SITE INSPECTION AND TEST RECORD ΑΤΣ

Description: Contract no.: Record no. :


FPFM1-REL670- DISTANCE&DEF RELAY 30631089/00 STR-3011
Customer: Contractor: Sheet:
SEC-COA AL FANAR 1 of 15
Site: Drawing ref.: Project no.:
S/S 9021 S

FEEDER/BAY: OHL - 9013

1 GENERAL DATA AND INFORMATION:


Designation No. : + U15.5001 Rated Current: 1.0 A.
Manufacturer : ABB Sweden Rated Voltage: 110-220 VAC
Type No. : REL670Ver.1p1r07 Rated Freq. : 60 HZ
Serial No. : T0725134 Aux. Voltage : 90-250 VDC
Order No. : 1MRK002812-AB Software Ver.: 1.4-72a
Comm. Scheme : PERMISSIVE opto-coupler supply: 48-250 VDC

2 MECHANICAL CHECK AND VISUAL INSPECTION:


Item Description Checked
1 Inspection for physical damage / defects.
2 Verify connections as per approved drawing.
3 Check tightness of all connections
4 Check ferrules
5 Check apparatus list
3 ELECTRICAL TEST:

3.1 Function Test:

Item Description Checked


1 Human Machine Interface (HMI) checked.
2 Test switch checked for correct function.
3 Case earthing checked.
4 Indications checked.
5 Alarm contacts checked.
6 Trip contacts checked.
7 Reset of indications checked.

3.2 Operating DC supply current:


DC voltage DC current w/o fault DC current with fault(mA) Max. calculated watt
(V) (mA) (W)

Limit: DC burden 50 watts typically. (Refer to the reference technical manual page 24).

Tested by: Witnessed by:


Name: ENG./ MONTASEL Name: ENG./ WALI
Signature & Date: Signature & Date:

SRR-3012-REL670 DIST&DEF
SITE INSPECTION AND TEST RECORD ΑΤΣ
Description: Contract no.: Record no. :
FPFM1-REL670- DISTANCE&DEF RELAY 30631089/00 STR-3011
Customer: Contractor: Sheet:
SEC-COA AL FANAR 2 of 15
Site: Drawing ref.: Project no.:
S/S 9021 S

3.3 Setting Adopted:


Refer enclosed setting printout

3.4 Secondary Injection Tests:

3.4.1 Distance Protection:

3.4.1.1 Zone Reach Measurements:


Item Description Checked
1 Print out from Freja attached.
PH-E (PE): -Resistive reach: RFn (Ω/loop) = RFn (Ω/loop)*Mf
-Reactive reach: Xn (Ω/loop) = Xn (Ω/phase) + XNn (Ω/phase), XNn = KNx* Xn (Ω/phase),
KNx= 1/ 3 ((X0 – X1)/ X1)
S0: Xn (Ω/loop) = 1/ 3 {(2 * Xn (Ω/phase) + X0n (Ω/phase)}*Mf.

PH-PH (PP&3PH): -Resistive reach: RFn (Ω/phase) = 1/ 2 RFn (Ω/loop)*Mf.


- Reactive reach: Xn (Ω/phase) = Xn (Ω/phase)*Mf.

RFn: Zone n resistive reach resistance.


Xn: zone n positive sequence reactance.
XNn: zone n earth returns reactance.
KNx: reactive compensation factor.
X0n: zone n zero sequence reactance.
X0: line zero sequence reactance.
X1: line positive sequence reactance.
Mf: CTR/VTR.

3.4.1.2 Zone Timing Test:


Item Description Checked
1 Print out from Freja attached.
Limit: 24 ms typically ± 10ms ± 0.5 %.

