Proyecto EPC Mina AAA Fecha: 24.10.

2015

Activity ID Activity Name Duration Start Finish Total Float Budgeted Total N D January 2014 F March 2014 April 2014 May 2014 June 2014
Cost
28 04 11 18 25 02 09 16 23 30 06 13 20 27 03 10 17 24 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23
EPC Mina AAA 158.00d 04-Nov-13 07:00 AM 15-Jun-14 05:00 PM 0.00d $472,434.61
Hitos 158.00d 04-Nov-13 07:00 AM 15-Jun-14 05:00 PM 0.00d $0.00
HT.001 Inicio 0.00d 04-Nov-13 07:00 AM 0.00d $0.00 Inicio
HT.002 Fin 0.00d 15-Jun-14 05:00 PM 0.00d $0.00 Fin
Ingeniería Detalle 67.00d 04-Nov-13 07:00 AM 06-Feb-14 05:00 PM 81.00d $120,258.00
Chancado Primario 67.00d 04-Nov-13 07:00 AM 06-Feb-14 05:00 PM 81.00d $120,258.00
Procesos 26.00d 04-Nov-13 07:00 AM 09-Dec-13 05:00 PM 8.00d $21,656.00
E.400.40.001 Process Flow Diagram (PFD) 12.00d 04-Nov-13 07:00 AM 19-Nov-13 05:00 PM 0.00d $13,520.00
E.400.40.003 Memoria Descriptiva y Balance Metalúrgico 10.00d 07-Nov-13 07:00 AM 20-Nov-13 05:00 PM 8.00d $2,416.00
E.400.40.004 Memoria de cálculo 8.00d 21-Nov-13 07:00 AM 02-Dec-13 05:00 PM 8.00d $1,904.00
E.400.40.002 Criterios de Diseño 5.00d 03-Dec-13 07:00 AM 09-Dec-13 05:00 PM 8.00d $3,816.00
Mecánica 50.00d 11-Nov-13 07:00 AM 21-Jan-14 05:00 PM 6.00d $30,240.00
E.400.43.001 Planos (Arreglo General y Detalle) 25.00d 11-Nov-13 07:00 AM 13-Dec-13 05:00 PM 0.00d $5,300.00
E.400.43.002 Criterio Diseño Mecánico 12.00d 11-Nov-13 07:00 AM 26-Nov-13 05:00 PM 1.00d $2,880.00
E.400.43.003 Listado de Equipos 7.00d 19-Nov-13 07:00 AM 27-Nov-13 05:00 PM 0.00d $1,160.00
E.400.43.004 Especificaciones técnicas 10.00d 28-Nov-13 07:00 AM 11-Dec-13 05:00 PM 0.00d $4,780.00
E.400.43.005 Memorias de cálculo 12.00d 12-Dec-13 07:00 AM 30-Dec-13 05:00 PM 6.00d $4,920.00
E.400.43.006 Hoja de Datos 5.00d 31-Dec-13 07:00 AM 07-Jan-14 05:00 PM 6.00d $5,160.00
E.400.43.007 Requisición de Materiales 10.00d 08-Jan-14 07:00 AM 21-Jan-14 05:00 PM 6.00d $6,040.00
Civil 41.00d 28-Nov-13 07:00 AM 27-Jan-14 05:00 PM 18.00d $22,374.00
E.400.41.002 Memoria descriptiva y especificaciones técnicas 10.00d 28-Nov-13 07:00 AM 11-Dec-13 05:00 PM 0.00d $2,325.00
E.400.41.003 Memoras de cálculo (Concreto) 15.00d 12-Dec-13 07:00 AM 03-Jan-14 05:00 PM 0.00d $1,359.00
E.400.41.001 Planos (Arreglos Generales y Detalle) 20.00d 30-Dec-13 07:00 AM 27-Jan-14 05:00 PM 0.00d $16,200.00
E.400.41.004 Metrados 12.00d 09-Jan-14 07:00 AM 24-Jan-14 05:00 PM 19.00d $2,490.00
Estructural 40.00d 28-Nov-13 07:00 AM 24-Jan-14 05:00 PM 23.00d $16,018.00
E.400.44.002 especificaciones técnicas y criterios de Diseño 10.00d 28-Nov-13 07:00 AM 11-Dec-13 05:00 PM 23.00d $1,900.00
E.400.44.003 Memorias de cálculo (Acero) 10.00d 12-Dec-13 07:00 AM 26-Dec-13 05:00 PM 23.00d $1,198.00
E.400.44.001 Planos Detalles 20.00d 27-Dec-13 07:00 AM 24-Jan-14 05:00 PM 23.00d $10,560.00
E.400.44.004 Metrados - Hoja Datos 10.00d 27-Dec-13 07:00 AM 10-Jan-14 05:00 PM 23.00d $1,145.00
E.400.44.005 Requisión de materiales 10.00d 13-Jan-14 07:00 AM 24-Jan-14 05:00 PM 23.00d $1,215.00
Tuberías 35.00d 28-Nov-13 07:00 AM 17-Jan-14 05:00 PM 41.00d $13,908.00
E.400.45.002 Criterios de Diseño y especificaciones técnicas 4.00d 28-Nov-13 07:00 AM 03-Dec-13 05:00 PM 28.00d $1,720.00
E.400.45.004 Memorias de cálculo 8.00d 04-Dec-13 07:00 AM 13-Dec-13 05:00 PM 39.00d $2,500.00
E.400.45.001 Planos P&IDs / Isométricos & Líena de tuberías 15.00d 16-Dec-13 07:00 AM 07-Jan-14 05:00 PM 39.00d $6,560.00
E.400.45.003 Metrados (Tuberías, accesorios y válvulas) 6.00d 26-Dec-13 07:00 AM 03-Jan-14 05:00 PM 41.00d $1,312.00
E.400.45.005 Requisición de materiales 10.00d 06-Jan-14 07:00 AM 17-Jan-14 05:00 PM 41.00d $1,816.00
Eléctrica 39.00d 28-Nov-13 07:00 AM 23-Jan-14 05:00 PM 28.00d $7,262.00
E.400.46.002 Criterios de Diseño 5.00d 28-Nov-13 07:00 AM 04-Dec-13 05:00 PM 28.00d $860.00
E.400.46.003 Especificaciones técnicas 6.00d 05-Dec-13 07:00 AM 12-Dec-13 05:00 PM 28.00d $1,220.00
E.400.46.005 Memoria de cálculo 8.00d 13-Dec-13 07:00 AM 24-Dec-13 05:00 PM 28.00d $1,324.00
E.400.46.001 Planos (Diagrama unifilares, Arreglos y puesta a tierra) 15.00d 26-Dec-13 07:00 AM 16-Jan-14 05:00 PM 28.00d $1,464.00
E.400.46.004 Listado (Equipos y Cables) 10.00d 26-Dec-13 07:00 AM 09-Jan-14 05:00 PM 28.00d $674.00
E.400.46.006 Requisición de materiales 10.00d 10-Jan-14 07:00 AM 23-Jan-14 05:00 PM 28.00d $1,720.00
Instrumentación 49.00d 28-Nov-13 07:00 AM 06-Feb-14 05:00 PM 81.00d $8,800.00

