Sei sulla pagina 1di 81

THIRD DIVISION action of certiorari, theCourt will not engage in a 7.

urt will not engage in a 7. ADMINISTRATIVE LAW; ADMINISTRATIVE AGENCIES; Claiming an unsatisfied account of P10,500,000.00 and
[G.R. No. 96283. February 25, 1992.] review of the facts found nor even of the law as interpreted DECISIONS WHICH ARE DECLARED FINAL BY LAW, NOT unpaid progress billings of P2,370,179.23, Roblecor on May
CHUNG FU INDUSTRIES (PHILIPP or applied by the arbitrator unless the supposed EXEMPT FROM JUDICIAL REVIEW. — Even 18, 1990, filed a petition for Compulsory Arbitration with
INES) INC., its Directors and errors of fact or of law are so patent and gross and decisions of administrative agencies which are declared prayer for Temporary Restraining Order before respondent
Officers namely: HUANG KUO- prejudicial as to amount to a grave abuse of discretion or "final" by law are not exempt from judicial review when so Regional Trial Court, pursuant to the arbitration clause in
CHANG, HUANG AN-CHUNG, an excess de pouvoir on the part of the arbitrator." warranted. Thus, in the case of Oceanic Bic Division the construction agreement.Chung Fu moved to dismiss the
JAMES J.R. CHEN, TRISTAN A. 3. ID.; ID.; ID.; ID.; APPLICABLE IN CASE AT BAR. — We find (FFW), et al. v. Flerida Ruth P. Romero, et al., this Court had petition and further prayed for the quashing of the
CATINDIG, VICENTE B. AMADOR, that petitioners have amply made out a case where the occasion to rule that: ". . . Inspite of statutory provisions restraining order.
ROCK A.C. HUANG, JEM S.C. voluntary arbitrator failed to apply the terms and making 'final' the decisions of certain administrative Subsequent negotiations between the parties eventually
HUANG, MARIA TERESA SOLIVEN provisions of the Construction Agreement which forms agencies, we have taken cognizance ofpetitions questioning led to the formulation of an arbitration agreement which,
and VIRGILIO M. DEL part of the law applicable as between the parties, thus these decisions where want of jurisdiction, grave among others, provides:
ROSARIO, petitioners, vs. COURT O committing a grave abuse of discretion. Furthermore, in abuse of discretion, violation of due process, "2. The parties mutually agree that
F APPEALS, HON. FRANCISCO X. granting unjustified extra compensation to respondent for denial of substantial justice or erroneous the arbitration shall proceed in
VELEZ (Presiding Judge, Regional several items, he exceeded his powers — all of which interpretation of the law were brought to our attention. x x " accordance with the following
Trial Court of Makati [Branch would have constituted ground for vacating the award It should be stressed too, that voluntary arbitrators, by the terms and conditions: —
57]) and ROBLECOR under Section 24 (d) of the Arbitration Law. But the nature of their functions, act in a quasi-judicial capacity. It xxx xxx xxx
PHILIPPINES INC.,respondents. respondent trial court's refusal to look into the stands to reason, therefore, that their decisions should not 'd. The parties
SYLLABUS merits of the case, despite prima facie showing of the be beyond the scope of the power ofjudicial mutually agree that they
1. REMEDIAL LAW; REGULAR COURTS; REMAIN THE FORA existence of grounds warranting judicial review, effectively review of this Court. will abide by the
TO RESOLVE THE DISPUTES OF PARTIES IN THE deprived petitioners of their opportunity to prove or DECISION decision of the arbitrator
ABSENCE OF AN AGREEMENT AS TO THE substantiate their allegations. In so doing, the ROMERO, J p: including any amount
MODE OF SETTLEMENT. — Absent an agreement of the trial court itself committed grave abuse of discretion. This is a special civil action for certiorari seeking to annul that may be awarded to
parties to resolve their disputes via a particular mode, it is 4. CIVIL LAW; CONTRACTS; ARBITRATION; STIPULATION the Resolutions of the Court of Appeals * dated October 22, either party as
the regular courts that remain the fora to resolve such TO REFER ONGOING OR FUTURE DISPUTES THERETO; 1990 and December 3, 1990 upholding the Orders of July compensation,
matters. However, the parties may opt for recourse to third VALID. — The stipulation to refer all future disputes to an 31, 1990 and August 23, 1990 of the Regional consequential damage
parties, exercising their basic freedom to "establish such arbitrator or to submit an ongoing dispute to one is valid. Trial Court of Makati, Branch 57, in Civil Case No. 90-1335. and/or interest thereon;
stipulations, clauses, terms and conditions as they may Being part of a contract between the parties, it is binding Respondent Court of Appeals affirmed the ruling of the 'e. The parties
deem convenient, provided they are not contrary to law, and enforceable in court in case one of them neglects, fails trial court that herein petitioners, after submitting mutually agree that the
morals, good customs, public order or public policy." In or refuses to arbitrate. Going a step further, in the event themselves for arbitration and agreeing to the terms and decision of the arbitrator
such a case, resort to the arbitration process may be that they declare their intention to refer their differences to conditions thereof, providing that the arbitration award shall be final and
spelled out by them in a contract in anticipation of disputes arbitration first before taking court action, this constitutes shall be final and unappealable, are precluded from seeking unappealable. Therefore,
that may arise between them. Or this may be stipulated in a a condition precedent, such that where a suit has been judicial review of subject arbitration award. there shall be no further
submission agreement when they are actually confronted instituted prematurely, the court shall suspend the same It appears that on May 17, 1989, judicial recourse if either
by a dispute. Whatever be the case, such recourse to an and the parties shall be directed forthwith to proceed to petitioner Chung Fu Industries (Philippines) (Chung Fu for party disagrees with the
extrajudicial means of settlement is not intended to arbitration. [Bengson v. Chan, No. L-27283, July 29, 1977, 78 brevity) and private respondent Roblecor Philippines, Inc. whole or any part of the
completely deprive the courts of jurisdiction. In fact, the SCRA 113] (Roblecor for short) forged a construction arbitrator's award;
early cases on arbitration carefully spelled out the 5. ID.; ID.; ID.; STIPULATION THAT ARBITRATOR'S AWARD agreement 1 whereby respondent contractor committed to
prevailing doctrine at the time, thus: ". . . a clause in a SHALL BE FINAL AND UNAPPEALABLE; RULE AND construct and finish on December 31, 1989, petitioner 'f. As an
contract providing that all matters in dispute between the EXCEPTION. — Under present law, may the parties who corporation's industrial/factory complex in Tanawan, exception to sub-
parties shall be referred to arbitrators and to them alone is agree to submit their disputes to arbitration further Tanza, Cavite for and in consideration of P42,000,000.00. In paragraph (e), above, the
contrary to public policy and cannot oust the provide that the arbitrators' award shall be final, the eventof disputes arising from the parties mutually agree
courts of jurisdiction. A court action may likewise be unappealable and executory? Article 2044 of theCivil performance of subject contract, it was stipulated therein that either party is
proper where the arbitrator has not been selected by the Code recognizes the validity of such stipulation, thus: "Any that the issue(s) shall be submitted for resolution before a entitled to seek judicial
parties [Umbao v. Yap, 100 Phil. 1008 (1957). stipulation that the arbitrators' award or decision shall be single arbitrator chosen by both parties. assistance for
2. ID.; SPECIAL CIVIL ACTIONS; CERTIORARI; LIES WHERE final is valid, without prejudice to Articles 2038, 2039 and Apart from the aforesaid construction purposes of enforcing
GRAVE ABUSE OF DISCRETION OR AN ACTWITHOUT OR 2040." Similarly, the Construction Industry Arbitration agreement, Chung Fu and Roblecor entered into two (2) the arbitrator's award;
IN EXCESS OF JURISDICTION IS CLEARLY SHOWN. — What Law provides that the arbitral award "shall be final and other ancillary contracts, to wit: one dated June 23, 1989, xxx xxx xxx" 4
if courts refuse or neglect to inquire into the factual inappealable except on questions of law which shall be for the construction of a dormitory and support facilities (Emphasis supplied)
milieu of an arbitrator's award to determine whether it is appealable to the Supreme Court. with a contract price of P3,875,285.00, to be completed on Respondent Regional Trial Court approved the arbitration
in accordance with law or within the scope of his authority? 6. LABOR AND SOCIAL LEGISLATION; VOLUNTARY or before October 31, 1989; 2 and the other dated August agreement thru its Order of May 30, 1990. Thereafter, Engr.
How may the power of judicial review be invoked? This is ARBITRATOR; MANDATED TO RENDER A DECISION 12, 1989, for the installation of electrical, water and Willardo Asuncion was appointed as the sole arbitrator.
where the proper remedy is certiorari under Rule 65 of the WITHIN TWENTY DAYS FROM hydrant systems at the plant site, commanding a On June 30, 1990, Arbitrator Asuncion ordered petitioners
Revised Rules of Court. It is to be borne in mind, however, DATE OF SUBMISSION OF THE DISPUTES. — Under price of P12.1 million and requiring completion thereof one to immediately pay respondent contractor, the
that this action will lie only where a grave the Labor Code, the voluntary arbitrator is now mandated month after civil works have been finished. 3 sum of P16,108,801.00. He further declared the award as
abuse of discretion or an act without or in to render an award or decision within twenty (20) calendar However, respondent Roblecor failed to complete the work final and unappealable, pursuant to the Arbitration
excess of jurisdiction on the partof the voluntary arbitrator days from the date of submission of the dispute and such despite the extension of time allowed it byChung Fu. Agreement precluding judicial review of the award.
is clearly shown. For "the writ of certiorari is an extra- decision shall be final and executory after ten (10) calendar Subsequently, the latter had to take over the construction Consequently, Roblecor moved for the confirmation of said
ordinary remedy and that certiorari jurisdiction is not to be days from receipt of the copy of the award or decision by when it had become evident that Roblecor was not in a award. On the other hand, Chung Fu moved to remand the
equated with appellate jurisdiction. In a special civil the parties. position to fulfill its obligation. LLjur case for further hearing and asked for a
reconsideration of the judgment award claiming that jurisdiction, as well as Industrial Peace Act which was passed in 1953 as completely deprive the courts of jurisdiction. In fact, the
Arbitrator Asuncion committed twelve (12) denied due process and Republic Act No. 875, favored the policy of free collective early cases on arbitration carefully spelled out the
instances of grave error by disregarding the substantial justice to bargaining, in general, and resort to grievance procedure, prevailing doctrine at the time, thus: ". . . a clause in a
provisions of the parties' contract. petitioner, by not vacating in particular, as the preferred mode ofsettling disputes in contract providing that all matters in dispute between the
Respondent lower court denied Chung Fu's Motion to and annulling the award industry. It was accepted and enunciated more explicitly in parties shall be referred to arbitrators and to them alone is
Remand thus compelling it to seek reconsideration dated 30 June 1990 of the the Labor Code, which was passed on November 1, 1974 contrary to public policy and cannot oust the
therefrom but to no avail. The trial court granted Arbitrator, on the ground as Presidential Decree No. 442, with the amendments later courts of jurisdiction." 13
Roblecor's Motion for Confirmation of Award and that the Arbitrator grossly introduced by Republic Act No. 6715 (1989). But certainly, the stipulation to refer all future disputes to
accordingly, entered judgment in conformity therewith. departed from the Whether utilized in business transactions or in employer- an arbitrator or to submit an ongoing dispute to one is
Moreover, it granted the motion for the issuance of a terms of the parties' employee relations, arbitration was gaining wide valid. Being part of a contract between the parties, it is
writ of execution filed by respondent. contracts and misapplied acceptance. A consensual process, it was preferred to binding and enforceable in court in case one ofthem
Chung Fu elevated the case via a petition for certiorari to the law, and thereby orders imposed by government upon the disputants. neglects, fails or refuses to arbitrate. Going a step further,
respondent Court of Appeals. On October 22, 1990 the exceeded the authority and Moreover, court litigations tended to be time-consuming, in the event that they declare their intention to refer their
assailed resolution was issued. The respondent power delegated to him. costly, and inflexible due to their scrupulous differences to arbitration first before taking court action,
appellate court concurred with the findings and (Rollo, p. 17). observance of the due process of law doctrine and their this constitutes a condition precedent, such that where a
conclusions of respondent trial court resolving Allow us to take a leaf from history and briefly trace the strict adherence to rules of evidence. suit has been instituted prematurely, the court shall
that Chung Fu and its officers, as signatories to the evolution of arbitration as a mode of dispute settlement. As early as the 1920's, this Court declared: suspend the same and the parties shall be directed
Arbitration Agreement are bound to observe the Because conflict is inherent in human society, much effort "In the Philippines fortunately, the forthwith to proceed to arbitration. 14
stipulations thereof providing for the finality of the award has been expended by men and institutions in devising attitude of the courts toward A court action may likewise be proper where the arbitrator
and precluding any appeal therefrom. ways of resolving the same. With the arbitration agreements is slowly has not been selected by the parties. 15
A motion for reconsideration of said resolution was filed by progress of civilization, physical combat has been ruled out crystallizing into definite and Under present law, may the parties who agree to submit
petitioner, but it was similarly denied by and instead, more pacific means have been evolved, such as workable form.... The rule now is their disputes to arbitration further provide that the
respondent Court of Appeals thru its questioned recourse to the good offices of a disinterested third party, that unless the agreement' is such arbitrators' award shall be final, unappealable and
resolution of December 3, 1990. whether this be a court or a private individual or as absolutely to close the executory?
Hence, the instant petition anchored on the following individuals. doors of the courts against the Article 2044 of the Civil Code recognizes the
grounds: Legal history discloses that "the early judges called upon to parties, which agreement would be validity of such stipulation, thus:.
First solve private conflicts were primarily the arbiters, persons void, the courts will look with favor "Any stipulation that the
Respondents Court of Appe not specially trained but in whose morality, probity and upon such amicable arrangements arbitrators' award or decision shall
als and trial Judge gravely good sense the parties in conflict reposed full trust. Thus, in and will only with great reluctance be final is valid, without prejudice
abused their discretion Republican Rome, arbiter and judge (judex) were interfere to anticipate or nullify the to Articles 2038, 2039 and 2040."
and/or exceeded their synonymous. The magistrate or praetor, after noting down action of the arbitrator." 10
jurisdiction, as well as the conflicting claims of litigants, and clarifying the issues, That there was a growing need for a law regulating Similarly, the Construction Industry Arbitration
denied due process and referred them for decision to a private person designated arbitration in general was acknowledged when Law provides that the arbitral award "shall be final and
substantial justice to by the parties, by common agreement, or selected by them RepublicAct No. 876 (1953), otherwise known as the inappealable except on questions of law which shall be
petitioners, — (a) by from an apposite listing (the album judicium) or else by Arbitration Law, was passed. "Said Act was obviously appealable to the Supreme Court." 16
refusing to exercise their having the arbiter chosen by lot. The judges proper, as adopted to supplement — not to supplant — the New Civil Under the original Labor Code, voluntary arbitration
judicial authority and legal specially trained state officials endowed with own power Code on arbitration. It expressly declares that 'the awards or decisions were final, unappealable and
duty to review the and jurisdiction, and taking cognizance of litigations from provisionsof chapters one and two, Title XIV, Book executory. "However, voluntary arbitration awards or
arbitration award, and (b) beginning to end, only appeared under the Empire, by the IV of the Civil Code shall remain in force.'" 11 decisions on money claims, involving an amount exceeding
by declaring that so-called cognitio extra ordinem." 5 In recognition of the pressing need for an arbitral One Hundred Thousand Pesos (P100,000.00) or forty-
petitioners are estopped Such means of referring a dispute to a third party has also machinery for the early and expeditious percent (40%) of the paid-up capital of the respondent
from questioning the long been an accepted alternative to litigation at common settlement ofdisputes in the construction industry, a employer, whichever is lower, may be appealed to the
arbitration award allegedly law. 6 Construction Industry Arbitration Commission (CIAC) was National Labor Relations Commission on any of the
in view of the stipulations Sparse though the law and jurisprudence may be on the created byExecutive Order No. 1008, enacted on February following grounds: (a) abuse of discretion; and (b) gross
in the parties' arbitration subject of arbitration in the Philippines, it was nonetheless 4, 1985. cdrep incompetence." 17 It is to be noted that the appeal in the
agreement that "the recognized in the Spanish Civil Code; specifically, the In practice nowadays, absent an agreement of the parties to instances cited were to be made to the National Labor
decision of the arbitrator provisions on compromises made applicable to arbitrations resolve their disputes via a particular mode, it is the Relations Commission and not to the courts.
shall be final and under Articles 1820 and 1821. 7 Although said provisions regular courts that remain the fora to resolve such matters. With the subsequent deletion of the above-cited provision
unappealable" and that were repealed by implication with the repeal of the Spanish However, the parties may opt for recourse to third parties, from the Labor Code, the voluntary arbitrator is now
"there shall be no further Law of Civil Procedure, 8 these and additional ones were exercising their basic freedom to "establish such mandated to render an award or decision within twenty
judicial recourse if either reinstated in the present Civil Code. 9 stipulations, clauses, terms and conditions as they may (20) calendar days from the date of submissionof the
party disagrees with the Arbitration found a fertile field in the resolution of labor- deem convenient, provided they are not contrary to law, dispute and such decision shall be final and executory after
whole or any part of the management disputes in the Philippines. Although early morals, good customs, public order or public policy." 12 In ten (10) calendar days from receipt of the copy of the
arbitrator's award." prLL on, Commonwealth Act 103 (1936) provided for such a case, resort to the arbitration process may be award or decision by the parties. 18
Second compulsory arbitration as the state policy to be spelled out by them in a contract in anticipation of disputes Where the parties agree that the decision of the arbitrator
Respondent Court of Appea administered by the Court of Industrial Relations, in time that may arise between them. Or this may be stipulated in a shall be final and unappealable as in the instant case, the
ls and trial Judge gravely such a modality gave way to voluntary arbitration. While submission agreement when they are actually confronted pivotal inquiry is whether subject arbitration award is
abused their discretion not completely supplanting compulsory arbitration which by a dispute. Whatever be the case, such recourse to an indeed beyond the ambit of the court's power of judicial
and/or exceeded their until today is practiced by government officials, the extrajudicial means of settlement is not intended to review.
We rule in the negative. It is stated explicitly under Art. conditions ofthe Construction Remand Case For Further Hearing and Reconsideration and SYNOPSIS
2044 of the Civil Code that the finality of the arbitrators' Agreement, Dormitory Contract Opposition to Motion for Confirmation of Award, we find Petitioner DMC-USA and its Managing Director for Export
award is not absolute and without exceptions. Where the and Electrical Contract, and in that petitioners have amply made out a case where the Sales Paul Derby, Jr. appointed respondent MMI as the sole
conditions described in Articles 2038, 2039 and 2040 using instead the "practices" in the voluntary arbitrator failed to apply the terms and and exclusive distributor of its Del Monte products in the
applicable to both compromises and arbitrations are construction industry; provisions of the Construction Agreement which forms Philippines. The contract provided for arbitration of all
obtaining, the arbitrators' award may be annulled or 2. The Honorable Arbitrator part of the law applicable as between the parties, thus disputes to be held in San Francisco, California under the
rescinded. 19 Additionally, under Sections 24 and 25 of the committed grave error in granting committing a grave abuse of discretion. Furthermore, in Rules of the American Arbitration Association. MMI, thru
Arbitration Law, there are grounds for vacating, modifying extra compensation to Roblecor for granting unjustified extra compensation to respondent for its Managing Director Lily Sy, appointed Sabrosa Foods, Inc.
or rescinding an arbitrator's award. 20 Thus, if and when loss of productivity due to adverse several items, he exceeded his powers - all of which would (SFI) as its marketing arm. Despite the agreement, Del
the factual circumstances referred to in the above-cited weather conditions; have constituted ground for vacating the award under Monte products were brought into the country by parallel
provisions are present, judicial review of the award is 3. The Honorable Arbitrator Section 24 (d) of the Arbitration Law. cdphil importers. Thus, the complaint for damages with prayer for
properly warranted. committed grave error in granting But the respondent trial court's refusal to look into the the issuance of a writ of preliminary attachment for
What if courts refuse or neglect to inquire into the factual extra compensation to Roblecor for merits of the case, despite prima facie showing of the violations of Articles 20, 21 and 23 of the Civil Code filed
milieu of an arbitrator's award to determine whether it is loss due to delayed existence of grounds warranting judicial review, effectively against DMC-USA, its Managing Director Derby, its Regional
in accordance with law or within the scope of his authority? payment of progress billings; deprived petitioners of their opportunity to prove or Director Collins, its Head of credit Services, Hidalgo and
How may the power of judicial review be invoked? 4. The Honorable Arbitrator substantiate their allegations. In so doing, the Dewey, Ltd., owner by assignment of its trademark here.
This is where the proper remedy is certiorari under Rule committed grave error in granting trial court itself committed grave abuse of discretion. Petitioners moved to suspend proceedings invoking the
65 of the Revised Rules of Court. It is to be borne in mind, extra compensation to Roblecor for Likewise, the appellate court, in not giving due course to arbitration clause in their contract. The trial court
however, that this action will lie only where a grave loss of productivity due to the the petition, committed grave abuse of discretion. originally deferred consideration on the motion but later
abuse of discretion or an act without or in cement crisis; Respondent courts should not shirk from exercising their denied the same on the ground that to allow suspension
excessof jurisdiction on the part of the voluntary arbitrator 5. The Honorable Arbitrator power to review, where under the applicable laws and will only delay the determination of the issues and delay
is clearly shown. For "the writ of certiorari is an extra- committed grave error in granting jurisprudence, such power may be rightfully exercised; the parties' rights to seek redress. The Court of Appeals
ordinary remedy and that certiorari jurisdiction is not to be extra compensation to Roblecor for more so where the objections raised against an arbitration affirmed the decision of the trial court. It held that the acts
equated with appellate jurisdiction. In a special civil losses allegedly sustained on award may properly constitute grounds for annulling, complained of required the interpretation of Article 21 of
action of certiorari, the Court will not engage in a account of the failed coup d'etat; vacating or modifying said award under the laws on the Civil Code and that a full blown trial is required in
review of the facts found nor even of the law as interpreted 6. The Honorable Arbitrator arbitration. determining whether the petitioners violated the law.
or applied by the arbitrator unless the supposed committed grave error in granting WHEREFORE, the petition is GRANTED. The Resort to this Court was made when petitioners' motion for
errors of fact or of law are so patent and gross and to Roblecor the amount Resolutions of the Court of Appeals dated October 22, 1990 reconsideration was denied.
prejudicial as to amount to a grave abuse of discretion or representing the alleged unpaid and December 3, 1990 as well as the Orders of respondent Arbitration in this jurisdiction is valid and constitutional
an excess de pouvoir on the part of the arbitrator." 21 billings of Chung Fu; Regional Trial Court dated July 31, 1990 and August 23, and that the provision to submit to arbitration any dispute
Even decisions of administrative agencies which are 7. The Honorable Arbitrator 1990, including the writ of execution issued pursuant arising therefrom and the relationship of the parties is part
declared "final" by law are not exempt from judicial review committed grave error in granting thereto, are hereby SET ASIDE. Accordingly, this case is of the contract and is itself a contract. As a rule, contracts
when so warranted. Thus, in the case of Oceanic Bic Division to Roblecor the amount REMANDED to the court of origin for further hearing on are respected as the law between the contracting parties
(FFW), et al. v. Flerida Ruth P. Romero, et representing the alleged extended this matter. All incidents arising therefrom are reverted to and produce effect as between them, their assigns and
al., 22 this Court had occasion to rule that: LexLib overhead expenses; the status quo ante until such time as the trial court shall heirs. However, where other persons, not bound by the
". . . Inspite of statutory provisions 8. The Honorable Arbitrator have passed upon the merits of this case. No costs. arbitration clause, are impleaded as parties to a case, the
making 'final' the committed grave error in granting SO ORDERED. splitting of the proceedings to arbitration as to some
decisions of certain administrative to Roblecor the amount ||| (Chung Fu Industries (Philippines) Inc. v. Court of Appeals, parties on one hand and trial for the others should not be
agencies, we have taken representing expenses for change G.R. No. 96283, [February 25, 1992]) allowed as it would result in multiplicity of suit, duplicitous
cognizance of petitions questioning order for site development outside procedure and unnecessary delay. EAIaHD
these decisions where the SECOND DIVISION SYLLABUS
want of jurisdiction, grave area of responsibility ofRoblecor; [G.R. No. 136154. February 7, 2001.] l. CIVIL LAW; SPECIAL CONTRACTS; ARBITRATION; VALID
abuseof discretion, violation of due 9. The Honorable Arbitrator DEL MONTE CORPORATION-USA, AND CONSTITUTIONAL. — There is no doubt that
process, denial of substantial justice committed grave error in granting PAUL E. DERBY, JR., DANIEL arbitration is valid and constitutional in our jurisdiction.
or erroneous interpretation of the to Roblecor the cost of warehouse COLLINS and LUIS Even before the enactment of RA 876, this Court has
law were brought to our attention. . No. 2; HIDALGO,petitioners, vs. COURT countenanced the settlement of disputes through
. ." 23 (Emphasis ours.). 10. The Honorable Arbitrator OF APPEALS, JUDGE BIENVENIDO arbitration. Unless the agreement is such as absolutely to
It should be stressed too, that voluntary arbitrators, by the committed grave error in granting L. REYES in his capacity as close the doors of the courts against the parties, which
nature of their functions, act in a quasi-judicial to Roblecor extra compensation for Presiding Judge, RTC-Br. 74, agreement would be void, the courts will look with favor
capacity. 24 It stands to reason, therefore, that their airduct change in dimension; Malabon, Metro Manila, upon such amicable arrangement and will only interfere
decisions should not be beyond the scope of the 11. The Honorable Arbitrator MONTEBUENO MARKETING, INC., with great reluctance to anticipate or nullify the action of
powerof judicial review of this Court. committed grave error in granting LIONG LIONG C. SY and SABROSA the arbitrator. Moreover, as RA 876 expressly authorizes
In the case at bar, petitioners assailed the arbitral award on to Roblecor extra compensation for FOODS, INC., respondents. arbitration of domestic disputes, foreign arbitration as a
the following grounds, most of which allege error on the airduct plastering; and Quisumbing Torres Law Office for petitioners. system of settling commercial disputes was likewise
part of the arbitrator in granting compensation for various 12. The Honorable Arbitrator Albano & Associates for private respondent Montebueno recognized when the Philippines adhered to the United
items which apparently are disputed by said petitioners: committed grave error in awarding Marketing Inc. Nations "Convention on the Recognition and the
1. The Honorable Arbitrator to Roblecor attorney's fees. Sioson Sandiego & Associates for respondents L.C. Sy and Enforcement of Foreign Arbitral Awards of 1958" under the
committed grave error in failing to After closely studying the list of errors, as well as Sabrosa 10 May 1965 Resolution No. 71 of the Philippine Senate,
apply the terms and petitioners' discussion of the same in their Motion to Foods Inc. giving reciprocal recognition and allowing enforcement of
international arbitration agreements between parties of and/or, if applicable, the United they should be held responsible for all the actual expenses Reconsideration of the affirmation was denied. Hence,
different nationalities within a contracting state. States of America. All disputes incurred by private respondents in the delayed shipment of this Petition for Review.
2. ID.; OBLIGATIONS AND CONTRACTS; CONTRACT, LAW arising out of or relating to this orders which resulted in the extra handling thereof, the The crux of the controversy boils down to whether the
BETWEEN PARTIES, THEIR ASSIGNS AND HEIRS; CASE AT Agreement or the parties' actual expenses and cost of money for the unused Letters of dispute between the parties warrants an order compelling
BAR. — The provision to submit to arbitration any dispute relationship, including the Credit (LCs) and the substantial opportunity losses due to them to submit to arbitration.
arising therefrom and the relationship of the parties is part termination thereof, shall be created out-of-stock situations and unauthorized Petitioners contend that the subject matter of private
of that contract and is itself a contract. As a rule, contracts resolved by arbitration in the City shipments of Del Monte-USA products to the Philippine respondents' causes of action arises out of or relates to the
are respected as the law between the contracting parties of San Francisco, State of California, Duty Free Area and Economic Zone; that the bad faith, Agreement between petitioners and private respondents.
and produce effect as between them, their assigns and under the Rules of the American fraudulent acts and willful negligence of petitioners, Thus, considering that the arbitration clause of the
heirs. Clearly, only parties to the Agreement, i.e., petitioners Arbitration Association. The motivated by their determination to squeeze private Agreement provides that all disputes arising out of or
DMC-USA and its Managing Director for Export Sales Paul arbitration panel shall consist of respondents out of the outstanding and ongoing relating to the Agreement or the parties' relationship,
E. Derby, Jr., and private respondents MMI and its three members, one of whom shall Distributorship Agreement in favor of another party, had including the termination thereof, shall be resolved by
Managing Director LILY SY are bound by the Agreement be selected by DMC-USA, one of placed private respondent LILY SY on tenterhooks since arbitration, they insist on the suspension of the
and its arbitration clause as they are the only signatories whom shall be selected by MMI, then; and, that the shrewd and subtle manner with which proceedings in Civil Case No. 2637-MN as mandated by Sec.
thereto. Petitioners Daniel Collins and Luis Hidalgo, and and third of whom shall be selected petitioners concocted imaginary violations by private 7 of RA 876 18 —
private respondent SFI, not parties to the Agreement and by the other two members and respondent MMI of the Distributorship Agreement in order SECTION 7. Stay of Civil Action. If
cannot even be considered assigns or heirs of the parties, shall have relevant experience in to justify the untimely termination thereof was a any suit or proceeding be brought
are not bound by the Agreement and the arbitration clause the industry . . . . subterfuge. For the foregoing, private' respondents upon an issue arising out of an
therein. Consequently, referral to arbitration in the State of In October 1994 the appointment of private respondent claimed, among other reliefs, the payment of actual agreement providing for
California pursuant to the arbitration clause and the MMI as the sole and exclusive distributor of Del Monte damages, exemplary damages, attorney's fees and litigation arbitration thereof, the court in
suspension of the proceedings in Civil Case No. 2637-MN products in the Philippines was published in several expenses. which such suit or proceeding is
pending the return of the arbitral award could be called newspapers in the country. Immediately after its pending, upon being satisfied that
for but onlyas to petitioners DMC-USA and Paul E. Derby, appointment, private respondent MMI appointed Sabrosa On 21 October 1996 petitioners filed a Motion to Suspend the issue involved in such suit or
Jr., and private respondents MMI and LILY SY, and not as to Foods, Inc. (SFI), with the approval of petitioner DMC-USA, Proceedings 13 invoking the arbitration clause in their proceeding is referable to
the other parties in this case, in accordance with the recent as MMI's marketing arm to concentrate on its marketing Agreement with private respondents. arbitration, shall stay the action or
case of Heirs of Augusto L. Salas, Jr. v. Laperal Realty and selling function as well as to manage its critical In a Resolution 14 dated 23 December 1996 the trial court proceeding until an arbitration has
Corporation, which superseded that of Toyota Motor relationship with the trade. deferred consideration of petitioners' Motion to Suspend been had in accordance with the
Philippines Corp. v. Court of Appeals. On 3 October 1996 private respondents MMI, SFI and Proceedings as the grounds alleged therein did not terms of the agreement. Provided,
3. ID.; SPECIAL CONTRACTS; ARBITRATION; DISPENSED MMI's Managing Director Liong Liong C. Sy (LILY SY) filed a constitute the suspension of the proceedings considering That the applicant for the stay is
WITHIN THE INTEREST OF JUSTICE. — The object of Complaint 5 against petitioners DMC-USA, Paul E. Derby, that the action was for damages with prayer for the not in default in proceeding with
arbitration is to allow the expeditious determination of a Jr., 6 Daniel Collins 7 and Luis Hidalgo, 8 and Dewey issuance of Writ of Preliminary Attachmentand not on the such arbitration.
dispute. Clearly, the issue before us could not be speedily Ltd. 9 before the Regional Trial Court of Malabon, Metro Distributorship Agreement. Private respondents claim, on the other hand, that their
and efficiently resolved in its entirety if we allow Manila. Private respondents predicated their complaint on On 15 January 1997 petitioners filed a Motion for causes of action are rooted in Arts. 20, 21 and 23 of the
simultaneous arbitration proceedings and trial, or the alleged violations by petitioners of Arts. Reconsideration to which private respondents filed Civil Code, 19 the determination of which demands a full
suspension of trial pending arbitration. Accordingly, the 20, 10 21 11 and 23 12 of the Civil Code. According to theirComment/Opposition. On 31 January 1997 petitioners blown trial, as correctly held by the Court of Appeals.
interest of justice would only be served if the trial court private respondents, DMC-USA products continued to be filed their Reply. Subsequently, private respondents filed Moreover, they claim that the issues before the trial court
hears and adjudicates the case in a single and complete brought into the country by parallel importers despite the an Urgent Motion for Leave to Admit Supplemental were not joined so that the Honorable Judge was not given
proceeding. appointment of private respondent MMI as the sole and Pleading dated 2 April 1997. This Motion was admitted, the opportunity to satisfy himself that the issue involved in
DECISION exclusive distributor of Del Monte products thereby over petitioners' opposition, in an Order of the trial court the case was referable to arbitration. They submit that,
BELLOSILLO, J p: causing them great embarrassment and substantial dated 27 June 1997. DEHaTC apparently, petitioners filed a motion to suspend
This Petition for Review on certiorari assails the 17 July damage. They alleged that the products brought into the As a result of the admission of the Supplemental Complaint, proceedings instead of sending a written demand to private
1998 Decision 1 of the Court of Appeals affirming the 11 country by these importers were aged, damaged, fake or petitioners filed on 22 July 1997 a Manifestationadopting respondents to arbitrate because petitioners were not sure
November 1997 Order 2 of the Regional Trial Court which counterfeit, so that in March 1995 they had to cause, after their Motion to Suspend Proceedings of 17 October 1996 whether the case could be a subject of arbitration. They
denied petitioners' Motion to Suspend Proceedings in Civil prior consultation with Antonio Ongpin, Market Director and Motion for Reconsideration of 14 January 1997. maintain that had petitioners done so and private
Case No. 2637-MN. It also questions the appellate for Special Markets of Del Monte Philippines, Inc., the On 11 November 1997 the Motion to Suspend respondents failed to answer the demand, petitioners could
court's Resolution 3 of 30 October 1998 which denied publication of a "warning to the trade" paid advertisement Proceedings was denied by the trial court on the ground have filed with the trial court their demand for arbitration
petitioners' Motion for Reconsideration. DTAHEC in leading newspapers. Petitioners DMC-USA and Paul E. that it "will not serve the ends of justice and to allow said that would warrant a determination by the judge whether
On 1 July 1994, in a Distributorship Agreement, petitioner Derby, Jr., apparently upset with the publication, instructed suspension will only delay the determination of the issues, to refer the case to arbitration. Accordingly, private
Del Monte Corporation-USA (DMC-USA) appointed private private respondent MMI to stop coordinating with Antonio frustrate the quest of the parties for a judicious respondents assert that arbitration is out of the question.'
respondent Montebueno Marketing, Inc. (MMI) as the sole Ongpin and to communicate directly instead with determination of their respective claims, and/or deprive and Private respondents further contend that the arbitration
and exclusive distributor of its Del Monte products in the petitioner DMC-USA through Paul E. Derby, Jr. delay their rights to seek redress." 15 clause centers more on venue rather than on arbitration.
Philippines for a period of five (5) years, renewable for two Private respondents further averred that petitioners On appeal, the Court of Appeals affirmed the decision of the They finally allege that petitioners filed their motion for
(2) consecutive five (5) year periods with the consent of knowingly and surreptitiously continued to deal with the trial court. It held that the alleged damaging acts recited in extension of time to file this petition on the same
the parties. The Agreement provided, among others, for an former in bad faith by involving disinterested third parties the Complaint, constituting petitioners' causes of action, date 20 petitioner DMC-USA filed a petition to compel
arbitration clause which states — and by proposing solutions which were entirely out of their required the interpretation of Art. 21 of the Civil private respondent MMI to arbitrate before the United
12. GOVERNING LAW AND control. Private respondents claimed that they had Code 16 and that in determining whether petitioners had States District Court in Northern California, docketed as
ARBITRATION 4 exhausted all possible avenues for an amicable resolution violated it "would require a full blown trial" making Case No. C-98-4446. They insist that the filing of the
This Agreement shall be governed and settlement of their grievances; that as a result of the arbitration "out of the question." 17 Petitioners' Motion for petition to compel arbitration in the United States made the
by the laws of the State of California fraud, bad faith, malice and wanton attitude of petitioners, petition filed before this Court an alternative remedy and,
in a way, an abandonment of the cause they are fighting for contractual commitments." 29 However, in Salas, Jr., only 3. ID.; ID.; ID.; ID.; ESTOPPEL; INVOKED ONLY IN HIGHLY certain other courts or quasi-judicial agencies for
here in the Philippines, thus warranting the dismissal of the parties to the Agreement, their assigns or heirs have the EXCEPTIONAL CASES. — The doctrine of estoppel is determination. Nevertheless, it can hardly be questioned
present petition before this Court. right to arbitrate or could be compelled to arbitrate. The predicated on, and has its origin in, equity which, broadly that the rules relating to the effects of want of jurisdiction
There is no doubt that arbitration is valid and Court went further by declaring that in recognizing the defined, is justice according to natural law and right. It is a over the subject matter should apply with equal vigor to
constitutional in our jurisdiction. 21 Even before the right of the contracting parties to arbitrate or to compel principle intended to avoid a clear case of injustice. The cases where the court is similarly bereft of jurisdiction over
enactment of RA 876, this Court has countenanced the arbitration, the splitting of the proceedings to arbitration term is hardly distinguishable from a waiver of right. the nature of the action.
settlement of disputes through arbitration. Unless the as to some of the parties on one hand and trial for the Estoppel, like its said counterpart, must be unequivocal and 7. ID.; ID.; ID.; ID.; CASE AT BENCH. — In the case at bench,
agreement is such as absolutely to close the doors of the others on the other hand, or the suspension of trial pending intentional for, when misapplied, it can easily become a the want of jurisdiction by the court is indisputable, given
courts against the parties, which agreement would be void, arbitration between some of the parties, should not be most convenient and effective means of injustice. Estoppel the nature of the controversy. The arbitration law explicitly
the courts will look with favor upon such amicable allowed as it would, in effect, result in multiplicity of suits, is not understood to be a principle that, as a rule, should confines the court's authority only to pass upon the issue of
arrangement and will only interfere with great reluctance duplicitous procedure and unnecessary delay. 30 prevalently apply but, such as it concededly is, as a mere whether there is or there is no agreement in writing
to anticipate or nullify the action of the The object of arbitration is to allow the expeditious exception from the standard legal norms of general providing for arbitration. In the affirmative, the statute
arbitrator. 22 Moreover, as RA 876 expressly authorizes determination of a dispute. 31 Clearly, the issue before us application that can be invoked only in highly exceptional ordains that the court shall issue an order "summarily
arbitration of domestic disputes, foreign arbitration as a could not be speedily and efficiently resolved in its entirety and justifiable cases. directing the parties to proceed with the arbitration in
system of settling commercial disputes was likewise if we allow simultaneous arbitration proceedings and trial, 4. ID.; ID.; ID.; ID.; ID.; ASSERTION OF AFFIRMATIVE accordance with the terms thereof." If the court, upon the
recognized when the Philippines adhered to the United or suspension of trial pending arbitration. Accordingly, the DEFENSE ALONG WITH OBJECTION TO COURT'S other hand, finds that no such agreement exists, "the
Nations "Convention on the Recognition and the interest of justice would only be served if the trial court JURISDICTION OVER THE PERSON, NOT A CASE OF. — The proceeding shall be dismissed." The proceedings are
Enforcement of Foreign Arbitral Awards of 1958" under the hears and adjudicates the case in a single and complete submission of other issues in a motion to dismiss, or of an summary in nature.
10 May 1965 Resolution No. 71 of the Philippine Senate, proceeding. 32 affirmative defense (as distinguished from an affirmative 8. ID.; ID.; SUMMARY OF RULES RELATING TO EFFECTS OF
giving reciprocal recognition and allowing enforcement of WHEREFORE, the petition is DENIED. The Decision of the relief) in an answer, would necessarily foreclose, and have WANT OF JURISDICTION BY THE COURT. — In summary, it
international arbitration agreements between parties of Court of Appeals affirming the Order of the Regional Trial the effect of a waiver of, the right of a defendant to set up is our considered view, as we now so hereby express, that
different nationalities within a contracting state. 23 Court of Malabon, Metro Manila, in Civil Case No. 2637-MN, the court's lack of jurisdiction over the person of the — (1) Jurisdiction over the person must be seasonably
A careful examination of the instant case shows that the which denied petitioners' Motion to Suspend Proceedings, is defendant. . . . In the same manner that a plaintiff may raised, i.e., that it is pleaded in a motion to dismiss or by
arbitration clause in the Distributorship Agreement AFFIRMED. The Regional Trial Court concerned is directed assert two or more causes of action in a court suit, a way of an affirmative defense in an answer. Voluntary
between petitioner DMC-USA and private respondent MMI to proceed with the hearing of Civil Case No. 2637-MN with defendant is likewise expressly allowed, under Section 2, appearance shall be deemed a waiver of this defense. The
is valid and the dispute between the parties is arbitrable. dispatch. No costs. Rule 8, of the Rules of Court, to put up his own defenses assertion, however, of affirmative defenses shall not be
However, this Court must deny the petition. cDEICH SO ORDERED. alternatively or even hypothetically. Indeed, under Section construed as an estoppel or as a waiver of such defense. (2)
The Agreement between petitioner DMC-USA and private ||| (Del Monte Corp.-USA v. Court of Appeals, G.R. No. 136154, 2, Rule 9, of the Rules of Court, defenses and objections not Where the court itself clearly has no jurisdiction over the
respondent MMI is a contract. The provision to submit to [February 7, 2001], 404 PHIL 192-203) pleaded either in a motion to dismiss or in an answer, subject matter or the nature of the action, the invocation of
arbitration any dispute arising therefrom and the except for the failure to state a cause of action, are deemed this defense may be done at any time. It is neither for the
relationship of the parties is part of that contract and is EN BANC waived. We take this to mean that a defendant may, in fact, courts nor the parties to violate or disregard that rule, let
itself a contract. As a rule, contracts are respected as the [G.R. No. 103200. August 31, 1994.] feel enjoined to set up, along with his objection to the alone to confer that jurisdiction, this matter being
law between the contracting parties and produce effect as LA NAVAL DRUG court's jurisdiction over his person, all other possible legislative in character. Barring highly meritorious and
between them, their assigns and heirs. 24 Clearly, only CORPORATION, petitioner, vs. THE defenses. It thus appears that it is not the invocation of any exceptional circumstances, such as hereinbefore
parties to the Agreement, i.e., petitioners DMC-USA and its HONORABLE COURT OF APPEALS of such defenses, but the failure to so raise them, that can exemplified, neither estoppel nor waiver shall apply.
Managing Director for Export Sales Paul E. Derby, Jr., and and WILSON C. YAO, respondents. result in waiver or estoppel. By defenses, of course, we DECISION
private respondents MMI and its Managing Director LILY SYLLABUS refer to the grounds provided for in Rule 16 of the Rules of VITUG, J p:
SY are bound by the Agreement and its arbitration clause 1. REMEDIAL LAW; REPUBLIC ACT NO. 876; Court that must be asserted in a motion to dismiss or by In an effort to declog the courts of an increasing volume of
as they are the only signatories thereto. Petitioners Daniel ARBITRATORS, HOW GOVERNED; CASE AT BAR. — way of affirmative defenses in an answer. work load and, most importantly, in order to accord
Collins and Luis Hidalgo, and private respondent SFI, not Arbitration, in particular, is governed by a special 5. ID.; ID.; JURISDICTION OVER THE SUBJECT MATTER, contending parties with expeditious alternatives for
parties to the Agreement and cannot even be considered law, Republic Act 876, suppletory to which are laws and LACK OF; EFFECTS THEREOF. — Lack of jurisdiction over settling disputes, the law authorizes, indeed discourages,
assigns or heirs of the parties, are not bound by the rules of general application. This case before us concerns the subject matter of the suit is yet another matter. out of court settlements or adjudications. Compromises
Agreement and the arbitration clause therein. the jurisdiction of courts, in relation to the provisions of Whenever it appears that the court has no jurisdiction over and arbitration are widely known and used as such
Consequently, referral to arbitration in the State of Section 6 of Republic Act No. 876, and, in that respect, the the subject matter, the action shall be dismissed (Section 2, acceptable methods of resolving adversarial claims.
California pursuant to the arbitration clause and the applicability of the doctrine of estoppel. Rule 9, Rules of Court). This defense may be interposed at Arbitrations, in particular, is governed by a special
suspension of the proceedings in Civil Case No. 2637-MN 2. ID.; CIVIL PROCEDURE; JURISDICTION OVER THE any time, during appeal (Roxas vs. Rafferty, 37 Phil. 957) or law, Republic Act 876, suppletory to which are laws and
pending the return of the arbitral award could be called PERSON; LACK OF; DEFENSE THEREOF, HOW WAIVED. — even after final judgment (Cruzcosa vs. Judge Concepcion, rules of general application. This case before us concerns
for 25 but only as to petitioners DMC-USA and Paul E. The lack of jurisdiction over the person of the defendant et al., 101 Phil. 146). Such is understandable, as this kind of the jurisdiction of courts, in relation to the provisions of
Derby, Jr., and private respondents MMI and LILY SY, and may be waived either expressly or impliedly. When a jurisdiction is conferred by law and not within the courts, Section 6 of Republic Act No. 876, and, in that respect, the
not as to the other parties in this case, in accordance with defendant voluntarily appears, he is deemed to have let alone the parties, to themselves determine or applicability of the doctrine of estoppel. The law (R.A. 876),
the recent case of Heirs of Augusto L. Salas, Jr. v. Laperal submitted himself to the jurisdiction of the court. If he so conveniently set aside. specifically Section 6 thereof, provides: cdrep
Realty Corporation, 26 which superseded that ofToyota wishes not to waive this defense, he must do so seasonably 6. ID.; ID.; JURISDICTION OVER THE NATURE OF THE "Sec. 6. Hearing by court. — A party
Motor Philippines Corp. v. Court of Appeals. 27 by motion for the purpose of objecting to the jurisdiction of ACTION, LACK OF; EFFECTS THEREOF. — Lack of aggrieved by the failure, neglect or
In Toyota, the Court ruled that "[t]he contention that the the court; otherwise, he shall be deemed to have submitted jurisdiction over the nature of the action is the situation refusal of another to perform under
arbitration clause has become dysfunctional because of the himself to that jurisdiction. The decisions promulgated that arises when a court, which ordinarily would have the an agreement in writing providing
presence of third parties is untenable ratiocinating that heretofore by this Court would likewise seemingly apply authority and competence to take a case, is rendered for arbitration may petition the
[c]ontracts are respected as the law between the estoppel to bar the defendant from pursuing that defense without it either because a special law has limited the court for an order directing that
contracting parties" 28 and that "[a]s such, the parties are by alleging in his answer any other issue for dismissing the exercise of its normal jurisdiction on a particular matter or such arbitration proceed in the
thereby expected to abide with good faith in their action. because the type of action has been reposed by law in manner provided for in such
agreement. Five days notice in Contract of Lease, composed of three (3) the delay in the arbitration was due
writing of the hearing of such thereby compelling members, one to be to respondent Yao's failure to
application shall be served either among others the appointed by LESSOR, perform what is incumbent upon
personally or by registered mail petitioner to go to Court another by LESSEE and him, of notifying and thereafter,
upon the party in default. The court for redress; and the third one to be requiring both arbitrators to
shall hear the parties, and upon respondent La Naval agreed upon by the two appoint the third member of the
being satisfied that the making of Drug Corporation's arbitrators previously Board of Arbitrators. According to
the agreement or such failure to counterclaim for chosen and the parties petitioner, it actually gave
comply therewith is not in issue, damages may be hereto shall submit to arbitrators Sabile and Alamarez a
shall make an order directing the entertained by this Court the decision of the free hand in choosing the third
parties to proceed to arbitration in in a hearing - not arbitrators.' arbitrator; and, therefore,
accordance with the terms of the summary - for the "Thus, on May 6, 1989, respondent respondent Yao has no cause of
agreement. If the making of the purpose, under the Rules Yao appointed Domingo Alamarez, action against it (petitioner). By
agreement or default be in issue the of Court. Jr. as his arbitrator, while on June 5, way of Counterclaim, petitioner
court shall proceed to summarily '(2) A 1989, petitioner chose Atty. alleged that it suffered actual
hear such issue. If the finding be preliminary hearing of Casiano Sabile as its arbitrator. The damages of P100,000.00; and
that no agreement in writing the special and confirmation of the appointment of incurred attorney's fees of
providing for arbitration was made, affirmative defense to Aurelio Tupang, as third arbitrator, P50,000.00, plus P500.00 for every
or that there is no default in the show that Petitioner has was held in abeyance because court appearance of its counsel.
proceeding thereunder, the no cause of action petitioner instructed Atty. Sabile to "On October 20, 1989, respondent
proceeding shall be dismissed. If against respondent's defer the same until its Board of Yao filed an amended petition for
the finding be that a written claim for damages is Directors could convene and 'Enforcement of Arbitration
provision for arbitration was made denied; a resolution on approve Tupang's appointment. Agreement with Damages;' praying
and there is a default in proceeding this issue deferred after Respondent Yao theorizes that this that petitioner be ordered to pay
thereunder, an order shall be made the trial of the case on was petitioner's design to delay the interest on the unpaid rents, at the
summarily directing the parties to the merits.' arbitration proceedings, in prevailing rate of interest in
proceed with the arbitration in violation of the Arbitration Law, commercial banks, and exemplary
accordance with the terms thereof. And challenges the Order of June and the governing stipulations of damages of at least P250,000.00.
"The court shall decide all motions, 22, 1990 denying its motion for their contract of lease. "On October 24, 1989, despite
petitions or application filed under reconsideration of the said earlier "On the basis of the aforesaid petitioner's opposition to the
the provisions of this Act, within Order. allegations, respondent Yao prayed motion to admit the amended
ten days after such motions, "From the petition below of that after summary hearing petition, the respondent court
petitions, or applications have been respondent Yao, it appears that he pursuant to Section 6 of the admitted the same.
heard by it." is the present owner of a Arbitration Law, Atty. Casiano "On October 31, 1989, petitioner
In chronology, the events that have led to the case at bench commercial building a portion of Sabile and Domingo Alamarez be answered the amended petition;
are detailed in the appealed decision of respondent which is leased to petitioner under directed to proceed with the contending, among others, that the
appellate court, which we here reproduce in toto. a contract of lease executed on arbitration in accordance with amended petition should be
"Original action for Certiorari and December 23, 1983 with the former Section 7 of subject Contract of dismissed on the ground of non-
Prohibition for Annulment of the owner thereof, La Proveedora, Inc., Lease and the applicable provisions payment of the requisite filing fees
Orders, dated April 26, 1990 and which contract expired on April 30, of the Arbitration Law, by therefor; and it being in the nature
June 22, 1990, respectively, of 1989. However, petitioner appointing and confirming the of an ordinary civil action, a full
Branch LXI, Regional Trial Court, exercised its option to lease the appointment of the Third blown and regular trial is
Angeles City, in Special Case No. same building for another five Arbitrator; and that the Board of necessary; so that respondent Yao's
6024 for Enforcement of years. But petitioner and Three Arbitrators be ordered to proposition for a summary hearing
ARBITRATION Agreement with respondent Yao disagreed on the immediately convene and resolve of the arbitration issue and
Damages. Petitioner assails that rental rate, and to resolve the the controversy before it, pursuant separate trial for his claim for
portion of subject Order of April 26, controversy, the latter, thru written to Section 12 and the succeeding damages is procedurally untenable
1990, stating as follows: notices to the former, expressed his sections of the Arbitration Law. and implausible.
"'(1) Petitione intention to submit their (Annex 'A,' Petition.). "Invoking Section 5, Rule 16 of the
r's claim for damages disagreement to arbitration, in "In its Answer with Counterclaim Rules of Court, petitioner presented
predicated on alleged accordance with Republic Act 876, (Annex 'C,' Petition), petitioner a 'Motion to Set Case for
tortuous acts of otherwise known as the Arbitration here specifically denied the Preliminary Hearing' of its special
respondents La Naval Law, and paragraph 7 of their lease averments of the petition below; and affirmative defenses, which are
Drug corporation such as contract, providing that: theorizing that such petition is grounds for a motion to dismiss.
their alleged interference "'7. . . . Should premature since respondent Yao "In its Order of November 14, 1989,
and dilatory tactics, etc. the parties fail to agree has not yet formally required the respondent court announced
in the implementation of on the rate of rentals, the arbitrators Alamarez and Sabile to that the two arbitrators chose Mrs.
the Arbitration same shall be submitted agree on the third arbitrator, within Eloisa R. Narciso as the third
Agreement in the to a group of Arbitrators ten (10) days from notice, and that arbitrator. And on November 21,
1989, it ordered the parties to heretofore by this Court would likewise seemingly apply Zurbito, supra, at page 751. That the effect of a waiver of, the right of a defendant to set up
submit their position papers on the estoppel to bar the defendant from pursuing that defense rule was followed in Ocampo vs. the court's lack of jurisdiction over the person of the
issue as to whether or not by alleging in his answer any other issue for dismissing the Mina and Arejola, 41 Phil. 308)." defendant. LLpr
respondent Yao's claim for action. The justification for the rule was expressed Not inevitably.
damages may be litigated upon in A citation of a few of our decisions might be apropos. in Republic vs. Ker and Company, Ltd. (18 SCRA 207, Section 1, Rule 16, of the Rules of Court, provides that a
the summary proceeding for In Wang Laboratories, Inc., vs. Mendoza (156 SCRA 44), this 213-214), in this wise: llcd motion to dismiss may be made on the following grounds:
enforcement of arbitration Court has ruled that if the defendant, besides setting up in a "We observe that the motion to "(a) That the court has no
agreement. It likewise informed the motion to dismiss his objection to the jurisdiction of the dismiss filed on April 14, 1962, jurisdiction over the person of the
parties that petitioner's 'Motion to court, alleges at the same time any other ground for aside from disputing the lower defendant or over the subject of the
Set Case for Preliminary Hearing' of dismissing the action, he is deemed to have submitted court's jurisdiction over action or suit;
Special and Affirmative Defenses himself to the jurisdiction of the court. In the process, it has defendant's person, prayed for "(b) That the court has no
would be resolved together with equated the matter to a situation where, such as dismissal of the complaint on the jurisdiction over the nature of the
the question of damages. in Immaculata vs. Judge Navarro, et al. (146 SCRA 5), the ground that plaintiff's cause of action or suit;
"On April 26, 1990, the aforequoted defendant invokes an affirmative relief against his action has prescribed. By "(c) The venue is improperly laid;
assailed Order issued. In moving for opponent. interposing such second ground in "(d) That the plaintiff has no legal
reconsideration of the said Order, In De Midgely vs. Judge Ferandos (64 SCRA 23, 31), the its motion to dismiss, Ker & Co., Ltd. capacity to sue;
petitioner argued that in Special Court elaborated thusly: availed of an affirmative defense on "(e) That there is another action
Case No. 6024, the respondent "We are of the opinion that the the basis of which it prayed the pending between the same parties
court sits as a special court lower court has acquired court to resolve controversy in its for the same cause;
exercising limited jurisdiction and jurisdiction over the person of Mrs. favor. For the court to validly "(f) That the cause of action is
is not competent to act on Midgely by reason of her voluntary decide the said plea of defendant barred by a prior judgment or by
respondent Yao's claim for appearance. The reservation in her Ker & Co., Ltd., it necessarily had to statute of limitations;
damages, which poses an issue motion to dismiss that she was acquire jurisdiction upon the "(g) That the complaint states no
litigable in an ordinary civil action. making a special appearance to latter's person, who, being the cause of action;
But the respondent court was not contest the court's jurisdiction over proponent of the affirmative "(h) That the claim or demand set
persuaded by petitioner's her person may be disregarded. defense, should be deemed to have forth in the plaintiff's pleading has
submission. On June 22, 1990, it "It may be disregarded because it abandoned its special appearance been paid, waived, abandoned, or
denied the motion for was nullified by the fact that in her and voluntarily submitted itself to otherwise extinguished;
reconsideration." (Rollo, pp. 89-93). motion to dismiss she relied not the jurisdiction of the court. "(i) That the claim on which the
While the appellate court has agreed with petitioner that, only on the ground of lack of action or suit is founded is
under Section 6 of Republic Act No. 876, a court, acting jurisdiction over her person but "Voluntary appearance cures unenforceable under the provisions
within the limits of its special jurisdiction, may in this case also on the ground that there was defects of summons, if any. Such of the statute of frauds;
solely determine the issue of whether the litigants should no showing that earnest efforts defect, if any, was further cured "(j) That the suit is between
proceed or not to arbitration, it, however, considered were exerted to compromise the when defendant filed its answer to members of the same family and no
petitioner in estoppel from questioning the competence of case and because she prayed 'for the complaint. A defendant can not earnest efforts towards a
the court to additionally hear and decide in the summary such other relief as' may be deemed be permitted to speculate upon the compromise have been made."
proceedings private respondent's claim for damages, it 'appropriate and proper.' judgment of the court by objecting Any ground for dismissal in a motion to dismiss,
(petitioner) having itself filed similarly its own "xxx xxx xxx to the court's jurisdiction over its except improper venue, may, as further set forth
counterclaim with the courta quo. LLphil "When the appearance is by motion person if the judgment is adverse to inSection 5 of the same rule, be pleaded as an
It is hardly disputable that when a court is called upon to for the purpose of objecting to the it, and acceding to jurisdiction over affirmative defense and a preliminary hearing may be
exercise limited and special jurisdiction, that court cannot jurisdiction of the court over the its person if and when the had thereon as if a motion to dismiss had been filed.
stray to matters outside the area of its declared authority person, it must be for the sole and judgment sustains its defenses." An answer itself contains the negative, as well as
or beyond what has been expressly invested by law separate purpose of objecting to The doctrine of estoppel is predicated on, and has its origin affirmative, defenses upon which the defendant may
(Elumbaring vs. Elumbaring, 12 Phil. 384, 387), particularly, the jurisdiction of the court. If his in, equity which, broadly defined, is justice according to rely (Section 4, Rule 6, Rules of Court). A negative
such as in this instance, where the proceedings are motion is for any other purpose natural law and right. It is a principle intended to avoid a defense denies the material facts averred in the
summary in nature. than to object to the jurisdiction of clear case of injustice. The term is hardly distinguishable complaint essential to establish the plaintiff's cause of
Prefatorily, recalling the distinctions, pertinent to the case, the court over his person, he from a waiver of right. Estoppel, like its said counterpart, action, while an affirmative defense is an allegation of
between the court's lack of jurisdiction over theperson of thereby submits himself to the must be unequivocal and intentional for, when misapplied, a new matter which, while admitting the material
the defendant, on the one hand, and its lack of jurisdiction jurisdiction of the court. A special it can easily become a most convenient and effective means allegations of the complaint, would, nevertheless,
over the subject matter or the nature of the action, upon the appearance by motion made for the of injustice. Estoppel is not understood to be a principle prevent or bar recovery by the plaintiff. Inclusive of
other hand, should be useful. purpose of objecting to the that, as a rule, should prevalently apply but, such as it these defenses are those mentioned in Rule 16 of the
The lack of jurisdiction over the person of the defendant jurisdiction of the court over the concededly is, as a mere exception from the standard legal Rules of Court which would permit the filing of a
may be waived either expressly or impliedly. When a person will be held to be a general norms of general application that can be invoked only in motion to dismiss. LLphil
defendant voluntarily appears, he is deemed to have appearance, if the party in said highly exceptional and justifiable cases. In the same manner that a plaintiff may assert two or more
submitted himself to the jurisdiction of the court. If he so motion should, for example, ask for Tested by the above criteria, the Court sees it propitious to causes of action in a court suit, a defendant is likewise
wishes not to waive this defense, he must do so seasonably a dismissal of the action upon the re-examine specifically the question of whether or not the expressly allowed, under Section 2, Rule 8, of the Rules of
by motion for the purpose of objecting to the jurisdiction of further ground that the court had submission of other issues in a motion to dismiss, or of an Court, to put up his own defenses alternatively or even
the court; otherwise, he shall be deemed to have submitted no jurisdiction over the subject affirmative defense (as distinguished from an affirmative hypothetically. Indeed, under Section 2, Rule 9, of the Rules
himself to that jurisdiction. The decisions promulgated matter. (Syllabus, Flores vs. relief) in an answer, would necessarily foreclose, and have of Court, defenses and objections not pleaded either in a
motion to dismiss or in an answer, except for the failure to dismissed (Section 2, Rule 9, Rules of Court). This defense (1) Jurisdiction over the person must be seasonably raised, This petition for review on certiorari 1 assails the
state a cause of action, are deemed waived. We take this to may be interposed at any time, during appeal (Roxas vs. i.e., that it is pleaded in a motion to dismiss or by way of an November 9, 1999 Order 2 of the Regional Trial Court of
mean that a defendant may, in fact, feel enjoined to set up, Rafferty, 37 Phil. 957) or even after final judgment affirmative defense in an answer. Voluntary appearance Makati City, Branch 135, in Civil Case No. 92-145 which
along with his objection to the court's jurisdiction over his (Cruzcosa vs. Judge Concepcion, et al., 101 Phil. 146). Such is shall be deemed a waiver of this defense. The assertion, dismissed the petition for review for lack of jurisdiction
person, all other possible defenses. It thus appears that it is understandable, as this kind of jurisdiction is conferred by however, of affirmative defenses shall not be construed as and its February 1, 2000 Order 3 denying reconsideration
not the invocation of any of such defenses, but the failure to law and not within the courts, let alone the parties, to an estoppel or as a waiver of such defense. thereof.
so raise them, that can result in waiver or estoppel. By themselves determine or conveniently set aside. In People (2) Where the court itself clearly has no jurisdiction over The antecedent facts are as follows:
defenses, of course, we refer to the grounds provided for in vs. Casiano (111 Phil. 73, 93-94), this Court, on the issue of the subject matter or the nature of the action, the On December 11, 1991, Far East Bank and Trust Company
Rule 16 of the Rules of Court that must be asserted in a estoppel, held: LibLex invocation of this defense may be done at any time. It is (Respondent) filed a complaint against Home Bankers
motion to dismiss or by way of affirmative defenses in an "The operation of the principle of neither for the courts nor the parties to violate or disregard Trust and Company (HBTC) 4 with the Philippine Clearing
answer. estoppel on the question of that rule, let alone to confer that jurisdiction, this matter House Corporation's (PCHC) Arbitration Committee
Mindful of the foregoing, in Signetics Corporation vs. Court jurisdiction seemingly depends being legislative in character. Barring highly meritorious docketed as Arbicom Case No. 91-069. 5 Respondent
of Appeals and Freuhauf Electronics Phil., Inc.(225 SCRA upon whether the lower court and exceptional circumstances, such as hereinbefore sought to recover from the petitioner, the sum of
737, 738), we lately ruled: actually had jurisdiction or not. If it exemplified, neither estoppel nor waiver shall apply. P25,200,000.00 representing the total amount of the three
"This is not to say, however, that had no jurisdiction, but the case In the case at bench, the want of jurisdiction by the court is checks drawn and debited against its clearing account.
the petitioner's right to question was tried and decided upon the indisputable, given the nature of the controversy.The HBTC sent these checks to respondent for clearing by
the jurisdiction of the court over its theory that it had jurisdiction, the arbitration law explicitly confines the court's authority only operation of the PCHC clearing system. Thereafter,
person is now to be deemed a parties are not barred, on appeal, to pass upon the issue of whether there is or there is no respondent dishonored the checks for insufficiency of
foreclosed matter. If it is true, as from assailing such jurisdiction, for agreement in writing providing for arbitration. In the funds and returned the checks to HBTC. However, the latter
Signetics claims, that its only the same 'must exist as a matter of affirmative, the statute ordains that the court shall issue an refused to accept them since the checks were returned by
involvement in the Philippines was law, and may not be conferred by order "summarily directing the parties to proceed with the respondent after the reglementary regional clearing
through a passive investment in consent of the parties or by arbitration in accordance with the terms thereof." If the period. 6
Sigfil, which it even later disposed estoppel' (5 C.J.S., 861-863). court, upon the other hand, finds that no such agreement Meanwhile, on January 17, 1992, before the termination of
of, and that TEAM Pacific is not its However, if the lower court had exists, "the proceeding shall be dismissed." The the arbitration proceedings, respondent filed another
agent, then it cannot really be said jurisdiction, and the case was heard proceedings are summary in nature. complaint but this time with the Regional Trial Court (RTC)
to be doing business in the and decided upon a given theory, in Makati City docketed as Civil Case No. 92-145 for Sum of
Philippines. It is a defense, such, for instance, as that the court All considered, the court a quo must then refrain from Money and Damages with Preliminary Attachment. The
however, that requires the had no jurisdiction, the party who taking up the claims of the contending parties for damages, complaint was filed not only against HBTC but also against
contravention of the allegations of induced it to adopt such theory will which, upon the other hand, may be ventilated in separate Robert Young, Eugene Arriesgado and Victor Tancuan
the complaint, as well as a full not be permitted, on appeal, to regular proceedings at an opportune time and venue. The (collectively known as Defendants), who were the
ventilation, in effect, of the main assume an inconsistent position — circumstances obtaining in this case are far, we hold, from president and depositors of HBTC respectively. 7 Aware of
merits of the case, which should not that the lower court had justifying the application of estoppel against either the arbitration proceedings between respondent and
thus be within the province of a jurisdiction. Here, the principle of party. cdll petitioner, the RTC, in an Omnibus Order dated April 30,
mere motion to dismiss. So, also, estoppel applies. The rule that WHEREFORE, the decision of the Court of Appeals and the 1992, 8suspended the proceedings in the case against all
the issue posed by the petitioner as jurisdiction is conferred by law, and orders of the trial court in question are SET ASIDE. The the defendants pending the decision of the Arbitration
to whether a foreign corporation does not depend upon the will of court a quo, in the instant proceedings, is ordered to Committee, to wit:
which has done business in the the parties, has no bearing DESIST from further hearing private respondent's claim, as WHEREFORE, the Court hereby
country, but which has ceased to do thereon." well as petitioner's counterclaim, for damages. No costs. orders:
business at the time of the filing of The rule was reiterated in Calimlim vs. Ramirez (118 SCRA SO ORDERED. (a) Home Bankers & Trust Co. to
a complaint, can still be made to 399, 406), and quite recently, in Southeast Asian Fisheries Narvasa, C.J., Cruz, Padilla, Bidin, Regalado, Davide, Jr., produce and permit plaintiff to
answer for a cause of action which Development Center-Aquaculture Department vs. National Romero, Bellosillo, Melo, Quiason, Puno, inspect, copy and/or photograph
accrued while it was doing Labor Relations Commission (206 SCRA 283). Kapunan andMendoza, JJ., concur. the checking account deposit ledger
business, is another matter that Jurisdiction over the nature of the action, in concept, differs Separate Opinions of Victor Tancuan's Account No.
would yet have to await the from jurisdiction over the subject matter. Illustrated, lack FELICIANO, J ., 1803-00605-3;
reception and admission of of jurisdiction over the nature of the action is the situation I concur except that in respect of penultimate paragraph in (b) The Motions to Dismiss filed by
evidence. Since these points have that arises when a court, which ordinarily would have the p. 17, I reserve my vote as to compulsory counterclaims for all defendants denied, for lack of
seasonably been raised by the authority and competence to take a case, is rendered damages. merit; and ITaCEc
petitioner, there should be no real without it either because a special law has limited the ||| (La Naval Drug Corp. v. Court of Appeals, G.R. No. 103200, (c) Proceedings in this case
cause for what may understandably exercise of its normal jurisdiction on a particular matter or [August 31, 1994]) against all defendants be
be its apprehension, i.e., that by its because the type of action has been reposed by law in suspended pending
participation during the trial on the certain other courts or quasi-judicial agencies for FIRST DIVISION award/decision in the
merits, it may, absent an invocation determination. Nevertheless, it can hardly be questioned [G.R. No. 141818. June 22, 2006.] arbitration proceedings against
of separate or independent reliefs that the rules relating to the effects of want of jurisdiction INSULAR SAVINGS Home Bankers and Trust Co.
of its own, be considered to have over the subject matter should apply with equal vigor to BANK, petitioner, vs. FAR EAST SO ORDERED. 9 (Emphasis
voluntarily submitted itself to the cases where the court is similarly bereft of jurisdiction over BANK AND TRUST supplied)
court's jurisdiction." the nature of the action. LibLex COMPANY, respondent. The above Omnibus Order was amended by the trial court
Lack of jurisdiction over the subject matter of the suit is yet In summary, it is our considered view, as we now so hereby DECISION in its October 1, 1992 Order, 10 the dispositive portion of
another matter. Whenever it appears that the court has no express, that — YNARES-SANTIAGO, J p: which reads as follows:
jurisdiction over the subject matter, the action shall be
WHEREFORE, the Omnibus Order for Lack of Jurisdiction, 17 which was opposed by the arbitration agreement embedded in their contract wherein rights of any party have been
dated 30 April 1992 is hereby petitioner. 18 Respondent then filed its Reply to the they consent that any future dispute or controversy materially prejudiced; or
reconsidered by deleting the opposition, 19 to which petitioner filed a Rejoinder. 20 On between its PCHC participants involving any check would (d) That the arbitrators exceeded
phrase "since the complaint also August 16, 1999, respondent submitted its Surrejoinder. 21 be submitted to the Arbitration Committee for arbitration. their powers, or so imperfectly
seeks exemplary damages, On November 9, 1999, the RTC rendered the assailed Order Petitioner and respondent are members of PCHC, thus they executed them, that a mutual, final
attorney's fees, litigation expenses which held, thus: underwent arbitration proceedings. and definite award upon the
and costs of suit against HBT," on Acting on plaintiff Far East Bank The PCHC has its own Rules of Procedure for Arbitration subject matter submitted to them
page 4 thereof and par. C of its and Trust Company's "Motion To (PCHC Rules). However, this is governed by Republic Act was not made. IEAaST
dispositive portion is amended to Dismiss Petition For Review For No. 876, also known as The Arbitration Law 26 and xxx xxx xxx
read: Lack Of Jurisdiction", considering supplemented by the Rules of Court. 27 Thus, we first SEC. 25. Grounds for modifying or
(c) "Procedings against Home that the petition for review is a thresh out the remedy of petition for review availed of by correcting award. — In any one of
Bankers and Trust Co. are separate and distinct case, the same the petitioner to appeal the order of the Arbitration the following cases, the court must
suspended pending award/decision must comply with all the Committee. make an order modifying or
in the arbitration proceedings requirements for filing initiatory Sections 23, 24 and 29 of The Arbitration Law, and Section correcting the award, upon the
while those against individual pleadings for civil actions before 13 of the PCHC Rules, provide: application of any party to the
defendants be immediately this Court so that since the SEC. 23. Confirmation of award. — controversy which was arbitrated:
reinstated and continued." commencement of the subject At any time within one month after
HBT and Tancuan's separate petition lacks the mandatory the award is made, any party to the (a) Where there was an evident
Motions for Reconsiderations are requirements provided for, except controversy which was miscalculation of figures, or an
hereby denied, for lack of merit. the payment of docket fees, for lack arbitrated may apply to the court evident mistake in the description
SO ORDERED. 11 of jurisdiction, the petition for having jurisdiction, as provided in of any person, thing or property
On February 2, 1998, the PCHC Arbitration Committee review is hereby dismissed. Section 28, for an order referred to in the award; or
rendered its decision in favor of respondent, 12 thus: SO ORDERED. 22 confirming the award; and (b) Where the arbitrators have
IN VIEW OF ALL THE FOREGOING, The RTC denied petitioner's motion for thereupon the court must grant awarded upon a matter not
judgment is hereby rendered in reconsideration, 23 hence, this petition on the sole ground, such order unless the award is submitted to them, not affecting the
favor of the plaintiff and against the to wit: vacated, modified or corrected, merits of the decision upon the
defendant sentencing the latter to THE REGIONAL TRIAL COURT as prescribed herein. Notice of matter submitted; or
pay the plaintiff the sum of P25.2 ERRED IN DISMISSING THE such motion must be served upon (c) Where the award is imperfect in
million as principal. In view of the PETITION OF PETITIONER FOR the adverse party or his attorney as a matter of form not affecting the
fact, however, that this amount was LACK OF JURISDICTION ON THE prescribed by law for the service of merits of the controversy, and if it
split between the plaintiff and the GROUND THAT IT SHOULD HAVE such notice upon an attorney in had been a commissioner's report,
defendant in the course of the BEEN DOCKETED AS A SEPARATE action in the same court. the defect could have been
proceedings, the amount to be paid CASE. 24 SEC. 24. Grounds for vacating amended or disregarded by the
by the defendant to the plaintiff Petitioner contends that Civil Case No. 92-145 was merely award. — In any one of the court.
should only be P12,600,000.00 plus suspended to await the outcome of the arbitration case following cases, the court must The order may modify and correct
interest on this latter amount at the pending before the PCHC. Thus, any petition questioning make an order vacating the award the award so as to effect the intent
rate of 12% per annum from the decision of the Arbitration Committee must be filed in upon the petition of any party to thereof and promote justice
February 11, 1992, the date when Civil Case No. 92-145 and should not be docketed as a the controversy when such party between the parties.
the total amount of P25.2 Million separate action. Likewise, petitioner avers that had it filed a proves affirmatively that in the SEC. 29. Appeals. — An appeal
was split between plaintiff and separate action, "this would have resulted in a multiplicity arbitration proceedings: may be taken from an order made
defendant up to the date of of suits, which is abhorred in procedure." HSDIaC (a) The award was procured by in a proceeding under this Act, or
payment. Meanwhile respondent avers that the RTC correctly corruption, fraud or other undue from judgment entered upon an
In view of the facts found by the dismissed the appeal from the award of private arbitrators means; or award
committee, no attorney's fees nor since there is no statutory basis for such appeal. (b) That there was evident through certiorari proceedings, but
other damages are Respondent argues that petitioner's claim that the parties partiality or corruption in the such appeals shall belimited to
awarded. cAaTED by agreement had conferred on the RTC appellate arbitrators or any of them; or questions of law. The proceedings
SO ORDERED. 13 jurisdiction over decisions of private arbitrators is (c) That the arbitrators were guilty upon such an appeal, including the
The motion for reconsideration filed by petitioner was erroneous because they cannot confer a non-existent of misconduct in refusing to judgment thereon shall be
denied by the Arbitration Committee. 14Consequently, to jurisdiction on the RTC or any court. Furthermore, the postpone the hearing upon governed by the Rules of Court
appeal the decision of the Arbitration Committee in petition for review filed by petitioner violated the rule on sufficient cause shown, or in insofar as they are applicable.
Arbicom Case No. 91-069, petitioner filed a petition for commencing an original action under Section 5, Rule 1, and refusing to hear evidence pertinent AMENDED ARBITRATION RULES
review in the earlier case filed by respondent in Branch the raffle of cases under Section 2, Rule 20 of the Rules of and material to the controversy; OF PROCEDURE OF PCHC
135 of the RTC of Makati and docketed as Civil Case No. Court, when it filed the same in Branch 135 of the RTC of that one or more of the arbitrators Sec. 13. — The findings of facts of
92-145. 15 In an order dated January 20, 1999, the RTC Makati where there was already a pending original was disqualified to act as such the decision or award rendered
directed both petitioner and respondent to file their action, i.e., Civil Case No. 92-145. under section nine hereof, and by the Arbitration Committee or
respective memoranda, after which, said petition would be The petition lacks merit. willfully refrained from disclosing by the sole Arbitrator as the case
deemed submitted for resolution. 16 The Philippine Clearing House Corporation was created to such disqualification or of any may be shall be final and
Both parties filed several pleadings. On February 8, 1999, facilitate the clearing of checks of member banks. Among other misbehavior by which the conclusive upon all the parties in
respondent filed a Motion to Dismiss Petition for Review these member banks exists a compromissoire, 25 or an said arbitration dispute. The
decision or award of the agency, the petition should be filed in and cognizable only proceedings are mainly governed bythe Arbitration wrote the Board of Directors of Tahanan Village
Arbitration Committee or of the by the Court of Appeals. 36 Law and suppletorily by the Rules of Court. Homeowner's Association requesting for the cancellation of
Sole Arbitrator or of the Board of In this instance, petitioner did not avail of any of the WHEREFORE, in light of the foregoing, the petition is the contractor's work permit. EHITaS
Directors, as the case may be, shall abovementioned remedies available to it. Instead it filed a DENIED. The November 9, 1999 Order of the Regional Trial Thus, on May 26, 2003, petitioner filed a complaint for
be appealable only on questions petition for review with the RTC where Civil Case No. 92- Court of Makati City, Branch 135, in Civil Case No. 92-145 Accounting, Collection of Sum of Money, Rescission of
of law to any of the Regional 145 is pending pursuant to Section 13 of the PCHC Rules to which dismissed the petition for review for lack of Contract with Damages against spouses Esquig and
Trial Courts in the National sustain its action. Clearly, it erred in the procedure it chose jurisdiction and the February 1, 2000 Order denying its Rosemarie Papas with the Regional Trial Court of
Capital Region where the Head for judicial review of the arbitral award. reconsideration, are AFFIRMED. Muntinlupa City which was docketed as Civil Case No. 03-
Office of any of the parties is Having established that petitioner failed to avail of the SO ORDERED. 110. In the complaint, petitioner prayed that an accounting
located. The appellant shall perfect abovementioned remedies, we now discuss the issue of the ||| (Insular Savings Bank v. Far East Bank & Trust Co., G.R. be rendered to determine the cost of the materials
his appeal by filing a notice of jurisdiction of the trial court with respect to the petition for No. 141818, [June 22, 2006], 525 PHIL 238-251) purchased by Papas; that respondents be ordered to pay
appeal to the Arbitration review filed by petitioner. the cost of the additional works done on the property; that
Secretariat and filing a Petition Jurisdiction is the authority to hear and determine a cause FIRST DIVISION the Design-Build Construction Agreement be ordered
with the Regional Trial Court of the — the right to act in a case. 37 Jurisdiction over the subject [G.R. No. 168384. August 7, 2006.] rescinded because respondents breached the same; and
National Capital Region for the matter is the power to hear and determine the general class CHARLES BERNARD that respondents be ordered to pay moral and exemplary
review of the decision or award of to which the proceedings in question belong. Jurisdiction H. REYES doing business under damages and litigation expenses.
the committee or sole arbitrator or over the subject matter is conferred by law and not by the the name and style On July 15, 2003, respondents filed a motion to dismiss
of the Board of Directors, as the consent or acquiescence of any or all of the parties or by CBH REYESARCHITECTS, petitione Civil Case No. 03-110 on the ground that the court has no
case may be, within a non- erroneous belief of the court that it exists. 38 r, vs. ANTONIO YULO BALDE II, jurisdiction over the subject matter of the case. They
extendible period of fifteen (15) In the instant case, petitioner and respondent have agreed PAULINO M. NOTO and ERNESTO J. claimed that the Design-Build Construction Agreement
days from and after its receipt of that the PCHC Rules would govern in case of controversy. BATTAD, SR., in their capacities as contained an arbitration clause, thus any dispute arising
the order denying or granting said However, since the PCHC Rules came about only as a result Arbitrators of the CONSTRUCTION therefrom should be brought before the CIAC.
motion for reconsideration or new of an agreement between and among member banks of INDUSTRY ARBITRATION On even date, respondents also filed a complaint before the
trial had been filed, within a non- PCHC and not by law, it cannot confer jurisdiction to the COMMISSION, SPOUSES CESAR CIAC against the petitioner, docketed as CIAC Case No. 13-
extendible period of fifteen (15) RTC. Thus, the portion of the PCHC Rules granting and CARMELITA ESQUIG and 2003. Respondents alleged that petitioner unreasonably
days from and after its receipt of jurisdiction to the RTC to review arbitral awards, only on ROSEMARIE PAPAS, respondents. delayed the construction and refused to finish the project.
the order denying or granting said questions of law, cannot be given effect. HTDcCE DECISION Thus, they prayed that petitioner be ordered to finish the
motion for reconsideration or of Consequently, the proper recourse of petitioner from the YNARES-SANTIAGO, J p: project or, in the alternative, to pay the cost to finish the
the decision rendered after the new denial of its motion for reconsideration by the Arbitration This Petition for Review on Certiorari under Rule 45 of the same; to reimburse the overpayments made by
trial if one had been Committee is to file either a motion to vacate the arbitral Rules of Court assails the Decision 1 of the Court of Appeals respondents; and to pay liquidated damages, attorney's
granted. DEScaT award with the RTC, a petition for review with the Court of dated February 18, 2005, which sustained the fees and costs of the suit.
xxx xxx xxx (Emphasis supplied) Appeals under Rule 43 of the Rules of Court, or a petition Order 2 dated April 23, 2004 of the Arbitral Tribunal3 of Instead of submitting an answer, petitioner filed with the
As provided in the PCHC Rules, the findings of facts of the for certiorari under Rule 65 of the Rules of Court. In the the Construction Industry Arbitration Commission (CIAC), CIAC a motion to dismiss 7 on grounds of lack of
decision or award rendered by the Arbitration Committee case at bar, petitioner filed a petition for review with the denying petitioner's Motion to Terminate Proceedings and jurisdiction to hear and decide the case as well as the
shall be final and conclusive upon all the parties in said RTC when the same should have been filed with the Court its Resolution 4 dated May 20, 2005 denying petitioner's pendency of the case before the trial court involving the
arbitration dispute. 28 Under Article 204429 of the New of Appeals under Rule 43 of the Rules of Court. Thus, the motion for reconsideration. same subject matter.