The relay is tested on final setting

Tested by: Witnessed by:


Name: ENG./ MONTASEL Name: ENG./ WALI
Signature & Date: Signature & Date:
SITE INSPECTION AND TEST RECORD ΑΤΣ
Description: Contract no.: Record no. :
FPFM1-REL670- DISTANCE&DEF RELAY 30631089/00 STR-3011
Customer: Contractor: Sheet:
SEC-COA AL FANAR 3 of 15
Site: Drawing ref.: Project no.:
S/S 9021 S

3.4.2 Phase Selection Function (PHS):

3.4.2.1. PHS Reach measurements:


Item Description Checked
1 Print out from Freja attached.
PH-E (PE): -Resistive reach: RLdfwphs (Ω/loop) = RLdfwphs (Ω/loop)*Mf.&RFrvphs(Ω/loop)= RFrvphs(Ω/loop)*Mf
-Reactive reach: X1phs (Ω/loop) = 1/ 3 {(2 * X1phs (Ω/phase) + X0phs (Ω/phase)}*Mf.
PH-PH (PP): -Resistive reach: RFphs (Ω/phase) = 1/ 2 RFphs (Ω/loop)*Mf.
- Reactive reach: X1phs (Ω/phase) = X1phs (Ω/phase)*Mf.
3PH: -Resistive reach: RFphs (Ω/phase) = 0.666 RFphs (Ω/phase)*Mf
- Reactive reach: X1phs (Ω/phase) = 1.333 * X1phs (Ω/phase)*Mf.
3.4.2.2. PHS timing test:
Item Description Checked
1 Print out from Freja attached.
Limit: 24 ms typically ± 10ms ± 0.5 %.

3.4.3 Power Swing Detection (PSD):

3.4.3.1 PSD Reach test Measurement:

Item Description Checked


1 Print out from Freja attached.

3.4.3.2 Timing Test:

3.4.3.2.1 CHECK THE BLOCKING TIME (t R2):

SETTING VALUE MEASURED VALUE


2.00 SEC.
Limit: ± 10 ms (see the tech. ref. manual page 90).

- FREJA GENERAL MODE


-1ST STAGE: 3PHASE V&I (I=Ir, V/I >outer zone setting impedance).
-2ND STAGE: 3PHASE V&I (I=Ir, V/I <inner zone setting impedance).
-3RD STAGE TAKE du/dt = 0.2 v/sec.
-PSD start contact to dual timer.

The relay is tested on final setting

3.4.3.2.2 CHECK THE OPERATING TIME (TP1):

Tested by: Witnessed by:Tp1 actual


Name: ENG./ MONTASEL Name: ENG./ WALI
Signature & Date: Signature & Date:

SRR-3012-REL670 DIST&DEF
SITE INSPECTION AND TEST RECORD ΑΤΣ
Description: Contract no.: Record no. :
FPFM1-REL670- DISTANCE&DEF RELAY 30631089/00 STR-3011
Customer: Contractor: Sheet:
SEC-COA AL FANAR 4 of 15
Site: Drawing ref.: Project no.:
S/S 9021 S

3 phase 40
-Freja general mode, sequence, 3 stages.
-1ST STAGE: 3phase V&I to get the impedance outside the outer zone area (I=Ir & V/I>Zouter and T =1 SEC).
-2ND STAGE: 3phase V&I to get the impedance between the outer and the inner zone area (I=Ir, V/I<Zouter,
V/I >Zinner and adjust the time; start with 30 msec; till you get PSD start).
-3RD STAGE: 3phase V&I to get the impedance inside zone1 (I=Ir & V/I<Zzone1 and T =0.1 SEC).

3.4.3.3 Check of the blocking function:


Item Description Checked
1 Blocking of zone 1, 2,3 & 5
* Test procedure: SAME AS BEFOR ONLY CHANGE THE TIME FOR 3RD STAGE TO BE LESS
THAN 1 SEC.
3.4.3.4 Check of the relay tripping during power swing if a single phase faults
Occurred [ ]
* Test procedure: SAME AS BEFOR ONLY CHANGE THE 3RD STAGE TIME TO 200 msec AND
THE 4RD STAGE TO SINGLE PHASE FAULT.

3.4.4. CURRENT SENSITIVITY TEST:


Ir = 1.0 A IB=2000A
PHASE Setting (A) Z(Ω) EXPECTED(A) PICK UP (mA)
PHS PHS Zn PHS Z1 Z2 Z3 Z5
IMinOp IMinOp n=1,2,3,5 FW FW FW FW

R 10%IB Z≤Zn 0.1 0.1


Y 10%IB Z≤Zn 0.1 0.1
B 10%IB Z≤Zn 0.1 0.1
RY 10%IB Z≤Zn 0.1 0.1
YB 10%IB Z≤Zn 0.1 0.1
BR 10%IB Z≤Zn 0.1 0.1
RYB 10%IB Z≤Zn 0.1 0.1