Critical Remaining Work Summary Date Revision Checked Approved


25-Oct-15 12:00 AM A OK OK
Milestone Remaining Work
Proyecto EPC Mina AAA Fecha: 24.10.2015

Activity ID Activity Name Duration Start Finish Total Float Budgeted Total N D January 2014 F March 2014 April 2014 May 2014 June 2014
Cost
28 04 11 18 25 02 09 16 23 30 06 13 20 27 03 10 17 24 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23
E.400.47.001 Criterios de Diseño 6.00d 28-Nov-13 07:00 AM 05-Dec-13 05:00 PM 47.00d $810.00
E.400.47.002 Especificaciones técnicas 5.00d 06-Dec-13 07:00 AM 12-Dec-13 05:00 PM 57.00d $780.00
E.400.47.008 Filosofía de Control 7.00d 06-Dec-13 07:00 AM 16-Dec-13 05:00 PM 47.00d $610.00
E.400.47.004 Arquitectura de Control 12.00d 17-Dec-13 07:00 AM 03-Jan-14 05:00 PM 47.00d $1,420.00
E.400.47.005 Listado de instrumentos 8.00d 30-Dec-13 07:00 AM 09-Jan-14 05:00 PM 39.00d $610.00
E.400.47.003 Planos de Detalle 15.00d 06-Jan-14 07:00 AM 24-Jan-14 05:00 PM 90.00d $2,590.00
E.400.47.006 Hoja de Datos 10.00d 10-Jan-14 07:00 AM 23-Jan-14 05:00 PM 39.00d $730.00
E.400.47.007 Requisición de materiales 10.00d 24-Jan-14 07:00 AM 06-Feb-14 05:00 PM 39.00d $1,250.00
Procura 90.00d 22-Jan-14 07:00 AM 21-Apr-14 05:00 PM 51.00d $101,500.00
Chancado Primario 90.00d 22-Jan-14 07:00 AM 21-Apr-14 05:00 PM 51.00d $101,500.00
Mecánica 90.00d 22-Jan-14 07:00 AM 21-Apr-14 05:00 PM 8.00d $12,000.00
P.400.43.002 Chutes de descarga 90.00d 22-Jan-14 07:00 AM 21-Apr-14 05:00 PM 8.00d $12,000.00
P.400.43.001 Chancadora Primaria (Cliente) 0.00d 15-Apr-14 07:00 AM 0.00d $0.00 Chancadora...
Estructural 70.00d 25-Jan-14 07:00 AM 04-Apr-14 05:00 PM 42.00d $55,000.00
P.400.44.001 Estructura Metálica Mediana (30kg/m < W < 60kg/m) 70.00d 25-Jan-14 07:00 AM 04-Apr-14 05:00 PM 33.00d $30,000.00
P.400.44.002 Coberturas Edificio Ch.Primario 70.00d 25-Jan-14 07:00 AM 04-Apr-14 05:00 PM 42.00d $25,000.00
Tuberías 70.00d 24-Jan-14 07:00 AM 03-Apr-14 05:00 PM 53.00d $6,000.00
P.400.45.001 Tubería, CS ASTM A-53 Grado B Tipo E 70.00d 24-Jan-14 07:00 AM 03-Apr-14 05:00 PM 53.00d $6,000.00
Eléctrica 83.00d 24-Jan-14 07:00 AM 17-Apr-14 07:00 AM 48.00d $19,500.00
P.400.46.002 Conductor de cobre desnudo 4/0 70.00d 24-Jan-14 07:00 AM 03-Apr-14 05:00 PM 40.00d $4,500.00
P.400.46.003 Cables de baja tensión 70.00d 24-Jan-14 07:00 AM 03-Apr-14 05:00 PM 61.00d $15,000.00