Civil Code, the validity of any stipulation on the finality of RTC of Makati did not err in dismissing the petition for The facts of the case are as follows: In an Order dated October 17, 2003, CIAC denied
the arbitrators' award or decision is recognized. However, review for lack of jurisdiction but not on the ground that On October 20, 2002, respondent-spouses Cesar and petitioner's motion to dismiss, holding that since the
where the conditions described in Articles petitioner should have filed a separate case from Civil Case Carmelita Esquig entered into a Design-Build Construction Design-Build Construction Agreement contained an
2038, 30 2039 31 and 2040 32 applicable to both No. 92-145 but on the necessity of filing the correct petition Agreement 5 with petitioner Charles Bernard H. Reyes, arbitration clause, any dispute arising from said contract is
compromises and arbitrations are obtaining, the in the proper court. It is immaterial whether petitioner doing business under the name and style of within CIAC's jurisdiction.
arbitrators' award may be annulled or filed the petition for review in Civil Case No. 92-145 as an CBH Reyes Architects, for the architectural design and Petitioner filed a motion for reconsideration which was
rescinded. 33Consequently, the decision of the Arbitration appeal of the arbitral award or whether it filed a separate construction of a 2-storey residence in Tahanan Village, denied by CIAC in its Order dated November 27, 2003.
Committee is subject to judicial review. case in the RTC, considering that the RTC will only have Paranaque City. Thus, petitioner filed his Answer Ad Cautelam. Thereafter,
Furthermore, petitioner had several judicial remedies jurisdiction over an arbitral award in cases of motions to In accordance with the contract, spouses Esquig paid the CIAC constituted the Arbitral Tribunal and directed the
available at its disposal after the Arbitration Committee vacate the same. Otherwise, as elucidated herein, the Court amount of P1,050,000 as down payment. 6Thereafter, same to carry on with the arbitration proceedings in
denied its Motion for Reconsideration. It may petition the of Appeals retains jurisdiction in petitions for review or in construction commenced. accordance with CIAC Rules. CDEaAI
proper RTC to issue an order vacating the award on the petitions for certiorari. Consequently, petitioner's The relationship between petitioner and respondent Meanwhile, on February 27, 2004, the Regional Trial Court
grounds provided for under Section 24 of the Arbitration arguments, with respect to the filing of separate action spouses went on smoothly until sometime in January 2003 of Muntinlupa City, Branch 203 issued an Order 8denying
Law. 34 Petitioner likewise has the option to file a petition from Civil Case No. 92-145 resulting in a multiplicity of when the latter left for the United States and designated the motion to dismiss filed by respondents. The trial court
for review under Rule 43 of the Rules of Court with the suits, cannot be given due course. their co-respondent, Rosemarie Papas, as their held that it has jurisdiction over the complaint for
Court of Appeals on questions of fact, of law, or mixed Alternative dispute resolution methods or ADRs — like representative. According to petitioner, Papas meddled accounting, rescission of contract and damages. Petitioner
questions of fact and law. 35 Lastly, petitioner may file a arbitration, mediation, negotiation and conciliation — are with the construction works by demanding changes and then filed with the CIAC a motion to terminate proceedings
petition for certiorari under Rule 65 of the Rules of Court encouraged by the Supreme Court. By enabling parties to additional works which entailed additional cost. Papas also but the same was denied 9 in an Order dated April 23,
on the ground that the Arbitrator Committee acted without resolve their disputes amicably, they provide solutions that refused to pay petitioner's progress billing and the salary of 2004.
or in excess of its jurisdiction or with grave abuse of are less time-consuming, less tedious, less confrontational, the laborers. Petitioner thereafter prepared an accounting Thus, petitioner filed a petition for certiorari and
discretion amounting to lack or excess of jurisdiction. Since and more productive of goodwill and lasting report of all the additional works and their corresponding prohibition before the Court of Appeals which was
this case involves acts or omissions of a quasi-judicial relationships. 39 It must be borne in mind that arbitration costs, however, Papas denied all the items in the list and docketed as CA-G.R. SP No. 83816. On February 18, 2005,
refused to pay the same. Worse, on May 8, 2003, Papas the Court of Appeals rendered the assailed Decision
dismissing the petition for lack of merit. It held that CIAC Philippines, whether the dispute We agree with the findings of the Court of Appeals that the 2005 17 in Civil Case No. 03-110 in favor of herein
properly acquired jurisdiction over the subject property. arises before or after the Design-Build Construction Agreement mutually entered petitioner, the dispositive portion of which reads:
Petitioner's motion for reconsideration was denied hence completion of the contract, or after into by the parties contain an arbitration clause, to wit: WHEREFORE, judgment is
this petition raising the following issues: the abandonment or breach ARTICLE 10. ARBITRATION. rendered declaring a rescission of
I thereof. These disputes may All questions in dispute under the the Design Build Construction
THE COURT OF APPEALS ERRED involve government or private Agreement shall be submitted in Agreement dated 20 October 2002;
WHEN IT RULED THAT contracts. For the Board to acquire accordance with the provisions of ordering defendants to render an
PETITIONER AGREED TO HAVE jurisdiction, the parties to a dispute Philippine Law on Arbitration and accounting of all the construction
THE CASE SUBMITTED FOR must agree to submit the same to provided for in Article 2042 of the materials they bought for the
VOLUNTARY ARBITRATION. voluntary arbitration. New Civil Code of the Philippines construction of the project subject
II The jurisdiction of the CIAC may and the provisions of Republic Act matter of the present case; further
EVEN ASSUMING ARGUENDO include but is not limited to No. 876. ordering defendants, jointly and
THAT PETITIONER AGREED TO violation of specifications for Clearly, the presence of the arbitration clause in the parties' severally, to pay plaintiff as follows:
HAVE THE PRESENT CASE materials and workmanship; contract vests jurisdiction on the CIAC on all controversies a. P840,300.00
SUBMITTED FOR ARBITRATION, violation of the terms of agreement; arising from such contract. The arbitral clause in the representing
THE COURT OF APPEALS ERRED IN interpretation and/or application agreement is a commitment by the parties to submit to cost of
HOLDING THAT THE CIAC MAY of contractual provisions; amount arbitration the disputes covered therein. Because that additional
TAKE COGNIZANCE OF THE of damages and penalties; clause is binding, they are expected to abide by it in good works and
PRESENT CASE CONSIDERING commencement time and delays; faith. 14 Where the jurisdiction of CIAC is properly changes in the
THAT THE PRESENT CASE maintenance and defects; payment invoked, the failure or refusal of herein petitioner to project plus
INVOLVED ISSUES WHICH ARE default of employer or contractor arbitrate shall not affect the proceedings. Arbitration legal interest
OUTSIDE ITS JURISDICTION. and changes in contract cost. proceedings shall continue notwithstanding the absence or until fully
III Excluded from the coverage of this lack of participation of petitioner, and the award shall be paid;
THE COURT OF APPEALS ERRED IN law are disputes arising from made after receiving the evidence of the claimant. 15 b. P296,658.85
NOT HOLDING THAT ANY employer-employee relationships representing
PROCEEDING IN THE CIAC MUST which shall continue to be covered With respect to petitioner's contention that the action is balance of the
BE TERMINATED SINCE THE RTC by the Labor Code of the purely civil in nature hence, jurisdiction rests with the contract price
ALREADY ASSUMED JURISDICTION Philippines. Regional Trial Court, the same must fail. Since the action is plus legal
OVER THE SUBJECT In the case of Philrock, Inc. v. Construction Industry rooted on alleged violations of the agreement, it is interest until
CONTROVERSY AND HAD NOT Arbitration Commission, 13 the Court has ruled that CIAC embraced by the term "construction dispute". As CIAC aptly fully paid;
RELINQUISHED THE SAME TO has original and exclusive jurisdiction over disputes arising ruled: DIEAHc c. P500,000.00 as and by
CIAC. 10 from or connected with construction contracts entered into As regards Respondent's assertion way of moral
The primordial issue in the instant case is, which body has by parties that have agreed to submit their dispute to that the claims in the civil case are damages;
jurisdiction over the present controversy — the Regional voluntary arbitration. not arbitrable, this Commission d. P500,000.00 as and by
Trial Court or the CIAC? Section 1, Article III of the CIAC Rules of Procedure again begs to digress. A cursory way of
Petitioner contends that the CIAC has no jurisdiction to Governing Construction Arbitration likewise provides that perusal of the claims in civil case exemplary
entertain the case because it is purely civil in nature and recourse to the CIAC may be availed of whenever a contract would show that such fall within damages;
does not involve construction dispute nor require the contains a clause for the submission of a future controversy the scope of CIAC jurisdiction, to e. P500,000.00 as and by
resolution of highly technical issues. Moreover, petitioner to arbitration, thus: wit: (1) accounting of all payments way of
alleges that the trial court acquired jurisdiction prior to the SECTION 1. Submission to CIAC made for the purchase of attorney's
CIAC since petitioner's complaint was filed earlier thus, Jurisdiction. — An arbitration construction materials; (2) cost of fees;
rendering the arbitration clause moot, unenforceable and clause in a construction contract additional work; (3) balance on the f. Cost of suit.
revocable. IADaSE or a submission to arbitration of contract price; (4) interest; (5) SO ORDERED. 18
The petition lacks merit. a construction dispute shall be rescission of contract; (6) moral On June 29, 2006, the presiding judge ordered the
Executive Order (EO) No. 1008 entitled, "Construction deemed an agreement to submit damages; (7) exemplary damages; designated sheriff to implement the writ of execution dated
Industry Arbitration Law" 11 provided for an arbitration an existing or future controversy and (8) cost of suit. 16 May 17, 2006. Consequently, Sheriff Melvin T. Bagabaldo
mechanism for the speedy resolution of construction to CIAC jurisdiction, Besides, Section 23 of E.O. No. 1008 expressly provides that levied on the personal properties of respondent Papas.
disputes other than by court litigation. It recognized the notwithstanding the reference to a all provisions of existing laws, proclamations, decrees, Hence, respondents' manifestation with prayer for the
role of the construction industry in the country's economic different arbitration institution or letters of instructions and executive orders contrary to or issuance of a temporary restraining order (TRO). ISHCcT
progress as it utilizes a large segment of the labor force and arbitral body in such contract or inconsistent with E.O. No. 1008 are repealed or modified In the Resolution dated July 12, 2006, we issued a TRO
contributes substantially to the gross national product of submission. When a contract accordingly. E.O. No. 1008 which vests jurisdiction to the enjoining the Presiding Judge of Regional Trial Court of
the country. 12 contains a clause for the CIAC over construction disputes is a special law; hence, it Muntinlupa City, Branch 203, from continuing with any of
Section 4 of E.O. No. 1008 provides: submission of a future controversy takes precedence over Batas Pambansa Blg. 129 or the proceedings in Civil Case No. 03-110 and from
SECTION 4. Jurisdiction. — The to arbitration, it is not necessary for the Judiciary Reorganization Act of 1980, a general law enforcing the Order dated June 29, 2006 ordering the
CIAC shall have original and the parties to enter into a which vests jurisdiction to the Regional Trial Courts over sheriff to implement the writ.
exclusive jurisdiction over disputes submission agreement before the civil actions in which the subject of the litigation is Thus, considering our findings that the CIAC and not the
arising from, or connected with, claimant may invoke the incapable of pecuniary estimation. RTC which has jurisdiction over the instant controversy,
contracts entered into by parties jurisdiction of CIAC. (Emphasis Meanwhile, it appears that the Regional Trial Court of the injunction against the Presiding Judge of the Regional
involved in construction in the supplied) Muntinlupa City, Branch 203 rendered judgment on July 29, Trial Court of Muntinlupa City, Branch 203 from further
proceeding with Civil Case No. 03-110 must be made respondent for collection of sum of money with the incurred by respondent in the take-over be set off against On February 22, 1983, Petitioner LM Power Engineering
permanent. All the proceedings therein are declared null RTC. The RTC subsequently ordered the respondent the amounts it owed petitioner? (3) How much were the Corporation and Respondent Capitol Industrial
and void for lack of jurisdiction. The designated sheriff is to give full payment for the work completed by advances and billable accomplishments? The resolution of Construction Groups Inc. entered into a "Subcontract
enjoined from proceeding with the sale of the levied petitioner. The CA, however, reversed the decision, the foregoing issues lies in the interpretation of the Agreement" involving electrical work at the Third Port of
personal properties and is ordered to return the same to and ordered the parties to present their dispute to provisions of the Agreement. . . . The instant case involves Zamboanga. 5
respondents. Accordingly, Civil Case No. 03-110 must be arbitration in accordance with the arbitral clause technical discrepancies that are better left to an arbitral On April 25, 1985, respondent took over some of the work
dismissed on the ground of lack of jurisdiction. provided in their subcontract agreement. body that has expertise in those areas. contracted to petitioner. 6 Allegedly, the latter had failed to
It bears to stress that being an inexpensive, speedy and The Supreme Court affirmed the CA 3.ID.; ID.; ID.; CONSTRUCTION INDUSTRY ARBITRATION finish it because of its inability to procure materials. 7
amicable method of settling disputes, arbitration — along decision, ruling: that any doubt should be resolved in COMMISSION (CIAC); HAS JURISDICTION TO DECIDE A Upon completing its task under the Contract, petitioner
with mediation, conciliation and negotiation — is favor of arbitration because aside from unclogging CONSTRUCTION DISPUTE WHEN CONSTRUCTION billed respondent in the amount of
encouraged by the Supreme Court. Aside from unclogging judicial dockets, arbitration also hastens the CONTRACT HAS AN ARBITRAL CLAUSE; CASE AT BAR. — P6,711,813.90. 8Contesting the accuracy of the amount of
judicial dockets, arbitration also hastens the resolution of resolution of disputes; that the instant case involves Section 1 of Article II of the old Rules of Procedure advances and billable accomplishments listed by the
disputes, especially of the commercial kind. It is thus technical discrepancies in the application of their Governing Construction Arbitration indeed required the former, the latter refused to pay. Respondent also took
regarded as the "wave of the future" in international civil agreement that are better left to an arbitral body that submission of a request for arbitration. . . On the other refuge in the termination clause of the Agreement. 9 That
and commercial disputes. Brushing aside a contractual has expertise in those areas; that under Sec. 1 Art. III hand, Section 1 of Article III of the newRules of Procedure clause allowed it to set off the cost of the work that
agreement calling for arbitration between the parties of the new Rules of Procedure, there is no more need Governing Construction Arbitration has dispensed with this petitioner had failed to undertake — due to termination or
would be a step backward. 19 to file a request with the Construction Industry requirement and recourse to the CIAC may now be availed take-over — against the amount it owed the latter.
WHEREFORE, in view of the foregoing, the instant petition Arbitration Commission (CIAC) in order to vest it with of whenever a contract "contains a clause for the Because of the dispute, petitioner filed with the Regional
is DENIED. The Decision of the Court of Appeals dated jurisdiction to decide a construction dispute. As long submission of a future controversy to arbitration,". . . Trial Court (RTC) of Makati (Branch 141) a
February 18, 2005 in CA-G.R. SP No. 83816 which sustained as the parties agree to submit to voluntary arbitration, Clearly, there is no more need to file a request with the Complaint 10 for the collection of the amount representing
the Order of the Arbitral Tribunal of the Construction regardless of what forum they may choose, they may CIAC in order to vest it with jurisdiction to decide a the alleged balance due it under the Subcontract. Instead of
Industry Arbitration Commission dated April 23, 2004 invoke the CIAC jurisdiction; that parties are expected construction dispute. submitting an Answer, respondent filed a Motion to
denying petitioner's Motion to Terminate Proceedings, and to abide by the arbitral clause in the agreement in 4.ID.; ID.; ID.; PARTIES ARE EXPECTED TO ABIDE BY THE Dismiss, 11 alleging that the Complaint was premature,
its Resolution dated May 20, 2005 denying petitioner's good faith; and that since petitioner has already filed a ARBITRAL CLAUSE IN GOOD FAITH; CASE AT BAR. — The because there was no prior recourse to arbitration.
motion for reconsideration, are AFFIRMED. The Presiding complaint with the RTC without prior recourse to arbitral clause in the Agreement is a commitment on the In its Order 12 dated September 15, 1987, the RTC denied
Judge of the Regional Trial Court of Muntinlupa City, arbitration, the proper procedure is to request the part of the parties to submit to arbitration the disputes the Motion on the ground that the dispute did not involve
Branch 203 is PERMANENTLY ENJOINED from proceeding suspension of such action as provided under RA covered therein. Because that clause is binding, they are the interpretation or the implementation of the Agreement
with Civil Case No. 03-110 and all the proceedings therein 876(the Arbitration Law) to enable the CIAC to decide expected to abide by it in good faith. And because it covers and was, therefore, not covered by the arbitral clause. 13
are DECLARED NULL AND VOID. Sheriff Melvin T. on the dispute. the dispute between the parties in the present case, either After trial on the merits, the RTC 14 ruled that the take-
Bagabaldo is ENJOINED from proceeding with the sale of SYLLABUS of them may compel the other to arbitrate. Since petitioner over of some work items by respondent was not equivalent
the levied personal properties and is ORDERED to return 1.LABOR AND SOCIAL LEGISLATION; LABOR RELATIONS; has already filed a Complaint with the RTC without prior to a termination, but a mere modification, of the
them to the respondents. The Presiding Judge of the VOLUNTARY ARBITRATION; ARBITRATION CLAUSES recourse to arbitration, the proper procedure to enable the Subcontract. The latter was ordered to give full payment
Regional Trial Court of Muntinlupa City, Branch 203 is SHOULD BE LIBERALLY CONSTRUED. — Being an CIAC to decide on the dispute is to request the stay or for the work completed by petitioner.
further DIRECTED to dismiss Civil Case No. 03-110 for lack inexpensive, speedy and amicable method of settling suspension of such action, as provided under RA 876 [the Ruling of the Court of Appeals
of jurisdiction. disputes, arbitration — along with mediation, conciliation Arbitration Law]. On appeal, the CA reversed the RTC and ordered the
SO ORDERED. and negotiation — is encouraged by the Supreme Court. DECISION referral of the case to arbitration. The appellate court held
||| (Reyes v. Balde II, G.R. No. 168384, [August 7, 2006]) Aside from unclogging judicial dockets, arbitration also PANGANIBAN, J p: as arbitrable the issue of whether respondent's take-over
hastens the resolution of disputes, especially of the Alternative dispute resolution methods or ADRs — like of some work items had been intended to be a termination
THIRD DIVISION commercial kind. It is thus regarded as the "wave of the arbitration, mediation, negotiation and conciliation — are of the original contract under Letter "K" of the Subcontract.
[G.R. No. 141833. March 26, 2003.] future" in international civil and commercial disputes. encouraged by the Supreme Court. By enabling parties to It ruled likewise on two other issues: whether petitioner
LM POWER ENGINEERING Brushing aside a contractual agreement calling for resolve their disputes amicably, they provide solutions that was liable under the warranty clause of the Agreement, and
CORPORATION, petitioner, vs. arbitration between the parties would be a step backward. are less time-consuming, less tedious, less confrontational, whether it should reimburse respondent for the work the
CAPITOL INDUSTRIAL Consistent with the above-mentioned policy of encouraging and more productive of goodwill and lasting latter had taken over. 15
CONSTRUCTION GROUPS, alternative dispute resolution methods, courts should relationships. 1 Hence, this Petition. 16
INC., respondent. liberally construe arbitration clauses. Provided such clause The Case The Issues
E.G. Ferry Law Offices for petitioner. is susceptible of an interpretation that covers the asserted Before us is a Petition for Review on Certiorari 2 under In its Memorandum, petitioner raises the following issues
Catindig Tiongko & Nibungco for private respondent. dispute, an order to arbitrate should be granted. Any doubt Rule 45 of the Rules of Court, seeking to set aside the for the Court's consideration:
SYNOPSIS should be resolved in favor of arbitration. AHcCDI January 28, 2000 Decision of the Court of Appeals 3 (CA) in "A
Petitioner LM Power Engineering 2.ID.; ID.; ID.; ID.; RESOLUTION OF TECHNICAL CA-GR CV No. 54232. The dispositive portion of the Whether or not there exist[s] a
Corporation and respondent Capitol Industrial DISCREPANCIES ARE BETTER LEFT TO AN ARBITRAL Decision reads as follows: controversy/dispute between
Construction Groups, Inc. entered into a subcontract BODY; CASE AT BAR. — Clearly, the resolution of the "WHEREFORE, the judgment petitioner and respondent
agreement involving electrical work at the Third Port dispute between the parties herein requires a referral to appealed from is REVERSED and regarding the interpretation and
of Zamboanga. the provisions of their Agreement. Within the scope of the SET ASIDE. The parties are implementation of the Sub-Contract
Due to petitioner's failure to complete the arbitration clause are discrepancies as to the amount of ORDERED to present their dispute Agreement dated February 22,
work on schedule, respondent took over some of advances and billable accomplishments, the application of to arbitration in accordance with 1983 that requires prior recourse
petitioner's work items. Thus, when petitioner the provision on termination, and the consequent set-off of their Sub-contract Agreement. The to voluntary arbitration;
completed its task under the contract, respondent expenses. A review of the factual allegations of the parties surety bond posted by "B
refused to pay petitioner's billings, and contested the reveals that they differ on the following questions: (1) Did a [respondent] is [d]ischarged." 4 In the affirmative, whether or not
billable accomplishments. The petitioner sued the take-over/termination occur? (2) May the expenses The Facts the requirements provided in
Article III [1] of CIAC Arbitration in violation of the provision in the Agreement as to time letters of credit, and taxes and duties as set forth in the arbitration also hastens the resolution of disputes,
Rules regarding request for schedule: Agreement. These data can be gathered from a review of especially of the commercial kind. 25 It is thus regarded as
arbitration ha[ve] been complied "G.TIME SCHEDULE the Agreement, pertinent portions of which are reproduced the "wave of the future" in international civil and
with[.]" 17 "[Petitioner] shall adhere strictly to hereunder: commercial disputes. 26 Brushing aside a contractual
The Court's Ruling the schedule related to the WORK "C.CONTRACT PRICE AND TERMS agreement calling for arbitration between the parties
The Petition is unmeritorious. and complete the WORK within the OF PAYMENT would be a step backward. 27
First Issue: period set forth in Annex C hereof. xxx xxx xxx Consistent with the above-mentioned policy of encouraging
Whether Dispute Is Arbitrable NO time extension shall be granted "All progress payments to be made alternative dispute resolution methods, courts should
Petitioner claims that there is no conflict regarding the by [respondent] to [petitioner] by [respondent] to [petitioner] liberally construe arbitration clauses. Provided such clause
interpretation or the implementation of the Agreement. unless a corresponding time shall be subject to a retention sum is susceptible of an interpretation that covers the asserted
Thus, without having to resort to prior arbitration, it is extension is granted by [the of ten percent (10%) of the value of dispute, an order to arbitrate should be granted. 28 Any
entitled to collect the value of the services it rendered Ministry of Public Works and the approved quantities. Any claims doubt should be resolved in favor of arbitration. 29
through an ordinary action for the collection of a sum of Highways] to the by [respondent] on [petitioner] Second Issue:
money from respondent. On the other hand, the latter CONSORTIUM." 20 may be deducted by [respondent] Prior Request for Arbitration
contends that there is a need for prior arbitration as Because of the delay, respondent alleges that it took over from the progress payments and/or According to petitioner, assuming arguendo that the
provided in the Agreement. This is because there are some some of the work contracted to petitioner, pursuant to the retained amount. Any excess from dispute is arbitrable, the failure to file a formal request for
disparities between the parties' positions regarding the following provision in the Agreement: the retained amount after arbitration with the Construction Industry Arbitration
extent of the work done, the amount of advances and "K.TERMINATION OF AGREEMENT deducting [respondent's] claims Commission (CIAC) precluded the latter from acquiring
billable accomplishments, and the set off of expenses "[Respondent] has the right to shall be released by [respondent] to jurisdiction over the question. To bolster its position,
incurred by respondent in its take-over of petitioner's terminate and/or take over this [petitioner] after the issuance of petitioner even cites our ruling in Tesco Services
work. TAIDHa Agreement for any of the following [the Ministry of Public Works and Incorporated v. Vera. 30 We are not persuaded.
causes: Highways] of the Certificate of Section 1 of Article II of the old Rules of Procedure
We side with respondent. Essentially, the dispute arose xxx xxx xxx Completion and final acceptance of Governing Construction Arbitration indeed required the
from the parties' incongruent positions on whether certain '6.If despite previous the WORK by [the Ministry of submission of a request for arbitration, as follows:
provisions of their Agreement could be applied to the facts. warnings by Public Works and Highways]. "SECTION 1.Submission to
The instant case involves technical discrepancies that are [respondent], xxx xxx xxx Arbitration — Any party to a
better left to an arbitral body that has expertise in those [petitioner] does not "D.IMPORTED MATERIALS AND construction contract wishing to
areas. In any event, the inclusion of an arbitration clause in execute the WORK in EQUIPMENT have recourse to arbitration by the
a contract does not ipso facto divest the courts of accordance with this "[Respondent shall open the letters Construction Industry Arbitration
jurisdiction to pass upon the findings of arbitral bodies, Agreement, of credit for the importation of Commission (CIAC) shall submit its
because the awards are still judicially reviewable under or persistently or equipment and materials listed in Request for Arbitration in sufficient
certain conditions. 18 flagrantly neglects to Annex E hereof after the drawings, copies to the Secretariat of the
In the case before us, the Subcontract has the following carry out [its] obligations brochures, and other technical data CIAC; PROVIDED, that in the case of
arbitral clause: under this of each items in the list have been government construction contracts,
"6.The Parties hereto agree that any Agreement." 21 formally approved by [the Ministry all administrative remedies
dispute or conflict as regards to Supposedly, as a result of the "take-over," respondent of Public Works and Highways]. available to the parties must have
interpretation and implementation incurred expenses in excess of the contracted price. It However, petitioner will still be been exhausted within 90 days
of this Agreement which cannot be sought to set off those expenses against the amount fully responsible for all imported from the time the dispute arose."
settled between [respondent] and claimed by petitioner for the work the latter accomplished, materials and equipment. Tesco was promulgated by this Court, using the foregoing
[petitioner] amicably shall be pursuant to the following provision: "All expenses incurred by provision as reference.
settled by means of arbitration . . "If the total direct and indirect cost [respondent], both in foreign and On the other hand, Section 1 of Article III of the new Rules
." 19 of completing the remaining part of local currencies in connection with of Procedure Governing Construction Arbitration has
Clearly, the resolution of the dispute between the parties the WORK exceed the sum which the opening of the letters of credit dispensed with this requirement and recourse to the CIAC
herein requires a referral to the provisions of their would have been payable to shall be deducted from the Contract may now be availed of whenever a contract "contains a
Agreement. Within the scope of the arbitration clause are [petitioner] had it completed the Prices. clause for the submission of a future controversy to
discrepancies as to the amount of advances and billable WORK, the amount of such excess xxx xxx xxx arbitration," in this wise:
accomplishments, the application of the provision on [may be] claimed by [respondent] "N.OTHER CONDITIONS "SECTION 1.Submission to CIAC
termination, and the consequent set-off of expenses. from either of the following: xxx xxx xxx Jurisdiction — An arbitration clause
A review of the factual allegations of the parties reveals '1.Any amount due [petitioner] "2.All customs duties, import in a construction contract or a
that they differ on the following questions: (1) Did a take- from [respondent] at the time of duties, contractor's taxes, income submission to arbitration of a
over/termination occur? (2) May the expenses incurred by the termination of this taxes, and other taxes that may be construction dispute shall be
respondent in the take-over be set off against the amounts Agreement." 22 required by any government deemed an agreement to submit an
it owed petitioner? (3) How much were the advances and The issue as to the correct amount of petitioner's advances agencies in connection with this existing or future controversy to
billable accomplishments? and billable accomplishments involves an evaluation of the Agreement shall be for the sole CIAC jurisdiction, notwithstanding
The resolution of the foregoing issues lies in the manner in which the parties completed the work, the account of [petitioner]." 23 the reference to a different
interpretation of the provisions of the Agreement. extent to which they did it, and the expenses each of them Being an inexpensive, speedy and amicable method of arbitration institution or arbitral
According to respondent, the take-over was caused by incurred in connection therewith. Arbitrators also need to settling disputes, 24 arbitration — along with mediation, body in such contract or
petitioner's delay in completing the work. Such delay was look into the computation of foreign and local costs of conciliation and negotiation — is encouraged by the submission. When a contract
materials, foreign and local advances, retention fees and Supreme Court. Aside from unclogging judicial dockets, contains a clause for the
submission of a future controversy SO ORDERED. "Reasonableness" is a relative term and it depends on the other and which, when connected, show the parties, subject
to arbitration, it is not necessary for ||| (LM Power Engineering Corp. v. Capitol Industrial attendant circumstances. Hence, a period of one month matter, terms and consideration, as in contracts entered
the parties to enter into a Construction Groups Inc., G.R. No. 141833, [March 26, 2003], from the time the parties held a conference to the time the into by correspondence. A contract may be encompassed in
submission agreement before the 447 PHIL 705-717) party invoked the arbitration clause is reasonable. several instruments even though every instrument it not
claimant may invoke the Republic Act No. 876 (Arbitration Law) merely suspends signed by the parties, since it is sufficient if the unsigned
jurisdiction of CIAC." THIRD DIVISION proceedings and does not divest courts of its jurisdiction. instruments are clearly identified or referred to and made
The foregoing amendments in the Rules were formalized [G.R. No. 120105. March 27, 1998.] After arbitration, the lower court may confirm the award part of the signed instrument or instruments. Similarly, a
by CIAC Resolution Nos. 2-91 and 3-93. 31 BF CORPORATION, petitioner, vs. made by the arbitrator. aHSCcE written agreement of which there are two copies, one
The difference in the two provisions was clearly explained COURT OF APPEALS, SHANGRI-LA SYLLABUS signed by each of the parties, is binding on both to the same
in China Chang Jiang Energy Corporation (Philippines) v. PROPERTIES, INC., RUFO B. 1. REMEDIAL LAW; SPECIAL CIVIL ACTIONS; CERTIORARI; extent as though there had been only one copy of the
Rosal Infrastructure Builders et al. 32 (an extended COLAYCO, ALFREDO C. RAMOS, NOT A SUBSTITUTE OF APPEAL. — The rule that the agreement and both had signed it.
unsigned Resolution) and reiterated inNational Irrigation MAXIMO G. LICAUCO III and special civil action of certiorari may not be invoked as a 7. ID.; ID.; ARBITRATION AGREEMENT; "REASONABLE
Administration v. Court of Appeals, 33 from which we quote BENJAMIN C. RAMOS,respondents. substitute for the remedy of appeal. TIME" WITHIN WHICH THE PARTIES MAY AVAIL OF THE
thus: Ponce Enrile Reyes and Manalastas for petitioner. 2. ID.; ID.; ID.; WILL NOT BE USED TO CORRECT RELIEF, CONSTRUED; ONE-MONTH PERIOD FROM TIME
"Under the present Rules of Sunico, Malabanan and Associates, Law Offices for private ERRONEOUS CONCLUSIONS OF LAW OR FACT. — The OF CONFERENCE, REASONABLE. — The arbitration clause
Procedure, for a particular respondents. Court has likewise ruled that "certiorari will not be issued provides for a "reasonable time" within which the parties
construction contract to fall within Quisumbing Torres and Evangelista for private respondents. to cure errors in proceedings or correct erroneous may avail, of the relief under that clause. "Reasonableness"
the jurisdiction of CIAC, it is merely SYNOPSIS conclusions of law or fact. As long as a court acts within its is a relative term and the question of whether the time
required that the parties agree to Petitioner BF Corporation and respondent Shangri-la jurisdiction, any alleged errors committed in the exercise of within which an act has to be done is reasonable depends
submit the same to voluntary Properties, Inc. (SPI) executed an Article of Agreement for its jurisdiction will amount to nothing more than errors of on attendant circumstances. This Court finds that under the
arbitration Unlike in the original the construction of a shopping mall complex. Delay judgment which are reviewable by timely appeal, and not circumstances obtaining in this case, a one-month period
version of Section 1, as applied in occurred in the construction of the mall and caused by a special civil action of certiorari." However, the question from the time the parties held a conference on July 12,
the Tesco case, the law as it now disagreements between the parties regarding their of jurisdiction, which is a question of law defends on the 1993 until private respondent SPI notified petitioner that it
stands does not provide that the respective liabilities. The parties held a conference but determination of the existence of the arbitration clause, was invoking the arbitration clause, is a reasonable time.
parties should agree to submit failed to settle. Petitioner then filed a complaint for which is a question of fact. Indeed, petitioner may not be faulted for resorting to the
disputes arising from their collection of the balance due against SPI and its co- 3. ID.; ACTIONS; TECHNICAL RULES MAY BE RELAXED TO court to claim what was due it under the contract.
agreement specifically to the CIAC defendants which, however, moved to suspend the PREVENT MISCARRIAGE OF JUSTICE. — Where a rigid However, we find its denial of the existence of the
for the latter to acquire jurisdiction proceedings claiming that their contract provided for an application of the rule that certiorari cannot be a substitute arbitration clause as an attempt to cover up its misstep in
over the same. Rather, it is plain arbitration clause embodied in the Conditions of Contract. for appeal will result in a manifest failure or miscarriage of hurriedly filing the complaint before the lower court.
and clear that as long as the parties The validity of that document containing the arbitration justice, the provisions of the Rules of Court which are 8. ID.; ID.; ID.; DOES NOT DEPRIVE COURT OF ITS
agree to submit to voluntary clause was assailed in that it was only initiated by technical railed may be relaxed. JURISDICTION. — In this connection, it bears stressing that
arbitration, regardless of what petitioner's representatives. The trial court, although 4. CIVIL LAW; OBLIGATIONS AND CONTRACTS; the lower court has not lost its jurisdiction over the case.
forum they may choose, their finding the existence of an arbitration clause, denied ARBITRATION AGREEMENT; FORMAL REQUISITES. — The Section 7 of Republic Act No. 876 provides that proceedings
agreement will fall within the petitioner's motion to suspend proceedings. SPI then filed a formal requirements of an agreement to arbitrate therein have only been stayed. After the special proceeding
jurisdiction of the CIAC, such that, petition for certiorari with the Court of Appeals which in under Republic Act No. 876 are the following: (a) it must be of arbitration has been pursued and completed, then the
even if they specifically choose turn stayed the proceedings in the lower court. The Court in writing and (c) it must be subscribed by the parties or lower court may confirm the award made by the arbitrator.
another forum, the parties will not of Appeals, contrary to the findings of the lower court, their representatives. There is no denying that the parties 9. ID.; ID.; ID.; HAS BEEN HELD VALID AND
be precluded from electing to found that private respondents were not in default in entered into a written contract that was submitted in CONSTITUTIONAL. — It should be noted that in this
submit their dispute before the invoking the provisions of the arbitration clause and that evidence before the lower court. To "subscribe" means to jurisdiction, arbitration has been held valid and
CIAC because this right has been the absence of initials of one party or his representative write underneath, as one's name; to sign at the end of a constitutional. Even before the approval on June 19, 1953
vested upon each party by does not militate against its effectivity where the main document. That word may sometimes be construed to ofRepublic Act No. 876, this Court has countenanced the
law, i.e., E.O. No. 1008." 34 contract containing said arbitration clause had been duly mean to give consent to or to attest. settlement of disputes through arbitration, Republic Act
Clearly, there is no more need to file a request with the signed by the parties. Hence, this recourse, petitioner 5. ID.; ID.; ID.; MAY BE INCLUDED BY REFERENCE. — The No. 876 was adopted to supplement the New Civil Code's
CIAC in order to vest it with jurisdiction to decide a further contending that the order of the lower court Court finds that, upon a scrutiny of the records of this case, provisions on arbitration. Its potentials as one of the
construction dispute. denying the motion to suspend is a resolution on the merits these requisites were complied with in the contract in alternative dispute resolution methods that are now
that can be elevated to a higher court in an ordinary appeal question. The Articles of Agreement, which incorporates all rightfully vaunted as "the wave of the future" in
The arbitral clause in the Agreement is a commitment on and not by certiorari. CaATDE the other contracts and agreements between the parties, international relations, is recognized worldwide. To brush
the part of the parties to submit to arbitration the disputes The Supreme Court held that where a rigid application of was signed by representatives of both parties and duly aside a contractual agreement calling for arbitration in case
covered therein. Because that clause is binding, they are the rule that certiorari cannot be a substitute for appeal notarized. The failure of the private respondent's of disagreement between the parties would therefore be a
expected to abide by it in good faith. 35And because it will result in a manifest or miscarriage of justice, the representative to initial the 'Conditions of Contract' would step backward.
covers the dispute between the parties in the present case, provisions of the Rules of Court which are technical rules therefor not affect compliance with the formal DECISION
either of them may compel the other to arbitrate. 36 may be relaxed. requirements for arbitration agreements because that ROMERO, J p:
Since petitioner has already filed a Complaint with the RTC A contract need not be contained in a single writing and particular portion of the covenants between the parties The basic issue in this petition for review on certiorari is
without prior recourse to arbitration, the proper procedure may be encompassed in several instruments even though was included by reference in the Articles of Agreement. whether or not the contract for the construction of the
to enable the CIAC to decide on the dispute is to request the every instrument is not signed by the parties, since it is 6. ID.; ID.; CONTRACT NEED NOT BE CONTAINED IN A EDSA Plaza between petitioner BF Corporation and
stay or suspension of such action, as provided under RA sufficient if the unsigned instruments are clearly identified SINGLE WRITING BUT MAY BE ENCOMPASSED IN respondent Shangri-la Properties, Inc. embodies an
876 [the Arbitration Law]. 37 or referred to and made part of the signed instrument or SEVERAL DOCUMENTS. — A contract need not be arbitration clause in case of disagreement between the
WHEREFORE, the Petition is DENIED and the assailed instruments. contained in a single writing. It may be collected from parties in the implementation of contractual
Decision AFFIRMED. Costs against petitioner. cEISAD several different writings which do not conflict with each provisions. aisadc
Petitioner and respondent Shangri-la Properties, Inc. (SPI) jurisdiction over the case and that arbitration would also provides that the 'Contract be later than the time of final
entered into an agreement whereby the latter engaged the expedite rather than delay the settlement of the parties' Documents' therein listed 'shall be payment except as otherwise
former to construct the main structure of the "EDSA Plaza respective claims against each other. deemed an integral part of this expressly stipulated in the
Project," a shopping mall complex in the City of In a rejoinder to SPI's reply, petitioner reiterated that there Agreement', and one of the said contract."
Mandaluyong. The construction work was in progress was no arbitration clause in the contract between the documents is the 'Conditions of Against the above backdrop, the lower court found that per
when SPI decided to expand the project by engaging the parties. It averred that granting that such a clause indeed Contract' which contains the the May 30, 1991 agreement, the project was to be
services of petitioner again. Thus, the parties entered into formed part of the contract, suspension of the proceedings Arbitration Clause relied upon by completed by October 31, 1991. Thereafter, the contractor
an agreement for the main contract works after which was no longer proper. It added that defendants should be the defendants in their Motion to would pay P80,000 for each day of delay counted from
construction work began. declared in default for failure to file their answer within the Suspend Proceedings. aisadc November 1, 1991 with "liquified (sic) damages up to a
However, petitioner incurred delay in the construction reglementary period. This Court notes, however, that the maximum of 5% of the total contract price."
work that SPI considered as "serious and substantial."1 On In its sur-rejoinder, SPI pointed out the significance of 'Conditions of Contract' referred to, The lower court also found that after the project was
the other hand, according to petitioner, the construction petitioner's admission of the due execution of the "Articles contains the following provisions: completed in accordance with the agreement that
works "progressed in faithful compliance with the First of Agreement." Thus, on page D/6 thereof, the signatures of '3. Contract Document. contained a provision on "progress payment billing," SPI
Agreement until a fire broke out on November 30, 1990 Rufo B. Colayco, SPI president, and Bayani Fernando, Three copies of the "took possession and started operations thereof by opening
damaging Phase I" of the Project. 2 Hence, SPI proposed the president of petitioner appear, while page D/7 shows that Contract Documents the same to the public in November, 1991." SPI, having
re-negotiation of the agreement between them. the agreement is a public document duly notarized on referred to in the Articles failed to pay for the works, petitioner billed SPI in the total
Consequently, on May 30, 1991, petitioner and SPI entered November 15, 1991 by Notary Public Nilberto R. Briones as of Agreement shall be amount of P110,883,101.52, contained in a demand letter
into a written agreement denominated as "Agreement for document No. 345, page 70, book No. LXX, Series of 1991 of signed by the parties to sent by it to SPI on February 17, 1993. Instead of paying the
the Execution of Builder's Work for the EDSA Plaza his notarial register. 5 the contract and amount demanded, SPI set up its own claim of
Project." Said agreement would cover the construction Thereafter, upon a finding that an arbitration clause indeed distributed to the Owner P220,000,000.00 and scheduled a conference on that claim
work on said project as of May 1, 1991 until its eventual exists, the lower court 6 denied the motion to suspend and the Contractor for for July 12, 1993. The conference took place but it proved
completion. proceedings, thus: their safe keeping.' futile.
According to SPI, petitioner "failed to complete the "It appears from the said document (emphasis supplied) Upon the above facts, the lower court concluded:
construction works and abandoned the project." 3 This that in the letter-agreement dated And it is significant to note further "Considering the fact that under the
resulted in disagreements between the parties as regards May 30, 1991 (Annex C, Complaint), that the said 'Conditions of supposed Arbitration Clause
their respective liabilities under the contract. On July 12, plaintiff BF and defendant Shangri- Contract' is not duly signed by the invoked by defendants, it is
1993, upon SPI's initiative, the parties' respective La Properties, Inc. agreed upon the parties on any page thereof — required that 'Notice of the demand
representatives met in conference but they failed to come terms and conditions of the although it bears the initials of BF's for arbitration of a dispute shall be
to an agreement. 4 Builders Work for the EDSA Plaza representatives (Bayani F. filed in writing with the other
Project (Phases I, II and Carpark), Fernando and Reynaldo M. de la party. . . in no case. . . later than the
Barely two days later or on July 14, 1993, petitioner filed subject to the execution by the Cruz) without the initials thereon time of final payment. . . " which
with the Regional Trial Court of Pasig a complaint for parties of a formal trade contract. of any representative of Shangri-La apparently, had elapsed, not only
collection of the balance due under the construction Defendants have submitted a copy Properties, Inc. because defendants had taken
agreement. Named defendants therein were SPI and of the alleged trade contract, which Considering the insistence of the possession of the finished works
members of its board of directors namely, Alfredo C. is entitled 'Contract Documents For plaintiff that the said Conditions of and the plaintiff's billings for the
Ramos, Rufo B. Colayco, Antonio B. Olbes, Gerardo O. Builder's Work Trade Contractor' Contract was not duly executed or payment thereof had remained
Lanuza, Jr., Maximo G. Licauco III and Benjamin C. Ramos. dated 01 May 1991, page 2 of which signed by the parties, and the pending since November, 1991 up
On August 3, 1993, SPI and its co-defendants filed a motion is entitled 'Contents of Contract failure of the defendants to submit to the filing of this case on July 14,
to suspend proceedings instead of filing an answer. The Documents' with a list of the any signed copy of the said 1993, but also for the reason that
motion was anchored on defendants' allegation that the documents therein contained, and document, this Court entertains defendants have failed to file any
formal trade contract for the construction of the project Section A thereof consists of the serious doubt whether or not the written notice of any demand for
provided for a clause requiring prior resort to arbitration abovementioned Letter-Agreement arbitration clause found in the said arbitration during the said long
before judicial intervention could be invoked in any dispute dated May 30, 1991. Section C of Conditions of Contract is binding period of one year and eight
arising from the contract. The following day, SPI submitted the said Contract Documents is upon the parties to the Articles of months, this Court finds that it
a copy of the conditions of the contract containing the entitled 'Articles of Agreement and Agreement." (Emphasis supplied.) cannot stay the proceedings in this
arbitration clause that it failed to append to its motion to Conditions of Contract' which, per The lower court then ruled that, assuming that the case as required by Sec. 7
suspend proceedings. its Index, consists of Part A arbitration clause was valid and binding, still, it was "too of Republic Act No. 876, because
Petitioner opposed said motion claiming that there was no (Articles of Agreement) and B late in the day for defendants to invoke arbitration." It defendants are in default in
formal contract between the parties although they entered (Conditions of Contract). The said quoted the following provision of the arbitration clause: proceeding with such arbitration."
into an agreement defining their rights and obligations in Articles of Agreement appears to "Notice of the demand for The lower court denied SPI's motion for reconsideration
undertaking the project. It emphasized that the agreement have been duly signed by President arbitration of a dispute shall be for lack of merit and directed it and the other defendants to
did not provide for arbitration and therefore the court Rufo B. Colayco of Shangri-La filed in writing with the other party file their responsive pleading or answer within fifteen (15)
could not be deprived of jurisdiction conferred by law by Properties, Inc. and President to the contract and a copy filed with days from notice.
the mere allegation of the existence of an arbitration clause Bayani F. Fernando of BF and their the Project Manager. The demand Instead of filing an answer to the complaint, SPI filed a
in the agreement between the parties. witnesses, and was thereafter for arbitration shall be made within petition for certiorari under Rule 65 of the Rules of Court
In reply to said opposition, SPI insisted that there was such acknowledged before Notary Public a reasonable time after the dispute before the Court of Appeals. Said appellate court granted
an arbitration clause in the existing contract between Nilberto R. Briones of Makati, has arisen and attempts to settle the petition, annulled and set aside the orders and stayed
petitioner and SPI. It alleged that suspension of Metro Manila on November 15, amicably have failed; in no case, the proceedings in the lower court. In so ruling, the Court of
proceedings would not necessarily deprive the court of its 1991. The said Articles of Agreement however, shall the demand he made Appeals held:
"The reasons given by the 26, 32 or 33 of these period of one year and eight DISCRETION IN THE FACTUAL
respondent Court in denying Conditions), the Owner months,. . . .' FINDINGS OF THE TRIAL COURT
petitioners' motion to suspend and the Contractor Respondent Court has overlooked THAT:
proceedings are untenable. hereby agree to exert all the fact that under the arbitration (i) THE PARTIES DID
1. The notarized copy of the articles efforts to settle their clause — NOT ENTER
of agreement attached as Annex A differences or dispute Notice of the demand for INTO AN
to petitioners' reply dated August amicably. Failing these arbitration dispute shall AGREEMENT
26, 1993, has been submitted by efforts then such dispute be filed in writing with TO
them to the respondent Court or difference shall be the other party to the ARBITRATE.
(Annex G, petition). It bears the referred to Arbitration in contract and a copy filed (ii) ASSUMING THAT
signature of petitioner Rufo B. accordance with the with the Project THE PARTIES
Colayco, president of petitioner rules and procedures of Manager. The demand for DID ENTER
Shangri-La Properties, Inc., and of the Philippine arbitration shall be made INTO THE
Bayani Fernando, president of Arbitration Law. within a reasonable time AGREEMENT
respondent Corporation (Annex G- after the dispute has TO
1, petition). At page D/4 of said The fact that said conditions of arisen and attempts to ARBITRATE,
articles of agreement it is expressly contract containing the arbitration settle amicably had RESPONDENT
provided that the conditions of clause bear only the initials of failed; in no case, S ARE
contract are 'deemed an integral respondent Corporation's however, shall the ALREADY IN
part' thereof (page 188, rollo). And representatives, Bayani Fernando demand be made later DEFAULT IN
it is at pages D/42 to D/44 of the and Reynaldo de la Cruz, without than the time of final INVOKING
conditions of contract that the that of the representative of payment except as THE
provisions for arbitration are found petitioner Shangri-La Properties, otherwise expressly AGREEMENT
(Annexes G-3 to G-5, petition, pp. Inc. does not militate against its stipulated in the contract TO
227-229). Clause No. 35 on effectivity. Said petitioner having (emphasis supplied) ARBITRATE."
arbitration specifically provides: categorically admitted that the quoted in its order (Annex A, On the first assigned error, petitioner contends that the
Provided always that in document, Annex A to its reply petition). As the respondent Court Order of the lower court denying the motion to suspend
case any dispute or dated August 26, 1993 (Annex G, there said, after the final demand to proceedings "is a resolution of an incident on the merits."
difference shall arise petition), is the agreement between pay the amount of As such, upon the continuation of the proceedings, the
between the Owner or the parties, the initial or signature P110,883,101.52, instead of paying, lower court would appreciate the evidence adduced in their
the Project Manager on of said petitioner's representative petitioners set up its own claim totality and thereafter render a decision on the merits that
his behalf and the to signify conformity to arbitration against respondent Corporation in may or may not sustain the existence of an arbitration
Contractor, either during is no longer necessary. The parties, the amount of P220,000,000.00 and clause. A decision containing a finding that the contract has
the progress or after the therefore, should be allowed to set a conference thereon on July 12, no arbitration clause can then be elevated to a higher court
completion or submit their dispute to arbitration 1993. Said conference proved futile. "in an ordinary appeal" where an adequate remedy could
abandonment of the in accordance with their The next day, July 14, 1993, be obtained. Hence, to petitioner, the Court of Appeals
Works as to the agreement. respondent Corporation filed its should have dismissed the petition for certiorari because
construction of this 2. The respondent Court held that complaint against petitioners. On the remedy of appeal would still be available to private
Contract or as to any petitioners 'are in default in August 13, 1993, petitioners wrote respondents at the proper time. 7
matter or thing of proceeding with such arbitration.' to respondent Corporation The above contention is without merit.
whatsoever nature It took note of 'the fact that under requesting arbitration. Under the The rule that the special civil action of certiorari may not be
arising thereunder or in the supposed Arbitration Clause circumstances, it cannot be said invoked as a substitute for the remedy of appeal is
connection therewith invoked by defendants, it is that petitioners' resort to succinctly reiterated in Ongsitco v. Court of Appeals 8 as
(including any matter or required that 'Notice of the demand arbitration was made beyond follows:
being left by this for arbitration of a dispute shall be reasonable time. Neither can they ". . . Countless times in the past, this
Contract to the filed in writing with the other be considered in default of their Court has held that 'where appeal is
discretion of the Project party. . . in no case. . . later than the obligation to respondent the proper remedy, certiorari will
Manager or the time of final payment," which Corporation." not lie.' The writs of certiorari and
withholding by the apparently, had elapsed, not only Hence, this petition before this Court. Petitioner assigns the prohibition are remedies to correct
Project Manager of any because defendants had taken following errors: lack or excess of jurisdiction or
certificate to which the possession of the finished works "A. grave abuse of discretion
Contractor may claim to and the plaintiff's billings for the THE COURT OF APPEALS ERRED IN equivalent to lack of jurisdiction
be entitled or the payment thereof had remained ISSUING THE EXTRAORDINARY committed by a lower court.
measurement and pending since November, 1991 up WRIT OF CERTIORARI ALTHOUGH 'Where the proper remedy is
valuation mentioned in to the filing of this case on July 14, THE REMEDY OF APPEAL WAS appeal, the action for certiorari will
clause 30 (5) (a) of these 1993, but also for the reason that AVAILABLE TO RESPONDENTS. not be entertained.. . . Certiorari is
Conditions or the rights defendants have failed to file any B. not a remedy for errors of
and liabilities of the written notice of any demand for THE COURT OF APPEALS ERRED IN judgment. Errors of judgment are
parties under clauses 25, arbitration during the said long FINDING GRAVE ABUSE OF correctible by appeal, errors of
jurisdiction are reviewable by answer the core issue of whether there exists an contract. Republic Act No. 876 provides for the formal contract between the parties into several parts. This
certiorari.' Arbitration Clause which, admittedly, is a question of fact. requisites of an arbitration agreement as follows: notwithstanding, petitioner ironically admits the execution
Rule 65 is very clear. The Moreover, where a rigid application of the rule that "Section 4. Form of arbitration of the Articles of Agreement. Notably, too, the lower court
extraordinary remedies of certiorari cannot be a substitute for appeal will result in a agreement. — A contract to found that the said Articles of Agreement "also provides
certiorari, prohibition and manifest failure or miscarriage of justice, the provisions of arbitrate a controversy thereafter that the 'Contract Documents' therein listed 'shall be
mandamus are available only when the Rules of Court which are technical rules may be arising between the parties, as well deemed an integral part of this Agreement,' and one of the
'there is no appeal or any plain, relaxed. 10 As we shall show hereunder, had the Court of as a submission to arbitrate an said documents is the 'Conditions of Contract' which
speedy and adequate remedy in the Appeals dismissed the petition for certiorari, the issue of existing controversy, shall be in contains the Arbitration Clause.'" It is this Articles of
ordinary course of law. . . ' That is whether or not an arbitration clause exists in the contract writing and subscribed by the party Agreement that was duly signed by Rufo B. Colayco,
why they are referred to as would not have been resolved in accordance with evidence sought to be charged, or by his president of private respondent SPI, and Bayani F.
'extraordinary.'. . . " extant in the record of the case. Consequently, this would lawful agent. Fernando, president of petitioner corporation. The same
The Court has likewise ruled that "certiorari will not be have resulted in a judicial rejection of a contractual The making of a contract or agreement was duly subscribed before notary public
issued to cure errors in proceedings or correct erroneous provision agreed by the parties to the contract. submission for arbitration Nilberto R. Briones. In other words, the subscription of the
conclusions of law or fact. As long as a court acts within its In the same vein, this Court holds that the question of the described in section two hereof, principal agreement effectively covered the other
jurisdiction, any alleged errors committed in the exercise of existence of the arbitration clause in the contract between providing for arbitration of any documents incorporated by reference therein.
its jurisdiction will amount to nothing more than errors of petitioner and private respondents is a legal issue that controversy, shall be deemed a This Court likewise does not find that the Court of Appeals
judgment which are reviewable by timely appeal and not must be determined in this petition for review on consent of the parties of the erred in ruling that private respondents were not in default
by a special civil action of certiorari." 9 certiorari. province or city where any of the in invoking the provisions of the arbitration clause which
This is not exactly so in the instant case. While this Court Petitioner, while not denying that there exists an parties resides, to enforce such states that "(t)he demand for arbitration shall be made
does not deny the eventual jurisdiction of the lower court arbitration clause in the contract in question, asserts that in contract of submission."(Emphasis within a reasonable time after the dispute has arisen and
over the controversy, the issue posed basically is whether contemplation of law there could not have been one supplied.) attempts to settle amicably had failed." Under the factual
the lower court prematurely assumed jurisdiction over it. If considering the following points. First, the trial court found The formal requirements of an agreement to arbitrate are milieu, private respondent SPI should have paid its
the lower court indeed prematurely assumed jurisdiction that the "conditions of contract" embodying the arbitration therefore the following: (a) it must be in writing and (b) it liabilities under the contract in accordance with its terms.
over the case, then it becomes an error of jurisdiction clause is not duly signed by the parties.Second, private must be subscribed by the parties or their representatives. However, misunderstandings appeared to have cropped up
which is a proper subject of a petition for certiorari before respondents misrepresented before the Court of Appeals There is no denying that the parties entered into a written between the parties ostensibly brought about by either
the Court of Appeals. And if the lower court does not have that they produced in the trial court a notarized duplicate contract that was submitted in evidence before the lower delay in the completion of the construction work or by
jurisdiction over the controversy, then any decision or original copy of the construction agreement because what court. To "subscribe" means to write underneath, as one's force majeure or the fire that partially gutted the project.
order it may render may be annulled and set aside by the were submitted were mere photocopies thereof. The name; to sign at the end of a document. 11 That word may The almost two-year delay in paying its liabilities may not
appellate court. contract(s) introduced in court by private respondents sometimes be construed to mean to give consent to or to therefore be wholly ascribed to private respondent SPI.
However, the question of jurisdiction, which is a question were therefore "of dubious authenticity" because: (a) the attest. 12 Besides, private respondent SPI's initiative in calling for a
of law depends on the determination of the existence of the Agreement for the Execution of Builder's Work for the The Court finds that, upon a scrutiny of the records of this conference between the parties was a step towards the
arbitration clause, which is a question of fact. In the instant EDSA Plaza Project does not contain an arbitration clause, case, these requisites were complied with in the contract in agreed resort to arbitration. However, petitioner posthaste
case, the lower court found that there exists an arbitration (b) private respondents "surreptitiously attached as question. The articles of Agreement, which incorporates all filed the complaint before the lower court. Thus, while
clause. However, it ruled that in contemplation of law, said Annexes 'G-3' to 'G-5' to their petition before the Court of the other contracts and agreements between the parties, private respondent SPI's request for arbitration on August
arbitration clause does not exist. Appeals but these documents are not parts of the was signed by representatives of both parties and duly 13, 1993 might appear an afterthought as it was made after
The issue, therefore, posed before the Court of Appeals in a Agreement of the parties as "there was no formal trade notarized. The failure of the private respondent's it had filed the motion to suspend proceedings, it was
petition for certiorari is whether the Arbitration Clause contract executed," (c ) if the entire compilation of representative to initial the 'Conditions of Contract' would because petitioner also appeared to act hastily in order to
does not in fact exist. On its face, the question is one of fact documents "is indeed a formal trade contract," then it therefor not affect compliance with the formal resolve the controversy through the courts.
which is not proper in a petition for certiorari. should have been duly notarized, (d) the certification from requirements for arbitration agreements because that The arbitration clause provides for a "reasonable time"
The Court of Appeals found that an Arbitration Clause does the Records Management and Archives Office dated August particular portion of the covenants between the parties within which the parties may avail of the relief under that
in fact exist. In resolving said question of fact, the Court of 26, 1993 merely states that "the notarial record of Nilberto was included by reference in the Articles of Agreement. clause. "Reasonableness" is a relative term and the
Appeals interpreted the construction of the subject Briones. . . is available in the files of (said) office as Notarial Petitioner's contention that there was no arbitration clause question of whether the time within which an act has to be
contract documents containing the Arbitration Clause in Registry Entry only," (e) the same certification attests that because the contract incorporating said provision is part of done is reasonable depends on attendant
accordance with Republic Act No. 876 (Arbitration Law) the document entered in the notarial registry pertains to a "hodge-podge" document, is therefore untenable. A circumstances. 15 This Court finds that under the
and existing jurisprudence which will be extensively the Articles of Agreement only without any other contract need not be contained in a single writing. It may circumstances obtaining in this case, a one-month period
discussed hereunder. In effect, the issue posed before the accompanying documents, and therefore, it is not a formal be collected from several different writings which do not from the time the parties held a conference on July 12,
Court of Appeals was likewise a question of law. Being a trade contract, and (f) the compilation submitted by conflict with each other and which, when connected, show 1993 until private respondent SPI notified petitioner that it
question of law, the private respondents rightfully invoked respondents are a "mere hodge-podge of documents and do the parties, subject matter, terms and consideration, as in was invoking the arbitration clause, is a reasonable time.
the special civil action of certiorari. not constitute a single intelligible agreement." LLcd contracts entered into by correspondence. 13 A contract Indeed, petitioner may not be faulted for resorting to the
It is that mode of appeal taken by private respondents may be encompassed in several instruments even though court to claim what was due it under the contract.
before the Court of Appeals that is being questioned by the In other words, petitioner denies the existence of the every instrument is not signed by the parties, since it is However, we find its denial of the existence of the
petitioners before this Court. But at the heart of said issue arbitration clause primarily on the ground that the sufficient if the unsigned instruments are clearly identified arbitration clause as an attempt to cover up its misstep in
is the question of whether there exists an Arbitration representatives of the contracting corporations did not sign or referred to and made part of the signed instrument or hurriedly filing the complaint before the lower court.
Clause because if an Arbitration Clause does not exist, then the "Conditions of Contract" that contained the said clause. instruments. Similarly, a written agreement of which there In this connection, it bears stressing that the lower court
private respondents took the wrong mode of appeal before Its other contentions, specifically that insinuating fraud as are two copies, one signed by each of the parties, is binding has not lost its jurisdiction over the case. Section 7
the Court of Appeals. regards the alleged insertion of the arbitration clause, are on both to the same extent as though there had been only of Republic Act No. 876 provides that proceedings therein
For this Court to be able to resolve the question of whether questions of fact that should have been threshed out below. one copy of the agreement and both had signed it. 14 have only been stayed. After the special proceeding of
private respondents took the proper mode of appeal, This Court may as well proceed to determine whether the The flaw in petitioner's contentions therefore lies in its arbitration 16 has been pursued and completed, then the
which, incidentally, is a question of law, then it has to arbitration clause does exist in the parties' having segmented the various components of the whole
lower court may confirm the award17 made by the KOGIES will ship the machinery and facilities necessary for as agreed upon in Article 15, the arbitration clause of their jurisdiction over any dispute that may arise between the
arbitrator. manufacturing LPG cylinders for which PGSMC would pay contract. parties. KOGIES' prayer for an injunctive writ was
It should be noted that in this jurisdiction, arbitration has USD 1,224,000. KOGIES would install and initiate the On June 23, 1998, PGSMC again wrote KOGIES reiterating denied. 10 The dispositive portion of the Order stated:
been held valid and constitutional. Even before the operation of the plant for which PGSMC bound itself to pay the contents of its June 1, 1998 letter threatening that the WHEREFORE, in view of the
approval on June 19, 1953 of Republic Act No. 876, this USD 306,000 upon the plant's production of the 11-kg. LPG machineries, equipment, and facilities installed in the plant foregoing consideration, this Court
Court has countenanced the settlement of disputes through cylinder samples. Thus, the total contract price amounted would be dismantled and transferred on July 4, 1998. Thus, believes and so holds that no
arbitration. 18 Republic Act No. 876 was adopted to to USD 1,530,000. on July 1, 1998, KOGIES instituted an Application for cogent reason exists for this Court
supplement the New Civil Code's provisions on On October 14, 1997, PGSMC entered into a Contract of Arbitration before the Korean Commercial Arbitration to grant the writ of preliminary
arbitration. 19 Its potentials as one of the alternative Lease 3 with Worth Properties, Inc. (Worth) for use of Board (KCAB) in Seoul, Korea pursuant to Art. 15 of the injunction to restrain and refrain
dispute resolution methods that are now rightfully vaunted Worth's 5,079-square meter property with a 4,032-square Contract as amended. defendant from dismantling the
as "the wave of the future" in international relations, is meter warehouse building to house the LPG manufacturing On July 3, 1998, KOGIES filed a Complaint for Specific machineries and facilities at the lot
recognized worldwide. To brush aside a contractual plant. The monthly rental was PhP322,560 commencing on Performance, docketed as Civil Case No. 98-117 8against and building of Worth Properties,
agreement calling for arbitration in case of disagreement January 1, 1998 with a 10% annual increment clause. PGSMC before the Muntinlupa City Regional Trial Court Incorporated at Carmona, Cavite
between the parties would therefore be a step backward. Subsequently, the machineries, equipment, and facilities for (RTC). The RTC granted a temporary restraining order and transfer the same to another
WHEREFORE, the questioned Decision of the Court of the manufacture of LPG cylinders were shipped, delivered, (TRO) on July 4, 1998, which was subsequently extended site: and therefore denies plaintiff's
Appeals is hereby AFFIRMED and the petition for certiorari and installed in the Carmona plant. PGSMC paid KOGIES until July 22, 1998. In its complaint, KOGIES alleged that application for a writ of
DENIED. This Decision is immediately executory. Costs USD 1,224,000. PGSMC had initially admitted that the checks that were preliminary injunction.
against petitioner. However, gleaned from the Certificate 4 executed by the stopped were not funded but later on claimed that it On July 29, 1998, KOGIES filed its Reply to Answer and
SO ORDERED. parties on January 22, 1998, after the installation of the stopped payment of the checks for the reason that "their Answer to Counterclaim. 11 KOGIES denied it had altered
||| (BF Corp. v. Court of Appeals, G.R. No. 120105, [March 27, plant, the initial operation could not be conducted as value was not received" as the former allegedly breached the quantity and lowered the quality of the machinery,
1998], 351 PHIL 507-526) PGSMC encountered financial difficulties affecting the their contract by "altering the quantity and lowering the equipment, and facilities it delivered to the plant. It claimed
supply of materials, thus forcing the parties to agree that quality of the machinery and equipment" installed in the that it had performed all the undertakings under the
SECOND DIVISION KOGIES would be deemed to have completely complied plant and failed to make the plant operational although it contract and had already produced certified samples of LPG
[G.R. No. 143581. January 7, 2008.] with the terms and conditions of the March 5, 1997 earlier certified to the contrary as shown in a January 22, cylinders. It averred that whatever was unfinished was
KOREA TECHNOLOGIES CO., contract. SDHacT 1998 Certificate. Likewise, KOGIES averred that PGSMC PGSMC's fault since it failed to procure raw materials due
LTD., petitioner, vs. HON. For the remaining balance of USD306,000 for the violated Art. 15 of their Contract, as amended, by to lack of funds. KOGIES, relying on Chung Fu Industries
ALBERTO A. LERMA, in his installation and initial operation of the plant, PGSMC issued unilaterally rescinding the contract without resorting to (Phils.), Inc. v. Court of Appeals, 12 insisted that the
capacity as Presiding Judge of two postdated checks: (1) BPI Check No. 0316412 dated arbitration. KOGIES also asked that PGSMC be restrained arbitration clause was without question valid.
Branch 256 of Regional Trial January 30, 1998 for PhP4,500,000; and (2) BPI Check No. from dismantling and transferring the machinery and After KOGIES filed a Supplemental Memorandum with
Court of Muntinlupa City, and 0316413 dated March 30, 1998 for PhP4,500,000. 5 equipment installed in the plant which the latter Motion to Dismiss 13 answering PGSMC's memorandum of
PACIFIC GENERAL STEEL When KOGIES deposited the checks, these were dishonored threatened to do on July 4, 1998. July 22, 1998 and seeking dismissal of PGSMC's
MANUFACTURING for the reason "PAYMENT STOPPED." Thus, on May 8, On July 9, 1998, PGSMC filed an opposition to the TRO counterclaims, KOGIES, on August 4, 1998, filed its Motion
CORPORATION, respondents. 1998, KOGIES sent a demand letter 6 to PGSMC threatening arguing that KOGIES was not entitled to the TRO since Art. for Reconsideration 14 of the July 23, 1998 Order denying
DECISION criminal action for violation of Batas Pambansa Blg. 22 in 15, the arbitration clause, was null and void for being its application for an injunctive writ claiming that the
VELASCO, JR., J p: case of nonpayment. On the same date, the wife of PGSMC's against public policy as it ousts the local courts of contract was not merely for machinery and facilities worth
In our jurisdiction, the policy is to favor alternative President faxed a letter dated May 7, 1998 to KOGIES' jurisdiction over the instant controversy. USD 1,224,000 but was for the sale of an "LPG
methods of resolving disputes, particularly in civil and President who was then staying at a Makati City hotel. She On July 17, 1998, PGSMC filed its Answer with Compulsory manufacturing plant" consisting of "supply of all the
commercial disputes. Arbitration along with mediation, complained that not only did KOGIES deliver a different Counterclaim 9 asserting that it had the full right to machinery and facilities" and "transfer of technology" for a
conciliation, and negotiation, being inexpensive, speedy brand of hydraulic press from that agreed upon but it had dismantle and transfer the machineries and equipment total contract price of USD 1,530,000 such that the
and less hostile methods have long been favored by this not delivered several equipment parts already paid for. because it had paid for them in full as stipulated in the dismantling and transfer of the machinery and facilities
Court. The petition before us puts at issue an arbitration On May 14, 1998, PGSMC replied that the two checks it contract; that KOGIES was not entitled to the PhP9,000,000 would result in the dismantling and transfer of the very
clause in a contract mutually agreed upon by the parties issued KOGIES were fully funded but the payments were covered by the checks for failing to completely install and plant itself to the great prejudice of KOGIES as the still
stipulating that they would submit themselves to stopped for reasons previously made known to KOGIES. 7 make the plant operational; and that KOGIES was liable for unpaid owner/seller of the plant. Moreover, KOGIES points
arbitration in a foreign country. Regrettably, instead of On June 1, 1998, PGSMC informed KOGIES that PGSMC was damages amounting to PhP4,500,000 for altering the out that the arbitration clause under Art. 15 of the Contract
hastening the resolution of their dispute, the parties canceling their Contract dated March 5, 1997 on the ground quantity and lowering the quality of the machineries and as amended was a valid arbitration stipulation under Art.
wittingly or unwittingly prolonged the controversy. that KOGIES had altered the quantity and lowered the equipment. Moreover, PGSMC averred that it has already 2044 of the Civil Code and as held by this Court in Chung Fu
Petitioner Korea Technologies Co., Ltd. (KOGIES) is a quality of the machineries and equipment it delivered to paid PhP2,257,920 in rent (covering January to July 1998) Industries (Phils.), Inc. 15
Korean corporation which is engaged in the supply and PGSMC, and that PGSMC would dismantle and transfer the to Worth and it was not willing to further shoulder the cost
installation of Liquefied Petroleum Gas (LPG) Cylinder machineries, equipment, and facilities installed in the of renting the premises of the plant considering that the In the meantime, PGSMC filed a Motion for Inspection of
manufacturing plants, while private respondent Pacific Carmona plant. Five days later, PGSMC filed before the LPG cylinder manufacturing plant never became Things 16 to determine whether there was indeed
General Steel Manufacturing Corp. (PGSMC) is a domestic Office of the Public Prosecutor an Affidavit-Complaint operational. EcaDCI alteration of the quantity and lowering of quality of the
corporation. for Estafa docketed as I.S. No. 98-03813 against Mr. Dae After the parties submitted their Memoranda, on July 23, machineries and equipment, and whether these were
On March 5, 1997, PGSMC and KOGIES executed a Hyun Kang, President of KOGIES. 1998, the RTC issued an Order denying the application for a properly installed. KOGIES opposed the motion positing
Contract 1 whereby KOGIES would set up an LPG Cylinder On June 15, 1998, KOGIES wrote PGSMC informing the writ of preliminary injunction, reasoning that PGSMC had that the queries and issues raised in the motion for
Manufacturing Plant in Carmona, Cavite. The contract was latter that PGSMC could not unilaterally rescind their paid KOGIES USD 1,224,000, the value of the machineries inspection fell under the coverage of the arbitration clause
executed in the Philippines. On April 7, 1997, the parties contract nor dismantle and transfer the machineries and and equipment as shown in the contract such that KOGIES in their contract.
executed, in Korea, an Amendment for Contract No. KLP- equipment on mere imagined violations by KOGIES. It also no longer had proprietary rights over them. And finally, the On September 21, 1998, the trial court issued an Order (1)
970301 dated March 5, 1997 2 amending the terms of insisted that their disputes should be settled by arbitration RTC held that Art. 15 of the Contract as amended was granting PGSMC's motion for inspection; (2) denying
payment. The contract and its amendment stipulated that invalid as it tended to oust the trial court or any other court KOGIES' motion for reconsideration of the July 23, 1998
RTC Order; and (3) denying KOGIES' motion to dismiss On the issue of nonpayment of docket fees and non- e. PROCLAIMING THE TWO motion to quash can then be used as part of his defense and
PGSMC's compulsory counterclaims as these counterclaims attachment of a certificate of non-forum shopping by ORDERS DATED JULY 23 AND subsequently can be raised as errors on his appeal if the
fell within the requisites of compulsory counterclaims. PGSMC, the CA held that the counterclaims of PGSMC were SEPTEMBER 21, 1998 NOT TO BE judgment of the trial court is adverse to him. The general
On October 2, 1998, KOGIES filed an Urgent Motion for compulsory ones and payment of docket fees was not PROPER SUBJECTS rule is that interlocutory orders cannot be challenged by an
Reconsideration 17 of the September 21, 1998 RTC Order required since the Answer with counterclaim was not an OF CERTIORARI AND PROHIBITION appeal. 27 Thus, in Yamaoka v. Pescarich Manufacturing
granting inspection of the plant and denying dismissal of initiatory pleading. For the same reason, the CA said a FOR BEING "INTERLOCUTORY IN Corporation, we held:
PGSMC's compulsory counterclaims. certificate of non-forum shopping was also not required. NATURE;" The proper remedy in such cases is
Ten days after, on October 12, 1998, without waiting for Furthermore, the CA held that the petition f. NOT GRANTING THE RELIEFS an ordinary appeal from an adverse
the resolution of its October 2, 1998 urgent motion for for certiorari had been filed prematurely since KOGIES did AND REMEDIES PRAYED FOR IN judgment on the merits,
reconsideration, KOGIES filed before the Court of Appeals not wait for the resolution of its urgent motion for HE (SIC) PETITION AND, INSTEAD, incorporating in said appeal the
(CA) a petition for certiorari 18 docketed as CA-G.R. SP No. reconsideration of the September 21, 1998 RTC Order DISMISSING THE SAME FOR grounds for assailing the
49249, seeking annulment of the July 23, 1998 and which was the plain, speedy, and adequate remedy ALLEGEDLY "WITHOUT interlocutory orders. Allowing
September 21, 1998 RTC Orders and praying for the available. According to the CA, the RTC must be given the MERIT." 23 appeals from interlocutory orders
issuance of writs of prohibition, mandamus, and opportunity to correct any alleged error it has committed, The Court's Ruling would result in the 'sorry spectacle'
preliminary injunction to enjoin the RTC and PGSMC from and that since the assailed orders were interlocutory, these The petition is partly meritorious. of a case being subject of a
inspecting, dismantling, and transferring the machineries cannot be the subject of a petition for certiorari. Before we delve into the substantive issues, we shall first counterproductiveping-pong to and
and equipment in the Carmona plant, and to direct the RTC Hence, we have this Petition for Review on Certiorari under tackle the procedural issues. from the appellate court as often as
to enforce the specific agreement on arbitration to resolve Rule 45. The rules on the payment of a trial court is perceived to have
the dispute. The Issues docket fees for counterclaims made an error in any of its
In the meantime, on October 19, 1998, the RTC denied Petitioner posits that the appellate court committed the and cross claims were amended interlocutory rulings. However,
KOGIES' urgent motion for reconsideration and directed following errors: effective August 16, 2004 where the assailed interlocutory
the Branch Sheriff to proceed with the inspection of the a. PRONOUNCING THE QUESTION KOGIES strongly argues that when PGSMC filed the order was issued with grave abuse
machineries and equipment in the plant on October 28, OF OWNERSHIP OVER THE counterclaims, it should have paid docket fees and filed a of discretion or patently erroneous
1998. 19 MACHINERY AND FACILITIES AS certificate of non-forum shopping, and that its failure to do and the remedy of appeal would
Thereafter, KOGIES filed a Supplement to the Petition 20 in "A QUESTION OF FACT" "BEYOND so was a fatal defect. not afford adequate and
CA-G.R. SP No. 49249 informing the CA about the October THE AMBIT OF A PETITION We disagree with KOGIES. expeditious relief, the Court
19, 1998 RTC Order. It also reiterated its prayer for the FOR CERTIORARI" INTENDED As aptly ruled by the CA, the counterclaims of PGSMC were allows certiorari as a mode of
issuance of the writs of prohibition,mandamus and ONLY FOR CORRECTION OF incorporated in its Answer with Compulsory Counterclaim redress. 28
preliminary injunction which was not acted upon by the ERRORS OF JURISDICTION OR dated July 17, 1998 in accordance with Section 8 of Rule 11, Also, appeals from interlocutory orders would open the
CA. KOGIES asserted that the Branch Sheriff did not have GRAVE ABUSE OF DISCRETION 1997 Revised Rules of Civil Procedure, the rule that was floodgates to endless occasions for dilatory motions. Thus,
the technical expertise to ascertain whether or not the AMOUNTING TO LACK OF (SIC) effective at the time the Answer with Counterclaim was where the interlocutory order was issued without or in
machineries and equipment conformed to the EXCESS OF JURISDICTION, AND filed. Sec. 8 on existing counterclaim or cross-claim states, excess of jurisdiction or with grave abuse of discretion, the
specifications in the contract and were properly CONCLUDING THAT THE TRIAL "A compulsory counterclaim or a cross-claim that a remedy is certiorari. 29 HDcaAI
installed. TaISDA COURT'S FINDING ON THE SAME defending party has at the time he files his answer shall be The alleged grave abuse of discretion of the respondent
On November 11, 1998, the Branch Sheriff filed his Sheriff's QUESTION WAS IMPROPERLY contained therein." court equivalent to lack of jurisdiction in the issuance of the
Report 21 finding that the enumerated machineries and RAISED IN THE PETITION BELOW; On July 17, 1998, at the time PGSMC filed its Answer two assailed orders coupled with the fact that there is no
equipment were not fully and properly installed. b. DECLARING AS NULL AND VOID incorporating its counterclaims against KOGIES, it was not plain, speedy, and adequate remedy in the ordinary course
The Court of Appeals affirmed the trial court and THE ARBITRATION CLAUSE IN liable to pay filing fees for said counterclaims being of law amply provides the basis for allowing the resort to a
declared ARTICLE 15 OF THE CONTRACT compulsory in nature. We stress, however, that effective petition forcertiorari under Rule 65.
the arbitration clause against public policy BETWEEN THE PARTIES FOR August 16, 2004 under Sec. 7, Rule 141, as amended Prematurity of the petition before the CA
On May 30, 2000, the CA rendered the assailed BEING "CONTRARY TO PUBLIC by A.M. No. 04-2-04-SC, docket fees are now required to be Neither do we think that KOGIES was guilty of forum
Decision 22 affirming the RTC Orders and dismissing the POLICY" AND FOR OUSTING THE paid in compulsory counterclaim or cross-claims. shopping in filing the petition for certiorari. Note that
petition for certiorari filed by KOGIES. The CA found that COURTS OF JURISDICTION; As to the failure to submit a certificate of forum shopping, KOGIES' motion for reconsideration of the July 23, 1998
the RTC did not gravely abuse its discretion in issuing the c. DECREEING PRIVATE PGSMC's Answer is not an initiatory pleading which RTC Order which denied the issuance of the injunctive writ
assailed July 23, 1998 and September 21, 1998 Orders. RESPONDENT'S COUNTERCLAIMS requires a certification against forum shopping under Sec. had already been denied. Thus, KOGIES' only remedy was
Moreover, the CA reasoned that KOGIES' contention that TO BE ALL COMPULSORY NOT 5 24 of Rule 7, 1997 Revised Rules of Civil Procedure. It is a to assail the RTC's interlocutory order via a petition
the total contract price for USD 1,530,000 was for the NECESSITATING PAYMENT OF responsive pleading, hence, the courts a quo did not for certiorari under Rule 65.
whole plant and had not been fully paid was contrary to the DOCKET FEES AND commit reversible error in denying KOGIES' motion to
finding of the RTC that PGSMC fully paid the price of USD CERTIFICATION OF NON-FORUM dismiss PGSMC's compulsory counterclaims. While the October 2, 1998 motion for reconsideration of
1,224,000, which was for all the machineries and SHOPPING; Interlocutory orders proper subject of certiorari KOGIES of the September 21, 1998 RTC Order relating to
equipment. According to the CA, this determination by the d. RULING THAT THE PETITION Citing Gamboa v. Cruz, 25 the CA also pronounced that the inspection of things, and the allowance of the
RTC was a factual finding beyond the ambit of a petition WAS FILED PREMATURELY "certiorari and Prohibition are neither the remedies to compulsory counterclaims has not yet been resolved, the
for certiorari. WITHOUT WAITING FOR THE question the propriety of an interlocutory order of the trial circumstances in this case would allow an exception to the
On the issue of the validity of the arbitration clause, the CA RESOLUTION OF THE MOTION FOR court." 26 The CA erred on its reliance rule that before certiorari may be availed of, the petitioner
agreed with the lower court that an arbitration clause RECONSIDERATION OF THE onGamboa. Gamboa involved the denial of a motion to must have filed a motion for reconsideration and said
which provided for a final determination of the legal rights ORDER DATED SEPTEMBER 21, acquit in a criminal case which was not assailable in an motion should have been first resolved by the court a quo.
of the parties to the contract by arbitration was against 1998 OR WITHOUT GIVING THE action for certiorari since the denial of a motion to quash The reason behind the rule is "to enable the lower court, in
public policy. TRIAL COURT AN OPPORTUNITY required the accused to plead and to continue with the the first instance, to pass upon and correct its mistakes
TO CORRECT ITSELF; aHIEcS trial, and whatever objections the accused had in his without the intervention of the higher court." 30
The September 21, 1998 RTC Order directing the branch arbitration is a contract. 36 Again in Del Monte RA 9285 incorporated the UNCITRAL Model law case. Well-settled is the rule that procedural laws are
sheriff to inspect the plant, equipment, and facilities when Corporation-USA v. Court of Appeals, we likewise ruled that to which we are a signatory construed to be applicable to actions pending and
he is not competent and knowledgeable on said matters is "[t]he provision to submit to arbitration any dispute arising For domestic arbitration proceedings, we have particular undetermined at the time of their passage, and are deemed
evidently flawed and devoid of any legal support. therefrom and the relationship of the parties is part of that agencies to arbitrate disputes arising from contractual retroactive in that sense and to that extent. As a general
Moreover, there is an urgent necessity to resolve the issue contract and is itself a contract."37 CAacTH relations. In case a foreign arbitral body is chosen by the rule, the retroactive application of procedural laws does
on the dismantling of the facilities and any further delay Arbitration clause not contrary to public policy parties, the arbitration rules of our domestic arbitration not violate any personal rights because no vested right has
would prejudice the interests of KOGIES. Indeed, there is The arbitration clause which stipulates that the arbitration bodies would not be applied. As signatory to the yet attached nor arisen from them. 42
real and imminent threat of irreparable destruction or must be done in Seoul, Korea in accordance with the Arbitration Rules of the UNCITRAL Model Law on Among the pertinent features of RA 9285 applying and
substantial damage to KOGIES' equipment and Commercial Arbitration Rules of the KCAB, and that the International Commercial Arbitration 41 of the United incorporating the UNCITRAL Model Law are the following:
machineries. We find the resort tocertiorari based on the arbitral award is final and binding, is not contrary to public Nations Commission on International Trade Law (1) The RTC must refer to arbitration in proper
gravely abusive orders of the trial court sans the ruling on policy. This Court has sanctioned the validity of arbitration (UNCITRAL) in the New York Convention on June 21, 1985, cases
the October 2, 1998 motion for reconsideration to be clauses in a catena of cases. In the 1957 case of Eastboard the Philippines committed itself to be bound by the Model Under Sec. 24, the RTC does not have jurisdiction over
proper. Navigation Ltd. v. Juan Ysmael and Co., Inc., 38 this Court Law. We have even incorporated the Model Law disputes that are properly the subject of arbitration
The Core Issue: Article 15 of the Contract had occasion to rule that an arbitration clause to resolve in Republic Act No. (RA) 9285, otherwise known as pursuant to an arbitration clause, and mandates the
We now go to the core issue of the validity of Art. 15 of the differences and breaches of mutually agreed contractual the Alternative Dispute Resolution Act of 2004 entitled An referral to arbitration in such cases, thus:
Contract, the arbitration clause. It provides: terms is valid. In BF Corporation v. Court of Appeals, we held Act to Institutionalize the Use of an Alternative Dispute SEC. 24. Referral to Arbitration. — A
Article 15. Arbitration. — All that "[i]n this jurisdiction, arbitration has been held valid Resolution System in the Philippines and to Establish the court before which an action is
disputes, controversies, or and constitutional. Even before the approval on June 19, Office for Alternative Dispute Resolution, and for Other brought in a matter which is the
differences which may arise 1953 of Republic Act No. 876, this Court has countenanced Purposes, promulgated on April 2, 2004. Secs. 19 and 20 of subject matter of an arbitration
between the parties, out of or in the settlement of disputes through arbitration. Republic Act Chapter 4 of the Model Law are the pertinent provisions: agreement shall, if at least one
relation to or in connection with No. 876 was adopted to supplement the New Civil Code's CHAPTER 4 — INTERNATIONAL party so requests not later than the
this Contract or for the breach provisions on arbitration." 39 And in LM Power Engineering COMMERCIAL ARBITRATION pre-trial conference, or upon the
thereof, shall finally be settled by Corporation v. Capitol Industrial Construction Groups, Inc., SEC. 19. Adoption of the Model Law request of both parties thereafter,
arbitration in Seoul, Korea in we declared that: on International Commercial refer the parties to arbitration
accordance with the Commercial Being an inexpensive, speedy and Arbitration. — International unless it finds that the arbitration
Arbitration Rules of the Korean amicable method of settling commercial arbitration shall be agreement is null and void,
Commercial Arbitration Board. The disputes, arbitration — along with governed by the Model Law on inoperative or incapable of being
award rendered by the mediation, conciliation and International Commercial performed.
arbitration(s) shall be final and negotiation — is encouraged by the Arbitration (the "Model Law") (2) Foreign arbitral awards must be confirmed by
binding upon both parties Supreme Court. Aside from adopted by the United Nations the RTC
concerned. (Emphasis supplied.) unclogging judicial dockets, Commission on International Trade Foreign arbitral awards while mutually stipulated by the
Petitioner claims the RTC and the CA erred in ruling that arbitration also hastens the Law on June 21, 1985 (United parties in the arbitration clause to be final and binding are
the arbitration clause is null and void. resolution of disputes, especially of Nations Document A/40/17) and not immediately enforceable or cannot be implemented
Petitioner is correct. the commercial kind. It is thus recommended for enactment by the immediately. Sec. 35 43 of the UNCITRAL Model Law
Established in this jurisdiction is the rule that the law of the regarded as the "wave of the General Assembly in Resolution No. stipulates the requirement for the arbitral award to be
place where the contract is made governs. Lex loci future" in international civil and 40/72 approved on December 11, recognized by a competent court for enforcement, which
contractus. The contract in this case was perfected here in commercial disputes. Brushing 1985, copy of which is hereto court under Sec. 36 of the UNCITRAL Model Law may
the Philippines. Therefore, our laws ought to govern. aside a contractual agreement attached as Appendix "A". cEATSI refuse recognition or enforcement on the grounds provided
Nonetheless, Art. 2044 of the Civil Code sanctions the calling for arbitration between the SEC. 20. Interpretation of Model for. RA 9285 incorporated these provisos to Secs. 42, 43,
validity of mutually agreed arbitral clause or the finality parties would be a step backward. Law. — In interpreting the Model and 44 relative to Secs. 47 and 48, thus:
and binding effect of an arbitral award. Art. 2044 provides, Consistent with the above- Law, regard shall be had to its
"Any stipulation that the arbitrators' award or decision mentioned policy of encouraging international origin and to the need SEC. 42. Application of the New York
shall be final, is valid, without prejudice to Articles 2038, alternative dispute resolution for uniformity in its interpretation Convention. — The New York
2039 and 2040." (Emphasis supplied.) methods, courts should liberally and resort may be made to Convention shall govern the
Arts. 2038, 31 2039, 32 and 2040 33 abovecited refer to construe arbitration clauses. thetravaux preparatories and the recognition and enforcement of
instances where a compromise or an arbitral award, as Provided such clause is susceptible report of the Secretary General of arbitral awards covered by said
applied to Art. 2044 pursuant to Art. 2043, 34 may be of an interpretation that covers the the United Nations Commission on Convention.
voided, rescinded, or annulled, but these would not asserted dispute, an order to International Trade Law dated The recognition and enforcement of
denigrate the finality of the arbitral award. arbitrate should be granted. Any March 25, 1985 entitled, such arbitral awards shall be filed
The arbitration clause was mutually and voluntarily agreed doubt should be resolved in favor "International Commercial with the Regional Trial Court in
upon by the parties. It has not been shown to be contrary to of arbitration. 40 Arbitration: Analytical Commentary accordance with the rules of
any law, or against morals, good customs, public order, or Having said that the instant arbitration clause is not against on Draft Trade identified by procedure to be promulgated by
public policy. There has been no showing that the parties public policy, we come to the question on what governs an reference number A/CN. 9/264." the Supreme Court. Said procedural
have not dealt with each other on equal footing. We find no arbitration clause specifying that in case of any dispute While RA 9285 was passed only in 2004, it nonetheless rules shall provide that the party
reason why the arbitration clause should not be respected arising from the contract, an arbitral panel will be applies in the instant case since it is a procedural law which relying on the award or applying
and complied with by both parties. In Gonzales v. Climax constituted in a foreign country and the arbitration rules of has a retroactive effect. Likewise, KOGIES filed its for its enforcement shall file with
Mining Ltd., 35 we held that submission to arbitration is a the foreign country would govern and its award shall be application for arbitration before the KCAB on July 1, 1998 the court the original or
contract and that a clause in a contract providing that all final and binding. and it is still pending because no arbitral award has yet authenticated copy of the award
matters in dispute between the parties shall be referred to been rendered. Thus, RA 9285 is applicable to the instant and the arbitration agreement. If
the award or agreement is not SEC. 48. Notice of Proceeding to arbitration award was made is Sec. 46 of RA 9285 provides for an appeal before the CA as
made in any of the official Parties. — In a special proceeding party to the New York Convention. the remedy of an aggrieved party in cases where the RTC
languages, the party shall supply a for recognition and enforcement of If the application for rejection or sets aside, rejects, vacates, modifies, or corrects an arbitral
duly certified translation thereof an arbitral award, the Court shall suspension of enforcement of an award, thus:
into any of such languages. send notice to the parties at their award has been made, the Regional SEC. 46. Appeal from Court Decision
The applicant shall establish that address of record in the arbitration, Trial Court may, if it considers it or Arbitral Awards. — A decision of
the country in which foreign or if any part cannot be served proper, vacate its decision and may the Regional Trial Court confirming,
arbitration award was made in notice at such address, at such also, on the application of the party vacating, setting aside, modifying or
party to the New York Convention. party's last known address. The claiming recognition or correcting an arbitral award may
xxx xxx xxx notice shall be sent al least fifteen enforcement of the award, order be appealed to the Court of Appeals
SEC. 43. Recognition and (15) days before the date set for the the party to provide appropriate in accordance with the rules and
Enforcement of Foreign Arbitral initial hearing of the application. security. ADHcTE procedure to be promulgated by
Awards Not Covered by the New It is now clear that foreign arbitral awards when confirmed xxx xxx xxx the Supreme Court.
