars-bottom
Bottom Bars
Ties
kgs.
(Note:1kg of #16 G.I. tie is equal to 53m)
Remarks
Top Bars
Cut Bars-top
Bottom Bars
Ties
kgs.
(Note:1kg of #16 G.I. tie is equal to 53m)
Remarks
Top Bars
Bottom Bars
Ties
kgs.
(Note:1kg of #16 G.I. tie is equal to 53m)
Remarks
Top Bars
Bottom Bars
Ties
kgs.
(Note:1kg of #16 G.I. tie is equal to 53m)
Remarks
Top Bars
Side Bars
Bottom Bars
kgs.
(Note:1kg of #16 G.I. tie is equal to 53m)
Remarks
Top Bars
Top Bars
Side Bars
Bottom Bars
Bottom Bars
kgs.
(Note:1kg of #16 G.I. tie is equal to 53m)
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
Length (m) Width (m) Thickness (m) Vol. of footing No. of Footings Total Volume
Column :
Length (m) Width (m) Height (m) Vol. of col. No. of columns Total Volume
C-1 0.44 0.44 2.10 0.40 15.00 5.96
0.40 0.40 3.53 0.56 15.00 8.46
0.40 0.40 3.20 0.51 15.00 7.68
0.40 0.40 3.20 0.51 15.00 7.68
Tie Beam :
Length (m) Width (m) Height (m) Vol. of beam No. of beams Total Volume
TB 1 0.30 0.50 2.50 0.38 15.00 5.63
TB 2 0.30 0.50 7.00 1.05 15.00 15.75
TB 3 0.30 0.50 13.50 2.03 14.00 28.35
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
Secondary Beam :
Length (m) Width (m) Height (m) Vol. of beam No. of beams Total Volume
B-1 0.20 0.40 4.50 0.36 24.00 8.64
B-2 0.30 0.40 4.50 0.54 4.00 2.16
B-3 0.20 0.40 3.75 0.30 4.00 1.20
12.00
Quantity
Portland Cement 109.20
Sand 6.00
Gravel 12.00
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
91.04
Quantity
Portland Cement 828.50
Sand 45.52
Gravel 91.04
36.40
Quantity
Portland Cement 331.24
Sand 18.20
Gravel 36.40
Slab on Fill :
Length (m) Width (m) Thickness (m) Vol. of slab No. of slabs Total Volume
SLAB @ ground 63.00 9.50 0.10 59.85 1.00 59.85
59.85
Quantity
Portland Cement 544.64
Sand 29.93
Gravel 59.85
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
2nd-3rd Floor :
Length (m) Width (m) Thickness (m) Vol. of slab No. of slabs Total Volume
SLAB 1 3.50 4.50 0.10 1.58 24.00 37.80
SLAB 2 3.50 4.50 0.10 1.58 24.00 37.80
SLAB 3 2.50 4.50 0.10 1.13 24.00 27.00
SLAB 4 2.50 4.50 0.10 1.13 4.00 4.50
SLAB 5 3.15 4.50 0.10 1.42 4.00 5.67
SLAB 6 1.50 3.75 0.10 0.56 8.00 4.50
117.27
Quantity
Portland Cement 1067.16
Sand 58.64
Gravel 117.27
Ramp :
Length (m) Width (m) Thickness (m) Vol. of slab No. of slabs Total Volume
5.30 1.60 0.10 0.85 2.00 1.70
1.70
Quantity
Portland Cement 15.43
Sand 0.85
Gravel 1.70
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
Stairs :
Length (m) Width (m) Thickness (m) Vol. of slab No. of Stairs Total Volume
14.78 1.50 0.35 7.76 4.00 31.04
slab 1.50 3.00 0.15 0.68 4.00 2.70
33.74
Quantity
Portland Cement 307.02
Sand 16.87
Gravel 33.74
Septic Tank
Length (m) Width (m) Thickness (m) Vol. of slab No. of slabs Total Volume
8.60 2.30 0.15 2.97 1.00 2.97
2.10 2.30 0.15 0.72 3.00 2.17
2.10 8.60 0.15 2.71 2.00 5.42
8.60 2.30 0.15 2.97 1.00 2.97
1.00 13.53
Quantity
Portland Cement 123.08
Sand 6.76
Gravel 13.53
Catch Basin
Length (m) Width (m) Thickness (m) Vol. of slab No. of slabs Total Volume
0.90 0.90 0.10 0.08 16.00 1.30
1.30
2.59
Quantity
Portland Cement 23.59
Sand 1.30
Gravel 2.59
SunBreaker
Length (m) Width (m) Thickness (m) Vol. of slab No. of slabs Total Volume
3.75 0.90 0.15 0.51 24.00 12.15
12.15
Quantity
Portland Cement 110.57
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
Sand 6.08
Gravel 12.15
PUBLIC WORKS AND HIGHWAYS
Remarks
LEAN CONCRETE
LEAN CONCRETE
bags
cu.m.
cu.m.
Remarks
FDN TO GF
GF TO 2F
2F TO 3F
3F TO ROOF
FDN TO GF
GF TO 2F
2F TO 3F
3F TO ROOF
FDN TO GF
GF TO 2F
2F TO 3F
3F TO ROOF
bags
cu.m.
cu.m.
Remarks
PUBLIC WORKS AND HIGHWAYS
bags
cu.m.
cu.m.
Remarks
bags
cu.m.
cu.m.
PUBLIC WORKS AND HIGHWAYS
Remarks
bags
cu.m.
cu.m.
