Sei sulla pagina 1di 4

METHOD STATEMENT

SYSTEM: AIR CONDITION & VENTILATION

METHOD STATEMENT FOR


FAN COIL UNIT INSTALLATION

1. GENERAL
This method statement describes the Fan Coil Unit installation. Detail of the procedure contained herein may be
modified based on the actual site condition.

2. EQUIPMENT AND TOOLS


Basic equipment for installation of ventilation fan is as follows; 2.1
Ladder
2.2 Scaffolding
2.3 Drilling machine
2.4 Wrench
2.5 Adjustable wrench
2.6 Chain lock
2.7 Spirit level
3. WORKING PROCEDURE
3.1 Site Preparation
3.1.1 Check the builder.s work and installation location.
3.1.2 Check setting out of pipe route lines
3.2 Equipment Check
3.2.1 Check FCU type and model.
3.2.2 Check visible damage of FCU.
3.2.3 Rotate fan blower by hand for abnormality check of blower and housing.
3.2.4 Ensure that there is no foreign material inside blower and housing.
3.3 Installation
3.3.1 Check dimension of FCU base and mounting points.
3.3.2 Fix expansion bolts, rods.
3.3.3 Size of hanger rods and type of vibration isolator shall be followed the summary table.
3.3.4 Hang or mount FCU with rubber pads or spring vibration isolator in accordance with
standard installation drawing.
3.3.5 Adjust FCU level to meet drain water flow to direction of condensate drain pipe. Fix
bolts, nuts and washers.
3.3.6 In case of FCU install in the conceal area, service panel minimum size 450x450 mm.
shall be provided. Service panel location and its detail drawing shall be coordinated with
architectural work in working drawing stage.

Page 1 of 4
METHOD STATEMENT

SYSTEM: AIR CONDITION & VENTILATION

4. QUALITY CONTROL
Quality control works should be performed in the particular works as discussed in the following.
4.1 FCU type and Model shall be checked before transportation to installation place.
4.2 Installation work shall be performed in accordance with approved shop drawing and acceptance by
inspection and check list as per attachment.

Page 2 of 4
METHOD STATEMENT

SYSTEM: AIR CONDITION & VENTILATION

AIR HANDLING UNIT INSTALLATION FLOW CHART

START

CHECK TYPE, MODEL AND DIMENTION OF FCU.S BASE OR SUPPORT

PREPARE FOR FCU.S SUPPORT OR HANGER

INSTALL

ADJUST LEVEL

FIX BOLTS, NUTS AND WASHERS

END

Page 3 of 4
METHOD STATEMENT

SYSTEM: AIR CONDITION & VENTILATION

CHECK LIST FOR FAN COIL UNIT INSTALLATION

PROJECT NAME : ____________________________ REF. NO. : ____________


LOCATION : ______________________________ DATE : ____/____/____
GRID LINE : ______________________________
REFER DRAWING NO. : _______________ REV. NO. : _______________

FCU : UNIT NO. __________________


: TYPE __________________
: MODEL __________________

INSPECTION AND STATUS


ITEM DESCRIPTION TEST REQUIRED SATISFIED UNSATISFIED REMARK
Equipment Type & Model
1 Type and Model Check Type & Model

Installation
1 Hanger and/or Support Physical Check
2 Adjust Level Physical Check
3 Bolts & Nuts Physical Check
4 Vibration Isolator Physical Check

Note: _____________________________________________________________________________________
___________________________________________________________________________________________
___________________________________________________________________________________________
___________________________________________________________________________________________

Inspected by: Approved by:

Signature: _______________ Signature: _______________


Name: __________________ Name: __________________
Date: ___________________ Date: ___________________

Page 4 of 4