IMinOp: zone n min. operating current. IB:base current


Limit PHS Imin : 1% of Ir (refer to reference Tec. Manual page : 174 table 87

The relay is tested on final setting

3.4.5. Directional test:


Line characteristic angle:
Relay directional angles: ArgDir (15) and ArgNegRes (115)
a) –forward direction; the operating chs Area from: to:
Tested by: Witnessed by:
Name: ENG./ MONTASEL Name: ENG./ WALI
Signature & Date: Signature & Date:

SRR-3012-REL670 DIST&DEF
SITE INSPECTION AND TEST RECORD ΑΤΣ
Description: Contract no.: Record no. :
FPFM1-REL670- DISTANCE&DEF RELAY 30631089/00 STR-3011
Customer: Contractor: Sheet:
SEC-COA AL FANAR 5 of 15
Site: Drawing ref.: Project no.:
S/S 9021 S

b) –reverse direction; the operating chs Area from: to:


c) – the non directional area from: to: and from to:
* Test procedure: -APPLY SINGLE PHASE V & I UNDER PHS SETTING. 90O
- CHANGE THE VOLTAGE ANGLE FROM 0 DEGREE UP TO
115O
360 DEGREE UNTIL THE INDICATION OF FW, REVESE
AND NON DIRECTIONAL APPEARS AS PER SETTING APPLIED.
FW
165O
ND 0O
3.4.6. Scheme Communication Test: 180 O

 Scheme selected: Permissive under reach. ND


ND
RV 345 O

 Coordination time : 0 ms.


3.4.6.1. carrier receive + Zone 2 fault 295 O

Trip Time : 270 O

Indication :
3.4.6.2. No carrier receive + Zone 2 fault
3.4.6.3. Trip Time :
Indication :
3.4.6.4. Zone 1 fault
Indication :
Carrier send time: ms.
T send min. : ms (100 ms setting)
* To check the T send min. time; the injection time should be less than 100ms.
Limit: ± 10 ms for operating time (see the tech. ref. manual page 122).

3.4.7 Dead Line Detection Function (DLD):


Setting Measured Values
Phase U<(V) I<(A) U<(V) U<(V) I<(mA) I<(mA)
op reset op reset
A 60%(39.84) 5%(0.05)
B 60%(39.84) 5%(0.05)
C 60%(39.84) 5%(0.05)
ABC 60%(39.84) 5%(0.05)
Limit: ± 1 % of Ur for U< and ± 1 % of Ir (see the tech. ref. manual page 242 table 125).
Testing guidelines: refer to the function logic and the commissioning manual page 95 .
TEST PROCEDURE:
- APPLY 3 PHASE V & I AT HEALTHY CASE ON GENERAL MODE.
- DECREASE ONE PHASE VOLTAGE UNTILL THE DLDUL INDICATION APPEARS.
- DECREASE ONE PHASE CURRENT UNTILL THE DLDIL INDICATION APPEARS.

3.4.8 Automatic Switch on to Fault (SOTF):


Tested by: Witnessed by:
Name: ENG./ MONTASEL Name: ENG./ WALI
Signature & Date: Signature & Date:

SRR-3012-REL670 DIST&DEF
SITE INSPECTION AND TEST RECORD ΑΤΣ
Description: Contract no.: Record no. :
FPFM1-REL670- DISTANCE&DEF RELAY 30631089/00 STR-3011
Customer: Contractor: Sheet:
SEC-COA AL FANAR 6 of 15
Site: Drawing ref.: Project no.:
S/S 9021 S

Distance Protection
SOTF - ON PHASE Trip Time indications
(msec)
*Internal SOTF with Select A
impedance mode. B LED4 SOTF TRIP
C
External SOTF with manual A
Close pulse. B LED4 SOTF TRIP
C
* Make at setting autoinit (on).
Testing guidelines: refer to the function logic and the commissioning manual page 140.