Remarks
bags
cu.m.
cu.m.
Remarks
bags
cu.m.
cu.m.
PUBLIC WORKS AND HIGHWAYS
Remarks
bags
cu.m.
cu.m.
Remarks
bags
cu.m.
cu.m.
PUBLIC WORKS AND HIGHWAYS
Remarks
bags
cu.m.
cu.m.
Remarks
bags
cu.m.
cu.m.
Remarks
for 16 sets
bags
cu.m.
cu.m.
Remarks
for 24 sets
bags
PUBLIC WORKS AND HIGHWAYS
cu.m.
cu.m.
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
Masonry:
CHB Width Length Area Deducted Net Area No. of Total Area Factor No. of Pcs. Say
Size Area Walls/
Surface
(m) (m) (sq.m.) (sq.m.) (sq.m.) n (sq.m.) (pcs./sq.m.) (pcs) (pcs)
SEPTIC TANK
1 #4 2.05 3.30 6.77 6.77 4.00 27.06 12.5 338.25 339.00
2 #4 2.05 1.50 3.08 3.08 6.00 18.45 12.5 230.63 231.00
45.51 570.00
SCHEDULE OF RSB FOR WALL
Quantity
Portland Cement 64.81
Sand 4.94
CHB 570.00
RSB 174.65
#16 G.I. Tie 2.14
Masonry:
CHB Width Length Area Deducted Net Area No. of Total Area Factor No. of Pcs. Say
Size Area Walls/
Surface
(m) (m) (sq.m.) (sq.m.) (sq.m.) n (sq.m.) (pcs./sq.m.) (pcs) (pcs)
Quantity
Portland Cement 9.17
Sand 0.89
C WORKS AND HIGHWAYS
Remarks
Wall
Side Wall
FOR 2 SETS
Quantity
bags
cu.m.
pcs.
kgs.
kgs.
Remarks
Quantity
bags
cu.m.
FORM WORKS
Column
Plywood Area x y Length used
No. of columns
thick (s. m.) (m.) (m.) (m.)
12.5 2.88 15.00 0.87 0.87 3.20
12.5 2.88 15.00 1.22 1.22 3.20
12.5 2.88 15.00 1.17 1.17 3.20
area
CWN Area x y no per kilos
No. of columns
(s. m.) (m.) (m.) (m.)
1", 1 1/2", 2 1/2", 3", 3 1/2", 4" 16.00 15.00 21.33 21.33 90.00
1", 1 1/2", 2 1/2", 3", 3 1/2", 4" 20.00 15.00 21.33 21.33 90.00
1", 1 1/2", 2 1/2", 3", 3 1/2", 4" 20.00 15.00 21.33 21.33 90.00
Tie Beam
Plywood Area x y Length used
No. of tiebeams
thick (s. m.) (m.) (m.) (m.)
12.5 2.88 15.00 0.00 1.00 2.50
12.5 2.88 15.00 0.00 1.00 7.00
12.5 2.88 14.00 0.00 1.00 13.50
12.5 2.88 4.00 0.00 0.80 3.00
12.5 2.88 4.00 0.00 0.80 3.00
12.5 2.88 2.00 0.00 0.80 4.50
area
CWN Area x y no per kilos
No. of columns
(s. m.) (m.) (m.) (m.)
1", 1 1/2", 2 1/2", 3", 3 1/2", 4" 12.50 15.00 100.00 100.00 120.00
1", 1 1/2", 2 1/2", 3", 3 1/2", 4" 35.00 14.00 100.00 100.00 120.00
1", 1 1/2", 2 1/2", 3", 3 1/2", 4" 35.00 14.00 93.33 93.33 120.00
@ 2ND FLOOR
Girder Beam
Plywood Area x y Length used
No. of tiebeams
thick (s. m.) (m.) (m.) (m.)
12.5 2.88 28.00 0.30 0.80 4.50
12.5 2.88 28.00 0.30 0.90 4.50
12.5 2.88 28.00 0.30 0.90 1.30
12.5 2.88 4.00 0.40 0.80 2.50
12.5 2.88 4.00 0.40 1.00 7.00
12.5 2.88 26.00 0.40 0.80 2.50
12.5 2.88 4.00 0.40 1.00 7.00
12.5 2.88 22.00 0.40 1.00 7.00
@ 3RD FLOOR
Girder Beam
Plywood Area x y Length used
No. of tiebeams
thick (s. m.) (m.) (m.) (m.)
12.5 2.88 28.00 0.30 0.80 4.50
12.5 2.88 28.00 0.30 0.90 4.50
12.5 2.88 28.00 0.30 0.90 1.50
12.5 2.88 4.00 0.40 0.80 2.50
12.5 2.88 4.00 0.40 0.80 7.00
12.5 2.88 26.00 0.40 0.80 2.50
12.5 2.88 14.00 0.40 1.00 7.00
12.5 2.88 22.00 0.40 1.00 7.00
area
CWN Area x y no per kilos
No. of columns
(s. m.) (m.) (m.) (m.)
1", 1 1/2", 2 1/2", 3", 3 1/2", 4" 11.25 28.00 133.33 133.33 120.00
1", 1 1/2", 2 1/2", 3", 3 1/2", 4" 38.75 28.00 133.33 133.33 120.00
1", 1 1/2", 2 1/2", 3", 3 1/2", 4" 38.75 28.00 133.33 133.33 120.00
Roof Beam
Plywood Area x y Length used
No. of tiebeams
thick (s. m.) (m.) (m.) (m.)