York Convention. — The recognition by the RTC are deemed not as a judgment of a foreign court SEC. 45. Rejection of a Foreign The losing party who appeals from
and enforcement of foreign arbitral but as a foreign arbitral award, and when confirmed, are Arbitral Award. — A party to a the judgment of the court
awards not covered by the New enforced as final and executory decisions of our courts of foreign arbitration proceeding may confirming an arbitral award shall
York Convention shall be done in law. oppose an application for be required by the appellate court
accordance with procedural rules Thus, it can be gleaned that the concept of a final and recognition and enforcement of the to post a counterbond executed in
to be promulgated by the Supreme binding arbitral award is similar to judgments or awards arbitral award in accordance with favor of the prevailing party equal
Court. The Court may, on grounds given by some of our quasi-judicial bodies, like the National the procedures and rules to be to the amount of the award in
of comity and reciprocity, recognize Labor Relations Commission and Mines Adjudication promulgated by the Supreme Court accordance with the rules to be
and enforce a non-convention Board, whose final judgments are stipulated to be final and only on those grounds enumerated promulgated by the Supreme Court.
award as a convention binding, but not immediately executory in the sense that under Article V of the New York Thereafter, the CA decision may further be appealed or
award. IEHaSc they may still be judicially reviewed, upon the instance of Convention. Any other ground reviewed before this Court through a petition for review
SEC. 44. Foreign Arbitral Award Not any party. Therefore, the final foreign arbitral awards are raised shall be disregarded by the under Rule 45 of the Rules of Court.
Foreign Judgment. — A foreign similarly situated in that they need first to be confirmed by Regional Trial Court. PGSMC has remedies to protect its interests
arbitral award when confirmed by the RTC. Thus, while the RTC does not have jurisdiction over Thus, based on the foregoing features of RA 9285, PGSMC
a court of a foreign country, shall be (3) The RTC has jurisdiction to review foreign disputes governed by arbitration mutually agreed upon by must submit to the foreign arbitration as it bound itself
recognized and enforced as a arbitral awards the parties, still the foreign arbitral award is subject to through the subject contract. While it may have misgivings
foreign arbitral award and not as a Sec. 42 in relation to Sec. 45 of RA 9285 designated and judicial review by the RTC which can set aside, reject, or on the foreign arbitration done in Korea by the KCAB, it has
judgment of a foreign court. vested the RTC with specific authority and jurisdiction to vacate it. In this sense, what this Court held in Chung Fu available remedies under RA 9285. Its interests are duly
A foreign arbitral award, when set aside, reject, or vacate a foreign arbitral award on Industries (Phils.), Inc. relied upon by KOGIES is applicable protected by the law which requires that the arbitral award
confirmed by the Regional Trial grounds provided under Art. 34 (2) of the UNCITRAL Model insofar as the foreign arbitral awards, while final and that may be rendered by KCAB must be confirmed here by
Court, shall be enforced in the same Law. Secs. 42 and 45 provide: binding, do not oust courts of jurisdiction since these the RTC before it can be enforced.
manner as final and executory SEC. 42. Application of the New York arbitral awards are not absolute and without exceptions as With our disquisition above, petitioner is correct in its
decisions of courts of law of the Convention. — The New York they are still judicially reviewable. Chapter 7 of RA contention that an arbitration clause, stipulating that the
Philippines. Convention shall govern the 9285 has made it clear that all arbitral awards, whether arbitral award is final and binding, does not oust our courts
xxx xxx xxx recognition and enforcement of domestic or foreign, are subject to judicial review on of jurisdiction as the international arbitral award, the
SEC. 47. Venue and Jurisdiction. — arbitral awards covered by said specific grounds provided for. award of which is not absolute and without exceptions, is
Proceedings for recognition and Convention. (4) Grounds for judicial review different in still judicially reviewable under certain conditions
enforcement of an arbitration The recognition and enforcement of domestic and foreign arbitral awards provided for by the UNCITRAL Model Law on ICA as
agreement or for vacations, setting such arbitral awards shall be filed The differences between a final arbitral award from an applied and incorporated in RA 9285. aHSCcE
aside, correction or modification of with the Regional Trial Court in international or foreign arbitral tribunal and an award Finally, it must be noted that there is nothing in the subject
an arbitral award, and any accordance with the rules of given by a local arbitral tribunal are the specific grounds or Contract which provides that the parties may dispense with
application with a court for procedure to be promulgated by conditions that vest jurisdiction over our courts to review the arbitration clause.
arbitration assistance and the Supreme Court. Said procedural the awards. Unilateral rescission improper and illegal
supervision shall be deemed as rules shall provide that the party For foreign or international arbitral awards which must Having ruled that the arbitration clause of the subject
special proceedings and shall be relying on the award or applying first be confirmed by the RTC, the grounds for setting aside, contract is valid and binding on the parties, and not
filed with the Regional Trial Court for its enforcement shall file with rejecting or vacating the award by the RTC are provided contrary to public policy; consequently, being bound to the
(i) where arbitration proceedings the court the original or under Art. 34 (2) of the UNCITRAL Model Law. contract of arbitration, a party may not unilaterally rescind
are conducted; (ii) where the asset authenticated copy of the award For final domestic arbitral awards, which also need or terminate the contract for whatever cause without first
to be attached or levied upon, or and the arbitration agreement. If confirmation by the RTC pursuant to Sec. 23 of RA resorting to arbitration.
the act to be enjoined is located; the award or agreement is not 876 44and shall be recognized as final and executory What this Court held in University of the Philippines v. de Los
(iii) where any of the parties to the made in any of the official decisions of the RTC, 45 they may only be assailed before Angeles 47 and reiterated in succeeding cases,48 that the
dispute resides or has his place of languages, the party shall supply a the RTC and vacated on the grounds provided under Sec. 25 act of treating a contract as rescinded on account of
business; or (iv) in the National duly certified translation thereof of RA 876. 46 infractions by the other contracting party is valid albeit
Judicial Capital Region, at the into any of such languages. (5) RTC decision of assailed foreign arbitral award provisional as it can be judicially assailed, is not applicable
option of the applicant. The applicant shall establish that appealable to the instant case on account of a valid stipulation on
the country in which foreign arbitration. Where an arbitration clause in a contract is
availing, neither of the parties can unilaterally treat the Firstly, while the issue of the proper installation of the (d) Interim or provisional relief is relation to arbitration proceedings,
contract as rescinded since whatever infractions or equipment and machineries might well be under the requested by written application irrespective of whether their place
breaches by a party or differences arising from the contract primary jurisdiction of the arbitral body to decide, yet the transmitted by reasonable means is in the territory of this State, as it
must be brought first and resolved by arbitration, and not RTC under Sec. 28 of RA 9285 has jurisdiction to hear and to the Court or arbitral tribunal as has in relation to proceedings in
through an extrajudicial rescission or judicial action. grant interim measures to protect vested rights of the the case may be and the party courts. The court shall exercise
parties. Sec. 28 pertinently provides: against whom the relief is sought, such power in accordance with its
The issues arising from the contract between PGSMC and SEC. 28. Grant of interim Measure of describing in appropriate detail the own procedures in consideration of
KOGIES on whether the equipment and machineries Protection. — (a) It is not precise relief, the party against the specific features of
delivered and installed were properly installed and incompatible with an arbitration whom the relief is requested, the international arbitration.
operational in the plant in Carmona, Cavite; the ownership agreement for a party to request, grounds for the relief, and the In the recent 2006 case of Transfield Philippines, Inc. v.
of equipment and payment of the contract price; and before constitution of the evidence supporting the request. Luzon Hydro Corporation, we were explicit that even "the
whether there was substantial compliance by KOGIES in tribunal, from a Court to grant (e) The order shall be binding pendency of an arbitral proceeding does not foreclose
the production of the samples, given the alleged fact that such measure. After constitution upon the parties. resort to the courts for provisional reliefs." We explicated
PGSMC could not supply the raw materials required to of the arbitral tribunal and during (f) Either party may apply with the this way:
produce the sample LPG cylinders, are matters proper for arbitral proceedings, a request for Court for assistance in As a fundamental point, the
arbitration. Indeed, we note that on July 1, 1998, KOGIES an interim measure of protection, implementing or enforcing an pendency of arbitral proceedings
instituted an Application for Arbitration before the KCAB in or modification thereof, may be interim measure ordered by an does not foreclose resort to the
Seoul, Korea pursuant to Art. 15 of the Contract as made with the arbitral or to the arbitral tribunal. courts for provisional reliefs. The
amended. Thus, it is incumbent upon PGSMC to abide by its extent that the arbitral tribunal (g) A party who does not comply Rules of the ICC, which governs the
commitment to arbitrate. has no power to act or is unable with the order shall be liable for all parties' arbitral dispute, allows the
Corollarily, the trial court gravely abused its discretion in to act effectivity, the request may damages resulting from application of a party to a judicial
granting PGSMC's Motion for Inspection of Things on be made with the Court. The noncompliance, including all authority for interim or
September 21, 1998, as the subject matter of the motion is arbitral tribunal is deemed expenses, and reasonable conservatory measures. Likewise,
under the primary jurisdiction of the mutually agreed constituted when the sole attorney's fees, paid in obtaining Section 14 of Republic Act (R.A.)
arbitral body, the KCAB in Korea. arbitrator or the third arbitrator, the order's judicial enforcement. No. 876 (The Arbitration Law)
In addition, whatever findings and conclusions made by the who has been nominated, has (Emphasis ours.) recognizes the rights of any party
RTC Branch Sheriff from the inspection made on October accepted the nomination and Art. 17 (2) of the UNCITRAL Model Law on ICA defines an to petition the court to take
28, 1998, as ordered by the trial court on October 19, 1998, written communication of said "interim measure" of protection as: measures to safeguard and/or
is of no worth as said Sheriff is not technically competent to nomination and acceptance has Article 17. Power of arbitral conserve any matter which is the
ascertain the actual status of the equipment and been received by the party making tribunal to order interim measures subject of the dispute in arbitration.
machineries as installed in the plant. the request. xxx xxx xxx In addition, R.A. 9285, otherwise
For these reasons, the September 21, 1998 and October 19, (b) The following rules on interim (2) An interim measure is known as the "Alternative Dispute
1998 RTC Orders pertaining to the grant of the inspection or provisional relief shall be any temporary measure, whether Resolution Act of 2004," allows the
of the equipment and machineries have to be recalled and observed: in the form of an award or in filing of provisional or interim
nullified. Any party may request that another form, by which, at any time measures with the regular courts
Issue on ownership of plant proper for arbitration provisional relief be granted prior to the issuance of the award whenever the arbitral tribunal has
Petitioner assails the CA ruling that the issue petitioner against the adverse party. by which the dispute is finally no power to act or to act
raised on whether the total contract price of USD 1,530,000 Such relief may be granted: decided, the arbitral tribunal effectively. 50 AacCIT
was for the whole plant and its installation is beyond the (i) to prevent orders a party to: It is thus beyond cavil that the RTC has authority and
ambit of a Petition for Certiorari. irreparable (a) Maintain or restore the status jurisdiction to grant interim measures of protection.
Petitioner's position is untenable. loss or quo pending determination of the Secondly, considering that the equipment and machineries
It is settled that questions of fact cannot be raised in an injury; dispute; are in the possession of PGSMC, it has the right to protect
original action for certiorari. 49 Whether or not there was (ii) to provide security (b) Take action that would prevent, and preserve the equipment and machineries in the best
full payment for the machineries and equipment and for the or refrain from taking action that is way it can. Considering that the LPG plant was non-
installation is indeed a factual issue prohibited by Rule 65. performance likely to cause, current or imminent operational, PGSMC has the right to dismantle and transfer
However, what appears to constitute a grave abuse of of any harm or prejudice to the arbitral the equipment and machineries either for their protection
discretion is the order of the RTC in resolving the issue on obligation; process itself; DTISaH and preservation or for the better way to make good use of
the ownership of the plant when it is the arbitral body (iii) to produce or (c) Provide a means of preserving them which is ineluctably within the management
(KCAB) and not the RTC which has jurisdiction and preserve any assets out of which a subsequent discretion of PGSMC.
authority over the said issue. The RTC's determination of evidence; or award may be satisfied; or Thirdly, and of greater import is the reason that
such factual issue constitutes grave abuse of discretion and (iv) to compel any other (d) Preserve evidence that may be maintaining the equipment and machineries in Worth's
must be reversed and set aside. appropriate relevant and material to the property is not to the best interest of PGSMC due to the
RTC has interim jurisdiction to protect the rights act or resolution of the dispute. prohibitive rent while the LPG plant as set-up is not
of the parties omission. Art. 17 J of UNCITRAL Model Law on ICA also grants courts operational. PGSMC was losing PhP322,560 as monthly
Anent the July 23, 1998 Order denying the issuance of the (c) The order granting provisional power and jurisdiction to issue interim measures: rentals or PhP3.87M for 1998 alone without considering
injunctive writ paving the way for PGSMC to dismantle and relief may be conditioned upon the Article 17 J. Court-ordered interim the 10% annual rent increment in maintaining the plant.
transfer the equipment and machineries, we find it to be in provision of security or any act or measures Fourthly, and corollarily, while the KCAB can rule on
order considering the factual milieu of the instant omission specified in the order. A court shall have the same power motions or petitions relating to the preservation or transfer
case. AcDaEH of issuing an interim measure in of the equipment and machineries as an interim measure,
yet on hindsight, the July 23, 1998 Order of the RTC Court (RTC), Branch 267, Pasig City, and Linberg Philippines, The energy fees payable to choice, while the other two (2) to
allowing the transfer of the equipment and machineries Inc., respondents." LINBERG shall be on the basis of be each chosen by the parties
given the non-recognition by the lower courts of the The facts of this case are: actual KWH generated by the plant. themselves, within fourteen (14)
arbitral clause, has accorded an interim measure of Fiesta World Mall Corporation, petitioner, owns and However, if the actual KWH days after the due date for such
protection to PGSMC which would otherwise been operates Fiesta World Mall located at Barangay Maraouy, generated is less than the minimum invoice and all or any part of the
irreparably damaged. Lipa City; while Linberg Philippines, Inc., respondent, is a energy off-take level, the disputed amount paid to LINBERG
Fifth, KOGIES is not unjustly prejudiced as it has already corporation that builds and operates power plants. calculation of the energy fees shall shall be paid together with interest
been paid a substantial amount based on the contract. On January 19, 2000, respondent filed with the Regional be made as if LINBERG has pursuant to Article XXV from the
Moreover, KOGIES is amply protected by the arbitral action Trial Court (RTC), Branch 267, Pasig City, a Complaint for generated the minimum energy off- due date of the invoice. It is agreed,
it has instituted before the KCAB, the award of which can Sum of Money against petitioner, docketed as Civil Case No. take level of 988,888 KW-HR per however, that both parties must
be enforced in our jurisdiction through the RTC. Besides, by 67755. The complaint alleges that on November 12, 1997, month. SCaEcD resolve the disputes within thirty
our decision, PGSMC is compelled to submit to arbitration petitioner and respondent executed a build-own-operate The complaint further alleges that respondent constructed (30) days, otherwise any delay in
pursuant to the valid arbitration clause of its contract with agreement, entitled "Contract Agreement for Power Supply the power plant in Lipa City at a cost of about payment resulting to loss to
KOGIES. Services, 3.8 MW Base Load Power Plant" 4 (the Contract). P130,000,000.00. In November 1997, the power plant LINBERG when converted to $US as
PGSMC to preserve the subject equipment and Under this Contract, respondent will construct, at its own became operational and started supplying a result of depreciation of the Pesos
machineries cost, and operate as owner a power plant, and to supply power/electricity to petitioner's shopping mall in Lipa City. shall be for the account of FIESTA
Finally, while PGSMC may have been granted the right to petitioner power/electricity at its shopping mall in Lipa In December 1997, respondent started billing petitioner. As WORLD. Corollarily, in case of
dismantle and transfer the subject equipment and City. Petitioner, on the other hand, will pay respondent of May 21, 1999, petitioner's unpaid obligation amounted erroneous billings, however,
machineries, it does not have the right to convey or dispose "energy fees" to be computed in accordance with the to P15,241,747.58, exclusive of interest. However, LINBERG shall be liable to pay
of the same considering the pending arbitral proceedings to Seventh Schedule of the Contract, the pertinent portions of petitioner questioned the said amount and refused to pay FIESTA WORLD for the cost of such
settle the differences of the parties. PGSMC therefore must which provide: despite respondent's repeated demands. deterioration, plus interest
preserve and maintain the subject equipment and 2.1 . . . In its Answer with Compulsory Counterclaim, petitioner computed pursuant to Art. XXV
machineries with the diligence of a good father of a E1 988,888 kw-hr x BER specifically denied the allegations in the complaint, from the date FIESTA WORLD paid
family 51 until final resolution of the arbitral proceedings E2 (ED-988,888) x BER claiming that respondent failed to fulfill its obligations for the erroneous billing.
and enforcement of the award, if any. Where: under the Contract by failing to supply all its power/fuel (Underscoring supplied)
WHEREFORE, this petition is PARTLY GRANTED, in that: E1 & E2 Energy fees in pesos for needs. From November 10, 1998 until May 21, 1999, Thereafter, petitioner filed a Motion to Set Case for
the billing period. Where E1 is petitioner personally shouldered the cost of fuel. Petitioner Preliminary Hearing on the ground that respondent
(1) The May 30, 2000 CA Decision in CA-G.R. SP No. 49249 based on the minimum energy off- also disputed the amount of energy fees specified in the violated the arbitration clause provided in the Contract,
is REVERSED and SET ASIDE; take of 988,888 kw-hrs. billings made by respondent because the latter failed to thereby rendering its cause of action premature.
(2) The September 21, 1998 and October 19, 1998 RTC per month and E2 is based on the monitor, measure, and record the quantities of This was opposed by respondent, claiming that paragraph
Orders in Civil Case No. 98-117 are REVERSED and SET actual meter reading less electricity delivered by taking photographs of the 7.4 of the Contract on arbitration is not the provision
ASIDE; the minimum off-take. electricity meter reading prior to the issuance of its applicable to this case; and that since the parties failed to
(3) The parties are hereby ORDERED to submit themselves BER Base energy rate at Ps invoices and billings, also in violation of the settle their dispute, then respondent may resort to court
to the arbitration of their dispute and differences arising 2.30/Kw-Hr billing rate based on Contract. 5 Moreover, in the computation of the electrical action pursuant to paragraph 17.2 of the same Contract
from the subject Contract before the KCAB; and the exchange rate of Ps 26.20 to billings, the minimum off-take of energy (E2) was based which provides:
(4) PGSMC is hereby ALLOWED to dismantle and transfer the US dollar, and with solely on the projected consumption as computed by 17.2 Amicable Settlement
the equipment and machineries, if it had not done so, and fuel oil to be supplied by respondent. However, based on petitioner's actual The parties hereto agree that in the
ORDERED to preserve and maintain them until the finality LINBERG at its own cost. experience, it could not consume the energy pursuant to event there is any dispute or
of whatever arbitral award is given in the arbitration The base energy rate is subject to the minimum off-take even if it kept open all its lights difference between them arising
proceedings. exchange rate adjustment and operated all its machinery and equipment for out of this Agreement or in the
No pronouncement as to costs. IEAHca accordingly to the formula as twenty-four hours a day for a month. This fact was interpretation of any of the
SO ORDERED. follows: admitted by respondent. While both parties had provisions hereto, they shall
||| (Korea Technologies Co., Ltd. v. Lerma, G.R. No. 143581, BER 0.6426 + 0.3224 Pn + 1.345 Fn discussions on the questioned billings, however, "there endeavor to meet together in an
[January 7, 2008], 566 PHIL 1-39) 26.40 4.00 were no earnest efforts to resolve the differences in effort to resolve such dispute by
WHERE: accordance with the arbitration clause provided for in the discussion between them but
SECOND DIVISION Pn is defined as the average of the Contract." failing such resolution the Chief
[G.R. No. 152471. August 18, 2006.] Bangko Sentral ng Finally, as a special affirmative defense in its answer, Executives of LINBERG and
FIESTA WORLD MALL Pilipinas' published dealing rates petitioner alleged that respondent's filing of the complaint FIESTA WORLD shall meet to
CORPORATION, petitioner, vs. for thirty (30) trading is premature and should be dismissed on the ground of resolve such dispute or
LINBERG PHILIPPINES, days immediately prior to the new non-compliance with paragraph 7.4 of the Contract which difference and the joint decision of
INC.,respondent. billing rate. provides: such shall be binding upon the
DECISION Fn Weighted average of fuel price 7.4 Disputes parties hereto, and in the event
SANDOVAL-GUTIERREZ, J p: per liter based on the If FIESTA WORLD disputes the that a settlement of any such
For our resolution is the instant Petition for Review average of the last three (3) amount specified by any invoice, dispute or difference is not
on Certiorari 1 assailing the Decision 2 dated December 12, purchases made by LINBERG it shall pay the undisputed amount reached, then the provisions of
2001 and Resolution 3 dated February 28, 2002 rendered as evidenced by purchase invoices. on or before such date(s), and the Article XXI shall apply.
by the Court of Appeals in CA-G.R. SP No. 63671, entitled ED Energy delivered in kw-hrs per disputed amount shall be Article XXI, referred to in paragraph 17.2 above, reads:
"Fiesta World Mall Corporation, petitioner, versus Hon. meter reading. resolved by arbitration of three ARTICLE XXI
Florito S. Macalino, Presiding Judge of the Regional Trial 3. Minimum Energy Off-Take (3) persons, one (1) by mutual JURISDICTION
The parties hereto submit to the Moreover, we note that the computation of the energy fees submitted its report to the trial court. Costs against original and exclusive jurisdiction over the case.
exclusive jurisdiction of the proper disputed by petitioner also involves technical matters that respondent. Respondents moved for reconsideration but their motion
courts of Pasig City, Republic of are better left to an arbitration panel who has expertise in SO ORDERED. was denied.
the Philippines for the hearing those areas. Alternative dispute resolution methods or ||| (Fiesta World Mall Corp. v. Linberg Phil., Inc., G.R. No. Aggrieved, the respondents questioned the dismissal of
and determination of any action ADRs — like arbitration, mediation, negotiation and 152471, [August 18, 2006], 530 PHIL 729-738) their complaint in a petition for certiorari and prohibition
or proceeding arising out of or in conciliation — are encouraged by this Court. By enabling before the Court of Appeals.
connection with this the parties to resolve their disputes amicably, they provide SECOND DIVISION The Court of Appeals granted the petition in its Decision
Agreement. IDScTE solutions that are less time-consuming, less tedious, less [G.R. No. 171763. June 5, 2009.] dated August 31, 2005, the dispositive portion of which
In its Order dated October 3, 2000, the trial court denied confrontational, and more productive of goodwill and MARIA LUISA PARK reads:
petitioner's motion for lack of merit. lasting relationships. 9 To brush aside such agreement ASSOCIATION, INC., petitioner, vs. WHEREFORE, in view of all the
Petitioner then filed a Motion for Reconsideration but it providing for arbitration in case of disputes between the SAMANTHA MARIE T. foregoing, the petition
was denied in an Order dated January 11, 2001. parties would be a step backward. As we held in BF ALMENDRAS and PIA ANGELA T. is GRANTED and the assailed
Dissatisfied, petitioner elevated the matter to the Court of Corporation v. Court of Appeals, 10 ALMENDRAS, respondents. orders of the respondent trial court
Appeals via a Petition for Certiorari, docketed as CA-G.R. SP It should be noted that in this DECISION are declared NULL AND VOID,
No. 63671. On December 12, 2001, the appellate court jurisdiction, arbitration has been QUISUMBING, J p: and SET ASIDE. Respondent RTC is
rendered its Decision dismissing the petition and affirming held valid and constitutional. Even This petition for review on certiorari assails the hereby ordered to take jurisdiction
the challenged Orders of the trial court. before the approval on June 19, Decision 1 dated August 31, 2005 and the of Civil Case No. CEB-29002.
Petitioner's Motion for Reconsideration of the above 1953 of Republic Act No. 876 (The Resolution 2 dated February 13, 2006 of the Court of SO ORDERED. 8
Decision was likewise denied by the appellate court in its Arbitration Law), this Court has Appeals in CA-G.R. SP No. 81069. MLPAI filed a motion for reconsideration but it was denied
Resolution 6 dated February 28, 2002. countenanced the settlement of The facts, culled from the records, are as follows: by the Court of Appeals in its Resolution dated February 13,
Hence, the instant Petition for Review on Certiorari. disputes through arbitration On February 6, 2002, respondents Samantha Marie T. 2006.
The sole issue for our resolution is whether the filing with (Puromines, Inc. v. Court of Appeals, Almendras and Pia Angela T. Almendras purchased from Hence, this petition raising the following issues:
the trial court of respondent's complaint is premature. G.R. No. 91228, March 22, 1993, MRO Development Corporation a residential lot located in I.
Paragraph 7.4 of the Contract, quoted earlier, mandates 220 SCRA 281-290). Republic Act Maria Luisa Estate Park, Banilad, Cebu City. After some WHETHER THE HONORABLE
that should petitioner dispute any amount of energy fees in No. 876 was adopted to supplement time, respondents filed with petitioner Maria Luisa Park COURT OF APPEALS HAS
the invoice and billings made by respondent, the same the New Civil Code's provisions on Association, Incorporated (MLPAI) an application to DISREGARDED LAWS AND WELL-
"shall be resolved by arbitration of three (3) persons, arbitration (Chung Fu Industries construct a residential house, which was approved SETTLED JURISPRUDENCE IN
one (1) by mutual choice, while the other two (2) to be Phils., Inc. v. Court of Appeals, G.R. in * February 10, 2002. Thus, respondents commenced the HOLDING THAT JURISDICTION
each chosen by the parties themselves." The parties, in No. 92683, February 25, 1992, 206 construction of their house. OVER [THE] DISPUTE BETWEEN
incorporating such agreement in their Contract, expressly SCRA 545, 551). Its potentials as Upon ocular inspection of the house, MLPAI found out that HOMEOWNERS AND
intended that the said matter in dispute must first be one of the alternative dispute respondents violated the prohibition against multi- HOMEOWNERS' ASSOCIATION LIES
resolved by an arbitration panel before it reaches the resolution methods that are now dwelling 3 stated in MLPAI's Deed of Restriction. WITH THE REGULAR COURTS AND
court. They made such arbitration mandatory. rightfully vaunted as 'the wave of Consequently, on April 28, 2003, MLPAI sent a letter to the NOT WITH HLURB.
It is clear from the records that petitioner disputed the the future' in international respondents, demanding that they rectify the structure; II.
amount of energy fees demanded by respondent. However, relations, is recognized worldwide. otherwise, it will be constrained to forfeit respondents' WHETHER THERE IS NO OTHER
respondent, without prior recourse to arbitration as o brush aside a contractual construction bond and impose stiffer penalties. RELIEF AND REMEDY AVAILABLE
required in the Contract, filed directly with the trial court agreement calling for arbitration in In a Letter 4 dated April 29, 2003, respondents, as TO PETITIONER TO AVERT THE
its complaint, thus violating the arbitration clause in the case of disagreement between the represented by their father Ruben D. Almendras denied CONDUCT OF A VOID
Contract. parties would therefore be a step having violated MLPAI's Deed of Restriction. IDSaEA [PROCEEDING] THAN THE
It bears stressing that such arbitration agreement is the law backward. IECAaD On May 5, 2003, MLPAI, in its reply, pointed out PRESENT RECOURSE. 9
between the parties. Since that agreement is binding In this connection, since respondent has already filed a respondents' specific violations of the subdivision rules, to Simply stated, the issue is whether the appellate court
between them, they are expected to abide by it in good complaint with the trial court without prior recourse to wit: (a) installation of a second water meter and tapping erred in ruling that it was the trial court and not the HLURB
faith. 7 And because it covers the dispute between them in arbitration, the proper procedure to enable an arbitration the subdivision's main water pipeline, and (b) construction that has jurisdiction over the case.
the present case, either of them may compel the other to panel to resolve the parties' dispute pursuant to their of "two separate entrances that are mutually exclusive of Petitioner MLPAI contends that the HLURB 10 has
arbitrate. 8 Thus, it is well within petitioner's right to Contract is for the trial court to stay the each other". It likewise reiterated its warning that failure to exclusive jurisdiction over the present controversy, it being
demand recourse to arbitration. proceedings. 11 After the arbitration proceeding has been comply with its demand will result in its exercise of more a dispute between a subdivision lot owner and a
We cannot agree with respondent that it can directly seek pursued and completed, then the trial court may confirm stringent measures. subdivision association, where the latter aimed to compel
judicial recourse by filing an action against petitioner the award made by the arbitration panel. 12 In view of these, respondents filed with the Regional Trial respondents to comply with the MLPAI's Deed of
simply because both failed to settle their differences In sum, we hold that the Court of Appeals erred in Court of Cebu City, Branch 7, a Complaint 5 on June 2, 2003 Restriction, specifically the provision prohibiting multi-
amicably. Suffice it to state that there is nothing in the disregarding the arbitration clause in the parties' for Injunction, Declaratory Relief, Annulment of Provisions dwelling.
Contract providing that the parties may dispense with Contract. 3upjur06 of Articles and By-Laws with Prayer for Issuance of a Respondents, on the other hand, counter that the case they
the arbitration clause. Article XXI on jurisdiction cited by WHEREFORE, we GRANT the instant petition. The assailed Temporary Restraining Order (TRO)/Preliminary filed against MLPAI is one for declaratory relief and
respondent, i.e., that "the parties hereto submit to the Decision and Resolution of the Court of Appeals in CA-G.R. Injunction. annulment of the provisions of the by-laws; hence, it is
exclusive jurisdiction of the proper courts of Pasig City" SP No. 63671 are REVERSED. The parties are ordered to MLPAI moved for the dismissal of the complaint on the outside the competence of the HLURB to resolve. They
merely provides for the venue of any action arising out of submit their controversy to the arbitration panel pursuant ground of lack of jurisdiction and failure to comply with the likewise stated that MLPAI's rules and regulations are
or in connection with the stipulations of the parties in the to paragraph 7.4 of the Contract. The Regional Trial Court, arbitration clause 6 provided for in MLPAI's by-laws. discriminatory and violative of their basic rights as
Contract. Branch 267, Pasig City is directed to suspend the In an Order 7 dated July 31, 2003, the trial court dismissed members of the association. They also argued that MLPAI's
proceedings in Civil Case No. 67755 until after the the complaint for lack of jurisdiction, holding that it was the acts are illegal, immoral and against public policy and that
Arbitration Panel shall have resolved the controversy and Housing and Land Use Regulatory Board (HLURB) that has
they did not commit any violation of the MLPAI's Deed of Disputes Triable by HIGC/Nature of The provisions of P.D. No. 957 were intended to encompass administrative tribunal to determine technical and intricate
Restriction. Proceedings all questions regarding subdivisions and condominiums. matters of fact. 29
We agree with the trial court that the instant controversy Section 1. Types of Disputes. — The The intention was aimed at providing for an appropriate In the instant case, the HLURB has the expertise to resolve
falls squarely within the exclusive and original jurisdiction HIGC or any person, officer, body, government agency, the HLURB, to which all parties the basic technical issue of whether the house built by the
of the Home Insurance and Guaranty Corporation board or committee duly aggrieved in the implementation of provisions and the respondents violated the Deed of Restriction, specifically
(HIGC), 11 now HLURB. designated or created by it shall enforcement of contractual rights with respect to said the prohibition against multi-dwelling.IcaHCS
Originally, administrative supervision over homeowners' have jurisdiction to hear and decide category of real estate may take recourse. The business of As observed in C.T. Torres Enterprises, Inc. v. Hibionada: 30
associations was vested by law with the Securities and cases involving the following: developing subdivisions and corporations being imbued The argument that only courts of
Exchange Commission (SEC). However, pursuant xxx xxx xxx with public interest and welfare, any question arising from justice can adjudicate claims
to Executive Order No. 535, 12 the HIGC assumed the (b) Controversies arising out of the exercise of that prerogative should be brought to the resoluble under the provisions of
regulatory and adjudicative functions of the SEC over intra-corporate relations between HLURB which has the technical know-how on the the Civil Code is out of step with the
homeowners' associations. Section 2 of E.O. No. and among members of the matter. 21 In the exercise of its powers, the HLURB must fast-changing times. There are
535provides: association, between any or all of commonly interpret and apply contracts and determine the hundreds of administrative bodies
2. In addition to the powers and them and the association of rights of private parties under such contracts. This ancillary now performing this function by
functions vested under the Home which they are members, and power is no longer a uniquely judicial function, exercisable virtue of a valid authorization from
Financing Act, the Corporation, between such association and the only by the regular courts. 22 the legislature. This quasi-judicial
shall have among others, the state/general public or other entity function, as it is called, is exercised
following additional powers: in so far as it concerns its right to It is apparent that although the complaint was by them as an incident of the
(a) . . . and exercise all the powers, exist as a corporate denominated as one for declaratory relief/annulment of principal power entrusted to them
authorities and responsibilities that entity. 16 (Emphasis supplied.) contracts, the allegations therein reveal otherwise. It of regulating certain activities
are vested on the Securities and xxx xxx xxx should be stressed that respondents neither asked for the falling under their particular
Exchange Commission with respect Later on, the above-mentioned powers and responsibilities, interpretation of the questioned by-laws nor did they allege expertise.
to homeowners associations, the which had been vested in the HIGC with respect to that the same is doubtful or ambiguous and require judicial In the Solid Homes case for
provision of Act 1459, as amended homeowners' associations, were transferred to the HLURB construction. In fact, what respondents really seek to example the Court affirmed
by P.D. 902-A, to the contrary pursuant to Republic Act No. 8763, 17 entitled "Home accomplish is to have a particular provision of the MLPAI's the competence of the Housing
notwithstanding; Guaranty Corporation Act of 2000". by-laws nullified and thereafter absolve them from any and Land Use Regulatory Board
(b) To regulate and supervise the In the present case, there is no question that respondents violations of the same. 23 InKawasaki Port Service to award damages although this
activities and operations of all are members of MLPAI as they have even admitted Corporation v. Amores, 24 the rule was stated: is an essentially judicial power
houseowners associations it. 18 Therefore, as correctly ruled by the trial court, the . . . where a declaratory judgment as exercisable ordinarily only by
registered in accordance therewith; case involves a controversy between the homeowners' to a disputed fact would be the courts of justice. This
xxx xxx xxx association and some of its members. Thus, the exclusive determinative of issues rather than departure from the traditional
Moreover, by virtue of this amendatory law, the HIGC also and original jurisdiction lies with the HLURB. a construction of definite stated allocation of governmental powers
assumed the SEC's original and exclusive jurisdiction under Indeed, in Sta. Clara Homeowners' Association v. Gaston, we rights, status and other relations, is justified by expediency, or the
Section 5 of Presidential Decree No. 902-A to hear and held: commonly expressed in written need of the government to respond
decide cases involving: . . . the HIGC exercises limited instrument, the case is not one for swiftly and competently to the
b) Controversies arising out of jurisdiction over homeowners' declaratory judgment. 25 pressing problems of the modern
intra-corporate or partnership disputes. The law confines its Contrary to the observation of the Court of Appeals, world. 31
relations, between and among authority to controversies that jurisdiction cannot be made to depend on the exclusive We also note that the parties failed to abide by the
stockholders, members, or arise from any of the following characterization of the case by one of the parties. 26 While arbitration agreement in the MLPAI by-laws. Article XII of
associates; between any and/or intra-corporate relations: (1) respondents are questioning the validity or legality of the the MLPAI by-laws entered into by the parties provide:
all of them and the corporation, between and among members of MLPAI's articles of incorporation and its by-laws, they did Mode of Dispute Resolution
partnership or association of the association; (2) between any not, however, raise any legal ground to support its Mode of Dispute Resolution. Should
which they are stockholders, and/or all of them and the nullification. The legality of the by-laws in its entirety was any member of the Association
members or associates, association of which they are never an issue in the instant controversy but merely the have any grievance, dispute or
respectively; and between such members; and (3) between the provision prohibiting multi-dwelling which respondents claim against the Association or any
corporation, partnership or association and the state insofar as assert they did not violate. 27 So to speak, there is no of the officers and governors
association and the state insofar as the controversy concerns its right justiciable controversy here that would warrant thereof in connection with their
it concerns their individual to exist as a corporate declaratory relief, or even an annulment of contracts. function and/or position in the
franchise or right to exist as such entity. 19 (Emphasis supplied.) We reiterate that in jurisdictional issues, what determines Association, the parties shall
entity; 13 (Emphasis The extent to which the HLURB has been vested with quasi- the nature of an action for the purpose of ascertaining endeavor to settle the same
supplied.) aCTcDH judicial authority must also be determined by referring to whether a court has jurisdiction over a case are the amicably. In the event that efforts
xxx xxx xxx Section 3 of P.D. No. 957, 20 which provides: allegations in the complaint and the nature of the relief at amicable settlement fail, such
Consequently, in Sta. Clara Homeowners' Association v. SEC. 3. National Housing sought. 28 dispute, difference or disagreement
Gaston 14 and Metro Properties, Inc. v. Magallanes Village Authority. — The National Housing Moreover, under the doctrine of primary administrative shall be brought by the member to
Association, Inc., 15 the Court recognized HIGC's "Revised Authority shall have exclusive jurisdiction, courts cannot or will not determine a an arbitration panel composed of
Rules of Procedure in the Hearing of Home Owner's jurisdiction to regulate the real controversy where the issues for resolution demand the three (3) arbitrators for final
Disputes", pertinent portions of which are reproduced estate trade and business in exercise of sound administrative discretion requiring the settlement, to the exclusion of all
below: accordance with the provisions of special knowledge, experience, and services of the other fora. Such arbitration may be
RULE II this Decree. (Emphasis supplied.) initiated by giving notice to the
other party, such notice designating MLPAI, are bound by its by-laws, and are expected to abide carrier (with a negotiable bill of lading or other SUPREME COURT DECISIONS
one (1) independent arbitrator. by it in good faith. 33 contract of carriage with respect to cargo) or a HOLDING THAT ARBITRATION IS A
Within thirty (30) from the receipt In the instant case, we observed that while both parties containership operator (owner, operator or CONDITION PRECEDENT TO SUIT
of said notice, the other party shall exchanged correspondence pertaining to the alleged charterer of containership on which the cargo is carried). WHERE SUCH AN AGREEMENT TO
designate a second independent violation of the Deed of Restriction, they, however, made no During the lifetime of the said Agreement, or on 18 May ARBITRATE EXISTS.
arbitrator by written notice to the earnest effort to resolve their differences in accordance 1991, Florex International, Inc. (hereinafter referred to as II
first party. Both arbitrators shall with the arbitration clause provided for in their by-laws. "Florex") delivered to private respondent AMML THE COURT OF APPEALS HAS
within fifteen (15) days thereafter Mere exchange of correspondence will not suffice much cargo of various foodstuffs, with Oakland, California as RULED IN A MANNER NOT IN
select a third independent less satisfy the requirement of arbitration. Arbitration port of discharge and San Francisco as place of delivery. ACCORD WITH JURISPRUDENCE
arbitrator, who shall be the being the mode of settlement between the parties expressly The corresponding Bill of Lading No. MAEU MNL110263 WHEN IT REFUSED TO HAVE THE
chairman of the Arbitration provided for in their by-laws, the same should be was issued to Florex by respondent AMML. Pursuant to the THIRD-PARTY COMPLAINT
Tribunal. In the event that the two respected. Unless an arbitration agreement is such as Agreement, respondent AMML loaded the subject cargo on DISMISSED FOR FAILURE TO
(2) arbitrators respectively absolutely to close the doors of the courts against the MS Sealand Pacer, a vessel owned by petitioner. Under this STATE A CAUSE OFACTION AND
nominated by the parties fail to parties, the courts should look with favor upon such arrangement, therefore, respondent AMML was the FOR RULING THAT THE FAILURE
select the third independent amicable arrangements. 34 principal carrier while petitioner was the containership TO STATE A CAUSE OF ACTION
arbitrator within the fifteen-day Arbitration is one of the alternative methods of dispute operator. MAY BE REMEDIED BY
period, the third arbitrator shall be resolution that is now rightfully vaunted as "the wave of The consignee refused to pay for the cargo, alleging that REFERENCE TO ITS
jointly selected by the parties. In the future" in international relations, and is recognized delivery thereof was delayed. Thus, on June 26, 1992, ATTACHMENTS. 8
the event that the other party does worldwide. To brush aside a contractual agreement calling Florex filed a complaint against respondent Maersk- Resolving first the issue of failure to state a cause of action,
not nominate an arbitrator, the for arbitration in case of disagreement between the parties Tabacalera Shipping Agency (Filipinas), Inc. for respondent Court of Appeals did not err in reading the
Arbitration Tribunal shall be would therefore be a step backward. 35 reimbursement of the value of the cargo and other Complaint of Florex and respondent AMML's Answer
composed of one (1) arbitrator WHEREFORE, the instant petition is GRANTED. The charges. 3 According to Florex, the cargo was received by together with the Third Party Complaint to determine
nominated by the party initiating Decision dated August 31, 2005 and Resolution dated the consignee only on June 28, 1991, since it was whether a cause of action is properly alleged. In Fil-Estate
the proceedings. The Arbitration February 13, 2006 of the Court of Appeals in CA-G.R. SP No. discharged in Long Beach, California, instead of in Oakland, Golf and
Tribunal shall render its decision 81069 are SET ASIDE. The Order dated July 31, 2003 of the California on June 5, 1991 as stipulated. dctai Development, Inc. vs. Court ofAppeals, 9 this Court ruled that
within forty-five (45) days from the Regional Trial Court of Cebu City, Branch 7, is Respondent AMML filed its Answer 4 alleging that even on in the determination of whether or not the complaint states
selection of the third arbitrator, hereby REINSTATED. the assumption that Florex was entitled to reimbursement, a cause of action, the annexes attached to the complaint
which decision shall be valid and SO ORDERED. it was petitioner who should be liable. Accordingly, may be considered, they being parts of the complaint. llcd
binding between the parties unless ||| (Maria Luisa Park Ass'n, Inc. v. Almendras, G.R. No. respondent AMML filed a Third Party Complaint 5 against Coming now to the main issue of arbitration, the pertinent
repudiated within five (5) days 171763, [June 5, 2009], 606 PHIL 670-686) petitioner on November 10, 1992, averring that whatever clauses of the "Co-operation in the Pacific" contract entered
from receipt thereof on grounds damages sustained by Florex were caused by petitioner, into by the parties provide:
that the same was procured FIRST DIVISION which actually received and transported Florex's cargo on 16.2 For the purposes of this
through fraud or violence, or that [G.R. No. 126212. March 2, 2000.] its vessels and unloaded them. agreement the
there are patent or gross errors in SEA- On January 1, 1993, petitioner filed a Motion to Dismiss the Containership Operator
facts made basis of the decision. LAND SERVICE, INC., petitioner, vs. Third Party Complaint 6 on the ground of failure to state a shall be deemed to have
The award of the Tribunal shall be COURT OF APPEALS, A.P. cause of action and lack of jurisdiction, the issued to the Principal
enforced by a court of competent MOLLER/MAERSK LINE and amount of damages not having been specified therein. Carrier for good
jurisdiction. Venue of action MAERSK-TABACALERA SHIPPING Petitioner also prayed either for dismissal or consideration and for
covered by this Article shall be in AGENCY suspension of the Third Party Complaint on the ground that both loaded and empty
the courts of justice of Cebu City (FILIPINAS), INC., respondents. there exists an arbitration agreement between it and containers its non-
only. DECISION respondent AMML. On September 27, 1993, the negotiable memo
Under the said provision of the by-laws, any dispute or YNARES-SANTIAGO, J p: lowercourt issued an Order denying petitioner's Motion to bills of lading in the form
claim against the Association or any of its officers and This petition for review on certiorari seeks to annul and set Dismiss. Petitioner's Motion for Reconsideration was attached hereto as
governors shall first be settled amicably. If amicable aside the decision of the Court of Appeals dated September likewise denied by the lower court in its August 22, 1994 Appendix 6, consigned
settlement fails, such dispute shall be brought by the 29, 1995 in CA-G.R. SP No. 35777, 1 dismissing the petition Order. LLpr only to the Principal
member to an arbitration panel for final settlement. The for certiorari filed by petitioner to annul the two (2) orders Undaunted, petitioner filed a petition for certiorari 7 with Carrier or its agents,
arbitral award shall be valid and binding between the issued by the Regional Trial Court of Quezon City, Branch the Court of Appeals on November 23, 1994. Meanwhile, provisions of which shall
parties unless repudiated on grounds that the same was 216, in Civil Case No. Q-92-12593. petitioner also filed its Answer to the Third Party govern the liability
procured through fraud or violence, or that there are The facts are as follows: LLpr Complaint in the trial court. between the Principal
patent or gross errors in the tribunal's findings of facts On April 29, 1991, petitioner Sea-Land Services, Inc. and On September 29, 1995, Carrier and the
upon which the decision was based. private respondent A.P. Moller/Maersk Line (hereinafter respondent Court of Appeals rendered the assailed Containership Operator
The terms of Article XII of the MLPAI by-laws clearly referred to as "AMML"), both carriers of cargo in Decision dismissing the petition for certiorari. With the and that for the
express the intention of the parties to bring first to the containerships as well as common carriers, entered into a denial of its Motion for Reconsideration, petitioner filed the purpose of determining
arbitration process all disputes between them before a contract entitled, "Co-operation in the instant petition for review, raising the following issues — the liability in
party can file the appropriate action. The agreement to Pacific" 2 (hereinafter referred to as the "Agreement"), a I accordance with either
submit all disputes to arbitration is a contract. As such, the vessel sharing agreement whereby they mutually agreed to THE COURT OF APPEALS DISREGA Lines' memo
arbitration agreement binds the parties thereto, as well as purchase, share and exchange needed space for cargo in RDED AN AGREEMENT TO bill of lading, the
their assigns and heirs. 32 Respondents, being members of their respective containerships. Under the Agreement, they ARBITRATE IN number of packages or
could be, depending on the occasion, either a principal VIOLATION OF STATUTE AND customary freight units
shown on the to the Containership the appointment, the between the Principal Carrier and the Containership
bill of lading issued by Operator provided that party appointing the Operator arising from contracts of carriage shall be
the Principal Carrier to notice of any extension third Arbitrator shall, governed by the provisions of the bills of lading deemed
its shippers shall be so granted is given to the after application from issued to the Principal Carrier by the Containership
controlling. cdphil Containership Operator the party having Operator. On the other hand, to sustain the Third Party
16.3 The Principal Carrier shall use within 30 days of any appointed his Arbitrator, Complaint would be to allow private respondent to hold
all reasonable such extension being also appoint an petitioner liable under the provisions of the bill of lading
endeavours to defend granted. cdll Arbitrator in issued by the Principal Carrier to Florex, under which the
all in personam and in xxx xxx xxx behalf of the party latter is suing in its Complaint, not under the bill of lading
rem suits for loss of or 32. ARBITRATION making default. petitioner, as containership operator, issued to respondent
damage to cargo carried 32.1 If at any time a dispute or 32.5 Any such arbitration shall be AMML, as Principal Carrier, contrary to what is
pursuant to claim arises out of or in in accordance with contemplated in Clause 16.2.
bills of lading issued by connection with the the Arbitration Act 1950 The Court of Appeals ruled that the terms of the Agreement
it, or to settle such suits Agreement the Lines as amended by "explicitly required that the principal carrier's claim
for as low a figure as shall endeavour to settle theArbitration Act 1979 against the containership operator first be finally
reasonably possible. The such amicably, failing or any other subsequent determined by, among others, a court judgment, before the
Principal Carrier shall which it shall be referred legislation and the right to arbitration accrues." However,
have the right to seek to arbitration by a single arbitrator's award shall the Court of Appeals failed to consider that,
damages and/or an arbitrator in London, be final and binding precisely,arbitration is the mode by which the
indemnity from the such arbitrator to be upon Lines. To the extent liability of the Containership Operator may be finally
Containership Operator appointed by agreement permitted by determined. This is clear from the mandate of Clause 16.3
by arbitrationpursuant to between the Lines within the Arbitration Act 1979 that "(T)he Principal Carrier shall have the right to seek
Clause 32 14 days after service by the Lines hereto exclude damages and/or an indemnity from the Containership
hereof. Notwithstanding one Line upon the pursuant to S Operator by arbitration" and that it "shall be entitled to
the provisions of the other of a notice 3(1) of that Act the commence such arbitration at any time until one year after
Lines' memo specifying the jurisdiction of the its liability has been finally determined by
bills of lading or any nature of the dispute or English agreement, arbitration award or judgment."
statutory claim and requiring High Court of Justice to For respondent Court of Appeals to say that the
rules incorporated therei reference of such dispute entertain any appeal or terms of the contract do not require arbitration as a
n or applicable or claim application under condition precedent to judicial action is erroneous. In the
thereto, the Principal to arbitration pursuant Section 1 and light of the Agreement clauses aforequoted, it is clear
Carrier shall be entitled to this Article. 2 of the Arbitration Act 1 that arbitration is the mode provided by which respondent
to commence 32.2 Failing agreement upon an 979. 10 AMML as Principal Carrier can seek damages and/or
such arbitration at any arbitrator within such From the foregoing, the following matters are indemnity from petitioner, as Containership Operator.
time until one year after period of 14 days, the clear: First, disputes between the Principal Carrier and the Stated differently, respondent AMML is barred from taking
its liability has been dispute shall be settled Containership Operator arising from contracts of carriage judicial action against petitioner by the clear terms of their
finally determined by by three Arbitrators, shall be governed by the provisions of the bills oflading Agreement. LexLib
agreement, arbitration a each party appointing issued to the Principal Carrier by the Containership As the Principal Carrier with which Florex directly dealt
ward or judgment, such one Arbitrator, the third Operator. Second, the Principal Carrier shall use its best with, respondent AMML can and should be held
award or judgment not being appointed by the efforts to defend or settle all suits against it for loss of or accountable by Florex in the event that it has a valid claim
being the President of the London damage to cargo pursuant to bills of lading issued by against the former. Pursuant to Clause 16.3 of the
subject of appeal, Maritime Arbitrators it. Third, the Principal Carrier shall have the right to seek Agreement, respondent AMML, when faced with such a suit
provided that the Association. damages and/or indemnity from the Containership "shall use all reasonable endeavours to defend" itself or
Containership Operator 32.3 If either of the appointed Operator by arbitration, pursuant to Clause 32 of the "settle such suits for as low a figure as reasonably
has been given Arbitrators refuses or is agreement. Fourth, the Principal Carrier shall have the right possible." In turn, respondent AMML can seek damages
notice of the said claim in incapable of acting, the to commence such arbitration any time until one year after and/or indemnity from petitioner as Containership
writing by the Principal party who appointed its liability has been finally determined by Operator for whatever final judgment may be adjudged
Carrier within three him shall appoint a new agreement, arbitration award or judgment, provided that against it under the Complaint of Florex. The crucial point
months of the Principal Arbitrator in his place. the Containership Operator was given notice in writing by is that collection of said damages and/or indemnity from
Carrier receiving notice 32.4 If one of the parties fails to the Principal Carrier within three months of the Principal petitioner should be by arbitration.
in writing of the appoint an Arbitrator — Carrier receiving notice in writing of said claim. dctai All told, when the text of a contract is explicit and leaves no
claim. Further the either originally or by doubt as to its intention, the court may not read into it any
Principal Carrier shall way of substitution — Prescinding from the foregoing matters, we find that both other intention that would contradict its plain
have the right to grant for two weeks after the the trial court and the Court of Appeals erred in denying import. 11 Arbitration being the mode of settlement
extensionsof time for the other party having petitioner's prayer for arbitration. between the parties expressly provided for by their
commencement of suit to appointed his Arbitrator To begin with, allowing respondent AMML's Third Party Agreement, the Third Party Complaint should have been
any third party has sent the party Claim against petitioner to proceed would be in dismissed.
interested in the cargo making default notice by violation of Clause 16.2 of the Agreement. As summarized, This Court has previously held that arbitration is one of the
without prior reference mail, fax or telex to make the clause provides that whatever dispute there may be alternative methods of dispute resolution that is now
rightfully vaunted as "the wave of the future" in examination of the mining claims for the purpose of pick-up checks from Benguet representing such royalties. The Court's Ruling
international relations, and is recognized worldwide. To determining whether or not they are worth developing However, starting August 1994, J.G. Realty allegedly Before we dwell on the substantive issues, we find that the
brush aside a contractual agreement calling with reasonable probability of profitable production. refused to collect such checks from Benguet. Thus, Benguet instant petition can be denied outright as Benguet resorted
for arbitration in case of disagreement between the parties Benguet undertook also to furnish J.G. Realty with a report posited that there was no valid ground for the termination to an improper remedy.
would therefore be a step backward. 12 on the examination, within a reasonable time after the of the RAWOP. It also reminded J.G. Realty that it should The last paragraph of Section 79 of Republic Act No. (RA)
WHEREFORE, premises considered, the instant Petition for completion of the examination. Moreover, also within the submit the disagreement to arbitration rather than 7942 or the "Philippine Mining Act of 1995" states, "A
Review on Certiorari is GRANTED. The examination period, Benguet shall conduct all necessary unilaterally terminating the RAWOP. petition for review by certiorari and question of law may be
decision ofthe Court of Appeals in CA-G.R. SP No. 35777 is exploration in accordance with a prepared exploration On June 7, 2000, J.G. Realty filed a Petition for Declaration filed by the aggrieved party with the Supreme Court within
REVERSED and SET ASIDE. The Regional program. If it chooses to do so and before the expiration of of Nullity/Cancellation of the RAWOP 9 with the Legaspi thirty (30) days from receipt of the order or decision of the
Trial Court of Quezon City, Branch 77, is ordered to the examination period, Benguet may undertake to develop City POA, Region V, docketed as DENR Case No. 2000-01 [MAB]."
DISMISS Respondent AMML's Third Party Complaint in the mining claims upon written notice to J.G. Realty. and entitled J.G. Realty v. Benguet. However, this Court has already invalidated such provision
Civil Case No. Q-92-12593. No pronouncement as to Benguet must then place the mining claims into On March 19, 2001, the POA issued a Decision, 10 dwelling in Carpio v. Sulu Resources Development Corp., 13ruling that
costs. prcd commercial productive stage within 24 months from the upon the issues of (1) whether the arbitrators had a decision of the MAB must first be appealed to the Court of
SO ORDERED. written notice. 6 It is also provided in the RAWOP that if jurisdiction over the case; and (2) whether Benguet Appeals (CA) under Rule 43 of the Rules of Court, before
||| (Sea-Land Service, Inc. v. Court of Appeals, G.R. No. the mining claims were placed in commercial production violated the RAWOP justifying the unilateral cancellation of recourse to this Court may be had. We held, thus:
126212, [March 2, 2000], 383 PHIL 887-897) by Benguet, J.G. Realty should be entitled to a royalty of five the RAWOP by J.G. Realty. The dispositive portion stated: To summarize, there are sufficient
percent (5%) of net realizable value, and to royalty for any WHEREFORE, premises considered, legal footings authorizing a review
SECOND DIVISION production done by Benguet whether during the the June 01, 1987 [RAWOP] and its of the MAB Decision under Rule 43
[G.R. No. 163101. February 13, 2008.] examination or development periods. Supplemental Agreement is hereby of the Rules of Court. First, Section
BENGUET Thus, on August 9, 1989, the Executive Vice-President of declared cancelled and without 30 of Article VI of the
CORPORATION, petitioner, vs. Benguet, Antonio N. Tachuling, issued a letter informing J.G. effect. BENGUET is hereby excluded 1987 Constitution, mandates that
DEPARTMENT OF ENVIRONMENT Realty of its intention to develop the mining claims. from the joint MPSA Application "[n]o law shall be passed increasing
AND NATURAL RESOURCES- However, on February 9, 1999, J.G. Realty, through its over the mineral claims the appellate jurisdiction of the
MINES ADJUDICATION BOARD President, Johnny L. Tan, then sent a letter to the President denominated as "BONITO-I", Supreme Court as provided in
and J.G. REALTY AND MINING of Benguet informing the latter that it was terminating the "BONITO-II", "BONITO-III" and thisConstitution without its advice
CORPORATION,respondents. RAWOP on the following grounds: "BONITO-IV". and consent." On the other hand,
DECISION a. The fact that your company has SO ORDERED. Section 79 of RA No. 7942 provides
VELASCO, JR., J p: failed to perform the obligations set Therefrom, Benguet filed a Notice of Appeal 11 with the that decisions of the MAB may be
The instant petition under Rule 65 of the Rules of Court forth in the RAWOP, i.e., to MAB on April 23, 2001, docketed as Mines Administrative reviewed by this Court on a
seeks the annulment of the December 2, 2002 undertake development works Case No. R-M-2000-01. Thereafter, the MAB issued the "petition for review by certiorari."
Decision 1 and March 17, 2004 Resolution 2 of the within 2 years from the execution assailed December 2, 2002 Decision. Benguet then filed a This provision is obviously an
Department of Environment and Natural Resources-Mining of the Agreement; Motion for Reconsideration of the assailed Decision which expansion of the Court's appellate
Adjudication Board (DENR-MAB) in MAB Case No. 0124-01 b. Violation of the Contract by was denied in the March 17, 2004 Resolution of the MAB. jurisdiction, an expansion to which
(Mines Administrative Case No. R-M-2000-01) allowing high graders to operate on Hence, Benguet filed the instant petition. this Court has not consented.
entitled Benguet Corporation (Benguet) v. J.G. Realty and our claim. The Issues Indiscriminate enactment of
Mining Corporation (J.G. Realty). The December 2, 2002 c. No stipulation was provided with 1. There was serious and palpable legislation enlarging the appellate
Decision upheld the March 19, 2001 Decision 3 of the MAB respect to the term limit of the error when the Honorable Board jurisdiction of this Court would
Panel of Arbitrators (POA) which canceled the Royalty RAWOP. failed to rule that the contractual unnecessarily burden it.
Agreement with Option to Purchase (RAWOP) dated June 1, d. Non-payment of the royalties obligation of the parties to arbitrate Second, when the Supreme Court, in
1987 4 between Benguet and J.G. Realty, and excluded thereon as provided in the under the Royalty Agreement is the exercise of its rule-making
Benguet from the joint Mineral Production Sharing RAWOP. 7 mandatory. power, transfers to the CA pending
Agreement (MPSA) application over four mining claims. In response, Benguet's Manager for Legal Services, 2. The Honorable Board exceeded cases involving a review of a quasi-
The March 17, 2004 Resolution denied Benguet's Motion Reynaldo P. Mendoza, wrote J.G. Realty a letter dated March its jurisdiction when it sustained judicial body's decisions, such
for Reconsideration. 8, 1999, 8 therein alleging that Benguet complied with its the cancellation of the Royalty transfer relates only to procedure;
The Facts obligations under the RAWOP by investing PhP42.4 million Agreement for alleged breach of hence, it does not impair the
On June 1, 1987, Benguet and J.G. Realty entered into a to rehabilitate the mines, and that the commercial contract despite the absence of substantive and vested rights of the
RAWOP, wherein J.G. Realty was acknowledged as the operation was hampered by the non-issuance of a Mines evidence. parties. The aggrieved party's right
owner of four mining claims respectively named as Bonito- Temporary Permit by the Mines and Geosciences Bureau 3. The Questioned Decision of the to appeal is preserved; what is
I, Bonito-II, Bonito-III, and Bonito-IV, with a total area of (MGB) which must be considered as force majeure, entitling Honorable Board in cancelling the changed is only the procedure by
288.8656 hectares, situated in Barangay Luklukam, Sitio Benguet to an extension of time to prosecute such permit. RAWOP prejudice[d] the which the appeal is to be made or
Bagong Bayan, Municipality of Jose Panganiban, Camarines Benguet further claimed that the high graders mentioned substantial rights of Benguet under decided. The parties still have a
Norte. The parties also executed a Supplemental by J.G. Realty were already operating prior to Benguet's the contract to the unjust remedy and a competent tribunal
Agreement 5 dated June 1, 1987. The mining claims were taking over of the premises, and that J.G. Realty had the enrichment of JG Realty. 12 to grant this remedy.
covered by MPSA Application No. APSA-V-0009 jointly filed obligation of ejecting such small scale miners. Benguet also Restated, the issues are: (1) Should the controversy have Third, the Revised Rules of Civil
by J.G. Realty as claimowner and Benguet as operator. alleged that the nature of the mining business made it first been submitted to arbitration before the POA took Procedure included Rule 43 to
In the RAWOP, Benguet obligated itself to perfect the rights difficult to specify a time limit for the RAWOP. Benguet cognizance of the case?; (2) Was the cancellation of the provide a uniform rule on appeals
to the mining claims and/or otherwise acquire the mining then argued that the royalties due to J.G. Realty were in fact RAWOP supported by evidence?; and (3) Did the from quasi-judicial agencies. Under
rights to the mineral claims. Within 24 months from the in its office and ready to be picked up at any time. It cancellation of the RAWOP amount to unjust enrichment of the rule, appeals from their
execution of the RAWOP, Benguet should also cause the appeared that, previously, the practice by J.G. Realty was to J.G. Realty at the expense of Benguet? judgments and final orders are now
required to be brought to the CA on for the exercise of our primary with the terms and conditions of arbitration a controversy
a verified petition for review. A jurisdiction. 14 the agreement. But to state that an thereafter arising between them.
quasi-judicial agency or body has The above principle was reiterated in Asaphil Construction aggrieved party cannot initiate an Such submission or contract
been defined as an organ of and Development Corporation v. Tuason, Jr. action without going to arbitration shall be valid, enforceable and
government, other than a court or (Asaphil). 15 However, the Carpio ruling was not applied would be tying one's hand even if irrevocable, save upon such
legislature, which affects the rights to Asaphil as the petition in the latter case was filed in 1999 there is a law which allows him to grounds as exist at law for the
of private parties through either or three years before the promulgation of Carpio in 2002. do so. 17 revocation of any contract.
adjudication or rule-making. MAB Here, the petition was filed on April 28, 2004 when The MAB, meanwhile, denied Benguet's contention on the Such submission or contract may
falls under this definition; hence, it the Carpio decision was already applicable, thus Benguet ground of estoppel, stating: include question[s] arising out of
is no different from the other quasi- should have filed the appeal with the CA. Besides, by its own act, Benguet is valuations, appraisals or other
judicial bodies enumerated under Petitioner having failed to properly appeal to the CA under already estopped in questioning the controversies which may be
Rule 43. Besides, the introductory Rule 43, the decision of the MAB has become final and jurisdiction of the Panel of collateral, incidental, precedent or
words in Section 1 of Circular No. 1- executory. On this ground alone, the instant petition must Arbitrators to hear and decide the subsequent to any issue between
91 –– "among these agencies are" – be denied. case. As pointed out in the appealed the parties. (Emphasis supplied.)
– indicate that the enumeration is Even if we entertain the petition although Benguet skirted Decision, Benguet initiated and In RA 9285 or the "Alternative Dispute Resolution Act of
not exclusive or conclusive and the appeal to the CA via Rule 43, still, the December 2, 2002 filed an Adverse Claim docketed as 2004," the Congress reiterated the efficacy of arbitration as
acknowledge the existence of other Decision and March 17, 2004 Resolution of the DENR-MAB MAC-R-M-2000-02 over the same an alternative mode of dispute resolution by stating in Sec.
quasi-judicial agencies which, in MAB Case No. 0124-01 should be maintained. mining claims without undergoing 32 thereof that domestic arbitration shall still be governed
though not expressly listed, should First Issue: The case should have contractual arbitration. In this by RA 876. Clearly, a contractual stipulation that requires
be deemed included therein. first been brought to voluntary particular case (MAC-R-M-2000- prior resort to voluntary arbitration before the parties can
arbitration before the POA 02) now subject of the appeal, go directly to court is not illegal and is in fact promoted by
Fourth, the Court realizes that Secs. 11.01 and 11.02 of the RAWOP pertinently provide: Benguet is likewise in estoppel the State. Thus, petitioner correctly cites several cases
under Batas Pambansa (BP) Blg. 11.01 Arbitration from questioning the competence whereby arbitration clauses have been upheld by this
129 as amended by RA No. 7902, Any disputes, differences or of the Panel of Arbitrators to hear Court. 21
factual controversies are usually disagreements between BENGUET and decide in the summary Moreover, the contention that RA 7942 prevails over RA
involved in decisions of quasi- and the OWNER with reference to proceedings J.G. Realty's petition, 876 presupposes a conflict between the two laws. Such is
judicial bodies; and the CA, which is anything whatsoever pertaining to when Benguet itself did not merely not the case here. To reiterate, availment of voluntary
likewise tasked to resolve this Agreement that cannot be move for the dismissal of the case arbitration before resort is made to the courts or quasi-
questions of fact, has more elbow amicably settled by them shall not but also filed an Answer with judicial agencies of the government is a valid contractual
room to resolve them. By including be cause of any action of any kind counterclaim seeking affirmative stipulation that must be adhered to by the parties. As stated
questions of fact among the issues whatsoever in any court or reliefs from the Panel of in Secs. 6 and 7 of RA 876:
that may be raised in an appeal administrative agency but shall, Arbitrators. 18 Section 6. Hearing by court. –– A
from quasi-judicial agencies to the upon notice of one party to the Moreover, the MAB ruled that the contractual provision on party aggrieved by the failure,
CA, Section 3 of Revised other, be referred to a Board of arbitration merely provides for an additional forum or neglect or refusal of another to
Administrative Circular No. 1-95 Arbitrators consisting of three (3) venue and does not divest the POA of the jurisdiction to perform under an agreement in
and Section 3 of Rule 43 explicitly members, one to be selected by hear the case. 19 writing providing for arbitration
expanded the list of such issues. BENGUET, another to be selected In its July 20, 2004 Comment, 20 J.G. Realty reiterated the may petition the court for an
According to Section 3 of Rule 43, by the OWNER and the third to be above rulings of the POA and MAB. It argued that RA order directing that such
"[a]n appeal under this Rule may be selected by the aforementioned two 7942 or the "Philippine Mining Act of 1995" is a special law arbitration proceed in the
taken to the Court of Appeals arbitrators so appointed. which should prevail over the stipulations of the parties manner provided for in such
within the period and in the xxx xxx xxx and over a general law, such as RA 876. It also argued that agreement.Five days notice in
manner herein provided whether 11.02 Court Action the POA cannot be considered as a "court" under the writing of the hearing of such
the appeal involves questions of No action shall be instituted in contemplation of RA 876 and that jurisprudence saying application shall be served either
fact, of law, or mixed questions of court as to any matter in dispute as that there must be prior resort to arbitration before filing a personally or by registered mail
fact and law." Hence, appeals from hereinabove stated, except to case with the courts is inapplicable to the instant case as upon the party in default. The
quasi-judicial agencies even only on enforce the decision of the majority the POA is itself already engaged in arbitration. court shall hear the parties, and
questions of law may be brought to of the Arbitrators. 16 On this issue, we rule for Benguet. upon being satisfied that the
the CA. Thus, Benguet argues that the POA should have first Sec. 2 of RA 876 elucidates the scope of arbitration: making of the agreement or such
Fifth, the judicial policy of referred the case to voluntary arbitration before taking Section 2. Persons and matters failure to comply therewith is
observing the hierarchy of courts cognizance of the case, citing Sec. 2 of RA 876 on persons subject to arbitration. –– Two or not in issue, shall make an order
dictates that direct resort from and matters subject to arbitration. more persons or parties may directing the parties to proceed
administrative agencies to this On the other hand, in denying such argument, the POA submit to the arbitration of one to arbitration in accordance with
Court will not be entertained, ruled that: or more arbitrators any the terms of the agreement. If the
unless the redress desired cannot While the parties may establish controversy existing between making of the agreement or
be obtained from the appropriate such stipulations clauses, terms and them at the time of the default be in issue the court shall
lower tribunals, or unless conditions as they may deem submission and which may be proceed to summarily hear such
exceptional and compelling convenient, the same must not be the subject of an action, or the issue. If the finding be that no
circumstances justify availment of a contrary to law and public policy. parties to any contract may in agreement in writing providing
remedy falling within and calling At a glance, there is nothing wrong such contract agree to settle by for arbitration was made, or that
there is no default in the Comparatively, in Reformist Union December 2, 2002 MAB Decision was promulgated, it filed a represented by such
proceeding thereunder, the of R.B. Liner, Inc. vs. motion for reconsideration with the MAB. When the deposits. (Emphasis supplied.)
proceeding shall be dismissed. If NLRC, compulsory arbitration has adverse March 17, 2004 MAB Resolution was issued, Evidently, the RAWOP itself provides for the mode of
the finding be that a written been defined both as "the process Benguet filed a petition with this Court pursuant to Sec. 79 royalty payment by Benguet. The fact that there was the
provision for arbitration was of settlement of labor disputes by of RA 7942 impliedly recognizing MAB's jurisdiction. In this previous practice whereby J.G. Realty picked-up the checks
made and there is a default in a government agency which has factual milieu, the Court rules that the jurisdiction of POA from Benguet is unavailing. The mode of payment is
proceeding thereunder, an order the authority to investigate and and that of MAB can no longer be questioned by Benguet at embodied in a contract between the parties. As such, the
shall be made summarily to make an award which is this late hour. What Benguet should have done was to contract must be considered as the law between the parties
directing the parties to proceed binding on all the parties, and as a immediately challenge the POA's jurisdiction by a special and binding on both. 26 Thus, after J.G. Realty informed
with the arbitration in mode of arbitration where the civil action for certiorari when POA ruled that it has Benguet of the bank account where deposits of its royalties
accordance with the terms parties are compelled to accept the jurisdiction over the dispute. To redo the proceedings fully may be made, Benguet had the obligation to deposit the
thereof. TcHCIS resolution of their dispute through participated in by the parties after the lapse of seven years checks. J.G. Realty had no obligation to furnish Benguet
xxx xxx xxx arbitration by a third party." While from date of institution of the original action with the POA with a Board Resolution considering that the RAWOP itself
Section 7. Stay of civil action. –– If a voluntary arbitrator is not part of would be anathema to the speedy and efficient provided for such payment scheme.
any suit or proceeding be brought the governmental unit or labor administration of justice. Notably, Benguet's claim that J.G. Realty must prove
upon an issue arising out of an department's personnel, said Second Issue: The cancellation of the RAWOP nonpayment of its royalties is both illogical and
agreement providing for the arbitrator renders arbitration was supported by evidence unsupported by law and jurisprudence.
arbitration thereof, the court in services provided for under labor The cancellation of the RAWOP by the POA was based on The allegation of nonpayment is not a positive allegation as
which such suit or proceeding is laws. 23 (Emphasis supplied.) two grounds: (1) Benguet's failure to pay J.G. Realty's claimed by Benguet. Rather, such is a negative allegation
pending, upon being satisfied that There is a clear distinction between compulsory and royalties for the mining claims; and (2) Benguet's failure to that does not require proof and in fact transfers the burden
the issue involved in such suit or voluntary arbitration. The arbitration provided by the POA seriously pursue MPSA Application No. APSA-V-0009 over of proof to Benguet. Thus, this Court ruled in Jimenez v.
proceeding is referable to is compulsory, while the nature of the arbitration provision the mining claims. National Labor Relations Commission:
arbitration, shall stay the action or in the RAWOP is voluntary, not involving any government As to the royalties, Benguet claims that the checks As a general rule, one who pleads
proceeding until an arbitration has agency. Thus, J.G. Realty's argument on this matter must representing payments for the royalties of J.G. Realty were payment has the burden of proving
been had in accordance with the fail. available for pick-up in its office and it is the latter which it. Even where the plaintiff must
terms of the agreement: Provided, As to J.G. Realty's contention that the provisions of RA refused to claim them. Benguet then thus concludes that it allege non-payment, the general
That the applicant, for the stay is 876 cannot apply to the instant case which involves an did not violate the RAWOP for nonpayment of royalties. rule is that the burden rests on the
not in default in proceeding with administrative agency, it must be pointed out that Section Further, Benguet reasons that J.G. Realty has the burden of defendant to prove payment, rather
such arbitration. (Emphasis 11.01 of the RAWOP states that: proving that the former did not pay such royalties than on the plaintiff to prove non-
supplied.) [Any controversy with regard to following the principle that the complainants must prove payment. The debtor has the
In other words, in the event a case that should properly be the contract] shall not be cause of their affirmative allegations. burden of showing with legal
the subject of voluntary arbitration is erroneously filed any action of any kind whatsoever With regard to the failure to pursue the MPSA application, certainty that the obligation has
with the courts or quasi-judicial agencies, on motion of the in any court or administrative Benguet claims that the lengthy time of approval of the been discharged by
defendant, the court or quasi-judicial agency shall agency but shall, upon notice of application is due to the failure of the MGB to approve it. In payment. 27 (Emphasis supplied.)
determine whether such contractual provision for one party to the other, be referred other words, Benguet argues that the approval of the In the instant case, the obligation of Benguet to pay
arbitration is sufficient and effective. If in affirmative, the to a Board of Arbitrators consisting application is solely in the hands of the MGB. royalties to J.G. Realty has been admitted and supported by
court or quasi-judicial agency shall then order the of three (3) members, one to be Benguet's arguments are bereft of merit. the provisions of the RAWOP. Thus, the burden to prove
enforcement of said provision. Besides, in BF Corporation v. selected by BENGUET, another to Sec. 14.05 of the RAWOP provides: such obligation rests on Benguet.
