Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
ID PREDECESSORS DURARTION
DESCREPTION 1 2 3 4 1 2 3
(A) SITE WORK
a-1 site clearing/grabing none 1
a-2 temporary facility a-1 1
a-3 material mobilization/delivery a-1, a-2 15
a-4 lay-out/excavation a-1 4
( B ) CONCRETE
b-1 excavation
b-2 rebars a-3,a-4 6
b-3 pouring of conc. for footing b-2 2
b-4 form works for column b-3 3
b-5 pouring of conc. for columns b-4 4
b-6 form works for roof beam b-5 2
b-7 pouring of conc. for Beam b-6 3
( c) MASONRY
c-1 rebars 4
c-2 laying out of hollow blocks b-5 4
c-3 finishings c-2 5
( D ) METAL WORKS
railings installation c-3 2
(G) ELECTRICAL
g-1 roughing -in of conduits b-4 14
g-2 wirring installation b-4 14
g-3 receptacle installation and fin. b-4 7
(H) PLUMBING
h-1 pipe roughing-in b-4 14
h-2 water supply installtion b-4 14
h-3 Fixture installation b-4 6
( I ) ARCHITECTURAL FINISHING
i-1 tiling b-7 5
i-2 painting c-3 5
FEBRUARY MARCH APRIL
4 1 2 3 4 1 2 3 4