12.5 2.88 42.00 0.30 0.80 4.50
12.5 2.88 13.00 0.20 0.80 9.50
12.5 2.88 2.00 0.20 0.80 10.00
12.5 2.88 2.00 0.20 0.80 7.00
12.5 2.88 2.00 0.20 0.80 7.00
area
CWN Area x y no per kilos
No. of columns
(s. m.) (m.) (m.) (m.)
1", 1 1/2", 2 1/2", 3", 3 1/2", 4" 95.00 1.00 253.33 253.33 120.00
1", 1 1/2", 2 1/2", 3", 3 1/2", 4" 95.00 1.00 253.33 253.33 120.00
1", 1 1/2", 2 1/2", 3", 3 1/2", 4" 95.00 1.00 253.33 253.33 120.00
area
CWN Area x y no per kilos
24.00
(s. m.) (m.) (m.) (m.)
1", 1 1/2", 2 1/2", 3", 3 1/2", 4" 220.50 24.00 3.50 4.50 120.00
1", 1 1/2", 2 1/2", 3", 3 1/2", 4" 220.50 24.00 3.50 4.50 120.00
1", 1 1/2", 2 1/2", 3", 3 1/2", 4" 220.50 24.00 2.50 4.50 120.00
1", 1 1/2", 2 1/2", 3", 3 1/2", 4" 220.50 4.00 2.50 4.50 120.00
1", 1 1/2", 2 1/2", 3", 3 1/2", 4" 220.50 4.00 3.15 4.50 120.00
1", 1 1/2", 2 1/2", 3", 3 1/2", 4" 220.50 8.00 1.50 3.75 120.00
Total
Remarks
(m.)
29.00 1st
40.67 2nd
39.00 3rd
108.67
bd ft
240.00 1,040.00 1st
87.00 377.00
300.00 1,300.00 2nd
80.00 426.67
300.00 1,300.00 3rd
76.72 409.18
108.67 4,852.85
312.96
Total
Remarks
(m.)
113.78 1st
142.22 2nd
142.22 3rd
398.22
Total
Remarks
(m.)
13.02 TB 1
36.46 TB 2
65.63 TB 3
3.33 STB 1
3.33 STB 2
2.50 FB-1
124.27
bd ft
15.00 100.00 TB 1
60.00 340.00
42.00 280.00 TB 2
233.33 933.33
105.00 525.00 TB 3
336.00 1,680.00
8.00 26.67 STB 1
24.00 80.00
8.00 26.67 STB 2
12.00 40.00
6.00 20.00 FB-1
12.00 60.00
861.33 4,111.67
2,480.64
Total
Remarks
(m.)
312.50 1st
816.67 2nd
762.22 3rd
1,891.39
Total
Remarks
(m.)
48.13 G-1
52.50 G-2
15.17 G-3
4.17 G-4
13.61 G-5
27.08 G-6
13.61 G-7
74.86 G-8
249.13
bd ft
96.25 385.00 G-1
308.00 1,540.00
105.00 420.00 G-2
385.00 1,540.00
28.00 121.33 G-3
102.67 444.89
10.00 33.33 G-4
40.00 133.33
28.00 112.00 G-5
96.00 384.00
55.71 222.86 G-6
173.33 866.67
28.00 112.00 G-7
96.00 384.00
154.00 616.00 G-8
528.00 2,112.00
2,233.96 9,427.41
6,433.82
Total
Remarks
(m.)
693.00 1st
2,356.20 2nd
2,356.20 3rd
5,405.40
Total
Remarks
(m.)
48.13 G-1
52.50 G-2
17.50 G-3
4.17 G-4
11.67 G-5
27.08 G-6
47.64 G-7
74.86 G-8
283.54
bd ft
96.25 385.00 G-1
308.00 1,540.00
105.00 420.00 G-2
385.00 1,540.00
32.31 140.00 G-3
118.46 513.33
10.00 33.33 G-4
40.00 133.33
24.00 96.00 G-5
96.00 384.00
55.71 222.86 G-6
173.33 866.67
98.00 392.00 G-7
336.00 1,344.00
154.00 616.00 G-8
528.00 2,112.00
2,560.07 10,738.52
7,372.99
Total
Remarks
(m.)
700.00 1st
2,411.11 2nd
2,411.11 3rd
5,522.22
Total
Remarks
(m.)
72.19 RG - 1
42.88 RG - 2
6.94 RG - 3
4.86 RG - 4a
4.86 RG - 4b
131.74
bd ft
144.38 577.50 RG - 1
462.00 2,310.00
85.76 343.06 RG - 2
343.06 1,372.22
12.82 55.56 RG - 3
51.28 222.22
11.67 38.89 RG - 4a
46.67 155.56
10.00 40.00 RG - 4b
40.00 160.00
1,207.63 5,275.00
3,477.98
Total
Remarks
(m.)
401.11 1st
401.11 2nd
401.11 3rd
1,203.33
Total
Remarks
(m.)
131.25 SLAB 1
131.25 SLAB 2
93.75 SLAB 3
15.63 SLAB 4
19.69 SLAB 5
15.63 SLAB 6
407.19
bd ft
210.00 1,050.00 SLAB 1
270.00 1,080.00
184.57 738.28
184.57 1,107.42
210.00 1,050.00 SLAB 2
270.00 1,080.00
184.57 738.28
184.57 1,107.42
150.00 750.00 SLAB 3
135.00 765.00
131.84 527.34
131.84 791.02
25.00 125.00 SLAB 4
25.00 83.33
43.95 175.78
43.95 263.67
31.50 126.00 SLAB 5
40.50 162.00
27.69 110.74
27.69 207.64
32.14 128.57 SLAB 6
32.14 128.57
23.44 78.13
21.97 131.84
2,621.91 12,506.04
7,551.10
Total
Remarks
(m.)
