Sei sulla pagina 1di 14

PIACENZA, February 09th 2012

POLITECNICO DI MILANO
Campus Piacenza
DEPARTMENT OF ENERGY

Written test of
ELECTRIC NETWORKS AND REGULATION FOR RENEWABLE
ENERGY SOURCES (SMART GRIDS)

(NAME-SURNAME):______________________________PERSONAL CODE_|_|_|_|_|_|_|

EXERCISE 1

GENERATOR G1 Sn = 100 MVA, VnomG1 = 15 kV


GENERATOR G2 Sn = 80 MVA, VnomG2 = 20 kV
TRANSFORMER T1 Sn = 120 MVA, V1nomT1= 15 kV, V2nomT1= 132 kV, vcc = 10%
TRANSFORMER T2 Sn = 100 MVA, V1nomT2= 132 kV, V2nomT2= 20 kV, vcc = 15%
LINE L1 VL1 = 132 kV, LL1 = 80 km, XL1 = 0.2 Ω/km
LINE L2 VL2 = 132 kV, LL2 = 50 km, XL2 = 0.3 Ω/km
LINE L3 VL3 = 132 kV, LL3 = 10 km, XL3 = 0.1 Ω/km
LINE L4 VL4 = 132 kV, LL4 = 30 km, XL4 = 0.15 Ω/km
LOAD C1 Sn = 50 MVA, cosφ = 0.7 lagging

Based on the information in the Table, the candidate should:


 calculate the per unit system for the network in the Figure
 calculate the per unit bus admittance matrix Ybus (6x6 matrix) for the network in the Figure
 comment about a possible simpler Ybus modeling the same network

Page 1
PIACENZA, February 09th 2012

Page 2
PIACENZA, February 09th 2012

Page 3
PIACENZA, February 09th 2012

Page 4
PIACENZA, February 09th 2012

EXERCISE 2

The figure shows the electrical scheme of a PV plant.


 The PV plant has a rated power equal to 900 kW. The produced energy E-p is equal to
1.200.000,00 kWh (costant during the whole life of a PV plant).
 The total energy losses are:
LV/LV transformer losses 0,20%
Inverter losses 0,60%
LV/MV transformer losses 2,00%

 The PV plant became operational after June 2011  Quarto Conto Energia. The PV plant is
classified as “Other PV”
Plants in operation after 30/06/2011
Power [kWp]
On Buildings [€/kWh] Other PV [€/kWh]
1<P≤3 0,368 0,327
3<P≤20 0,339 0,303
20<P≤200 0,321 0,291
200<P≤1.000 0,303 0,263
1.000<P≤5.000 0,280 0,250
P>5.000 0,269 0,238

 The minimum guaranteed price for the energy injected is always equal to 0,1034 €/kWh.
 The CTR income is equal to 0,00388 €/kWh.
 The total cost of PV plant is equal to € 3.000.000,00 (CAPEX); the operation and maintenance
costs are equal to 1,5% of the cost of PV plant; GSE and measurement fees are equal to 0.
 The inflation rate for costs is equal to 2%; the inflation rate for revenues is equal to 1%

Based on the information above, the candidate should


 calculate the operating profit for a PV plant at the year 5;
 comment the simplified approach adopted.

Page 5
PIACENZA, February 09th 2012

Page 6
PIACENZA, February 09th 2012

Page 7
PIACENZA, February 09th 2012

Page 8
PIACENZA, February 09th 2012

QUESTION 1 OF 3
Day-ahead market: the candidate should describe:
 the main characteristics of the Italian market;
 with a simple example the day-ahead unconstrained market clearing (clearing
price&quantity);
 and the relevant optimization problem (the producer surplus, the consumer surplus and the
social welfare).

Page 9
PIACENZA, February 09th 2012

Page 10
PIACENZA, February 09th 2012

QUESTION 2 OF 3
Connection rules for power plants: the candidate should describe:
 shallow costs/deep costs approach;
 the rules for connection to LV and MV networks (time schedule and responsibilities, the
connection charges formula);
 the procedure to request a connection (TSO/DSO/ network users).

Page 11
PIACENZA, February 09th 2012

Page 12
PIACENZA, February 09th 2012

QUESTION 3 OF 3
Hosting capacity approach: the candidate should describe:
 the three nodal operating limits;
 the reverse power flow issue;
 the Interface Protection Relay issues (both local and system) and the possible solution.

Page 13
PIACENZA, February 09th 2012

Page 14

Potrebbero piacerti anche