Court of Appeals, we already ruled: be selected by the OWNER and the 14.05 Bank Account It should also be borne in mind that MPSA Application No.
In this connection, it bears third to be selected by the OWNER shall maintain a bank APSA-V-0009 has been pending with the MGB for a
stressing that the lower court has aforementioned two arbiters so account at ___________ or any other considerable length of time. Benguet, in the RAWOP,
not lost its jurisdiction over the appointed.24 (Emphasis supplied.) bank from time to time selected by obligated itself to perfect the rights to the mining claims
case. Section 7 of Republic Act No. There can be no quibbling that POA is a quasi-judicial body OWNER with notice in writing to and/or otherwise acquire the mining rights to the mineral
876 provides that proceedings which forms part of the DENR, an administrative agency. BENGUET where BENGUET shall claims but failed to present any evidence showing that it
therein have only been stayed. Hence, the provision on mandatory resort to arbitration, deposit to the OWNER's credit any exerted efforts to speed up and have the application
After the special proceeding of freely entered into by the parties, must be held binding and all advances and payments approved. In fact, Benguet never even alleged that it
arbitration has been pursued and against them. 25 which may become due the OWNER continuously followed-up the application with the MGB and
completed, then the lower court In sum, on the issue of whether POA should have referred under this Agreement as well as the that it was in constant communication with the
may confirm the award made by the case to voluntary arbitration, we find that, indeed, POA purchase price herein agreed upon government agency for the expeditious resolution of the
the arbitrator. 22 has no jurisdiction over the dispute which is governed in the event that BENGUET shall application. Such allegations would show that, indeed,
J.G. Realty's contention, that prior resort to arbitration is by RA 876, the arbitration law. exercise the option to purchase Benguet was remiss in prosecuting the MPSA application
unavailing in the instant case because the POA's mandate is However, we find that Benguet is already estopped from provided for in the Agreement. Any and clearly failed to comply with its obligation in the
to arbitrate disputes involving mineral agreements, is questioning the POA's jurisdiction. As it were, when J.G. and all deposits so made by RAWOP.
misplaced. A distinction must be made between voluntary Realty filed DENR Case No. 2000-01, Benguet filed its BENGUET shall be a full and Third Issue: There is no unjust enrichment in the
and compulsory arbitration. In Ludo and Luym Corporation answer and participated in the proceedings before the POA, complete acquittance and instant case
v. Saordino, the Court had the occasion to distinguish Region V. Secondly, when the adverse March 19, 2001 POA release to [sic] BENGUET from Based on the foregoing discussion, the cancellation of the
between the two types of arbitrations: Decision was rendered, it filed an appeal with the MAB in any further liability to the RAWOP was based on valid grounds and is, therefore,
Mines Administrative Case No. R-M-2000-01 and again OWNER of the amounts justified. The necessary implication of the cancellation is
participated in the MAB proceedings. When the adverse the cessation of Benguet's right to prosecute MPSA
Application No. APSA-V-0009 and to further develop such own initiative, dismissed the complaint without prejudice NUMBER OF DAYS DOES NOT MEAN THAT THE CASE not have been possible had the dismissal without prejudice
mining claims. for failure of petitioner to prosecute. However, upon WOULD BE DISMISSED. — Contrary to respondent Uy's been resuscitated. Surely, the court a quo could not have
In Car Cool Philippines, Inc. v. Ushio Realty and Development motion of petitioner, the trial court issued an Order dated 8 asseverations, the impact of the second paragraph upon the denied on 6 November 2000 petitioner's motion to
Corporation, we defined unjust enrichment, as follows: September 2000 reconsidering the dismissal. It further first is simply to illustrate what the trial court would do calendar Civil Case No. 99-518 for pre-trial if the dismissal
We have held that "[t]here is unjust directed the petitioner to submit the compromise after setting aside the dismissal without prejudice: had been restored to life in the meantime. By then the
enrichment when a agreement within 15 days from receipt thereof and warned submission of the compromise agreement for the dismissal without prejudice would have already become
person unjustly retains a benefit to that for failure on its part to submit the said agreement consideration of the trial court. Nothing in the second final and executory so as to effectively remove the civil case
the loss of another, or when a shall cause the imposition of payment of the required paragraph do we read that the reconsideration is subject to from the docket of the trial court. The same is true with
person retains money or property docket fees for re-filing of the case. On 27 July 2000, two (2) qualifications. Certainly far from it, for in Goldloop the Order of 16 November 2000 denying due course to
of another against the fundamental petitioner filed a Motion to Set Case for Pre-Trial Properties, Inc. v. Court of Appeals a similar directive, i.e., petitioner's Notice of Appeal. There would have been no
principles of justice, equity and Conference, but then it was denied by the trial court "[t]he parties are given a period of fifteen (15) days from basis for such exercise of discretion because the
good conscience." Article 22 of the because of its failure to submit a compromise agreement. today within which to submit a Compromise Agreement," jurisdiction of the court a quo over the civil case would
Civil Code provides that "[e]very Petitioner filed a Petition for Certiorari before the Court of was held to mean that "should the parties fail in their have been discharged and terminated by the presumed
person who through an act of Appeals. It argued that the trial court had no authority to negotiations the proceedings would continue from where dismissal thereof. Moreover, we note the ground for
performance by another, or any compel the parties to enter into an amicable settlement nor they left off." Goldloop Properties, Inc. further said that its denying due course to the appeal: the "Orders dated 8
other means, acquires or comes to deny the holding of a pre-trial conference on the ground order, or a specie of it, did not constitute an agreement or September 2000 and 6 November 2000 are interlocutory
into possession of something at the that no compromise agreement was turned over to the even an expectation of the parties that should they fail to orders and therefore, no appeal may be taken from . . . ."
expense of the latter without just or courta quo: The appellate court affirmed the orders of the settle their differences within the stipulated number of This declaration strongly suggests that something more
legal ground, shall return the same trial court. Hence, this petition. days their case would be dismissed. was to be accomplished in the civil case, thus negating the
to him." The principle of unjust The Court saw no reason why the trial court should stop 3. ID.; ID.; ID.; DOCKET FEES ARE DEFRAYED ONLY AFTER claim that the Order of dismissal without prejudice was
enrichment under Article 22 short of hearing the civil case on the merits. There was no THE DISMISSAL BECOMES FINAL AND EXECUTORY AND resurrected upon the parties' failure to yield a compromise
requires two conditions: (1) that a substantial policy worth pursuing by requiring petitioner WHEN THE CIVIL CASE IS RE-FILED. — It must be agreement.
person is benefited without a valid to pay again the docket fees when it had already discharged emphasized however that once the dismissal attains the 6. ID.; ID.; "FINAL ORDER" DIFFERENTIATED FROM
basis or justification, and (2) that this obligation simultaneously with the filing of the attribute of finality, the trial court cannot impose legal fees "INTERLOCUTORY ORDER." — A "final order" issued by a
such benefit is derived at another's complaint for collection of a sum of money. The procedure anew because a final and executory dismissal although court has been defined as one which disposes of the subject
expense or damage. for dismissed cases when re-filed is the same as though it without prejudice divests the trial court of jurisdiction over matter in its entirety or terminates a particular proceeding
There is no unjust enrichment was initially lodged, i.e., the filing of answer, reply, answer the civil case as well as any residual power to order or action, leaving nothing else to be done but to enforce by
when the person who will benefit to counterclaim, including other foot-dragging maneuvers, anything relative to the dismissed case; it would have to execution what has been determined by the court, while an
has a valid claim to such except for the rigmarole of raffling cases which is wait until the complaint is docketed once again. On the "interlocutory order" is one which does not dispose of a
benefit. 28 (Emphasis supplied.) dispensed with since the re-filed complaint is automatically other hand, if we are to concede that the trial court retains case completely but leaves something more to be decided
Clearly, there is no unjust enrichment in the instant case as assigned to the branch to which the original case pertained. jurisdiction over Civil Case No. 99-518 for it to issue the upon.
the cancellation of the RAWOP, which left Benguet without A complaint that is re-filed leads to the re-enactment of the assailed Orders, a continuation of the hearing thereon 7. ID.; ID.; DISMISSAL OF ACTION; GOLD LOOP PROPERTIES,
any legal right to participate in further developing the past proceedings with the concomitant full attention of the would not trigger a disbursement for docket fees on the INC. vs. COURT OF APPEALS; APPLICABLE IN CASE AT BAR.
mining claims, was brought about by its violation of the same trial court exercising an immaculate slew of part of petitioner as this would obviously imply the setting — Besides the semantic and consequential improbabilities
RAWOP. Hence, Benguet has no one to blame but itself for jurisdiction and control over the case that was previously aside of the order of dismissal and the reinstatement of the of respondent Uy's argument, our ruling in Goldloop
its predicament. dismissed, which in the context of the instant case is a complaint. Properties, Inc., is decisive of the instant case. In Goldloop
WHEREFORE, we DISMISS the petition, and AFFIRM the waste of judicial time, capital and energy. Accordingly, the 4. ID.; ID.; ID.; ID.; CASE AT BAR. — The addition of the Properties, Inc., we reversed the action of the trial court in
December 2, 2002 Decision and March 17, 2004 Resolution instant petition was granted. second sentence in the second paragraph does not change dismissing the complaint for failure of the plaintiff to
of the DENR-MAB in MAB Case No. 0124-01 upholding the SYLLABUS the absolute nullification of the dismissal without prejudice prosecute its case, which was in turn based on its inability
cancellation of the June 1, 1987 RAWOP. No costs. 1. REMEDIAL LAW; CIVIL PROCEDURE; PROCEDURE FOR decreed in the first paragraph. The sentence "[f]ailure on to forge a compromise with the other parties within fifteen
SO ORDERED. REFILING OF DISMISSED CASES. — There is no substantial the part of plaintiff to submit the said agreement shall (15) days from notice of the order to do so and held —
||| (Benguet Corp. v. Department of Environment and policy worth pursuing by requiring petitioner to pay again cause the imposition of payment of the required docket "Since there is nothing in the Rules that imposes the
Natural Resources - Mines Adjudication Board, G.R. No. the docket fees when it has already discharged this fees for re-filing of this case" is not a directive to pay docket sanction of dismissal for failing to submit a compromise
163101, [February 13, 2008], 568 PHIL 756-774) obligation simultaneously with the filing of the complaint fees but only a statement of the event that may result in its agreement, then it is obvious that the dismissal of the
for collection of a sum of money. The procedure for imposition. The reason for this is that the trial court could complaint on the basis thereof amounts no less to a gross
SECOND DIVISION dismissed cases when re-filed is the same as though it was not have possibly made such payment obligatory in the procedural infirmity assailable by certiorari. For such
[G.R. No. 152878. May 5, 2003.] initially lodged, i.e., the filing of answer, reply, answer to same civil case, i.e., Civil Case No. 99-518, since docket fees submission could at most be directory and could not result
RIZAL COMMERCIAL BANKING counter-claim, including other foot-dragging maneuvers, are defrayed only after the dismissal becomes final and in throwing out the case for failure to effect a compromise.
CORPORATION, petitioner, vs. except for the rigmarole of raffling cases which is executory and when the civil case is re-filed. While a compromise is encouraged, very strongly in fact,
MAGWIN MARKETING dispensed with since the re-filed complaint is automatically 5. ID.; ID.; ID.; SUBSEQUENT ACTIONS OF THE TRIAL failure to consummate one does not warrant any
CORPORATION, NELSON TIU, assigned to the branch to which the original case pertained. COURT BELIE AN INTENTION TO REVIVE THE ORDER OF procedural sanction, much less an authority to jettison a
BENITO SY and ANDERSON A complaint that is re-filed leads to the re-enactment of DISMISSAL WITHOUT PREJUDICE IN THE EVENT THAT civil complaint worth P4,000,000.00 . . . Plainly, submission
UY,respondents. past proceedings with the concomitant full attention of the PETITIONER FAILS TO SUBMIT A COMPROMISE of a compromise agreement is never mandatory, nor is it
Siguion Reyna Montecillo & Ongsiako for petitioner. same trial court exercising an immaculate slew of AGREEMENT; CASE AT BAR. — The subsequent actions of required by any rule."
Sycip Salazar Hernandez & Gatmaitan for respondent A. Uy. jurisdiction and control over the case that was previously the trial court also belie an intention to revive theOrder of 8. ID.; ID.; PROPER COURSE OF ACTION TO BE TAKEN BY
Ernest S. Ang, Jr. for private respondents. dismissed, which in the context of the instant case is a dismissal without prejudice in the event that petitioner THE COURT A QUO, UPON MANIFESTATION OF THE
SYNOPSIS waste of judicial time, capital and energy. fails to submit a compromise agreement. The Orders of 6 PARTIES OF THEIR WILLINGNESS TO DISCUSS A
In a complaint for recovery of sum of money filed by 2. ID.; ID.; DISMISSAL OF ACTION; FAILURE TO SUBMIT A and 16 November 2000 plainly manifest that it was SETTLEMENT. — The proper course of action that should
petitioner against the respondents, the trial court, on its COMPROMISE AGREEMENT WITHIN THE STIPULATED retaining jurisdiction over the civil case, a fact which would have been taken by the court a quo, upon manifestation of
the parties of their willingness to discuss a settlement, was Properties, Inc. In any event, given that the instant case another creative remedy was available to the court a quo to 1999 the writ was returned partially satisfied since only a
to suspend the proceedings and allow them reasonable merely revolves around the search for a reasonable attain a speedy disposition of Civil Case No. 99-518 without parcel of land purportedly owned by defendant Benito Sy
time to come to terms (a) If willingness to discuss a interpretation of the several Ordersof the trial court, i.e., as sacrificing the course of justice. Since the failure of was attached. 3 In the meantime, summons was served on
possible compromise is expressed by one or both parties; to whether the dismissal without prejudice was revived petitioner to submit a compromise agreement was the each of the defendants, respondents herein, who filed their
or (b) If it appears that one of the parties, before the upon petitioner's helplessness to perfect an out-of-court refusal of just one of herein respondents,i.e., Benito Sy, to respective answers, except for defendant Gabriel Cheng
commencement of the action or proceeding, offered to arrangement, with more reason must we employ the ruling sign his name on the conforme of the loan restructure who was dropped without prejudice as party-defendant as
discuss a possible compromise but the other party refused inGoldloop Properties, Inc. to resolve the parties' differences documents, and the common concern of the courts a his whereabouts could not be located. 4 On 21 September
the offer, pursuant to Art. 2030 of the Civil Code. If despite of opinion. quo was dispatch in the proceedings, the holding of a pre- 1999 petitioner moved for an alias writ of attachment
efforts exerted by the trial court and the parties the 11. ID.; ID.; ID.; GROUNDS FOR DISMISSAL DUE TO trial conference was the best-suited solution to the which on 18 January 2000 the court a quodenied. 5
negotiations still fail, only then should the action continue PLAINTIFF'S FAULT. — A complaint may be dismissed due problem as this stage in a civil action is where issues are Petitioner did not cause the case to be set for pre-
as if no suspension had taken place. to plaintiff's fault: (a) if he fails to appear during a simplified and the dispute quickly and genuinely trial. 6 For about six (6) months thereafter, discussions
scheduled trial, especially on the date for the presentation reconciled. By means of pre-trial, the trial court is fully between petitioner and respondents Magwin Marketing
9. ID.; ID.; RULES ALLOW THE TRIAL COURT TO SUSPEND of his evidence in chief, or when so required at the pre- empowered to sway the litigants to agree upon some fair Corporation, Nelson Tiu, Benito Sy and Anderson Uy, as
ITS PROCEEDINGS TO ENCOURAGE THE USE OF trial; (b) if he neglects to prosecute his action for an compromise. EACIaT parties in Civil Case No. 99-518, were undertaken to
ALTERNATIVE MECHANISMS OF DISPUTE RESOLUTION. unreasonable length of time; or (c) if he does not comply 15. ID.; ID.; DISMISSAL OF ACTION; INCONSIDERATE restructure the indebtedness of respondent Magwin
— Ostensibly, while the rules allow the trial court to with the rules or any order of the court. DISMISSALS, EVEN IF WITHOUT PREJUDICE, DO NOT Marketing Corporation. 7 On 9 May 2000 petitioner
suspend its proceedings consistent with the policy to 12. ID.; ID.; ID.; ID.; FAILURE TO PROSECUTE; NOT CONSTITUTE A SOLUTION TO THE CONGESTION OF approved a debt payment scheme for the corporation
encourage the use of alternative mechanisms of dispute PRESENT IN CASE AT BAR. — To constitute a sufficient COURT DOCKETS. — Dismissing the civil case and which on 15 May 2000 was communicated to the latter by
resolution, in the instant case, the trial court only gave the ground for dismissal, the inattention of plaintiff to pursue compelling petitioner to re-file its complaint is a dangerous, means of a letter dated 10 May 2000 for the conformity of
parties fifteen (15) days to conclude a deal. This was, to say his cause must not only be prolonged but also be costly and circuitous route that may end up aggravating, its officers, i.e., respondent Nelson Tiu as
the least, a passive and paltry attempt of the court a quo in unnecessary and dilatory resulting in the trifling of judicial not resolving, the disagreement. This case management President/General Manager of Magwin Marketing
its task of persuading litigants to agree upon a reasonable processes. In the instant case, the adjournment was not strategy is frighteningly deceptive because it does so at the Corporation and respondent Benito Sy as Director
concession. Hence, if only to inspire confidence in the only fleeting as it lasted less than six (6) months but was expense of petitioner whose cause of action, perhaps, may thereof. 8 Only respondent Nelson Tiu affixed his signature
pursuit of a middle ground between petitioner and also done in good faith to accommodate respondents' have already been admitted by its adverse parties as shown on the letter to signify his agreement to the terms and
respondents, we must not interpret the trial incessant pleas to negotiate. Although the dismissal of a by three (3) of four (4) defendants not willing to contest conditions of the restructuring. 9
court's Orders as dismissing the action on its own motion case for failure to prosecute is a matter addressed to the petitioner's allegations, and more critically, since this
because the parties, specifically petitioner, were anxious to sound discretion of the court, that judgment however must approach promotes the useless and thankless duplication On 20 July 2000 the RTC of Makati City, on its own initiative,
litigate their case as exhibited in their several not be abused. The availability of this recourse must be of hard work already undertaken by the trial court. As we issued an Order dismissing without prejudice Civil Case No.
manifestations and motions. determined according to the procedural history of each have aptly observed, "[i]nconsiderate dismissals, even if 99-518 for failure of petitioner as plaintiff therein to
10. ID.; ID.; DISMISSAL OF ACTION; GOLDLOOP case, the situation at the time of the dismissal, and the without prejudice, do not constitute a panacea nor a "prosecute its action for an unreasonable length of time . .
PROPERTIES, INC. vs. COURT OF APPEALS; COURT DOES diligence of plaintiff to proceed therein. Stress must also be solution to the congestion of court dockets. While they lend ." 10 On 31 July 2000 petitioner moved for reconsideration
NOT TOLERATE A WRONGFUL DISMISSAL JUST BECAUSE laid upon the official directive that courts must endeavor to a deceptive aura of efficiency to records of individual of the Order by informing the trial court of
THE PARTIES FAILED TO SUBMIT COMPROMISE convince parties in a civil case to consummate a fair judges, they merely postpone the ultimate reckoning respondents' unremitting desire to settle the case amicably
AGREEMENT; APPLIED IN CASE AT BAR. — To begin with, settlement, and to mitigate damages to be paid by the between the parties. In the absence of clear lack of merit or through a loan restructuring program. 11On 22 August
whether the dismissal is with or without prejudice if losing party who has shown a sincere desire for such give- intention to delay, justice is better served by a brief 2000 petitioner notified the trial court of the acquiescence
grievously erroneous is detrimental to the cause of the and-take. All things considered, we see no compelling continuance, trial on the merits, and final disposition of the thereto of respondent Nelson Tiu as an officer of Magwin
affected party; Goldloop Properties, Inc. does not tolerate a circumstances to uphold the dismissal of petitioner's cases before the court." HIAcCD Marketing Corporation and defendant in the civil case. 12
wrongful dismissal just because it was without prejudice. complaint regardless of its characterization as being DECISION On 8 September 2000 the court a quo issued
More importantly, the facts in Goldloop Properties, Inc. without prejudice. BELLOSILLO, J p: an Order reconsidering the dismissal without prejudice of
involve, as in the instant case, a dismissal for failure to 13. ID.; ID.; ID.; COURTS SHOULD DECIDE TO DISPENSE WE ARE PERTURBED that this case should drag this Court Civil Case No. 99-518 —
prosecute on the ground of the parties' inability to come up RATHER THAN WIELD THEIR AUTHORITY TO DISMISS. — in the banal attempts to decipher the hazy and confused Acting on plaintiff's "Motion for
with a compromise agreement within fifteen (15) days A court may dismiss a case on the ground of non intent of the trial court in proceeding with what would Reconsideration" of the Order
from notice of the court's order therein. All told, the prosequitur but the real test of the judicious exercise of have been a simple, straightforward and hardly arguable dated 20 July 2000 dismissing this
parallelism between them is unmistakable. Even if we are such power is whether under the circumstances plaintiff is collection case. Whether the dismissal without prejudice for case for failure to prosecute, it
to accept on face value respondent's understanding chargeable with want of fitting assiduousness in not acting failure to prosecute was unconditionally reconsidered, appearing that there was already
of Goldloop Properties, Inc. as solely about the failure to on his complaint with reasonable promptitude. Unless a reversed and set aside to reinstate the civil case and have it conformity to the restructuring of
submit a compromise agreement, it is apparent that the party's conduct is so indifferent, irresponsible, ready for pre-trialare matters which should have been defendants' indebtedness with
present case confronts a similar problem. Perhaps initially contumacious or slothful as to provide substantial grounds clarified and resolved in the first instance by the court a plaintiff by defendant Nelson Tiu,
the issue was one of failure to prosecute, as can be for dismissal, i.e., equivalent to default or non-appearance quo. Unfortunately, this feckless imprecision of the trial President of defendant corporation
observed from the Order dated 20 July 2000, although later in the case, the courts should consider lesser sanctions court became the soup stock of the parties and their per "Manifestation and Motion"
reversed and set aside. But thereafter, in the Order of 6 which would still amount to achieving the desired end. In lawyers to further delay the case below when they could filed by plaintiff on 22 August 2000,
November 2000, the trial court refused to proceed to pre- the absence of a pattern or scheme to delay the disposition have otherwise put things in proper order efficiently and there being probability of
trial owing to the "failure of the plaintiff to submit a of the case or of a wanton failure to observe the mandatory effectively. settlement among the parties, as
compromise agreement pursuant to the Order dated 8 requirement of the rules on the part of the plaintiff, as in On 4 March 1999 petitioner Rizal Commercial Banking prayed for, the Order dated 20 July
September 2000." When the civil case was stalled on the case at bar, courts should decide to dispense rather Corporation (RCBC) filed a complaint for recovery of a sum 2000 is hereby set aside.
account of the trial court's refusal to call the parties to a than wield their authority to dismiss. of money with prayer for a writ of preliminary attachment Plaintiff is directed to submit the
pre-trial conference, the reason or basis therefor was the 14. ID.; ID.; PRE-TRIAL CONFERENCE; BEST-SUITED against respondents Magwin Marketing Corporation, compromise agreement within 15
absence of a negotiated settlement — a circumstance that SOLUTION FOR FAILURE OF THE PARTIES TO SUBMIT A Nelson Tiu, Benito Sy and Anderson Uy. 1 On 26 April 1999, days from receipt hereof. Failure on
takes the case at bar within the plain ambit of Goldloop COMPROMISE AGREEMENT; CASE AT BAR. — Clearly, the trial court issued a writ of attachment. 2 On 4 June the part of plaintiff to submit the
said agreement shall cause the On 28 September 2001 the appellate court promulgated applicability to this case of the ruling in Goldloop Properties, of the instant case is a waste of judicial time, capital and
imposition of payment of the its Decision dismissing the petition for lack of merit and Inc. v. Court of Appeals. Respondent Uy claims that energy.
required docket fees for re-filing of affirming the assailed Orders of the trial court 21 holding the Order reconsidering the dismissal of Civil Case No. 99-
this case. 13 that — EDHCSI 518 without prejudice is on its face contingent upon the What judicial benefit do we derive from starting the civil
On 27 July 2000 petitioner filed in Civil Case No. 99-518 . . . although the language of the submission of the compromise agreement which in the first case all over again, especially where three (3) of the four
a Manifestation and Motion to Set Case for Pre-Trial September 8, 2000 Order may not place was the principal reason of petitioner to justify the (4) defendants, i.e., Magwin Marketing Corporation, Nelson
Conference alleging that "[t]o date, only defendant Nelson be clear, yet, a careful reading of withdrawal of the Order declaring his failure to prosecute Tiu and Benito Sy, have not contested petitioner's plea
Tiu had affixed his signature on the May 10, 2000 letter the same would clearly show that the civil case. He further contends that the trial court did before this Court and the courts a quo to advance to pre-
which informed the defendants that plaintiff [herein the setting aside of the Order dated not force the parties in the civil case to execute a trial conference? Indeed, to continue hereafter with the
petitioner] already approved defendant Magwin Marketing July 20, 2000 which dismissed compromise agreement, the truth being that it dismissed resolution of petitioner's complaint without the usual
Corporations request for restructuring of its loan petitioner's complaint . . . for failure the complaint therein for petitioner's dereliction. procedure for the re-filing thereof, we will save the court a
obligations to plaintiff but subject to the terms and to prosecute its action for an Finally, respondent Uy contests the relevance of Goldloop quo invaluable time and other resources far outweighing
conditions specified in said letter." 14 This motion was unreasonable length of time is Properties, Inc. v. Court of Appeals, and refers to its the docket fees that petitioner would be forfeiting should
followed on 5 October 2000 by petitioner'sSupplemental dependent on the following incongruence with the instant case, i.e., that the complaint we rule otherwise.
Motion to Plaintiffs Manifestation and Motion to Set Case for conditions, to wit: a) The of petitioner was dismissed for failure to prosecute and not Going over the specifics of this petition and the arguments
Pre-Trial Conference affirming that petitioner "could not submission of the compromise for its reckless disregard to present an amicable settlement of respondent Anderson Uy, we rule that theOrder of 8
submit a compromise agreement because only defendant agreement by petitioner within as was the situation inGoldloop Properties, Inc., and that the September 2000 did not reserve conditions on the
Nelson Tiu had affixed his signature on the May 10, 2000 fifteen (15) days from notice; and dismissal was without prejudice, in contrast with the reconsideration and reversal of the Orderdismissing
letter. . . ." 15 Respondent Anderson Uy opposed the b) Failure of petitioner to submit dismissal with prejudice ordered in the cited case. For their without prejudice Civil Case No. 99-518. This is quite
foregoing submissions of petitioner while respondents the said compromise agreement part, respondents Magwin Marketing Corporation, Nelson evident from its text which does not use words to signal an
Magwin Marketing Corporation, Nelson Tiu and Benito Sy shall cause the imposition of the Tiu and Benito Sy waived their right to file a comment on intent to impose riders on the dispositive portion —
neither contested nor supported them. 16 payment of the required docket the instant petition and submitted the same for resolution Acting on plaintiff's "Motion for
The trial court, in an undated Order (although a date was fees for the re-filing of the case; so of this Court. 24 Reconsideration" of the Order
later inserted in the Order), denied petitioner's motion to much so that the non-compliance The petition of Rizal Commercial Banking Corporation is dated 20 July 2000 dismissing this
calendar Civil Case No. 99-518 for pre-trial stating that — by petitioner of condition no. 1 meritorious. It directs our attention to questions of case for failure to prosecute, it
Acting on plaintiff's [herein would make condition no. 2 substance decided by the courts a quo plainly in a way not appearing that there was already
petitioner] "Manifestation and effective, especially that in accord with applicable precedents as well as the conformity to the restructuring of
Motion to Set Case for Pre-Trial petitioner's manifestation and accepted and usual course of judicial proceedings; it offers defendants' indebtedness with
Conference," the "Opposition" filed motion to set case for pre-trial special and important reasons that demand the exercise of plaintiff by defendant Nelson Tiu,
by defendant Uy and the conference and supplemental our power of supervision and review. Furthermore, President of defendant corporation
subsequent "Supplemental Motion" motion . . . [were] denied by the petitioner's objections to the proceedings below per "Manifestation and Motion"
filed by plaintiff; defendant Uy's respondent judge in his Order encompass not only the Order of 8 September 2000 but filed by plaintiff on 22 August 2000,
"Opposition," and plaintiff's dated November 6, 2000, which in include the cognate Orders of the trial court of 6 and 16 there being probability of
"Reply"; for failure of the plaintiff to effect means that the Order dated November 2000. This is evident from the prayer of the settlement among the parties, as
submit a compromise agreement July 20, 2000 was ultimately not set instant petition which seeks to reverse and set aside prayed for, the Order dated 20 July
pursuant to the Order dated 8 aside considering that a party need the Decision of the appellate court and to direct the trial 2000 is hereby set aside.
September 2000 plaintiff's motion not pay docket fees for the re-filing court to proceed with the pre-trial conference in Civil Case Plaintiff is directed to submit the
to set case for pre-trial conference of a case if the original case has No. 99-518. Evidently, the substantive issue involved compromise agreement within 15
is hereby denied. 17 been revived and reinstated. 22 herein is whether the proceedings in the civil case should days from receipt hereof. Failure on
On 15 November 2000 petitioner filed its Notice of On 2 April 2002 reconsideration of the Decision was progress, a question which at bottom embroils all the part of plaintiff to submit the
Appeal from the 8 September 2000 Order of the trial court denied; hence, this petition. the Orders affirmed by the Court of Appeals. said agreement shall cause the
as well as its undated Order in Civil Case No. 99-518. On 16 In the instant case, petitioner maintains that the trial court On the task at hand, we see no reason why RTC-Br. 135 of imposition of payment of the
November 2000 the trial court issued two (2) Orders, one cannot coerce the parties in Civil Case No. 99-518 to Makati City should stop short of hearing the civil case on required docket fees for re-filing of
of which inserted the date "6 November 2000" in the execute a compromise agreement and penalize their failure the merits. There is no substantial policy worth pursuing this case. 27
undated Order rejecting petitioner's motion for pre-trial in to do so by refusing to go forward with the pre-trial by requiring petitioner to pay again the docket fees when it Contrary to respondent Uy's asseverations, the impact of
the civil case, and the other denying due course to conference. To hold otherwise, so petitioner avers, would has already discharged this obligation simultaneously with the second paragraph upon the first is simply to illustrate
the Notice of Appeal on the ground that the "Orders dated 8 violate Art. 2029 of the Civil Code which provides that the filing of the complaint for collection of a sum of money. what the trial court would do after setting aside the
September 2000 and 6 November 2000 are interlocutory "[t]he court shall endeavor to persuade the litigants in a The procedure for dismissed cases when re-filed is the dismissal without prejudice: submission of the compromise
orders and therefore, no appeal may be taken. . . ." 18 civil case to agree upon some fair compromise," and this same as though it was initially lodged, i.e., the filing of agreement for the consideration of the trial court. Nothing
On 7 December 2000 petitioner elevated the Orders dated 8 Court's ruling in Goldloop Properties, Inc. v. Court of answer, reply, answer to counter-claim, including other in the second paragraph do we read that the
September 2000, 6 November 2000 and 16 November Appeals 23 where it was held that the trial court cannot foot-dragging maneuvers, except for the rigmarole of reconsideration is subject to two (2) qualifications.
2000 of the trial court to the Court of Appeals in a petition dismiss a complaint for failure of the parties to submit a raffling cases which is dispensed with since the re-filed Certainly far from it, for in Goldloop Properties, Inc. v. Court
for certiorari under Rule 65 of theRules of Civil compromise agreement. complaint is automatically assigned to the branch to which of Appeals 28 a similar directive, i.e., "[t]he parties are
Procedure. 19 In the main, petitioner argued that the On the other hand, respondent Anderson Uy filed his the original case pertained. 25 A complaint that is re-filed given a period of fifteen (15) days from today within which
court a quo had no authority to compel the parties in Civil comment after several extensions asserting that there are leads to the re-enactment of past proceedings with the to submit a Compromise Agreement," was held to mean
Case No. 99-518 to enter into an amicable settlement nor to no special and important reasons for undertaking this concomitant full attention of the same trial court exercising that "should the parties fail in their negotiations the
deny the holding of a pre-trial conference on the ground review. He also alleges that petitioner's attack is limited to an immaculate slew of jurisdiction and control over the proceedings would continue from where they left
that no compromise agreement was turned over to the the Order dated 8 September 2000 as to whether it is case that was previously dismissed, 26 which in the context off." Goldloop Properties, Inc. further said that its order, or a
court a quo. 20 conditional as the Court of Appeals so found and the specie of it, did not constitute an agreement or even an
expectation of the parties that should they fail to settle have already become final and executory so as to effectively parties; or (b) If it appears that one of the parties, before to whether the dismissal without prejudice was revived
their differences within the stipulated number of days their remove the civil case from the docket of the trial court. the commencement of the action or proceeding, offered to upon petitioner's helplessness to perfect an out-of-court
case would be dismissed. The same is true with the Order of 16 November 2000 discuss a possible compromise but the other party refused arrangement, with more reason must we employ the ruling
The addition of the second sentence in the second denying due course to petitioner's Notice of Appeal. There the offer, pursuant to Art. 2030 of the Civil Code. If despite in Goldloop Properties, Inc. to resolve the parties'
paragraph does not change the absolute nullification of the would have been no basis for such exercise of discretion efforts exerted by the trial court and the parties the differences of opinion.
dismissal without prejudice decreed in the first paragraph. because the jurisdiction of the court a quoover the civil case negotiations still fail, only then should the action continue We also find nothing in the record to support respondent
The sentence "[f]ailure on the part of plaintiff to submit the would have been discharged and terminated by the as if no suspension had taken place. 33 Uy's conclusion that petitioner has been mercilessly
said agreement shall cause the imposition of payment of presumed dismissal thereof. Moreover, we note the ground Ostensibly, while the rules allow the trial court to suspend delaying the prosecution of Civil Case No. 99-518 to
the required docket fees for re-filing of this case" is not a for denying due course to the appeal: the "Orders dated 8 its proceedings consistent with the policy to encourage the warrant its dismissal. A complaint may be dismissed due to
directive to pay docket fees but only a statement of the September 2000 and 6 November 2000 are interlocutory use of alternative mechanisms of dispute resolution, in the plaintiff's fault: (a) if he fails to appear during a scheduled
event that may result in its imposition. The reason for this orders and therefore, no appeal may be taken from . . instant case, the trial court only gave the parties fifteen trial, especially on the date for the presentation of his
is that the trial court could not have possibly made such ." 30 This declaration strongly suggests that something (15) days to conclude a deal. This was, to say the least, a evidence in chief, or when so required at the pre-trial; (b) if
payment obligatory in the same civil case, i.e., Civil Case No. more was to be accomplished in the civil case, thus passive and paltry attempt of the court a quo in its task of he neglects to prosecute his action for an unreasonable
99-518, since docket fees are defrayed only after the negating the claim that the Order of dismissal without persuading litigants to agree upon a reasonable length of time; or (c) if he does not comply with the rules or
dismissal becomes final and executory and when the civil prejudice was resurrected upon the parties' failure to yield concession. 34 Hence, if only to inspire confidence in the any order of the court. None of these was obtaining in the
case is re-filed. a compromise agreement. A "final order" issued by a court pursuit of a middle ground between petitioner and civil case.
It must be emphasized however that once the dismissal has been defined as one which disposes of the subject respondents, we must not interpret the trial While there was a lull of about six (6) months in the
attains the attribute of finality, the trial court cannot matter in its entirety or terminates a particular proceeding court's Orders as dismissing the action on its own motion prosecution of Civil Case No. 99-518, it must be
impose legal fees anew because a final and executory or action, leaving nothing else to be done but to enforce by because the parties, specifically petitioner, were anxious to remembered that respondents themselves contributed
dismissal although without prejudice divests the trial court execution what has been determined by the court, while an litigate their case as exhibited in their several largely to this delay. They repeatedly asked petitioner to
of jurisdiction over the civil case as well as any residual "interlocutory order" is one which does not dispose of a manifestations and motions. consider re-structuring the debt of respondent Magwin
power to order anything relative to the dismissed case; it case completely but leaves something more to be decided We reject respondent Uy's contention that Goldloop Marketing Corporation to which petitioner graciously
would have to wait until the complaint is docketed once upon. 31 Properties, Inc. v. Court of Appeals is irrelevant to the case at acceded. Petitioner approved a new debt payment scheme
again. 29 On the other hand, if we are to concede that the Besides the semantic and consequential improbabilities of bar on the dubious reasoning that the complaint of that was sought by respondents, which it then
trial court retains jurisdiction over Civil Case No. 99-518 respondent Uy's argument, our ruling in Goldloop petitioner was dismissed for failure to prosecute and not communicated to respondent Corporation through a letter
for it to issue the assailedOrders, a continuation of the Properties, Inc., is decisive of the instant case. In Goldloop for the non-submission of a compromise agreement which for the conformity of the latter's officers, i.e., respondent
hearing thereon would not trigger a disbursement for Properties, Inc., we reversed the action of the trial court in was the bone of contention in that case, and that the Nelson Tiu as President/General Manager and respondent
docket fees on the part of petitioner as this would dismissing the complaint for failure of the plaintiff to dismissal imposed in the instant case was without Benito Sy as Director thereof. Regrettably, only respondent
obviously imply the setting aside of the order of dismissal prosecute its case, which was in turn based on its inability prejudice, in contrast to the dismissal with prejudice Nelson Tiu affixed his signature on the letter to signify his
and the reinstatement of the complaint. to forge a compromise with the other parties within fifteen decreed in the cited case. To begin with, whether the concurrence with the terms and conditions of the
Indubitably, it is speculative to reckon the effectivity of (15) days from notice of the order to do so and held — dismissal is with or without prejudice if grievously arrangement. The momentary lag in the civil case was
the Order of dismissal without prejudice to the Since there is nothing in the Rules erroneous is detrimental to the cause of the affected aggravated when respondent Benito Sy for unknown and
presentation of the compromise agreement. If we are to that imposes the sanction of party; Goldloop Properties, Inc. does not tolerate a wrongful unexplained reasons paid no heed to the adjustments in the
admit that the efficacy of the invalidation of theOrder of dismissal for failing to submit a dismissal just because it was without prejudice. More indebtedness although curiously he has not opposed before
dismissal is dependent upon this condition, then we must compromise agreement, then it is importantly, the facts in Goldloop Properties, Inc. involve, as this Court or the courts a quo petitioner's desire to go
inquire: from what date do we count the fifteen (15)-day obvious that the dismissal of the in the instant case, a dismissal for failure to prosecute on ahead with the pre-trial conference. CSaITD
reglementary period within which the alleged revival of the complaint on the basis thereof the ground of the parties' inability to come up with a Admittedly, delay took place in this case but it was not an
order of dismissal began to run? Did it commence from the amounts no less to a gross compromise agreement within fifteen (15) days from interruption that should have entailed the dismissal of the
lapse of the fifteen (15) days provided for in the Order of 8 procedural infirmity assailable notice of the court's order therein. All told, the parallelism complaint even if such was designated as without
September 2000? Or do we count it from the 6 November by certiorari. For such submission between them is unmistakable. prejudice. To constitute a sufficient ground for dismissal,
2000 Orderwhen the trial court denied the holding of a pre- could at most be directory and the inattention of plaintiff to pursue his cause must not
trial conference? Or must it be upon petitioner's receipt of could not result in throwing out the Even if we are to accept on face value respondent's only be prolonged but also be unnecessary and dilatory
the 16 November 2000 Order denying due course to case for failure to effect a understanding of Goldloop Properties, Inc. as solely about resulting in the trifling of judicial processes. In the instant
its Notice of Appeal? The court a quo could not have compromise. While a compromise the failure to submit a compromise agreement, it is case, the adjournment was not only fleeting as it lasted less
instituted an Order that marked the proceedings before it is encouraged, very strongly in fact, apparent that the present case confronts a similar problem. than six (6) months but was also done in good faith to
with a shadow of instability and chaos rather than a failure to consummate one does not Perhaps initially the issue was one of failure to prosecute, accommodate respondents' incessant pleas to negotiate.
semblance of constancy and firmness. warrant any procedural sanction, as can be observed from the Orderdated 20 July 2000, Although the dismissal of a case for failure to prosecute is a
The subsequent actions of the trial court also belie an much less an authority to jettison a although later reversed and set aside. But thereafter, in matter addressed to the sound discretion of the court, that
intention to revive the Order of dismissal without prejudice civil complaint worth the Order of 6 November 2000, the trial court refused to judgment however must not be abused. The availability of
in the event that petitioner fails to submit a compromise P4,000,000.00 . . . Plainly, proceed to pre-trial owing to the "failure of the plaintiff to this recourse must be determined according to the
agreement. The Orders of 6 and 16 November 2000 plainly submission of a compromise submit a compromise agreement pursuant to the Order procedural history of each case, the situation at the time of
manifest that it was retaining jurisdiction over the civil agreement is never mandatory, nor dated 8 September 2000." When the civil case was stalled the dismissal, and the diligence of plaintiff to proceed
case, a fact which would not have been possible had the is it required by any rule. 32 on account of the trial court's refusal to call the parties to a therein. 35 Stress must also be laid upon the official
dismissal without prejudice been resuscitated. Surely, the As also explained therein, the proper course of action that pre-trial conference, the reason or basis therefor was the directive that courts must endeavor to convince parties in a
court a quo could not have denied on 6 November 2000 should have been taken by the court a quo, upon absence of a negotiated settlement — a circumstance that civil case to consummate a fair settlement 36 and to
petitioner's motion to calendar Civil Case No. 99-518 for manifestation of the parties of their willingness to discuss a takes the case at bar within the plain ambit ofGoldloop mitigate damages to be paid by the losing party who has
pre-trial if the dismissal had been restored to life in the settlement, was to suspend the proceedings and allow them Properties, Inc. In any event, given that the instant case shown a sincere desire for such give-and-take. 37 All things
meantime. By then the dismissal without prejudice would reasonable time to come to terms (a) If willingness to merely revolves around the search for a reasonable considered, we see no compelling circumstances to uphold
discuss a possible compromise is expressed by one or both interpretation of the several Orders of the trial court, i.e., as
the dismissal of petitioner's complaint regardless of its of Makati City, docketed as Civil Case No. 99-518, are also Warehouse Club and Administration Building in Libis, project, the same being for the
characterization as being without prejudice. REVERSED and SET ASIDE insofar as these Orders are Quezon City for a fee of P120,936,591.50, payable in account of the [Titan]. On the other
In fine, petitioner cannot be said to have lost interest in interpreted to impose upon and collect anew from monthly progress billings to be certified to by Uniwide's hand, [Titan] is absolved of any
fighting the civil case to the end. A court may dismiss a case petitioner RIZAL COMMERCIAL BANKING CORPORATION representative. 7 The parties stipulated that the building liability on the counterclaim for
on the ground of non prosequitur but the real test of the docket or legal fees for its complaint, or to dismiss without shall be completed not later than 30 November 1991. As defective construction of this
judicious exercise of such power is whether under the prejudice Civil Case No. 99-518, or to preclude the trial found by the CIAC, the building was eventually finished on project.
circumstances plaintiff is chargeable with want of fitting court from calling the parties therein to pre-trial 15 February 1992 8 and turned over to Uniwide. [Uniwide] is held liable for the
assiduousness in not acting on his complaint with conference, or from proceeding thereafter with dispatch to PROJECT 2. unpaid balance in the amount of
reasonable promptitude. Unless a party's conduct is so resolve the civil case. Sometime in July 1992, Titan and Uniwide entered into the P6,301,075.77 which is ordered to
indifferent, irresponsible, contumacious or slothful as to Civil Case No. 99-518 is deemed REINSTATED in, as it was second agreement (Project 2) whereby the former agreed be paid to the [Titan] with 12%
provide substantial grounds for dismissal, i.e., equivalent to never taken out from, the dockets of the Regional Trial to construct an additional floor and to renovate the latter's interest per annum commencing
default or non-appearance in the case, the courts should Court, Branch 135, of Makati City. The trial court is warehouse located at the EDSA Central Market Area in from 19 December 1992 until the
consider lesser sanctions which would still amount to ORDERED to exercise its jurisdiction over Civil Case No. 99- Mandaluyong City. There was no written contract executed date of payment.
achieving the desired end. 38 In the absence of a pattern or 518, to CONDUCT the pre-trial conference therein with between the parties for this project. Construction was On Project 3 — Kalookan:
scheme to delay the disposition of the case or of a wanton dispatch, and to UNDERTAKE thereafter such other allegedly to be on the basis of drawings and specifications [Uniwide] is held liable for the
failure to observe the mandatory requirement of the rules proceedings as may be relevant, without petitioner being provided by Uniwide's structural engineers. The parties unpaid balance in the amount of
on the part of the plaintiff, as in the case at bar, courts charged anew docket or other legal fees in connection with proceeded on the basis of a cost estimate of P21,301,075.77 P5,158,364.63 which is ordered to
should decide to dispense rather than wield their authority its reinstatement. Costs against respondents. inclusive of Titan's 20% mark-up. Titan conceded in its be paid to the [Titan] with 12%
to dismiss. 39 SO ORDERED. complaint to having received P15,000,000.00 of this interest per annum commencing
Clearly, another creative remedy was available to the ||| (Rizal Commercial Banking Corp. v. Magwin Marketing amount. This project was completed in the latter part of from 08 September 1993 until the
court a quo to attain a speedy disposition of Civil Case No. Corp., G.R. No. 152878, [May 5, 2003], 450 PHIL 720-743) October 1992 and turned over to Uniwide. date of payment.
99-518 without sacrificing the course of justice. Since the PROJECT 3. 9 [Uniwide] is held liable to pay in
failure of petitioner to submit a compromise agreement THIRD DIVISION The parties executed the third agreement (Project 3) in full the VAT on this project, in such
was the refusal of just one of herein respondents, i.e., [G.R. No. 126619. December 20, 2006.] May 1992. In a written "Construction Contract," Titan amount as may be computed by the
Benito Sy, to sign his name on theconforme of the loan UNIWIDE SALES REALTY AND undertook to construct the Uniwide Sales Department Bureau of Internal Revenue to be
restructure documents, and the common concern of the RESOURCES Store Building in Kalookan City for the price of paid directly thereto. The BIR is
courts a quo was dispatch in the proceedings, the holding of CORPORATION, petitioner, vs. P118,000,000.00 payable in progress billings to be certified hereby notified that [Uniwide]
a pre-trial conference was the best-suited solution to the TITAN-IKEDA CONSTRUCTION to by Uniwide's representative. 10 It was stipulated that Sales Realty and Resources
problem as this stage in a civil action is where issues are AND DEVELOPMENT the project shall be completed not later than 28 February Corporation has assumed
simplified and the dispute quickly and genuinely CORPORATION, respondent. 1993. The project was completed and turned over to responsibility and is held liable for
reconciled. By means of pre-trial, the trial court is fully DECISION Uniwide in June 1993. cCTAIE VAT payment on this project. This
empowered to sway the litigants to agree upon some fair TINGA, J p: Uniwide asserted in its petition that: (a) it overpaid Titan accordingly exempts Claimant
compromise. This Petition for Review on Certiorari under Rule 45 seeks for unauthorized additional works in Project 1 and Project Titan-Ikeda Construction and
Dismissing the civil case and compelling petitioner to re- the partial reversal of the 21 February 1996 Decision 1 of 3; (b) it is not liable to pay the Value-Added Tax (VAT) for Development Corporation from this
file its complaint is a dangerous, costly and circuitous route the Court of Appeals Fifteenth Division in CA-G.R. SP No. Project 1; (c) it is entitled to liquidated damages for the obligation.
that may end up aggravating, not resolving, the 37957 which modified the 17 April 1995 Decision 2 of the delay incurred in constructing Project 1 and Project 3; and Let a copy of this Decision be
disagreement. This case management strategy is Construction Industry Arbitration Commission (CIAC). (d) it should not have been found liable for deficiencies in furnished the Honorable Aurora P.
frighteningly deceptive because it does so at the expense of The case originated from an action for a sum of money filed the defectively constructed Project 2. Navarette Recina, Presiding Judge,
petitioner whose cause of action, perhaps, may have by Titan-Ikeda Construction and Development Corporation An Arbitral Tribunal consisting of a chairman and two Branch 119, Pasay City, in Civil Case
already been admitted by its adverse parties as shown by (Titan) against Uniwide Sales Realty and Resources members was created in accordance with the CIAC Rules of No. 94-0814 entitled Titan-Ikeda
three (3) of four (4) defendants not willing to contest Corporation (Uniwide) with the Regional Trial Court (RTC), Procedure Governing Construction Arbitration. It Construction Development
petitioner's allegations, and more critically, since this Branch 119, 3 Pasay City arising from Uniwide's non- conducted a preliminary conference with the parties and Corporation, Plaintiff — versus —
approach promotes the useless and thankless duplication payment of certain claims billed by Titan after completion thereafter issued a Terms of Reference (TOR) which was Uniwide Sales Realty and Resources
of hard work already undertaken by the trial court. As we of three projects covered by agreements they entered into signed by the parties. The tribunal also conducted an ocular Corporation, Defendant, pending
have aptly observed, "[i]nconsiderate dismissals, even if with each other. Upon Uniwide's motion to inspection, hearings, and received the evidence of the before said court for information
without prejudice, do not constitute a panacea nor a dismiss/suspend proceedings and Titan's open court parties consisting of affidavits which were subject to cross- and proper action.
solution to the congestion of court dockets. While they lend manifestation agreeing to the suspension, Civil Case No. 98- examination. On 17 April 1995, after the parties submitted SO ORDERED." 12
a deceptive aura of efficiency to records of individual 0814 was suspended for it to undergo arbitration. 4 Titan's their respective memoranda, the Arbitral Tribunal Uniwide filed a motion for reconsideration of the 17 April
judges, they merely postpone the ultimate reckoning complaint was thus re-filed with the CIAC. 5 Before the promulgated a Decision, 11 the decretal portion of which is 1995 decision which was denied by the CIAC in its
between the parties. In the absence of clear lack of merit or CIAC, Uniwide filed an answer which was later amended as follows: Resolution dated 6 July 1995. Uniwide accordingly filed a
intention to delay, justice is better served by a brief and re-amended, denying the material allegations of the "WHEREFORE, judgment is hereby petition for review with the Court of Appeals, 13which
continuance, trial on the merits, and final disposition of the complaint, with counterclaims for refund of overpayments, rendered as follows: rendered the assailed decision on 21 February 1996.
cases before the court." 40 actual and exemplary damages, and attorney's fees. The On Project 1 — Libis: Uniwide's motion for reconsideration was likewise denied
WHEREFORE, the Petition for Review is GRANTED. agreements between Titan and Uniwide are briefly [Uniwide] is absolved of any by the Court of Appeals in its assailed Resolution 14 dated
The Decision dated 28 September 2001 described below. liability for the claims made by 30 September 1996.
and Resolutiondated 2 April 2002 of the Court of Appeals in PROJECT 1. 6 [Titan] on this Project. Hence, Uniwide comes to this Court via a petition for
CA-G.R. SP No. 62102 are REVERSED and SET ASIDE. The first agreement (Project 1) was a written "Construction Project 2 — Edsa Central: review under Rule 45. The issues submitted for resolution
The Orders dated 8 September 2000, 6 November 2000 and Contract" entered into by Titan and Uniwide sometime in [Uniwide] is absolved of any of this Court are as follows: 15 (1) Whether Uniwide is
16 November 2000 of the Regional Trial Court, Branch 135, May 1991 whereby Titan undertook to construct Uniwide's liability for VAT payment on this entitled to a return of the amount it allegedly paid by
mistake to Titan for additional works done on Project 1; (2) the Arbitral Tribunal considering that the computations, as paid a debt even while it knew that it was not legally be evidence establishing the frame of mind of the payor at
Whether Uniwide is liable for the payment of the Value- well as the propriety of the awards, are unquestionably compelled to do so. As such debtor, Uniwide could no the time the payment was made. 32
Added Tax (VAT) on Project 1; (3) Whether Uniwide is factual issues that have been discussed by the Arbitral longer demand the refund of the amount already paid. The CIAC refused to acknowledge that the additional works
entitled to liquidated damages for Projects 1 and 3; and (4) Tribunal and affirmed by the Court of Appeals. SACEca Uniwide counters that Art. 1724 makes no distinction as to on Project 1 were indeed unauthorized by Uniwide. Neither
Whether Uniwide is liable for deficiencies in Project 2. whether payment for the "additional works" had already did the Court of Appeals arrive at a contrary determination.
As a rule, findings of fact of administrative agencies and In the present case, only the first issue presented for been made. It claims that it had made the payments, subject There would thus be some difficulty for this Court to agree
quasi-judicial bodies, which have acquired expertise resolution of this Court is a question of law while the rest to reservations, upon the false representation of Titan- with this most basic premise submitted by Uniwide that it
because their jurisdiction is confined to specific matters, are factual in nature. However, we do not hesitate to Ikeda that the "additional works" were authorized in did not authorize the additional works on Project 1
are generally accorded not only respect, but also finality, inquire into these factual issues for the reason that the writing. Uniwide characterizes the payment as a "mistake," undertaken by Titan. Still, Uniwide does cite testimonial
especially when affirmed by the Court of Appeals. 16 In CIAC and the Court of Appeals, in some matters, differed in and not a "voluntary" fulfillment under Art. 1423 of the evidence from the record alluding to a concession by
particular, factual findings of construction arbitrators are their findings. Civil Code. Hence, it urges the application, instead, of the employees of Titan that these additional works on Project 1
final and conclusive and not reviewable by this Court on We now proceed to discuss the issues in seriatim. principle of solutio indebiti under Arts. 2154 28 and were either authorized or documented. 33
appeal. 17 This rule, however admits of certain exceptions. Payment by Mistake for Project 1 2156 29 of the Civil Code. Yet even conceding that the additional works on Project 1
In David v. Construction Industry and Arbitration The first issue refers to the P5,823,481.75 paid by Uniwide To be certain, this Court has not been wont to give an were not authorized or committed into writing, the
Commission, 18 we ruled that, as exceptions, factual for additional works done on Project 1. Uniwide asserts expansive construction of Art. 1724, denying, for example, undisputed fact remains that Uniwide paid for these
findings of construction arbitrators may be reviewed by that Titan was not entitled to be paid this amount because claims that it applies to constructions made of ship additional works. Thus, to claim a refund of payments
this Court when the petitioner proves affirmatively that: the additional works were without any written vessels, 30 or that it can validly deny the claim for payment made under the principle of solutio indebiti, Uniwide must
(1) the award was procured by corruption, fraud or other authorization. of professional fees to the architect. 31 The present be able to establish that these payments were made
undue means; (2) there was evident partiality or It should be noted that the contracts do not contain situation though presents a thornier problem. Clearly, Art. through mistake. Again, this is a factual matter that would
corruption of the arbitrators or of any of them; (3) the stipulations on "additional works," Uniwide's liability for 1724 denies, as a matter of right, payment to the contractor have acquired a mantle of invulnerability had it been
arbitrators were guilty of misconduct in refusing to hear "additional works," and prior approval as a requirement for additional works which were not authorized in writing determined by both the CIAC and the Court of Appeals.
evidence pertinent and material to the controversy; (4) one before Titan could perform "additional works." by the proprietor, and the additional price of which was not However, both bodies failed to arrive at such a conclusion.
or more of the arbitrators were disqualified to act as such Nonetheless, Uniwide cites Article (Art.) 1724 of the New determined in writing by the parties. Moreover, Uniwide is unable to direct our attention to any
under Section nine of Republic Act No. 876 and willfully Civil Code as basis for its claim that it is not liable to pay for Yet the distinction pointed out by the Court of Appeals is pertinent part of the record that would indeed establish
refrained from disclosing such disqualifications or of any "additional works" it did not authorize or agree upon in material. The issue is no longer centered on the right of the that the payments were made by reason of
other misbehavior by which the rights of any party have writing. The provision states: contractor to demand payment for additional works mistake. HEacAS
been materially prejudiced; or (5) the arbitrators exceeded Art. 1724. The contractor who undertaken because payment, whether mistaken or not, We note that Uniwide alleged in its petition that the CIAC
their powers, or so imperfectly executed them, that a undertakes to build a structure or was already made by Uniwide. Thus, it would not anymore award in favor of Titan in the amount P5,158,364.63 as the
mutual, final and definite award upon the subject matter any other work for a stipulated be incumbent on Titan to establish that it had the right to unpaid balance in Project 3 included claims for additional
submitted to them was not made. 19 price, in conformity with plans and demand or receive such payment. works of P1,087,214.18 for which no written authorization
Other recognized exceptions are as follows: (1) when there specifications agreed upon with the But, even if the Court accepts Art. 1724 as applicable in this was presented. Unfortunately, this issue was not included
is a very clear showing of grave abuse of landowner, can neither withdraw case, such recognition does not ipso facto accord Uniwide in its memorandum as one of the issues submitted for the
discretion 20 resulting in lack or loss of jurisdiction as from the contract nor demand an the right to be reimbursed for payments already made, resolution of the Court.
when a party was deprived of a fair opportunity to present increase in the price on account of since Art. 1724 does not effect such right of Liability for the Value-Added Tax (VAT)
its position before the Arbitral Tribunal or when an award the higher cost of labor or reimbursement. It has to be understood that Art. 1724 does The second issue takes us into an inquiry on who, under
is obtained through fraud or the corruption of materials, save when there has not preclude the payment to the contractor who performs the law, is liable for the payment of the VAT, in the absence
arbitrators, 21 (2) when the findings of the Court of been a change in the plans and additional works without any prior written authorization of a written stipulation on the matter. Uniwide claims that
Appeals are contrary to those of the CIAC, 22and (3) when specifications, provided: or agreement as to the price for such works if the owner the VAT was already included in the contract price for
a party is deprived of administrative due process. 23 (1) Such change has been decides anyway to make such payment. What the provision Project 1. Citing Secs. 99 and 102 of the National Internal
Thus, in Hi-Precision Steel Center, Inc. v. Lim Kim Builders, authorized by does preclude is the right of the contractor to insist upon Revenue Code, Uniwide asserts that VAT, being an indirect
Inc., 24 we refused to review the findings of fact of the CIAC the proprietor payment for unauthorized additional works. tax, may be shifted to the buyer by including it in the cash
for the reason that petitioner was requiring the Court to go in writing; and Accordingly, Uniwide, as the owner who did pay the or selling price and it is entirely up to the buyer to agree or
over each individual claim and counterclaim submitted by (2) The additional price contractor for such additional works even if they had not not to agree to absorb the VAT. 34 Thus, Uniwide
the parties in the CIAC. A review of the CIAC's findings of to be paid to been authorized in writing, has to establish its own right to concludes, if there is no provision in the contract as to who
fact would have had the effect of "setting at naught the the contractor reimbursement not under Art. 1724, but under a different should pay the VAT, it is presumed that it would be the
basic objective of a voluntary arbitration and would reduce has been provision of law. Uniwide's burden of establishing its legal seller. 35
arbitration to a largely inutile institution." Further, determined in right to reimbursement becomes even more crucial in the The contract for Project 1 is silent on which party should
petitioner therein failed to show any serious error of law writing by light of the general presumption contained in Section 3(f), shoulder the VAT while the contract for Project 3 contained
amounting to grave abuse of discretion resulting in lack of both parties. Rule 131 of the Rules of Court that "money paid by one to a provision to the effect that Uniwide is the party
jurisdiction on the part of the Arbitral Tribunal, in either The Court of Appeals did take note of this provision, but another was due to the latter." responsible for the payment of the VAT. 36 Thus, when
the methods employed or the results reached by the deemed it inapplicable to the case at bar because Uniwide Uniwide undertakes such a task before this Court, citing the Uniwide paid the amount of P2,400,000.00 as billed by
Arbitral Tribunal, in disposing of the detailed claims of the had already paid, albeit with unwritten reservations, for provisions on solutio indebiti under Arts. 2154 and 2156 of Titan for VAT, it assumed that it was the VAT for Project 3.
respective parties. In Metro Construction, Inc. v. Chatham the "additional works." The provision would have been the Civil Code. However, it is not enough to prove that the However, the CIAC and the Court of Appeals found that the
Properties, Inc., 25 we reviewed the findings of fact of the operative had Uniwide refused to pay for the costs of the payments made by Uniwide to Titan were "not due" same was for Project 1.
Court of Appeals because its findings on the issue of "additional works." Instead, the Court of Appeals applied because there was no prior authorization or agreement We agree with the conclusions of both the CIAC and the
whether petitioner therein was in delay were contrary to Art. 1423 27 of the New Civil Code and characterized with respect to additional works. There is a further Court of Appeals that the amount of P2,400,000.00 was
the findings of the CIAC. Finally, in Megaworld Globus Asia, Uniwide's payment of the said amount as a voluntary requirement that the payment by the debtor was made paid by Uniwide as VAT for Project 1. This conclusion was
Inc. v. DSM Construction and Development fulfillment of a natural obligation. The situation was either through mistake or under a cloud of doubt. In short, drawn from an Order of Payment 37 dated 7 October 1992
Corporation, 26 we declined to depart from the findings of characterized as being akin to Uniwide being a debtor who for the provisions on solutio indebiti to apply, there has to wherein Titan billed Uniwide the amount of P2,400,000.00
as "Value Added Tax based on P60,000,000.00 Contract," Memorandum submitted to the CIAC at the end of the the TOR in order to accommodate attributable to the contractor if not otherwise justifiable.
computed on the basis of 4% of P60,000,000.00. Said arbitration proceeding. The Court of Appeals also noted the issues related to its belated Contrarily, Uniwide's belated claim constitutes an
document which was approved by the President of Uniwide that the only evidence on record to prove delay in the counterclaim" on this issue. admission that the delay was justified and implies a waiver
expressly indicated that the project involved was the construction of Project 1 is the testimony of Titan's (Emphasis supplied.) THSaEC of its right to such damages.
"UNIWIDE SALES WAREHOUSE CLUB & ADMIN BLDG." engineer regarding the date of completion of the project Arbitration has been defined as "an arrangement for taking Project 2: "as-built" plans, overpricing, defective
located at "90 E. RODRIGUEZ JR. AVE., LIBIS, Q.C." The while the only evidence of delay in the construction of and abiding by the judgment of selected persons in some construction
reduced base for the computation of the tax, according to Project 3 is the affidavit of Uniwide's President. disputed matter, instead of carrying it to established To determine whether or not Uniwide is liable for the
the Court of Appeals, was an indication that the parties According to Uniwide, the ruling of the Court of Appeals on tribunals of justice, and is intended to avoid the formalities, unpaid balance of P6,301,075.77 for Project 2, we need to
agreed to pass the VAT for Project 1 to Uniwide but based the issue of liquidated damages goes against the the delay, the expense and vexation of ordinary resolve four sub-issues, namely: (1) whether or not it was
on a lower contract price. Indeed, the CIAC found as established judicial policy that a court should always strive litigation." 43 Voluntary arbitration, on the other hand, necessary for Titan to submit "as-built" plans before it can
follows: to settle in one proceeding the entire controversy leaving involves the reference of a dispute to an impartial body, the be paid by Uniwide; (2) whether or not there was
Without any documentary evidence no root or branch to bear the seeds of future members of which are chosen by the parties themselves, overpricing of the project; (3) whether or not the
than Exhibit "H" to show the extent litigations. 41 Uniwide claims that the required evidence which parties freely consent in advance to abide by the P15,000,000.00 paid by Uniwide to Titan for Project 2
of tax liability assumed by for an affirmative ruling on its claim is already on the arbitral award issued after proceedings where both parties constitutes full payment; and (4) whether or not Titan can
[Uniwide], the Tribunal holds that record. It cites the pertinent provisions of the written had the opportunity to be heard. The basic objective is to be held liable for defective construction of Project 2.
the parties is [sic] obliged to pay contracts which contained deadlines for liquidated provide a speedy and inexpensive method of settling The CIAC, as affirmed by the Court of Appeals, held Uniwide
only a share of the VAT payment up damages. Uniwide also noted that the evidence show that disputes by allowing the parties to avoid the formalities, liable for deficiency relating to Project 2 in the amount of
to P60,000,000.00 out of the total Project 1 was completed either on 15 February 1992, as delay, expense and aggravation which commonly P6,301,075.77. It is nonetheless alleged by Uniwide that
contract price of found by the CIAC, or 12 March 1992, as shown by Titan's accompany ordinary litigation, especially litigation which Titan failed to submit any "as-built" plans for Project 2,
P120,936,591.50. As explained by own evidence, while Project 3, according to Uniwide's goes through the entire hierarchy of courts. 44 As an such plans allegedly serving as a condition precedent for
Jimmy Gow, VAT is paid on labor President, was completed in June 1993. Furthermore, arbitration body, the CIAC can only resolve issues brought payment. Uniwide further claims that Titan had
only for construction contracts Uniwide asserts, the CIAC should have applied procedural before it by the parties through the TOR which functions substantially overcharged Uniwide for Project 2, there
since VAT had already been paid rules such as Section 5, Rule 10 with more liberality similarly as a pre-trial brief. Thus, if Uniwide's claim for being uncontradicted expert testimony that the total cost of
on the materials purchased. because it was an administrative tribunal free from the liquidated damages was not raised as an issue in the TOR Project 2 did not exceed P7,812,123.60. Furthermore,
Since labor costs is [sic] rigid technicalities of regular courts. 42 or in any modified or amended version of it, the CIAC Uniwide alleged that the works performed were
proportionately placed at 60%- On this point, the CIAC held: cannot make a ruling on it. The Rules of Court cannot be structurally defective, as evidenced by the structural
40% of the contract price, The Rule of Procedure Governing used to contravene the spirit of the CIAC rules, whose damage on four columns as observed on ocular inspection
simplified accounting computes Construction Arbitration policy and objective is to "provide a fair and expeditious by the CIAC and confirmed by Titan's project manager.
VAT at 4% of the contract price. promulgated by the CIAC contains settlement of construction disputes through a non-judicial On the necessity of submitting "as-built" plans, this Court
Whatever is the balance for VAT no provision on the application of process which ensures harmonious and friendly relations rules that the submission of such plans is not a pre-
that remains to be paid on Project 1 the Rules of Court to arbitration between or among the parties." 45 requisite for Titan to be paid by Uniwide. The argument
— Libis shall remain the obligation proceedings, even in a suppletory Further, a party may not be deprived of due process of law that said plans are required by Section 308 ofPresidential
of [Titan]. (Emphasis supplied.) 38 capacity. Hypothetically admitting by an amendment of the complaint as provided in Section Decree No. 1098 (National Building Code) and by Section
Liquidated Damages that there is such a provision, 5, Rule 10 of the Rules of Court. In this case, as noted by the 2.11 of its Implementing Rules before payment can be
On the third issue of liquidated damages, the CIAC rejected suppletory application is made only Court of Appeals, Uniwide only introduced and quantified made is untenable. The purpose of the law is "to safeguard
such claim while the Court of Appeals held that the matter if it would not contravene a specific its claim for liquidated damages in its memorandum life, health, property, and public welfare, consistent with
should be left for determination in future proceedings provision in the arbitration rules submitted to the CIAC at the end of the arbitration the principles of sound environmental management and
where the issue has been made clear. and the spirit thereof. The Tribunal proceeding. Verily, Titan was not given a chance to present control." The submission of these plans is necessary only in
holds that such importation of the evidence to counter Uniwide's claim for liquidated furtherance of the law's purpose by setting minimum
In rejecting Uniwide's claim for liquidated damages, the Rules of Court provision on damages. standards and requirements to control the "location, site,
CIAC held that there is no legal basis for passing upon and amendment to conform to Uniwide alludes to an alleged judicial admission made by design, quality of materials, construction, use, occupancy,
resolving Uniwide's claim for the following reasons: (1) no evidence would contravene the Engr. Luzon Tablante wherein he stated that Project 1 was and maintenance" of buildings constructed and not as a
claim for liquidated damages arising from the alleged delay spirit, if not the letter of the CIAC completed on 10 March 1992. It now claims that by virtue requirement for payment to the contractor. 47 The
was ever made by Uniwide at any time before the rules. This is for the reason that the of Engr. Tablante's statement, Titan had admitted that it testimony of Engr. Tablante to the effect that the "as-built"
commencement of Titan's complaint; (2) the claim for formulation of the Terms of was in delay. We disagree. The testimony of Engr. Tablante plans are required before payment can be claimed by Titan
liquidated damages was not included in the counterclaims Reference is done with the active was offered only to prove that Project 1 was indeed is a mere legal conclusion which is not binding on this
stated in Uniwide's answer to Titan's complaint; (3) the participation of the parties and completed. It was not offered to prove the fact of delay. It Court.
claim was not formulated as an issue to be resolved by the their counsel themselves. The TOR must be remembered that the purpose for which evidence Uniwide claims that, according to one of its consultants, the
CIAC in the TOR; 39 and (4) no attempt was made to is further required to be signed by is offered must be specified because such evidence may be true price for Project 2 is only P7,812,123.60. The CIAC and
modify the TOR to accommodate the same as an issue to be all the parties, their respective admissible for several purposes under the doctrine of the Court of Appeals, however, found the testimony of this
resolved. counsel and all the members of the multiple admissibility, or may be admissible for one consultant suspect and ruled that the total contract price
Uniwide insists that the CIAC should have applied Section Arbitral Tribunal. Unless the issues purpose and not for another, otherwise the adverse party for Project 2 is P21,301,075.77. The CIAC held:
5, Rule 10 of the Rules of Court. 40 On this matter, the thus carefully formulated in the cannot interpose the proper objection. Evidence submitted The Cost Estimate
Court of Appeals held that the CIAC is an arbitration body, Terms of Reference were expressly for one purpose may not be considered for any other for Architectural and Site
which is not necessarily bound by the Rules of Court. Also, showed [sic] to be amended, issues purpose. 46 Furthermore, even assuming, for the sake of Development Works for the EDSA
the Court of Appeals found that the issue has never been outside thereof may not be argument, that said testimony on the date of completion of Central, Dau Branch Project
made concrete enough to make Titan and the CIAC aware resolved. As already noted in the Project 1 is admitted, the establishment of the mere fact of (Exhibit "2-A" for [Uniwide] and
that it will be an issue. In fact, Uniwide only introduced and Decision, "no attempt was ever delay is not sufficient for the imposition of liquidated made as a common exhibit by
quantified its claim for liquidated damages in its made by the [Uniwide] to modify damages. It must further be shown that delay was [Titan] who had it marked at [sic]
its own Exhibit "U"), which was responsible for damages if the edifice constructed falls severely impaired. Further, it was found that the concrete factual conclusions of the Tribunal
admittedly prepared by within fifteen years from completion on account of defects slab placed by Titan was not attached to the old columns which resulted in deprivation of
Fermindoza and Associates, in the construction or the use of materials of inferior where cracks were discovered. The CIAC held that the post- one or the other party of a fair
[Uniwide]'s own architects, shows quality furnished by him or due to any violation of the tensioning of the new concrete slab could not have caused opportunity to present its position
that the amount of P17,750,896.48 terms of the contract. any of the defects manifested by the old columns. We are before the Arbitral Tribunal, and an
was arrived at. Together with the On this matter, the CIAC conducted an ocular inspection of bound by this finding of fact by the CIAC. award obtained through fraud or
agreed upon mark-up of 20% on the premises on 30 January 1995. What transpired in the It is worthy to stress our ruling in Hi-Precision Steel Center, the corruption of arbitrators. Any
said amount, the total project said ocular inspection is described thus: Inc. v. Lim Kim Steel Builders, Inc. 54 which was reiterated other, more relaxed rule would
cost was P21,301,075.77. On 30 January 1995, an ocular in David v. Construction Industry and Arbitration result in setting at naught the
inspection was conducted by the Commission, 55 that: basic objective of a voluntary
The Tribunal holds that the Arbitral Tribunal as requested by . . . Executive Order No. arbitration and would reduce
foregoing document is binding [Uniwide]. Photographs were taken 1008 created an arbitration facility arbitration to a largely inutile
upon the [Uniwide], it being the of the alleged construction defects, to which the construction industry institution. (Emphasis supplied.)
mode agreed upon by which its an actual ripping off of the plaster in the Philippines can have WHEREFORE, premises considered, the petition is DENIED
liability for the project cost was to of a certain column to expose the recourse. The Executive Order and the Decision of the Court of Appeals dated 21 February
be determined. 48 (Emphasis alleged structural defect that is was enacted to encourage the 1996 in CA-G.R. SP No. 37957 is hereby
supplied.) EAcHCI claimed to have resulted in its early and expeditious settlement AFFIRMED. TSDHCc
Indeed, Uniwide is bound by the amount indicated in the being "heavily damaged" was done, of disputes in the construction SO ORDERED.
above document. Claims of connivance or fraudulent clarificatory questions were asked industry, a public policy the ||| (Uniwide Sales Realty and Resources Corp. v. Titan-Ikeda
conspiracy between Titan and Uniwide's representatives and manifestations on observations implementation of which is Construction and Development Corporation, G.R. No. 126619,
which, it is alleged, grossly exaggerated the price may were made by the parties and their necessary and important for the [December 20, 2006], 540 PHIL 350-376)
properly be dismissed. As held by the CIAC: respective counsels. The entire realization of national
The Tribunal holds that proceedings were recorded on tape development goals. THIRD DIVISION
[Uniwide] has not introduced any and subsequently transcribed. The Aware of the objective of voluntary [G.R. Nos. 132848-49. June 26, 2001.]
evidence to sustain its charge of photographs and transcript of the arbitration in the labor field, in the PHILROCK, INC., petitioner, vs.
fraudulent conspiracy. As a ocular inspection form part of the construction industry, and in any CONSTRUCTION INDUSTRY
matter of fact, [Uniwide]'s own records and considered as other area for that matter, the ARBITRATION COMMISSION and
principal witness, Jimmy Gow, evidence. 52 Court will not assist one or the Spouses VICENTE and NELIA
admitted on cross-examination that And, according to these evidence, the CIAC concluded as other or even both parties in any CID, respondents.
he does not have any direct follows: effort to subvert or defeat that Ponce Enrile Reyes Manalastas for petitioner.
evidence to prove his charge of It is likewise the holding of this objective for their private SYNOPSIS
connivance or complicity Tribunal that [Uniwide]'s purposes. The Court will not A complaint for damages was filed with the RTC by the Cid
between the [Titan] and his own counterclaim of defective review the factual findings of an spouses against Philrock, Inc. and seven of its officers in
representatives. He only made construction has not been arbitral tribunal upon the artful connection with the construction of the former's house.
that conclusion by the process of sufficiently proven. The allegation that such body had The same was dismissed and referred to the CIAC pursuant
his own "logical reasoning" arising credibility of Engr. Cruz, "misapprehended facts" and will to the parties' Agreement to Arbitrate. Due to
from his consultation with other [Uniwide]'s principal witness on not pass upon issues which are, disagreements on the inclusion of the seven officers therein
contractors who gave him a much this issue, has been severely at bottom, issues of fact, no who are not parties to the Agreement to Arbitrate, the case
lower estimate for the construction impaired. During the ocular matter how cleverly disguised was remanded to the trial court who, however, declared
of the Dau Project. There is thus inspection of the premises, he gave they might be as "legal that it no longer had jurisdiction. The case was remanded
no reason to invalidate the such assurance of the soundness of questions." The parties here had back to the CIAC and proceedings therein continued with
binding character of Exhibit "2- his opinion as an expert that a recourse to arbitration and the exclusion of the seven officers. Terms of Reference to
A" which, it is significant to point certain column was heavily chose the arbitrators settle the differences of the parties by an Arbitral Tribunal
out, is [Uniwide]'s own damaged judging from the external themselves; they must have had was signed and later, the CIAC rendered a decision in favor
evidence. 49 (Emphasis supplied.) cracks that was readily apparent . . . confidence in such arbitrators. of the Cid spouses. Petitioner contested the jurisdiction of
Accordingly, deducting the P15,000,000.00 already paid by xxx xxx xxx The Court will not, therefore, the CIAC and assailed its decision, but the Court of Appeals
Uniwide from the total contract price of P21,301,075.77, On insistence of the Tribunal, the permit the parties to relitigate upheld the same. Hence, this petition.
the unpaid balance due for Project 2 is P6,301,075.77. This plaster was chipped off and before it the issues of facts Section 4 of Executive Order 1008 expressly vests in the
is the same amount reflected in the Order of Payment revealed a structurally sound previously presented and argued CIAC original and exclusive jurisdiction over disputes
prepared by Uniwide's representative, Le Consultech, Inc. column . . . before the Arbitral Tribunal, arising from construction contracts entered into by parties
and signed by no less than four top officers and architects Further, it turns out that what was save only where a clear showing that have agreed to submit their dispute to voluntary
of Le Consultech, Inc. endorsing for payment by Uniwide to being passed off as a defective is made that, in reaching its arbitration. Here, the parties agreed to arbitrate in the CIAC
Titan the amount of P6,301,075.77. 50 construction by [Titan], was in factual conclusions, the Arbitral with the issue of exclusion of the seven officers settled.
Uniwide asserts that Titan should not have been allowed to fact an old column, as admitted by Tribunal committed an error so Petitioner continued participating in the arbitration
recover on Project 2 because the said project was defective Mr. Gow himself . . . 53 (Emphasis egregious and hurtful to one proceedings and even signed the Terms of Reference.
and would require repairs in the amount of P800,000.00. It supplied.) party as to constitute a grave Petitioner was estopped in questioning the jurisdiction of
claims that the CIAC and the Court of Appeals should have Uniwide had the burden of proving that there was defective abuse of discretion resulting in the CIAC.
applied Nakpil and Sons v. Court of Appeals 51 and Art. construction in Project 2 but it failed to discharge this lack or loss of jurisdiction. SYLLABUS
1723 of the New Civil Code holding a contractor burden. Even the credibility of its own witness was Prototypical examples would be
1. ADMINISTRATIVE LAW; CONSTRUCTION INDUSTRY that respondent spouses did not engage the services of Before us is a Petition for Review under Rule 45 of the '. . .