352.80 SLAB 1
352.80 SLAB 2
308.70 SLAB 3
51.45 SLAB 4
56.23 SLAB 5
77.18 SLAB 6
1,199.15
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
Masonry:
1ST FLOOR
CHB Width Length Area Deducted Net Area No. of Walls/ Total Area Factor No. of Pcs.
Size Area Surface
(m) (m) (sq.m.) (sq.m.) (sq.m.) n (sq.m.) (pcs./sq.m.) (pcs)
FRONT
#6 63.00 3.13 196.88 196.88 1.00 196.88 12.5 2,460.94
INTERIOR
#6 7.00 3.13 21.88 21.88 9.00 196.88 12.5 2,460.94
REAR
#6 63.00 3.13 196.88 196.88 1.00 196.88 12.5 2,460.94
LESS #6
FRONT D1 0.90 2.50 2.25 2.25 12.00 27.00 12.5 337.50
W2 1.40 1.50 2.10 2.10 12.00 25.20 12.5 315.00
REAR W1 2.50 1.50 3.75 3.75 12.00 45.00 12.5 562.50
W3 1.90 0.64 1.21 1.21 2.00 2.41 12.5 30.16
W4 0.60 0.64 0.38 0.38 2.00 0.76 12.5 9.53
CHB #6
2ND FLOOR
CHB Width Length Area Deducted Net Area No. of Walls/ Total Area Factor No. of Pcs.
Size Area Surface
(m) (m) (sq.m.) (sq.m.) (sq.m.) n (sq.m.) (pcs./sq.m.) (pcs)
FRONT
#6 63.00 2.80 176.40 176.40 1.00 176.40 12.5 2,205.00
INTERIOR
#6 7.00 2.80 19.60 19.60 9.00 176.40 12.5 2,205.00
REAR
#6 63.00 2.80 176.40 176.40 1.00 176.40 12.5 2,205.00
LESS #6
FRONT D1 0.90 2.50 2.25 2.25 12.00 27.00 12.5 337.50
W2 1.40 1.50 2.10 2.10 12.00 25.20 12.5 315.00
REAR W1 2.50 1.50 3.75 3.75 12.00 45.00 12.5 562.50
W3 1.90 0.64 1.21 1.21 2.00 2.41 12.5 30.16
CHB #6
3RD FLOOR
CHB Width Length Area Deducted Net Area No. of Walls/ Total Area Factor No. of Pcs.
Size Area Surface
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
Masonry:
1ST FLOOR
CHB Width Length Area Deducted Net Area No. of Walls/ Total Area Factor No. of Pcs.
Size Area Surface
(m) (m) (sq.m.) (sq.m.) (sq.m.) n (sq.m.) (pcs./sq.m.) (pcs)
(m) (m) (sq.m.) (sq.m.) (sq.m.) n (sq.m.) (pcs./sq.m.) (pcs)
FRONT
#6 63.00 2.80 176.40 176.40 1.00 176.40 12.5 2,205.00
INTERIOR
#6 7.00 2.80 19.60 19.60 9.00 176.40 12.5 2,205.00
REAR
#6 63.00 2.80 176.40 176.40 1.00 176.40 12.5 2,205.00
LESS #6
FRONT D1 0.90 2.50 2.25 2.25 12.00 27.00 12.5 337.50
W2 1.40 1.50 2.10 2.10 12.00 25.20 12.5 315.00
REAR W1 2.50 1.50 3.75 3.75 12.00 45.00 12.5 562.50
W3 1.90 0.64 1.21 1.21 2.00 2.41 12.5 30.16
CHB #6
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
Masonry:
1ST FLOOR
CHB Width Length Area Deducted Net Area No. of Walls/ Total Area Factor No. of Pcs.
Size Area Surface
(m) (m) (sq.m.) (sq.m.) (sq.m.) n (sq.m.) (pcs./sq.m.) (pcs)
EAVES WALL SIDE FLASHING
CHB Width Length Area Deducted Net Area No. of Walls/ Total Area Factor No. of Pcs.
Size Area Surface
(m) (m) (sq.m.) (sq.m.) (sq.m.) n (sq.m.) (pcs./sq.m.) (pcs)
FRONT
#6 9.50 1.25 11.88 11.88 2.00 23.75 12.5 296.88
23.75
CHB #6
Quantity
Portland Cement
Sand
CHB
RSB
#16 G.I. Tie
UBLIC WORKS AND HIGHWAYS
Say Remarks
(pcs)
6,126.00
Say Remarks
(pcs)
5,368.00
Say Remarks
UBLIC WORKS AND HIGHWAYS
Say Remarks
(pcs)
(pcs)
5,368.00
UBLIC WORKS AND HIGHWAYS
Say Remarks
(pcs)
Say Remarks
(pcs)
297.00
1,456.65 bags
2,079.59 cu.m.
17,159.00 pcs.
6,419.58 kgs.
78.62 kgs.
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
Masonry:
1ST FLOOR
CHB Width Length Area Deducted Net Area No. of Walls/ Total Area Factor No. of Pcs.