3.4.9 Fuse failure supervision function (FUSE):


Setting Measured Values
3U0 3I0< Ph 3U0>(V)op 3U0>(V)reset 3I0<(A) op 3I0<(A) reset
>V A ae
A

10% 10% B
(6.6) (0.1)
C

3U0= Ua + Ub + Uc
3I0= Ia + Ib + Ic
Limit: ± 1 % of Ur for 3U0> and ± 1 % of Ir (see the tech. ref. manual page 468 table 256).
Testing guidelines: refer to the function logic and the commissioning manual page 185.
GENERAL MODE
-1ST STAGE: 3PHASE V&I HEALTHY CASE.
- DECREASE ONE PHASE VOLTAGE TILL THE INDICAION LED FUSE FAIL APPERAS.
- DECREASE THE SAME PHASE CURRENT TILL THE INDICTION LED FUSE FAIL RESET.
3.4.9.1 Fuse failure operating time: m sec.
-1ST STAGE: 3PHASE V&I HEALTHY CASE.
-2ND STAGE: PUT FUSE FAIL CONDITION (TAKE CONTACT FUSE FAIL)
3.4.9.2 Check the blocking of the relay when the general block functions
(VT MCB TRIP) is activated [ ].
3.4.9.3 Check the latching facility of fuse fail function [ ].

3.4.9.4 V.T supervision latching time = sec.


* General mode:
- 1ST STAGE: 3PHASES V&I HEALTHY CASE. (TAKE TIME 1 SEC)
-2ND STAGE: PUT 3 PHASE (V) TO ACHIVE THE DLD AND FUSE FAIL FOR MORE THAN 5 SEC.
-USE CONTACT FUSE -VTF3PH.
Tested by: Witnessed by:
Name: ENG./ MONTASEL Name: ENG./ WALI
Signature & Date: Signature & Date:

SRR-3012-REL670 DIST&DEF
SITE INSPECTION AND TEST RECORD ΑΤΣ
Description: Contract no.: Record no. :
FPFM1-REL670- DISTANCE&DEF RELAY 30631089/00 STR-3011
Customer: Contractor: Sheet:
SEC-COA AL FANAR 7 of 15
Site: Drawing ref.: Project no.:
S/S 9021 S

3.4.9.5 Check the relay operation if a fault occurred during the fuse fail [ ].
* General mode:
- 1ST STAGE: FUSE FAIL CONDITION (TAKE TIME 1 SEC)
-2ND STAGE: FAULT CONDITION
3.4.9.6. Check the blocking of the relay when the general block functions
(DISCPO binary input) is activated [ ].
Simulate normal operating conditions 3PHASES V&I HEALTHY CASE
Active DISCPO binary input The BLKU Signals appear without any time delay
The BLKZ and 3PH Signals not appear.
Only distance protection function operates.

3.4.9.7Checking the operation of the du/dt &di/dt based function:


Setting Measured Values
Indication

DU> DI< Phase DU > DI <


op op Yellow Led
Seting Seting Fuse fail
Alarm
60% A
25%Ibase
Ubase B
(0.25)
(39.84) C
* General mode:
- 1ST STAGE: 3PHASES V&I HEALTHY CASE. -

-2ND STAGE: PUT 3 PHASE (V) TO ACHIVE THE DLD AND FUSE FAIL FOR MORE THAN 5 SEC.
-USE CONTACT FUSE -VTF3PH
From st2 change the voltages and currents in all three phases simultaneously The voltage change should be greater then set DU>& The voltage
change should be Lessr than set DI<
Connect nominal dc voltage to the CBCLOSED binary input.
The BLKU and BLKZ Signals appear without any time delay .BLKZ signal will be activated ,only if the DLD is not activated at the same time.
Also 3PH Should appear after 5 sec if the remaining voltage levels are lower than the set UDLD < VDLDPU OF THE DLD Function.

Apply normal conditions the BLKU, BLKZ and 3PH signals should reset.

Repeat same procedure without CBCLOSED binary input not active .

DU> OP = ( 66.4-voltage get from stage2 when fuse fail alarm get) and also DI< =( 1.0 - CURRENT get from stage2 when fuse fail alarm get)

Stage1 : 66.4∟0+66.4∟240+66.4∟120 V 1.0∟0 + 1.0∟240 + 1.0∟120 Amp


Stage2 : get fuse fail at 25.85∟0 + 25.85∟240 + 25.85∟120 V 0.749 ∟0 + 0.749 ∟240 + 0.749∟120 Amp

3.4.10. Service values for measurements:


PH voltage applied: 66.4 V.
PH current applied: 1.0 A.

