Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
SPECIFICATION
FOR
Prepared P.J
Checked R.P
Approved M.N
CLIENT: CONSULTANT:
TABLE OF CONTENTS
Page
1.0 INTRODUCTION
Arvandan Oil and Gas company intends to construct an 8" N.B. buried flowline
from Sohrab WH1 to South Azadegan North Cluster.
Sohrab Field is located at North of Azadegan Field, and 115 Km North West of
Ahwaz right along the international border with Iraq.
1.2 SCOPE
This specification covers the minimum requirements for the supply of the cathodic
protection equipment to be used for the protection system.
These equipment include:
- Transformer/rectifier(s)
- Anodes
- Earthing cells
- AC and DC cables
- Test/bond boxes
- Thermit-welds
- Joint equipment
- Control box
- Cable accessories
- Isolating joint and accessories (coupling)
- Spark gaps
- Miscellaneous equipment
1.2.1 Engineering
1.3 Equipment
All necessary cathodic protection equipment and material specified according to this
and attached documents shall be in VENDOR’s scope of supply.
AC Alternating Current
DC Direct Current
LV Low Voltage (below 1000 V)
CLIENT: CONSULTANT:
In any case the vendor shall inform purchaser and obtain clarification before
proceeding with any work.
The following codes, standards and regulations form a part of this specification.
The design of electrical power system and equipment shall be in accordance with all
applicable sections of the latest edition and their current amendments:
NFPA-70
Deviation from this specification are only acceptable where the VENDOR has listed
in his quotation the requirements he cannot, or does not wish to comply with, and
the PURCHASER has accepted in writing the deviations before the order is placed.
In the absence of a list of deviations, it will be assumed that the VENDOR complies
fully with this specification.
Sohrab Field is located at North of Azadegan Field, and 115 Km North West of
Ahwaz right along the international border with Iraq.
The equipment and all its components should be entirely suitable for service
under the conditions specified in Process design basis No AOGC-036-PR-ESS-001.
NOTES :
(1) The maximum temperature given are for calculating the maximum temperature
rise of the equipment.
(2) Repertoire black body surface temperature under direct sun radiation, without
forced cooling.
CLIENT: CONSULTANT:
4.0 DESIGN
A cathodic protection system shall be installed for all buried or submerged facilities
to mitigate corrosion that might result in structural failure. A test procedure shall be
developed to determine if adequate cathodic protection has been achieved.
Temporary cathodic protection to be used if main CP system is predicted to be
energized later than 2 months after complete burial.
Design and selection of the cathodic protection system to be utilized shall be based
upon this specification and sound engineering judgement, substantiated by:
The resultant cathodic protection system shall be designed to eliminate any adverse
corrosive effect upon nearby structures, equipment, pipe, cables, etc. owned by
others or by the government. In addition, design drawings shall clearly define the
location of all cathodic equipment incorporated on the pipeline, the system and all
other facilities, whether above or below ground, that could affect or be affected by
the cathodic protection system. The system design life is 20 years.
4.2 Surveys
The survey method to be used for this project shall consist of rapid or spot testing of
soil resistivities as typical points along the structure. The environmental conditions,
size, physical layout, economics and need for design information will determine
which variables require field measurements.
CLIENT: CONSULTANT:
Survey data shall also indicate the location of all buried structures on and adjacent
to the job site, the condition of exposed metal surfaces and the insulating qualities of
any coatings and structures.
- be based on a continuous operation of the system for the specified design life
of the structure or equipment to be protected.
- include details for system commissioning, the design and location of insulating
joints and monitoring points.
The cathodic protection system shall be designed so that the potential at any point
of the protected pipeline shall be minimum -0.85V.
The potentials are measured in the "Instantaneous off" condition when the power
supply from the rectifier is disconnected.
In case of sulphate reducing bacterial (SRB) existence the min. negative potential
shall be considered as -0.95 V.
CLIENT: CONSULTANT:
OFF POTENTIALS,
COATING SYSTEM
VOLT (Ref. Cu/CuSo4)
Epoxy powder fusion-bonded - 1.1
Asphalt and coal tar enamel - 2.0
Tape wrap (laminated tape system) - 1.1
Epoxy coal tar - 1.5
Polyethylene (2 layers) - 1.0
Polyethylene (3 layers) - 1.1
Polyurethane pu -1.1
Cold applied petrolatum and - 1.1
petroleum wax tape
3 ply cold applied plastic tape -1.1
The Contractor shall carry out pipeline attenuation calculations to determine the
pipeline current demand and spacing between cathodic protection stations as
required during the pipeline design life.
MAXIMUM
MAXIMUM PROBABLE
OPERATING CONSUMPTION
MATERIAL DENSITY OPERATING UTILIZATION REMARKS
CURRENT RATE
VOLTAGE FACTOR
DENSITY
g/cm3 A/m2 Mass/A year V %
Steel 7.85 5 9 kg 50 30 to 50 Used with carbonaceous
Impregnated back fill
1.1 10 0.5 kg 50 50
graphite
Higher consumption
occurs in chloride
containing environment
High silicon iron 7.0 50 02 ~ 1.0 kg 50 50 to 90 unless chromium or
molybdenum is add4ed.
MMO Anodes:
The mixed metal oxide coating is a crystaling electrically conductive coating that
activates and enables a titanium/Platinum substrate to function as an anode.
MMO anode shall be Rod type according to top schedule specification.
4.7.1 Location
The temporary ground bed shall be located at the site selected for the proposed
permanent facility.
Temporary electrical test power may consist of engine driven generators, storage
batteries, existing cathodic protection units, portable rectifiers combined with
available commercial power, etc. This equipment shall be capable of providing well-
regulated constant direct current voltage and amperage or required magnitudes for
the particular test duration.
Temporary ground beds may consist of buried junk pipe, abandoned buried metallic
structures, aluminium foil in burrow ditch water, etc, which may be utilised to provide
sufficient electrical ground contact to allow stimulation of the proposed ground beds.
Temporary wiring used for connecting the ground beds shall have sufficient
insulation to prevent uncontrolled circuits and to provide personnel safety.
After the system has stabilised at the required protective levels, measurements shall
be made of current drainage at all current sources including control bands.
Soil to pipeline potentials shall be obtained at all test leads, both sides of insulation
joints or unions, foreign pipeline or other buried metallic structure crossings, or like a
structure in a close proximity to the structure being protected (where such readings
are practical and obtainable), and elsewhere, as deemed necessary, to establish the
effectiveness of the proposed cathodic protection and to assure against induced
parasitic current corrosion on structures not to be included into the cathodic
protection system.
All voltage levels shall be recorded to the nearest suitable precision mili volt-meter
using instruments and standard copper/copper-sulphate half-cell reference
electrodes or silver/silver-clorure (Ag/AgCl) half-cell reference electrodes.
CLIENT: CONSULTANT:
The electrode position, with respect to the buried structure, shall be recorded for
each potential measurement.
No applied current:
This is the so-called ‘normal’ or native electrical condition of the buried structure.
These conditions are to be ‘shifted’ by applied cathodic protection to an electrical
state meeting one or more of the applicable protective criteria. Choice of criteria
shall be governed by economics, coating conditions, environment and type of buried
structure to be protected.
After the minimum protective current requirements have been determined, the
current output of the temporary simulated cathodic protection system shall be
increased until the upper limits of the acceptable protective levels have been
reached. Protective attenuation across the entire structure shall then be measured.
Resistivity measurements at proposed galvanic anode sites shall be taken along the
pipe at suitable intervals using potential electrode spacing as required. Resistivity
measurements shall be corrected to consider the worst resistivity condition, that is
summer conditions.
5.1 General
These facilities include such as rectifiers, ground beds and galvanic anodes that
supply protective current through a cable connection to the buried metallic structure.
Anticipated changes in soil characteristics and in coating efficiency shall be
considered in case of choosing and sizing cathodic protection equipment.
Rectifiers will usually provide the most economic power supply where AC power is
available and where the current demand will exceed that economically obtained from
galvanic anodes.
Galvanic anodes are the most economic cathodic protection for short pipeline
systems.
Rectifier units shall be located in the nearest position to the under ground pipe lines
distribution center.
Oil cooled transformer rectifier shall be supplied with the first complete of oil
which shall comply with the requirements of IPS-M-EL-155(1) "Material and
Equipment Standard for Transformer Rectifiers for Cathodic Protection"
Generally, 63 steps transformer shall be used.