Size Area Surface
(m) (m) (sq.m.) (sq.m.) (sq.m.) n (sq.m.) (pcs./sq.m.) (pcs)
@ STAIR & CR
1ST FLOOR
#4 34.10 3.13 106.56 106.56 2.00 213.13 12.5 2,664.06
LESS #4
INTERIOR D2 0.90 2.10 1.89 1.89 2.00 3.78 12.5 47.25
D3 0.80 2.10 1.68 1.68 2.00 3.36 12.5 42.00
D4 0.60 1.50 0.90 0.90 2.00 1.80 12.5 22.50
D5 0.80 2.10 1.68 1.68 2.00 3.36 12.5 42.00
225.43
CHB #4
2ND FLOOR
CHB Width Length Area Deducted Net Area No. of Walls/ Total Area Factor No. of Pcs.
Size Area Surface
(m) (m) (sq.m.) (sq.m.) (sq.m.) n (sq.m.) (pcs./sq.m.) (pcs)
@ STAIR & CR
2ND FLOOR
#4 12.90 2.80 36.12 36.12 2.00 72.24 12.5 903.00
LESS #4
INTERIOR D3 0.80 2.10 1.68 1.68 2.00 3.36 12.5 42.00
D4 0.60 1.50 0.90 0.90 4.00 3.60 12.5 45.00
79.20
CHB #4
3RD FLOOR
CHB Width Length Area Deducted Net Area No. of Walls/ Total Area Factor No. of Pcs.
Size Area Surface
(m) (m) (sq.m.) (sq.m.) (sq.m.) n (sq.m.) (pcs./sq.m.) (pcs)
@ STAIR & CR
3RD FLOOR
#4 17.00 2.80 47.60 47.60 2.00 95.20 12.5 1,190.00
LESS #4
INTERIOR D3 0.80 2.10 1.68 1.68 2.00 3.36 12.5 42.00
D4 0.60 1.50 0.90 0.90 4.00 3.60 12.5 45.00
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
Masonry:
1ST FLOOR
CHB Width Length Area Deducted Net Area No. of Walls/ Total Area Factor No. of Pcs.
Size Area Surface
(m) (m) (sq.m.) (sq.m.) (sq.m.) n (sq.m.) (pcs./sq.m.) (pcs)
102.16
CHB #4
WALL RAILING
CHB Width Length Area Deducted Net Area No. of Walls/ Total Area Factor No. of Pcs.
Size Area Surface
(m) (m) (sq.m.) (sq.m.) (sq.m.) n (sq.m.) (pcs./sq.m.) (pcs)
FRONT
#4 45.00 0.90 40.50 40.50 1.00 40.50 12.5 506.25
#4 63.00 0.90 56.70 56.70 1.00 56.70 12.5 708.75
#4 63.00 0.90 56.70 56.70 1.00 56.70 12.5 708.75
153.90
CHB #4
Masonry:
1ST FLOOR
CHB Width Length Area Deducted Net Area No. of Walls/ Total Area Factor No. of Pcs.
Size Area Surface
(m) (m) (sq.m.) (sq.m.) (sq.m.) n (sq.m.) (pcs./sq.m.) (pcs)
Quantity
Portland Cement
Sand
CHB #4
RSB
#16 G.I. Tie
Quantity
Portland Cement
Sand
PUBLIC WORKS AND HIGHWAYS
Say Remarks
(pcs)
2,552.00
Say Remarks
(pcs)
816.00
Say Remarks
(pcs)
Say Remarks
(pcs)
1,103.00
Say Remarks
(pcs)
1,925.00
PUBLIC WORKS AND HIGHWAYS
Say Remarks
(pcs)
390.59 bags
514.80 cu.m.
6,396.00 pcs.
2,956.79 kgs.
25.12 kgs.
Quantity
50.85 bags
2.83 cu.m.
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
Remarks
corridor handrail
stairway handrail
stairway balluster
PWD-CR Handrail
Ramp Handrail
Ramp Handrail Support
Nozing
Nozing anchor support
Nozing anchor support
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
COMFORT ROOM
Dimension of tile : 0.20 x 0.20
Length Width Area No. of Total Area No. of tiles
Wall/Surface (Total Area/Area of Tile)
SHE
GF 4.50 2.00 9.00 2.00 18.00
2.68 1.15 3.08 2.00 6.15
2.00 1.60 3.20 2.00 6.40
4.50 1.60 7.20 2.00 14.40
3.15 1.60 5.04 2.00 10.08
2.00 1.60 3.20 2.00 6.40
2.00 1.60 3.20 2.00 6.40
4.70 1.60 7.52 2.00 15.04
2F 3.30 3.15 10.40 4.00 41.58
3.15 1.60 5.04 4.00 20.16
3.30 1.60 5.28 4.00 21.12
3.15 1.60 5.04 4.00 20.16
3.30 1.60 5.28 4.00 21.12
3F 3.30 3.15 10.40 4.00 41.58
3.15 1.60 5.04 4.00 20.16
3.30 1.60 5.28 4.00 21.12
3.15 1.60 5.04 4.00 20.16
3.30 1.60 5.28 4.00 21.12
HE
GF 2.00 3.00 6.00 2.00 12.00
2.00 4.50 9.00 2.00 18.00
3.15 1.60 5.04 2.00 10.08
4.50 1.60 7.20 2.00 14.40
2.00 1.60 3.20 2.00 6.40
2.00 1.60 3.20 2.00 6.40
2.00 1.60 3.20 2.00 6.40
4.50 1.60 7.20 2.00 14.40
2F 3.05 3.16 9.64 4.00 38.55
1.45 1.80 2.61 4.00 10.44
3.16 1.60 5.06 4.00 20.22
4.50 1.60 7.20 4.00 28.80
3.16 1.60 5.06 4.00 20.22
4.50 1.60 7.20 4.00 28.80
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
Remarks
Floor
Wall 1
Wall 2
Wall 3
Wall 3-a
Wall 3-b
Wall 4
Floor
Wall 1
Wall 2
Wall 3
Wall 4
Floor
Wall 1
Wall 2
Wall 3
Wall 4
Floor
Wall 1
Wall 2
Wall 3
Wall 3-a
Wall 3-b
Wall 4
Floor
Wall 1
Wall 2
Wall 3
Wall 4
BLIC WORKS AND HIGHWAYS
Floor
Wall 1
Wall 2
Wall 3
Wall 4
floor
wall
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
EARTHWORKS
EXCAVATION:
FOOTING:
V= Length x Width x Depth x No. of Footings
= 6.00 x 3.50 x 2.10 x 15.00
= 661.50 cu.m.