Tested by: Witnessed by:


Name: ENG./ MONTASEL Name: ENG./ WALI
Signature & Date: Signature & Date:

SRR-3012-REL670 DIST&DEF
SITE INSPECTION AND TEST RECORD ΑΤΣ
Description: Contract no.: Record no. :
FPFM1-REL670- DISTANCE&DEF RELAY 30631089/00 STR-3011
Customer: Contractor: Sheet:
SEC-COA AL FANAR 8 of 15
Site: Drawing ref.: Project no.:
S/S 9021 S

Phase shift : 0,240,120 degree.


Frequency : 60 HZ.
CT ratio : 2000/1 A.
VT ratio : 380/0.115 KV.

Values Sec. Values Prim. values Values Sec. Values Prim. Values

UL1 IL1

UL2 IL2

UL3 IL3

UL4 IL4
- -
UL1 – UL2 P
- -
UL2 – UL3 Q
- -
UL3 – UL1 F

3-5 DIRECTIONAL EARTH FAULT TEST (DEF)

Tested by: Witnessed by:


Name: ENG./ MONTASEL Name: ENG./ WALI
Signature & Date: Signature & Date:
SITE INSPECTION AND TEST RECORD ΑΤΣ
Description: Contract no.: Record no. :
FPFM1-REL670- DISTANCE&DEF RELAY 30631089/00 STR-3011
Customer: Contractor: Sheet:
SEC-COA AL FANAR 9 of 15
Site: Drawing ref.: Project no.:
S/S 9021 S

3.5.1 INDir. PICKUP AND DROP OFF LEVEL :


a) UNRel has a setting of 1% of base voltage.
Ubase = 380 Kv
Ibase = 3000 A
b) The relay characteristic angle has setting of 60 degree.
Pick-up Drop-off
Setting INDir(A) Angle
Value (mA) Value (mA) Indication
o
0.05 X Ibase =0.05 60
o
0.20 x Ibase=0.20 60
o
0.35 X Ibase =0.35 60
o
1.0X base=1.0 60

Limit: Setting ≤Ir ±1% of Ir


Setting (2.5 – 10 mA) 0.5 m A
Setting (2.5 – 50 mA) 1.0 m A
Refer to the logic and the commissioning manual page 304 table :156
*use the general start contact to monitor the pick up and drop off values (U11.115.X21:7, 9).

3.5.2 Check the operating characteristic angle:


A- Forward direction: from to .
B-Reverse direction: from to .
(For directional check use the contacts -STFW & -STRV; U11.115.X21:1, 2 & 1, 5)
Tested by: Witnessed by:
Name: ENG./ MONTASEL Name: ENG./ WALI
Signature & Date: Signature & Date:
SITE INSPECTION AND TEST RECORD ΑΤΣ
Description: Contract no.: Record no. :
FPFM1-REL670- DISTANCE&DEF RELAY 30631089/00 STR-3011
Customer: Contractor: Sheet:
SEC-COA AL FANAR 10 of 15
Site: Drawing ref.: Project no.:
S/S 9021 S

3Io PICK UP AT VARIOUS OPERATING ANGLE:


INDir Set = 0.2 A UN REL = 0.664 V

Pick-up Drop-off
SET TIME
Disturbance
Angle OP TIME
Value (mA) Value (mA) recorder
SEC

0 FORWARD
0.0

FORWARD
60 1.0
1.5 FORWARD
145
- - REVERSE
155
- - REVERSE
225
- - REVERSE
270
- - REVERSE
325
1.0 FORWARD
335

Tested by: Witnessed by:


Name: ENG./ MONTASEL Name: ENG./ WALI
Signature & Date: Signature & Date:
SITE INSPECTION AND TEST RECORD ΑΤΣ
Description: Contract no.: Record no. :
FPFM1-REL670- DISTANCE&DEF RELAY 30631089/00 STR-3011
Customer: Contractor: Sheet:
SEC-COA AL FANAR 11 of 15
Site: Drawing ref.: Project no.:
S/S 9021 S