ARBITRATION COMMISSION; JURISDICTION THEREOF legal counsel. Also, it contends that attorney's fees and Rules of Court. The Petition seeks the reversal of the July 9, the Arbitral
UNDER SECTION 4 OF EXECUTIVE ORDER NO. 1008. — litigation expenses are awarded only if the opposing party 1997 Decision 1 and the February 24, 1998 Resolution of Tribunal
Section 4 of Executive Order 1008 expressly vests in the acted in gross and evident bad faith in refusing to satisfy the Court of Appeals (CA) in the consolidated cases hereby
CIAC original and exclusive jurisdiction over disputes plaintiff's valid, just and demandable claim. We disagree. docketed as CA-GR SP Nos. 39781 and 42443. The assailed formally
arising from or connected with construction contracts The award is not only for attorney's fees, but also for Decision disposed as follows: dismisses the
entered into by parties that have agreed to submit their expenses of litigation. Hence, it does not matter if WHEREFORE, judgment is hereby above-
dispute to voluntary arbitration. TAESDH respondents represented themselves in court, because it is rendered DENYING the petitions captioned case
2. CIVIL LAW; ESTOPPEL; AFTER SUBMITTING ITSELF TO obvious that they incurred expenses in pursuing their and, accordingly, AFFIRMING in for referral to
ARBITRATION PROCEEDINGS AND ACTIVELY action before the CIAC, as well as the regular and the totothe CIAC's decision. Costs Branch 82 of
PARTICIPATING THEREIN, PETITIONER IN CASE AT BAR appellate courts. We find no reason to disturb this award. against petitioner." 2 the Regional
IS ESTOPPED FROM ASSAILING JURISDICTION OF THE 7. REMEDIAL LAW; CIVIL PROCEDURE; ACTIONS; CAUSE The assailed Resolution ruled in this wise: Trial Court,
CONSTRUCTION INDUSTRY ARBITRATION COMMISSION, OF ACTION; DEFINED; WHEN COMPLAINT DEEMED TO "Considering that the matters Quezon City
MERELY BECAUSE LATTER RENDERED AN ADVERSE HAVE STATED A CAUSE OF ACTION. — Cause of action is raised and discussed in the motion where it first
DECISION. — As pointed out by the solicitor general, defined as an act or omission by which a party violates the for reconsideration filed by originated.
petitioner maneuvered to avoid the RTC's final resolution right of another. A complaint is deemed to have stated a appellant's counsel are SO ORDERED.'
of the dispute by arguing that the regular court also lost cause of action provided it has indicated the following: (1) substantially the same arguments "The Cid spouses then filed with
jurisdiction after the arbitral tribunal's April 13, 1994 the legal right of the plaintiff, (2) the correlative obligation which the Court had passed upon said Branch of the Regional Trial
Order referring the case back to the RTC. In so doing, of the defendant, and (3) the act or the omission of the and resolved in the decision sought Court of Quezon City a Motion To
petitioner conceded and estopped itself from further defendant in violation of the said legal right. The cause of to be reconsidered, and there being Set Case for Hearing which motion
questioning the jurisdiction of the CIAC. The Court will not action against petitioner was clearly established. no new issue raised, the subject was opposed by Philrock.
countenance the effort of any party to subvert or defeat the Respondents were purchasers of ready-mix concrete from motion is hereby DENIED." 3
objective of voluntary arbitration for its own private petitioner. The concrete delivered by the latter turned out The Facts "On June 13, 1995, the trial court
motives. After submitting itself to arbitration proceedings to be of substandard quality. As a result, respondents The undisputed facts of the consolidated cases are declared that it no longer had
and actively participating therein, petitioner is estopped sustained damages when the structures they built using summarized by the CA as follows: jurisdiction over the case and
from assailing the jurisdiction of the CIAC, merely because such cement developed cracks and honeycombs. "On September 14, 1992, the Cid ordered the records of the case to
the latter rendered an adverse decision. Consequently, the construction of their residence had to be spouses, herein private be remanded anew to the CIAC for
3. ID.; DAMAGES; PAYMENT OF INTEREST IN CASE AT BAR stopped. AHCcET respondents, filed a Complaint for arbitral proceedings.
BASED ON ARTICLE 2209 OF CIVIL CODE. — The payment 8. ID.; EVIDENCE; DESPITE STATUTORY PROVISIONS damages against Philrock and "Pursuant to the aforementioned
of interest is based on Article 2209 of the Civil Code, which MAKING DECISIONS OF CERTAIN ADMINISTRATIVE seven of its officers and engineers Order of the Regional Trial C[o]urt
provides that if the obligation consists of the payment of a AGENCIES "FINAL," COURT STILL TAKES COGNIZANCE OF with the Regional Trial Court of of Quezon City, the CIAC resumed
sum of money, and the debtor incurs delay, the indemnity PETITIONS SHOWING WANT OF JURISDICTION, GRAVE Quezon City, Branch 82. conducting preliminary
for damages shall be the payment of legal interest which is ABUSE OF DISCRETION, VIOLATION OF DUE PROCESS, "On December 7, 1993, the initial conferences. On August 21, 1995,
six per cent per annum, in the absence of a stipulation of DENIAL OF SUBSTANTIAL JUSTICE OR ERRONEOUS trial date, the trial court issued an herein [P]etitioner Philrock
the rate. INTERPRETATION OF THE LAW. — As pointed out earlier, Order dismissing the case and requested to suspend the
4. ID.; ID.; MORAL DAMAGES; AWARD THEREOF, PROPER factual findings of quasi-judicial bodies that have acquired referring the same to the CIAC proceedings until the court clarified
IN CASE AT BAR. — Respondents were deprived of the expertise are generally accorded great respect and even because the Cid spouses and its ruling in the Order dated June
comfort and the safety of a house and were exposed to the finality, if they are supported by substantial evidence. The Philrock had filed an Agreement to 13, 1995. Philrock argued that said
agony of witnessing the wastage and the decay of the Court, however, has consistently held that despite statutory Arbitrate with the CIAC. Order was based on a mistaken
structure for more than seven years. In her Memorandum, provisions making the decisions of certain administrative "Thereafter, preliminary premise that 'the proceedings in
Respondent Nelia G. Cid describes her family's sufferings agencies "final," it still takes cognizance of petitions conferences were held among the the CIAC fell through because of the
arising from the unreasonable delay in the construction of showing want of jurisdiction, grave abuse of discretion, parties and their appointed refusal of [Petitioner] Philrock to
their residence, as follows: "The family lives separately for violation of due process, denial of substantial justice or arbitrators. At these conferences, include the issue of damages
lack of space to stay in. Mrs. Cid is staying in a small dingy erroneous interpretation of the law. Voluntary arbitrators, disagreements arose as to whether therein,' whereas the true reason
bodega, while her son occupies another makeshift room. by the nature of their functions, act in a quasi-judicial moral and exemplary damages and for the withdrawal of the case from
Their only daughter stayed with her aunt from 1992 until capacity, such that their decisions are within the scope of tort should be included as an issue the CIAC was due to Philrock's
she got married in 1996. . . . ." The Court also notes that judicial review. along with breach of contract, and opposition to the inclusion of its
during the pendency of the case, Respondent Vicente Cid DECISION whether the seven officers and seven officers and engineers, who
died without seeing the completion of their home. Under PANGANIBAN, J p: engineers of Philrock who are not did not give their consent to
the circumstances, the award of moral damages is proper. Courts encourage the use of alternative methods of dispute parties to the Agreement to arbitration, as party defendants. On
5. ID.; ID.; NOMINAL DAMAGES; WHEN RECOVERABLE. — resolution. When parties agree to settle their disputes Arbitrate should be included in the the other hand, private respondent
Nominal damages are recoverable only if no actual or arising from or connected with construction contracts, the arbitration proceedings. No Nelia Cid manifested that she was
substantial damages resulted from the breach, or no Construction Industry Arbitration Commission (CIAC) common ground could be reached willing to exclude the seven officers
damage was or can be shown. Since actual damages have acquires primary jurisdiction. It may resolve not only the by the parties, hence, on April 2, and engineers of Philrock as parties
been proven by private respondents for which they were merits of such controversies; when appropriate, it may also 1994, both the Cid spouses and to the case so as to facilitate or
amply compensated, they are no longer entitled to nominal award damages, interests, attorney's fees and expenses of Philrock requested that the case be expedite the proceedings. With
damages. litigation. remanded to the trial court. On such manifestation from the Cid
6. ID.; ID.; ATTORNEY'S FEES; AWARDED IN CASE AT BAR. The Case April 13, 1994, the CIAC issued an spouses, the Arbitral Tribunal
— Petitioner protests the grant of attorney's fees, arguing Order stating, thus: denied Philrock's request for the
suspension of the proceedings. 2. P65,000.00 representing Since the issues concerning the monetary awards were We disagree. Section 4 of Executive Order 1008 expressly
Philrock's counsel agreed to the retrofitting costs. questions of fact, the CA held that those awards were vests in the CIAC original and exclusive jurisdiction over
continuation of the proceedings but 3. P13,404.54 representing refund inappropriate in a petition for certiorari. Such questions disputes arising from or connected with construction
reserved the right to file a pleading of the value of delivered are final and not appealable according to Section 19 of EO contracts entered into by parties that have agreed to
elucidating the position he [had] but unworkable concrete 1008, which provides that "arbitral awards shall be . . . final submit their dispute to voluntary arbitration. 8
raised regarding the Court's Order mix that was laid to and [u]nappealable except on questions of law which shall It is undisputed that the parties submitted themselves to
dated June 13, 1995. The parties waste. be appealable to the Supreme Court . . . ." Nevertheless, the the jurisdiction of the Commission by virtue of their
then proceeded to finalize, approve 4. P50,000.00 representing moral CA reviewed the records and found that the awards were Agreement to Arbitrate dated November 24, 1993.
and sign the Terms of Reference. damages. supported by substantial evidence. In matters falling under Signatories to the Agreement were Atty. Ismael J. Andres
Philrock's counsel and 5. P50,000.00 representing nominal the field of expertise of quasi-judicial bodies, their findings and Perry Y. Uy (president of Philippine Rock Products,
representative, Atty. Pericles C. damages. of fact are accorded great respect when supported by Inc.) for petitioner, and Nelia G. Cid and Atty. Esteban A.
Consunji affixed his signature to 6. P50,000.00 representing substantial evidence. Bautista for respondent spouses. 9
said Terms of Reference which attorney's fees and Hence, this Petition. 6 Petitioner claims, on the other hand, that this Agreement
stated that 'the parties agree that expenses of litigation. Issues was withdrawn by respondents on April 8, 1994, because
their differences be settled by an 7. P144,756.80 representing The petitioner, in its Memorandum, raises the following of the exclusion of the seven engineers of petitioners in the
Arbitral Tribunal . . .' (p. 9, Terms of arbitration fees, minus issues: arbitration case. This withdrawal became the basis for the
Reference, p. 200, Rollo). such amount that may "A. April 13, 1994 CIAC Order dismissing the arbitration case
"On September 12, 1995, already have been paid Whether or not the CIAC could take jurisdiction over the and referring the dispute back to the RTC. Consequently,
[P]etitioner Philrock filed its to CIAC by respondent. case of Respondent Cid spouses against Petitioner Philrock the CIAC was divested of its jurisdiction to hear and decide
Motion to Dismiss, alleging therein "Let a copy of this Decision be after the case had been dismissed by both the RTC and the the case.
that the CIAC had lost jurisdiction furnished the Honorable Salvador CIAC. This contention is untenable. First, private respondents
to hear the arbitration case due to C. Ceguera, presiding judge, Branch "B. removed the obstacle to the continuation of the arbitration,
the parties' withdrawal of their 82 of Regional Trial Court of Whether or not Respondent Cid spouses have a cause of precisely by withdrawing their objection to the exclusion of
consent to arbitrate. The motion Quezon City who referred this case action against Petitioner Philrock. the seven engineers. Second, petitioner continued
was denied by . . . CIAC per Order to the Construction Industry "C. participating in the arbitration even after the CIAC Order
dated September 22, 1995. On Arbitration Commission for Whether or not the awarding of the amount of P23,276.75 had been issued. It even concluded and signed the Terms of
November 8, public respondent arbitration and proper disposition.' for materials ordered by Respondent Spouses Cid plus Reference 10 on August 21, 1995, in which the parties
ordered the parties to appear (pp. 44-45, Rollo, CA-G.R. SP No. interest thereon at the rate of 6% from 26 September 1995 stipulated the circumstances leading to the dispute;
before it on November 28, 1995 for 42443)"4 is proper. summarized their respective positions, issues, and claims;
the continuation of the arbitral Before the CA, petitioner filed a Petition for Review, "D. and identified the composition of the tribunal of
proceedings, and on February 7, docketed as CA-GR SP No. 42443, contesting the Whether or not the awarding of the amount of P65,000.00 arbitrators. The document clearly confirms both parties'
1996, public respondent directed jurisdiction of the CIAC and assailing the propriety of the as retrofitting costs is proper. intention and agreement to submit the dispute to voluntary
[P]etitioner Philrock to set two monetary awards in favor of respondent spouses. This "E. arbitration. In view of this fact, we fail to see how the CIAC
hearing dates in the month of Petition was consolidated by the CA with CA-GR SP No. Whether or not the awarding of the amount of P1,340,454 could have been divested of its jurisdiction.
February to present its evidence 39781, a Petition for Certiorari earlier elevated by for the value of the delivered but the allegedly unworkable Finally, as pointed out by the solicitor general, petitioner
and to pay all fees assessed by it, petitioner questioning the jurisdiction of the CIAC. concrete which was wasted is proper. maneuvered to avoid the RTC's final resolution of the
otherwise . . . Philrock would be Ruling of the Court of Appeals "F. dispute by arguing that the regular court also lost
deemed to have waived its right to The CA upheld the jurisdiction of the CIAC 5 over the Whether or not the awarding o[f] moral and nominal jurisdiction after the arbitral tribunal's April 13, 1994
present evidence. dispute between petitioner and private respondent. damages and attorney's fees and expenses of litigation in Order referring the case back to the RTC. In so doing,
"Hence, petitioner instituted the Under Executive Order No. 1008, the CIAC acquires favor of respondents is proper. petitioner conceded and estopped itself from further
petition for certiorari but while said jurisdiction when the parties agree to submit their dispute "G. questioning the jurisdiction of the CIAC. The Court will not
petition was pending, the CIAC to voluntary arbitration. Thus, in the present case, its Whether or not Petitioner Philrock should be held liable for countenance the effort of any party to subvert or defeat the
rendered its Decision dated jurisdiction continued despite its April 13, 1994 Order the payment of arbitration fees." 7 objective of voluntary arbitration for its own private
September 24, 1996, the dispositive referring the case back to the Regional Trial Court (RTC) of In sum, petitioner imputes reversible error to the CA (1) for motives. After submitting itself to arbitration proceedings
portion of which reads, as follows: Quezon City, Branch 82, the court of origin. The CIAC's upholding the jurisdiction of the CIAC after the latter had and actively participating therein, petitioner is estopped
'WHEREFORE, judgment is hereby action was based on the principle that once acquired, dismissed the case and referred it to the regular court, (2) from assailing the jurisdiction of the CIAC, merely because
rendered in favor of the Claimant, jurisdiction remains "until the full termination of the case for ruling that respondent spouses had a cause of action the latter rendered an adverse decision. 11
directing Respondent to pay unless a law provides the contrary." No such "full against petitioner, and (3) for sustaining the award of
Claimant as follows: termination" of the case was evident in the said Order; nor damages. Second Issue:
1. P23,276.25 representing the did the CIAC or private respondents intend to put an end to This Court's Ruling Cause of Action
excess cash payment for the case. DTSaIc The Petition has no merit. Petitioner contends that respondent spouses were
materials ordered by the Besides, according to Section 3 of the Rules of Procedure First Issue: negligent in not engaging the services of an engineer or
Claimants, (No. 7 of Governing Construction Arbitration, technical rules of law Jurisdiction architect who should oversee their construction, in
admitted facts) plus or procedure are not applicable in a single arbitration or Petitioner avers that the CIAC lost jurisdiction over the violation of Section 308 of the National Building Code. It
interests thereon at the arbitral tribunal. Thus, the "dismissal" could not have arbitration case after both parties had withdrawn their adds that even if the concrete it delivered was defective,
rate of 6% per annum divested the CIAC of jurisdiction to ascertain the facts of the consent to arbitrate. The June 13, 1995 RTC Order respondent spouses should bear the loss arising from their
from September 26, case, arrive at a judicious resolution of the dispute and remanding the case to the CIAC for arbitration was illegal operation. In short, it alleges that they had no cause
1995 to the date enforce its award or decision. allegedly an invalid mode of referring a case for arbitration. of action against it.
payment is made.
We disagree. Cause of action is defined as an act or Section 19, EO 1008, expressly provides that monetary Awards for Retrofitting Costs, Wasted Unworkable damages is DELETED for lack of legal basis. Costs against
omission by which a party violates the right of awards by the CIAC are final and unappealable. But Delivered Concrete, and Arbitration Fees petitioner.
another.12 A complaint is deemed to have stated a cause of We disagree with the solicitor general. As pointed out Petitioner maintains that the defects in the concrete SO ORDERED.
action provided it has indicated the following: (1) the legal earlier, factual findings of quasi-judicial bodies that have structure were due to respondent spouses' failure to secure ||| (Philrock, Inc. v. Construction Industry Arbitration
right of the plaintiff, (2) the correlative obligation of the acquired expertise are generally accorded great respect the services of an engineer or architect to supervise their Commission, G.R. Nos. 132848-49, [June 26, 2001], 412 PHIL
defendant, and (3) the act or the omission of the defendant and even finality, if they are supported by substantial project. Hence, it claims that the award for retrofitting cost 236-251)
in violation of the said legal right. 13 The cause of action evidence. 15 The Court, however, has consistently held that was without legal basis. It also denies liability for the
against petitioner was clearly established. Respondents despite statutory provisions making the decisions of wasted unworkable but delivered concrete, for which the FIRST DIVISION
were purchasers of ready-mix concrete from petitioner. certain administrative agencies "final," it still takes arbitral court awarded P13,404.54. Finally, it complains [G.R. No. 141897. September 24, 2001.]
The concrete delivered by the latter turned out to be of cognizance of petitions showing want of jurisdiction, grave against the award of litigation expenses, inasmuch as the METRO CONSTRUCTION,
substandard quality. As a result, respondents sustained abuse of discretion, violation of due process, denial of case should not have been instituted at all had respondents INC., petitioner, vs. CHATHAM
damages when the structures they built using such cement substantial justice or erroneous interpretation of the complied with the requirements of the National Building PROPERTIES, INC., respondent.
developed cracks and honeycombs. Consequently, the law. 16 Voluntary arbitrators, by the nature of their Code. Abello Concepcion Regala & Cruz for petitioner.
construction of their residence had to be stopped. functions, act in a quasi-judicial capacity, such that their We are unconvinced. Not only did respondents disprove Picazo Buyco Tan Fider & Santos for respondent.
Further, the CIAC Decision clearly spelled out respondents' decisions are within the scope of judicial review. 17 the contention of petitioner; they also showed that they SYNOPSIS
cause of action against petitioner, as follows: Petitioner protests the award to respondent spouses of sustained damages due to the defective concrete it had On April 21, 1994, respondent and
"Accordingly, this Tribunal finds P23,276.25 as excess payment with six percent interest delivered. These were items of actual damages they petitioner entered into a contract for the construction
that the mix was of the right beginning September 26, 1995. It alleges that this item was sustained due to its breach of contract. of the Chatham House in Makati City. In April 1998,
proportions at the time it left the neither raised as an issue by the parties during the Moral and Nominal Damages, Attorney's Fees and Costs petitioner sought to collect from respondent a sum of
plant. This, however, does not arbitration case, nor was its justification discussed in the Petitioner assails the award of moral damages, claiming no money for unpaid progress billings and other charges
necessarily mean that all of the CIAC Decision. It further contends that it could not be held malice or bad faith on its part. and instituted a request for adjudication of its claims
concrete mix delivered had liable for interest, because it had earlier tendered a check We disagree. Respondents were deprived of the comfort with the Construction Industry Arbitration
remained workable when it in the same amount to respondent spouses, who refused to and the safety of a house and were exposed to the agony of Commission (CIAC). Among others, the parties
reached the jobsite. It should be receive it. witnessing the wastage and the decay of the structure for submitted for CIAC's resolution the issue on whether
noted that there is no evidence to Petitioner's contentions are completely untenable. more than seven years. In her Memorandum, Respondent or not petitioner failed to complete and/or deliver the
show that all the transit mixers Respondent Nelia G. Cid had already raised the issue of Nelia G. Cid describes her family's sufferings arising from project within the approved completion date and, if
arrived at the site within the overpayment even prior to the formal arbitration. In the unreasonable delay in the construction of their so, whether petitioner was liable for liquidated
allowable time that would ensure paragraph 9 of the Terms of Reference, she stated: residence, as follows: "The family lives separately for lack damages. After due hearing, the CIAC rendered
the workability of the concrete mix "9. Claimants were assured that the of space to stay in. Mrs. Cid is staying in a small dingy judgment in favor of petitioner and directed the
delivered. problem and her demands had bodega, while her son occupies another makeshift room. respondent to pay petitioner P16,126,922.91. The
"On the other hand, there is been the subject of several staff Their only daughter stayed with her aunt from 1992 until CIAC held that the provision of the contract insofar as
sufficiently strong evidence to meetings and that Arteche was very she got married in 1996. . . ." 21 The Court also notes that the Overall Schedule is concerned cannot be
show that difficulties were much aware of it, a memorandum during the pendency of the case, Respondent Vicente Cid justifiably applied in the instant case in view of the
encountered in the pouring of having been submitted citing all the died without seeing the completion of their home.22 Under implied takeover of the project by respondent.
concrete mix from certain transit demands of [c]laimants. This the circumstances, the award of moral damages is proper. Accordingly, the CIAC found it unnecessary to rule on
mixers necessitating the [addition] assurance was made on July 31, Petitioner also contends that nominal damages should not whether MCI completed and/or delivered the project
of water and physically pushing the 1992 when Respondents Secillano, have been granted, because it did not breach its obligation within the approved completion schedule of the
mix, obviously because the same Martillano and Lomibao came to to respondent spouses. project since respondent failed to observe the
[was] no longer workable. This see Claimant Nelia Cid and offered Nominal damages are recoverable only if no actual or antecedent acts required for the termination of the
Tribunal holds that the to refund P23,276.25, [t]he substantial damages resulted from the breach, or no contract, as set forth in the Construction Agreement.
unworkability of said concrete mix difference between the billing by damage was or can be shown. 23 Since actual damages The CIAC, however, found petitioner liable for
has been firmly established. Philrock's Marketing Department in have been proven by private respondents for which they liquidated damages. Based on the CIAC's assessment,
"There is no dispute, however, to the amount of P125,586.25 and the were amply compensated, they are no longer entitled to petitioner's responsibility was based on its delay in
the fact that there are defects in amount charged by Philrock's nominal damages. the concreting milestone. Respondent instituted a
some areas of the poured Batching Plant Department in the Petitioner protests the grant of attorney's fees, arguing that petition for review with the Court of Appeals. The
structures. In this regard, this amount of only P102,586.25, which respondent spouses did not engage the services of legal Court of Appeals upheld the decision of the CIAC
Tribunal holds that the only logical [c]laimant refused to accept by counsel. Also, it contends that attorney's fees and litigation except on the matter of liquidated damages. In its
reason is that the unworkable saying, 'Saka na lang'." 18 expenses are awarded only if the opposing party acted in decision, the appellate court held that there was no
concrete was the one that was The same issue was discussed during the hearing before gross and evident bad faith in refusing to satisfy plaintiff's takeover by respondent and that petitioner exercised
poured in the defective the arbitration tribunal on December 19, 1995. 19 It was valid, just and demandable claim. complete control, authority and responsibility over
sections." 14 also mentioned in that tribunal's Decision dated September We disagree. The award is not only for attorney's fees, but the construction. The appellate court also found
Third Issue: 24, 1996. 20 also for expenses of litigation. Hence, it does not matter if petitioner liable for liquidated damages but made a
Monetary Awards The payment of interest is based on Article 2209 of the respondents represented themselves in court, because it is contrary conclusion and declared that petitioner was
Petitioner assails the monetary awards given by the Civil Code, which provides that if the obligation consists of obvious that they incurred expenses in pursuing their in delay based on the overall schedule of completion
arbitral tribunal for alleged lack of basis in fact and in law. the payment of a sum of money, and the debtor incurs action before the CIAC, as well as the regular and the of the project. Thus, it directed petitioner to pay
The solicitor general counters that the basis for petitioner's delay, the indemnity for damages shall be the payment of appellate courts. We find no reason to disturb this award. respondent the sum of P4,935,578.31. Petitioner
assigned errors with regard to the monetary awards is legal interest which is six per cent per annum, in the WHEREFORE, the Petition is DENIED and the assailed moved for reconsideration, but the appellate court
purely factual and beyond the review of this Court. Besides, absence of a stipulation of the rate. Decision AFFIRMED; however, the award of nominal denied the same for lack of merit. IHTASa
Hence, this instant petition for review. not included in the enumeration but should be deemed prerogative, inter alia, to promulgate rules concerning Joven B. Joaquin as Chairman, and Beda G. Fajardo and
Petitioner alleged that the Court of Appeals, in included. In addition, the CIAC is obviously excluded in the pleadings, practice and procedure in all courts, as well as to Loreto C. Aquino as members. .
reviewing and reversing the CIAC's factual findings, catalogue of cases not covered by the Circular and review rules of procedure of special courts and quasi- The preliminary conference before the CIAC started in June
contravened Section 19 of Executive Order (E.O.) No. mentioned in Section 2 thereof for the reason that at the judicial bodies, which, however, shall remain in force until 1998 and was concluded a month after with the signing of
1008, which provides that the arbitral award of the time the Circular took effect, E.O. No. 1008 allows appeals disapproved by the Supreme Court. This power is the Terms of Reference (TOR) of the Case. 1 The hearings
CIAC is final and unappealable, except on questions of to the Supreme Court on questions of law. constitutionally enshrined to enhance the independence of immediately started with the presentation of MCI's
law, which are appealable to the Supreme Court. 2. ID.; ID.; ID.; ARBITRAL AWARDS THEREOF MAY BE the Supreme Court. witnesses, namely: Ms. Ma. Suzette S. Nucum, Chief
The Court rejected petitioner's contention BROUGHT TO THE COURT OF APPEALS AND NOT TO THE 6. ID.; ID.; A LITIGANT HAS NO VESTED RIGHT IN A Accountant; Ms. Isabela Redito, Office Engineer; Mr. John
holding that under Circular No. 1-91, appeals from the SUPREME COURT. — Under Circular No. 1-91, appeals from PARTICULAR REMEDY. — The right to appeal from Romulo, Field Manager; and Dr. John Y. Lai, President.
arbitral awards of the CIAC may be brought to the the arbitral awards of the CIAC may be brought to the Court judgments, awards, or final orders of the CIAC is granted CHATHAM's witnesses were: Engr. Ruperto Kapunan III,
Court of Appeals, and not to the Supreme Court alone. of Appeals, and not to the Supreme Court alone. The in E.O. No. 1008. The procedure for the exercise or Managing Director of RK Development and Construction
The grounds for the appeal are likewise broadened to grounds for the appeal are likewise broadened to include application of this right was initially outlined in E.O. No. Co., Inc. (RKDCCI), which was the Construction Manager
include appeals on questions of facts and appeals appeals on questions of facts and appeals involving mixed 1008. While R.A. No. 7902 and circulars subsequently firm hired by CHATHAM to oversee the construction work
involving mixed questions of fact and law. The questions of fact and law. AacCIT issued by the Supreme Court and its amendments to the of the Chatham House; Engr. Alex Bautista, Area Manager of
jurisdiction of the Court of Appeals over appeals from 3. ID.; ID.; ID.; REVIEW OF AWARD THEREOF MAY 1997 Rules on Procedure effectively modified the manner RKDCCI; Mr. Avelino M. Mercado, CHATHAM's Project
final orders or decisions of the CIAC is further fortified INVOLVE EITHER QUESTIONS OF FACT, OF LAW, OR OF by which the right to appeal ought to be exercised, nothing Manager; and Engr. Jose T. Infante.
by the amendments to B.P. Blg. 129, as introduced FACT AND LAW. — Any remaining doubt on the procedural in these changes impaired vested rights. The new rules do In the meantime, the TOR was amended and finalized on 19
byR.A. No. 7902. mutation of the provisions on appeal in E.O. No. 1008, vis-à- not take away the right to appeal allowed in E.O. No. 1008. August 1998. 2
The Court affirmed the CIAC's findings and vis Circular No. 1-91 and R.A. No. 7902, was completely They only prescribe a new procedure to enforce the right. The facts, as admitted by the parties before the CIAC and
arbitral award. The Court found that the evidence removed with the issuance by the Supreme Court of No litigant has a vested right in a particular remedy, which incorporated in the original TOR, are as follows:
taken as a whole or in their totality revealed that Revised Administrative Circular No. 1-95 and the 1997 may be changed by substitution without impairing vested 1. On 21 April 1994, the parties
there was an implied takeover by respondent on the Rules of Civil Procedure. Both categorically include the rights; hence, he can have none in rules of procedure which formally entered into a . .
completion of the project. CIAC in the enumeration of quasi-judicial agencies relate to remedy." . contract for the
SYLLABUS comprehended therein. Section 3 of the former and Section 7. ID.; RULES OF PROCEDURE; CANNOT BE ALTERED, construction of the
1. ADMINISTRATIVE LAW; ADMINISTRATIVE AGENCY; 3, Rule 43 of the latter, explicitly expand the issues that CHANGED OR MODIFIED BY AGREEMENTS OR "Chatham House" . . . for
CONSTRUCTION INDUSTRY ARBITRATION COMMISSION may be raised in an appeal from quasi-judicial agencies or STIPULATIONS OF THE PARTIES. — The TOR, any contract the contract price of
(CIAC); COVERED BY CIRCULAR NO. 1-91; QUASI-JUDICIAL instrumentalities to the Court of Appeals within the period or agreement of the parties cannot amend, modify, limit, P50,000,000.00 inclusive
AGENCY, DEFINED. — Through Circular No. 1-91, the and in the manner therein provided. Indisputably, the restrict or circumscribe legal remedies or the jurisdiction of value-added tax,
Supreme Court intended to establish a uniform procedure review of the CIAC award may involve either questions of of courts. Rules of procedure are matters of public order subject to adjustments in
for the review of the final orders or decisions of the Court fact, of law, or of fact and law. and interest and unless the rules themselves so allow, they accordance with Article
of Tax Appeals and other quasi-judicial agencies provided 4. REMEDIAL LAW; COURTS; COURT OF APPEALS; cannot be altered, changed or regulated by agreements 9 of the contract.
that an appeal therefrom is then allowed under existing APPELLATE JURISDICTION OVER QUASI-JUDICIAL between or stipulations of the parties for their singular Construction of the
statutes to either the Court of Appeals or the Supreme AGENCIES. — The jurisdiction of the Court of Appeals over convenience. aCSEcA project, however,
Court. The Circular designated the Court of Appeals as the appeals from final orders or decisions of the CIAC is further commenced on 15 April
reviewing body to resolve questions of fact or of law or fortified by the amendments to B.P. Blg. 129, as introduced 8. ID.; EVIDENCE; FINDINGS OF FACTS OF THE COURT OF 1994 upon the release by
mixed questions of fact and law. It is clear that Circular No. by R.A. No. 7902. With the amendments, the Court of APPEALS ARE BINDING ON THE SUPREME COURT; CHATHAM of the
1-91 covers the CIAC. In the first place, it is a quasi-judicial Appeals is vested with appellate jurisdiction over all final EXCEPTION. — Settled is the general rule that the findings downpayment.
agency. A quasi-judicial agency or body has been defined as judgments, decisions, resolutions, orders or awards of of facts of the Court of Appeals are binding on us. There are 2. On 12 July 1994, a Supplemental
an organ of government other than a court and other than a Regional Trial Courts and quasi-judicial agencies, recognized exceptions to the rule, such as when the Contract was executed
legislature, which affects the rights of private parties instrumentalities, boards or commissions, except "those findings are contrary to those of the trial court, as in this by and between the
through either adjudication or rule-making. The very within the appellate jurisdiction of the Supreme Court in case. Hence, we have to take a closer reexamination of this parties whereby
definition of an administrative agency includes its being accordance with theConstitution, the Labor Code of the case. CHATHAM authorized
vested with quasi-judicial powers. The ever increasing Philippines under Presidential Decree No. 442, as amended, DECISION MCI to procure in behalf
variety of powers and functions given to administrative the provisions of this Act, and of subparagraph (1) of the DAVIDE, JR., C.J p: of the former materials,
agencies recognizes the need for the active intervention of third paragraph and subparagraph (4) of the fourth The core issue in this case is whether under existing law equipment, tools,
administrative agencies in matters calling for technical paragraph of Section 17 of the Judiciary Act of 1948." and rules the Court of Appeals can also review findings of fixtures, refurbishing,
knowledge and speed in countless controversies which While, again, the CIAC was not specifically named in said facts of the Construction Industry Arbitration Commission furniture, and
cannot possibly be handled by regular courts. The CIAC's provision, its inclusion therein is irrefutable. The CIAC was (CIAC). accessories necessary for
primary function is that of a quasi-judicial agency, which is not expressly covered in the exclusion. Further, it is a Respondent Chatham Properties, Inc. (CHATHAM) and the completion of the
to adjudicate claims and/or determine rights in accordance quasi-judicial agency or instrumentality. petitioner Metro Construction, Inc. (MCI) entered into a project.
with procedures set forth in E.O. No. 1008. In the second 5. ID.; APPEAL; PROCEDURE FOR THE EXERCISE OF THE contract for the construction of a multi-storey building 3. Under Section 1.04 of the
place, the language of Section 1 of Circular No. 1-91 RIGHT TO APPEAL MAY BE ALTERED AND MODIFIED known as the Chatham House located at the corner of Supplemental Contract,
emphasizes the obvious inclusion of the CIAC even if it is PROVIDED THAT VESTED RIGHTS ARE NOT IMPAIRED. — Herrera and Valero Streets, Salcedo Village, Makati City, the total amount of
not named in the enumeration of quasi-judicial agencies. There is no controversy on the principle that the right to Metro Manila. In April 1998, MCI sought to collect from procurement and
The introductory words "[a]mong these agencies are" appeal is statutory. However, the mode or manner by CHATHAM a sum of money for unpaid progress billings and transportation cost[s]
preceding the enumeration of specific quasi-judicial which this right may be exercised is a question of other charges and instituted a request for adjudication of and expenses which may
agencies only highlight the fact that the list is not exclusive procedure which may be altered and modified provided its claims with the CIAC. The case was docketed as CIAC be reimbursed by MCI
or conclusive. Further, the overture stresses and that vested rights are not impaired. The Supreme Court is Case No. 10-98. The arbitral tribunal was composed of from CHATHAM shall not
acknowledges the existence of other quasi-judicial agencies bestowed by the Constitution with the power and
exceed the amount of liable for the same? If so, attorney's fees and cost agreement for a lump sum contract
P75,000,000.00. how much? of litigation? If so, how amount of P125,000,000.00.
4. In the course of the construction, 5. Is MCI entitled to an additional much? 3 xxx xxx xxx
Change Orders No. 1, 4, reimbursement of In the resolution of these issues, the CIAC discovered There was also the admitted fact
8A, 11, 12 and 13 were P40,000.00 for bonuses significant data, which were not evident or explicit in the that the contract was negotiated
implemented, payment granted to workers as an documents and records but otherwise revealed or elicited and awarded in the absence of a
of which were incentive for the early during the hearings, which the CIAC deemed material and complete construction plan. In any
recommended by . . . completion of each floor? relevant to the complete adjudication of the case. In its case, in support of the total contract
RKDCCI and approved by 6. Were the deductions in the decision of 19 October 1998, 4 the CIAC made the following amount of P125 MILLION, is a Cost
one of CHATHAM's amount of P1,393,458.84 findings and conclusions: Breakdown (Exh. 17-L), where the
Project Managers, made by CHATHAM in It was established during the estimated quantities of owner
Romulo F. Sugay. MCI's progress billing hearing that the contract was furnished materials (OFM) are
5. On 15 September 1995, reasonable? awarded to MCI through indicated. It is however,
CHATHAM through its 7. Is MCI's claim of P1,646,502.00 negotiation as no bidding was understood that these quantities
Project Manager, Romulo for labor escalation conducted. . . . It was also revealed are estimates, based on (an)
F. Sugay, agreed to give valid? that two agreements were entered incomplete set of construction
P20,000 per floor for five 8. Is MCI entitled to payment of into, one is labeled Construction plans. It is likewise understood that
(5) floors, or a total of attendance fee? To what Contract for the total fixed amount except for the OFM, all the other
P100,000.00 as extent and how much? of P50,000,000.00 and the other a costs in the Cost Breakdown form
bonus/incentive pay to 9. Did MCI fail to complete and/or Supplemental Contract for an the basis for the lump-sum
MCI's construction deliver the project amount not to exceed agreement under the contract,
workers for the within the approved P75,000,000.00. The latter is subject to adjustment only if there
completion of each floor completion period? If so, supposed to cover the procurement are any significant changes in the
on schedule. CHATHAM is MCI liable for of materials for the project. The contract plans.
reimbursed MCI the liquidated damages and Construction Contract provides for RKDCCI in its letter to MCI dated 15
amount of P60,000.00 how much? monthly progress billings and Feb. 1995 (Exh. 4), informed MCI
corresponding to 10. Whether or not CHATHAM is payments based on actual that it was confirming the
bonuses advanced to its entitled to claim . . . accomplishments of the various agreement allegedly accepted by
workers by the latter for actual damages? If so, to phases of work. The Supplemental Dr. Lai that the Building Committee
the 14th, 16th, and 17th what extent and how Contract provides for will take over the management of
floors. much? reimbursement of [the] total the construction operations (of the
6. CHATHAM's payments to MCI 11. Whether or not CHATHAM is amount of procurement and project) albeit under certain
totaled P104,875,792.37, entitled to . . . additional transportation costs and expenses, conditions. Specifically, the take
representing payments counterclaims as follows: upon MCI's presentation of over was for an interim period and
for portions of MCI's 11.1. Core testing suppliers' invoices/receipts. will extend only after concreting of
progress billings and . . . expenses and However, from testimonies of up to basement level 5 or up to 30
additional charges. penalty for witnesses from both parties, it was May 1995 whichever is later. The
The parties then stipulated on the following issues, again, concrete revealed that the two distinct letter also stated that the Building
as set forth in the TOR: strength manner(s) of payment to MCI was Committee . . . will be responsible
1. Is MCI entitled to its claims for failure set aside. The earlier attempt by for management and direction
unpaid progress billings P3,630,587.38 CHATHAM to prove that MCI was including management of MCI
amounting to . remiss in submitting suppliers' engineers at the site, sequencing of
P21,062,339.76? 11.2. Expenses to rectify invoices and/or receipts in support work, additional labor, additional
2. Were the approved Change structural of its billings against the equipment and management of the
Orders 1, 4, 8a, 11, 12 steel works Supplemental Contract was in fact yard and staging area. The letter,
and 13 fully paid by for the later on abandoned when however, emphasized that the
CHATHAM? If not, is MCI foundation CHATHAM's witness Mercado intent is not a take over of the
entitled to its claim for P1,331,139.74 admitted that the matter of contract or take over of the entire
the unpaid balance? . adherence to the payment work and in fact, it was mentioned
3. Is CHATHAM liable for Change 11.3. Cost of additional provision of the Supplemental that MCI will still be responsible for
Orders 7a, 7b, 10, 14, 15, materials Contract is a 'non-issue.' This was earth anchoring and steel
16, 17, 19 and 20? (concrete & borne out by the fact that progress fabrication work.
4. Were the CHB works from the rebars) billings and payments under both CHATHAM claims that the interim
8th to the 31st floors supplied by contracts were made on the basis of take-over was necessitated by
part of the original CPI percentage of project completion. MCI's delay in the progress of its
contract or in the nature P5,761,457.91 Both documentary and testimonial work, due allegedly to MCI's lack of
of extra/additional . evidence prove that, effectively, the manpower and equipment. During
works? Is CHATHAM 12. Are the parties entitled to their construction contract and the hearings of this case, this claim
respective claims for supplemental contract is but one of MCI's lack of manpower,
necessary equipment, qualified dated 18 January 1997 (Exhibit E- (CHATHAM's) witnesses, representatives to take
engineers and inefficient 1) the first paragraph of which the decision not to such steps it considered
construction management was reads as follows: terminate the contract necessary to insure
testified to by both Mr. Mercado [of After evaluating all the was not due to the completion of the project
CHATHAM] and Engr. Kapunan of documents issued and admitted 'special within the period
RKDCCI. CHATHAM's witnesses, received from both relations' only, but also desired by CHATHAM, it
however, testified that in spite of Chatham Properties Inc. due to the greater deviated from some
these alleged deficiencies, MCI was and Metro Construction, problems the project generally accepted
nevertheless allowed to continue to Inc., the Building would be faced with by procedures in the
take full control of the operations. Committee of Chatham terminating the MCI construction industry in
When asked why termination of the Properties, Inc. contract and mobilizing dealing with MCI. One
contract was not resorted to if evaluated them. The another contractor. example was not giving
truly, MCI was not performing its Building Committee 2. That while there was no official MCI the opportunity to
contracted obligations, witnesses finds the total receivable termination of the rectify some of what
Mercado and Kapunan cited of Metro Construction is contract, the manner by CHATHAM considered as
"special relations" between the in the amount of EIGHT which CHATHAM had construction deficiencies
owner of MCI (Dr. John Lai) and the MILLION PESOS taken upon themselves and instead engaging the
president of CHATHAM (Mr. (P8,000,000.00) the procurement of services of other parties
Lamberto UnOcampo) as the only. DSETcC materials, the fielding of to undertake the
reason. When queried by the Tribunal if the labor, the control over corrective works and
On the other hand, Dr. Lai contends said amount already took into MCI's engineers, and the later on charging the
that, as explained in his letter to account the costs and expenses subcontracting of costs thereof to MCI.
CHATHAM dated 17 February (Chatham) claims to have incurred various phases of work In addition to the above
1995, (Exh. 4-A) MCI's work was on for the account of MCI, Mr. Mercado on its own, is considered conclusions resulting from what
schedule. During the hearings, Dr. answered in the affirmative. When by this Tribunal as this Tribunal considered peculiar of
Lai also insisted that beginning 15 queried further how the amount implied termination of circumstances surrounding the
February 1995, MCI was relieved of was arrived at, Mr. Mercado replied the contract. The idea of implementation of the project that
full control of the construction that it was the sum the Building allowing MCI to remain were revealed during the
operations, that it was relegated to Committee figured it was willing to on the project in spite of proceedings of this case, this
(be) a mere supplier of labor, pay MCI simply to close the issue. what CHATHAM claims Tribunal finds the necessity of
materials and equipment, and that Mr. Mercado even added that while (to be) MCI's establishing a cut-off date with
the alleged interim takeover MCI is not actually entitled to this shortcomings, and MCI's regard to the fiscal liability of one
actually extended through the amount, it was out of a "friendship" agreement to stay on the party towards the other.
completion of the project. Dr. Lai that CHATHAM offered this sum to project under conditions Mr. Avelino Mercado of CHATHAM
cited CHATHAM's purchases of MCI as final settlement under the set by CHATHAM, is presented a list of what he claims
materials, fielding labor force and contract. believed a matter of as its Payments to MCI (Exhibit 7)
sub-contracting works allegedly for It is with the above attendant mutual benefit to both summarized as follows:
the project without his knowledge circumstances that this Tribunal parties. a. Down payment (Paid in two
and consent as proof that will be guided in the resolution of 3. That CHATHAM's invoking its equal trances) P20,000,000.00
CHATHAM had taken full control of issues brought before it for rights under the b. Cash Advance for
the project. adjudication. From what this provisions of Article 27 Mobilization 800,000.00
Tribunal finds as peculiar of the construction c. Payments of Progress Billings up
To the above allegation of MCI that circumstances surrounding the contract is believed out to
CHATHAM went ahead and contracting and implementation of of place, as it failed to Billing No.
procured materials, hired labor and the CHATHAM House Project, it observe the required 19 71,081,183.44
entered into sub-contract arrived at the following antecedent acts before it d. Other Payments (Mar. 1994 to
agreements with the intention of fundamental conclusions: can exercise its Apr. 1996) 5,474,419.67
eventually charging the costs 1. That indeed 'special friendly prerogative under the e. Advances on MCI Payrolls (April
thereof to MCI, witness Mercado relations' were present said contract provision. 1996 to March
countered, that CHATHAM has the between the parties in 4. That there is no reason to 1997) 8,196,755.51
right to do this under the this case, although believe, either party was ————————
provisions of Article 27 of the decisions by either party in any way guilty of bad Total P104,752,358.42
contract, dealing with 'Recission, on any particular issue faith in acting as it did on The records of this case show that
Cancellation, Termination of were made not purely on certain relevant matters. the last progress payment to MCI
Contract.' the basis of such special However, this Tribunal is was in January 1996 representing
By way of responding to the relations. For example, of the belief that due payment of Progress Billing No. 19
various counterclaims of this Tribunal believes perhaps to the eagerness for the period ending 31 December
CHATHAM, MCI referred to a letter that, contrary to the on the part particularly 1995. The percentage of
of [the former] addressed to MCI allegation of of CHATHAM's completion claimed then by MCI
was 80.02%, the amount evaluated amounted to P24,005,732.66 Bautista of RKDCCI, when he said such projected delay was included
and eventually paid to MCI was the computed as follows: that it was an evaluation of the in Exh. 3-I as it should be.
equivalent of 77.15% work Total accomplishment as project's completion stage, not This Tribunal holds that Exh. 3-I
accomplishment. No further of 23 May 1996 at necessarily MCI's work showing a delay of 294 days in
progress payments were made 94.12% 117,655,000.00 accomplishment. This Tribunal concreting milestones should
thereafter, other than for advances Add approved change therefore stands firm on its rightfully be used in computing
to cover MCI payrolls from April orders 5,353,091.08 conclusion that MCI's liquidated damages. Accordingly,
1996 to March 1997 in the amount ——————— accomplishment is only up to the this Tribunal holds that MCI is
of P8,196,755.51 and for various Total P123,008,091.08 extent of 94.10%. 5 liable for liquidated damages in the
advances and payments of Less payments up to 23 With those findings, the CIAC disposed of the specific amount of P3,062,498.78 as
approved change orders in the May 1996 99,002,358.42 money claims by either granting or reducing them. On Issue follows:
amount of P5,474,419.67. Balance due MCI as of 23 No. 9, i.e., whether CHATHAM failed to complete and/or 1/4 x 1/3[(1/10 x
In the meantime, up to Billing No. May 1996 P24,005,732.66 deliver the project within the approved completion period P125,000,000.00) 1%] x 294 =
23 for the period ending 30 April Of the above balance of and, if so, whether CHATHAM is liable for liquidated P3,062,498.78. 6
1996, MCI billed CHATHAM a total P24,005,732.66 as of 23 May 1996, damages and how much, the CIAC ruled in this wise: The CIAC then decreed:
accomplishment of 95.29%. This the only payments made by This Tribunal holds that the Accordingly, as presented below, all
billing was however, evaluated by CHATHAM to MCI is the sum of provision of the contract insofar as the amounts due MCI are first listed
CHATHAM, and in its letter to MCI P5,750,000.00 from June 1996 the Overall Schedule is concerned and added up and the total
dated 27 May 1996 (Exhibit E) it onwards, allegedly to cover MCI cannot justifiably be applied in the payment is deducted therefrom.
confirmed that MCI's remaining payrolls. It is of course noted that instant case in view of the implied The admitted total payment figure
balance of work stands at CHATHAM's suspension of further take-over of the Chatham House as reflected in the Terms of
P7,374,201.15 as of 23 May 1996. payments to MCI was because it project by CHATHAM. Accordingly, Reference is the amount applied
This amount, percentage-wise, had been undertaking on its own, this Tribunal finds no necessity to instead of the total reflected in
equals roughly 5.88% of the the further procurement of resolve whether or not MCI CHATHAM's Summary of Payments
contract amount as testified to by materials and sub-contracting of complete[d] and/or deliver[ed] the which incidentally reflected a lesser
Engr. Jose Infante. (Exhibit 22-B). various phases of works on the project within the approved amount. From the 'Balance Due
Therefore, what was computed as project. completion period. In fact, Mr. MCI' the 'Amounts CPI is Held
MCI's work accomplishment as of In consideration of the above facts, Mercado testified that it was Entitled To' is deducted and the
23 May 1996 was 94.12% and it is this Tribunal's conclusion that CHATHAM who ultimately 'Net Amount Due MCI' is arrived at.
this evaluation which this Tribunal there was in fact an implied take completed the project, with A. AMOUNTS HELD MCI IS
believes MCI is entitled to as of said over of the project is further assistance of the construction ENTITLED TO:
date. confirmed. Furthermore, this managers. A.1. From the original contract:
Applying this percentage of Tribunal additionally concludes In any case, this Tribunal finds 94.12% of
completion of 94.12% to the that the cut-off date for purposes of merit in RKDCCI's claim that MCI P125,000,000.00
P125,000,000.00 contract amount delineating the financial obligations was in delay in the concreting P117,650,000.0
gives a total accomplishment of the parties between them should milestone and that [it] is liable for 0
equivalent to P117,650,000.00 as of be 23 May 1996, the date when liquidated damages therefor. This, A.2. Approved Change
23 May 1996. Add to this amount CHATHAM evaluated MCI's notwithstanding MCI's invoking Orders 5,353,091.08
the sum of P5,353,091.08 accomplishment at 94.10% but that Chatham is estopped from A.3. Pending Change
representing the total of approved nevertheless suspended all further claiming liquidated damages after it Orders 1,648,560.46
Change Orders as of 31 December progress payments to MCI. failed to deduct the alleged A.4. CHB Works 1,248,654.71
1995 gives a total MCI MCI presented further liquidated damages from MCI's A.5. Workers Bonus -0-
accomplishment of documentary evidence (Exhibit E- progress billings. This Tribunal A.6. Disputed
P123,003,091.08, as CHATHAM 6) the subject of which is a holds that such failure to deduct, Deductions 909,484.70
saw it. Of this amount, CHATHAM "PUNCHLISTING-CIVIL which CHATHAM claims it did in A.7. Labor
admitted having paid MCI the total STRUCTURAL." In this particular order not to hamper progress of Escalation 1,076,256.00
sum of P104,752,358.42 only document which bears the work in the project, is an option A.8. Attendance
(Exhibit 7) up to March 15, 1997, signatures of representatives of which [it] may or may not exercise. Fee 508,162.73
leaving a balance of both MCI and RKDCCI, MCI tried to ——————
P18,250,732.66. It should be noted prove that as of 30 August 1996 it However, this Tribunal finds that Total P128,394,209.68
that of the total payment of had actually attained 99.16% work CHATHAM's Exh. 11-A where the ———————
P104,752,358.42, the sum of accomplishment. While it may be liquidated damages on delays in Less: Total payments-
P5,750,000.00 was paid after May true that as of that date the project concreting milestone was applied is Item II-6 of TOR 104,875,792.37
1996 so that as of 23 May 1996, had reached 99.16% completion, not consistent with [its] own ———————
CHATHAM's total payment to MCI there is no incontrovertible Exhibit 3-I. This Tribunal notes that Balance Due MCI P23,518,417.31
was P99,002,358.42. evidence showing that MCI was in Exh. 11-A, CHATHAM included a B. AMOUNTS HELD CPI IS
Effectively, therefore, the amount responsible for such projected delay of 85 days for the ENTITLED TO:
due MCI as of 23 May 1996 accomplishment. This was in fact Helipad Concreting works, while no B.1. Liquidated
actually testified to by Engr. Alex Damages P3,062,498.78
B.2. Actual The Arbitral Tribunal committed with the schedule of completion, Ruiz of RKDCCI to Dr. Lai
Damages 335,994.50 gross and reversible error in since at that time the project was containing the reasons
B.3. Penalties 1,778,285. equating the percentage of MCI's very much delayed; thereafter, the for the takeover. HAEIac
44 work accomplishment with the MCI was back in full control of the Exhibit "8A" — Letter
B.4. Cash Payments in entire work in place, despite project. 12 dated 5 September 1995
Behalf of MCI 2,214,715.68 evidence to the contrary. 2. Testimony of Engr. Bautista that written by Dr. E.G.
—————— The Arbitral Tribunal gravely erred the takeover was only partial and Tabujara to Dr.
Total Amount Due in making 23 May 1996 as the cut- temporary and limited to the Lai/Romy Laron (Project
CPI P7,391,494.40 off date for purposes of delineating management portion on the Manager of MCI)
C. NET AMOUNT DUE MCI (A minus the financial obligations of the basement only and that MCI was requesting for an
B) P16,126,922.91 parties. always in control of the project. 13 engineer of MCI to
WHEREFORE, judgment is hereby The Arbitral Tribunal erred in 3. Testimony of Engr. Infante that accompany the inspector
rendered in favor of the Claimant denying CHATHAM its claim for MCI personnel were constantly of RKDCCI to witness
[MCI] directing Respondent actual damages pursuant to Article present in the project and the batching procedures. By
[CHATHAM] to pay Claimant [MCI] 27.8 of the Construction Contract. "intervention" (not takeover) by so doing, Dr. E.G.
the net sum of SIXTEEN MILLION The facts set forth in CHATHAM's CHATHAM was justified to ensure Tabujara acknowledged
ONE HUNDRED TWENTY SIX Answer with Compulsory completion of the project on that Dr. Lai was in
THOUSAND NINE HUNDRED Counterclaim as well as its time. 14 control of the project.
TWENTY TWO & 91/100 documentary and testamentary 4. Documentary exhibits evincing Exhibit "8" — Letter
(16,126,922.91) PESOS. evidence were not overturned or the nature and extent of MCI's work dated 4 September 1995
SO ORDERED. 7 controverted by any contrary during the takeover period which by Engr. Romulo R Sugay
Impugning the decision of the CIAC, CHATHAM instituted a evidence. 8 belied its claims that it was not in to Dr. Lai offering an
petition for review with the Court of Appeals, which was In its decision of 30 September 1999, 9 the Court of control of the project because of the incentive to the workers
docketed as CA-G.R. SP No. 49429. In its petition, Appeals simplified the assigned errors into one core issue, takeover thus: of MCI to exert (their)
CHATHAM alleged that: namely, the "propriety" of the CIAC's factual findings and Exhibit "4" — Letter best effort for topping off
The Arbitral Tribunal grossly erred conclusions. In upholding the decision of the CIAC, the dated 15 February 1995 by the end of December;
in failing to indicate specific Court of Appeals confirmed the jurisprudential principle of Engr. Kapunan of another clear indication
reference to the evidence presented that absent any showing of arbitrariness, the CIAC's RKDCCI to John Lai of that Dr. Lai was in
or to the transcript of stenographic findings as an administrative agency and quasi-judicial MCI stating that the control of the project.
notes in arriving at its questioned body should not only be accorded great respect but also takeover of directions or Exhibit "4-D" — Letter
Decision, in violation of the cardinal given the stamp of finality. However, the Court of Appeals management of the field dated 4 January 1996
rule under Section 1, Rule 36 of the found exception in the CIAC's disquisition of Issue No. 9 on operations is indicating that Mr. H.T.
Revised Rules of Civil Procedure the matter of liquidated damages. interim, i.e. while the Go offered Dr. Lai an
that a judgment must state clearly The Court of Appeals disagreed with the CIAC's finding that takeover is effective incentive of P1,800,000
and definitely the facts and the law there was an implied takeover by CHATHAM of the project immediately it will on the condition that
on which it is based. and that it was unnecessary for the CIAC to rule on whether extend only after MCI meets the new
The Tribunal's conclusions are MCI completed and/or delivered the project within the concreting Level B-1 or schedule/milestones.
grounded entirely on speculations, approved completion schedule of the project since approximately until 30 MCI's acceptance of the
surmises and conjectures. CHATHAM failed to observe the antecedent acts required May 1995 which ever is incentive offer likewise
The Arbitral Tribunal grossly erred for the termination of the contract, as set forth in the later. shows that MCI was in
in failing to consider the evidence Construction Agreement. Exhibit "4-A" — Letter control of the Project.
presented by CHATHAM and the The Court of Appeals ascertained that the evidence dated 17 February 1995 Exhibits "3", "3-I", "3-M",
testimony of its witnesses. overwhelmingly proved that there was no takeover by written by Dr. Lai of MCI "3-N", "3-W-1", 3-X", "3-
The Arbitral Tribunal gravely CHATHAM and that MCI exercised complete control, to Engr. Kapunan in Y", and "3-Z" — among
abused its discretion in considering authority and responsibility over the construction. In response to the latter's others containing
arbitrarily that there was an support of this conclusion, the appellate court pointed to 15 February 1995 letter reminders to MCI of its
implied takeover contrary to the the following evidentiary bases: 10 stating that "[A]lso we duties and shortcomings,
facts and evidence submitted. 1. Testimony of CHATHAM's Engr. were assured that we likewise attest to the fact
The Arbitral Tribunal committed Kapunan that the interim takeover will not be responsible that MCI was in control
grave error and gross for the works on the basement was for any errors or (of) and responsible for
misapprehension of facts in holding triggered by lack of manpower and accidents that may occur the Project, although
that CHATHAM is not entitled to delays as early as February 1995, during this INTERIM markedly deficient.
liquidated damages despite failure as evidenced by their period," indicating that Exhibits "5", "5-A", "5-B",
of MCI to meet the over-all assessment 11 and that the interim Dr. Lai was very much "5-C", "5-D", "5-E", "5-F",
schedule of completion. takeover was only with respect to aware of the interim "5-O", "C-7", and "E-9" —
The Arbitral Tribunal manifestly the direction or management of the period. evidencing that MCI
erred in holding that MCI is entitled field operations and was limited Exhibit "4-C" — Letter continued to manage
to its claim for unpaid progress only to works on the basement and dated 18 February 1995 other works on the
billings. intended to assist MCI to catch up written by Engr. Ben C. project even during the
time of the interim amounts due the CONTRACTOR, project within the period stipulated B. AMOUNTS [CHATHAM] IS
takeover of the basement the amount equivalent to 1/10 of in the Construction Contract and ENTITLED TO:
works, as seen in the 1% of the Contract Sum for every even despite an extension of 53 B.1. Liquidated
series of calendar day of delay, provided, days from the original schedule or Damages P24,125,000.00
communications however, that the maximum of the overall schedule of B.2. Actual
between CHATHAM or penalty should not exceed 25% of completion. [MCI] should therefore Damages 335,994.50
RKDCCI and MCI within the fee payable to the pay [CHATHAM] the amount of B.3. Penalties 1,778,285.
the period beginning CONTRACTOR as stipulated in the liquidated damages equivalent to 44
February 1995 to 30 May Bill of Quantities. Penalties from P24,125,000.00 for 193 days of B.4. Cash Payments in
1995. concreting milestones shall be delay in the overall schedule of Behalf of
5. Respondent's Request for deducted from the penalty of Over- completion counted from overall MCI 2,214,715.68
Adjudication, Annex G, Records, All Schedule. 15 completion date on July 22, 1996 ———————
Folder No. 6 — which incorporated The Court of Appeals disposed of the controversy in this up to the date of completion on Total Amount Due
Change Order No. 12, among wise: February 15, 1997, as stated in the CPI P28,453,995.62
others, dated 28 August 1995, As is extant from the records, the Certificate of Occupancy, computed C. NET AMOUNT DUE [CHATHAM]
recommended by the RKDCCI and completion date of the Project as follows, to wit: (B minus
accepted by Dr. Lai, and which under the Construction Contract or 1/10[1%(P125,000,000.00)] per A) P4,935,578.31
request for an extension of 25 days under the revised construction day x 193 days Correspondingly, Respondent [MCI] is hereby directed to
readily showed that even after 30 schedule was never met by reason = [1/10 (P1,250,000.00)] per day x pay the Petitioner [CHATHAM] the net sum of FOUR
May 1995, after the close of the of [MCI's] lack of manpower, 193 days MILLION NINE HUNDRED THIRTY-FIVE THOUSAND FIVE
supposed takeover period, MCI was necessary equipment, qualified = P125,000.00 per day x 193 days HUNDRED SEVENTY-EIGHT & 31/100 (P4,935,578.31)
still the contractor in complete engineers and inefficient = P24,125,000.00 PESOS. 16
control of the project for it would management of construction works IN VIEW OF ALL THE FOREGOING, MCI promptly filed on 25 October 1999 a motion for
not have otherwise accepted the on the Project. Thus, under the judgment is hereby rendered reconsideration. In its Resolution of 4 February 2000, the
said change order if it (were) no Contract (Exhibit '1'), [MCI] had partially granting [CHATHAM's] Court of Appeals denied MCI's motion for reconsideration
longer the Contractor of the project 780 days, or until 22 January 1996, claim for liquidated damages. The for lack of merit, as well as CHATHAM's Motion to Lift
due to the termination of the from starting date, or April 12, Tribunal's Decision dated 19 Garnishment and Levy Pending Appeal, filed on 13 October
Construction agreement as of said 1994, to finish the project. The October 1998 is hereby AFFIRMED 1999, for being premature. 17
date on account of the alleged completion date, however, was not with the modification on [MCI's] Thus, MCI filed the instant petition for review to challenge
takeover. followed and was revised as early liability for liquidated damages in the decision of the Court of Appeals. MCI alleges that the
6. Exhibits "3-J", "3-M", "3-Q", "3-R", as December 17, 1994, extending the amount of P24,125,000.00. Court of Appeals erred in reviewing and reversing the
"3-V", "3-W-1", "3-W-2", "5-F", "5- the milestone dates up to March 15, Thus, CIAC's factual findings, that there was an implied takeover
1", "6", "12-II", "12-JJ", "12-MM", 1996 (Exhibits '3-G' and '3-H'). As A. AMOUNTS [MCI] IS ENTITLED TO: by CHATHAM of the project, and that MCI was not in delay
and "12-NN" — tending to prove of December 25, 1995, the number A.1. From the original in the overall schedule. In so doing, the Court of Appeals
that RKDCCI monitored the work of days delayed was already 294 contract: 94.12% contravened Section 19 of Executive Order (E.O.) No.
from start to finish and had days. Thus, on February 22, 1996, of 1008, 18 which limits the review of an Arbitral Award to
zealously pointed out to MCI the the contract milestones were again P125,000,000.00 only questions of law, thus:
defects or improper execution of revised, inclusive of 53 days P117,650,000.0 SECTION 19. Finality of Awards —
the construction works, and gave extension, to May 23, 1996 0 The arbitral award shall be binding
MCI all the opportunity to rectify (Exhibits '3-I' and '3-O'). The May A.2. Approved Change upon the parties. It shall be final
the construction deficiencies and 23, 1996 turnover milestone nor Orders 5,353,091.08 and inappealable (sic) except on
complete the works of the project. the July 22, 1996 turnover of the A.3. Pending Change questions of law which shall be
The Court of Appeals concluded that the interim takeover whole project were neither met Orders 1,648,560.46 appealable to the Supreme Court.
was necessitated by CHATHAM's insistence to meet its own (Exhibits '3-P', '3-R', '3-S' and '3-T' A.4. CHB Works 1,248,654.71 MCI then asserts that as signatories to the contract, it and
turnover dates with the buyers of the project's units. Thus, but [CHATHAM] was again A.5. Workers Bonus -0- CHATHAM complied with this legal provision when they
CHATHAM was constrained to hire subcontractors with constrained to allow [MCI] to A.6. Disputed included as part of their TOR the stipulation that "[t]he
sufficient manpower and supervision and incur various continue working on the Project to Deductions 909,484.70 decision of the Arbitral Tribunal shall be final and non-
expenses to facilitate the completion of the project and/or complete the balance of the works A.7. Labor appealable except on questions of law." Accordingly, the
assist MCI in making up for its delay. (Exhibit 'M'). And all throughout Escalation 1,076,256.00 binding character of this provision upon the parties is
the construction of the Project, A.8. Attendance conclusive and final.
The Court of Appeals then considered it imperative to [CHATHAM] had to assist [MCI] Fee 508,162.73 MCI also contends that while it may be argued that recent
determine whether MCI failed to complete the project on along the way to expedite the —————— (1) issuances by the Supreme Court, specifically, Circular
time for which it may be held liable for liquidated damages execution and completion of the Total P128,394,209.68 No. 1-91, which eventually became Revised Administrative
based on the delays in the overall schedule of completion Project (Exhibits '3-K' and '3-V'). —————— Circular No. 1-95; (2) legislation, in particular, Republic Act
pursuant to Art. 13.5 of the Construction Agreement, to wit: From the foregoing disquisitions, it Less: Total payments- No. 7902, which amended Batas Pambansa Blg. 129; and
13.5. Over-All Schedule — For not is clear that [MCI] is liable for Item II-6 of (3) amendments to the Rules on Civil Procedure,
meeting the final completion date liquidated damages, as per Article TOR 104,875,792.37 modifying E.O. No. 1008 in the sense that "questions of
of the PROJECT, the OWNER will 13.5 of the Construction Contract, Balance Due facts, of law, or mixed questions of facts and law may be the
deduct from the Contract Sum or for its failure to complete the Respondent P23,518,417.31 subject of an appeal of the CIAC's decision to the Court of
Appeals," it is still E.O. No. 1008 which remains to be the same in the Court of Appeals, and whether appeals from final judgments or decisions of the Registration Authority, Social
fundamental and substantive law that endows parties to an CIAC awards are no longer confined to questions of law. Court of Appeals, the aggrieved Security Commission, Civil
arbitral controversy the right to appeal. Hence, the On 27 February 1991, this Court issued Circular No. 1-91, party may appeal by certiorari to Aeronautics Board, Bureau of
provisions on appeal of E.O. No. 1008 should be which prescribes the Rules Governing Appeals to the Court the Supreme Court as provided in Patents, Trademarks and
controlling, i.e., only questions of law should be of Appeals from Final Orders or Decisions of the Court of Rule 45 of the Rules of Court. Technology Transfer, National
entertained. Therefore, the only effect of these rules on E.O. Tax Appeals and Quasi-Judicial Agencies. Pertinent Subsequently, on 23 February 1995, R.A. No. 7902 was Electrification Administration,
No. 1008 is the transfer of the appeal forum from the portions thereof read as follows: enacted. It expanded the jurisdiction of the Court of Energy Regulatory Board, National
Supreme Court to the Court of Appeals. aEAIDH 1. Scope. — These rules shall apply Appeals and amended for that purpose Section 9 of B.P. Blg. Telecommunication Commission,
MCI further asserts that, even assuming that the CIAC's to appeals from final orders or 129, otherwise known as the Judiciary Reorganization Act Department of Agrarian Reform
findings of facts are reviewable on appeal, the Court of decisions of the Court of Tax of 1980. 20 under Republic Act No. 6657,
Appeals gravely abused its discretion when it accepted Appeals. They shall also apply to Section 9(3) thereof reads: Government Service Insurance
"hook, line and sinker" CHATHAM's contention that MCI appeals from final orders or SECTION 9. Jurisdiction. — The System, Employees Compensation
was in delay, and ignored competent, clear and substantial decisions of any quasi-judicial Court of Appeals shall exercise: Commission, Agricultural
evidence that prove the contrary, and that CHATHAM is not agency from which an appeal is xxx xxx xxx Inventions Board, Insurance
entitled to liquidated damages. now allowed by statute to the Court (3) Exclusive appellate jurisdiction Commission, Philippine Atomic
For its part, CHATHAM avers that the evolution on the rules of Appeals or the Supreme Court. over all final judgments, decisions, Energy Commission, Board of
governing appeals from judgments, decisions, resolutions, Among these agencies are the resolutions, orders or awards of Investments, and Construction
orders or awards of the CIAC convincingly discloses Securities and Exchange Regional Trial Courts and quasi- Industry Arbitration Commission.
that E.O. No. 1008 has already been superseded. With the Commission, Land Registration judicial agencies, instrumentalities, SECTION 2. Cases Not Covered. —
power of the Supreme Court to promulgate rules Authority, Social Security boards or commissions, including These rules shall not apply to
concerning the protection and enforcement of Commission, Civil Aeronautics the Securities and Exchange judgments or final orders issued
constitutional rights, pleadings, practice, and procedure in Board, Bureau of Patents, Commission, the Social Security under the Labor Code of the
all courts, its issuances and amendments to the Rules on Trademarks and Technology Commission, the Employees Philippines, Central Board of
Civil Procedure, not to mention R.A. No. 7902, as enacted by Transfer, National Electrification Compensation Commission and the Assessment Appeals, and by other
Congress, effectively modified E.O. No. 1008. Accordingly, Administration, Energy Regulatory Civil Service Commission, except quasi-judicial agencies from which
the judgments, awards, decisions, resolutions, orders or Board, National those falling within the appellate no appeal to the court is prescribed
awards of the CIAC are now appealable to the Court of Telecommunications Commission, jurisdiction of the Supreme Court in or allowed.
Appeals on questions of facts, mixed questions of facts and Secretary of Agrarian Reform and accordance with the Constitution, SECTION 3. Where to Appeal. — An
law, and questions of law, and no longer with the Supreme Special Agrarian Courts under R.A. the Labor Code of the Philippines appeal under these rules may be
Court on exclusively questions of law. Further, the TOR No. 6657, Government Service under Presidential Decree No. 442, taken to the Court of Appeals
cannot limit the expanded jurisdiction of the Court of Insurance System, Employees as amended, the provisions of this within the period and in the
Appeals based on the latest rules. Thus, the Court of Compensation Commission, Act, and of subparagraph (1) of the manner herein provided, whether
Appeals did not err in reviewing the factual findings of the Agricultural Inventions Board, third paragraph and subparagraph the appeal involves questions of
CIAC. Insurance Commission and (4) of the fourth paragraph of fact, of law, or mixed questions of
CHATHAM also contends that, even if the Court of Appeals Philippine Atomic Energy Section 17 of the Judiciary Act of fact and law.
can only review questions of law, said court did not err in Commission. 1948. Thereafter, this Court promulgated the 1997 Rules on Civil
rendering the questioned decision as the conclusions The Court of Appeals shall have the Procedure. Sections 1, 2 and 3 of Rule 43 thereof provides:
therein, drawn as they were from factual determinations, 2. Cases not Covered. — These rules power to try cases and conduct SECTION 1. Scope. — This Rule
can be considered questions of law. shall not apply to decisions and hearings, receive evidence and shall apply to appeals from
Finally, CHATHAM asseverates that the Court of Appeals interlocutory orders of the National perform any and all acts necessary judgments or final orders of the
did not commit grave abuse of discretion in reversing the Labor Relations Commission or the to resolve factual issues raised in Court of Tax Appeals and from
CIAC's ascertainment on the implied take-over and Secretary of Labor and cases falling within its original and awards, judgments, final orders or
liquidated damages. Employment under the Labor appellate jurisdiction, including the resolutions of or authorized by any
This Court shall now resolve the primary issue raised in Codeof the Philippines, the Central power to grant and conduct new quasi-judicial agency in the
this case. Board of Assessment Appeals, and trials or further proceedings. . . . exercise of its quasi-judicial
E.O. No. 1008 vests upon the CIAC original and exclusive other quasi-judicial agencies from Then this Court issued Administrative Circular No. 1- functions. Among these agencies
jurisdiction over disputes arising from, or connected with, which no appeal to the courts is 95, 21 which revised Circular No. 1-91. Relevant portions are the Civil Service Commission,
contracts entered into by parties involved in construction prescribed or allowed by statute. of the former reads as follows: Central Board of Assessment
in the Philippines, whether the dispute arises before or 3. Who may appeal and where to 1. Scope. — These rules shall apply Appeals, Securities and Exchange
after the completion of the contract, or after the appeal. — The appeal of a party to appeals from judgments or final Commission, Office of the
abandonment or breach thereof. 19 By express provision of affected by a final order, decision, orders of the Court of Tax Appeals President, Land Registration
Section 19 thereof, the arbitral award of the CIAC is final or judgment of the Court of Tax and from awards, judgments, final Authority, Social Security
and unappealable, except on questions of law, which are Appeals or a quasi-judicial agency orders or resolutions of any quasi- Commission, Civil Aeronautics
appealable to the Supreme Court. shall be taken to the Court of judicial agency from which an Board, Bureau of Patents,
The parties, however, disagree on whether the subsequent Appeals within the period and in appeal is authorized to be taken to Trademarks and Technology
Supreme Court issuances on appellate procedure and R.A. the manner herein provided, the Court of Appeals or the Transfer, National Electrification
No. 7902 removed from the Supreme Court its appellate whether the appeal involves Supreme Court. Among these Administration, Energy Regulatory
jurisdiction in Section 19 of E.O. No. 1008and vested the questions of fact or of law or mixed agencies are the Securities and Board, National
questions of fact and law. From Exchange Commission, Land Telecommunications Commission,
Department of Agrarian Reform included. In addition, the CIAC is obviously excluded in the word 'instrumentality,' with merely adopted Section 19 of E.O. No. 1008, which, as
under Republic Act No. 6657, catalogue of cases not covered by the Circular and respect to a state, contemplates an shown above, had been modified.
Government Service Insurance mentioned in Section 2 thereof for the reason that at the authority to which the state The TOR, any contract or agreement of the parties cannot
System, Employees Compensation time the Circular took effect, E.O. No. 1008 allows appeals delegates governmental power for amend, modify, limit, restrict or circumscribe legal
Commission, Agricultural to the Supreme Court on questions of law. the performance of a state function. remedies or the jurisdiction of courts. Rules of procedure
Inventions Board, Insurance In sum, under Circular No. 1-91, appeals from the arbitral are matters of public order and interest and unless the
Commission, Philippine Atomic awards of the CIAC may be brought to the Court of Appeals, Any remaining doubt on the procedural mutation of the rules themselves so allow, they cannot be altered, changed
Energy Commission, Board of and not to the Supreme Court alone. The grounds for the provisions on appeal in E.O. No. 1008, vis-à-visCircular No. or regulated by agreements between or stipulations of the
Investments, Construction Industry appeal are likewise broadened to include appeals on 1-91 and R.A. No. 7902, was completely removed with the parties for their singular convenience. 29
Arbitration Commission, and questions of facts and appeals involving mixed questions of issuance by the Supreme Court of Revised Administrative Having resolved the existence of the authority of the Court
voluntary arbitrators authorized by fact and law. Circular No. 1-95 and the 1997 Rules of Civil Procedure. of Appeals to review the decisions, awards, or final orders
law. The jurisdiction of the Court of Appeals over appeals from Both categorically include the CIAC in the enumeration of of the CIAC, the Court shall now determine whether the
SECTION 2. Cases Not Covered. — final orders or decisions of the CIAC is further fortified by quasi-judicial agencies comprehended therein. Section 3 of Court of Appeals erred in rendering the questioned
This Rule shall not apply to the amendments to B.P. Blg. 129, as introduced by R.A. No. the former and Section 3, Rule 43 of the latter, explicitly decision of 30 September 1999.
judgments or final orders issued 7902. With the amendments, the Court of Appeals is vested expand the issues that may be raised in an appeal from Settled is the general rule that the findings of facts of the
under the Labor Code of the with appellate jurisdiction over all final judgments, quasi-judicial agencies or instrumentalities to the Court of Court of Appeals are binding on us. There are recognized
Philippines. decisions, resolutions, orders or awards of Regional Trial Appeals within the period and in the manner therein exceptions to the rule, such as when the findings are
SECTION 3. Were to Appeal. — An Courts and quasi-judicial agencies, instrumentalities, provided. Indisputably, the review of the CIAC award may contrary to those of the trial court, 30 as in this case.
appeal under this Rule may be boards or commissions, except "those within the appellate involve either questions of fact, of law, or of fact and law. Hence, we have to take a closer reexamination of this case.
taken to the Court of Appeals jurisdiction of the Supreme Court in accordance with In view of all the foregoing, we reject MCI's submission that The CIAC is certain that the evidence overwhelmingly
within the period and in the the Constitution, theLabor Code of the Philippines Circular No. 1-91, B.P. Blg. 129, as amended byR.A. 7902, tended to prove that the manner by which CHATHAM took
manner herein provided, whether under Presidential Decree No. 442, as amended, the Revised Administrative Circular 1-95, and Rule 43 of the charge in the procurement of materials, fielding of labor,
the appeal involves question of fact, provisions of this Act, and of subparagraph (1) of the third 1997 Rules of Civil Procedure failed to efficaciously modify control of MCI engineers and the subcontracting of various
of law, or mixed questions of fact paragraph and subparagraph (4) of the fourth paragraph of the provision on appeals in E.O. No. 1008. We further phases of the work, constituted an implied takeover of the
and law. acHDTA Section 17 of the Judiciary Act of 1948." discard MCI's claim that these amendments have the effect project. The CIAC then concludes that the cut-off date for
Through Circular No. 1-91, the Supreme Court intended to While, again, the CIAC was not specifically named in said of merely changing the forum for appeal from the Supreme delineating the fiscal liabilities of the parties is 23 May
establish a uniform procedure for the review of the final provision, its inclusion therein is irrefutable. The CIAC was Court to the Court of Appeals. 1996 when CHATHAM evaluated MCI's work
orders or decisions of the Court of Tax Appeals and other not expressly covered in the exclusion. Further, it is a There is no controversy on the principle that the right to accomplishment at 94.12% and then suspended all further
quasi-judicial agencies provided that an appeal therefrom quasi-judicial agency or instrumentality. The decision appeal is statutory. However, the mode or manner by progress payments to MCI. For these reasons, the CIAC
is then allowed under existing statutes to either the Court in Luzon Development Bank v. Luzon Development Bank which this right may be exercised is a question of found it trifling to determine whether MCI was in delay
of Appeals or the Supreme Court. The Circular designated Employees 24 sheds light on the matter, thus: procedure which may be altered and modified provided based on the Overall Schedule. However, the CIAC
the Court of Appeals as the reviewing body to resolve Assuming arguendo that the that vested rights are not impaired. The Supreme Court is discovered that MCI was in delay for 294 days in the
questions of fact or of law or mixed questions of fact and voluntary arbitrator or the panel of bestowed by the Constitution with the power and concreting milestone and held the latter liable for
law. voluntary arbitrators may not prerogative, inter alia, to promulgate rules concerning liquidated damages in the amount of P3,062,498.78.
It is clear that Circular No. 1-91 covers the CIAC. In the first strictly be considered as a quasi- pleadings, practice and procedure in all courts, as well as to The Court of Appeals made a contrary conclusion and
place, it is a quasi-judicial agency. A quasi-judicial agency judicial agency, board or review rules of procedure of special courts and quasi- declared that MCI was in delay for 193 days based on the
or body has been defined as an organ of government other commission, still both he and the judicial bodies, which, however, shall remain in force until overall schedule of completion of the project and should
than a court and other than a legislature, which affects the panel are comprehended within the disapproved by the Supreme Court. 25 This power is incur liquidated damages in the amount of P24,125,000.00.
rights of private parties through either adjudication or concept of a 'quasi-judicial constitutionally enshrined to enhance the independence of It is undisputed that the CIAC and the Court of Appeals
rule-making. 22 The very definition of an administrative instrumentality.' It may even be the Supreme Court. 26 found MCI liable for liquidated damages but on different
agency includes its being vested with quasi-judicial powers. stated that it was to meet the very The right to appeal from judgments, awards, or final orders premises. Based on the CIAC's assessment, MCI's
The ever increasing variety of powers and functions given situation presented by the quasi- of the CIAC is granted in E.O. No. 1008. The procedure for responsibility was anchored on its delay in theconcreting
to administrative agencies recognizes the need for the judicial functions of the voluntary the exercise or application of this right was initially milestone, while the Court of Appeal's evaluation
active intervention of administrative agencies in matters arbitrators here, as well as the outlined in E.O. No. 1008. While R.A. No. 7902 and circulars concentrated on MCI's delay in completing the project
calling for technical knowledge and speed in countless subsequent arbitrator/arbitral subsequently issued by the Supreme Court and its based on the overall schedule of work. The variance in the
controversies which cannot possibly be handled by regular tribunal operating under the amendments to the 1997 Rules on Procedure effectively evaluation spells a staggering difference in the party who
courts. 23 The CIAC's primary function is that of a quasi- Construction Industry Arbitration modified the manner by which the right to appeal ought to should ultimately be held liable and the net amount
judicial agency, which is to adjudicate claims and/or Commission, that the broader term be exercised, nothing in these changes impaired vested involved.
determine rights in accordance with procedures set forth 'instrumentalities' was purposely rights. The new rules do not take away the right to appeal A study of the final computation of the net amount due in
in E.O. No. 1008. included in [Section 9 of B.P. Blg. allowed in E.O. No. 1008. They only prescribe a new both the final disquisitions of the CIAC and the Court of
In the second place, the language of Section 1 of Circular 129 as amended by R.A. No. 7902]. procedure to enforce the right. 27 No litigant has a vested Appeals shows that all the other figures therein are
No. 1-91 emphasizes the obvious inclusion of the CIAC even An 'instrumentality' is anything right in a particular remedy, which may be changed by constant, save for the amount of liquidated damages for
if it is not named in the enumeration of quasi-judicial used as a means or agency. Thus, substitution without impairing vested rights; hence, he can which MCI should be accountable. If this Court concurs
agencies. The introductory words "[a]mong these agencies the terms governmental 'agency' or have none in rules of procedure which relate to with the CIAC's conclusions, MCI's responsibility for
are" preceding the enumeration of specific quasi-judicial 'instrumentality' are synonymous remedy." 28 liquidated damages is, as already stated, P3,062,498.78.
agencies only highlight the fact that the list is not exclusive in the sense that either of them is a The foregoing discussion renders academic MCI's assertion Setting this off against CHATHAM's overall fiscal
or conclusive. Further, the overture stresses and means by which a government acts, on the binding effect of its stipulation with CHATHAM in accountability would bring the latter's total liability to MCI
acknowledges the existence of other quasi-judicial agencies or by which a certain government the TOR that the decision of the CIAC shall be final and non- to P16,126,922.91. If the Court of Appeals is correct, MCI
not included in the enumeration but should be deemed act or function is performed. The appealable except on questions of law. The agreement would be held liable for a much higher P24,125,000
liquidated damages. Setting this off against CHATHAM's SYSTEMS (WINS) JAPAN CO., WINS WEEKLY as shown by a series of written exchanges trial for the Petition for
monetary responsibilities, MCI would still have to pay LTD., respondent. between the parties. He also ruled that, had there really Confirmation of Arbitral Award.