Vt = 1,025.64 cu.m.
TIE BEAM
Vt = Total Length x Width x Depth
= 553.50 x 0.30 x 1.00
Vt = 166.05 cu.m.
SEPTIC TANK
Vt = Total Length x Width x Depth x No. of Septic Tank
= 8.60 x 2.30 x 1.500 x 2.00
= 59.34 cu.m.
Vt = 2,492.54 cu.m.
BACKFILL :
Vt = 48.84 cu.m.
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
EARTHWORKS
EMBANKMENT:
BUILDING
V= Length x Width x Depth x No. of Area
= 63.00 x 9.50 x 0.30 x 1.00
= 179.55 cu.m.
DOORS & WINDOWS AND FRAME
Ground Floor
MARK Width Length Numbers Total
Remarks
W1 jalousie
blades 1.30 2.50 12.00 39.00
transom 0.30 2.50 12.00 9.00
W2
jalousie 1.30 1.40 12.00 21.84
transom 0.30 1.40 12.00 5.04
W3 jalousie
blades 0.64 1.90 2.00 2.43
W4
blades 0.64 0.60 2.00 0.77
Total Area 78.08
jamb-sizes vertical bd ft
2" x 6" x 5' 1.00 5.00 12.00 60.00 W1 300.00
horizontal
2" x 6" x 8' 1.00 3.00 12.00 36.00 W1 288.00
vertical
2" x 6" x 5' 1.00 3.00 12.00 36.00 W2 180.00
horizontal
2" x 6" x 6' 1.00 3.00 12.00 36.00 W2 216.00
vertical
2" x 6" x 6' 1.00 3.00 2.00 6.00 W3 30.00
horizontal
2" x 6" x 6' 1.00 2.00 2.00 4.00 W3 24.00
vertical
2" x 6" x 6' 1.00 2.00 2.00 4.00 W4 20.00
horizontal
2" x 6" x 6' 1.00 2.00 2.00 4.00 W4 24.00
1,082.00
TRUSSES:
0.00
Silver Paint
gal.
Base Plates
Dimension No. of Columns No. of Pcs per col. Total Remarks
4.00 1.00 4.00 for col. joint
Bolts
4.00 4.00 16.00 for col. Joint
WALL FRAMING :
Diameter Length No. of Pcs Total Length
Remarks
(inches) (m.) (pcs.) (m.)
2" 21.42 1.00 21.42 Front Frame
2" 11.04 1.00 11.04 Left Frame
2" 19.06 1.00 19.06 Right Frame
2" 6.8 1.00 6.80 Door Frame
58.32
STEEL SCREEN :
Dimension Height (ave.) Width Area Remarks
2" x 2" 2.85 4.61 13.14 Front
2" x 2" 2.97 2.80 8.32 Left
2" x 2" 2.97 2.80 8.32 Right Frame
ROOF FRAMING :
Channel Bars
Dimension Length No. of Pcs. Total Length Remarks
2" x 6" 4.00 5.00 20.00 Rafter
2" x 6" 6.25 9.00 56.25 Rafter
Total : 76.25
Miscellaneous Materials
Welding Rod
CARPENTRY WORKS
Ceiling Panel
Fiber Cement Area Width Length Total
Remarks
thick (s. m.) (m.) (m.) (m.)
4.5 2.88 9.50 63.00 207.81 1st
4.5 2.88 9.50 63.00 207.81 2nd
4.5 2.88 12.50 64.20 278.65 3rd
pcs 694.27
area 1,999.50
CWN
Diameter Length No. of Pcs Total Length
Remarks
(inches) (pcs.) (m.)
