SEPTEMBER FOR UNLOADING OF TNB MANHOLE Time Description Friday, 22th September 2017 Setting up of road barrier and signage to temporary close the entrance of access 8:00pm to 8:30pm road to RTM truck parking area. 8:30pm to 11:00pmRoad Cutting works. To cut 2 groove line on road surface. 11pm to 11:30pm Remove road barrier, access road open for traffic.
Saturday, 23th September 2017
Set up barrier & flagman to block traffic flow to prevent cars moving towards RTM 8:00am to 9:00am truck parking area. Excavate a 3 meter deep x 2.5 meter width trench from existing TNB manhole 9:00am to 5:00pm (outside site office gate) to hoarded new construction area, lay 24 way HDPE pipe, secure the pipes arrangement. 5:00pm to 6:00pm Pour concrete to encase the pipe route 7:00pm to 9:00pm backfill with soil to level with existing road
Sunday, 24th September 2017
excavate to trim down soil level, lay crusher run, compact and reinstate of tarmac 9:00am to 5:00pm road / pour concrete. 5:00pm to 6:00pm Remove road barrier, access road open for traffic.