CHATHAM P4,935,578.31. DECISION been a material breach of the agreement, petitioner should SO ORDERED.
After painstakingly combing through the voluminous CORONA, J p: have terminated the same instead of sending a mere notice Petitioner moved for reconsideration. The same was
records, we affirm the findings of the CIAC. The evidence This petition for review on certiorari under Rule 45 of the to terminate said agreement. The arbitrator found that denied. Hence, this petition.
taken as a whole or in their totality reveals that there was Rules of Court seeks to set aside the February 16, 2005 petitioner threatened to terminate the agreement due to its Petitioner contends that the CA, in effect, ruled that: (a) it
an implied takeover by CHATHAM on the completion of the decision 1 and August 16, 2005 resolution 2 of the Court of desire to compel respondent to re-negotiate the terms should have first filed a petition to vacate the award in the
project. The evidence that appears to accentuate the Court Appeals (CA) in CA-G.R. SP No. 81940. thereof for higher fees. He further stated that even if RTC and only in case of denial could it elevate the matter to
of Appeals' decision ironically bolstered the CIAC's On September 27, 1999, petitioner ABS-CBN Broadcasting respondent committed a breach of the agreement, the same the CA via a petition for review under Rule 43 and (b) the
conclusion. The testimonies of Engr. Kapunan, Engr. Corporation entered into a licensing agreement with was seasonably cured. He then allowed respondent to assailed decision implied that an aggrieved party to an
Bautista, Dr. Lai, and the letter of Engr. respondent World Interactive Network Systems (WINS) recover temperate damages, attorney's fees and one-half of arbitral award does not have the option of directly filing a
Ruiz, 31 acknowledging the "temporary takeover" by Japan Co., Ltd., a foreign corporation licensed under the the amount it paid as arbitrator's fee. SHADcT petition for review under Rule 43 or a petition for
CHATHAM of the project, underscore the palpable fact that laws of Japan. Under the agreement, respondent was Petitioner filed in the CA a petition for review under Rule certiorari under Rule 65 with the CA even if the issues
there was indeed a takeover. We confer particular credit to granted the exclusive license to distribute and sublicense 43 of the Rules of Court or, in the alternative, a petition for raised pertain to errors of fact and law or grave abuse of
Dr. Lai's testimony that as of 15 February 1995, MCI was the distribution of the television service known as "The certiorari under Rule 65 of the same Rules, with application discretion, as the case may be, and not dependent upon
relieved of full control of the construction operations, that Filipino Channel" (TFC) in Japan. By virtue thereof, for temporary restraining order and writ of preliminary such grounds as enumerated under Section 24 (petition to
it was relegated to a mere supplier of labor, materials and petitioner undertook to transmit the TFC programming injunction. It was docketed as CA-G.R. SP No. 81940. It vacate an arbitral award) of RA 876 (the Arbitration Law).
equipment, and that the alleged interim takeover actually signals to respondent which the latter received through its alleged serious errors of fact and law and/or grave abuse of Petitioner alleged serious error on the part of the
extended through the completion of the project. Even decoders and distributed to its subscribers. aTHCSE discretion amounting to lack or excess of jurisdiction on the CA. HTAIcD
CHATHAM admits the takeover but sugarcoated the same A dispute arose between the parties when petitioner part of the arbitrator. The issue before us is whether or not an aggrieved party in
with words like "interim" and "charging the costs to MCI." accused respondent of inserting nine episodes of WINS Respondent, on the other hand, filed a petition for a voluntary arbitration dispute may avail of, directly in the
With these glaring admissions, we can even consider that WEEKLY, a weekly 35-minute community news program confirmation of arbitral award before the Regional Trial CA, a petition for review under Rule 43 or a petition for
the takeover was not implied but blatant. for Filipinos in Japan, into the TFC programming from Court (RTC) of Quezon City, Branch 93, docketed as Civil certiorari under Rule 65 of the Rules of Court, instead of
Exhibits "4", "4-A", "4-C", "8A", "8", "4-D", "3", "3-I", "3-M", March to May 2002. 3 Petitioner claimed that these were Case No. Q-04-51822. filing a petition to vacate the award in the RTC when the
"3-N", "3-W-1", "3-X", "3-Y", "3-Z", "5", "5-A", "5-B", "5-C", "unauthorized insertions" constituting a material breach of Consequently, petitioner filed a supplemental petition in grounds invoked to overturn the arbitrator's decision are
"5-D", "5-E", "5-F", "5-O", "C-7", "E-9", etc., 32 relied upon their agreement. Consequently, on May 9, the CA seeking to enjoin the RTC of Quezon City from other than those for a petition to vacate an arbitral award
by the Court of Appeals when considered by themselves 2002, 4 petitioner notified respondent of its intention to further proceeding with the hearing of respondent's enumerated under RA 876.
and singly, seemingly and initially evince MCI's control terminate the agreement effective June 10, 2002. petition for confirmation of arbitral award. After the RA 876 itself mandates that it is the Court of First Instance,
over the project. However, they eventually lose evidentiary Thereafter, respondent filed an arbitration suit pursuant to petition was admitted by the appellate court, the RTC of now the RTC, which has jurisdiction over questions relating
puissance to support the Court of Appeals' conclusion when the arbitration clause of its agreement with petitioner. It Quezon City issued an order holding in abeyance any to arbitration, 9 such as a petition to vacate an arbitral
reckoned against the totality of the evidence that contended that the airing of WINS WEEKLY was made with further action on respondent's petition as the assailed award.
CHATHAM took charge of the completion of the project, petitioner's prior approval. It also alleged that petitioner decision of the arbitrator had already become the subject of Section 24 of RA 876 provides for the specific grounds for a
particularly, the fact that CHATHAM suspended all progress only threatened to terminate their agreement because it an appeal in the CA. Respondent filed a motion for petition to vacate an award made by an arbitrator:
billing payments to MCI. The continued presence and wanted to renegotiate the terms thereof to allow it to reconsideration but no resolution has been issued by the Sec. 24. Grounds for vacating award.
participation of MCI in the project was, as found by the demand higher fees. Respondent also prayed for damages lower court to date. 8 — In any one of the following
CIAC, a matter of mutual benefit to and convenience of the for petitioner's alleged grant of an exclusive distribution On February 16, 2005, the CA rendered the assailed cases, the court must make an
parties. license to another entity, NHK (Japan Broadcasting decision dismissing ABS-CBN's petition for lack of order vacating the award upon
WHEREFORE, IN VIEW OF ALL THE FOREGOING, the Corporation). 5 jurisdiction. It stated that as the TOR itself provided that the petition of any party to the
assailed 30 September 1999 decision of the Court of The parties appointed Professor Alfredo F. Tadiar to act as the arbitrator's decision shall be final and unappealable controversy when such party
Appeals in CA-G.R. SP No. 49429 is hereby PARTIALLY sole arbitrator. They stipulated on the following issues in and that no motion for reconsideration shall be filed, then proves affirmatively that in the
MODIFIED by setting aside the order directing Metro their terms of reference (TOR): 6 HIETAc the petition for review must fail. It ruled that it is the RTC arbitration proceedings:
Construction, Inc. to pay Chatham Properties, Inc. the 1. Was the broadcast of WINS which has jurisdiction over questions relating to (a) The award was procured by
amount of P4,935,578.31. The arbitral award of the WEEKLY by the claimant duly arbitration. It held that the only instance it can exercise corruption, fraud, or other undue
Construction Industry Arbitration Commission in CIAC authorized by the respondent jurisdiction over an arbitral award is an appeal from the means; or
Case 10-98, promulgated on 19 October 1998, directing [herein petitioner]? trial court's decision confirming, vacating or modifying the (b) That there was evident
Chatham Properties, Inc. to pay Metro Construction, Inc. 2. Did such broadcast constitute a arbitral award. It further stated that a petition for certiorari partiality or corruption in the
the sum of SIXTEEN MILLION ONE HUNDRED TWENTY-SIX material breach of the agreement under Rule 65 of the Rules of Court is proper in arbitration arbitrators or any of them;
THOUSAND NINE HUNDRED TWENTY-TWO & 91/100 that is a ground for termination of cases only if the courts refuse or neglect to inquire into the or THEDcS
(P16,126,922.91) PESOS, is accordingly REINSTATED. the agreement in accordance with facts of an arbitrator's award. The dispositive portion of the (c) That the arbitrators were guilty
No pronouncement as to costs. Section 13 (a) thereof? CA decision read: TSIEAD of misconduct in refusing to
SO ORDERED. 3. If so, was the breach seasonably WHEREFORE, the instant petition is postpone the hearing upon
||| (Metro Construction, Inc. v. Chatham Properties, Inc., G.R. cured under the same contractual hereby DISMISSED for lack of sufficient cause shown, or in
No. 141897, [September 24, 2001], 418 PHIL 176-208) provision of Section 13 (a)? jurisdiction. The application for a refusing to hear evidence pertinent
4. Which party is entitled to the writ of injunction and temporary and material to the controversy;
FIRST DIVISION payment of damages they claim and restraining order is that one or more of the arbitrators
[G.R. No. 169332. February 11, 2008.] to the other reliefs prayed for? likewise DENIED. The Regional was disqualified to act as such
ABS-CBN BROADCASTING xxx xxx xxx Trial Court of Quezon City, Branch under section nine hereof, and
CORPORATION, petitioner, vs. The arbitrator found in favor of respondent. 7 He held that 93 is directed to proceed with the willfully refrained from disclosing
WORLD INTERACTIVE NETWORK petitioner gave its approval to respondent for the airing of such disqualifications or of any
other misbehavior by which the which was not favorable to herein final orders of the Court of Tax there has been a grave abuse of
rights of any party have been petitioners and because it Appeals and from awards, discretion amounting to lack or
materially prejudiced; or considered that herein private judgments, final orders or excess of jurisdiction on the part
(d) That the arbitrators exceeded respondents, by submitting the resolutions of or authorized by any of any branch or instrumentality
their powers, or so imperfectly controversy to arbitration, was quasi-judicial agency in the of the Government. (Emphasis
executed them, that a mutual, final seeking to renege on its obligations exercise of its quasi-judicial supplied) DHTECc
and definite award upon the under the contract. functions. Among these agencies As may be gleaned from the above stated provision, it is
subject matter submitted to them xxx xxx xxx are the Civil Service Commission, well within the power and jurisdiction of the Court to
was not made. It is clear then that the Court of Central Board of Assessment inquire whether any instrumentality of the Government,
Based on the foregoing provisions, the law itself clearly Appeals reversed the trial Appeals, Securities and Exchange such as a voluntary arbitrator, has gravely abused its
provides that the RTC must issue an order vacating an court not because the latter Commission, Office of the discretion in the exercise of its functions and prerogatives.
arbitral award only "in any one of the . . . cases" reviewed the arbitration award President, Land Registration Any agreement stipulating that "the decision of the
enumerated therein. Under the legal maxim in statutory involved herein, but because the Authority, Social Security arbitrator shall be final and unappealable" and "that no
construction expressio unius est exclusio alterius, the explicit respondent appellate court Commission, Civil Aeronautics further judicial recourse if either party disagrees with the
mention of one thing in a statute means the elimination of found that the trial court had no Board, Bureau of Patents, whole or any part of the arbitrator's award may be availed
others not specifically mentioned. As RA 876 did not legal basis for vacating the Trademarks and Technology of" cannot be held to preclude in proper cases the power of
expressly provide for errors of fact and/or law and grave award. (Emphasis supplied). Transfer, National Electrification judicial review which is inherent in courts. 16 We will not
abuse of discretion (proper grounds for a petition for In cases not falling under any of the aforementioned Administration, Energy Regulatory hesitate to review a voluntary arbitrator's award where
review under Rule 43 and a petition for certiorari under grounds to vacate an award, the Court has already made Board, National there is a showing of grave abuse of authority or discretion
Rule 65, respectively) as grounds for maintaining a petition several pronouncements that a petition for review under Telecommunications Commission, and such is properly raised in a petition
to vacate an arbitral award in the RTC, it necessarily Rule 43 or a petition for certiorari under Rule 65 may be Department of Agrarian Reform for certiorari 17 and there is no appeal, nor any plain,
follows that a party may not avail of the latter remedy on availed of in the CA. Which one would depend on the underRepublic Act Number 6657, speedy remedy in the course of law. 18
the grounds of errors of fact and/or law or grave abuse of grounds relied upon by petitioner. Government Service Insurance Significantly, Insular Savings Bank v. Far East Bank and
discretion to overturn an arbitral award. In Luzon Development Bank v. Association of Luzon System, Employees Compensation Trust Company 19 definitively outlined several judicial
Adamson v. Court of Appeals 10 gave ample warning that a Development Bank Employees, 11 the Court held that a Commission, Agricultural remedies an aggrieved party to an arbitral award may
petition to vacate filed in the RTC which is not based on the voluntary arbitrator is properly classified as a "quasi- Inventions Board, Insurance undertake:
grounds enumerated in Section 24 of RA 876 should be judicial instrumentality" and is, thus, within the ambit of Commission, Philippine Atomic (1) a petition in the proper RTC to
dismissed. In that case, the trial court vacated the arbitral Section 9 (3) of the Judiciary Reorganization Act, as Energy Commission, Board of issue an order to vacate the award
award seemingly based on grounds included in Section 24 amended. Under this section, the Court of Appeals shall Investments, Construction Industry on the grounds provided for in
of RA 876 but a closer reading thereof revealed otherwise. exercise: Arbitration Commission, Section 24 of RA 876; ASCTac
On appeal, the CA reversed the decision of the trial court xxx xxx xxx and voluntary arbitrators (2) a petition for review in the CA
and affirmed the arbitral award. In affirming the CA, we (3) Exclusive appellate jurisdiction authorized by law. (Emphasis under Rule 43 of the Rules of Court
held: over all final judgments, decisions, supplied) on questions of fact, of law, or
The Court of Appeals, in reversing resolutions, orders or awards of This rule was cited in Sevilla Trading Company v. mixed questions of fact and law;
the trial court's decision held that Regional Trial Courts and quasi- Semana, 13 Manila Midtown Hotel v. and
the nullification of the decision of judicial Borromeo, 14 andNippon Paint Employees Union-Olalia v. (3) a petition for certiorari under
the Arbitration Committee was not agencies, instrumentalities, board Court of Appeals. 15 These cases held that the proper Rule 65 of the Rules of Court should
based on the grounds provided s or commissions, including the remedy from the adverse decision of a voluntary arbitrator, the arbitrator have acted without
by the Arbitration Law and that . . . Securities and Exchange if errors of fact and/or law are raised, is a petition for or in excess of his jurisdiction or
private respondents (petitioners Commission, the Employees' review under Rule 43 of the Rules of Court. Thus, with grave abuse of discretion
herein) have failed to substantiate Compensation Commission and the petitioner's contention that it may avail of a petition for amounting to lack or excess of
with any evidence their claim of Civil Service Commission, except review under Rule 43 under the circumstances of this case jurisdiction.
partiality. Significantly, even as those falling within the appellate is correct. Nevertheless, although petitioner's position on the judicial
respondent judge ruled against the jurisdiction of the Supreme Court in As to petitioner's arguments that a petition remedies available to it was correct, we sustain the
arbitrator's award, he could not accordance with the Constitution, for certiorari under Rule 65 may also be resorted to, we dismissal of its petition by the CA. The remedy petitioner
find fault with their impartiality the Labor Code of the Philippines hold the same to be in accordance with availed of, entitled "alternative petition for review under
and integrity. Evidently, the under Presidential Decree No. 442, the Constitution and jurisprudence. Rule 43 or petition for certiorari under Rule 65," was
nullification of the award as amended, the provisions of this Section 1 of Article VIII of the 1987 Constitution provides wrong. CcTHaD
rendered at the case at bar was Act and of subparagraph (1) of the that: Time and again, we have ruled that the remedies of appeal
not made on the basis of any of third paragraph and subparagraph SEC. 1. The judicial power shall be and certiorari are mutually exclusive and not alternative or
the grounds provided by (4) of the fourth paragraph of vested in one Supreme Court and in successive. 20
law. AEIHCS Section 17 of the Judiciary Act of such lower courts as may be Proper issues that may be raised in a petition for review
1948. (Emphasis supplied) established by law. under Rule 43 pertain to errors of fact, law or mixed
xxx xxx xxx As such, decisions handed down by voluntary arbitrators Judicial power includes the duty questions of fact and law. 21 While a petition for certiorari
It is clear, therefore, that the fall within the exclusive appellate jurisdiction of the CA. of the courts of justice to settle under Rule 65 should only limit itself to errors of
award was vacated not because This decision was taken into consideration in approving actual controversies involving jurisdiction, that is, grave abuse of discretion amounting to
of evident partiality of the Section 1 of Rule 43 of the Rules of Court. 12Thus: cICHTD rights which are legally a lack or excess of jurisdiction. 22 Moreover, it cannot be
arbitrators but because the latter SEC. 1. Scope. — This Rule shall demandable and enforceable, availed of where appeal is the proper remedy or as a
interpreted the contract in a way apply to appeals from judgments or and to determine whether or not substitute for a lapsed appeal. 23
In the case at bar, the questions raised by petitioner in TANTAMOUNT TO LACK Before the Court is a special civil action not belong to any association the 1% share,
its alternative petition before the CA were the following: OR EXCESS OF for certiorari assailing the Decision 1 dated December 7, instead of reverting said share to the centrals. Petitioners
A. THE SOLE ARBITRATOR JURISDICTION. 2001 and the Resolution dated October 30, contended that respondents unduly accorded the
COMMITTED SERIOUS A careful reading of the assigned errors reveals that the 2002 of the Court of Appeals (CA) in CA-G.R. SP No. 56166 independent Planters more benefits and thus prayed that
ERROR AND/OR real issues calling for the CA's resolution were less the which set aside the Joint Orders 2 dated August 26, 1999 an order be issued directing the parties to commence with
GRAVELY ABUSED HIS alleged grave abuse of discretion exercised by the and October 29, 1999 issued by the Regional arbitration in accordance with the terms of the milling
DISCRETION IN RULING arbitrator and more about the arbitrator's appreciation of Trial Court (RTC) ofOrmoc City, Branch 12 upholding contracts. They also demanded that respondents be
THAT THE BROADCAST the issues and evidence presented by the parties. petitioners' legal personality to demand arbitration from penalized by increasing their member Planters' 65% share
OF "WINS WEEKLY" Therefore, the issues clearly fall under the classification of respondents and directing respondents to nominate two provided in the milling contract by 1%, to 66%.
WAS DULY AUTHORIZED errors of fact and law — questions which may be passed arbitrators to represent them in the Respondents filed a motion to dismiss on
BY ABS-CBN. upon by the CA via a petition for review under Rule 43. Board of Arbitrators. cHaADC ground of lack of cause of action because petitioners had no
B. THE SOLE ARBITRATOR Petitioner cleverly crafted its assignment of errors in such a Petitioners are associations organized by and whose milling contract with respondents. According to
COMMITTED SERIOUS way as to straddle both judicial remedies, that is, by members are individual sugar planters (Planters). The respondents, only some eighty (80) Planters who were
ERROR AND/OR alleging serious errors of fact and law (in which case a membership of each association follows: 264 Planters were members of OSPA, one of the petitioners, executed milling
GRAVELY ABUSED HIS petition for review under Rule 43 would be proper) and members of OSPA; 533 Planters belong to OLFAMCA; contracts. Respondents and these 80 Planterswere the
DISCRETION IN RULING grave abuse of discretion (because of which a petition for 617 Planters joined UNIFARM; 760 Planters enlisted with signatories of the milling contracts. Thus, it was the
THAT THE certiorari under Rule 65 would be permissible). ITaESD ONDIMCO; and the rest belong to BAP-MPC which did not individual Planters, and not petitioners, who had legal
UNAUTHORIZED It must be emphasized that every lawyer should be familiar join the lawsuit. standing to invoke the arbitration clause in the milling
BROADCAST DID NOT with the distinctions between the two remedies for it is not Respondents Hideco Sugar Milling Co., Inc. (Hideco) contracts. Petitioners, not being privy to the milling
CONSTITUTE MATERIAL the duty of the courts to determine under which rule the and Ormoc Sugar Milling Co., Inc. (OSCO) are sugar centrals contracts, had no legal standing whatsoever to demand or
BREACH OF THE petition should fall. 24 Petitioner's ploy was fatal to its engaged in grinding and milling sugarcane delivered to sue for arbitration. HcACTE
AGREEMENT. cause. An appeal taken either to this Court or the CA by the them by numerous individual sugar planters, who may or On August 26, 1999, the RTC issued a Joint Order 5 denying
C. THE SOLE ARBITRATOR wrong or inappropriate mode shall be dismissed. 25 Thus, may not be members of an association such as petitioners. the motion to dismiss, declaring the existence ofa milling
COMMITTED SERIOUS the alternative petition filed in the CA, being an Petitioners assert that the relationship between contract between the parties, and directing respondents to
ERROR AND/OR inappropriate mode of appeal, should have been dismissed respondents and the individual sugar planters is governed nominate two arbitrators to the Boardof Arbitrators, to wit:
GRAVELY ABUSED HIS outright by the CA. by milling contracts. To buttress this claim, petitioners When these cases were called for
DISCRETION IN RULING WHEREFORE, the petition is hereby DENIED. The February presented representative samples of the milling hearing today, counsels for the
THAT WINS 16, 2005 decision and August 16, 2005 resolution of the contracts. 3 petitioners and respondents argued
SEASONABLY CURED Court of Appeals in CA-G.R. SP No. 81940 directing the Notably, Article VII of the milling contracts provides that their respective stand. The Court is
THE BREACH. CaDATc Regional Trial Court of Quezon City, Branch 93 to proceed 34% of the sugar and molasses produced from milling the convinced that there is an existing
D. THE SOLE ARBITRATOR with the trial of the petition for confirmation of arbitral Planter's sugarcane shall belong to the centrals milling contract between the
COMMITTED SERIOUS award is AFFIRMED. (respondents) as compensation, 65% thereof shall go to the petitioners and respondents and
ERROR AND/OR Costs against petitioner. SaETCI Planter and the remaining 1% shall go the association to these planters are represented by
GRAVELY ABUSED HIS SO ORDERED. which the Planter concerned belongs, as aid to the the officers of the associations. The
DISCRETION IN RULING ||| (ABS-CBN Broadcasting Corp. v. World Interactive said association. The 1% aid shall be used by petitioners have the right to sue in
THAT TEMPERATE Network Systems Japan Co., Ltd., G.R. No. 169332, [February the association for any purpose that it may deem fit for its behalf of the planters.
DAMAGES IN THE 11, 2008], 568 PHIL 282-296) members, laborers and their dependents. If the Planter was This Court, acting on the petitions,
AMOUNT OF not a member of any association, then the said 1% shall directs the respondents to
P1,166,955.00 MAY BE FIRST DIVISION revert to the centrals. Article XIV, paragraph B 4 states that nominate two arbitrators to
AWARDED TO WINS. [G.R. No. 156660. August 24, 2009.] the centrals may not, during the life of the milling contract, represent HIDECO/HISUMCO and
E. THE SOLE ARBITRATOR ORMOC SUGARCANE PLANTERS' sign or execute any contract or agreement that will provide OSCO in the Board of Arbitrators
COMMITTED SERIOUS ASSOCIATION, INC. (OSPA), better or more benefits to a Planter, without the written within fifteen (15) days from
ERROR AND/OR OCCIDENTAL LEYTE FARMERS consent of the existing and recognized associations except receipt of this Order. . . .
GRAVELY ABUSED HIS MULTI-PURPOSE COOPERATIVE, toPlanters whose plantations are situated in areas beyond However, if the respondents fail to
DISCRETION IN INC. (OLFAMCA), UNIFARM thirty (30) kilometers from the mill. Article XX provides nominate their two arbitrators,
AWARDING MULTI-PURPOSE COOPERATIVE, that all differences and controversies which may arise upon proper motion by the
ATTORNEY'S FEES IN INC. (UNIFARM) between the parties concerning the agreement shall be petitioners, then the Court will be
THE UNREASONABLE and ORMOC NORTH DISTRICT submitted for discussion to a Board of Arbitration, compelled to use its discretion to
AMOUNT AND IRRIGATION MULTI-PURPOSE consisting of five (5) members — two (2) of which shall be appoint the two (2) arbitrators, as
UNCONSCIONABLE COOPERATIVE, INC. appointed by the centrals, two (2) by the Planter and the embodied in the Milling Contract
AMOUNT OF (ONDIMCO), petitioners, vs. fifth to be appointed by the four appointed by the parties. and R.A. 876.
P850,000.00. THE COURT OF APPEALS (Special On June 4, 1999, petitioners, without impleading xxx xxx xxx
F. THE ERROR COMMITTED BY Former Sixth Division), HIDECO any of their individual members, filed twin petitions with Their subsequent motion for reconsideration having been
THE SOLE ARBITRATOR SUGAR MILLING CO., INC., the RTC for Arbitration under R.A. 876, Recovery of Equal denied by the RTC in its Joint Order 6 dated October 29,
IS NOT A SIMPLE ERROR and ORMOC SUGAR MILLING CO., Additional Benefits, Attorney's Fees and Damages,against 1999, respondents elevated the case to the CA through
OF JUDGMENT OR INC., respondents. HIDECO and OSCO, docketed as Civil Case Nos. 3696-O and a Petition for Certiorari with Prayer for the
ABUSE OF DISCRETION. DECISION 3697-O, respectively. Issuance of Temporary Restraining Order and/or
IT IS GRAVE ABUSE OF LEONARDO-DE CASTRO, J p: Petitioners claimed that respondents violated the Milling Writ of Preliminary Injunction.
DISCRETION Contract when they gave to independent planterswho do
On December 7, 2001, the CA rendered its challenged jurisdiction of the court to render said decision — the same and an agreement to abide by the award, either in express controversy, shall be deemed a
Decision, setting aside the assailed Orders of the RTC. is beyond the province of a special civil action forcertiorari. language or by implication. consent of the parties to the
The CA held that petitioners neither had an existing Erroneous findings and conclusions do not render the The requirements that an arbitration agreement must be jurisdiction of the Courtof First
contract with respondents nor were they privy to the appellate court vulnerable to the corrective written and subscribed by the parties thereto were Instance of the province or city
milling contracts between respondents and the writ of certiorari. For where the court has jurisdiction over enunciated by the Court in B.F. Corporation v. CA. 12 where any of the parties resides, to
individual Planters. In the main, the CA concluded that the case, even if its findings are not correct, they would, at During the proceedings before the CA, it was established enforce such contract ofsubmission.
petitioners had no legal personality to bring the action most constitute errors of law and not abuse of discretion that there were more than two thousand (2,000)Planters in The formal requirements of an agreement to arbitrate are
against respondents or to demand for arbitration. correctable by certiorari. 9 the district at the time the case was commenced at the RTC therefore the following: (a) it must be in writing and (b) it
Petitioners filed a motion for reconsideration, but it too Moreover, even if this Court overlooks the procedural lapse in 1999. The CA further found that ofthose 2,000 Planters, must be subscribed by the parties or their representatives.
was denied by the CA in its Resolution 7 dated October 30, committed by petitioners and decides this matter on the only about eighty (80) Planters, who were all To subscribe means to write underneath, as one's name; to
2002. Thus, the instant petition. merits, the present petition will still not prosper. members of petitioner OSPA, in fact individually executed sign at the end of a document. That word may sometimes
At the outset, it must be noted that petitioners filed the Stripped to the core, the pivotal issue here is whether or milling contracts with respondents. No milling contracts be construed to mean to give consent to or to
instant petition for certiorari under Rule 65 of the not petitioners — sugar planters' associations — are signed by members of the other petitioners were presented attest. 13 aTDcAH
Rules of Court, to challenge the judgment of the CA. Section clothed with legal personality to file a suit against, or before the CA. aIcDCA Petitioners would argue that they could sue respondents,
1 of Rule 65 states: ESaITA demand arbitration from, respondents in their own name By their own allegation, petitioners are associations duly notwithstanding the fact that they were not signatories in
Section 1.Petition for Certiorari. — without impleading the individual Planters. aTEHIC existing and organized under Philippine law, i.e.,they have the milling contracts because they are the
When any tribunal, board or officer On this point, we agree with the findings of the CA. juridical personalities separate and distinct from recognized representatives of the Planters.
exercising judicial or quasi-judicial Section 2 of R.A. No. 876 (the Arbitration that of their member Planters. It is likewise undisputed that This claim has no leg to stand on since petitioners did not
functions has acted without or in Law) 10 pertinently provides: the eighty (80) milling contracts that were presented were sign the milling contracts at all, whether as a party or as a
excess of its jurisdiction, or with Sec. 2.Persons and matters subject signed only by the member Planter concerned and representative of their member Planters. The individual
grave abuse of discretion to arbitration. — Two or more one of the Centrals as parties. In other words, none of the Planter and the appropriate central were the only
amounting to lack or excess of its or persons or parties may submit to petitioners were parties or signatories to the milling signatories to the contracts and there is no provision in the
his jurisdiction and there is no the arbitration of one or more contracts. This circumstance is fatal to petitioners' cause milling contracts that the individual Planter is authorizing
appeal, or any plain, speedy and arbitrators any controversy since they anchor their right to demand arbitration from the association to represent him/her in a legal action in
adequate remedy in the existing between them at the the respondent sugar centrals upon the arbitration clause case of a dispute over the milling contracts.
course of law, a person aggrieved timeof the submission and which found in the milling contracts. There is no legal basis for Moreover, even assuming that petitioners are indeed
thereby may file a verified petition may be the subject of an petitioners' purported right to demand arbitration when representatives of the member Planters who have milling
in the proper court, alleging the action, or the parties to any they are not parties to the milling contracts, especially contracts with the respondents and assuming further that
facts with certainty and praying contract may in such contract when the language of the arbitration clause expressly petitioners signed the milling contracts
that judgment be rendered agree to settle by arbitration a grants the right to demand arbitration only to the parties to asrepresentatives of their members, petitioners could not
annulling or modifying the controversy thereafter arising the contract. initiate arbitration proceedings in their own nameas they
proceedings of such tribunal, board between them. Such submission or Simply put, petitioners do not have any agreement to had done in the present case. As mere agents, they should
or officer, and granting such contract shall be valid, enforceable arbitrate with respondents. Only eighty (80) Planterswho have brought the suit in the name of the principals that
incidental relief as law and justice and irrevocable, save upon such were all members of OSPA were shown to have such an they purportedly represent. Even if Section 4 of R.A. No.
require. . . . (emphasis ours) grounds as exist at law for the agreement to arbitrate, included as a stipulation in their 876 allows the agreement to arbitrate to be signed by a
The instant recourse is improper because the revocation of any contract. . . . individual milling contracts. The other petitioners failed to representative, the principal is still the one who has the
resolution of the CA was a final order from which the (Emphasis ours) prove that any of their members had milling contracts with right to demand arbitration.
remedyof appeal was available under Rule 45 in relation to respondents, much less, that respondents had an Indeed, Rule 3, Section 2 of the Rules of Court requires suits
Rule 56. The existence and availability of the right ofappeal The foregoing provision speaks of two agreement to arbitrate with the petitioner associations to be brought in the name of the real party in interest, to
proscribes resort to certiorari because one of the modes of arbitration: (a) an agreement to submit to themselves. wit:
requirements for availment of the latter is precisely that arbitration some future dispute, usually stipulated upon in Even assuming that all the petitioners were able to present Sec. 2.Parties in interest. — A real
there should be no appeal. It is elementary that a civil contract between the parties, and known as milling contracts in favor of their members, it is undeniable party in interest is the party who
for certiorari to prosper, it is not enough that the an agreement to submit to arbitration, and (b) an that under the arbitration clause in these contracts it is the stands to be benefited or injured by
trialcourt committed grave abuse of discretion amounting agreement submitting an existing matter of difference to parties thereto who have the right to submit a controversy the judgment in the suit, or the
to lack or excess of jurisdiction; the requirement that there arbitrators, termed the submission agreement. Article or dispute to arbitration. party entitled to the avails of the
is no appeal, nor any plain, speedy and adequate remedy in XX of the milling contract is an agreement to submit to Section 4 of R.A. 876 provides: suit. Unless otherwise authorized
the ordinary course of law must likewise be satisfied. 8 The arbitrationbecause it was made in anticipation of a dispute Section 4.Form of Arbitration by law or these Rules, every action
proper mode of recourse for petitioners was to file a that might arise between the parties after the contract's Agreement. — A contract to must be prosecuted or defended in
petition for review of the CA's decision under Rule 45. execution. arbitrate a controversy thereafter the name of the real party in
Petitioners principally argue that the CA committed a grave Except where a compulsory arbitration is provided by arising between the parties, as well interest.
error in setting aside the challenged Joint Ordersof the RTC statute, the first step toward the settlement of a difference as a submission to arbitrate an We held in Oco v. Limbaring 14 that:
which allegedly unduly curtailed the right of petitioners to by arbitration is the entry by the parties into a valid existing controversy, shall be in As applied to the present case, this
represent their planters-members and enforce the milling agreement to arbitrate. An agreement to arbitrate is a writing and subscribed by the party provision has two requirements: 1)
contracts with respondents. Petitioners assert the said contract, the relation of the parties is contractual, and the sought to be charged, or by his to institute an action, the plaintiff
which orders were issued in accordance with Article rights and liabilities of the parties are controlled by the lawful agent. must be the real party in interest;
XX of the Milling Contract and the applicable law of contracts. 11 In an agreement for arbitration, the The making of a contract or and 2) the action must be
provisions of Republic Act (R.A.) No. 876. ordinary elements of a valid contract must appear, submission for arbitration prosecuted in the name of the real
Where the issue or question involved affects the wisdom or including an agreement to arbitrate some specific thing, described in section two hereof, party in interest. Necessarily, the
legal soundness of the decision — not the providing for arbitration of any purposes of this provision are 1) to
prevent the prosecution of actions thereto as against each other, the The heir is not liable beyond the a stipulation meant to benefit thePlanters. Even the 1%
by persons without any right, title real parties-in-interest, either as value of the property he received share to be given to the association as aid does not redound
or interest in the case; 2) to require plaintiff or defendant, in an from the decedent. to the benefit of theassociation but is intended to be used
that the actual party entitled to action upon that contract must, If a contract should contain some for its member Planters. Not only that, it is explicit that said
legal relief be the one to prosecute generally, either be parties to stipulation in favor of a third share reverts back to respondent sugar centrals if the
the action; 3) to avoid a said contract. (emphasis and person, he may demand its contracting Planter is not affiliated with any
multiplicity of suits; and 4) to words in brackets ours) fulfillment provided he recognizedassociation. TCIDSa
discourage litigation and keep it The main cause of action of petitioners in their request for communicated his acceptance to To be considered a pour autrui provision, an incidental
within certain bounds, pursuant to arbitration with the RTC is the alleged violation ofthe the obligor before its revocation. A benefit or interest, which another person gains, is not
sound public policy. clause in the milling contracts involving the proportionate mere incidental benefit or sufficient. The contracting parties must have clearly and
Interest within the sharing in the proceeds of the harvest. Petitioners interest of a person is not sufficient. deliberately conferred a favor upon a third person.18 Even
meaning of the Rules means essentially demand that respondents increase the The contracting parties must have the clause stating that respondents must secure the
material interest or an interest share of the member Planters to 66% to equalize their clearly and deliberately conferred a consent of the association if respondents grant better
in issue to be affected by the situation with those of the non-member Planters. Verily, favor upon a third person. benefits to a Planter has for its rationale the
decree or judgment of the from petitioners' own allegations, the party who would be To summarize, the requisites of a stipulation pour autrui or protection of the member Planter. The only
case, as distinguished from mere injured or benefited by a decision in the arbitration a stipulation in favor of a third person are the following: (1) interest ofthe association therein is that its member Planter
curiosity about the question proceedings will be the memberPlanters involved and not there must be a stipulation in favor of a third person, (2) will not be put at a disadvantage vis a vis other Planters.
involved. One having no material petitioners. In sum, petitioners are not the real parties in the stipulation must be a part, not the whole, of the Thus, the associations' interest in these milling contracts is
interest to protect cannot invoke interest in the present case. contract, (3) the contracting parties must have clearly and only incidental to their avowed purpose ofadvancing the
the jurisdiction of the courtas the Assuming petitioners had properly brought the case in the deliberately conferred a favor upon a third person, not a welfare and rights of their member Planters.
plaintiff in an action. When the name of their members who had existing milling contracts mere incidental benefit or interest, (4) the third person In all, the Court finds no grave abuse of discretion nor
plaintiff is not the real party in with respondents, petitioners must still prove that they must have communicated his acceptance to the obligor reversible error committed by the CA in setting aside the
interest, the case is dismissible were indeed authorized by the said members to institute an before its revocation, and (5) neither of the contracting Joint Orders issued by the RTC.
on the action for and on the members' behalf. In the same manner parties bears the legal representation or WHEREFORE, petition is hereby DISMISSED.
ground of lack of cause of action. that an officer of the corporation cannot bring action in authorization of the third party. 17 These requisites are not Costs against petitioners.
DHcTaE behalf of a corporation unless it is clothed with a board present in this case. SO ORDERED.
xxx xxx xxx resolution authorizing an officer to do so, an authorization Article VI of the Milling Contract is the solitary provision ||| (Ormoc Sugarcane Planters' Ass'n, Inc. v. Court of Appeals,
The parties to a contract are the from the individual member planter is a sine qua non for that mentions some benefit in G.R. No. 156660, [August 24, 2009], 613 PHIL 240-256)
real parties in interest in an theassociation or any of its officers to bring an action favor of theassociation of which the planter is a member
action upon it, as consistently before the court of law. The mere fact that petitioners were and we quote: SPECIAL SECOND DIVISION
held by the Court. Only the organized for the purpose of advancing the interests and VI [G.R. No. 161957. January 22, 2007.]
contracting parties are bound by welfare of their members does not necessarily mean that SHARE IN THE SUGAR JORGE GONZALES and PANEL OF
the stipulations in the petitioners have the authority to represent their members Thirty four per centrum * ARBITRATORS, petitioners, vs.
contract; they are the ones who in legal proceedings, including the present arbitration (34%) of the sugar ad * molasses CLIMAX MINING LTD., CLIMAX-
would benefit from and could proceedings. resulting from the milling of the ARIMCO MINING CORP., and
violate it. Thus, one who is not a PLANTER's sugarcane, as computed AUSTRALASIAN PHILIPPINES
party to a contract, and for whose As we see it, petitioners had no intention to litigate the case from the weight and MINING INC.,respondents.
benefit it was not expressly in a representative capacity, as they contend. All the analysis of the sugarcane delivered [G.R. No. 167994. January 22, 2007.]
made, cannot maintain an action pleadings from the RTC to this Court belie this claim. Under by the PLANTER, shall belong to the JORGE GONZALES, petitioner, vs.
on it. One cannot do so, even if the Section 3 of Rule 3, where the action is allowed to be CENTRAL; sixty five per centum HON. OSCAR B. PIMENTEL, in his
contract performed by the prosecuted by a representative, the beneficiary shall be (65%) thereof to the PLANTER, and capacity as PRESIDING JUDGE of
contracting parties would included in the title of the case and shall be deemed to be one per centum (1%) as aid to BR. 148 of the REGIONAL TRIAL
incidentally inure to one's the real party in interest. As repeatedly pointed out earlier, the association of the PLANTER; COURT of MAKATI CITY, and
benefit. (emphasis ours) the individual Planterswere not even impleaded as parties provided that, if the PLANTER is CLIMAX-ARIMCO MINING
In Uy v. Court of Appeals, 15 this Court held that the to this case. In addition, petitioners need a power-of- not a CORPORATION, respondents.
agents of the parties to a contract do not have the right to attorney to represent the Planters whether in the lawsuit member of any association recogniz RESOLUTION
bring an action even if they rendered some service on or to demand arbitration. 16 None was ever presented ed by the CENTRAL, said one per TINGA, J p:
behalf of their principals. To quote from that decision: here. TIADCc centum (1%) shall revert to the This is a consolidation of two petitions rooted in the same
. . .[Petitioners] are mere Lastly, petitioners theorize that they could demand and sue CENTRAL. The 1% aid shall be used disputed Addendum Contract entered into by the parties. In
agents of the owners of the land for arbitration independently of the Plantersbecause the by the association for any purpose G.R. No. 161957, the Court in its Decision of 28 February
subject of the sale. As agents, they milling contract is a contract pour autrui under Article that it may deem fit for its 2005 1 denied the Rule 45 petition of petitioner Jorge
only render some service or do 1311 of the Civil Code. members, laborers and their Gonzales (Gonzales). It held that the DENR Panel of
something in representation or on ART. 1311.Contracts take effect dependents, or for its other socio- Arbitrators had no jurisdiction over the complaint for the
behalf of their principals. The only between the parties, their economic projects. annulment of the Addendum Contract on grounds of fraud
renderingof such service did not assigns and heirs, except in case The foregoing provision cannot, by any stretch of the and violation of the Constitution and that the action should
make them parties to the where the rights and obligations imagination, be considered as a stiputation * pour autrui or have been brought before the regular courts as it involved
contracts of sale executed in arising from the contract are not for the benefit of the petitioners. The primary rationale for judicial issues. Both parties filed separate motions for
behalf of the latter. Since a contract transmissible by their nature, or by the said stipulation is to ensure a just share in the reconsideration. Gonzales avers in his Motion for
may be violated only by the parties stipulation or by provision of law. proceeds of the harvest to the Planters. In other words, it is Reconsideration 2 that the Court erred in holding that the
DENR Panel of Arbitrators was bereft of jurisdiction, pursuant to Clause 19.1 11 of the Addendum Contract and immediately ordering the parties to proceed with subject matter of an arbitration
reiterating its argument that the case involves a mining also in accordance with Sec. 5 of R.A. No. 876. The petition arbitration despite the proper, valid, and timely raised agreement shall, if at least one
dispute that properly falls within the ambit of the Panel's for arbitration was subsequently filed and Climax-Arimco argument in his Answer with Counterclaim that the party so requests not later than the
authority. Gonzales adds that the Court failed to rule on sought an order to compel the parties to arbitrate pursuant Addendum Contract, containing the arbitration clause, is pre-trial conference, or upon the
other issues he raised relating to the sufficiency of his to the said arbitration clause. The case, docketed as Civil null and void. Gonzales has also sought a temporary request of both parties thereafter,
complaint before the DENR Panel of Arbitrators and the Case No. 00-444, was initially raffled to Br. 132 of the RTC restraining order to prevent the enforcement of the refer the parties to arbitration
timeliness of its filing. of Makati City, with Judge Herminio I. Benito as Presiding assailed orders directing the parties to arbitrate, and to unless it finds that the arbitration
Respondents Climax Mining Ltd., et al., (respondents) filed Judge. Respondent Climax-Arimco filed on 5 April 2000 a direct Judge Pimentel to hold a pre-trial conference and the agreement is null and void,
their Motion for Partial Reconsideration and/or motion to set the application to compel arbitration for necessary hearings on the determination of the nullity of inoperative or incapable of being
Clarification 3 seeking reconsideration of that part of the hearing. the Addendum Contract. HSCAIT performed.
Decision holding that the case should not be brought for On 14 April 2000, Gonzales filed a motion to dismiss which In support of his argument, Gonzales invokes Sec. 6 of R.A.
arbitration under Republic Act (R.A.) No. 876, also known he however failed to set for hearing. On 15 May 2000, he No. 876: According to Gonzales, the above-quoted provisions of law
as the Arbitration Law. 4 Respondents, citing American filed an Answer with Counterclaim, 12 questioning the Sec. 6. Hearing by court. — A party outline the procedure to be followed in petitions to compel
jurisprudence 5 and the UNCITRAL Model Law, 6 argue validity of the Addendum Contract containing the aggrieved by the failure, neglect or arbitration, which the RTC did not follow. Thus, referral of
that the arbitration clause in the Addendum Contract arbitration clause. Gonzales alleged that the Addendum refusal of another to perform under the parties to arbitration by Judge Pimentel despite the
should be treated as an agreement independent of the Contract containing the arbitration clause is void in view of an agreement in writing providing timely and properly raised issue of nullity of the Addendum
other terms of the contract, and that a claimed rescission of Climax-Arimco's acts of fraud, oppression and violation of for arbitration may petition the Contract was misplaced and without legal basis. Both R.A.
the main contract does not avoid the duty to arbitrate. the Constitution. Thus, the arbitration clause, Clause 19.1, court for an order directing that No. 876 and R.A. No. 9285 mandate that any issue as to the
Respondents add that Gonzales's argument relating to the contained in the Addendum Contract is also null and such arbitration proceed in the nullity, inoperativeness, or incapability of performance of
alleged invalidity of the Addendum Contract still has to be void ab initio and legally inexistent. manner provided for in such the arbitration clause/agreement raised by one of the
proven and adjudicated on in a proper proceeding; that is, On 18 May 2000, the RTC issued an order declaring agreement. Five days notice in parties to the alleged arbitration agreement must be
an action separate from the motion to compel arbitration. Gonzales's motion to dismiss moot and academic in view of writing of the hearing of such determined by the court prior to referring it to arbitration.
Pending judgment in such separate action, the Addendum the filing of his Answer with Counterclaim. 13 application shall be served either They require that the trial court first determine or resolve
Contract remains valid and binding and so does the On 31 May 2000, Gonzales asked the RTC to set the case for personally or by registered mail the issue of nullity, and there is no other venue for this
arbitration clause therein. Respondents add that the pre-trial. 14 This the RTC denied on 16 June 2000, holding upon the party in default. The court determination other than a pre-trial and hearing on the
holding in the Decision that "the case should not be brought that the petition for arbitration is a special proceeding that shall hear the parties, and upon issue by the trial court which has jurisdiction over the case.
under the ambit of the Arbitration Law" appears to be is summary in nature. 15 However, on 7 July 2000, the RTC being satisfied that the making of Gonzales adds that the assailed 13 February 2001 Order
premised on Gonzales's having "impugn[ed] the existence granted Gonzales's motion for reconsideration of the 16 the agreement or such failure to also violated his right to procedural due process when the
or validity" of the addendum contract. If so, it supposedly June 2000 Order and set the case for pre-trial on 10 August comply therewith is not in issue, trial court erroneously ruled on the existence of the
conveys the idea that Gonzales's unilateral repudiation of 2000, it being of the view that Gonzales had raised in his shall make an order directing the arbitration agreement despite the absence of a hearing for
the contract or mere allegation of its invalidity is all it takes answer the issue of the making of the arbitration parties to proceed to arbitration in the presentation of evidence on the nullity of the
to avoid arbitration. Hence, respondents submit that the agreement. 16 accordance with the terms of the Addendum Contract.
court's holding that "the case should not be brought under Climax-Arimco then filed a motion to resolve its pending agreement. If the making of the Respondent Climax-Arimco, on the other hand, assails the
the ambit ofthe Arbitration Law" be understood or clarified motion to compel arbitration. The RTC denied the same in agreement or default be in issue the mode of review availed of by Gonzales. Climax-Arimco cites
as operative only where the challenge to the arbitration its 24 July 2000 order. court shall proceed to summarily Sec. 29 of R.A. No. 876:
agreement has been sustained by final judgment. On 28 July 2000, Climax-Arimco filed a Motion to Inhibit hear such issue. If the finding be Sec. 29. Appeals. — An appeal may
Both parties were required to file their respective Judge Herminio I. Benito for "not possessing the cold that no agreement in writing be taken from an order made in a
comments to the other party's motion for neutrality of an impartial judge." 17 On 5 August 2000, providing for arbitration was made, proceeding under this Act, or from
reconsideration/clarification. 7 Respondents filed their Judge Benito issued an Order granting the Motion to Inhibit or that there is no default in the a judgment entered upon an award
Comment on 17 August 2005, 8 while Gonzales filed his and ordered the re-raffling of the petition for proceeding thereunder, the through certiorari proceedings, but
only on 25 July 2006. 9 arbitration. 18 The case was raffled to the sala of public proceeding shall be dismissed. If such appeals shall be limited to
On the other hand, G.R. No. 167994 is a Rule 65 petition respondent Judge Oscar B. Pimentel of Branch 148. HSTAcI the finding be that a written questions of law. The proceedings
filed on 6 May 2005, or while the motions for On 23 August 2000, Climax-Arimco filed a motion for provision for arbitration was made upon such an appeal, including the
reconsideration in G.R. No. 161957 10 were pending, reconsideration of the 24 July 2000 Order. 19 Climax- and there is a default in proceeding judgment thereon shall be
wherein Gonzales challenged the orders of the Regional Arimco argued that R.A. No. 876 does not authorize a pre- thereunder, an order shall be made governed by the Rules of Court in
Trial Court (RTC) requiring him to proceed with the trial or trial for a motion to compel arbitration but directs summarily directing the parties to so far as they are applicable.
arbitration proceedings as sought by Climax-Arimco Mining the court to hear the motion summarily and resolve it proceed with the arbitration in Climax-Arimco mentions that the special civil action
Corporation (Climax-Arimco). within ten days from hearing. Judge Pimentel granted the accordance with the terms thereof. for certiorari employed by Gonzales is available only where
On 5 June 2006, the two cases, G.R. Nos. 161957 and motion and directed the parties to arbitration. On 13 The court shall decide all motions, there is no appeal or any plain, speedy, and adequate
167994, were consolidated upon the recommendation of February 2001, Judge Pimentel issued the first assailed petitions or applications filed under remedy in the ordinary course of law against the
the Assistant Division Clerk of Court since the cases are order requiring Gonzales to proceed with arbitration the provisions of this Act, within challenged orders or acts. Climax-Arimco then points out
rooted in the same Addendum Contract. proceedings and appointing retired CA Justice Jorge Coquia ten (10) days after such motions, that R.A. No. 876 provides for an appeal from such orders,
We first tackle the more recent case which is G.R. No. as sole arbitrator. 20 petitions, or applications have been which, under the Rules of Court, must be filed within 15
167994. It stemmed from the petition to compel arbitration Gonzales moved for reconsideration on 20 March 2001 but heard by it. days from notice of the final order or resolution appealed
filed by respondent Climax-Arimco before the RTC of this was denied in the Order dated 7 March 2005.21 Gonzales also cites Sec. 24 of R.A. No. 9285 or the from or of the denial of the motion for reconsideration filed
Makati City on 31 March 2000 while the complaint for the Gonzales thus filed the Rule 65 petition assailing the Orders "Alternative Dispute Resolution Act of 2004:" in due time. Gonzales has not denied that the relevant 15-
nullification of the Addendum Contract was pending before dated 13 February 2001 and 7 March 2005 of Judge Sec. 24. Referral to Arbitration. — A day period for an appeal had elapsed long before he filed
the DENR Panel of Arbitrators. On 23 March 2000, Climax- Pimentel. Gonzales contends that public respondent Judge court before which an action is this petition forcertiorari. He cannot use the special civil
Arimco had sent Gonzales a Demand for Arbitration Pimentel acted with grave abuse of discretion in brought in a matter which is the action of certiorari as a remedy for a lost appeal.
Climax-Arimco adds that an application to compel The grounds Gonzales invokes for the revocation of the under certiorari under Rule 45 of the Rules of Court that a question of law which may be properly taken cognizance
arbitration under Sec. 6 of R.A. No. 876 confers on the trial Addendum Contract — fraud and oppression in the raises pure questions of law. 26 There is no merit to of in a petition for certiorari under Rule 65, so the Court
court only a limited and special jurisdiction, i.e., a execution thereof — are also not grounds for the Gonzales's argument that the use of the permissive term held. 31
jurisdiction solely to determine (a) whether or not the revocation of the arbitration clause in the Contract, Climax- "may" in Sec. 29, R.A. No. 876 in the filing of appeals does The situation in BF Corporation is not availing in the
parties have a written contract to arbitrate, and (b) if the Arimco notes. Such grounds may only be raised by way of not prohibit nor discount the filing of a petition present petition. The disquisition in BF Corporation led to
defendant has failed to comply with that contract. Climax- defense in the arbitration itself and cannot be used to for certiorari under Rule 65. 27 Proper interpretation of the conclusion that in order that the question of
Arimco cites La Naval Drug Corporation v. Court of frustrate or delay the conduct of arbitration proceedings. the aforesaid provision of law shows that the term "may" jurisdiction may be resolved, the appellate court had to
Appeals, 22 which holds that in a proceeding to compel Instead, these should be raised in a separate action for refers only to the filing of an appeal, not to the mode of deal first with a question of law which could be addressed
arbitration, "[t]he arbitration law explicitly confines the rescission, it continues. review to be employed. Indeed, the use of "may" merely in a certiorari proceeding. In the present case, Gonzales's
court's authority only to pass upon the issue of whether Climax-Arimco emphasizes that the summary proceeding reiterates the principle that the right to appeal is not part petition raises a question of law, but not a question of
there is or there is no agreement in writing providing for to compel arbitration under Sec. 6 of R.A. No. 876should of due process of law but is a mere statutory privilege to be jurisdiction. Judge Pimentel acted in accordance with the
arbitration," and "[i]n the affirmative, the statute ordains not be confused with the procedure in Sec. 24 of R.A. No. exercised only in the manner and in accordance with law. procedure prescribed in R.A. No. 876 when he ordered
that the court shall issue an order 'summarily directing the 9285. Sec. 6 of R.A. No. 876 refers to an application to Neither can BF Corporation v. Court of Appeals 28 cited by Gonzales to proceed with arbitration and appointed a sole
parties to proceed with the arbitration in accordance with compel arbitration where the court's authority is limited to Gonzales support his theory. Gonzales argues that said case arbitrator after making the determination that there was
the terms thereof.'" 23 Climax-Arimco argues that R.A. No. resolving the issue of whether there is or there is no recognized and allowed a petition for certiorari under Rule indeed an arbitration agreement. It has been held that as
876 gives no room for any other issue to be dealt with in agreement in writing providing for arbitration, while Sec. 65 "appealing the order of the Regional Trial Court long as a court acts within its jurisdiction and does not
such a proceeding, and that the court presented with an 24 of R.A. No. 9285 refers to an ordinary action which disregarding the arbitration agreement as an acceptable gravely abuse its discretion in the exercise thereof, any
application to compel arbitration may order arbitration or covers a matter that appears to be arbitrable or subject to remedy." 29 The BF Corporation case had its origins in a supposed error committed by it will amount to nothing
dismiss the same, depending solely on its finding as to arbitration under the arbitration agreement. In the latter complaint for collection of sum of money filed by therein more than an error of judgment reviewable by a timely
those two limited issues. If either of these matters is case, the statute is clear that the court, instead of trying the petitioner BF Corporation against Shangri-la Properties, appeal and not assailable by a special civil action
disputed, the court is required to conduct a summary case, may, on request of either or both parties, refer the Inc. (SPI). SPI moved to suspend the proceedings alleging of certiorari. 32 Even if we overlook the employment of the
hearing on it. Gonzales's proposition contradicts both the parties to arbitration, unless it finds that the arbitration that the construction agreement or the Articles of wrong remedy in the broader interests of justice, the
trial court's limited jurisdiction and the summary nature of agreement is null and void, inoperative or incapable of Agreement between the parties contained a clause petition would nevertheless be dismissed for failure of
the proceeding itself. being performed. Arbitration may even be ordered in the requiring prior resort to arbitration before judicial Gonzalez to show grave abuse of discretion.
Climax-Arimco further notes that Gonzales's attack on or same suit brought upon a matter covered by an arbitration intervention. The trial court found that an arbitration Arbitration, as an alternative mode of settling disputes, has
repudiation of the Addendum Contract also is not a ground agreement even without waiting for the outcome of the clause was incorporated in the Conditions of Contract long been recognized and accepted in our jurisdiction. The
to deny effect to the arbitration clause in the Contract. The issue of the validity of the arbitration agreement. Art. 8 of appended to and deemed an integral part of the Articles of Civil Code is explicit on the matter. 33 R.A. No. 876 also
arbitration agreement is separate and severable from the the UNCITRAL Model Law 24 states that where a court Agreement. Still, the trial court denied the motion to expressly authorizes arbitration of domestic disputes.
contract evidencing the parties' commercial or economic before which an action is brought in a matter which is suspend proceedings upon a finding that the Conditions of Foreign arbitration, as a system of settling commercial
transaction, it stresses. Hence, the alleged defect or failure subject of an arbitration agreement refers the parties to Contract were not duly executed and signed by the parties. disputes of an international character, was likewise
of the main contract is not a ground to deny enforcement of arbitration, the arbitral proceedings may proceed even The trial court also found that SPI had failed to file any recognized when the Philippines adhered to the United
the parties' arbitration agreement. Even the party who has while the action is pending. written notice of demand for arbitration within the period Nations "Convention on the Recognition and the
repudiated the main contract is not prevented from Thus, the main issue raised in the Petition for Certiorari is specified in the arbitration clause. The trial court denied Enforcement of Foreign Arbitral Awards of 1958," under
enforcing its arbitration provision. R.A. No. 876 itself treats whether it was proper for the RTC, in the proceeding to SPI's motion for reconsideration and ordered it to file its the 10 May 1965 Resolution No. 71 of the Philippine
the arbitration clause or agreement as a contract separate compel arbitration under R.A. No. 876, to order the parties responsive pleading. Instead of filing an answer, SPI filed a Senate, giving reciprocal recognition and allowing
from the commercial, economic or other transaction to be to arbitrate even though the defendant therein has raised petition for certiorari under Rule 65, which the Court of enforcement of international arbitration agreements
arbitrated. The statute, in particular paragraph 1 of Sec. 2 the twin issues of validity and nullity of the Addendum Appeals, favorably acted upon. In a petition for review between parties of different nationalities within a
thereof, considers the arbitration stipulation an Contract and, consequently, of the arbitration clause before this Court, BF Corporation alleged, among others, contracting state. 34 The enactment of R.A. No. 9285 on 2
independent contract in its own right whose enforcement therein as well. The resolution of both Climax-Arimco's that the Court of Appeals should have dismissed the April 2004 further institutionalized the use of alternative
may be prevented only on grounds which legally make the Motion for Partial Reconsideration and/or Clarification in petition for certiorari since the order of the trial court dispute resolution systems, including arbitration, in the
arbitration agreement itself revocable, thus: G.R. No. 161957 and Gonzales's Petition for Certiorari in denying the motion to suspend proceedings "is a resolution settlement of disputes.
Sec. 2. Persons and matters subject G.R. No. 167994 essentially turns on whether the question of an incident on the merits" and upon the continuation of Disputes do not go to arbitration unless and until the
to arbitration. — Two or more of validity of the Addendum Contract bears upon the the proceedings, the trial court would eventually render a parties have agreed to abide by the arbitrator's decision.
persons or parties may submit to applicability or enforceability of the arbitration clause decision on the merits, which decision could then be Necessarily, a contract is required for arbitration to take
the arbitration of one or more contained therein. The two pending matters shall thus be elevated to a higher court "in an ordinary appeal." 30 place and to be binding. R.A. No. 876recognizes the
arbitrators any controversy jointly resolved. contractual nature of the arbitration agreement, thus:
existing, between them at the time We address the Rule 65 petition in G.R. No. 167994 first The Court did not uphold BF Corporation's argument. The Sec. 2. Persons and matters subject
of the submission and which may from the remedial law perspective. It deserves to be issue raised before the Court was whether SPI had taken to arbitration. — Two or more
be the subject of an action, or the dismissed on procedural grounds, as it was filed in lieu of the proper mode of appeal before the Court of Appeals. The persons or parties may submit to
parties to any contract may in such appeal which is the prescribed remedy and at that far question before the Court of Appeals was whether the trial the arbitration of one or more
contract agree to settle by beyond the reglementary period. It is elementary in court had prematurely assumed jurisdiction over the arbitrators any controversy
arbitration a controversy thereafter remedial law that the use of an erroneous mode of appeal is controversy. The question of jurisdiction in turn depended existing, between them at the
arising between them. Such cause for dismissal of the petition for certiorari and it has on the question of existence of the arbitration clause which time of the submission and which
submission or contract shall be been repeatedly stressed that a petition for certiorari is not is one of fact. While on its face the question of existence of may be the subject of an action, or
valid, enforceable and irrevocable, a substitute for a lost appeal. As its nature, a petition the arbitration clause is a question of fact that is not proper the parties to any contract may in
save upon such grounds as exist at for certiorari lies only where there is "no appeal," and "no in a petition for certiorari, yet since the determination of such contract agree to settle by
law for the revocation of any plain, speedy and adequate remedy in the ordinary course the question obliged the Court of Appeals as it did to arbitration a controversy
contract. of law." 25 The Arbitration Law specifically provides for an interpret the contract documents in accordance with R.A. thereafter arising between
xxx xxx xxx appeal by certiorari, i.e., a petition for review No. 876 and existing jurisprudence, the question is likewise them. Such submission or
contract shall be valid, agreement. If the making of the determine if they should proceed to same be in issue, the court shall proceed summarily to the
enforceable and irrevocable, agreement or default be in issue the arbitration or not. . . . 43 trial thereof" — the U.S. High Court held that the court
save upon such grounds as exist court shall proceed to summarily Implicit in the summary nature of the judicial proceedings should not order the parties to arbitrate if the making of
at law for the revocation of any hear such issue. If the finding be is the separable or independent character of the arbitration the arbitration agreement is in issue. The parties should be
contract. that no agreement in writing clause or agreement. This was highlighted in the cases ordered to arbitration if, and only if, they have contracted
Such submission or contract may providing for arbitration was of Manila Electric Co. v. Pasay Trans. Co. 44and Del Monte to submit to arbitration. Prima Paint was not entitled to
include question arising out of made, or that there is no default in Corporation-USA v. Court of Appeals. 45 trial on the question of whether an arbitration agreement
valuations, appraisals or other the proceeding thereunder, the The doctrine of separability, or severability as other was made because its allegations of fraudulent inducement
controversies which may be proceeding shall be dismissed. If writers call it, enunciates that an arbitration agreement is were not directed to the arbitration clause itself, but only to
collateral, incidental, precedent or the finding be that a written independent of the main contract. The arbitration the consulting agreement which contained the arbitration
subsequent to any issue between provision for arbitration was agreement is to be treated as a separate agreement and the agreement. 50Prima Paint held that "arbitration clauses are
the parties. made and there is a default in arbitration agreement does not automatically terminate 'separable' from the contracts in which they are embedded,
A controversy cannot be arbitrated proceeding thereunder, an order when the contract of which it is part comes to an end. 46 and that where no claim is made that fraud was directed to
where one of the parties to the shall be made summarily directing The separability of the arbitration agreement is especially the arbitration clause itself, a broad arbitration clause will
controversy is an infant, or a the parties to proceed with the significant to the determination of whether the invalidity of be held to encompass arbitration of the claim that the
person judicially declared to be arbitration in accordance with the the main contract also nullifies the arbitration clause. contract itself was induced by fraud." 51
incompetent, unless the terms thereof. Indeed, the doctrine denotes that the invalidity of the main There is reason, therefore, to rule against Gonzales when
appropriate court having The court shall decide all motions, contract, also referred to as the "container" contract, he alleges that Judge Pimentel acted with grave abuse of
jurisdiction approve a petition for petitions or applications filed under does not affect the validity of the arbitration agreement. discretion in ordering the parties to proceed with
permission to submit such the provisions of this Act, within Irrespective of the fact that the main contract is invalid, the arbitration. Gonzales's argument that the Addendum
controversy to arbitration made by ten days after such motions, arbitration clause/agreement still remains valid and Contract is null and void and, therefore the arbitration
the general guardian or petitions, or applications have been enforceable. 47 clause therein is void as well, is not tenable. First, the
guardian ad litem of the infant or of heard by it. [Emphasis added.] The separability of the arbitration clause is confirmed in proceeding in a petition for arbitration under R.A. No.
the incompetent. [Emphasis This special proceeding is the procedural mechanism for Art. 16 (1) of the UNCITRAL Model Law and Art. 21 (2) of 876 is limited only to the resolution of the question of
added.] the enforcement of the contract to arbitrate. The the UNCITRAL Arbitration Rules. 48 whether the arbitration agreement exists. Second, the
Thus, we held in Manila Electric Co. v. Pasay Transportation jurisdiction of the courts in relation to Sec. 6 of R.A. No. The separability doctrine was dwelt upon at length in the separability of the arbitration clause from the Addendum
Co. 35 that a submission to arbitration is a contract. A 876 as well as the nature of the proceedings therein was U.S. case of Prima Paint Corp. v. Flood & Conklin Contract means that validity or invalidity of the Addendum
clause in a contract providing that all matters in dispute expounded upon in La Naval Drug Corporation v. Court of Manufacturing Co. 49 In that case, Prima Paint and Flood Contract will not affect the enforceability of the agreement
between the parties shall be referred to arbitration is a Appeals. 39 There it was held that R.A. No. 876explicitly and Conklin (F & C) entered into a consulting agreement to arbitrate. Thus, Gonzales's petition for certiorari should
contract, 36 and in Del Monte Corporation-USA v. Court of confines the court's authority only to the determination of whereby F & C undertook to act as consultant to Prima be dismissed.
Appeals 37 that "[t]he provision to submit to arbitration whether or not there is an agreement in writing providing Paint for six years, sold to Prima Paint a list of its customers This brings us back to G.R. No. 161957. The adjudication of
any dispute arising therefrom and the relationship of the for arbitration. In the affirmative, the statute ordains that and promised not to sell paint to these customers during the petition in G.R. No. 167994 effectively modifies part of
parties is part of that contract and is itself a contract. As a the court shall issue an order "summarily directing the the same period. The consulting agreement contained an the Decision dated 28 February 2005 in G.R. No. 161957.
rule, contracts are respected as the law between the parties to proceed with the arbitration in accordance with arbitration clause. Prima Paint did not make payments as Hence, we now hold that the validity of the contract
contracting parties and produce effect as between them, the terms thereof." If the court, upon the other hand, finds provided in the consulting agreement, contending that F & containing the agreement to submit to arbitration does not
their assigns and heirs." 38 that no such agreement exists, "the proceeding shall be C had fraudulently misrepresented that it was solvent and affect the applicability of the arbitration clause itself. A
The special proceeding under Sec. 6 of R.A. No. dismissed." 40 The cited case also stressed that the able for perform its contract when in fact it was not and contrary ruling would suggest that a party's mere
876 recognizes the contractual nature of arbitration proceedings are summary in nature. 41 The same thrust had even intended to file for bankruptcy after executing the repudiation of the main contract is sufficient to avoid
clauses or agreements. It provides: was made in the earlier case of Mindanao Portland Cement consultancy agreement. Thus, F & C served Prima Paint arbitration. That is exactly the situation that the
Sec. 6. Hearing by court. — A party Corp. v. McDonough Construction Co. of Florida 42 which with a notice of intention to arbitrate. Prima Paint sued in separability doctrine, as well as jurisprudence applying it,
aggrieved by the failure, neglect or held, thus: court for rescission of the consulting agreement on the seeks to avoid. We add that when it was declared in G.R.
refusal of another to perform under Since there obtains herein a written ground of fraudulent misrepresentation and asked for the No. 161957 that the case should not be brought for
an agreement in writing provision for arbitration as well as issuance of an order enjoining F & C from proceeding with arbitration, it should be clarified that the case referred to is
providing for arbitration may failure on respondent's part to arbitration. F & C moved to stay the suit pending the case actually filed by Gonzales before the DENR Panel
petition the court for an order comply therewith, the court a arbitration. The trial court granted F & C's motion, and the of Arbitrators, which was for the nullification of the main
directing that such arbitration quo rightly ordered the parties to U.S. Supreme Court affirmed. contract on the ground of fraud, as it had already been
proceed in the manner provided for proceed to arbitration in determined that the case should have been brought before
in such agreement. Five days notice accordance with the terms of their The U.S. Supreme Court did not address Prima Paint's the regular courts involving as it did judicial issues.
in writing of the hearing of such agreement (Sec. 6, Republic Act argument that it had been fraudulently induced by F & C to The Motion for Reconsideration of Gonzales in G.R.
application shall be served either 876). Respondent's arguments sign the consulting agreement and held that no court No. 161957 should also be denied. In the motion, Gonzales
personally or by registered mail touching upon the merits of the should address this argument. Relying on Sec. 4 of the raises the same question of jurisdiction, more particularly
upon the party in default. The court dispute are improperly raised Federal Arbitration Act — which provides that "if a party that the complaint for nullification of the Addendum
shall hear the parties, and upon herein. They should be addressed [claims to be] aggrieved by the alleged failure . . . of another Contract pertained to the DENR Panel of Arbitrators, not
being satisfied that the making of to the arbitrators. This proceeding to arbitrate . . . , [t]he court shall hear the parties, and upon the regular courts. He insists that the subject of his
the agreement or such failure to is merely a summary remedy to being satisfied that the making of the agreement for complaint is a mining dispute since it involves a dispute
comply therewith is not in issue, enforce the agreement to arbitrate. arbitration or the failure to comply therewith is not in concerning rights to mining areas, the Financial and
shall make an order directing the The duty of the court in this case is issue, the court shall make an order directing the parties to Technical Assistance Agreement (FTAA) between the
parties to proceed to arbitration in not to resolve the merits of the proceed to arbitration . . . . If the making of the arbitration parties, and it also involves claimowners. He adds that the
accordance with the terms of the parties' claims but only to agreement or the failure, neglect, or refusal to perform the Court failed to rule on other issues he raised, such as
whether he had ceded his claims over the mineral deposits Addendum Contract are grounds for the annulment of a of Salas, Jr.'s land when respondent Laperal Realty to develop Salas, Jr.'s land and sell the same. They are,
located within the Addendum Area of Influence; whether voidable contract under the Civil Code. 55 Under Art. 1391 subdivided it and sold portions thereof to respondent lot rather, buyers of the land that respondent Laperal Realty
the complaint filed before the DENR Panel of Arbitrators of the Code, an action for annulment shall be brought buyers. The trial court dismissed the case because they was given the authority to develop and sell under the
alleged ultimate facts of fraud; and whether the action to within four years, in the case of fraud, beginning from the failed to resort to arbitration which was required in the Agreement. As such, they are not "assigns" contemplated in
declare the nullity of the Addendum Contract on the ground time of the discovery of the same. However, the time of the original agreement entered into by and between Salas, Jr. Art. 1311 of the New Civil Code which provides that
of fraud has prescribed. discovery of the alleged fraud is not clear from the and Laperal Realty Corporation. "contracts take effect only between the parties, their
These are the same issues that Gonzales raised in his Rule allegations of Gonzales's complaint. That being the Petitioners, however, claimed that their causes of action assigns and heirs." For while rescission, as a general rule, is
45 petition in G.R. No. 161957 which were resolved against situation coupled with the fact that this Court is not a trier did not emanate from the original agreement, hence, their an arbitrable issue, they impleaded in the suit for rescission
him in the Decision of 28 February 2005. Gonzales does not of facts, any ruling on the issue of prescription would be failure to arbitrate should not be a ground for dismissal of the respondent lot buyers who are neither parties to the
raise any new argument that would sway the Court even a uncalled for or even unnecessary. the case. Agreement nor the latter's assigns or heirs. Consequently,
bit to alter its holding that the complaint filed before the WHEREFORE, the Petition for Certiorari in G.R. No. 167994 On appeal, the Supreme Court held that petitioners-heirs of the right to arbitrate as provided in Article VI of the
DENR Panel of Arbitrators involves judicial issues which is DISMISSED. Such dismissal effectively renders Salas, Jr., and Laperal Realty are certainly bound by the Agreement was never vested in respondent lot buyers.
should properly be resolved by the regular courts. He superfluous formal action on the Motion for Partial arbitration provision unlike respondent lot buyers who are 4. REMEDIAL LAW; ACTIONS; TRIAL COURT, IN INTEREST
alleged fraud or misrepresentation in the execution of the Reconsideration and/or Clarification filed by Climax Mining neither parties to the Agreement nor the latter's assigns or OF JUSTICE, SHOULD ADJUDICATE ALL ISSUES RAISED IN
Addendum Contract which is a ground for the annulment of Ltd., et al. in G.R. No. 161957. heirs. However, to hold trial in abeyance for respondent lot A SINGLE AND COMPLETE PROCEEDING. — Respondent
a voidable contract. Clearly, such allegations entail legal The Motion for Reconsideration filed by Jorge Gonzales in buyers pending arbitration between petitioners and Laperal Realty, as a contracting party to the Agreement, has
questions which are within the jurisdiction of the courts. G.R. No. 161957 is DENIED WITH FINALITY. TEacSA Laperal Realty would result in multiplicity of suits. the right to compel petitioners to first arbitrate before
The question of whether Gonzales had ceded his claims SO ORDERED. The Supreme Court, therefore, granted the petition and seeking judicial relief. However, to split the proceedings
over the mineral deposits in the Addendum Area of ||| (Gonzales v. Climax Mining Ltd., G.R. No. 161957, 167994, ordered the trial court to proceed with the hearing of the into arbitration for respondent Laperal Realty and trial for
Influence is a factual question which is not proper for [January 22, 2007], 541 PHIL 143-171) suit for rescission. the respondent lot buyers, or to hold trial in abeyance
determination before this Court. At all events, moreover, SYLLABUS pending arbitration between petitioners and respondent
the question is irrelevant to the issue of jurisdiction of the **CASE OF: Agan, Jr. v. Philippine International Air 1. CIVIL LAW; OBLIGATIONS AND CONTRACTS; Laperal Realty, would in effect result in multiplicity of suits,
DENR Panel of Arbitrators. It should be pointed out that the Terminals Co., Inc., (SEPARATE PAGE) ARBITRATION AGREEMENTS; VALID, BINDING, duplicitous procedure and unnecessary delay. On the other
DENR Panel of Arbitrators made a factual finding in its SECOND DIVISION ENFORCEABLE AND NOT CONTRARY TO PUBLIC POLICY. hand, it would be in the interest of justice if the trial court
Order dated 18 October 2001, which it reiterated in its [G.R. No. 135362. December 13, 1999.] — In a catena of cases inspired by Justice Malcolm's hears the complaint against all herein respondents and
Order dated 25 June 2002, that Gonzales had, "through the HEIRS OF AUGUSTO L. SALAS, JR., provocative dissent in Vega v. San Carlos Milling Co., this adjudicates petitioners' rights as against theirs in a single
various agreements, assigned his interest over the mineral namely: TERESITA D. SALAS for Court has recognized arbitration agreements as valid, and complete proceeding. DCASEc
claims all in favor of [Climax-Arimco]" as well as that herself and as legal guardian of binding, enforceable and not contrary to public policy so DECISION
without the complainant [Gonzales] assigning his interest the minor FABRICE CYRILL D. much so that when there obtains a written provision for DE LEON, JR., J p:
over the mineral claims in favor of [Climax-Arimco], there SALAS, MA. CRISTINA S. LESACA, arbitration which is not complied with, the trial court Before us is a petition for review on certiorari of the
would be no FTAA to speak of." 52 This finding was and KARINA TERESA D. should suspend the proceedings and order the parties to Order 1 of Branch 85 of the Regional Trial Court of Lipa
affirmed by the Court of Appeals in its Decision dated 30 SALAS, petitioners, vs. LAPERAL proceed to arbitration in accordance with the terms of their City 2 dismissing petitioners' complaint 3 for rescission of
July 2003 resolving the petition for certiorari filed by REALTY CORPORATION, agreement. Arbitration is the "wave of the future" in several sale transactions involving land owned by Augusto
Climax-Arimco in regard to the 18 October 2001 Order of ROCKWAY REAL ESTATE dispute resolution. To brush aside a contractual agreement L. Salas, Jr., their predecessor-in-interest, on the ground
the DENR Panel. 53 CORPORATION, SOUTH RIDGE calling for arbitration in case of disagreement between that they failed to first resort to arbitration.LexLib
The Court of Appeals likewise found that Gonzales's VILLAGE, INC., MAHARAMI parties would be a step backward. Salas, Jr. was the registered owner of a vast tract of land in
complaint alleged fraud but did not provide any particulars DEVELOPMENT CORPORATION, 2. ID.; ID.; ID.; BINDS PARTIES THERETO AS WELL AS Lipa City, Batangas spanning 1,484,354 square meters.
to substantiate it. The complaint repeatedly mentioned Spouses THELMA D. ABRAJANO THEIR ASSIGNS AND HEIRS; CASE AT BAR. — A On May 15, 1987, he entered into an Owner-Contractor
fraud, oppression, violation of the Constitution and similar and GREGORIO ABRAJANO, submission to arbitration is a contract. As such, the Agreement 4 (hereinafter referred to as the Agreement)
conclusions but nowhere did it give any ultimate facts or OSCAR DACILLO, Spouses Agreement, containing the stipulation on arbitration, binds with respondent Laperal Realty Corporation (hereinafter
particulars relative to the allegations. 54 VIRGINIA D. LAVA and RODEL the parties thereto, as well as their assigns and heirs. But referred to as Laperal Realty) to render and provide
Sec. 5, Rule 8 of the Rules of Court specifically provides that LAVA, EDUARDO A. VACUNA, only they. Petitioners, as heirs of Salas, Jr., and respondent complete (horizontal) construction services on his land.
in all averments of fraud, the circumstances constituting FLORANTE DE LA CRUZ, JESUS Laperal Realty are certainly bound by the Agreement. If On September 23, 1988, Salas, Jr. executed a Special Power
fraud must be stated with particularity. This is to enable VICENTE B. CAPELLAN, and the respondent Laperal Realty had assigned its rights under the of Attorney in favor of respondent Laperal Realty to
the opposing party to controvert the particular facts REGISTER OF DEEDS FOR LIPA Agreement to a third party, making the former, the exercise general control, supervision and management of
allegedly constituting the same. Perusal of the complaint CITY, respondents. assignor, and the latter, the assignee, such assignee would the sale of his land, for cash or on installment basis.
indeed shows that it failed to state with particularity the Corpus & Associates for petitioners. also be bound by the arbitration provision since On June 10, 1989, Salas, Jr. left his home in the morning for
ultimate facts and circumstances constituting the alleged Jesus Vicente V. Capellan for private respondents. assignment involves such transfer of rights as to vest in the a business trip to Nueva Ecija. He never returned.prcd
fraud. It does not state what particulars about Climax- Horacio M. Pascual and Vicente P. Acsay for Maharami assignee the power to enforce them to the same extent as On August 6, 1996, Teresita Diaz Salas filed with the
Arimco's financial or technical capability were Development Corp. and Florante de la Cruz. the assignor could have enforced them against the debtor Regional Trial Court of Makati City a verified petition for
misrepresented, or how the misrepresentation was done. Luis A. Ilagan, Jr. for Rockway Real Estate Corp. and South or in this case, against the heirs of the original party to the the declaration of presumptive death of her husband, Salas,
Incorporated in the body of the complaint are verbatim Ridge Village Inc. Agreement. Jr., who had then been missing for more than seven (7)
reproductions of the contracts, correspondence and Santiago Cruz & Sarte Law Offices for Laperal Realty Corp. 3. ID.; ID.; ID.; ID.; LOT BUYERS IN CASE AT BAR NOT years. It was granted on December 12, 1996. 5
government issuances that reportedly explain the Jano P. Liu Chaing for Abrajano, Spouses Lava and Dacillo. BOUND BY CONTRACT. — However, respondents Rockway Meantime, respondent Laperal Realty subdivided the land
allegations of fraud and misrepresentation, but these are, at SYNOPSIS Real Estate Corporation, South Ridge Village, Inc., of Salas, Jr. and sold subdivided portions thereof to
best, evidentiary matters that should not be included in the Petitioners filed a complaint for rescission of several sale Maharami Development Corporation, spouses Abrajano, respondents Rockway Real Estate Corporation and South
pleading. transactions involving land owned by Augusto L. Salas, Jr., spouses Lava, Oscar Dacillo, Eduardo Vacuna, Florante de la Ridge Village, Inc. on February 22, 1990; to respondent
As to the issue of prescription, Gonzales's claims of fraud their predecessor-in-interest, claiming they Cruz and Jesus Vicente Capellan arenot assignees of the spouses Abrajano and Lava and Oscar Dacillo on June 27,
and misrepresentation attending the execution of the suffered lesion of more than one-fourth (1/4) of the value rights of respondent Laperal Realty under the Agreement 1991; and to respondents Eduardo Vacuna, Florante de la
Cruz and Jesus Vicente Capalan on June 4, 1996 (all of heirs. 17 But only they. Petitioners, as heirs of Salas, Jr., and ASIDE. Said court is hereby ordered to proceed with the request for arbitration
whom are hereinafter referred to as respondent lot respondent Laperal Realty are certainly bound by the hearing of Civil Case No. 98-0047. dated 3 November 2000
buyers). Agreement. If respondent Laperal Realty had assigned its Costs against private respondents. prLL pursuant to the Turnkey
On February 3, 1998, petitioners as heirs of Salas, Jr. filed in rights under the Agreement to a third party, making the SO ORDERED. Contract between LHC
the Regional Trial Court of Lipa City a Complaint6 for former, the assignor, and the latter, the assignee, such ||| (Heirs of Salas, Jr. v. Laperal Realty Corp., G.R. No. 135362, and TPI;
declaration of nullity of sale, reconveyance, cancellation of assignee would also be bound by the arbitration provision [December 13, 1999], 378 PHIL 369-376) 3. G.R. No. 146717, Transfield
contract, accounting and damages against herein since assignment involves such transfer of rights as to vest Philippines, Inc. v. Luzon
respondents which was docketed as Civil Case No. 98- in the assignee the power to enforce them to the same SPECIAL SECOND DIVISION Hydro Corporation,
0047. LLpr extent as the assignor could have enforced them against the [G.R. No. 146717. May 19, 2006.] Australia and New
On April 24, 1998, respondent Laperal Realty filed a Motion debtor 18 or in this case, against the heirs of the original TRANSFIELD PHILIPPINES, Zealand Banking Group
to Dismiss 7 on the ground that petitioners failed to submit party to the Agreement. However, respondents Rockway INC., petitioner, vs. LUZON HYDRO Limited and Security
their grievance to arbitration as required under Article VI Real Estate Corporation, South Ridge Village, Inc., CORPORATION, AUSTRALIA AND Bank Corp. filed on 5
of the Agreement which provides: Maharami Development Corporation, spouses Abrajano, NEW ZEALAND BANKING GROUP February 2001, which
"ARTICLE VI. ARBITRATION. spouses Lava, Oscar Dacillo, Eduardo Vacuna, Florante de la LIMITED and SECURITY BANK was an appeal
All cases of dispute between Cruz and Jesus Vicente Capellan are not assignees of the CORPORATION,respondents. by certiorari with prayer
CONTRACTOR and OWNER'S rights of respondent Laperal Realty under the Agreement RESOLUTION for TRO/preliminary
representative shall be referred to to develop Salas, Jr.'s land and sell the same. They are, TINGA, J p: prohibitory and
the committee represented by: rather, buyers of the land that respondent Laperal Realty The adjudication of this case proved to be a two-stage mandatory injunction, of
a. One representative of the was given the authority to develop and sell under the process as its constituent parts involve two segregate but the Court of Appeals
OWNER; Agreement. As such, they are not"assigns" contemplated equally important issues. The first stage relating to the Decision dated 31
b. One representative of the in Art. 1311 of the New Civil Code which provides that merits of the case, specifically the question of the propriety January 2001 in CA-G.R.