Assorted Assorted 3.00 6.00 18.00 1st,2nd&3rd
Concrete Assorted 2.00 6.00 12.00 1st,2nd&3rd
cwn 18.00
concrete 12.00
1st
2nd
3rd
6m/length
1st
2nd
3rd
6m/length
1st
2nd
3rd
1st
2nd
3rd
1st
2nd
3rd
260.00
Remarks
Project Name: CONSTRUCTION OF THREE STOREY EIGHTEEN CLASSROOM SCHOOL BUILDING
Project Location : SAN FRANCISCO, ADS
TRUSSES
MARK Pcs Length Numbers Unit length Total per length
t1 2-50mm x 50mm x 6mm
TOP 2.00 11.10 13.00 6.00 48.10 26.58
BOTTOM 2.00 19.00 13.00 6.00 82.33 26.58
WEB
Vetical 1 2.00 5.00 13.00 6.00 21.67 18.36
Vertical 2 2.00 7.60 13.00 6.00 32.93 18.36
Diagonal1 2.00 4.00 13.00 6.00 17.33 18.36
Diagonal2 2.00 5.80 13.00 6.00 25.13 18.36
Horizontal Eaves 2.00 3.00 13.00 6.00 13.00 26.58
Top End Flashing 2.00 0.60 22.00 6.00 4.40 26.58
End Flashing 2.00 11.00 4.00 6.00 14.67 26.58
1,278.50
2,188.42
397.80
604.66
318.24
461.45
345.54
116.95
389.84
6,101.39
8,024.94
296.00
234.00
162.78
28.42
15.42
Project Name: CONSTRUCTION OF THREE STOREY EIGHTEEN CLASSROOM SCHOOL BUILDING
Project Location : SAN FRANCISCO, ADS
Water Closet (6.0 gpf) w/ complete accy set & assy. set 15.00
Lavatory w/ complete accy set & assy. set 2.00
Soap & Paper Holder set 15.00
PVC Pipe x s1000
150mm dia x 3mts mts
150mm dia x 1/8 bend pipe pcs
150mm dia x wye pipe pcs
100mm dia x 3mts mts 10.00
50mm dia x 3mts mts 8.00
100mm dia x wye pipe pcs 8.00
100mm dia x 1/8 bend pipe pcs 10.00
100mm dia x cap pipe pcs 6.00
100mm dia x 90 elbow pipe pcs 16.00
100mm dia x tee pipe pcs 12.00
100mm dia x p-trap pipe pcs 6.00
50mm x 100mm dia x wye pipe pcs 6.00
50mm dia x elbow pipe pcs 8.00
50mm dia x 1/8 bend pipe pcs 4.00
20mm dia x 3mts Ppr pipe pcs 12.00
20mm dia x elbow uPVC pipe pcs 25.00
20mm dia x tee uPVC pipe pcs 15.00
20mm dia x coupling w/ one-side tread uPVC pipe pcs 10.00
20mm dia x Gate Valves (brass/Ppr/equiv.) pcs 10.00
Teflon tape pcs 12.00
Stainless Steel Floor Drain pcs 6.00
Range Hood pcs 1.00
Exhaust Fan pcs 4.00
ING
UNIT RATE
8,750.00
5,575.00
350.00
-
85.00
750.00
650.00
85.00
85.00
65.00
85.00
85.00
85.00
65.00
55.00
55.00
375.00
55.00
55.00
75.00
75.00
10.00
150.00
4,575.00
1,575.00
Project Name: CONSTRUCTION OF THREE STOREY EIGHTEEN CLASSROOM SCHOOL BUILDING
Project Location : SAN FRANCISCO, ADS
Panel Board DP
Main : 30AT, 2p, 50AF, 240V
Branches : 2-15AT, to 20AT, 2P, 240V (Plug in type) set 1.00
HOOL BUILDING
UNIT RATE
70.00
10.00
45.00
40.00
12.00
6.00
70.00
460.00
70.00
550.00
2,000.00
2,800.00
36.00
375.00
220.00
345.00
385.00
40.00
10,000.00
250.00
1,975.00
3,750.00
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
Masonry:
CHB Width Length Area Deducted Net Area No. of Total Area Factor No. of Pcs. Say
Size Area Walls
(m) (m) (sq.m.) (sq.m.) (sq.m.) n
/Surface (sq.m.) (pcs./sq.m.) (pcs) (pcs)
FRONT WALL
1 #6 4.5 3.80 17.10 5.22 11.88 10.00 118.80 12.5 1485.00 1485.00
2 #6 4.5 2.70 12.15 5.22 6.93 10.00 69.30 13.5 935.55 936.00
BACK WALL
1 #6 4.5 3.80 17.10 5.20 11.90 10.00 119.00 12.5 1487.50 1488.00
2 #6 4.5 2.70 12.15 5.20 6.95 10.00 69.50 13.5 938.25 939.00
3 #6 4.5 3.80 17.10 1.08 16.02 2.00 32.04 12.5 400.50 401.00
4 #6 4.5 2.70 12.15 1.44 10.71 1.00 10.71 13.5 144.59 145.00
5 #6 4.5 2.70 12.15 1.44 10.71 1.00 10.71 13.5 144.59 145.00
LEFT WALL
1 #6 7.0 3.80 26.60 26.60 1.00 26.60 12.5 332.50 333.00
RIGHT WALL
1 #6 7 3.80 26.60 5.22 21.38 1.00 21.38 12.5 267.25 268.00
2 #6 4.5 2.70 12.15 1.44 10.71 1.00 10.71 13.5 144.59 145.00
EXTENSION
1 #6 2.70 0.00 13.30 -13.30 1.00 12.5 0.00 0.00
488.75 6285.00
SCHEDULE OF RSB FOR WALL
Quantity
Portland Cement 981.02
Sand 50.34
CHB 6285.00
RSB 1857.56
#16 G.I. Tie 15.64
C WORKS AND HIGHWAYS
Remarks
1ST FLOOR
2ND FLOOR
Quantity
bags
cu.m.
pcs.
kgs.
kgs.
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
Masonry:
1ST FLOOR
CHB Width Length Area Deducted Net Area No. of Walls/ Total Area Factor No. of Pcs.
