TNB EXTERNAL INFRASTRUCTURE WORK SCHEDULE

APPLICATION OF ACCESS ROAD CLOSURE ON 22th & 24th


SEPTEMBER FOR UNLOADING OF TNB MANHOLE
Time Description
Friday, 22th September 2017
Setting up of road barrier and signage to temporary close the entrance of access
8:00pm to 8:30pm
road to RTM truck parking area.
8:30pm to 11:00pmRoad Cutting works. To cut 2 groove line on road surface.
11pm to 11:30pm Remove road barrier, access road open for traffic.

Saturday, 23th September 2017


Set up barrier & flagman to block traffic flow to prevent cars moving towards RTM
8:00am to 9:00am
truck parking area.
Excavate a 3 meter deep x 2.5 meter width trench from existing TNB manhole
9:00am to 5:00pm (outside site office gate) to hoarded new construction area, lay 24 way HDPE pipe,
secure the pipes arrangement.
5:00pm to 6:00pm Pour concrete to encase the pipe route
7:00pm to 9:00pm backfill with soil to level with existing road

Sunday, 24th September 2017


excavate to trim down soil level, lay crusher run, compact and reinstate of tarmac
9:00am to 5:00pm
road / pour concrete.
5:00pm to 6:00pm Remove road barrier, access road open for traffic.