P.400.46.001 Sala Eléctrica y Equipamiento (Cliente) 0.00d 17-Apr-14 07:00 AM 40.00d $0.00 Sala Eléct...
Instrumentación 60.00d 07-Feb-14 07:00 AM 07-Apr-14 05:00 PM 65.00d $9,000.00
P.400.47.001 Instrumentos (Medidores nivel-Chutes de descarga) 60.00d 07-Feb-14 07:00 AM 07-Apr-14 05:00 PM 55.00d $5,000.00
P.400.47.002 Dispositivos Detección de Alarmas e incendios 60.00d 07-Feb-14 07:00 AM 07-Apr-14 05:00 PM 65.00d $4,000.00
Construcción 115.00d 21-Feb-14 07:00 AM 15-Jun-14 05:00 PM 0.00d $250,676.61
Chancado Primario 115.00d 21-Feb-14 07:00 AM 15-Jun-14 05:00 PM 0.00d $250,676.61
Civil 43.00d 21-Feb-14 07:00 AM 04-Apr-14 05:00 PM 0.00d $35,882.56
C.400.41.001 Excavación localizada para cimentaciones 6.00d 21-Feb-14 07:00 AM 26-Feb-14 05:00 PM 0.00d $2,463.81
C.400.41.000 Recepción del área (Acta de entrega) 0.00d 21-Feb-14 07:00 AM 0.00d $0.00 Recepción ...
C.400.41.002 Solado (Fc=100Kg/cm2) 6.00d 27-Feb-14 07:00 AM 04-Mar-14 05:00 PM 0.00d $11,511.15
C.400.41.003 Acero refuerzo Cimentaciones(Fy=4200 Kg/cm2) 1.00d 05-Mar-14 07:00 AM 05-Mar-14 05:00 PM 0.00d $632.15
C.400.41.004 Encofrado y desencofrado-Cimentaciones 4.00d 06-Mar-14 07:00 AM 09-Mar-14 05:00 PM 0.00d $1,010.00
C.400.41.005 Concreto Cimentaciones (Fc=280Kg/m2) 1.00d 10-Mar-14 07:00 AM 10-Mar-14 05:00 PM 0.00d $2,449.20
C.400.41.006 Acero refuerzo Ch.Primaria 6.00d 16-Mar-14 07:00 AM 21-Mar-14 05:00 PM 0.00d $4,660.83
C.400.41.009 Acero refuerzo Pedestales (Fy=4200 Kg/cm2) - Estructuras 3.00d 16-Mar-14 07:00 AM 18-Mar-14 05:00 PM 16.00d $2,303.31
C.400.41.007 Encofrado y desencofrado Ch.Primaria(Fy=4200 Kg/cm2) 10.00d 22-Mar-14 07:00 AM 31-Mar-14 05:00 PM 0.00d $2,627.74
C.400.41.008 Concreto Ch.Primaria (Fc=280Kg/m2) 3.00d 01-Apr-14 07:00 AM 03-Apr-14 05:00 PM 0.00d $6,823.14
C.400.41.010 Concreto Pedestales (Fc=280Kg/m2) - Estructuras 1.00d 04-Apr-14 07:00 AM 04-Apr-14 05:00 PM 0.00d $1,401.23
Mecánica 23.00d 15-Apr-14 07:00 AM 07-May-14 05:00 PM 0.00d $63,000.00
C.400.43.001 Montaje Ch.Primaria 15.00d 15-Apr-14 07:00 AM 29-Apr-14 05:00 PM 0.00d $58,000.00
C.400.43.002 Montaje Chutes Descarga 8.00d 30-Apr-14 07:00 AM 07-May-14 05:00 PM 0.00d $5,000.00
Estructuras 19.00d 08-May-14 07:00 AM 26-May-14 05:00 PM 0.00d $58,200.29
C.400.44.001 Montaje Estructuras Edificio Ch.Primario 9.00d 08-May-14 07:00 AM 16-May-14 05:00 PM 0.00d $44,900.00