Size Area Surface
(m) (m) (sq.m.) (sq.m.) (sq.m.) n (sq.m.) (pcs./sq.m.) (pcs)
FRONT
#6 63.00 3.20 201.60 201.60 1.00 201.60 12.5 2,520.00
INTERIOR
#6 7.00 3.20 22.40 22.40 9.00 201.60 12.5 2,520.00
REAR
#6 63.00 3.20 201.60 201.60 1.00 201.60 12.5 2,520.00
@ STAIR & CR
1ST FLOOR
#4 20.00 3.20 64.00 64.00 2.00 128.00 12.5 1,600.00
LESS #6
FRONT D1 0.90 2.40 2.16 2.16 12.00 25.92 12.5 324.00
W2 1.40 1.50 2.10 2.10 12.00 25.20 12.5 315.00
REAR W1 2.50 1.50 3.75 3.75 12.00 45.00 12.5 562.50
W3 1.90 0.64 1.21 1.21 2.00 2.41 12.5 30.16
W4 0.60 0.64 0.38 0.38 2.00 0.76 12.5 9.53
LESS #4
INTERIOR D2 0.90 2.10 1.89 1.89 2.00 3.78 12.5 47.25
D3 0.80 2.10 1.68 1.68 2.00 3.36 12.5 42.00
D4 0.60 1.50 0.90 0.90 2.00 1.80 12.5 22.50
D5 0.80 2.10 1.68 1.68 2.00 3.36 12.5 42.00
844.40
2ND FLOOR
CHB Width Length Area Deducted Net Area No. of Walls/ Total Area Factor No. of Pcs.
Size Area Surface
(m) (m) (sq.m.) (sq.m.) (sq.m.) n (sq.m.) (pcs./sq.m.) (pcs)
FRONT
#6 63.00 3.20 201.60 201.60 1.00 201.60 12.5 2,520.00
INTERIOR
#6 7.00 3.20 22.40 22.40 9.00 201.60 12.5 2,520.00
REAR
#6 63.00 3.20 201.60 201.60 1.00 201.60 12.5 2,520.00
@ STAIR & CR
2ND FLOOR
#4 17.00 3.20 54.40 54.40 2.00 108.80 12.5 1,360.00
LESS #6
FRONT D1 0.90 2.40 2.16 2.16 12.00 25.92 12.5 324.00
W2 1.40 1.50 2.10 2.10 12.00 25.20 12.5 315.00
REAR W1 2.50 1.50 3.75 3.75 12.00 45.00 12.5 562.50
W3 1.90 0.64 1.21 1.21 2.00 2.41 12.5 30.16
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
Masonry:
1ST FLOOR
CHB Width Length Area Deducted Net Area No. of Walls/ Total Area Factor No. of Pcs.
Size Area Surface
(m) (m) (sq.m.) (sq.m.) (sq.m.) n (sq.m.) (pcs./sq.m.) (pcs)
LESS #4
INTERIOR D3 0.80 2.10 1.68 1.68 2.00 3.36 12.5 42.00
D4 0.60 1.50 0.90 0.90 4.00 3.60 12.5 45.00
819.09
3RD FLOOR
CHB Width Length Area Deducted Net Area No. of Walls/ Total Area Factor No. of Pcs.
Size Area Surface
(m) (m) (sq.m.) (sq.m.) (sq.m.) n (sq.m.) (pcs./sq.m.) (pcs)
FRONT
#6 63.00 3.20 201.60 201.60 1.00 201.60 12.5 2,520.00
INTERIOR
#6 7.00 3.20 22.40 22.40 9.00 201.60 12.5 2,520.00
REAR
#6 63.00 3.20 201.60 201.60 1.00 201.60 12.5 2,520.00
@ STAIR & CR
3RD FLOOR
#4 17.00 3.20 54.40 54.40 2.00 108.80 12.5 1,360.00
LESS #6
FRONT D1 0.90 2.40 2.16 2.16 12.00 25.92 12.5 324.00
W2 1.40 1.50 2.10 2.10 12.00 25.20 12.5 315.00
REAR W1 2.50 1.50 3.75 3.75 12.00 45.00 12.5 562.50
W3 1.90 0.64 1.21 1.21 2.00 2.41 12.5 30.16
LESS #4
INTERIOR D3 0.80 2.10 1.68 1.68 2.00 3.36 12.5 42.00
D4 0.60 1.50 0.90 0.90 4.00 3.60 12.5 45.00
819.09
EAVES WALL SIDE FLASHING
CHB Width Length Area Deducted Net Area No. of Walls/ Total Area Factor No. of Pcs.
Size Area Surface
(m) (m) (sq.m.) (sq.m.) (sq.m.) n (sq.m.) (pcs./sq.m.) (pcs)
FRONT
#6 9.50 2.50 23.75 23.75 1.00 23.75 12.5 296.88
23.75
Masonry:
1ST FLOOR
CHB Width Length Area Deducted Net Area No. of Walls/ Total Area Factor No. of Pcs.
Size Area Surface
(m) (m) (sq.m.) (sq.m.) (sq.m.) n (sq.m.) (pcs./sq.m.) (pcs)
Quantity
Portland Cement
Sand
CHB
RSB
#16 G.I. Tie
PUBLIC WORKS AND HIGHWAYS
Say Remarks
(pcs)
Say Remarks
(pcs)
Say Remarks
(pcs)
1,233.00 TOTAL
Say Remarks
(pcs)
Say Remarks
(pcs)
Say Remarks
(pcs)
4,864.29 bags
2,414.10 cu.m.
- pcs.
13,865.62 kgs.
117.80 kgs.