3.5.3 POLARIZING VOLTAGE (UNRel) PICKUP AND DROP OFF TEST:


Set INDir =3Io = 0.2 A
UNRel setting Operating values at 2* Is
% of Uph (volts) Angle Pick up Volts Drop off Volts Indication
o
1 % =0.664 V 60
o
5 %=3.32 V 60
o
10%=6.64V 60
f) CHANNEL SEND & START REVERSE FUNCTIONS:
Contact Contact Oper time
Fault Oper time
(channel send) Indication (start reverse) Indication
U11.101:2B U11.115.X131:7
Forward fault(P.S)
U11.101:1B U11.115.X131:8
U11.101:2B U11.115.X131:7
Reverse fault(B.S)
U11.101:1B U11.115.X131:8
Note: P.S=permissive scheme and B.S=blocking scheme.
3.5.4 CHANEL DELAY TIME To ‘T coordination’: (Permissive scheme).
Energize: forward fault with Channel Receive input IDIR= 0.2A, Injected = 2xIDIR

Tested by: Witnessed by:


Name: ENG./ MONTASEL Name: ENG./ WALI
Signature & Date: Signature & Date:
SITE INSPECTION AND TEST RECORD ΑΤΣ
Description: Contract no.: Record no. :
FPFM1-REL670- DISTANCE&DEF RELAY 30631089/00 STR-3011
Customer: Contractor: Sheet:
SEC-COA AL FANAR 12 of 15
Site: Drawing ref.: Project no.:
S/S 9021 S

To set Operating time Contact Indication


(ms) ms
0 mSec U11.101:1B
50 mSec U11.101:5B

*Actual time = T set + T start ± 10 ms ± 0.5 %.


* T start = operated time start function typically 150ms at 0 to 2Iset
See the technical reference manual–page:304-305.table 156
3.5.5 BACK UP TIME ‘T def’: (Permissive scheme)
Energize: forward fault without Channel Receive input IN dir= 0.2A, Injected = 2xINdir
Tdif set Operating time Contact Indication
ms ms
0
400 U11.101:1B
1000 U11.101:10B
3000

* T start = operated time start function typically 150ms at 0 to 2Iset ..


Timer accuracy.=±10ms±0.5%,Actual time=Tset+Tstart±10ms±0.5%,
See the technical reference manual–page:304 - 305table 156.

3.5.6 INNonDir. PICKUP AND DROP OFF LEVEL :

Pick-up Drop-off
Setting
INNonDir Value (mA) Value (mA)
Indication
0.05 X Ibase
=0.05 A
0.20 x 67N/51N DELAY
Ibase=0.20 A TRIP LED 6
0.5 X Ibase
=0.50 A
1.0X base=1.0
A

Limits: Setting ≤Ir ±1% of Ir

Setting (10 – 50) mA) 1.0 m A


Tested by: Witnessed by:
Name: ENG./ MONTASEL Name: ENG./ WALI
Signature & Date: Signature & Date:
SITE INSPECTION AND TEST RECORD ΑΤΣ
Description: Contract no.: Record no. :
FPFM1-REL670- DISTANCE&DEF RELAY 30631089/00 STR-3011
Customer: Contractor: Sheet:
SEC-COA AL FANAR 13 of 15
Site: Drawing ref.: Project no.:
S/S 9021 S

See the technical reference manual–page:304 - 305table 156

3.5.7 BACK UP TIME ‘tINNonDir’


Operate time Indication
tINNonDir
sec sec
0
67N/51N DELAY TRIP
1.0
LED 6
1.5
2

*Actual time = tINNonDir set + 60ms ± 10 ms ± 0.5 %.


OPERATE TIME AT 2ISET =60ms typically AT 0.0 SEC SET

See the technical reference manual–page:304 - 305table 156

3.5.8 WEAK END INFEED ECHO:


WEI ECHO = ON
a. Apply momentary pulse to Channel Receive Input (U11.101:11B):
Without any fault injection and check Channel send is given.
Channel Send operating time: __________________
Channel sends pulse length : ________________ (<200ms)
Indications : __________________
Tested by: Witnessed by:
Name: ENG./ MONTASEL Name: ENG./ WALI
Signature & Date: Signature & Date:
SITE INSPECTION AND TEST RECORD ΑΤΣ
Description: Contract no.: Record no. :
FPFM1-REL670- DISTANCE&DEF RELAY 30631089/00 STR-3011
Customer: Contractor: Sheet:
SEC-COA AL FANAR 14 of 15
Site: Drawing ref.: Project no.:
S/S 9021 S

b. Apply a reverse fault with CR and check that


no channel Send is given __________________
3.5.9 WEAK END INFEED TRIP:
WEI TRIP = ON
a. Apply momentary pulse to Channel Receive Input (U11.101:11B)
and check trip is given when 3I0 is zero and 3U0 is above the following values.
S.NO. Us Us Us Indication
set cal (V) meas (V)
1 0.05 x Uph 3.32
2 0.20 x Uph 13.28
3 0.35 x Uph 23.24