CONTRACTOR; "contracts take effect only between the parties, their of calling on the securities during the pendency of the SP No. 61901. AHEDaI
c. One representative acceptable to assigns and heirs". arbitral proceedings, was resolved in favor of Luzon Hydro a. CA-G.R. SP No. 61901
both OWNER and CONTRACTOR." 8 Corporation (LHC) with the Court's Decision 1 of 22 was a petition
On May 5, 1998, respondent spouses Abrajano and Lava Petitioners claim that they suffered lesion of more than November 2004. The second stage involving the issue of for review of
and respondent Dacillo filed a Joint Answer with one-fourth (1/4) of the value of Salas, Jr.'s land when forum-shopping on which the Court required the parties to the Decision in
Counterclaim and Crossclaim 9 praying for dismissal of respondent Laperal Realty subdivided it and sold portions submit their respective memoranda 2 is disposed of in this Civil Case No.
petitioners' Complaint for the same reason. thereof to respondent lot buyers. Thus, they instituted Resolution. 00-1312,
On August 9, 1998, the trial court issued the herein assailed action 19 against both respondent Laperal Realty and The disposal of the forum-shopping charge is crucial to the wherein TPI
Order dismissing petitioners' Complaint for non- respondent lot buyers for rescission of the sale parties to this case on account of its profound effect on the claimed that
compliance with the foregoing arbitration clause. transactions and reconveyance to them of the subdivided final outcome of the international arbitral proceedings LHC's call on
Hence this petition. prcd lots. They argue that rescission, being their cause of action, which they have chosen as their principal dispute the securities
Petitioners argue, thus: falls under the exception clause in Sec. 2 of Republic Act No. resolution mechanism. 3 was
"The petitioners' causes of action 876 which provides that "such submission [to] or contract LHC claims that Transfield Philippines, Inc. (TPI) is guilty of premature
did not emanate from the Owner- [of arbitration] shall be valid, enforceable and forum-shopping when it filed the following suits: considering
Contractor Agreement." irrevocable, save, upon such grounds as exist at law for 1. Civil Case No. 04-332 filed on 19 that the issue
"The petitioners' causes of action the revocation of any contract". March 2004, pending of default has
for cancellation of contract and The petitioners' contention is without merit. For while before the Regional Trial not yet been
accounting are covered by the rescission, as a general rule, is an arbitrable issue, 20they Court (RTC) of Makati, resolved with
exception under the Arbitration impleaded in the suit for rescission the respondent lot Branch 56 for finality; the
Law." buyers who are neither parties to the Agreement nor the confirmation, petition was
"Failure to arbitrate is not a ground latter's assigns or heirs. Consequently, the right to arbitrate recognition and however
for dismissal." 10 as provided in Article VI of the Agreement was never enforcement of the Third denied by the
In a catena of cases 11 inspired by Justice Malcolm's vested in respondent lot buyers. dctai Partial Award in case Court of
provocative dissent in Vega v. San Carlos Milling Co. 12 , Respondent Laperal Realty, as a contracting party to the 11264 TE/MW, ICC Appeals;
this Court has recognized arbitration agreements as valid, Agreement, has the right to compel petitioners to first International Court of b. Civil Case No. 00-1312
binding, enforceable and not contrary to public policy so arbitrate before seeking judicial relief. However, to split the Arbitration, was a
much so that when there obtains a written provision for proceedings into arbitration for respondent Laperal Realty entitled Transfield complaint for
arbitration which is not complied with, the trial court and trial for the respondent lot buyers, or to hold trial in Philippines, Inc. v.Luzon injunction
should suspend the proceedings and order the parties to abeyance pending arbitration between petitioners and Hydro Corporation. 4 with prayer
proceed to arbitration in accordance with the terms of their respondent Laperal Realty, would in effect result in 2. ICC Case No. for temporary
agreement. 13 Arbitration is the "wave of the future" in multiplicity of suits, duplicitous procedure and 11264/TE/MW, Transfiel restraining
dispute resolution. 14 To brush aside a contractual unnecessary delay. On the other hand, it would be in the d Philippines, order and/or
agreement calling for arbitration in case of disagreement interest of justice if the trial court hears the complaint Inc. v. Luzon Hydro writ of
between parties would be a step backward. 15 against all herein respondents and adjudicates petitioners' Corporation filed before preliminary
Nonetheless, we grant the petition. LexLib rights as against theirs in a single and complete proceeding. the International Court injunction
A submission to arbitration is a contract. 16 As such, the WHEREFORE, the instant petition is hereby GRANTED. The of Arbitration, dated 5
Agreement, containing the stipulation on arbitration, binds Order dated August 19, 1998 of Branch 85 of the Regional International Chamber of November
the parties thereto, as well as their assigns and Trial Court of Lipa City is hereby NULLIFIED and SET Commerce (ICC) a 2000, which
sought to grounded on the same cause on the supposition that one or agreement whose partial award is sought to be February 1999 Notice to
restrain LHC the other court would make a favorable disposition. 13 enforced. ACDTcE Correct. 23
from calling Thus, for forum-shopping to exist, there must be (a) As a fundamental point, the pendency of arbitral According to LHC, the filing of the above case constitutes
on the identity of parties, or at least such parties as represent the proceedings does not foreclose resort to the courts for forum-shopping since it is the same claim for the return of
securities and same interests in both actions; (b) identity of rights provisional reliefs. The Rules of the ICC, which governs the US$17.9 Million which TPI made before the ICC Arbitral
respondent asserted and relief prayed for, the relief being founded on parties' arbitral dispute, allows the application of a party to Tribunal and before this Court. LHC adds that while Civil
banks from the same facts; and (c) the identity of the two preceding a judicial authority for interim or conservatory Case No. 04-332 is styled as an action for money, the Third
transferring particulars is such that any judgment rendered in the other measures. 17 Likewise, Section 14 of Republic Act (R.A.) Partial Award used as basis of the suit does not authorize
or paying of action will, regardless of which party is successful, amount No. 876 (The Arbitration Law) 18 recognizes the rights of TPI to seek a writ of execution for the sums drawn on the
the securities; to res judicata in the action under consideration. 14 any party to petition the court to take measures to letters of credit. Said award does not even contain an order
the complaint There is no identity of causes of action between and among safeguard and/or conserve any matter which is the subject for the payment of money, but instead has reserved the
was denied by the arbitration case, the instant petition, and Civil Case No. of the dispute in arbitration. In addition, R.A. 9285, quantification of the amounts for a subsequent
the RTC. 04-332. otherwise known as the "Alternative Dispute Resolution determination, LHC argues. In fact, even the Fifth Partial
On the other hand, TPI claims that it is LHC which is guilty The arbitration case, ICC Case No. 11264 TE/MW, is an Act of 2004," allows the filing of provisional or interim Award, 24 dated 30 March 2005, does not contain such
of forum-shopping when it raised the issue of forum- arbitral proceeding commenced pursuant to the Turnkey measures with the regular courts whenever the arbitral orders. LHC insists that the declarations or the partial
shopping not only in this case, but also in Civil Case No. 04- Contract between TPI and LHC, to determine the primary tribunal has no power to act or to act effectively. 19 awards issued by the ICC Arbitral Tribunal do not
332, and even asked for the dismissal of the other case issue of whether the delays in the construction of the TPI's verified petition in Civil Case No. 04-332, filed on 19 constitute orders for the payment of money and are not
based on this ground. Moreover, TPI argues that LHC is project were excused delays, which would consequently March 2004, was captioned as one "For: Confirmation, intended to be enforceable as such, but merely constitute
relitigating in Civil Case No. 04-332 the very same causes of render valid TPI's claims for extension of time to finish the Recognition and Enforcement of Foreign Arbitral Award in amounts which will be included in the Final Award and will
action in ICC Case No. 11264/TE/MW, and even project. Together with the primary issue to be settled in the Case 11264 TE/MW, ICC International Court of Arbitration, be taken into account in determining the actual amount
manifesting therein that it will present evidence earlier arbitration case is the equally important question of 'Transfield Philippines, Inc. v. Luzon Hydro payable to the prevailing party. 25
presented before the arbitral tribunal. 5 monetary awards to the aggrieved party. DHaEAS Corporation (Place of arbitration: Singapore)." 20 In the R.A. No. 9825 provides that international commercial
Meanwhile, ANZ Bank and Security Bank moved to be On the other hand, Civil Case No. 00-1312, the precursor of said petition, TPI prayed: arbitrations shall be governed shall be governed by the
excused from filing a memorandum. They claim that with the instant petition, was filed to enjoin LHC from calling on 1. That the THIRD PARTIAL Model Law on International Commercial Arbitration
the finality of the Court's Decision dated 22 November the securities and respondent banks from transferring or AWARD dated February 18, 2004 in ("Model Law") adopted by the United Nations Commission
2004, any resolution by the Court on the issue of forum- paying the securities in case LHC calls on them. However, in Case No. 11264/TE/MW made by on International Trade Law (UNCITRAL). 26 The
shopping will not materially affect their role as the banking view of the fact that LHC collected the proceeds, TPI, in its the ICC International Court of UNCITRAL Model Law provides:
entities involved are concerned. 6 The Court granted their appeal and petition for review asked that the same be Arbitration, the signed original ARTICLE 35. Recognition and
respective motions. returned and placed in escrow pending the resolution of copy of which is hereto attached as enforcement
On 1 August 2005, TPI moved to set the case for oral the disputes before the ICC arbitral tribunal. 15 Annex "H" hereof, be confirmed, (1) An arbitral award, irrespective
argument, positing that the resolution of the Court on the While the ICC case thus calls for a thorough review of the recognized and enforced in of the country in which it was
issue of forum-shopping may have significant implications facts which led to the delay in the construction of the accordance with law. made, shall be recognized as
on the interpretation of the Alternative Dispute Resolution project, as well as the attendant responsibilities of the binding and, upon application in
Act of 2004, as well as the viability of international parties therein, in contrast, the present petition puts in 2. That the corresponding writ of writing to the competent court,
commercial arbitration as an alternative mode of dispute issue the propriety of drawing on the letters of credit execution to enforce Question 31 of shall be enforced subject to the
resolution in the country. 7 Said motion was opposed by during the pendency of the arbitral case, and of course, the said Third Partial Award, be provisions of this article and of
LHC in its opposition filed on 2 September 2005, with LHC absent a final determination by the ICC Arbitral tribunal. issued, also in accordance with law. article 36. ADHcTE
arguing that the respective memoranda of the parties are Moreover, as pointed out by TPI, it did not pray for the 3. That TPI be granted such other (2) The party relying on an award
sufficient for the Court to resolve the issue of forum- return of the proceeds of the letters of credit. What it asked relief as may be deemed just and or applying for its enforcement
shopping. 8 On 28 October 2005, TPI filed its Manifestation instead is that the said moneys be placed in escrow until equitable, and allowed, in shall supply the duly authenticated
and Reiterative Motion 9 to set the case for oral argument, the final resolution of the arbitral case. Meanwhile, in Civil accordance with law. 21 original award or a duly certified
where it manifested that the International Chamber of Case No. 04-332, TPI no longer seeks the issuance of a The pertinent portion of the Third Partial Award 22 relied copy thereof, and the original
Commerce (ICC) arbitral tribunal had issued its Final provisional relief, but rather the issuance of a writ of upon by TPI were the answers to Questions 10 to 26, to wit: arbitration agreement referred to
Award ordering LHC to pay TPI US$24,533,730.00 execution to enforce the Third Partial Award. "Question 30 in article 7 or a duly certified copy
(including the US$17,977,815.00 proceeds of the two Neither is there an identity of parties between and among Did TPI [LHC] wrongfully draw thereof. If the award or agreement
standby letters of credit). TPI also submitted a copy thereof the three (3) cases. The ICC case only involves TPI and LHC upon the security? is not made in an official language
with a Supplemental Petition 10 to the Regional Trial Court logically since they are the parties to the Turnkey Contract. Yes of this State, the party shall supply
(RTC), seeking recognition and enforcement of the said In comparison, the instant petition includes Security Bank "Question 31 a duly certified translation thereof
award. 11 and ANZ Bank, the banks sought to be enjoined from Is TPI entitled to have returned to into such language.
The essence of forum-shopping is the filing of multiple suits releasing the funds of the letters of credit. The Court agrees it any sum wrongfully Moreover, the New York Convention, 27 to which the
involving the same parties for the same cause of action, with TPI that it would be ineffectual to ask the ICC to issue taken by LHC for Philippines is a signatory, governs the recognition and
either simultaneously or successively, for the purpose of writs of preliminary injunction against Security Bank and liquidated damages? enforcement of foreign arbitral awards. The applicability of
obtaining a favorable judgment. 12 Forum-shopping has ANZ Bank since these banks are not parties to the Yes the New York Convention in the Philippines was confirmed
likewise been defined as the act of a party against whom an arbitration case, and that the ICC Arbitral tribunal would "Question 32 in Section 42 of R.A. 9285. Said law also provides that the
adverse judgment has been rendered in one forum, seeking not even be able to compel LHC to obey any writ of Is TPI entitled to any acceleration application for the recognition and enforcement of such
and possibly getting a favorable opinion in another forum, preliminary injunction issued from its end. 16 Civil Case costs? TPI is entitled to awards shall be filed with the proper RTC. While TPI's
other than by appeal or the special civil action of certiorari, No. 04-322, on the other hand, logically involves TPI and the reasonable costs TPI resort to the RTC for recognition and enforcement of the
or the institution of two or more actions or proceedings LHC only, they being the parties to the arbitration incurred after Typhoon Third Partial Award is sanctioned by both the New York
Zeb as a result of LHC's 5 Convention and R.A. 9285, its application for enforcement,
however, was premature, to say the least. True, the ICC payable. 31 (Emphasis COTOCO, petitioners, vs. RCBC CAPI throughout the period indicated
Arbitral Tribunal had indeed ruled that LHC wrongfully Supplied.) TALCORPORATION, respondent. and:
drew upon the securities, yet there is no order for the Further, in the Declarations part of the award, the tribunal DECISION i) the balance sheet of
payment or return of the proceeds of the said securities. In held: VELASCO, JR., J p: Bankard as of 31
fact, Paragraph 2142, which is the final paragraph of the 6.2 Declarations The Case December 1999, as
Third Partial Award, reads: 168. The Tribunal makes the This Petition for Review on Certiorari under Rule 45 seeks prepared and certified
2142. All other issues, including following declarations: the reversal of the January 8, 2008 2 and March 17, by SGV & Co. ("SGV"),
any issues as to quantum and costs, xxx xxx xxx 2008 3 Orders of the Regional Trial Court (RTC), Branch and the unaudited
are reserved to a future award. 28 3. LHC is liable to repay TPI the face 148 in Makati City in SP Proc. Case No. 6046, entitledIn the balance sheet for the
Meanwhile, the tribunal issued its Fifth Partial value of the securities drawn Matter of ICC Arbitration Ref. No. 13290/MS/JB/JEM first quarter ended 31
Award 29 on 30 March 2005. It contains, among others, a claimed by TPI in respect of the Between RCBC Capital Corporation, (Claimant), March 2000, present a
declaration that while LHC wrongfully drew on the drawdown of the andEquitable PCI Banking Corporation, Inc. et al., fair and accurate
securities, the drawing was made in good faith, under the securities. EIDTAa (Respondents). The assailed January 8, 2008 Order statement as of those
mistaken assumption that the contractor, TPI, was in xxx xxx xxx. 32 confirmed the Partial Award dated September 27, dates, of Bankard's
default. Thus, the tribunal ruled that while the amount Finally, on 9 August 2005, the ICC Arbitral tribunal issued 2007 4 rendered by the International Chamber of financial condition and
drawn must be returned, TPI is not entitled to any damages its Final Award, in essence awarding US$24,533,730.00, Commerce-International Court of Arbitration (ICC-ICA) in of all its assets and
or interests due to LHC's drawing on the securities. 30 In which included TPI's claim of U$17,977,815.00 for the Case No. 13290/MS/JB/JEM, liabilities, and is
the Fifth Partial Award, the tribunal ordered: return of the securities from LHC. 33 entitled RCBC Capital Corporation(Philippines) v. Equitable complete in all material
6. Order The fact that the ICC Arbitral tribunal included the PCI Bank, Inc. & Others (Philippines). The March 17, 2008 respects; and
6.1 General proceeds of the securities shows that it intended to make a Order denied petitioners' motion for reconsideration of the ii) the statements of
166. This Fifth Partial Award deals final determination/award as to the said issue only in the January 8, 2008 Order. cADEHI Bankard's profit and loss
with many issues of Final Award and not in the previous partial awards. This The Facts accounts for the fiscal
quantum. However, it supports LHC's position that when the Third Partial Award On May 24, 2000, petitioners Equitable PCI Bank, Inc. years 1996 to 1999, as
does not resolve them was released and Civil Case No. 04-332 was filed, TPI was (EPCIB) and the individual shareholders of Bankard, Inc., as prepared and certified
all. The outstanding not yet authorized to seek the issuance of a writ of sellers, and respondent RCBC Capital Corporation (RCBC), by SGV, and the
quantum issues will be execution since the quantification of the amounts due to as buyer, executed a Share Purchase Agreement 5 (SPA) for unaudited profit and loss
determined in a future TPI had not yet been settled by the ICC Arbitral tribunal. the purchase of petitioners' interests in Bankard, accounts for the first
award. It will contain a Notwithstanding the fact that the amount of proceeds representing 226,460,000 shares, for the price of quarter ended 31 March
reconciliation of the drawn on the securities was not disputed the application PhP1,786,769,400. To expedite the purchase, RCBC agreed 2000, fairly and
amounts awarded to for the enforcement of the Third Partial Award was to dispense with the conduct of a due diligence audit on the accurately present the
each party and a precipitately filed. To repeat, the declarations made in the financial status of Bankard. results of the operations
determination of the net Third Partial Award do not constitute orders for the Under the SPA, RCBC undertakes, on the date of contract of Bankard for the
amount payable to payment of money. execution, to deposit, as downpayment, 20% of the periods indicated, and
Claimant or Respondent, Anent the claim of TPI that it was LHC which committed purchase price, or PhP357,353,880, in an escrow account. are complete in all
as the case may be. forum-shopping, suffice it to say that its bare allegations The escrowed amount, the SPA stated, should be released material respects.
167. In view of this the Tribunal are not sufficient to sustain the charge. to petitioners on an agreed-upon release date and the h. Except as disclosed in the
will make no orders for WHEREFORE, the Court RESOLVES to DISMISS the charges balance of the purchase price shall be delivered to the Disclosures, and except to the
payment in this Fifth of forum-shopping filed by both parties against each other. share buyers upon the fulfillment of certain conditions extent set forth or reserved in the
Partial Award. The No pronouncement as to costs. agreed upon, in the form of a manager's check. audited financial statements of
Tribunal will make a SO ORDERED. The other relevant provisions of the SPA are: Bankard as of 31 December 1999
number of declarations ||| (Transfield Phil., Inc. v. Luzon Hydro Corp., G.R. No. Section 5. Sellers' Representations and its unaudited financial
concerning the quantum 146717, [May 19, 2006], 523 PHIL 374-390) and Warranties. — statements as of 31 March 2000,
issues it has resolved in The SELLERS jointly and severally Bankard, as of such dates and up to
this Award together with SECOND DIVISION represent and warrant to the 31 May 2000, had and shall have no
the outstanding liability [G.R. No. 182248. December 18, 2008.] BUYER that: liabilities, omissions or mistakes in
issues. The declarations EQUITABLE PCI BANKING CORPO xxx xxx xxx its records which will have material
do not constitute RATION, 1 GEORGE L. GO, The Financial Condition of Bankard adverse effect on the net worth or
orders for the payment PATRICK D. GO, GENEVIEVE W.J. g. The audited financial statements financial condition of Bankard to
of money and are not GO, FERDINAND MARTIN G. of Bankard for the three (3) fiscal the extent of more than One
intended to be ROMUALDEZ, OSCAR P. LOPEZ- years ended December 31, 1997, Hundred Million Pesos
enforceable as such. DEE, RENE J. BUENAVENTURA, 1998 and 1999, and the unaudited (P100,000,000.00) in the aggregate.
They merely constitute GLORIA L. TAN-CLIMACO, ROGELIO financial statements for the first In the event such material adverse
amounts which will be S. CHUA, FEDERICO C. PASCUAL, quarter ended 31 March 2000, are effect on the net worth or financial
included in the Final LEOPOLDO S. VEROY, WILFRIDO V. fair and accurate, and complete in condition of Bankard exceeds One
Award and will be VERGARA, EDILBERTO V. JAVIER, all material respects, and have been Hundred Million Pesos
taken into account in ANTHONY F. CONWAY, ROMULAD prepared in accordance with (P100,000,000.00), the Purchase
determining the actual U. DY TANG, WALTER C. WESSMER, generally accepted accounting Price shall be reduced in
amount and ANTONIO N. principles consistently followed accordance with the following
formula:
Reduction in Purchase Price = X (the "Related Agreements"), the entitled to rescission having had ample opportunity and (e) The Claimant is not entitled to
multiplied by 226,460,000 Parties hereby agree that: reasonable time to file a claim against petitioners; RCBC is rescission of the SPA.
where xxx xxx xxx not entitled to its alternative prayer of damages, being (f) All other issues, including any
Amount by which negative e) Notwithstanding the provisions guilty of laches and failing to set out the details of the issue relating to costs, will be dealt
adjustment exceeds P100 Million of Sec. 7 of the Share Purchase breach as required under Sec. 7. with in a further or final award.
X = __________________________ (1.925) Agreement to the contrary, the Arbitration in the ICC-ICA proceeded after the formation of 15.2 A further Procedural Order
338,000,000 remedy for a breach of the the arbitration tribunal consisting of retired Justice will be necessary subsequent to the
xxx xxx xxx SELLERS' representation and Santiago M. Kapunan, nominated by petitioners; Neil delivery of this Partial Award to
Section 7. Remedies for Breach of warranty in Section 5 (h) of the Kaplan, RCBC's nominee; and Sir Ian Barker, appointed by deal with the determination of
Warranties. — Share Purchase Agreement shall be the ICC-ICA. quantum and in particular, whether
a. If any of the representations and available if the demand therefor After drawn out proceedings with each party alleging there should be an Expert
warranties of any or all of the is presented to the SELLERS in deviation and non-compliance by the other with arbitration appointed by the Tribunal under
SELLERS or the BUYER (the writing together with schedules rules, the tribunal, with Justice Kapunan dissenting, Article 20(4) of the ICC Rules to
"Defaulting Party") contained in and data to substantiate such rendered a Partial Award dated September 27, assist the Tribunal in this regard.
Sections 5 and 6 shall be found to demand, on or before 31 2007, 10 the dispositive portion of which states: 15.3 This Award is delivered by a
be untrue when made and/or as of December 2000. (Emphasis 15 AWARD AND DIRECTIONS majority of the Tribunal (Sir Ian
the Closing Date, the other added.) 15.1 The Tribunal makes the Barker and Mr. Kaplan). Justice
party, i.e., the BUYER if the Sometime in September 2000, RCBC had Bankard's following declarations by way of Kapunan is unable to agree with
Defaulting Party is any or all of the accounts audited, creating for the purpose an audit team Partial Award: the majority's conclusion on the
SELLERS and the SELLERS if the led by a certain Rubio, the Vice-President for Finance claim of estoppel brought by the
Defaulting Party is the BUYER of RCBC at the time. Rubio's conclusion was that the (a) The Claimant's claim is not respondents.
(hereinafter referred to as the warranty, as contained in Section 5 (h) of the SPA (simply time-barred under the provisions On the matter of prescription, the tribunal held
"Non-Defaulting Party") shall have Sec. 5 [h] hereinafter), was correct. of this SPA. that RCBC's claim is not time-barred, the claim properly
the right to require the Defaulting On December 28, 2000, RCBC paid the balance of the (b) The Claimant is not estopped by falling under the contemplation of Sec. 5 (g) and not Sec. 5
Party, at the latter's expense, to contract price. The corresponding deeds of sale for the its conduct or (h). As such, the tribunal concluded, RCBC's claim was filed
cure such breach, and/or seek shares in question were executed in January 2001. the equitable doctrine of laches within the three (3)-year period under Sec. 5 (g) and that
damages, by providing notice or Thereafter, in a letter of May 5, 2003, RCBC informed from pursuing its claim. the six (6)-month period under Sec. 5 (h) did not apply.
presenting a claim to the Defaulting petitioners of its having overpaid the purchase price of the (c) As detailed in the Partial Award, The tribunal also exonerated RCBC from laches, the latter
Party, reasonably specifying subject shares, claiming that there was an overstatement of the Claimant has established the having sought relief within the three (3)-year period
therein the particulars of the valuation of accounts amounting to PhP478 million, following breaches by the prescribed in the SPA. On the matter of estoppel suggested
breach. The foregoing remedies resulting in the overpayment of over PhP616 million. Respondents of clause 5(g) of the in petitioners' answer, the tribunal stated in par. 10.27 of
shall be available to the Non- Thus, RCBC claimed that petitioners violated their SPA: the Partial Award the following:
Defaulting Party only if the demand warranty, as sellers, embodied in Sec. 5 (g) of the SPA (Sec. i) the assets, revenue and 10.27 Clearly, there has to be both
therefor is presented in writing to 5 [g] hereinafter). net worth of Bankard an admission or representation by
the Defaulting Party within three Following unsuccessful attempts at settlement, RCBC, in were overstated by (in this case) the Claimant [RCBC],
(3) years from the Closing Date accordance with Sec. 10 of the SPA, filed a Request for reason of its policy on plus reliance upon it by (in this
except that the remedy for a breach Arbitration dated May 12, 2004 8 with the ICC-ICA. In the and recognition of Late case) the Respondents [herein
of the SELLERS' representation and request, RCBC charged Bankard with deviating from, Payment Fees; petitioners]. The Tribunal cannot
warrant in Section 5 (h) shall be contravening and not following generally accepted ii) reported receivables find as proved any
available only if the demand accounting principles and practices in maintaining their were higher than their admission/representation that the
therefor is presented to the books. Due to these improper accounting realizable values by Claimant was abandoning a 5(g)
Defaulting Party in writing together practices, RCBC alleged that both the audited and reason of the 'bucketing' claim, any reliance by the
with schedules and to substantiate unaudited financial statements of Bankard prior to the method, thus overstating Respondents on an admission, and
such demand, within six (6) months stock purchase were far from fair and accurate and, hence, Bankard's assets; any detriment to the Respondents
from the Closing Date. 6 CIaHDc violated the representations and warranties of petitioners and EaISTD such as would entitle them to have
On June 2, 2000, RCBC deposited the stipulated in the SPA. Per RCBC, its overpayment amounted to PhP556 iii) the relevant Bankard the Claimant deprived of the
downpayment amount in an escrow account after which it million. It thus prayed for the rescission of the SPA, statements were benefit of clause 5(g). These
was given full management and operational control of restitution of the purchase price, payment of actual inadequate and aspects of the claim for estoppels
Bankard. June 2, 2000 is also considered by the parties as damages in the amount of PhP573,132,110, legal interest misleading in that their are rejected. 11
the Closing Date referred to in the SPA. on the purchase price until actual restitution, moral disclosures caused Notably, the tribunal considered the rescission of the SPA
Thereafter, the parties executed an Amendment to Share damages, and litigation and attorney's fees. As alternative readers to be and ASPA as impracticable and "totally out of the
Purchase Agreement (ASPA) dated September 19, to rescission and restitution,RCBC prayed for damages in misinformed about question". 12
2000. 7 Its paragraph 2 (e) provided that: the amount of at least PhP809,796,092 plus legal Bankard's accounting In his Dissenting Opinion 13 which he submitted to and
2. Notwithstanding any provisions interest. DcCEHI policies on revenue and which was received on September 24, 2007 by the ICC-ICA,
to the contrary in the Share To the Request for Arbitration, petitioners filed an Answer receivables. Justice Kapunan stated the observation that RCBC's claim is
Purchase Agreement and/or any dated July 28, 2004, 9 denying RCBC's inculpatory (d) Subject to proof of loss the time-barred, falling as such claim did under Sec. 5 (h),
agreement, instrument or averments and setting up the following affirmative Claimant is entitled to damages for which prescribes a comparatively shorter prescriptive
document entered into or executed allegations: the period for filing of the asserted claim had the foregoing breaches. period, not 5 (g) as held by the majority of the tribunal, to
by the Parties in relation thereto already lapsed by force of Sec. 7 of the SPA; RCBC is not wit:
Claimant admits that the Claim is that it now assails. By paying the This petition seeks the review, As earlier recited, the ICC-ICA's Partial Award dated
for recovery of P431 million on balance of the purchase price reversal and setting aside of the September 27, 2007 was confirmed by the RTC in its first
account of alleged "overvaluation of without taking exception or orders Annexes A and B and, in lieu assailed order of January 8, 2008. Thereafter, the RTC, by
the net worth of Bankard", objecting to the accounting of them, it seeks judgment vacating order of March 17, 2008, denied petitioners' motion for
allegedly for "improper accounting practices disclosed through Mr. the arbitrators' liability award, reconsideration. Therefrom, petitioners came directly to
practices" resulting in "its book Rubio's review and the Information Annex C, on these grounds: this Court on a petition for review under Rule 45 of the
value per share as of 31 December Memorandum, Claimant is deemed (a) The trial court acted Rules of Court.
1999 [being] overstated." to have accepted such practices as contrary to law and This is a procedural miscue for petitioners who
Claimant's witness, Dean Echanis correctly reporting the 1999 net judicial authority in erroneously bypassed the Court of Appeals (CA) in pursuit
asserts that "the inadequate worth. . . . refusing to vacate the of its appeal. While this procedural gaffe has not been
provisioning for Bankard's doubtful xxx xxx xxx arbitral award, raised by RCBC, still we would be remiss in not pointing out
accounts result[ed] in an As last point, I note that my notwithstanding it was the proper mode of appeal from a decision of the RTC
overstatement of its December 31, colleagues invoke a principle that rendered in plain confirming, vacating, setting aside, modifying, or correcting
1999 total assets and net worth of for estoppels to apply there must disregard of the parties' an arbitral award.
by [sic] least P418.2 million." be positive indication that the right contract and applicable Rule 45 is not the remedy available to petitioners as the
In addition, Claimant's demand to sue was waived. I am of the view Philippine law, under proper mode of appeal assailing the decision of the RTC
letter addressed to the that there is no such principle which the claim in confirming as arbitral award is an appeal before the CA
Respondents alleged that "we under Philippine law. What is arbitration was pursuant to Sec. 46 of Republic Act No. (RA) 9285,
overpaid for the Shares to the applicable is the holding in Knecht indubitably time- otherwise known as the Alternative Dispute Resolution Act
extent of the impact of the said and in Coca-Cola that prior barred. aSCHcA of 2004, or completely, An Act to Institutionalize the Use of
overstatement on the Book Value knowledge of an unfavorable fact is (b) The trial court acted an Alternative Dispute Resolution System in the Philippines
per share". binding on the party who has such contrary to law and and to Establish the Office for Alternative Dispute Resolution,
These circumstances establish knowledge; "when the purchaser judicial authority in and for other Purposes, promulgated on April 2, 2004 and
beyond dispute that the Claim is proceeds to make investigations by refusing to vacate and in became effective on April 28, 2004 after its publication on
based on the alleged overstatement himself, and the vendor does confirming the arbitral April 13, 2004.
of the 1999 net worth of Bankard, nothing to prevent such award, notwithstanding In Korea Technologies Co., Ltd. v. Lerma, we explained, inter
which the parties relied on in investigation from being as that the arbitrators had alia, that the RTC decision of an assailed arbitral award is
setting the purchase price of the complete as the former might wish, plainly and admittedly appealable to the CA and may further be appealed to this
shares. Moreover, it is clear that the purchaser cannot later allege failed to accord Court, thus:
there was an overstatement that the vendor made false petitioners' due process Sec. 46 of RA 9285 provides for an
because of "improper accounting representations to him" (Cf. by denying them a appeal before the CA as the remedy
practices" which led Claimant to Songco v. Sellner, 37 Phil. 254 hearing on the basic of an aggrieved party in cases
overpay for the shares. cdasia citations omitted). factual matter upon where the RTC sets aside, rejects,
Ultimately, the Claim is one for Applied to this case, the Claimant which their liability is vacates, modifies, or corrects an
recovery of overpayment in the cannot seek relief on the basis that predicated. arbitral award, thus:
purchase price of the shares. . . . when it paid the purchase price in (c) The trial court
As to the issue of estoppel, Justice Kapunan stated: December 2000, it was unaware committed grave error in SEC. 46. Appeal from Court Decision
Moreover, Mr. Rubio's findings that the accounting practices that confirming the or Arbitral Awards. — A decision of
merely corroborated the went into the reporting of the 1999 arbitrators' award, the Regional Trial Court confirming,
disclosures made in the net worth as amounting to which held petitioners- vacating, setting aside, modifying or
Information Memorandum that P1,387,275,847 were not in sellers liable for an correcting an arbitral award may
Claimant received from the conformity with GAAP [generally alleged improper be appealed to the Court of
Respondents prior to the execution accepted accounting principles]. recording of accounts, Appeals in accordance with the
of the SPA. In this connection, I note (Emphasis added.) allegedly affecting the rules and procedure to be
that Bankard's policy on On October 26, 2007, RCBC filed with the RTC a Motion to value of the shares they promulgated by the Supreme Court.
provisioning and setting of Confirm Partial Award. On the same day, petitioners sold, notwithstanding The losing party who appeals from
allowances using the Bucketed countered with a Motion to Vacate the Partial Award. On that the respondent- the judgment of the court
Method and income recognition November 9, 2007, petitioners again filed a Motion to buyer knew before confirming an arbitral award shall
from AR/Principal, AR/Interest and Suspend and Inhibit Barker and Kaplan. contracting that the be required by the appellate court
AR/LPFs were disclosed in the On January 8, 2008, the RTC issued the first assailed order accounts were kept in to post a counterbond executed in
Information Memorandum. Thus, confirming the Partial Award and denying the adverted the manner complained favor of the prevailing party equal
these alleged improper accounting separate motions to vacate and to suspend and inhibit. of, and in fact ratified to the amount of the award in
practices were known to the From this order, petitioners sought reconsideration, but and adopted the accordance with the rules to be
Claimant even prior to the their motion was denied by the RTC in the equally assailed questioned accounting promulgated by the Supreme Court.
execution of the SPA. second order of March 17, 2008. practice and policies. 14 Thereafter, the CA decision may
Thus, when Claimant paid the From the assailed orders, petitioners came directly to this The Court's Ruling further be appealed or reviewed
balance of the purchase price, it did Court through this petition for review. The petition must be denied. before this Court through a petition
so with full knowledge of these The Issues On Procedural Misstep of Direct Appeal to This for review under Rule 45 of the
accounting practices of Bankard Court Rules of Court. 15
It is clear from the factual antecedents that RA 9285 applies conformity thereto. Thus, Sections must clearly and unequivocally violate an established legal quarter ended
to the instant case. This law was already effective at the 24 and 25 of the Arbitration precedent. Anything less would not suffice. 31 March
time the arbitral proceedings were commenced Lawprovide grounds for vacating, In the present case, petitioners, in a bid to establish that the 2000,present
by RCBC through a request for arbitration filed before the rescinding or modifying an arbitral award was issued in manifest disregard of the law, a fair and
ICC-ICA on May 12, 2004. Besides, the assailed arbitration award. Where the allege that the Partial Award violated the principles of accurate
confirmation order of the RTC was issued on March 17, conditions described in Articles prescription, due process, and estoppel. A review of statement as
2008. Thus, petitioners clearly took the wrong mode of 2038, 2039 and 2040 of the Civil petitioners' arguments would, however, show that their of those
appeal and the instant petition can be outright rejected and Code applicable to compromises arguments are bereft of merit. Thus, the Partial Award dates, of
dismissed. HDIaET and arbitration are attendant, the dated September 27, 2007 cannot be vacated. Bankard's
Even if we entertain the petition, the outcome will be the arbitration award may also be RCBC's Claim Is Not Time-Barred financial
same. annulled. Petitioners argue that RCBC's claim under Sec. 5 (g) is condition
The Court Will Not Overturn an Arbitral Award xxx xxx xxx based on overvaluation of Bankard's revenues, assets, and and of all its
Unless it Was Made in Manifest Disregard of the Finally, it should be stressed that net worth, hence, for price reduction falling under Sec. 5 assets and
Law while a court is precluded from (h), in which case it was belatedly filed, forRCBC presented liabilities,
In Asset Privatization Trust v. Court of Appeals, 16 the Court overturning an award for errors in the claim to petitioners on May 5, 2003, when the period and is
passed on similar issues as the ones tendered in the instant determination of factual issues, for presenting it under Sec. 5 (h) expired on December 31, complete in
petition. In that case, the arbitration committee issued an nevertheless, if an examination of 2000. As a counterpoint, RCBC asserts that its claim clearly all material
arbitral award which the trial court, upon due proceedings, the record reveals no support comes under Sec. 5 (g) in relation to Sec. 7 which thus gave respects; and
confirmed despite the opposition of the losing party. whatever for the arbitrators' it three (3) years from the closing date of June 2, 2000, or ii) the statements of
Motions for reconsideration by the losing party were determinations, their award must until June 1, 2003, within which to make its Bankard's
denied. An appeal interposed by the losing party to the CA be vacated. In the same manner, an claim. RCBC contends having acted within the required profit and
was denied due course. On appeal to this Court, we award must be vacated if it was period, having presented its claim-demand on May 5, loss accounts
established the parameters by which an arbitral award may made in "manifest disregard of 2003. TcIAHS for the fiscal
be set aside, to wit: the law." 17 (Emphasis To make clear the issue at hand, we highlight the pertinent years 1996 to
As a rule, the award of an supplied.)cADEHI portions of Secs. 5 (g), 5 (h), and 7 bearing on what 1999, as
arbitrator cannot be set aside for Following Asset Privatization Trust, errors in law and fact petitioners warranted relative to the financial condition of prepared and
mere errors of judgment either would not generally justify the reversal of an arbitral Bankard and the remedies available to RCBCin case of certified by
as to the law or as to the facts. award. A party asking for the vacation of an arbitral award breach of warranty: SGV, and the
Courts are without power to must show that any of the grounds for vacating, rescinding, g. The audited financial unaudited
amend or overrule merely or modifying an award are present or that the arbitral statements of Bankard profit and
because of disagreement with award was made in manifest disregard of the law. for the three (3) fiscal loss accounts
matters of law or facts Otherwise, the Court is duty-bound to uphold an arbitral years ended December for the first
determined by the arbitrators. award. 31, 1997, 1998 and quarter
They will not review the findings The instant petition dwells on the alleged manifest 1999, and the ended 31
of law and fact contained in an disregard of the law by the ICC-ICA. unaudited financial March 2000,
award, and will not undertake to The US case of Merrill Lynch, Pierce, Fenner & Smith, Inc. v. statements for the first fairly and
substitute their judgment for Jaros 18 expounded on the phrase "manifest disregard of quarter ended 31 accurately
that of the arbitrators, since any the law" in the following wise: March 2000, are fair present the
other rule would make an award This court has emphasized that and accurate, and results of the
the commencement, not the end, manifest disregard of the law is a complete in all operations of
of litigation. Errors of law and very narrow standard of material respects, and Bankard for
fact, or an erroneous decision of review.Anaconda Co. v. District have been prepared in the periods
matters submitted to the Lodge No. 27, 693 F.2d 35 (6th Cir. accordance with indicated,
judgment of the arbitrators, are 1982). A mere error in generally accepted and are
insufficient to invalidate an interpretation or application of the accounting complete in
award fairly and honestly made. law is insufficient. Anaconda, 693 principlesconsistently all material
Judicial review of an arbitration F.2d at 37-38. Rather, the decision followed throughout the respects.
is, thus, more limited than must fly in the face of clearly period indicated and: h. Except as disclosed in the
judicial review of a trial. established legal precedent. When i) the balance sheet of Disclosures, and except
Nonetheless, the arbitrators' faced with questions of law, an Bankard as of to the extent set forth or
awards is not absolute and without arbitration panel does not act in 31 December reserved in the audited
exceptions. The arbitrators cannot manifest disregard of the law 1999, as financial statements of
resolve issues beyond the scope of unless (1) the applicable legal prepared and Bankard as of 31
the submission agreement. The principle is clearly defined and not certified by December 1999 and its
parties to such an agreement are subject to reasonable debate; and SGV & Co. unaudited financial
bound by the arbitrators' award (2) the arbitrators refused to heed ("SGV"), and statements for the first
only to the extent and in the that legal principle. the unaudited quarter ended 31 March
manner prescribed by the contract Thus, to justify the vacation of an arbitral award on account balance sheet 2000, Bankard, as of
and only if the award is rendered in of "manifest disregard of the law", the arbiter's findings for the first such dates and up to 31
May 2000, had and in writing together with schedules omissions and mistakes on the We cannot sustain petitioners' position.
shall have no liabilities, and data to substantiate such financial statements as of 31 It cannot be disputed that an overstatement or
omissions or mistakes demand, within six (6) months December 1999 and the UFS as of overvaluation of Bankard's financial condition as of closing
in its records which from the Closing Date. (Emphasis 31 May 2000, provided that the date translates into a misrepresentation not only of the
will have a material supplied.) material adverse effect on the net accuracy and truthfulness of the financial statements under
adverse effect on the Before we address the issue put forward by petitioners, worth exceeds PhP100M and the Sec. 5 (g), but also as to Bankard's actual net worth
net worth or financial there is a necessity to determine the nature and application written demand is presented mentioned in Sec. 5 (h). Overvaluation presupposes
condition of Bankard of the reliefs provided under Sec. 5 (g) and Sec. 5 (h) in within six (6) months from closing mistakes in the entries in the financial statements and
to the extent of more conjunction with Sec. 7, thus: date (extended to 31 December amounts to a breach of petitioners' representations and
than One Hundred 2000); and warranties under Sec. 5. Consequently, such error in the
Million Pesos (1) The relief under Sec. 5 (h) is specifically for price 2. An action to cure the breach like financial statements would impact on the figure
(P100,000,000.00) in reduction as said section explicitly states that the specific performance and/or representing the net worth of Bankard as of closing date.
the aggregate. In the "Purchase Price shall be reduced in accordance with the damages under Sec. 5(g) based on An overvaluation means that the financial condition of
event such material following formula . . . ." In addition, Sec. 7 gives the Bankard's breach of warranty Bankard as of closing date, i.e., June 2, 2000, is overstated, a
adverse effect on the net aggrieved party the right to ask damages based on the involving its AFS for the three (3) situation that will definitely result in a breach of EPCIB's
worth or financial stipulation that the non-defaulting party "shall have the fiscal years ending 31 December representations and warranties.
condition of Bankard right to require the Defaulting Party, at the latter's expense, 1997, 1998, and 1999 and the UFS A scrutiny of Sec. 5 (g) and Sec. 5 (h) in relation to Sec. 7 of
exceeds One Hundred to cure such breach and/or seek damages." for the first quarter ending 31 the SPA would indicate the following remedies available
Million Pesos On the other hand, the remedy under Sec. 5 (g) in March 2000 provided that the to RCBC should it be discovered, as of closing date, that
(P100,000,000.00), the conjunction with Sec. 7 can include specific performance, written demand shall be presented there is overvaluation which will constitute breach of the
Purchase Price shall be damages, and other reliefs excluding price reduction. within three (3) years from closing warranty clause under either Sec. 5 (g) or (h), to wit:
reduced in accordance (2) Sec. 5 (g) warranty covers the audited financial date. (1) An overvaluation of Bankard's actual financial condition
with the following statements (AFS) for the three (3) years ending December Has RCBC the option to choose between Sec. 5 (g) or Sec. 5 as of closing date taints the veracity and accuracy of the
formula: IAcTaC 31, 1997 to 1999 and the unaudited financial statements (h)? AFS for 1997, 1998, and 1999 and the UFS for the first
xxx xxx xxx (UFS) for the first quarter ending March 31, 2000. On the The answer is yes. Sec. 5 and Sec. 7 are clear that it is quarter of 2000 and is an actionable breach of petitioners'
Section 7. Remedies for Breach of other hand, the Sec. 5 (h) warranty refers only to the AFS discretionary on the aggrieved parties to avail themselves warranties under Sec. 5 (g). acCDSH
Warranties. — for the year ending December 31, 1999 and the UFS up to of any remedy mentioned above. They may choose one and (2) An overvaluation of Bankard's financial condition as of
If any of the representations and May 31, 2000. It is undenied that Sec. 5 (h) refers to price dispense with the other. Of course, the relief for price May 31, 2000, encompassing the warranted financial
warranties of any or all of the reduction as it covers "only the most up-to-date audited reduction under Sec. 5 (h) will have to conform to the condition as of December 31, 1999 through the AFS for
SELLERS or the BUYER (the and unaudited financial statements upon which the price prerequisites and time frame of six (6) months; otherwise, 1999 and as of March 31, 2000 through the UFS for the first
"Defaulting Party") contained in must have been based." 19 it is waived. quarter of 2000, is a breach of petitioners' representations
Sections 5 and 6 shall be found to (3) Under Sec. 5 (h), the responsibility of petitioners for its Preliminarily, petitioners' basic posture that RCBC's claim and warranties under Sec. 5 (h).
be untrue when made and/or as of warranty shall exclude the disclosures and reservations is for the recovery of overpayment is specious. The records Thus, RCBC has two distinct alternative remedies in case of
the Closing Date, the other made in AFS of Bankard as of December 31, 1999 and its show that in its Request for Arbitration dated May 12, an overvaluation of Bankard's financial condition. It may
party, i.e., the BUYER if the UFS up to May 31, 2000. No such exclusions were made 2004, RCBC prayed for the rescission of the SPA, restitution invoke Sec. 5 (h) when the conditions of the threshold
Defaulting is any of the SELLERS under Sec. 5 (g) with respect to the warranty of petitioners of the whole purchase price, and damages not for reduction aggregate overvaluation and the claim made within the six-
and the SELLERS if the Defaulting in the AFS and UFS of Bankard. of price or for the return of any overpayment. Even in its month time-bar are present. In the alternative, it may
Party is the BUYER (hereinafter (4) Sec. 5 (h) gives relief only if there is material adverse May 5, 2000 letter, 21 RCBC did not ask for the recovery of invoke Sec. 5 (g) when it finds that a claim for "curing the
referred to as the "Non-Defaulting effect in the net worth in excess of PhP100 million and it any overpayment or reduction of price, merely stating in it breach" and/or damages will be more advantageous to its
Party") shall have the right to provides a formula for price reduction. 20 On the other that the accounts of Bankard, as reflected in its AFS for interests provided it is filed within three (3) years from
require the Defaulting Party, at hand, Sec. 5 (g) can be the basis for remedies like specific 1999, were overstated which, necessarily, resulted in an closing date. Since it has two remedies, RCBC may opt to
the latter's expense, to cure such performance, damages, and other reliefs, except price overpayment situation. RCBC was emphatic and exercise either one. Of course, the exercise of either one
breach, and/or seek damages, by reduction, even if the overvaluation is less or above unequivocal that petitioners violated their warranty will preclude the other.
providing notice or presenting a PhP100 million and there is no formula for computation of covered by Sec. 5 (g) of the SPA. Moreover, the language employed in Sec. 5 (g) and Sec. 5
claim to the Defaulting Party, damages. It is thus evident that RCBC did not avail itself of the option (h) is clear and bereft of any ambiguity. The SPA's
reasonably specifying therein the (5) Under Sec. 7, the aggrieved party shall present its under Sec. 5 (h), i.e., for price reduction or the return of any stipulations reveal that the non-use or waiver of Sec. 5 (h)
particulars of the breach. The written demand to the defaulting party within three (3) overpayment arising from the overvaluation of Bankard's does not preclude RCBC from availing itself of the second
foregoing remedies shall be years from closing date. Under Sec. 5 (h), the written financial condition. Clearly, RCBCinvoked Sec. 5 (g) to claim relief under Sec. 5 (g). Article 1370 of the Civil Code is
available to the Non-Defaulting demand shall be presented within six (6) months from damages from petitioners which is one of the alternative explicit that "if terms of a contract are clear and leave no
Party only if the demand therefor closing date. In accordance with par. 2 (c) of the ASPA, the reliefs granted under Sec. 7 in addition to rescission and doubt upon the intention of the contracting parties the
is presented in writing to the deadline to file the demand under Sec. 5 (h) was extended restitution of purchase price. literal meaning of its stipulations shall control." Since the
Defaulting Party within three (3) to December 31, 2000. Petitioners do not deny that RCBC formally filed its claim terms of a contract have the force of law between the
years from the Closing Date, From the above determination, it becomes clear that the under Sec. 5 (g) which is anchored on the material parties, 22 then the parties must respect and strictly
except that the remedy for a aggrieved party is entitled to two (2) separate alternative overstatement or overvaluation of Bankard's revenues, conform to it. Lastly, it is a long held cardinal rule that
breach of the SELLERS' remedies under Secs. 5 and 7 of the SPA, thus: CAHaST assets, and net worth and, hence, the overstatement of the when the terms of an agreement are reduced to writing, it
representation and warranty in 1. A claim for price reduction under purchase price. They, however, assert that such claim for is deemed to contain all the terms agreed upon and no
Section 5 (h) shall be available Sec. 5(h) and/or damages based on overpayment is actually a claim under Sec. 5 (h) of the SPA evidence of such terms can be admitted other than the
only if the demand therefor is the breach of warranty by Bankard for price reduction which it forfeited after December 31, contents of the agreement itself. 23 Since the SPA is
presented to the Defaulting Party on the absence of liabilities, 2000.
unambiguous, and petitioners failed to adduce evidence to However, since the parties completeness of the AFS and also a breach of the warranty Anent the use but non-presentation of the source
the contrary, then they are legally bound to comply with it. explicitly included Section 5(h) in under Sec. 5 (g). Thus, the subject of the warranty in Sec. 5 documents as the jumping board for a claim of denial of
Petitioners agreed ultimately to the stipulation that: their SPA, which assures the (h) is also covered by the warranty in Sec. 5 (g), and Sec. 5 due process, petitioners cite Compania Maritima v. Allied
Each of the representations and Claimant that there were no (h) cannot exclude such breach from the ambit of Sec. 5 (g). Free Worker's Union. 30 It may be stated, however, that
warranties of the SELLERS is "omissions or mistakes in the There is no need to rely on Sec. 12, Rule 130 of the Rules of such case is not on all fours with the instant case and,
deemed to be a separate records" that would misstate the Court for both Sec. 5 (g) and Sec. 5 (h) as alternative therefore, cannot be applied here considering that it does
representation and warranty, 1999 net worth account, I am left remedies are of equal footing and one need not categorize not involve an administrative body exercising quasi-judicial
and the BUYER has placed complete with no other conclusion but that one section as a general provision and the other a function but rather the regular court.
reliance thereon in agreeing to the the accuracy of the net worth particular provision. In a catena of cases, we have ruled that "[t]he essence of
Purchase Price and in entering into was the subject of the warranty More importantly, a scrutiny of the four corners of the SPA due process is the opportunity to be heard. What the law
this Agreement. The in Section 5(h), while the does not explicitly reveal any stipulation nor even prohibits is not the absence of previous notice but the
representations and warranties of accuracy or correctness of impliedly that the parties intended to limit the scope of the absolute absence thereof and the lack of opportunity to be
the SELLERS shall be correct as of the other accounts that did not warranty in Sec. 5 (g) or gave priority to Sec. 5 (h) over Sec. heard." 31
the date of this Agreement and as of bear on, or affect Bankard's net 5 (g). We also explained in Lastimoso v. Asayo that "[d]ue process
the Closing Date with the same worth, were guaranteed by The arbitral tribunal did not find any legal basis in the SPA in an administrative context does not require trial type
force and effect as though such Section 5(g). that Sec. 5 (h) "somehow cuts down" the scope of Sec. 5 (g), proceedings similar to those in courts of justice. Where an
representations and warranties had xxx xxx xxx thus: opportunity to be heard either through oral arguments or
been made as of the Closing This manner of reconciling the two 9.10 In the opinion of the through pleadings is accorded, there is no denial of
Date.24 (Emphasis supplied.) provisions is consistent with the Tribunal, there is nothing in the procedural due process." 32 ScAHTI
The Court sustains the finding in the Partial Award that Sec. principle in Rule 130, Section 12 of wording used in the SPA to give Were petitioners afforded the opportunity to refute the
5 (g) of the SPA is a free standing warranty and not the Rules of Court that "when a priority to one warranty over the summaries and pieces of evidence submitted
constricted by Sec. 5 (h) of the said agreement. general and a particular provision other. There is nothing in the byRCBC which became the bases of the experts' opinion?
Upon the foregoing premises and in the light of the are inconsistent, the latter is wording used to indicate that the The answer is in the affirmative.
undisputed facts on record, RCBC's claim for rescission of paramount to the former. . . [so] a parties intended to limit the We recall the events that culminated in the issuance of the
the SPA and damages due to overvaluation of Bankard's particular intent will control a scope of the warranty in 5(g). If it challenged Partial Award, thus:
accounts was properly for a breach of the warranty under general one that is inconsistent be contended that, on a true On May 17, 2004, the ICC-ICA received the Request for
Sec. 5 (g) and was not time-barred. To with it." This is also consistent with construction of the two warranties, Arbitration dated May 12, 2004 from RCBC seeking
repeat, RCBC presented its written claim on May 5, 2003, or existing doctrines on statutory 5(h) somehow cuts down the scope rescission of the SPA and restitution of all the amounts paid
a little less than a month before closing date, well within construction, the application of of 5(g), the Tribunal can find no by RCBC to petitioners, with actual and moral damages,
the three (3)-year prescriptive period provided under Sec. which is illustrated in the case justification for such conclusion interest, and costs of suit.
7 for the exercise of the right provided under Sec. 5 of Commissioner of Customs vs. on the wording used. On August 8, 2004, petitioners filed an Answer to the
(g). STaHIC Court of Tax Appeals, G.R. No. L- Furthermore, the Tribunal is of the Request for Arbitration dated July 28, 2004, setting up a
Petitioners bemoan the fact that "the arbitrators' liability 41861, dated March 23, 1987 . . . . view that very clear words would counterclaim for USD300,000 for actual and exemplary
award (a) disregarded the 6-month contractual limitation xxx xxx xxx be needed to cut down the scope of damages.
for RCBC's 'overprice' claim, and [b] substituted in its The Claim is for recovery of the the 5(g) warranty. 28 RCBC filed its Reply 33 dated August 31, 2004 to
place the 3-year limitation under the contract for other excess price by way of actual The Court upholds the conclusion of the tribunal and rules petitioners' Answer to the Request for Arbitration.
claims," 25 adopting in that regard the interpretation of damages. 27 . . . (Emphasis that the claim of RCBC under Sec. 5 (g) is not time- On October 4, 2004, the parties entered into the Terms of
the SPA made by arbitral tribunal member, retired Justice supplied.)AHDTIE barred. HTDCAS Reference. 34 At the same time, the chairperson of the
Kapunan, in his Dissenting Opinion, in which he asserted: Justice Kapunan noted that without Sec. 5 (h), RCBC's claim Petitioners Were Not Denied Due Process arbitral tribunal issued a provisional timetable 35 for the
would fall under Sec. 5 (g), impliedly admitting that both Petitioners impute on RCBC the act of creating summaries arbitration.
Ultimately, the Claim is one for provisions could very well cover RCBC's claim, except that of the accounts of Bankard which "in turn were used by its On October 25, 2004, as previously agreed upon in the
recovery of overpayment in the Sec. 5 (h) excludes the situation contemplated in it from the experts to conclude that Bankard improperly recorded its meeting on October 4, 2004, petitioners filed a Motion to
purchase price of the shares. And it general terms of Sec. 5 (g). receivables and committed material deviations from GAAP Dismiss 36 while RCBC filed a "Claimant's Position Paper
is in this context, that I respectfully Such view is incorrect. requirements." 29 Later, petitioners would assert that "the (Re: [Petitioners'] Assertion
submit that Section 5 (h) and not While it is true that Sec. 5 (h), as couched, is a warranty on arbitrators' partial award admitted and used the that RCBCCAPITAL CORPORATION's Present Claim Is Time
Section 5 (g), applies to the present the accuracy of the Bankard's net worth while Sec. 5 (g), as Summaries as evidence, and held on the basis of the Barred)." 37
controversy. 26 also couched, is a warranty on the veracity, accuracy, and 'information' contained in them that petitioners were in Then, the tribunal issued Procedural Order No. 1 dated
xxx xxx xxx completeness of the AFS in all material respects as breach of their warranty in GAAP compliance." January 12, 2005, 38 denying the motion to dismiss and
True, without Section 5(h), the prepared in accordance with generally accepted accounting To petitioners, the ICC-ICA's use of such summaries but setting the initial hearing of the case on April 11, 2005.
Claim for price recovery would fall principles consistently followed throughout the period without presenting the source documents violates their In a letter dated February 9, 2005, 39 petitioners requested
under Section 5(g). The recovery of audited, yet both warranties boil down to the same thing right to due process. Pressing the point, petitioners had that the tribunal direct RCBC to produce certain
the pecuniary loss of the Claimant and stem from the same accounts as summarized in the moved, but to no avail, for the exclusion of the said documents. At the same time, petitioners sought the
in the form of the excess price paid AFS. Since the net worth is the balance of Bankard's summaries. Petitioners allege that they had reserved the postponement of the hearing on April 11, 2005 to March
would be in the nature of a claim assets less its liabilities, it necessarily includes all the right to cross-examine the witnesses of RCBCwho testified 21, 2005, in light of their own request.
for actual damages by way of accounts under the AFS. In short, there are no accounts on the summaries, pending the resolution of their motion On February 11, 2005, petitioners received RCBC's brief of
compensation. In that situation, all in the AFS that do not bear on the net worth of to exclude. But, according to them, they were effectively evidence and supporting documentation in accordance
the accounts in the 1999 financial Bankard. Moreover, as earlier elucidated, any denied the right to cross-examine RCBC's witnesses when with the provisional timetable. 40 In the brief of
statements would be the subject of overvaluation of Bankard's net worth is necessarily a the ICC-ICA admitted the summaries of RCBC as evidence. evidence, RCBC provided summaries of the accounts of
the warranty in Section 5(g). misrepresentation of the veracity, accuracy, and Petitioners' position is bereft of merit. Bankard, which petitioners now question. aSTAHD
Later, in a letter dated February 14, 2005, 41 petitioners that RCBC allegedly did not cooperate in providing data directing the tribunal to reset the hearing for April 21 and Later, petitioners moved to vacate the said award before
complained to the tribunal with regard to their lack of that would facilitate their verification. Petitioners 24, 2006. the RTC. Such motion was denied by the trial court in the
access to RCBC's external auditor. Petitioners sought an specifically mentioned the following data: (1) list of names Thereafter, in a letter dated January 18, first assailed order dated January 8, 2008. Petitioners then
audit by an accounting firm of the records of Bankard with of cardholders whose accounts are sources of data 2006, 57 petitioners wrote the tribunal requesting moved for a reconsideration of such order, but their motion
respect to the claims of RCBC. By virtue of such requests, gathered or calculated in the summaries; (2) references to that RCBC be directed to: (1) provide petitioners with was also denied in the second assailed order dated March
petitioners also sought a rescheduling of the provisional the basic cardholder documents from which such data were information identifying the journal vouchers and other 17, 2008.
timetable, despite their earlier assurance to the tribunal collected; and (3) access to the underlying cardholder supporting documents that RCBC used to arrive at the The foregoing events unequivocally demonstrate ample
that if they received the documents that they requested on documents at a time and under conditions mutually figures set out in the summaries and other relevant opportunity for petitioners to verify and
February 9, 2005 on or before February 21, 2005, they convenient to the parties. As regards the compact discs of information necessary to enable them to reconstruct examineRCBC's summaries, accounting records, and
would abide by the provisional timetable. information provided to petitioners, it is claimed that such and/or otherwise understand the figures or amounts in reports. The pleadings reveal that RCBC granted
Thereafter, the tribunal issued Procedural Order No. 2 information could not be accessed as the software each summary; and (2) submit to petitioners the requested petitioners' requests for production of documents and
dated February 18, 2005, 42 in which it allowed the necessary for the handling of the data could not be made pieces of information as soon as these are or have become accounting records. More so, they had more than three (3)
discovery and inspection of the documents requested by immediately available to them. available, or in any case not later than five days. years to prepare for their defense after RCBC's submission
petitioners that were also scheduled on February 18, 2005. In Procedural Order No. 3 dated March 11, 2005, 47 the In response to such letter, RCBC addressed a letter dated of its brief of evidence. Finally, it must be emphasized that
The request for an audit of Bankard's accounts was denied initial hearing was moved to June 13 to 16, 2005, January 31, 2006 58 to the tribunal claiming that the pieces petitioners had the opportunity to appeal the Partial Award
without prejudice to the conduct of such audit during the considering that petitioners failed to pay the advance on of information that petitioners requested are already to the RTC, which they in fact did. Later, petitioners even
course of the hearings. Consequently, the tribunal amended costs of the tribunal. known to petitioners considering that RCBCmerely moved for the reconsideration of the denial of their appeal.
the provisional timetable, extending the deadline for On March 23, 2005, RCBC paid the balance of the advance maintained the systems that they inherited when it bought Having been able to appeal and move for a reconsideration
petitioners to file their brief of evidence and documents to on costs. 48 Bankard from petitioners. RCBC added that the documents of the assailed rulings, petitioners cannot claim a denial of
March 21, 2005. The date of the initial hearing, however, On April 22, 2005, petitioners sent the tribunal a that EPCIB originally transmitted to it when RCBC bought due process. 65 THIECD
remained on April 11, 2005. letter, 49 requesting for the postponement of the hearing Bankard were all being made available to petitioners; thus, Petitioners' right to due process was not breached.
On February 18, 2005, petitioners were furnished the scheduled on June 13 to 16, 2005 on the ground that they any missing supporting documents from these files were As regards petitioners' claim that its right to due process
documents that they requested RCBC. 43 The parties also could not submit their witness' statements due to the never transmitted to them in the first place. was violated when they were allegedly denied the right to
agreed to meet again on February 23, 2005 to provide volume of data that they acquired from RCBC. Later, petitioners sent to the tribunal a letter dated cross-examine RCBC's witnesses, their claim is also bereft
petitioners with a "walk-through" of Bankard's Statistical In a letter dated April 25, 2005, 50 petitioners demanded February 10, 2006, 59 asking that it direct RCBC to provide of merit.
Analysis System and to provide petitioners with a soft copy from RCBC that they be allowed to examine the journal petitioners with the supporting documents Sec. 15 of RA 876 or the Arbitration Law provides that:
of all of Bankard's cardholders. 44 vouchers earlier made available to them during the that RCBC mentioned in its letter dated January 31, 2006. Section 15. Hearing by arbitrators.
February 23, 2005 meeting. This demand was answered Petitioners wrote that should RCBC fail to present such — Arbitrators may, at the
During the February 23, 2005 meeting, EPCIB's by RCBC in a letter dated April 26, 2005, 51 stating that documents, RCBC's summaries should be excluded from commencement of the hearing, ask
counsels/representatives were accompanied to the such demand was being denied by virtue of Procedural the records. SIEHcA both parties for brief statements of
Bankard's Credit-MIS Group. There, Bankard's Order No. 2, in which it was ruled that further requests for In a letter dated March 10, 2006, 60 petitioners requested the issues in controversy and/or an
representative, Amor Lazaro, described and explained to discovery would not be made except with leave of the that they be given an additional period of at least 47 days agreed statement of facts.
petitioners' representatives the steps involved in procuring chairperson of the tribunal. within which to submit their evidence-in-chief with the Thereafter the parties may offer
and translating raw data on customer transactions. Lazaro In Procedural Order No. 4, 52 the tribunal granted corresponding request for the cancellation of the hearing such evidence as they desire, and
explained that Bankard captures cardholder information petitioners' request for the postponement of the hearing on on April 24, 2006. Petitioners submit that should such shall produce such additional
and transactions through encoding or electronic data June 13, 2005 and rescheduled it to November 21, 2005 in request be denied, RCBC's summaries should be excluded evidence as the arbitrators shall
capture. Thereafter, such data are transmitted to its main light of the pending motions filed by EPCIB with the RTC in from the records. require or deem necessary to an
credit card administration system. Such raw data are then Makati City. CHTcSE On April 6, 2006, petitioners filed their arbitration briefs understanding and determination
sent to Bankard's Information Technology Group. Using a On July 29, 2005, the parties held a meeting wherein it was and witness statements. By way of reply, on April 17, of the dispute. The arbitrators
proprietary software called SAS, the raw data is then agreed that petitioners would be provided with hard and 2006, RCBC submitted Volumes IV and V of its exhibits and shall be the sole judge of the
converted into SAS files which may be viewed, handled, and soft copies of the inventory of the journal vouchers earlier Volume II of its evidence-in-chief. 61 relevancy and materiality of the
converted into Excel files for reporting purposes. During presented to its representatives, while making the journal On April 18, 2006, petitioners requested the tribunal that evidence offered or produced,
the walk-through, petitioners' representatives asked vouchers available to petitioners for two weeks for they be allowed to file rejoinder briefs, or otherwise and shall not be bound to
questions which were answered in detail by Lazaro. examination and photocopying. 53 exclude RCBC's reply brief and witness statements. 62 In conform to the Rules of Court
At the same time, another Bankard representative, Felix L. On September 2, 2005, petitioners applied for the this request, petitioners also requested that the hearing set pertaining to evidence.
Sincoñegue, accompanied two auditors/representatives of postponement of the November 21, 2005 hearing due to for April 24, 2006 be moved. These requests were denied. Arbitrators shall receive as
petitioners to examine the journal vouchers and supporting the following: (1) petitioners had earlier filed a motion Consequently, on April 24 to 27, 2006, the arbitral tribunal exhibits in evidence any
documents of Bankard consisting of several boxes. The dated August 11, 2005 with the RTC, in which the issue of conducted hearings on the case. 63 document which the parties may
auditors randomly sifted through the boxes which they had whether the non-Filipino members of the tribunal were On December 4, 2006, petitioners submitted rejoinder wish to submit and the exhibits
earlier requested to be inspected. DAaIHT illegally practicing law in the Philippines by hearing their affidavits, raising new issues for the first time, to shall be properly identified at
In addition, petitioners were furnished with an electronic case, which was still pending; and (2) the gathering and which RCBC submitted Volume III of its evidence-in-chief the time of submission. All
copy of the details of all cardholders, including relevant processing of the data and documents made available by way of a reply. exhibits shall remain in the custody
data for aging of receivables for the years 2000 to 2003, as by RCBC would require 26 weeks. 54 Such application was On January 16, 2007, both parties simultaneously of the Clerk of Court during the
well as data containing details of written-off accounts from denied by the tribunal in Procedural Order No. 5 dated submitted their memoranda. On January 26, 2007, both course of the arbitration and shall
1999 to March 2000 contained in compact discs. 45 September 16, 2005. 55 parties simultaneously filed their reply to the other's be returned to the parties at the
On March 4, 2005, petitioners sent a letter 46 to the On October 21, 2005, the tribunal issued Procedural Order memorandum. 64 time the award is made. The
tribunal requesting for a postponement of the April 11, No. 6, 56 postponing the November 21, 2005 hearing by Thus, on September 27, 2007, the Partial Award was arbitrators may make an ocular
2005 hearing of the case. Petitioners claim that they could virtue of an order issued by the RTC in Makati City rendered by the Tribunal. inspection of any matter or
not confirm the summaries prepared by RCBC, considering premises which are in dispute, but
such inspection shall be made only ruling. It does not require trial- And later in Velez v. De Vera, the Court En Banc expounded thatRCBC continued with Bankard's accounting policies
in the presence of all parties to the type proceedings similar to those in on the above rulings, adding that in administrative and practices and found them to conform to the generally
arbitration, unless any party who the courts of justice. Where proceedings, cross-examination is not indispensable, thus: accepted accounting principles, contrary
shall have received notice thereof opportunity to be heard either Due process of law in to RCBC's allegations.
fails to appear, in which event such through oral arguments or through administrative cases is not identical It also bears stating that in his dissent, retired Justice
inspection shall be made in the pleadings is accorded, there is no with "judicial process" for a trial in Kapunan, an arbitral tribunal member, argued that
absence of such party. (Emphasis denial of procedural due court is not always essential to due Bankard's accounting practices were disclosed in the
supplied.) process. 67 (Emphasis process. While a day in court is a information memorandum provided to RCBC;
supplied.) ITCcAD matter of right in judicial hence,RCBC was supposed to know such accounting
The well-settled rule is that administrative agencies Citing Vertudes v. Buenaflor, petitioners also cry denial of proceedings, it is otherwise in practices and to have accepted their propriety even before
exercising quasi-judicial powers shall not be fettered by the due process when they were allegedly denied the right to administrative proceedings since the execution of the SPA. He then argued that when it paid
rigid technicalities of procedure, albeit they are, at all times cross-examine the witnesses presented by RCBC. It is true they rest upon different principles. the purchase price on December 29, 2000, RCBCcould no
required, to adhere to the basic concepts of fair play. The that in Vertudes, we stated: "The right of a party to confront The due process clause guarantees longer claim that the accounting practices that went into
Court wrote in CMP Federal Security Agency, Inc. v. NLRC: and cross-examine opposing witnesses in a judicial no particular form of procedure the reporting of the 1999 AFS of Bankard were not in
While administrative tribunals litigation, be it criminal or civil in nature, or in proceedings and its requirements are not accord with generally accepted accounting principles. He
exercising quasi-judicial powers, before administrative tribunals with quasi-judicial powers, technical. Thus, in certain pointed out that RCBC was bound by the audit conducted
like the NLRC and Labor Arbiters, is a fundamental right which is part of due process." 68 proceedings of administrative by a certain Rubio prior to the full payment of the purchase
are free from the rigidity of certain It is, however, equally true that: character, the right to a notice or price of Bankard. Anchored on these statements by Justice
procedural requirements, they are [T]he right is a personal one which hearing [is] not essential to due Kapunan, petitioners conclude that RCBC is estopped from
nonetheless bound by law and may be waived expressly or process of law. The constitutional claiming that the former violated their warranties under
practice to observe the impliedly by conduct amounting to requirement of due process is met the SPA.
fundamental and essential a renunciation of the right of cross- by a fair hearing before a regularly Petitioners' contention is not meritorious.
requirements of due process. The examination. Thus, where a party established administrative agency Art. 1431 of the Civil Code, on the subject of estoppel,
standard of due process that must has had the opportunity to cross- or tribunal. It is not essential that provides: "Through estoppel an admission or
be met in administrative tribunals examine a witness but failed to hearings be had before the making representation is rendered conclusive upon the person
allows a certain degree of latitude avail himself of it, he necessarily of a determination if thereafter, making it, and cannot be denied or disproved as against the
as long as fairness is not ignored. forfeits the right to cross- there is available trial and tribunal person relying thereon." IAETSC
Hence, it is not legally examine and the testimony given before which all objections and The doctrine of estoppel is based upon the grounds of
objectionable, for being violative of on direct examination of the defenses to the making of such public policy, fair dealing, good faith, and justice; and its
due process, for the Labor Arbiter witness will be received or determination may be raised and purpose is to forbid one to speak against one's own acts,
to resolve a case based solely on allowed to remain in the considered. One adequate hearing representations, or commitments to the injury of one to
the position papers, affidavits or record. 69 (Emphasis supplied.) is all that due process requires. whom they were directed and who reasonably relied on
documentary evidence submitted We also held in one case: What is required for "hearing" may them. 72
by the parties. The affidavits of However, the right has always differ as the functions of the We explained the principle of estoppel in Philippine Savings
witnesses in such case may take the been understood as requiring administrative bodies Bank v. Chowking Food Corporation:
place of their direct testimony. 66 not necessarily an actual cross- differ. HSEIAT . . . The equitable doctrine of
Of the same tenor is our holding in Quiambao v. Court of examination but merely an The right to cross-examine is not estoppel was explained by this
Appeals: opportunity to exercise the right an indispensable aspect of due Court in Caltex (Philippines), Inc. v.
In resolving administrative cases, to cross-examine if desired. What process. 71 . . . (Emphasis Court of Appeals:
conduct of full-blown trial is not is proscribed by statutory norm supplied.) Under the doctrine of
indispensable to dispense justice to and jurisprudential precept is Clearly, the right to cross-examine a witness, although a estoppel, an admission
the parties. The requirement of the absence of the opportunity to fundamental right of a party, may be waived. Petitioners or representation is
notice and hearing does not cross-examine. The right is a themselves admit having had the opportunity to cross- rendered conclusive
connote full adversarial personal one and may be waived examine RCBC's witnesses during the hearings before the upon the person making
proceedings. Submission of expressly or impliedly. There is an tribunal, but declined to do so by reserving such right at a it, and cannot be denied
position papers may be sufficient implied waiver when the party was later time. Having had the opportunity to cross- or disproved as against
for as long as the parties thereto given the opportunity to confront examine RCBC's witnesses, petitioners were not denied the person relying
are given the opportunity to be and cross-examine an opposing their right to due process. thereon. A party may not
heard. In administrative witness but failed to take RCBC is Not Estopped from Questioning the go back on his own acts
proceedings, the essence of due advantage of it for reasons Financial Condition of Bankard and representations to
process is simply an opportunity attributable to himself alone. If by On estoppel, petitioners contend that RCBC already knew the prejudice of the
to be heard, or an opportunity to his actuations, the accused lost his the recording of the Bankard accounts before it paid the other party who relied
explain one's side or opportunity opportunity to cross-examine balance of the purchase price and could no longer challenge upon them. In the law of
to seek a reconsideration of the wholly or in part the witnesses the financial statements of Bankard.RCBC, they claim, had evidence, whenever a
action or ruling complained of. against him, his right to cross- full control of the operations of Bankard since June 2, 2000 party has, by his own
This constitutional mandate is examine is impliedly and RCBC's audit team reviewed the accounts in September declaration, act, or
deemed satisfied if a person is waived. 70 (Emphasis supplied.) 2000. Thus, RCBC is now precluded from denying the omission, intentionally
granted an opportunity to seek fairness and accuracy of said accounts since it did not seek and deliberately led
reconsideration of an action or a price reduction under Sec. 5 (h). Lastly, they asseverate another to believe a
particular thing true, to "RCBC was aware of the manner in which the Bankard claim of overvaluation to petitioners. RCBC, therefore, had which would have given
act upon such belief, he accounts were recorded, well before it consummated the no sufficient knowledge of the correctness of Bankard's the Respondents the
cannot, in any litigation SPA by taking delivery of the shares and paying the accounts. impression that they
arising out of such outstanding 80% balance of the contract price." 75 On another issue, RCBC could not have immediately were being relieved over
declaration, act, or Petitioners, therefore, theorize that in this case, the first changed the Bankard accounting practices until it had the next three years of
omission, be permitted element of estoppel in relation to the party sought to be conducted a more extensive and thorough audit of susceptibility to a claim
to falsify it. estopped is that RCBC made a false representation that it Bankard's voluminous records and transactions to uncover under clause 5(g). Maybe
The principle received further considered Bankard's accounts to be in order and, any irregularities. That would be the only logical the TC could have been
elaboration in Maneclang v. Baun: thus, RCBC abandoned any claim under Sec. 5 (g) and 5 (h) explanation why Bankard's alleged irregular practices were more proactive in
In estoppel by pais, as related to the by its inaction. maintained for more than two (2) years from closing date. commissioning further
party sought to be estopped, it is Such contention is incorrect. The fact that RCBC continued with the audit of Bankard's or more in-depth audits
necessary that there be a It must be emphasized that it was only after a second audit AFS and records after the termination of the Rubio audit but it was not. It did not
concurrence of the following that RCBC presented its claim to petitioners for violation of can only send the clear message to petitioners that RCBC is have to be. It is
requisites: (a) conduct amounting Sec. 5 (g), within the three (3)-year period prescribed. In still entertaining the possibility of filing a claim under Sec. commercially unlikely
to false representation or other words, RCBC, prior to such second audit, did not have 5 (g). It cannot then be said that petitioners' reliance that it have been done
concealment of material facts or at full and thorough knowledge of the correctness of on RCBC's acts after full payment of the price could have so, with the necessary
least calculated to convey the Bankard's accounts, in relation to Sec. 5 (g). RCBC, misled them into believing that no more claim will be degree of attention to
impression that the facts are therefore, could not have misrepresented itself considering presented by RCBC. detail, within the
otherwise than, and inconsistent that it was still in the process of verifying the warranties The Arbitral Tribunal explained in detail why estoppel is relatively short time
with, those which the party covered under Sec. 5 (g). Considering that there must be a not present in the case at bar, thus: EDHCSI between the
subsequently attempts to assert; concurrence of the elements of estoppel for it to arise, on 10.18 The audit exercise conducted appointment of the TC
(b) intent, or at least expectation this ground alone such claim is already negated. As will be by Mr. Legaspi and Mr. and the ultimate
that this conduct shall be acted shown, however, all the other elements of estoppel are Rubio was clearly not settlement date of the
upon, or at least influenced by the likewise absent in the case at bar. one comprehensive purchase — a period of
other party; and (c) knowledge, As to the second element, in order to establish enough to have some three months. An
actual or constructive of the actual estoppel, RCBC must have intended that petitioners would discovered the problems interim arrangement
facts. act upon its actions. This element is also missing. RCBC by later unearthed by Dr. was obviously sensible
Estoppel may vary somewhat in its actions did not mislead petitioners into believing that it Laya and Dean Ledesma. to enable the Claimant
definition, but all authorities agree waived any claim for violation of a warranty. The periods ... and its staff to become
that a party invoking the doctrine under Sec. 5 (g) and 5 (h) were still available 10.19 Although the powers of the familiar with the
must have been misled to one's to RCBC. CDHSac TC [Transition practices and procedures
prejudice. That is the final and, in The element that petitioners relied on the acts and conduct Committee] may have of Bankard.
reality, most important of the of RCBC is absent. The Court finds that there was no been widely expressed in 10.21 The core consideration
elements of equitable estoppel. It is reliance on the part of petitioners on the acts of RCBC that the view of Mr. Rogelio weighing with the
this element that is lacking would lead them to believe that the RCBC will forego the Chua, then in charge of Tribunal in assessing
here. 73 (Emphasis supplied.) filing of a claim under Sec. 5 (g). The allegation Bankard . . . the TC these claims for estoppel
The elements of estoppel pertaining to the party estopped that RCBC knew that the Bankard accounts did not comply conducted meetings only is that the SPA allowed
are: with generally accepted accounting principles before to get updated on the two types of claim; one
(1) conduct which amounts to a payment and, hence, it cannot question the financial status and progress of within six months under
false representation or statements of Bankard is meritless. Precisely, the SPA Bankard's operations. 5(h) and one within
concealment of material facts, or, at explicitly provides that claims for violation of the Commercially, one would three years under 5(g).
least, which calculated to convey warranties under Sec. 5 (g) can still be filed within three expect that an unpaid The Tribunal has already
the impression that the facts are (3) years from the closing date. Petitioners' contention vendor expecting to held the present claim is
otherwise than, and inconsistent that RCBC had full control of Bankard operations after receive 80% of a large not barred by clause
with, those which the party payment of the price and that an audit undertaken by the purchase price would 5(h). It must therefore
subsequently attempts to assert; Rubio team did not find anything wrong with the accounts not be receptive to a have been within the
(2) intention, or at least could not have plausibly misled petitioners into believing purchaser making vast reasonable
expectation, that such conduct shall that RCBC will waive its right to file a claim under Sec. 5 (g). policy changes in the contemplation of the
be acted upon by the other party; After all, the period to file a claim under Sec. 5 (g) is three operation of the business parties that a 5(g) claim
and (3) knowledge, actual or (3) years under Sec. 7, much longer than the six (6)-month until the purchaser has could surface within the
constructive, of the actual period under Sec. 5 (h). Petitioners are fully aware that the paid up its money. It is three-year period and
facts. 74 DHETIS warranties under Sec. 5 (g) (1997 up to March 2000) are of more likely that, until the that it could be
a wider scope than that of Sec. 5 (h) (AFS of 1999 and UFS settlement date, there somewhat differently
In the case at bar, the first element of estoppel in relation to up to May 31, 2000), necessitating a longer audit period was a practice of assessed than the claim
the party sought to be estopped is not present. Petitioners than the six (6)-month period under Sec. 5 (h). maintaining the status under 5(h). The Tribunal
claim that RCBC misrepresented itself when RCBC made it The third element of estoppel in relation to the party quo at Bankard. cannot find estoppel by
appear that they considered petitioners to have sufficiently sought to be estopped is also absent considering that, as 10.20 But neither the Claimant nor conduct either from the
complied with its warranties under Sec. 5 (g) and 5 (h), in stated, RCBC was still in the process of verifying the the TC did anything, in formation of the TC or
relation to Sec. 7 of the SPA. Petitioners' position is that correctness of Bankard's accounts prior to presenting its the Tribunal's view, from the limited auditing
exercise done by Mr. possible reduction in the clause 5(g). These proof of the necessary
Rubio and Mr. Legaspi. price to be paid on aspects of the claim of representation to the
The onus proving settlement. estoppel are rejected. Respondent, nor any
estoppel is on the 10.25 The fact that the purchase xxx xxx xxx detriment to the
Respondents and it has price was paid over in 10.42 The Tribunal is not the Respondent proved. The
not been discharged. full without any appropriate forum for grounds of delay and
10.22 If the parties had wished the deduction in terms of deciding whether there laches are not
avenues of relief for clause 5(h) is not a bar to have been any regulatory substantiated.
misrepresentation the Claimant bringing a or ethical infractions by In summary, the tribunal properly ruled that petitioners
afforded to the Claimant claim under 5(g) within Bankard and/or the failed to prove that the formation of the Transition
to have been restricted the three-year period. Claimant in setting the Committee and the conduct of the audit by Rubio and
to a claim under Clause The fact that payment 'buy-back' price. It has Legaspi were admissions or representations by RCBCthat it
5(h), then they could was made can be, as the no bearing on whether would not pursue a claim under Sec. 5 (g) and that
have said so. The 'special Tribunal has held, a the Claimant must be petitioners relied on such representation to their
audit' may have barrier to a claim for considered as having detriment. We agree with the findings of the tribunal that
provided an answer to rescission and restitution waived its right to claim estoppel is not present in the situation at bar.
any claim based on ad inegrum. A claim for against the Additionally, petitioners claim that in Knecht v. Court of
clause 5(h) but it cannot estoppel needs a finding Respondents. HCSEIT Appeals 76 and Coca-Cola Bottlers Philippines, Inc. v. Court
do so in respect of a of representation by 10.43 In the Tribunal's view, of Appeals (Coca-Cola), 77 this Court ruled that the absence
claim based on Clause words of conduct or a neither any infraction by of the element of reliance by a party on the representation
5(g). Clause 5(g) shared presumption that Bankard in failing to of another does not negate the principle of estoppel. Those
imposed a positive a right would not be advise the Central Bank cases are, however, not on all fours with and cannot be
obligation on the relied upon. The party of the experts' findings, applied to this case.
Respondents from which relying on estoppel has nor a failure to put a tag In Knecht, the buyer had the opportunity of knowing the
they cannot be excused, to show reliance to its on the accounts nor to conditions of the land he was buying early on in the
simply by reason of detriment or that, have said something to transaction, but proceeded with the sale anyway. According
either the formation and otherwise, it would be the shareholders in the to the Court, the buyer was estopped from claiming that the
conduct of the TC or of unconscionable to resile buy-back exercise vendor made a false representation as to the condition of
the limited from the provision. operates as a "technical the land. This is not true in the instant case. RCBC did not
audit. CSTDEH 10.26 Article 1431 of the Civil Code knock-out" of Claimant's conduct a due diligence audit in relation to Sec. 5 (g) prior
10.23 The three-year limitation states: claim. to the sale due to petitioners' express representations and
period obviously "Through estoppel an admission or warranties. The examination conducted by RCBC, through
contemplated that it representation is 10.44 The Tribunal notes that the Rubio, after the execution of the SPA on June 2, 2000, was
could take some time to rendered conclusive conciliation process confined to finding any breach under Sec. 5 (h) for a
ascertain whether there upon the person making mandated by the SPA possible reduction of the purchase price prior to the
had been a breach of the it, and cannot be denied took most of 2003 and payment of its balance on December 31, 2000. Further, the
GAAP standards, etc. or disproved as against this may explain a part of parties clearly agreed under Sec. 7 of the SPA to a three (3)-
Such was the case. A six- the person relying the delay in commencing year period from closing date within which to present a
month limitation period thereon." arbitral proceedings. claim for damages for violation of the warranties under the
under Clause 5(h), in 10.27 Clearly, there has to both an 10.45 Whatever the status of Mr. SPA. Hence, Knecht is not a precedent to the case at bar.
contrast, presaged a admission or Rubio's and Mr. So is Coca-Cola. As lessee, Coca-Cola Bottlers was well
somewhat less stringent representation by (in Legaspi's enquiries in aware of the nature and situation of the land relative to its
enquiry of the kind this case) the Claimant, late 2000, the Claimant intended use prior to the signing of the contract. Its
carried out by Mr. Rubio plus reliance upon it by was quite entitled to subsequent assertion that the land was not suited for the
and Mr. Legaspi. (in this case) the commission subsequent purpose it was leased was, therefore, cast aside for being
10.24 Clause 2(3) of the Respondents. The reports from Dr. Laya unmeritorious. Such circumstance does not obtain in the
Amendment to the SPA Tribunal cannot find as and Dr. Echanis and, on instant case. There was no prior due diligence audit
strengthens the proved any the basis of those conducted by RCBC, it having relied, as earlier stated, on
conclusion that the admission/representatio reports, make a timeous the warranties of petitioners with regard to the financial
parties were concerned n that the Claimant was claim under clause 5(g) condition of Bankard under Sec. 5 (g). As such, Sec. 5 (g)
only with a 5(h) claim abandoning a 5(g) claim, of the SPA. guaranteed RCBC that it could file a claim for damages for
during the TC's reign. any reliance by 10.46 In the Tribunal's view, any mistakes in the AFS and UFS of Bankard. Clearly, Coca-
The focus of the 'audit' Respondents on an therefore, there is no Cola also cannot be applied to the instant case.
— however intense it admission, and any merit in Respondents' It becomes evident from all of the foregoing findings that
was — conducted by Mr. detriment to the various submissions that the ICC-ICA is not guilty of any manifest disregard of the
Rubio and Mr. Legaspi, Respondents such as the Claimant is debarred law on estoppel. As shown above, the findings of the ICC-
was on establishing would entitle them to from prosecuting its ICA in the Partial Award are well-supported in law and
possible liability under have the Claimant claims on the grounds of grounded on facts. The Partial Award must be upheld.
that section and thus as a deprived of the benefit of estoppel. There is just no
We close this disposition with the observation that a 1 — Cawayan area In the meantime, by March 1993, On July 7, 1994, NPC filed a Petition
member of the three-person arbitration panel was selected P52,081,421.00 the works in Botong area were in for Certiorari with Prayer for
by petitioners, while another was respondent's choice. The 1A — Botong area considerable delay. By May 1993, Temporary Restraining Order and
respective interests of the parties, therefore, are very much P56,412,545.30 civil works in Botong were kept at a Preliminary Injunction before the
safeguarded in the arbitration proceedings. Any suggestion, –––––––––––––– minimum until on November 1, First Division of the Court of
therefore, on the partiality of the arbitration tribunal has to P108,493,966.30 1993, the entire operation in the Appeals asserting that no
be dismissed. DCcSHE Appended with the Contract is the area completely ceased and FUCC injunction may issue against any
WHEREFORE, the instant petition is hereby DENIED. The contract price schedule which was abandoned the project. government projects pursuant
assailed January 8, 2008 and March 17, 2008 Orders of the submitted by the respondent FUCC Several written and verbal to Presidential Decree
RTC, Branch 148 in Makati City are hereby AFFIRMED. during the bidding. The price for warnings were given by NPC to 1818. HCITAS
Costs against petitioners. grading excavation was P76.00 per FUCC. On March 14, 1994, NPC's On July 8, 1994, the Court of
SO ORDERED. cubic meter. Board of Directors passed Appeals through then Associate
||| (Equitable PCI Banking Corp. v. RCBC Capital Corp., G.R. Construction activities commenced Resolution No. 94-63 approving the Justice Bernardo Pardo issued a
No. 182248, [December 18, 2008], 595 PHIL 537-589) in August 1992. In the latter part of recommendation of President temporary restraining order and on
September 1992 and after Francisco L. Viray to take over the October 20, 1994, the said court
SECOND DIVISION excavating 5.0 meters above the contract. President Viray's rendered a Decision granting NPC's
[G.R. No. 148318. November 22, 2004.] plant elevation, FUCC requested recommendation to take over the Petition for Certiorari and setting
NATIONAL POWER NPC that it be allowed to blast to project was compelled by the need aside the lower court's Order dated
CORPORATION, petitioner, vs. the design grade of 495 meters to stave-off huge pecuniary and April 21, 1994 and the Writ of
HON. ROSE MARIE ALONZO- above sea level as its dozers and non-monetary losses, namely: Preliminary Injunction dated May
LEGASTO, as Presiding Judge, rippers could no longer excavate. It (a) Generation loss estimated to be 5, 1994.
RTC of Quezon City, Branch 99, further requested that it be paid at P26,546,400/month; However, notwithstanding the
JOSE MARTINEZ, Deputy Sheriff, P1,346.00 per cubic meter similar (b) Payment of steam penalties to dissolution by the Court of Appeals
RTC of Quezon City, CARMELO V. to the rate of NPC's project in PNOC-EDC the amount of the said injunction, on July 15,
SISON, Chairman, Arbitration Palinpinon. estimated to be at 1995, FUCC filed a Complaint
Board, and FIRST UNITED While blasting commenced on P10,206,048.00/month; before the Office of the
CONSTRUCTORS October 6, 1992, NPC and FUCC (c) Payment of liquidated damages Ombudsman against several NPC
CORPORATION, respondents. were discussing the propriety of an due to the standby of employees for alleged violation of
DECISION extra work order and if such is in electromechanical Republic Act No. 3019, otherwise
TINGA, J p: order, at what price should FUCC be contractor; known as the Anti-Graft and
National Power Corporation (NPC) filed the instant Petition paid. (d) Loss of guaranteed protection Corrupt Practices Act. Together
for Review 1 dated July 19, 2001, assailing theDecision 2 of Sometime in March 1993, NPC Vice (warranties) of all with the complaint was an
the Court of Appeals dated May 28, 2001 which affirmed President for Engineering delivered plant Urgent Ex-Parte Motion for the
with modification the Order 3 and Writ of Construction, Hector Campos, equipment and issuance of a cease and [d]esist
Execution 4 respectively dated May 22, 2000 and June 9, created a task force to review accessories as Mitsubishi [o]rder to restrain NPC and other
2000 issued by the Regional Trial Court. In its FUCC's blasting works. The Corporation, NPC officials involved in the
assailed Decision, the appellate court declared respondent technical task force recommended electromechanical BACMAN II project from canceling
First United Constructors Corporation (FUCC) entitled to that FUCC be paid P458.07 per contractor, will not be and/or from taking over FUCC's
just compensation for blasting works it undertook in cubic meter as such being the price liable after six months of contract for civil works of said
relation to a contract for the construction of power agreed upon by FUCC. delivery. project.
facilities it entered into with petitioner. The Court of The matter was further referred to To prevent NPC from taking over Then on November 16, 1994, FUCC
Appeals, however, deleted the award for attorney's fees the Department of Public [W]orks the project, on March 28, 1994, filed before the Supreme Court a
having found no basis therefor. and Highways (DPWH), which in a FUCC filed an action for Specific Petition for Review assailing the
The facts culled from the Decision of the Court of Appeals letter dated May 19, 1993, Performance and Damages with Decision of the Court of [A]ppeals
are undisputed: recommended the price range of Preliminary Injunction and dated October 20, 1994. In its
On April 14, 1992, NPC and FUCC P500.00 to P600.00 per cubic Temporary Restraining Order Comment, NPC raised the issue that
entered into a contract for the meter as reasonable. It further before Branch 99, Regional Trial FUCC resorted to forum shopping
construction of power facilities opined that the price of P983.75 Court, Quezon City. as it applied for a cease and desist
(civil works) — Schedule 1 — 1x20 per cubic meter proposed by Lauro Under paragraph 19 of its order before the National
MW Bacon-Manito II Modular R. Umali, Project Manager of Complaint, FUCC admitted that it Ombudsman despite the
Geothermal Power Plant (Cawayan BACMAN II was high. A copy of the agreed to pay the price of P458.07 dissolution of the injunction by the
area) and Schedule 1A — 1x20 MW DPWH letter is attached as Annex per cubic meter. Court of Appeals.
Bacon-Manito II Modular "C", FUCC's Exhibit EEE-Arbitration. On April 5, 1994, Judge de Guzman Pending the petition filed by FUCC
Geothermal Power Plant (Botong In a letter dated June 28, 1993, issued a temporary restraining before the Supreme Court, on April
area) in Bacon, Sorsogon (BACMAN FUCC formally informed NPC that it order and on April 21, 1994, the 20, 1995 the NPC and FUCC entered
II). The total contract price for the is accepting the proposed price of trial court resolved to grant the into a Compromise Agreement.
two schedules is P108,493,966.30, P458.07 per cubic meter. A copy of application for issuance of a writ of Under the Compromise Agreement,
broken down as follows: the said letter is attached as Annex preliminary injunction. the parties agreed on the following:
SCHEDULE "D", FUCC's Exhibit L Arbitration.
1. Defendant shall process and pay the parties shall and sign this which the
the undisputed unpaid immediately execute the Compromise arbitrable
billings of Plaintiff in proper documents Agreement issues shall be
connection with the mutually terminating which they referred to the
entire project fifteen Plaintiff's contract for will submit for Arbitration
(15) days after a the civil works of the approval by Board. The
reconciliation of BACMAN II Project this Court. terms of
accounts by both (Contract No. Sp90DLM- Under this reference shall
Plaintiff and Defendant 918 (I & A); Compromise form part of
or thirty (30) days from 6. Such mutual termination of Agreement the
the date of approval of Plaintiff's contract shall both parties Compromise
this Compromise have the following agree that: Agreement
Agreement by the Court effects and/or xxx xxx xxx and shall be
whichever comes first. consequences: (a) the STAGE 2 submitted by
Both parties agree to construction works of 7.1 The parties shall the parties to
submit and include those Plaintiff at the Kawayan submit for the Honorable
accounts which could not and Bolong sites, at its arbitration to Court within a
be reconciled among the present stage of settle: (a) the period of
issues to be arbitrated as completion, shall be price of seven (7) days
hereunder provided; accepted and/or deemed blasting, (b) from the
2. Plaintiff accepts and to have been accepted by both parties' signing of the
acknowledges that defendant; (b) Plaintiff claims for Compromise
Defendant shall have the shall have no more damages, Agreement;
right to proceed with the obligation to Defendant delays,
works by re-bidding or in respect of the interests, and 7.4 The Arbitration
negotiating the project BACMAN II Project (c) all other Board shall
immediately upon the except as provided in unresolved have a non-
signing of herein clause (e) below; (c) claims of both extendible
Compromise Agreement; Defendant shall release parties, period of
3. This Compromise Agreement all retention moneys of including the three (3)
shall serve as the plaintiff within a exact volume months within
Supplemental maximum period of of blasted which to
Agreement for payment thirty (30) days from the rocks; complete the
of plaintiff's blasting date of final Resolution 7.2 The arbitration shall arbitration
works at the Botong site; of the Arbitration; (d) no be through a process and
4. Upon approval of this retention money shall three-member submit its
Compromise Agreement thenceforth be withheld commission to Decision to
by the Court or Plaintiff's by Defendant in its be appointed the Honorable
receipt of payment of payment to Plaintiff by the Court;
this undisputed unpaid under this Compromise Honorable 7.5 The parties agree
billings from Defendant Agreement, and (e) Court. Each that the
whichever comes first, Plaintiff shall put up a party shall Decision of the
the parties shall one-year guaranty bond nominate one Arbitration
immediately file a Joint for its completed civil member. The Board shall be
Manifestation and works at the Kawayan Chairman of final and
Motion for the site, retroactive to the the executory;
withdrawal of the date of actual use of the Arbitration 7.6 By virtue of this
following Plaintiff's plant by defendant; Board shall be Compromise
petition from the 7. Plaintiff's blasting works claims [a] person Agreement,
Supreme Court, and other unresolved mutually except as
Plaintiff's Complaint claims, as well as the acceptable to herein
from the National claims of damages of both parties, provided, the
Ombudsman, the both parties shall be preferably parties shall
Complaint and Amended settled through a two from the mutually
Complaint from the RTC, stage process to wit: academe; waive, forego
Br. 99 of Quezon City; STAGE 1 7.3 The parties shall and dismiss all
5. Upon final resolution of the 7.1 Plaintiff and likewise agree of their other
Arbitration, as Defendant upon the claims and/or
hereunder prescribed, shall execute terms under counterclaim
in this case. Arbitration Board shall right to question said Decision of before the Court of Appeals. It claims that the appellate
Plaintiff and be final and executory. the Board. Hence, they agreed in court failed to pass upon the following issues:
defendant SO ORDERED. clear and unequivocal terms in the 1. The Chairman of the Arbitration
warrant that On December 10, 1999 plaintiff Compromise Agreement that said Board showed extreme
after approval FUCC filed a Motion for Execution Decision would be immediately bias in prejudging the
by the Court of while defendant NPC filed a Motion final and executory. Plaintiff relied case.
this to Vacate Award by the Arbitration upon this stipulation in complying 2. The Chairman of the Arbitration
Compromise Board on December 20, 1999. with its various obligations under Board greatly exceeded
Agreement On May 22, 2000 Presiding Judge the agreement. To allow defendant his powers when he
neither party Rose Marie Alonzo Legasto issued to now go back on its word and mediated for settlement
shall file an order the dispositive portion of start questioning the Decision in the court of
Criminal or which states: would be grossly unfair considering arbitration proceedings.
Administrativ "WHEREFORE, the that the latter was also a party to 3. The Chairman of the Arbitration
e cases or Arbitration Award the Compromise Agreement Board committed serious
suits against issued by the Arbitration entered into part of which dealt irregularity in hastily
each other or Board is hereby with the creation of the Arbitration convening the Board in
its Board or APPROVED and the Board. 6 two days, which
member of its Motion for Execution The appellate court likewise held that petitioner failed to thereafter released its
officials on filed by plaintiff hereby present evidence to prove its claim of bias and partiality on report.
grounds GRANTED. The Motion to the part of the Chairman of the Arbitration Board, Mr. 4. The Arbitration Board
arising from Vacate Award filed by Carmelo V. Sison (Mr. Sison). aIcCTA Committed manifest
the case. defendant is hereby Further, the Court of Appeals found that blasting is not part injustice prejudicial to
The Compromise Agreement was DENIED for lack of merit. of the unit price for grading and structural excavation petitioner based on the
subsequently approved by the Accordingly, let a writ of provided for in the contract for the BACMAN II Project, and following:
Court on May 24, 1995. execution be issued to that there was no perfected contract between the parties a. It rendered an award
The case was subsequently referred enforce the Arbitration for an extra work order for blasting. Nonetheless, since based on
by the parties to the arbitration Award. FUCC relied on the representation of petitioner's officials equity despite
board pursuant to their SO that the extra work order would be submitted to its Board the mandatory
Compromise Agreement. On ORDERED." 5 (Bracketed of Directors for approval and that the blasting works would provision of
December 9, 1999 the Arbitration words supplied) be paid, the Court of Appeals ruled that FUCC is entitled to the law.
Board rendered its ruling the NPC went to the Court of Appeals on the lone issue of just compensation on grounds of equity and promissory b. The Board's decision
dispositive portion of which states: whether respondent judge acted with grave abuse of estoppel. to justify that
WHEREFORE, claimant is discretion in issuing the Order dated May 22, 2000 and Anent the issue of just compensation, the appellate court equity applies
hereby declared entitled directing the issuance of a Writ of Execution. took into account the estimate prepared by a certain Mr. herein despite
to an award of In its assailed Decision, the appellate court declared that the Lauro R. Umali (Mr. Umali), Project Manager of the the fact
P118,681,328.28 as just court a quo did not commit grave abuse of discretion BACMAN II Project, which itemized the various costs that FUCC
compensation for considering that the Arbitration Board acted pursuant to its involved in blasting works and came up with P1,310.82 per never
blasting works, plus ten powers under the Compromise Agreement and that its cubic meter, consisting of the direct cost for drilling, submitted its
percent (10%) thereof award has factual and legal bases. blasting excavation, stockpiling and hauling, and a 30% own actual
for attorney's fees and The Court of Appeals gave primacy to the court-approved mark up for overhead, contractor's tax and contingencies. costs for
expenses of litigation. Compromise Agreement entered into by the parties and This estimate was later changed to P983.75 per cubic blasting and
Considering that concluded that they intended the decision of the arbitration meter to which FUCC agreed. The Court of Appeals, PHESCO, INC.,
payment in the total panel to be final and executory. Said the court: however, held that just compensation should cover only the the succeeding
amount of For one, what the price agreed to direct costs plus 10% for overhead expenses. Thus, it contractor, did
P36,550,000.00 had be submitted for arbitration are declared that the amount of P763.00 7 per cubic meter is not employ
previously been made, pure issues of fact (i.e., the price of sufficient. Since the total volume of blasted rocks as blasting but
respondent is hereby blasting; both parties' claims for computed by Dr. Benjamin Buensuceso, Jr. 8 of the U.P. used ordinary
ordered to pay claimant damages, delay, interests and all College of Engineering is 97,032.16 cubic meters, FUCC is excavation
the remaining sum of other unresolved claims of both entitled to the amount of P74,035,503.50 as just method at
P82,131,328.28 for parties, including the exact volume compensation. P75.59 per
attorney's fees and of blasted rocks). Also, the manner Although the Court of Appeals adjudged FUCC entitled to cubic meter
expenses of litigation. by which the Arbitration Board was interest, 9 the dispositive portion of the which is
Pursuant to the formed and the terms under which assailedDecision 10 did not provide for the payment of approximately
Compromise Agreement the arbitrable issues were referred interest. Moreover, the award of attorney's fees was the same unit
approved by this to said Board are specified in the deleted as there was no legal and factual ground for its price of
Honorable Court, the agreement. Clearly, the parties had imposition. plaintiff
parties have agreed that left to the Arbitration Board the Petitioner, represented by the Office of the Solicitor (FUCC).
the decision of the final adjudication of their General in the instant Petition, rehashes its submissions c. It gravely erred when
remaining claims and waived their the Board
claimed that meter. 11 [Emphasis in possession. In any event, the unit price of P430.00 per hear evidence pertinent
an award of the original] cubic meter appearing in the sub-contract represents only and material to the
just Specifically, petitioner asserts that Mr. Sison exhibited bias a fraction of the costs incurred by FUCC for the blasting controversy; that one or
compensation and prejudgment when he exhorted it to pay FUCC for the works. more of the arbitrators
must be given blasting works after concluding that the latter was allowed Petitioner filed a Reply 14 dated March 18, 2002 reiterating was disqualified to act as
to respondent to blast. Moreover, Mr. Sison allegedly attempted to its earlier submissions. such under section nine
FUCC for what mediate the conflict between the parties in violation The parties in the present case mutually agreed to submit hereof, and willfully
it has actually of Section 20, 12 paragraph 2 ofRepublic Act No. 876 (R.A. to arbitration the settlement of the price of blasting, the refrained from disclosing
spent and yet 876) otherwise known as the Arbitration Law. Petitioner parties' claims for damages, delay and interests and all such disqualifications or
instead of also questions the abrupt manner by which the decision of other unresolved claims including the exact volume of of any other misbehavior
using as basis the Arbitration Board was released. blasted rocks. 15 They further mutually agreed that the by which the rights of
P458.07 Petitioner avers that FUCC's claim for blasting works was decision of the Arbitration Board shall be final and any party have been
which is the not approved by authorized officials in accordance immediately executory. 16 materially prejudiced; or
price agreed with Presidential Decree No. 1594 (P.D. 1594) and its A stipulation submitting an ongoing dispute to arbitration (d) That the arbitrators exceeded
upon by FUCC, implementing rules which specifically require the approval is valid. As a rule, the arbitrator's award cannot be set aside their powers, or so
it chose of the extra work by authorized officials before an extra for mere errors of judgment either as to the law or as to the imperfectly executed
an estimate m work order may be issued in favor of the contractor. Thus, facts. Courts are generally without power to amend or them, that a mutual, final
ade by an NPC it should not be held liable for the claim. If at all, only the overrule merely because of disagreement with matters of and definite award upon
employee. erring officials should be held liable. Further, FUCC did not law or facts determined by the arbitrators. They will not the subject matter
d. It gravely erred when present evidence to prove the actual expenses it incurred review the findings of law and fact contained in an award, submitted to them was
it relied for the blasting works. What the Arbitration Board relied and will not undertake to substitute their judgment for that not made.
heavily on the upon was the memorandum of Mr. Umali which was of the arbitrators. A contrary rule would make an When an award is vacated, the
purported neither identified or authenticated during the arbitration arbitration award the commencement, not the end, of court, in its discretion, may direct a
letter of NPC proceedings nor marked as evidence for FUCC. Moreover, litigation. Errors of law and fact, or an erroneous decision new hearing either before the same
Project the figures indicated in Mr. Umali's memorandum were on matters submitted to the judgment of the arbitrators, arbitrators or before a new
Manager allegedly mere estimates and were recommendatory at are insufficient to invalidate an award fairly and honestly arbitrator or arbitrators to be
Lauro R. most. made. Judicial review of an arbitration award is, thus, more chosen in the manner provided in
Umali, when Petitioner likewise claims that its succeeding contractor, limited than judicial review of a trial. 17 the submission or contract for the
the same has Phesco, Inc. (Phesco), was able to excavate the same rock However, an arbitration award is not absolute and without selection of the original arbitrator
not been formation without blasting. exceptions. Where the conditions described inArticles or arbitrators, and any provision
identified nor Finally, it asserts that the award of P763.00 per cubic meter 2038, 2039 and 2040 of the Civil Code 18 applicable to limiting the time in which the
were the has no factual and legal basis as the sub-contract between both compromises and arbitrations are obtaining, the arbitrators may make a decision
handwritten FUCC and its blasting sub-contractor, Dynamic Blasting arbitrators' award may be annulled or shall be deemed applicable to the
entries in Specialists of the Philippines (Dynamic), was only P430.00 rescinded. 19 Additionally, judicial review of an arbitration new arbitration to commence from
Annex ii per cubic meter. award is warranted when the complaining party has the date of the court's order.
established to presented proof of the existence of any of the grounds for Where the court vacates an award,
be made by In its Comment 13 dated October 15, 2001, FUCC points out vacating, modifying or correcting an award outlined costs not exceeding fifty pesos and
him. that petitioner's arguments are exactly the same as the under Sections 24 and 25 of R.A. 876,viz: disbursements may be awarded to
5. The Arbitration Board gravely ones it raised before the Arbitration Board, the trial court Section 24. Grounds for vacating an the prevailing party and the
erred in computing and the Court of Appeals. Moreover, in the Compromise award. — In any of the following payment thereof may be enforced
interest at 12% and from Agreement between the parties, petitioner committed to cases, the court must make an in like manner as the payment of
the time of plaintiff's abide by the decision of the Arbitration Board. It should not order vacating the award upon the costs upon the motion in an action.
extrajudicial claim now be allowed to question the decision. petition of any party to the Section 25. Grounds for modifying or
despite the fact that FUCC likewise notes that Atty. Jose G. Samonte (Atty. controversy when such party correcting an award. — In any one
herein case is an action Samonte), one of the members of the Arbitration Board, proves affirmatively that in the of the following cases, the court
for specific performance was nominated by petitioner itself. If there was any arbitration proceedings: must make an order modifying or
and not for payment of irregularity in its proceedings such as the bias and (a) The award was procured by correcting the award, upon the
loan or forbearance of prejudgment petitioner imputes upon Mr. Sison, Atty. corruption, fraud, or application of any party to the
money, and despite the Samonte would have complained. As it is, Atty. Samonte other undue means; controversy which was arbitrated:
fact that it has resolved concurred in the decision of the Arbitration Board and or cSATEH (a) Where there was an evident
that there was no dissented only as to the award of attorney's fees. (b) That there was evident miscalculation of figures,
perfected contract and As regards the issue of interest, FUCC claims that the case partiality or corruption or an evident mistake in
there was no bad faith on involves forbearance of money and not a claim for damages in the arbitrators or any the description of any
the part of defendant. for breach of an obligation in which case interest on the of them; or person, thing or property
6. On June 25, 2000, NPC discovered amount of damages awarded may be imposed at the rate of (c) That the arbitrators were guilty referred to in the award;
the Sub-Contract six percent (6%) per annum. of misconduct in refusing or
Agreement of FUCC with Finally, FUCC asserts that its sub-contract agreement with to postpone the hearing (b) Where the arbitrators have
a unit price of only Dynamic is not newly-discovered evidence. Petitioner's upon sufficient cause awarded upon a matter
P430/per cubic lawyers allegedly had a copy of the sub-contract in their shown, or in refusing to not submitted to them,
not affecting the merits Minister of Public Works, orders/extra work orders beyond office/agency/corporation
of the decision upon the Transportation and 100% of the escalated original concerned.
matter submitted; or Communications, the Minister of contract cost shall be subject to b. The Regional Director concerned,
(c) Where the award is imperfect in Public Highways, or the Minister of public bidding except where the upon receipt of the proposed
a matter of form not Energy, as the case may be. works involved are inseparable from Change Order, Extra Work Order or
affecting the merits of The pertinent portions of the Implementing Rules and the original scope of the project in Supplemental Agreement shall
the controversy, and if it Regulations of P.D. 1594 provide: which case negotiation with the immediately instruct the technical
had been a CI — Contract Implementation: incumbent contractor may be staff of the Region to conduct an
commissioner's report, These Provisions Refer to Activities allowed, subject to approval by the on-the-spot investigation to verify
the defect could have During Project Construction, i.e., appropriate authorities. the need for the work to be
been amended or After Contract Award Until prosecuted. A report of such
disregarded by the court. Completion, Except as May 7. Any Variation Order (Change verification shall be submitted
The order may modify and correct Otherwise be Specifically Referred Order, Extra Work Order or directly to the Regional Director
the award so as to effect the intent to Provisions Under Section II. IB — Supplemental Agreement) shall be concerned.
thereof and promote justice Instructions to Bidders. subject to the escalation formula c. The Regional Director concerned
between the parties. CI 1 — Variation Orders — Change used to adjust the original contract after being satisfied that such
In this case, petitioner does not specify which of the Order/Extra Work price less the cost of mobilization. Change Order, Extra Work Order or
foregoing grounds it relies upon for judicial review. Order/Supplemental Agreement In claiming for any Variation Order, Supplemental Agreement is
Petitioner avers that "if and when the factual circumstances 4. An Extra Work Order may be the contractor shall, within seven justified and necessary, shall
referred to in the provisions aforementioned are present, issued by the implementing official (7) calendar days after such work review the estimated quantities
judicial review of the award is warranted." 20 From its to cover the introduction of new has been commenced or after the and prices and forward the
presentation of issues, however, it appears that the alleged work items after the same has been circumstances leading to such proposal with the supporting
evident partiality of Mr. Sison is singled out as a ground to found to strictly comply with Section condition(s) leading to the extra documentation to the head of
vacate the board's decision. CI-1-1 and approved by the cost, and within 28 calendar days office/agency/corporation for
We note, however, that the Court of Appeals found that appropriate official if the amount of deliver a written communication consideration. aEDCSI
petitioner did not present any proof to back up its claim of the Extra Work Order is within the giving full and detailed particulars d. If, after review of the plans,
evident partiality on the part of Mr. Sison. Its averments to limits of the former's authority to of any extra cost in order that it quantities and estimated unit cost
the effect that Mr. Sison was biased and had prejudged the approve original contracts and may be investigated at that time. of the items of work involved, the
case do not suffice to establish evident partiality. Neither under the following conditions: Failure to provide either of such proper office/agency/corporation
does the fact that a party was disadvantaged by the a. Where there are additional notices in the time stipulated shall committee empowered to review
decision of the arbitration committee prove evident works needed and necessary for constitute a waiver by the and evaluate Change Orders, Extra
partiality. 21 the completion, improvement or contractor for any claim. The Work Orders or Supplemental
According to the appellate court, "[p]etitioner was never protection of the project which preparation and submission of Agreements recommends approval
deprived of the right to present evidence nor was there any were not included as items of work Change Orders, Extra Work Orders thereof, the head of
showing that the Board showed signs of any bias in favor of in the original contract. or Supplemental Agreements are as office/agency/corporation,
FUCC. As correctly found by the trial court, this Court b. Where there are subsurface or follows: believing the Change Order, Extra
cannot find its way to support petitioner's contention that latent physical conditions at the a. If the Project Engineer believes Work Order or Supplemental
there was evident partiality in the assailed Award of the site differing materially from those that a Change Order, Extra Work Agreement to be in order, shall
Arbitrator in favor of the respondent because the indicated in the contract. Order or Supplemental Agreement approve the same. The limits of
conclusion of the Board, which the Court found to be well- c. Where there are duly unknown should be issued, he shall prepare approving authority for any
founded, is fully supported by substantial evidence." 22 physical conditions at the site of an the proposed Order or individual, and the aggregate of,
There is no reason to depart from this conclusion. unusual nature differing materially Supplemental Agreement Change Orders, Extra Work Orders
However, we take exception to the arbitrators' from those ordinarily encountered accompanied with the notices or Supplemental Agreements for
determination that based on promissory estoppel per se or and generally recognized as submitted by the contractor, the any project of the head of
alone, FUCC is entitled to just compensation for blasting inherent in the work or character plans therefore, his computations office/agency/corporation shall not
works for the reasons discussed hereunder. provided for in the contract. as to the quantities of the be greater than those granted for
Section 9 of P.D. No. 1594, entitled Prescribing Policies, d. Where there are duly approved additional works involved per item an original project.
Guidelines, Rules and Regulations for Government construction drawings or any indicating the specific stations CI 3 — Conditions under which
Infrastructure Contracts, provides: instruction issued by the where such works are needed, the Contractor is to Start Work under
SECTION 9. Change Order and Extra implementing office/agency during date of his inspections and Variation Orders and Receive
Work Order. — A change order or the term of contract which involve investigations thereon, and the log Payments
extra work order may be issued extra cost. book thereof, and a detailed 1. Under no circumstances shall a
only for works necessary for the xxx xxx xxx estimate of the unit cost of such contractor proceed to commence
completion of the project and, 6. A separate Supplemental items of work, together with his work under any Change Order, Extra
therefore, shall be within the Agreement may be entered into for justifications for the need of such Work Order or Supplemental
general scope of the contract as all Change Orders and Extra Work Change Order, Extra Work Order or Agreement unless it has been
bid[ded] and awarded. All change Orders if the aggregate amount Supplemental Agreement, and shall approved by the Secretary or his
orders and extra work orders shall exceeds 25% of the escalated submit the same to the Regional duly authorized representative.
be subject to the approval of the original contract price. All change Director of
Exceptions to the preceding rule outlined under Contract Implementation (CI) 1(7) above the price per cubic meter for similar Dumaliang, TSN, 28 October 1996,
are the following: should have been complied with. Accordingly, petitioner's blasting works at Palinpinon, or at 43–49).
a. The Regional Director, or its officials should not have authorized the commencement of P1,346.00 per cubic meter. 6. In mid-October 1992, three (3)
equivalent position in blasting works nor should FUCC have proceeded with the 4. Claimant sent two (2) Vice-Presidents of respondent visited
agencies/offices/corporations same. confirmatory letters to respondent, the project site and were informed of
without plantilla position for the The following events, culled from the decision of the both addressed to its President, one claimant's blasting activities. While
same, may, subject to the Arbitration Board and the assailed Decision, are made the dated 30 September 1992, and sent respondent claims that one of the
availability of funds, authorize the bases for the finding of promissory estoppel on the part of through Mr. Angelito Senga, Chief Vice-Presidents, Mr.Rodrigo Falcon,
immediate start of work under any petitioner: Civil Design — Thermal, the other raised objections to claimant's
Change or Extra Work Order under 1. After claimant [respondent dated 02 October 1992, and sent blasting works as an extra work
any or all of the following herein] encountered what it claimed through Mr. Lauro R. Umali, Project order, they instructed claimant to
conditions: to be massive hard rock Manager-BacMan II (Exhs. "D" and speed up the works because of the
(1) In the event of an emergency formation (Testimony of witness "E"; Testimony of witness power crisis then hounding the
where the prosecution of the work Dumaliang, TSN, 28 October 1996, Dumaliang, TSN, 28 October 1996, country. Stipulation no. 24 of the
is urgent to avoid detriment to pp. 41–42; Testimony of witness pp. 43–49). The identical letters Joint Stipulation of Facts of the
public service, or damage to life Lataquin, 28 November 1996, pp. read: parties which reads: "24. In mid-
and/or property; and/or 2–3; 20–23; Exh. "JJJ" and sub- We wish to confirm your October 1992, three (3) Vice-
(2) When time is of the essence; markings) and informed instruction for us to Presidents of respondent, namely:
provided, however, that such respondent[petitioner herein] about proceed with the Mr. Hector N. Campos, Sr., of
approval is valid on work done up it, respondent's own geologists went blasting of the Botong Engineering Construction, Mr. C.A.
to the point where the cumulative to the Botong site to investigate and Plant site to the design Pastoral of Engineering Design, and
increase in value of work on the confirmed the rock formation and grade pending issuance Mr. Rodrigo P. Falcon, visited the
project which has not yet been duly recommended blasting (Cf. of the relevant variation project site and were likewise
fully approved does not exceed five Memorandum of Mr. Petronilo E. order. This is to avoid apprised of claimant's blasting
percent (5%) of the adjusted Pana, Acting Manager of the delay in the activities. They never complained
original contract price, or P500,000 Geoscience Services Department implementation of this about the blasting works, much less
whichever is less; provided, further, and the report of the geologists critical project due to the ordered its cessation. In fact, no
that immediately after the start of who conducted the site urgent need to blast official of respondent ever ordered
work, the corresponding investigation; Exhs. "F" and "F-1"). rocks on the plant site. that the blasting works be stopped."
Change/Extra Work Order shall be 2. Claimant asked for clearance to We are confirming 7. After visiting Botong, Mr. Hector
prepared and submitted for blast the rock formation to the further your statement N. Campos, Sr., then Vice President
approval in accordance with the design grade (Letter dated 28 that the said blasting of Engineering Construction,
above rules herein set. Payments September 1992; Exh. "UU"). The works is an extra work instructed Mr. Fernando A.
for works satisfactorily engineers of respondent at the order and that we will be Magallanes then Manager of the
accomplished on any Change/Extra project site advised claimant to paid using the price Luzon Engineering Projects
Work Order may be made only proceed with its suggested method established in your Department, to evaluate claimant's
after approval of the same by the of extraction (Order/Instruction Palinpinon contract with blasting works and to submit his
Secretary or his duly authorized given by Mr. Reuel R. Declaro and Phesco. recommendations on the proper
representative. Mr. Francis A. Paderna dated 29 Thank you for your price therefor. In a memorandum
b. For a Change/Extra Work Order September 1992; Exh. "C"). timely action and we dated 17 November 1992 (Exh. "G"
involving a cumulative amount 3. Claimant requested that the look forward to the and sub-markings), Mr. Magallanes
exceeding five percent (5%) of the intended blasting works be immediate issuance of confirmed that claimant's blasting
original contract price or original confirmed as extra work order by the extra work order. works was an extra work order and
adjusted contract price no work responsible officials of We are now mobilizing recommended that it be paid at the
thereon may be commenced unless respondent directly involved in the equipment and price for similar blasting works at
said Change/Extra Work Order has BACMAN II Project (i.e., then manpower for the said Palinpinon, or at P1,346.00 per
been approved by the Secretary or BACMAN II Project Manager, Mr. work and hope to start cubic meter. Mr. Campos concurred
his duly authorized representative. Lauro R. Umali and Mr. Angelito G. blasting next week. with the findings and
[Emphasis supplied] Senga, Section Chief, Civil 5. Respondent received the letters recommendations of Mr. Magallanes
It is petitioner's submission, and FUCC does not deny, that Engineering Design of respondent's but did not reply thereto nor and instructed Mr. Lauro R. Umali,
the claim for payment of blasting works in Botong alone Design Department which bidded countermand the earlier then Project Manager of BacMan II,
was approximately P170,000,000.00, a figure which far the project). These officials issued instructions given to claimant to to implement the same as shown by
exceeds the original contract price of P80,000,000.00 for verbal instructions to the effect: (a) proceed with the blasting works. his instructions scribbled on the
two (2) project sites. Under the foregoing implementing that claimant could blast the rock The due execution and authenticity memorandum.
rules, for an extra work order which exceeds 5% of the formation down to the design grade of these letters (Exhs. "D-1" and "E-
original contract price, no blasting work may be of 495 masl; (b) that said blasting 1") and the fact of receipt (Exhs. "D- 8. Mr. Umali and the project team
commenced without the approval of the Secretary or his works would be an extra work 2" and "E-2") were duly proved by prepared proposed Extra Work
duly authorized representative. Moreover, the procedure order; and (c) that claimant would claimant (Testimony of witness Order No. 2 — Blasting (Exh."DDD"
for the preparation and approval of the extra work order be paid for said blasting works using — Memorandum of Mr. Umali to
Mr. Campos dated 20 January 1993 12. Respondent asked the result in other injustice." 24 Promissory estoppel This brings us to the issue of just compensation.
forwarding proposed Extra Work Department of Public Works and presupposes the existence of a promise on the part of one The parties proposed in the terms of reference jointly
Order No. 2), recommending a price Highways (DPWH) about the against whom estoppel is claimed. The promise must be submitted to the Arbitration Board that should FUCC be
of P983.75 per cubic meter for standard prices for blasting in the plain and unambiguous and sufficiently specific so that the adjudged entitled to just compensation for its blasting
claimant's blasting works.Claimant projects of the DPWH. The DPWH court can understand the obligation assumed and enforce works, the price therefor should be determined based on
agreed to this price (Testimony of officially replied to respondent's the promise according to its terms. 25 the payment for blasting works in similar projects of FUCC
witness Dumaliang, 7 November query in a letter dated 19 May 1993 In the present case, the foregoing events clearly evince that and the amount it paid to its blasting
1996, p. 48). but the task force still failed to seek the promise that the blasting works would be paid was subcontractor. 29 They agreed further that "the price of the
9. On 19 February 1993, claimant Board approval for claimant's predicated on the approval of the extra work order by blasting at the Botong site . . . shall range from Defendant's
brought the matter of its unpaid variation order. The task force petitioner's Board. Even FUCC acknowledged that the position of P76.00 per cubic meter as per contract to a
blasting works to the attention of eventually recommended that the blasting works should be an extra work order and maximum of P1,144.00". 30
the then NPC Chairman [also issue of grading excavation and requested that the extra work order be confirmed as such Petitioner contends that the Arbitration Board, trial court
Secretary of the Department of structural excavation and the unit and approved by the appropriate officials. Notably, even as and the appellate court unduly relied on the memorandum
Energy then] Delfin L. Lazaro prices therefor be brought into the extra work order allegedly promised to it was not yet of Mr. Umali which was allegedly not marked as an exhibit.
during a meeting with the multi- voluntary arbitration (Testimony of forthcoming, FUCC commenced blasting. We note, however, that this memorandum actually forms
sectoral task force monitoring the witness Dumaliang, 7 November The alleged promise to pay was therefore conditional and part of the record of the case as Exhibit
implementation of power plant 1996, pp. 30–57). up to this point, promissory estoppel cannot be established "DDD." 31 Moreover, both the Arbitration Board and the
projects, who asked then NPC 13. Claimant thereafter saw as the basis of petitioner's liability especially in light of P.D. Court of Appeals found that Mr. Umali's proposal is the best
President Pablo B. Malixi what he Mr. Francisco L. Viray, the new NPC 1594 and its implementing rules of which both parties are evidence on record as it is supported by detailed cost
was doing about the President, who proposed that presumed to have knowledge. In Mendoza v. Court of estimates that will serve as basis to determine just
problem. President Malixi thereafter claimant accept the price of P458.07 Appeals, supra, we ruled that "[a] cause of action for compensation.
convened respondent's vice- per cubic meter for its blasting promissory estoppel does not lie where an alleged oral While the Arbitration Board found that FUCC did not
presidents and ordered them to works with the balance of its claim promise was conditional, so that reliance upon it was not present evidence showing the amount it paid to its blasting
quickly document the variation to be the subject of reasonable. It does not operate to create liability where it sub-contractor, it did present testimony to the effect that it
order and pay claimant. The vice- arbitration. Claimant accepted the does not otherwise exist." incurred other costs and expenses on top of the actual
president, and specifically offer and sent the letter dated 28 Petitioner's argument that it is not bound by the acts of its blasting cost. Hence, the amount of P430.00 per cubic
Mr. Campos, pledged that the September 1993 (Exh. "O") to officials who acted beyond the scope of their authority in meter indicated in FUCC's Contract of Agreement with
variation order for claimant's formalize said acceptance. However, allowing the blasting works is correct. Petitioner is a Dynamic is not controlling.
blasting works would be submitted no variation order was issued and government agency with a juridical personality separate Moreover, FUCC presented evidence showing that in two
for the approval of the NPC Board the promised payment never came. and distinct from the government. It is not a mere agency of (2) other projects where blasting works were undertaken,
during the first week of March (Testimony of witness Dumaliang, the government but a corporate entity performing petitioner paid the contractors P1,346 per cubic meter for
1993. Claimant thereafter sent 7 November 1996, p. 58). proprietary functions. It has its own assets and liabilities blasting and disposal of solid rocks in the Palinpinon
respondent a letter dated 22 14. After some time, claimant met and exercises corporate powers, including the power to project and P1,144.51 per cubic meter for rock excavation
February 1993 (Ex. "K") to confirm Mr. Viray on 19 October 1993 at the enter into all contracts, through its Board of Directors. in the Hermosa Balintawak project. Besides, while
this pledge (Testimony of witness project site, and with some NPC In this case, petitioner's officials exceeded the scope of petitioner claims that in a contract with Wilper
Dumaliang, 7 November 1996, pp. officers in attendance, particularly their authority when they authorized FUCC to commence Construction for the construction of the Tayabas sub-
28–30). Mr. Gilberto A. Pastoral, Vice- blasting works without an extra work order properly station, the price agreed for blasting was only P96.13,
10. Mr. Campos created a task force President for Engineering Design, approved in accordance with P.D. 1594. Their acts cannot petitioner itself did not present evidence in support of this
(i.e., the Technical Task Force on who was instructed by Mr. Viray to bind petitioner unless it has ratified such acts or is claim. 32
the Study and Review of Extra prepare the necessary memorandum estopped from disclaiming them. 26 Parenthetically, the point raised by petitioner that its
Work Order No. 2; Exh. "FFF") to (i.e., that claimant would be paid However, the Compromise Agreement entered into by the subsequent contractor, Phesco, did not undertake blasting
review claimant's blasting P458.07 per cubic meter with the parties, petitioner, being represented by its President, Mr. works in excavating the same rock formation is extraneous
works. After several meetings with balance of its claim to be the subject Guido Alfredo A. Delgado, acting pursuant to its Board and irrelevant. The fact is that petitioner allowed FUCC to
the task force, claimant agreed to of arbitration) for the approval of Resolution No. 95-54 dated April 3, 1995, is a confirmatory blast and undertook to pay for the blasting works.
the lower price of P458.07 per cubic the NPC Board. Claimant formalized act signifying petitioner's ratification of all the prior acts of At this point, we hearken to the rule that the findings of the
meter, in exchange for quick what transpired during this meeting its officers. Significantly, the parties agreed that "[t]his Arbitration Board, affirmed by the trial court and the Court
payment(Testimony of witness in its letter to Mr.Pastoral dated 22 Compromise Agreement shall serve as the Supplemental of Appeals and supported as they are by substantial
Dumaliang, 7 November 1996, p. October 1993 (Exhibit "R"). But no Agreement for the payment of plaintiff's blasting works at evidence, should be accorded not only respect but
30). aSITDC action was taken by Mr. Pastoral the Botong site" 27 in accordance with CI 1(6) afore- finality. 33 Accordingly, the amount of P763.00 per cubic
11. However, no variation order was and no variation order was issued by quoted. In other words, it is primarily by the force of this meter fixed by the Arbitration Board and affirmed by the
issued and no payment came, respondent (Testimony of witness Compromise Agreement that the Court is constrained to appellate court as just compensation should stand.
although it appears from two (2) Dumaliang, 7 November 1996, pp. declare FUCC entitled to payment for the blasting works it As regards the issue of interest, while the appellate court
radiograms sent by Mr. Campos to 57–58). 23[Emphasis supplied and undertook. declared in the body of its Decision "that interest which
Mr. Paderna at the project site that bracketed words] Moreover, since the blasting works were already rendered would represent the cost of the money spent be imposed
the variation order was being Promissory estoppel "may arise from the making of a by FUCC and accepted by petitioner and in the absence of on the money actually spent by claimant for the blasting
processed and that payment to promise, even though without consideration, if it was proof that the blasting was done gratuitously, it is but works," 34 there is no pronouncement as to the payment of
claimant was forthcoming (Exhs. intended that the promise should be relied upon and in fact equitable that petitioner should make compensation interest in the dispositive portion of the Decision even as it
"AAA" and "BBB"). it was relied upon, and if a refusal to enforce it would be therefor, pursuant to the principle that no one should be specifically deleted the award of attorney's fees.
virtually to sanction the perpetration of fraud or would permitted to enrich himself at the expense of another. 28
Despite its knowledge of the appellate court's omission, into, operational or the price of US$192 per metric ton; that the delivery of the By way of Sur-Rejoinder, petitioner contended that
FUCC did not file a motion for reconsideration or appeal behavioral terms, of the molasses was to be made in January/February 1997 and respondent had even clarified that the issue boiled down to
from its Decision. In failing to do so, FUCC allowed annulment of the Deed of payment was to be made by means of an Irrevocable Letter whether the arbitration clause contained in the contract
the Decision to become final as to it. Sale with Assumption of of Credit payable at sight, to be opened by September 15, subject of the complaint is valid and enforceable; that the
In Edwards v. Arce, 35 we ruled that in a case decided by a Mortgage, from which 1996; that sometime prior to September 15, 1996, the arbitration clause did not violate any of the cited provisions
court, the true judgment of legal effect is that entered by petitioners' title or claim parties agreed that instead of January/February 1997, the of the Arbitration Law.
the clerk of said court pursuant to the dispositive part of its of title embodied in TCT delivery would be made in April/May 1997 and that On September 17, 1998, the RTC rendered an Order, 8 the
decision. The only portion of the decision that may be the 133153 flows." (Italics payment would be by an Irrevocable Letter of Credit dispositive portion of which reads:
subject of execution is that which is ordained or decreed in supplied) 39 payable at sight, to be opened upon petitioner's advice. Premises considered, defendant's
the dispositive portion. Whatever may be found in the body In this case, the omission of the award of interest was Petitioner, as seller, failed to comply with its obligations "Motion to Dismiss/Suspend
of the decision can only be considered as part of the obviously inadvertent. Correction is therefore in order. under the contract, despite demands from respondent, Proceedings and to Refer
reasons or conclusions of the court and serve only as However, we do not agree with the Arbitration Board that thus, the latter prayed for rescission of the contract and Controversy to Voluntary
guides to determine the ratio decidendi. 36 the interest should be computed at 12%. Since the case payment of damages. Arbitration" is hereby DENIED.
Even so, the Court allows a judgment which had become does not involve a loan or forbearance of money, goods or On July 24, 1998, petitioner filed a Motion to Defendant is directed to file its
final and executory to be clarified when there is an credit and court judgments thereon, the interest due shall Dismiss/Suspend Proceedings and to Refer Controversy to answer within ten (10) days from
ambiguity caused by an omission or mistake in the be computed at 6% per annum computed from the time the Voluntary Arbitration, 4 wherein it argued that the alleged receipt of a copy of this order. 9
dispositive portion of the decision. 37 In Reinsurance claim was made in 1992 as determined by the Arbitration contract between the parties, dated July 11, 1996, was In denying the motion, the RTC found that there was no
Company of the Orient, Inc. v. Court of Appeals, 38 we held: Board and in accordance with Articles 2209 and 1169 of never consummated because respondent never returned clear basis for petitioner's plea to dismiss the case,
In Republic Surety and Insurance the Civil Code. The actual base for the computation of legal the proposed agreement bearing its written acceptance or pursuant to Section 7 of the Arbitration Law. The RTC said
Company, Inc. v. Intermediate interest shall be on the amount finally conformity nor did respondent open the Irrevocable Letter that the provision directed the court concerned only to stay
Appellate Court, the Court applying adjudged. 40 Further, when the judgment awarding a sum of Credit at sight. Petitioner contended that the controversy the action or proceeding brought upon an issue arising out
the above doctrine said: of money becomes final and executory, the rate of legal between the parties was whether or not the alleged of an agreement providing for the arbitration thereof, but
". . . We clarify, in other interest shall be 12% per annum from such finality until its contract between the parties was legally in existence and did not impose the sanction of dismissal. However, the RTC
words, what we did satisfaction, this interim period being deemed to be by then the RTC was not the proper forum to ventilate such issue. It did not find the suspension of the proceedings warranted,
affirm. What is involved an equivalent to a forbearance of credit. 41 claimed that the contract contained an arbitration clause, since the Arbitration Law contemplates an arbitration
here is not what is WHEREFORE, the petition is GRANTED in part. The to wit: EDACSa proceeding that must be conducted in the Philippines
ordinarily regarded as a appealed decision is MODIFIED in that the amount of ARBITRATION under the jurisdiction and control of the RTC; and before an
clerical error in the P74,035,503.50 shall earn legal interest of six percent (6%) Any dispute which the Buyer and arbitrator who resides in the country; and that the arbitral
dispositive part of the from 1992. A twelve percent (12%) interest, in lieu of six Seller may not be able to settle by award is subject to court approval, disapproval and
decision of the Court of percent (6%), shall be imposed on such amount upon mutual agreement shall be settled modification, and that there must be an appeal from the
First Instance, which finality of this decision until the payment thereof.SIDEaA by arbitration in the City of New judgment of the RTC. The RTC found that the arbitration
type of error is perhaps SO ORDERED. York before the American clause in question contravened these procedures, i.e., the
best typified by an error ||| (National Power Corp. v. Alonzo-Legasto, G.R. No. 148318, Arbitration Association. The arbitration clause contemplated an arbitration proceeding
in arithmetical [November 22, 2004], 485 PHIL 732-763) Arbitration Award shall be final and in New York before a non-resident arbitrator (American
computation. At the binding on both parties. 5 Arbitration Association); that the arbitral award shall be
same time, what is SECOND DIVISION that respondent must first comply with the final and binding on both parties. The RTC said that to
involved here is not a [G.R. No. 175404. January 31, 2011.] arbitration clause before resorting to court, thus, the apply Section 7 of the Arbitration Law to such an
correction of an CARGILL PHILIPPINES, RTC must either dismiss the case or suspend the agreement would result in disregarding the other sections
erroneous judgment or INC., petitioner, vs. SAN proceedings and direct the parties to proceed with of the same law and rendered them useless and mere
dispositive portion of a FERNANDO REGALA TRADING, arbitration, pursuant to Sections 6 6 and 7 7 of surplusages.
judgment. What we INC.,respondent. Republic Act (R.A.) No. 876, or the Arbitration Law. Petitioner filed its Motion for Reconsideration, which the
believe is involved here DECISION Respondent filed an Opposition, wherein it argued that the RTC denied in an Order 10 dated November 25, 1998.
is in the nature of PERALTA, J p: RTC has jurisdiction over the action for rescission of Petitioner filed a petition for certiorari with the CA raising
an inadvertent omission Before us is a petition for review on certiorari seeking to contract and could not be changed by the subject the sole issue that the RTC acted in excess of jurisdiction or
on the part of the Court of reverse and set aside the Decision 1 dated July 31, 2006 arbitration clause. It cited cases wherein arbitration with grave abuse of discretion in refusing to dismiss or at
First Instance (which and the Resolution 2 dated November 13, 2006 of the Court clauses, such as the subject clause in the contract, had been least suspend the proceedings a quo, despite the fact that
should have been of Appeals (CA) in CA G.R. SP No. 50304. struck down as void for being contrary to public policy the party's agreement to arbitrate had not been complied
noticed by private The factual antecedents are as follows: since it provided that the arbitration award shall be final with.
respondent's counsel On June 18, 1998, respondent San Fernando Regala and binding on both parties, thus, ousting the courts of Respondent filed its Comment and Reply. The parties were
who had prepared the Trading, Inc. filed with the Regional Trial Court (RTC) of jurisdiction. then required to file their respective Memoranda.
complaint), of what Makati City a Complaint for Rescission of Contract with In its Reply, petitioner maintained that the cited decisions On July 31, 2006, the CA rendered its assailed Decision
might be described as a Damages 3 against petitioner Cargill Philippines, Inc. In its were already inapplicable, having been rendered prior to denying the petition and affirming the RTC Orders.
logical follow-through of Complaint, respondent alleged that it was engaged in the effectivity of the New Civil Code in 1950 and the In denying the petition, the CA found that stipulation
something set forth both buying and selling of molasses and petitioner was one of its Arbitration Law in 1953. providing for arbitration in contractual obligation is both
in the body of the decision various sources from whom it purchased molasses. In its Rejoinder, respondent argued that the arbitration valid and constitutional; that arbitration as an alternative
and in the dispositive Respondent alleged that it entered into a contract dated clause relied upon by petitioner is invalid and mode of dispute resolution has long been accepted in our
portion thereof : the July 11, 1996 with petitioner, wherein it was agreed upon unenforceable, considering that the requirements imposed jurisdiction and expressly provided for in the Civil Code;
inevitable follow- that respondent would purchase from petitioner 12,000 by the provisions of the Arbitration Law had not been that R.A. No. 876 (the Arbitration Law) also expressly
through, or translation metric tons of Thailand origin cane blackstrap molasses at complied with. aCHDST authorized the arbitration of domestic disputes. The CA
found error in the RTC's holding that Section 7 of R.A. No. Petitioner contends that as the defendant in the RTC, it provisions contained thereunder, including the arbitration prescribed in R.A. No. 876 when he ordered Gonzales to
876 was inapplicable to arbitration clause simply because presented two alternative defenses, i.e., the parties had not clause; that if respondent relies on said contract for its proceed with arbitration and appointed a sole arbitrator
the clause failed to comply with the requirements entered into any agreement upon which respondent as cause of action against petitioner, it must also consider after making the determination that there was indeed an
prescribed by the law. The CA found that there was nothing plaintiff can sue upon; and, assuming that such agreement itself bound by the rest of the terms and conditions arbitration agreement. It had been held that as long as a
in the Civil Code, or R.A. No. 876, that require that existed, there was an arbitration clause that should be contained thereunder notwithstanding that respondent court acts within its jurisdiction and does not gravely abuse
arbitration proceedings must be conducted only in the enforced, thus, the dispute must first be submitted to may find some provisions to be adverse to its position; that its discretion in the exercise thereof, any supposed error
Philippines and the arbitrators should be Philippine arbitration before an action can be instituted in court. respondent's citation of theGonzales case, decided in 2005, committed by it will amount to nothing more than an error
residents. It also found that the RTC ruling effectively Petitioner argues that under Section 1 (j) of Rule 16 of the to show that the validity of the contract cannot be the of judgment reviewable by a timely appeal and not
invalidated not only the disputed arbitration clause, but all Rules of Court, included as a ground to dismiss a complaint subject of the arbitration proceeding and that it is the RTC assailable by a special civil action of certiorari. 14
other agreements which provide for foreign arbitration. is when a condition precedent for filing the complaint has which has the jurisdiction to resolve the situation between In this case, petitioner raises before the CA the issue that
The CA did not find illegal or against public policy the not been complied with; and that submission to arbitration the parties herein, is not correct since in the resolution of the respondent Judge acted in excess of jurisdiction or with
arbitration clause so as to render it null and void or when such has been agreed upon is one such condition the Gonzales' motion for reconsideration in 2007, it had grave abuse of discretion in refusing to dismiss, or at least
ineffectual. CTSDAI precedent. Petitioner submits that the proceedings in the been ruled that an arbitration agreement is effective suspend, the proceedings a quo, despite the fact that the
Notwithstanding such findings, the CA still held that the RTC must be dismissed, or at least suspended, and the notwithstanding the fact that one of the parties thereto party's agreement to arbitrate had not been complied with.
case cannot be brought under the Arbitration Lawfor the parties be ordered to proceed with arbitration. IaAHCE repudiated the main contract which contained it. DEIHAa Notably, the RTC found the existence of the arbitration
purpose of suspending the proceedings before the RTC, On March 12, 2007, petitioner filed a We first address the procedural issue raised by respondent clause, since it said in its decision that "hardly disputed is
since in its Motion to Dismiss/Suspend proceedings, Manifestation 12 saying that the CA's rationale in declining that petitioner's petition for certiorari under Rule 65 filed the fact that the arbitration clause in question contravenes
petitioner alleged, as one of the grounds thereof, that the to order arbitration based on the 2005 Gonzales ruling had in the CA against an RTC Order denying a Motion to several provisions of the Arbitration Law . . . and to apply
subject contract between the parties did not exist or it was been modified upon a motion for reconsideration decided Dismiss/Suspend Proceedings and to Refer Controversy to Section 7 of the Arbitration Law to such an agreement
invalid; that the said contract bearing the arbitration clause in 2007; that the CA decision lost its legal basis, because it Voluntary Arbitration was a wrong remedy invoking would result in the disregard of the afore-cited sections
was never consummated by the parties, thus, it was proper had been ruled that the arbitration agreement can be Section 29 of R.A. No. 876, which provides: of the Arbitration Law and render them useless and mere
that such issue be first resolved by the court through an implemented notwithstanding that one of the parties Section 29. surplusages." However, notwithstanding the finding that an
appropriate trial; that the issue involved a question of fact thereto repudiated the contract which contained such . . . An appeal may be taken from an arbitration agreement existed, the RTC denied petitioner's
that the RTC should first resolve. Arbitration is not proper agreement based on the doctrine of separability. order made in a proceeding under motion and directed petitioner to file an answer.
when one of the parties repudiated the existence or validity In its Comment, respondent argues that certiorari under this Act, or from a judgment In La Naval Drug Corporation v. Court of Appeals, 15 it was
of the contract. Rule 65 is not the remedy against an order denying a entered upon an award held that R.A. No. 876 explicitly confines the court's
Petitioner's motion for reconsideration was denied in a Motion to Dismiss/Suspend Proceedings and To Refer through certiorari proceedings, but authority only to the determination of whether or not there
Resolution dated November 13, 2006. Controversy to Voluntary Arbitration. It claims thatthe such appeals shall be limited to is an agreement in writing providing for arbitration. In the
Hence, this petition. Arbitration Law which petitioner invoked as basis for its question of law. . . . . affirmative, the statute ordains that the court shall issue an
Petitioner alleges that the CA committed an error of law in Motion prescribed, under its Section 29, a remedy, i.e., To support its argument, respondent cites the case order summarily directing the parties to proceed with the
ruling that arbitration cannot proceed despite the fact that: appeal by a petition for review on certiorari under Rule 45. of Gonzales v. Climax Mining Ltd. 13 (Gonzales case), arbitration in accordance with the terms thereof. If the
(a) it had ruled, in its assailed decision, that the arbitration Respondent contends that theGonzales case, which was wherein we ruled the impropriety of a petition court, upon the other hand, finds that no such agreement
clause is valid, enforceable and binding on the parties; (b) decided in 2007, is inapplicable in this case, especially as to for certiorari under Rule 65 as a mode of appeal from exists, the proceedings shall be dismissed.
the case of Gonzales v. Climax Mining Ltd. 11 is inapplicable the doctrine of separability enunciated therein. Respondent an RTC Order directing the parties to arbitration. In issuing the Order which denied petitioner's Motion to
here; (c) parties are generally allowed, under the Rules of argues that even if the existence of the contract and the We find the cited case not in point. Dismiss/Suspend Proceedings and to Refer Controversy to
Court, to adopt several defenses, alternatively or arbitration clause is conceded, the decisions of the RTC and In the Gonzales case, Climax-Arimco filed before the RTC of Voluntary Arbitration, the RTC went beyond its authority of
hypothetically, even if such defenses are inconsistent with the CA declining referral of the dispute between the parties Makati a petition to compel arbitration underR.A. No. 876, determining only the issue of whether or not there is an
each other; and (d) the complaint filed by respondent with to arbitration would still be correct. This is so because pursuant to the arbitration clause found in the Addendum agreement in writing providing for arbitration by directing
the trial court is premature. respondent's complaint filed in Civil Case No. 98-1376 Contract it entered with Gonzales. Judge Oscar Pimentel of petitioner to file an answer, instead of ordering the parties
Petitioner alleges that the CA adopted inconsistent presents the principal issue of whether under the facts the RTC of Makati then directed the parties to arbitration to proceed to arbitration. In so doing, it acted in excess of
positions when it found the arbitration clause between the alleged in the complaint, respondent is entitled to rescind proceedings. Gonzales filed a petition for certiorari with Us its jurisdiction and since there is no plain, speedy, and
parties as valid and enforceable and yet in the same breath its contract with petitioner and for the latter to pay contending that Judge Pimentel acted with grave abuse of adequate remedy in the ordinary course of law, petitioner's
decreed that the arbitration cannot proceed because damages; that such issue constitutes a judicial question or discretion in immediately ordering the parties to proceed resort to a petition for certiorari is the proper remedy.
petitioner assailed the existence of the entire agreement one that requires the exercise of judicial function and with arbitration despite the proper, valid and timely raised We now proceed to the substantive issue of whether the CA
containing the arbitration clause. Petitioner claims the cannot be the subject of arbitration. argument in his Answer with counterclaim that the erred in finding that this case cannot be brought under the
inapplicability of the cited Gonzales case decided in 2005, Respondent contends that Section 8 of the Rules of Court, Addendum Contract containing the arbitration clause was arbitration law for the purpose of suspending the
because in the present case, it was respondent who had which allowed a defendant to adopt in the same action null and void. Climax-Arimco assailed the mode of review proceedings in the RTC.
filed the complaint for rescission and damages with the several defenses, alternatively or hypothetically, even if availed of by Gonzales, citing Section 29 of R.A. No. We find merit in the petition.
RTC, which based its cause of action against petitioner on such defenses are inconsistent with each other refers to 876 contending that certiorari under Rule 65 can be availed Arbitration, as an alternative mode of settling disputes, has
the alleged agreement dated July 11, 2006 between the allegations in the pleadings, such as complaint, of only if there was no appeal or any adequate remedy in long been recognized and accepted in our
parties; and that the same agreement contained the counterclaim, cross-claim, third-party complaint, answer, the ordinary course of law; that R.A. No. 876 provides for jurisdiction. 16 R.A. No. 876 17 authorizes arbitration of
arbitration clause sought to be enforced by petitioner in but not to a motion to dismiss. Finally, respondent claims an appeal from such order. We then ruled that Gonzales' domestic disputes. Foreign arbitration, as a system of
this case. Thus, whether petitioner assails the genuineness that petitioner's argument is premised on the existence of a petition for certiorari should be dismissed as it was filed in settling commercial disputes of an international character,
and due execution of the agreement, the fact remains that contract with respondent containing a provision for lieu of an appeal bycertiorari which was the prescribed is likewise recognized. 18 The enactment of R.A. No.
the agreement sued upon provides for an arbitration arbitration. However, its reliance on the contract, which it remedy under R.A. No. 876 and the petition was filed far 9285 on April 2, 2004 further institutionalized the use of
clause; that respondent cannot use the provisions favorable repudiates, is inappropriate. beyond the reglementary period. HIEAcC alternative dispute resolution systems, including
to him and completely disregard those that are In its Reply, petitioner insists that respondent filed an We found that Gonzales' petition for certiorari raises a arbitration, in the settlement of disputes. 19 DaCEIc
unfavorable, such as the arbitration clause. action for rescission and damages on the basis of the question of law, but not a question of jurisdiction; that A contract is required for arbitration to take place and to be
contract, thus, respondent admitted the existence of all the Judge Pimentel acted in accordance with the procedure binding. 20 Submission to arbitration is a contract 21 and a
clause in a contract providing that all matters in dispute arbitration clause that the case referred to is the case invalid or did not come into existence, since the arbitration
between the parties shall be referred to arbitration is a itself. A party cannot actually filed by Gonzales before agreement shall be treated as a separate agreement
contract. 22 The provision to submit to arbitration any rely on the contract the DENR Panel of Arbitrators, independent of the main contract. To reiterate a contrary
dispute arising therefrom and the relationship of the and claim rights or which was for the nullification of ruling would suggest that a party's mere repudiation of the
parties is part of the contract and is itself a contract. 23 obligations under it the main contract on the ground of main contract is sufficient to avoid arbitration and that is
In this case, the contract sued upon by respondent provides and at the same time fraud, as it had already been exactly the situation that the separability doctrine sought
for an arbitration clause, to wit: impugn its existence or determined that the case should to avoid. Thus, we find that even the party who has
ARBITRATION validity. Indeed, have been brought before the repudiated the main contract is not prevented from
Any dispute which the Buyer and litigants are enjoined regular courts involving as it did enforcing its arbitration clause.
Seller may not be able to settle by from taking judicial issues. 26 Moreover, it is worthy to note that respondent filed a
mutual agreement shall be settled inconsistent positions. . In so ruling that the validity of the contract containing the complaint for rescission of contract and damages with the
by arbitration in the City of New .. arbitration agreement does not affect the applicability of RTC. In so doing, respondent alleged that a contract exists
York before the American Consequently, the petitioner herein the arbitration clause itself, we then applied the doctrine of between respondent and petitioner. It is that contract
Arbitration Association, The cannot claim that the contract was separability, thus: which provides for an arbitration clause which states that
Arbitration Award shall be final and never consummated and, at the The doctrine of separability, or "any dispute which the Buyer and Seller may not be able to
binding on both parties. same time, invokes the arbitration severability as other writers call it, settle by mutual agreement shall be settled before the City
The CA ruled that arbitration cannot be ordered in this clause provided for under the enunciates that an arbitration of New York by the American Arbitration Association. The
case, since petitioner alleged that the contract between the contract which it alleges to be non- agreement is independent of the arbitration agreement clearly expressed the parties'
parties did not exist or was invalid and arbitration is not existent or invalid. Petitioner main contract. The arbitration intention that any dispute between them as buyer and
proper when one of the parties repudiates the existence or claims that private respondent's agreement is to be treated as a seller should be referred to arbitration. It is for the
validity of the contract. Thus, said the CA: complaint lacks a cause of action separate agreement and the arbitrator and not the courts to decide whether a contract
Notwithstanding our ruling on the due to the absence of any valid arbitration agreement does not between the parties exists or is valid.
validity and enforceability of the contract between the parties. automatically terminate when the Respondent contends that assuming that the existence of
assailed arbitration clause Apparently, the arbitration clause is contract of which it is a part comes the contract and the arbitration clause is conceded, the CA's
providing for foreign arbitration, it being invoked merely as a fallback to an end. decision declining referral of the parties' dispute to
is our considered opinion that the position. The petitioner must first The separability of the arbitration arbitration is still correct. It claims that its complaint in the
case at bench still cannot be adduce evidence in support of its agreement is especially significant RTC presents the issue of whether under the facts alleged,
brought underthe Arbitration claim that there is no valid contract to the determination of whether the it is entitled to rescind the contract with damages; and that
Law for the purpose of suspending between them and should the court invalidity of the main contract also issue constitutes a judicial question or one that requires the
the proceedings before the trial a quo find the claim to be nullifies the arbitration clause. exercise of judicial function and cannot be the subject of an
court. We note that in its Motion to meritorious, the parties may then Indeed, the doctrine denotes that arbitration proceeding. Respondent cites our ruling
Dismiss/Suspend Proceedings, etc., be spared the rigors and expenses the invalidity of the main contract, inGonzales, wherein we held that a panel of arbitrators is
petitioner Cargill alleged, as one of that arbitration in a foreign land also referred to as the "container" bereft of jurisdiction over the complaint for declaration of
the grounds thereof, that the would surely entail. 24 IcESaA contract, does not affect the validity nullity/or termination of the subject contracts on the
alleged contract between the However, the Gonzales case, 25 which the CA relied upon of the arbitration agreement. grounds of fraud and oppression attendant to the execution
parties do not legally exist or is for not ordering arbitration, had been modified upon a Irrespective of the fact that the of the addendum contract and the other contracts
invalid. As posited by petitioner, it motion for reconsideration in this wise: main contract is invalid, the emanating from it, and that the complaint should have been
is their contention that the said . . . The adjudication of the arbitration clause/agreement still filed with the regular courts as it involved issues which are
contract, bearing the arbitration petition in G.R. No. 167994 remains valid and enforceable. 27 judicial in nature.
clause, was never consummated by effectively modifies part of the Respondent argues that the separability doctrine is not Such argument is misplaced and respondent cannot rely on
the parties. That being the case, it is Decision dated 28 February 2005 applicable in petitioner's case, since in the Gonzalescase, the Gonzales case to support its argument.
but proper that such issue be first in G.R. No. 161957. Hence, we Climax-Arimco sought to enforce the arbitration clause of In Gonzales, petitioner Gonzales filed a complaint before
resolved by the court through an now hold that the validity of the its contract with Gonzales and the former's move was the Panel of Arbitrators, Region II, Mines and Geosciences
appropriate trial. The issue contract containing the premised on the existence of a valid contract; while Bureau, of the Department of Environment and Natural
involves a question of fact that the agreement to submit to Gonzales, who resisted the move of Climax-Arimco for Resources (DENR) against respondents Climax-Mining Ltd.,
trial court should first resolve. arbitration does not affect the arbitration, did not deny the existence of the contract but Climax-Arimco and Australasian Philippines Mining, Inc.,
Arbitration is not proper when one applicability of the arbitration merely assailed the validity thereof on the ground of fraud seeking the declaration of nullity or termination of the
of the parties repudiates the clause itself. A contrary ruling and oppression. Respondent claims that in the case before addendum contract and the other contracts emanating
existence or validity of the contract. would suggest that a party's Us, petitioner who is the party insistent on arbitration also from it on the grounds of fraud and oppression. The Panel
Apropos is Gonzales v. Climax mere repudiation of the main claimed in their Motion to Dismiss/Suspend Proceedings dismissed the complaint for lack of jurisdiction. However,
Mining Ltd., 452 SCRA 607, (G.R. No. contract is sufficient to avoid that the contract sought by respondent to be rescinded did the Panel, upon petitioner's motion for reconsideration,
161957), where the Supreme Court arbitration. That is exactly the not exist or was not consummated; thus, there is no room ruled that it had jurisdiction over the dispute maintaining
held that: situation that the separability for the application of the separability doctrine, since there that it was a mining dispute, since the subject complaint
The question of doctrine, as well as is no container or main contract or an arbitration clause to arose from a contract between the parties which involved
validity of the contract jurisprudence applying it, seeks speak of. SDTcAH the exploration and exploitation of minerals over the
containing the to avoid. We add that when it was We are not persuaded. disputed area. Respondents assailed the order of the Panel
agreement to submit to declared in G.R. No. 161957 that Applying the Gonzales ruling, an arbitration agreement of Arbitrators via a petition for certiorari before the CA. The
arbitration will affect the case should not be brought for which forms part of the main contract shall not be regarded CA granted the petition and declared that the Panel of
the applicability of the arbitration, it should be clarified as invalid or non-existent just because the main contract is Arbitrators did not have jurisdiction over the complaint,
since its jurisdiction was limited to the resolution of mining Arbitration before the Panel of
disputes, such as those which raised a question of fact or Arbitrators is proper only when
matter requiring the technical knowledge and experience there is a disagreement between
of mining authorities and not when the complaint alleged the parties as to some provisions of
fraud and oppression which called for the interpretation the contract between them, which
and application of laws. The CA further ruled that the needs the interpretation and the
petition should have been settled through arbitration application of that particular
under R.A. No. 876 — the Arbitration Law — as provided knowledge and expertise possessed
under the addendum contract. cCSDaI by members of that Panel. It is not
On a review on certiorari, we affirmed the CA's finding that proper when one of the parties
the Panel of Arbitrators who, under R.A. No. 7942of the repudiates the existence or validity
Philippine Mining Act of 1995, has exclusive and original of such contract or agreement on
jurisdiction to hear and decide mining disputes, such as the ground of fraud or oppression
mining areas, mineral agreements, FTAAs or permits and as in this case. The validity of the
surface owners, occupants and contract cannot be subject of
claimholders/concessionaires, is bereft of jurisdiction over arbitration proceedings. Allegations
the complaint for declaration of nullity of the addendum of fraud and duress in the execution
contract; thus, the Panels' jurisdiction is limited only to of a contract are matters within the
those mining disputes which raised question of facts or jurisdiction of the ordinary courts
matters requiring the technical knowledge and experience of law. These questions are legal in
of mining authorities. We then said: nature and require the application
In Pearson v. Intermediate Appellate and interpretation of laws and
Court, this Court observed that the jurisprudence which is necessarily
trend has been to make the a judicial function. 29
adjudication of mining cases a In fact, We even clarified in our resolution on Gonzales'
purely administrative matter. motion for reconsideration that "when we declared that the
Decisions of the Supreme Court on case should not be brought for arbitration, it should be
mining disputes have recognized a clarified that the case referred to is the case actually filed
distinction between (1) the by Gonzales before the DENR Panel of Arbitrators, which
primary powers granted by was for the nullification of the main contract on the ground
pertinent provisions of law to the of fraud, as it had already been determined that the case
then Secretary of Agriculture and should have been brought before the regular courts
Natural Resources (and the bureau involving as it did judicial issues." We made such
directors) of an executive or clarification in our resolution of the motion for
administrative nature, such as reconsideration after ruling that the parties in that case can
granting of license, permits, lease proceed to arbitration under the Arbitration Law, as
and contracts, or approving, provided under the Arbitration Clause in their Addendum
rejecting, reinstating or canceling Contract. AaSIET
applications, or deciding conflicting WHEREFORE, the petition is GRANTED. The Decision dated
applications, and (2) controversies July 31, 2006 and the Resolution dated November 13, 2006
or disagreements of civil or of the Court of Appeals in CA-G.R. SP No. 50304
contractual nature between are REVERSED and SET ASIDE. The parties are
litigants which are questions of a hereby ORDERED to SUBMIT themselves to the arbitration
judicial nature that may be of their dispute, pursuant to their July 11, 1996 agreement.
adjudicated only by the courts of SO ORDERED.
justice. This distinction is carried ||| (Cargill Philippines, Inc. v. San Fernando Regala Trading,
on even in Rep. Act No. 7942. 28 Inc., G.R. No. 175404, [January 31, 2011])
We found that since the complaint filed before the DENR
Panel of Arbitrators charged respondents with
disregarding and ignoring the addendum contract, and
acting in a fraudulent and oppressive manner against
petitioner, the complaint filed before the Panel was not a
dispute involving rights to mining areas, or was it a dispute
involving claimholders or concessionaires, but essentially
judicial issues. We then said that the Panel of Arbitrators
did not have jurisdiction over such issue, since it does not
involve the application of technical knowledge and
expertise relating to mining. It is in this context that we
said that:

Potrebbero piacerti anche