The rectifier shall be of the silicon or selenium type, connected for full wave
rectification in accordance with the requirements of IPS-M-EL-155(1) "Material and
Equipment Standard for Transformer Rectifiers for Cathodic Protection".
6.1 Location
The location selection of ground bed sites shall be based on:
6.1.2 Accessibility
The design should strive to minimise right-of-way procurement problems while
providing maximum accessibility for installation, inspection and maintenance.
OFF POTENTIALS,
COATING SYSTEM
VOLT (Ref. Cu/CuSo4)
Epoxy powder fusion-bonded - 1.1
Asphalt and coal tar enamel - 2.0
Tape wrap (laminated tape system) - 1.1
Epoxy coal tar - 1.5
Polyethylene (2 layers) - 1.0
Polyethylene (3 layers) - 1.1
Polyurethane pu -1.1
Cold applied petrolatum and - 1.1
petroleum wax tape
3 ply cold applied plastic tape -1.1
All measured protection potentials shall be "instant-off". Cathodic protection
system shall be equipped with synchronized interrupters for this purpose.
CLIENT: CONSULTANT:
6.2 Type
The choice of surface versus deep-well ground beds shall be governed by such
variables as annual rainfall, soil conditions, interference problems and right-of-way
acquisition costs.
Generally, passive (graphite, cast iron, lead silver or MMO) rather than sacrificial
type anodes shall be used. Such anodes shall be surrounded with tamped soft coal
or calcined petroleum coke breeze, if practical, in order to increase effective anode
size.
Ferro-silicon anodes shall be used for deep-well beds and are preferred for surface
beds.
- Low current drain (3-4 amps per anode) to minimise gassing and promote
longevity.
- Anode centralizers
Maximum design current for graphite anodes shall be 3 amperes for 75 mm x 1500
mm anodes and 4 amperes for 100 mm x 2000 mm anodes. For other anode types it
depends on current density (mA/cm3) which could be supported by anode material.
Continuous ground bed output may be assured by providing for future water
replenishment.
Gas elimination devices such as vent pipes and drain tiles must be used to assure
continuous full current output. Vent pipes installed in deep-well ground beds shall be
drilled with adequately spaced and properly sized holes to insure against plugging
and to provide adequate gas venting.
7.1 Application
For rectifier control and continuous measurement of potential, each rectifier is fitted
with two reference electrodes.
7.2 Location
7.3 Type
The reference electrodes shall be one Cu/CuSo4 electrode and one Zn electrode.
CLIENT: CONSULTANT:
Electrode size, shape, weight, purity and backfill shall be governed by the
requirements of the particular installation in accordance with materials specified
herein.
8.1 Application
They may serve for installations remote from electric power or for protection of small
insulated sections in a large unprotected system.
Magnesium anodes are frequently the most economic cathodic protection choice for
long or complex piping systems coated with long-life, high dielectric.
8.2 Location
Galvanic anodes shall be installed in battery groups at distributed locations along the
system to provide complete protection and to allow for future inspection and
maintenance.
Soils having the best combination of low electrical resistivity, high chemical
concentration and maximum moisture content shall be selected for the galvanic
anode site. Distance for buried structure should not exceed 3000 mm.
8.3 Type
Zinc anodes shall be used only in low-resistance soils say up to 500 ohm.cm and
where low current outputs and resultant low solution potentials are tolerable.
Anode size, shape, weight, purity and backfill shall be governed by the requirements
of the particular installation in accordance with materials specified herein.
Anodes shall be of magnesium type high potential alloys assembled with lead wires
in accordance with the following compositions: (IPS-M-TP-750)
9.1 General
Test points are defined as those points or locations along the protected buried
metallic system at which electrical-current or potential measurements are made to
evaluate the level or status of cathodic protection.
These points shall be provided within the limits of economical and logical feasibility,
in sufficient quantities and at appropriate intervals to minimise the possibility of
overcooking a non-protected corroding portion of the buried metallic structure.
Test points for potential measurements shall consist of welded, metallic contacts to
the buried structure which provide for efficient clip-on measurements and reliable
repetitive readings. Use of such points shall provide for minimum damage to
CLIENT: CONSULTANT:
decorative coatings and eliminate notch penetrations into the metallic structure by
repeated base metal contacts.
In most instances, properly sized and insulated stranded copper wire shall be used
to transfer metallic contact from buried structures to conveniently located above-
ground test terminals.
Protruding bolt threads (softer than steel test clips) shall provide the testing
connections at the wire terminal. Suitable rigid conduit connections, risers and boxes
are used to protect the test points.
Casing vent pipes, pipeline risers, valves, etc., may provide the metallic transfer path
from buried structure to above-ground. In such instances, short lengths of solid or
tubular copper shall be welded or soldered to the structure to provide a test point.
Refer to table 2 (in appendix) for location of electrical test points for current
measurement.
Test points for measurements of electrical current shall generally consist of shunt-
type measuring facilities which allow measurements of current without breaking the
cathodic protection circuit.
Standard one mili-volt per one ampere (0.001 ohm) suitable capacity shunts shall be
used, if possible. For galvanic anode installations and low current rectifiers, the ten
mili-volt per one ampere (0.01 ohm) shunt may be used. The shunts shall be
contained in proper housings.
Where sacrificial anode systems are used, potentials measurements shall be made
faraway from the anodes.
Insulating fittings shall be designed for above-ground installations to control the flow
of electrical currents. Where fittings are buried, properly sized leads on both side of
the insulation shall be brought above ground for current measurements and control.
Insulation fittings shall be provided at sufficient intervals along the metallic cathodic
protection circuit to result in adequate circuit control.
CLIENT: CONSULTANT:
Selection and design of the insulation fitting to be used shall be governed by the
requirements of the particular application. Material shall be selected from standard
VENDOR items.
Storage tanks shall be insulated from connected buried metallic structure and
production tanks shall be insulated from OSBL system.
Buried flanges and above-ground flanges shall be provided with sufficient insulation
to insulate fully each bolt from both flanges.
Valves in valve box shall be insulated at the support point by two sheets of metal
separated by a sheet of insulating material. This insulator combination shall be
completely coated.
Pier supports shall be isolated from pipelines by multiple layers of glass wrapper
saturated with coating material of sheet-insulating material.
A minimum space of 300 mm shall be provided between cross lines for insulation
purposes. If this spacing cannot be obtained, insulation insurance can be obtained
by using sheet insulating material. Thickness of insulating sheet will be governed by
distance between lines, but should not be less than 6.35 mm (1/4 in). If practical, the
space between parallel lines of 6’’ and larger should be a minimum of 2.5 times the
diameter of the largest line.
Electrical ground connections and conduit shall be isolated from coated pipeline
sections. Bare copper ground cables shall be spaced at least 300 mm from other
buried dissimilar metallic structure.
CLIENT: CONSULTANT:
Public sewer, gas and electricity lines shall be insulated from government’s buried
metallic structures.
Buried dissimilar metallic structures shall be insulated from each other.
Corrosion prevention design of all buried metallic structures shall minimise the
probability of parasitic currents flowing between existing and/or proposed facilities.
Adequate coatings and/or insulation shall be provided at anticipated trouble points to
minimise the flow of parasitic currents. Design shall normally incorporate appropriate
bond circuits between buried metallic structures to prevent the corrosive effect of
parasitic currents.
A solid low resistance metallic circuit connecting electrically the offending and
offended structures.
Similar to solid bond with the exception that a resistor is placed in the circuit to
restrict the operating bond current.
CLIENT: CONSULTANT:
Similar to resistance bond with the exception that an electrolyte is used in place of
the resistor. Galvanic anodes may be buried close together or near a buried metallic
structure to utilize the soil as the electrolyte resistance.
Similar to resistance bond with the exception that an air gap resistance is used in
place of the resistor.
A half-wave rectifier that allows current to flow from a buried structure through a
metallic conductor to the offending structure, but blocks current flowing from the
offending structure through the metallic conductor. This type of bond must be
provided with properly designed surge protection for continued performance.
15.1 General
Where contact between dissimilar metals can occur, as with galvanised piping,
copper ground wires, zinc grounds, steel pipe, cast iron structure, etc., protection
shall be provided with sufficient coating to exclude moisture, electrical insulation or
cathodic protection to prevent corrosion damage.
16.1 General
This section will provide the basic criteria, including quality control and acceptance,
for material and equipment required for cathodic protection facilities associated with
the handling of crude oil transported by flow line or associated facilities.
The transformer rectifier units shall comprise a main transformer and a rectifier with
manual output regulation equipment. They shall all be installed either:
In a welded weatherproof steel tank for oil filled type; (with transformer, rectifier
and regulating equipment all below oil level) or:
In a standard cast iron pillar / weather proof steel cabinet, in case of dry type
transformers.
The main transformer shall be a double wound type in accordance with IEC
publication No. 76, suitable for connection to a supply system rated at voltage and
current given in data sheet and for environmental conditions.
All coils for transformer, chokes, wire wound resistors etc., shall be fully
impregnated with suitable oil resistant insulating varnish, either by vacuum
application or by preheating to a minimum 100°C, fully immersing the coil in
varnish while still hot, allowing the coil to cool in the varnish and then over drying
all in accordance with the varnish manufacturer's instructions.
All assembled electrical components which are not oil immersed shall be protected
with fungicide materials when required.
The transformer shall be equipped with rotary selector switches for adjusting the
output in 63 steps unless otherwise specified.
16.3 Rectifiers
The rectifier shall be of the silicon or selenium type, connected for full wave
rectification in accordance with the requirements of IEC 146.
- Input to transformer
- Input to rectifier and,
- Rectifier output
16.3.1 Enclosure
16.3.3 Transformers
There shall be a separate transformer for each electrical phase used in the rectifier.
Bolt connections shall have double nuts with cable connections soldered to the first
nut. All cable terminals shall be crimped and soldered to the cable.
16.3.6 Instruments
Rectifier shall have readily accessible direct-current voltmeters and external shunt-
type ammeters.
16.4.1 When required a single phase adjustable time switch complete with suitable
contactor to IEC 158 capable of switching the unit at full output on a "3" minute on
"2" minute off cycle shall be fitted.
16.4.2 A double pole selector switch shall be provided to enable a selection to be made
for either continuous operation or time switch controlled operation of the unit.
16.5.1 A control box shall be installed on the outside of the tank and shall be provided with
a hinged lockable door, suitably stiffened to prevent distortion and provided with a
reinforced glass for viewing the meters.
- The manual control of the regulation device, and the time/ continuous supply
control switch, where applicable.
- There shall be a schematic circuit diagram on the inside of control box door of
the transformer rectifier.
anode shall be encased with well-compacted soft coal or calcined petroleum coke
breeze screened to proper particle size requirements.
Cable from the rectifier unit to ground-bed shunt junctions and to the protected
structure shall be sized to carry the system’s total current without undue voltage
drop.
On all anodes, special care shall be taken with anode-to-cable junction. This flexure
area is subject to damage and is a known cause of many past ground bed failures.
Rigid inspection enforcement is mandatory for this sensitive anode region.
Each anode and all protective current connecting cables require current
measurement methods. Generally, calibrated shunts are the simplest method for
such measurements. These voltage-drop shunts shall be housed in adequately
sized surface cabinets, if possible. Where below-ground shunt installations are
required, they shall be fully insulated to the soil.
Pressure-sleeve connectors
CLIENT: CONSULTANT:
16.6.5 Insulation
Buried negative cable splices shall be insulated with one of the following materials:
Hot-applied asphalt or coal-tar pipeline enamel poured into a properly formed and
sized container over primed surface.
Canvas-based phenolic insulating board material shall be used for special insulating
problems, such as positioning bolted connection in above-ground junction boxes.
16.6.6 Casing
In low resistance soils (less than 1.500 ohm/cm), zinc or high potential magnesium
anodes shall be used in series with a suitable resistor.
All galvanic anodes used for soil applications require proper low resistance drilling
mud type back-fill material with moisture retention characteristics to insure
dependable anode output.
Anode weight, size and shape shall be chosen from standard economically available
materials according to individual installation requirements.
16.7.4 Shunts
16.8.1 General
Electrical test points are required to evaluate cathodic protection effectiveness. Both
voltage (soil to pipe potential) and current drainage measurements are required.
These test leads shall be constructed of properly sized, stranded copper cable with
polyethylene insulation suitable for soil burial. Above ground, where repeated
readings are required, stub-type materials made of copper or aluminium (in sulphur-
contaminated atmospheres) provide the most effective, long lasting contact
mechanism.
Test leads shall be brought into adequately sized above ground galvanised terminal
boxes via standard-weight rigid galvanised conduit. In severe atmospheric corrosion
areas, plastic conduits and junction boxes shall be used.
The test lead may be connected to the metallic structure where it is to serve by
either arc welding, thermit welding, brazing, soldering or bolting. Thermit weld
connections shall not use powder charges larger than Caldwell’s n°15 cartridge or
equivalent.
16.9.1 General
The metallic parts of the insulating joint shall be of forged steel conforming to the
requirements of MSS-SP-44.
Insulating materials shall be made of age resisting laminated epoxy resin
reinforced with glass fiber conforming to ASTM specification D 709 Type IV Group
G 10/G 11 or equivalent standard.
The primary and secondary sealing gaskets shall be made of fluorinated
elastomers like PTFE and/or Butadieneacrylonitrile copolymers like Nitrile rubber
according to ASTM specification D 2000, or equivalent standard.
Filling materials shall be of adhesive sealant elastomer having a compressive
strength greater than 1500 kg/cm².
Insulating pipeline unions can be used, if they meet pipeline hydraulic requirement.
In areas subject to high lightning strike (high resistance soil regions, etc), arrestors
shall be installed across the union.
16.10.1 General
Depending upon individual project conditions, insulating of the pipeline from casings
at highway and railroad crossings shall use one of the following techniques and
materials:
Coated pipelines can be insulated from their casing sections with built-up abrasion
and support pads fabricated in the field with coating materials used on the line.
16.10.3 Mechanical
Plastic or neoprene insulating devices shall be used for insulating pipelines from
carrier casings. The following material requirements apply in their selection:
Skid-type insulating devices are required to support weights involved with the large
pipelines. Insulators shall be steel-banded with inside and edges insulated and with
skids made of either glass-reinforced epoxy, polyester or phenolic based material.
Minimum width of insulator shall be 8 inch with the more durable 12 inch insulator
being specified for larger-diameter pipe as governed by weights involved. Paper-
based phenolic, non-reinforced plastics, or plastics other than above are not
acceptable because of ‘cold flow’ or moisture absorption tendencies.
Like casing insulators, casing seals may either be fabricated in the field using the
pipeline’s coating materials or by installing purchased mechanical seals. Purchased
seals shall be neoprene. Either the pull-on or the wrap-around seal will serve,
depending upon characteristics of the pipeline system involved.
Sensitive parts shall be packed separately thus to avoid damage during shipment.
Each item is to be securely labelled with indestructible tags with the following
markings:
a) Destination
b) Purchase order number
c) PURCHASER's equipment number
CLIENT: CONSULTANT:
Boxes containing loose parts are to be clearly identified by description, the major
equipment with which they are associated, the purchase order number and the
equipment number.
The VENDOR shall provide the PURCHASER with drawings and documentation for
the purpose of design explanation, actual design and instruction for installation,
service and maintenance as indicated below:
The VENDOR shall specify in his proposal the recommended spare parts for the
commissioning period a two year operation period, type and number specified in
PURCHASER’s data sheets with individual prices for each item.
21.1 The manufacturer shall be responsible for the conformity to all codes, standards and
recommendations referred in this specification. Any special certification
requirements or inspections by other authorities shall be arranged by the contractor.
21.2 If any mal-performance or defects occur during the guarantee period, VENDOR shall
make available repaired, altered or replacement parts free of any charges whatever
direct on the PURCHASER's job site. VENDOR shall make available free of charge
to the PURCHASER qualified representatives as he deems necessary to supervise
the removal, repair and replacement of the defective parts in such manner that the
guarantee be maintained.
CLIENT: CONSULTANT:
21.3 The guarantee period for repaired or replaced parts shall be 12 months after start up
of repaired equipment but not more than 18 months after the repaired parts and/or
equipment are shipped. The guarantee period for the remaining equipment its
operation is dependent upon the proper performance of the repaired part shall be
extended by the number of days of fraction thereof that the equipment had been
inoperative because of defects. Field labor charges for works during the guarantee
period shall be subject to negotiation between the PURCHASER and VENDOR.
NOTE: For cathodic protection, contractor shall purchase required equipment
from approved vendors by A.O.G.C and all cathodic protection equipment and
facilities shall be meet requirement of IPS-M-TP-750 "Material and Equipment
Standard for Cathodic Protection".
After cathodic protection removable links inside the accessible equipment shall be
left opened and no impressed current stations shall be energized without Company’s
approval.
22.2 Start-up
Upon completion of the whole cathodic protection works, it shall be proceeded to:
22.3 Commissioning
The commissioning shall be carried out under the supervision of a qualified Cathodic
Protection engineer.
Upon completion of all works on the plant which may affect the cathodic protection
system operation, its commissioning shall include :
The bonding of all negative and positive circuits, resistors being set back to
zero, potential survey on the whole structures including the foreign ones which
are connected in the test boxes, impressed current stations being maintained
off.
A first adjustment of the impressed current stations, according to the design
parameters and a preliminary checking of potential levels.
CLIENT: CONSULTANT:
The above information, when available shall be incorporated in the plant data
book.
The design documents shall be submitted to the company for approval, covering the
following requirements :
a) Results of any site surveys and soil investigations that have been carried out.
b) Justification of the selected cathodic protection system and made materials.
c) Calculations of current requirements, pipeline attenuation, resistance and
current output of ground beds.
d) A summary of the used formulate and standards.
e) A schematic diagram of the proposed cathodic protection system.
f) A list of the estimated number and types of cathodic protection system.
g) Any sensitivities in the proposed cathodic protection system that requires
special attention.
h) Any other information that is regarded by the contractor as essential for this
stage of the cathodic protection design.
APPENDIX
TESTS
LOCATION REMARKS
POINTS
Coated pipeline, cased at roads, Measurements of pipe-to-soil and casing-to-
railways, canals soil potentials
1
casings less than 30 m in length 1 Measurements of pipe-to-soil and casing-to-
casings 30 m and greater in length 2 soil potentials at each end of casing
Coated pipeline greater than 750 m Measurements of pipe-to-soil potential near
2 1
between casings center
3 Long coated pipeline sections 0.5 km intervals Measurements of pipe-to-soil potential
Long bare pipeline section being
4 0,5 km intervals Measurements of pipe-to-soil potential
cathodically protected
Pipeline near foreign-owned rectifier Measurements of pipe-to-soil potential where
5 2
ground bed pipe enters and leaves anodic field
Pipeline opposite government-owned
6 rectifier ground bed within 300 m of 1 Measurements of pipe-to-soil potential
line
Joint interference at crossing of foreign Requires prior approval of regulatory agency
7 1
line and foreign company
8 Insulated joints or couplings 2 One on each side
9 Main line riser 1 Adjacent ground junction with riser
Buried structure opposite galvanic
10 1 Measurements of pipe-to-soil potential
anode battery
Measurements of buried structure-to-soil
Dissimilar metal systems near ground potential on affected metal as galvanized as
11 1
bed conduit, iron sewer line, copper ground cables,
steel anchors etc.
CLIENT: CONSULTANT:
TESTS
LOCATION REMARKS
POINTS
1 Rectifiers and galvanic anode batteries 1 Measurements of total current output
2 Ground bed connected to rectifier 1 Measurements of individual ground bed
3 Power anode 1 Measurements of anode output
Measurements of return current from each
4 Buried metallic structure 1 structure connected to negative side of
cathodic output
Negative rectifier lead connected to Measurement of current magnitude and
5 1
buried structure direction flowing in the structure
Maximum 10 km Measurement of cathodic protection current
6 Long coated pipeline sections
intervals flow
7 Insulated joints 1 Measurement of possible current flow
Measurement of current magnitude and
At practical
8 Pipelines operated by others direction where ownership or operation
points
jurisdiction changes
Measurements of currents entering and
9 Long inaccessible pipeline sections 2 leaving sections such as major water crossings
and congested areas
Measurements of current as required for
10 Interfering and/or straying currents As required
specific instance