Critical Remaining Work Summary Date Revision Checked Approved


25-Oct-15 12:00 AM A OK OK
Milestone Remaining Work
Proyecto EPC Mina AAA Fecha: 24.10.2015

Activity ID Activity Name Duration Start Finish Total Float Budgeted Total N D January 2014 F March 2014 April 2014 May 2014 June 2014
Cost
28 04 11 18 25 02 09 16 23 30 06 13 20 27 03 10 17 24 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23
C.400.44.002 Montaje Coberturas Edificio Ch.Primario 10.00d 17-May-14 07:00 AM 26-May-14 05:00 PM 0.00d $13,300.29
Tuberías 6.00d 27-May-14 07:00 AM 01-Jun-14 05:00 PM 0.00d $10,872.00
C.400.45.001 Montaje de Tuberías CS 6.00d 27-May-14 07:00 AM 01-Jun-14 05:00 PM 0.00d $10,872.00
Eléctrica 33.00d 04-Apr-14 07:00 AM 06-May-14 05:00 PM 40.00d $66,000.00
C.400.46.001 Instalación Malla a tierra 8.00d 04-Apr-14 07:00 AM 11-Apr-14 05:00 PM 40.00d $24,160.00
C.400.46.002 Montaje Sala eléctrica 8.00d 17-Apr-14 07:00 AM 24-Apr-14 05:00 PM 40.00d $35,000.00
C.400.46.003 Cabaleado baja tensión 12.00d 25-Apr-14 07:00 AM 06-May-14 05:00 PM 40.00d $6,840.00
Instrumentación 14.00d 02-Jun-14 07:00 AM 15-Jun-14 05:00 PM 0.00d $16,721.76
C.400.47.001 Instalación de instrumentos 10.00d 02-Jun-14 07:00 AM 11-Jun-14 05:00 PM 0.00d $15,106.00
C.400.47.002 Instalación de dispositivos de alarma contra incendio 4.00d 12-Jun-14 07:00 AM 15-Jun-14 05:00 PM 0.00d $1,615.76

Critical Remaining Work Summary Date Revision Checked Approved


25-Oct-15 12:00 AM A OK OK
Milestone Remaining Work