* Voltage accuracy: ± 1 % of Ur (see tech. ref. manual page 648 table 342)
Measured Trip time = ________________ms
- - ( time accuracy ± 0.5% ± 10 msec).
-See the technical reference manual–page:648table 342.
b. Apply a reverse fault with CR and check for the above condition that
no WEI trip is given. : ___________
3.5.10 CURRENT REVERSAL LOGIC CHECK:Curr Rev = ON
a) Apply a reverse fault to check: t pick up (I > I setting and V > V setting
Freja general mode, sequence, 3 stages 1ST STAGE: 3phase V&I to get the forward fault
2ND STAGE: 3phase V&I to get the get reverse fault T≥Tdelay seting
3RD STAGE: 3phase V&I to get the forward fault T≥Tdelay seting
T pick up:
T pick up Operating time Contact Indication
(ms) ms
0 mSec U11.115.X131:13
500mSec U11.115.X131:14
1000mSec

3.6 Trip indication test For Distance& DEF:


No. Type of fault Indication Led No Remark
01 Z1 , single phase L1 Z1 trip & start L1, 21CS, Led1&7,12,
02 Z , duple phase L 2 & L3 Z1 trip&start L2,L3, 21CS, Led1&7,8,12,
Z1 , three phase Z1 trip&startL1,L2,L3, 21CS, Led1&7,8,9,12,
03
14
04 Z2 , single phase L2 Z2,3,5 delay trip &start L2 Led1&8
05 Z2 , duple phase L 1 & L3 Z2,3,5 delay trip&start L1,L3, Led3&7,9,
Tested by: Witnessed by:
Name: ENG./ MONTASEL Name: ENG./ WALI
Signature & Date: Signature & Date:
SITE INSPECTION AND TEST RECORD ΑΤΣ
Description: Contract no.: Record no. :
FPFM1-REL670- DISTANCE&DEF RELAY 30631089/00 STR-3011
Customer: Contractor: Sheet:
SEC-COA AL FANAR 15 of 15
Site: Drawing ref.: Project no.:
S/S 9021 S

06 Z2 , three phase Z2,3,5 delay trip 7start L1,L2,L3, Led3&7,8,9,


07 Z2 , single phase L3 with CR Distance aided trip&start L3,CR, Led2&9,13,
08 Z3 , single phase L3 Z2,3,5 delay trip7start L3, Led3&9,
09 Z3 , duple phase L 1& L2 Z2,3,5 delay trip&start L1,L2, Led3&7,8,
10 Z3 , three phase Z2,3,5 delay trip&start L1,L2,L3, Led3&7,8,9,
11 Z5 , single phase L1 Z2,3,5 delay trip &startL1 Led3&7
12 Z5 , duple phase L1&L2 Z2,3,5 delay trip&start L1,L2, Led3&7,8
13 Z5 , three phase Z2,3,5 delay trip&startL1,L2,L3, Led3&7,8,9
Z4 , single phase L2 with active SOTF trip &start L2, Led4&8
14 SOTF Binary input CB Close
15 Power swing condition PSD Start Led10
16 Fuse Faliure condition Fuse Fail Alarm Led11
Distance CS Distance CS Led12
17
Distance CR Distance CR Led13
18
DEF 67N CS DEF 67N CS Led14
19
DEF 67N CR DEF 67N CR Led15
20
21 DEF,FW WITH CR DEF AIDED TRIP,CR,CS Led5,14,15
22 DEF 67N FW WIithout CR 67N &51N DELAY TRIP,CS Led6,14
23 DEF Non DIR 67N &51N DELAY TRIP Led6
3.4.12 Disturbance recorder checked [ ].
3.4.13 Binary outputs checked [ ].
3.4.14 Binary inputs checked [ ]

Tested by: Witnessed by:


Name: ENG./ MONTASEL Name: ENG./ WALI
Signature & Date: Signature & Date: