UCH-II GAS DEVELOPMENT PROJECT ACTIVITY SCHEDULE 23-Sep-13 09:40

Activity ID Activity Name Original Start Finish 2013 2014


Duration
Sep Oct Nov Dec Jan Feb Mar Apr May
UCH-II GAS DEVELOPMENT PROJECT 247 25-Aug-13 29-Apr-14 29-Apr-14, UCH-II GAS DEVELO

CIVIL 247 25-Aug-13 29-Apr-14 29-Apr-14, CIVIL

CIVIL WORK FOR UCH-II PLANT 247 25-Aug-13 29-Apr-14 29-Apr-14, CIVIL WORK FOR U
A6410 PROJECT START 0 25-Aug-13 PROJECT START
TANKS 111 07-Sep-13 26-Dec-13 26-Dec-13, TANKS
RAW WATER TANK 50 07-Sep-13 26-Oct-13 26-Oct-13, RAW WATER TANK
A1370 LAYOUT MARKING 1 07-Sep-13* 07-Sep-13 LAYOUT MARKING
A1380 EXCAVATION 2 08-Sep-13 09-Sep-13 EXCAVATION
A1400 LEVELING & COMPACTION 3 10-Sep-13 12-Sep-13 LEVELING & COMPACTION
A1420 LEAN WORK 1 13-Sep-13 13-Sep-13 LEAN WORK
A1430 RE-BAR WORK 6 24-Sep-13 29-Sep-13 RE-BAR WORK
A1440 FORM WORK 6 28-Sep-13 03-Oct-13 FORM WORK
A1450 PVC CONDUITS INSTALLATION 1 04-Oct-13 04-Oct-13 PVC CONDUITS INSTALLATION
A1470 CONCRETE POURING 1 05-Oct-13 05-Oct-13 CONCRETE POURING
A1480 REMOVAL OF FORM WORK 5 06-Oct-13 10-Oct-13 REMOVAL OF FORM WORK
A6395 BACK FILLING 16 11-Oct-13 26-Oct-13 BACK FILLING
DIESEL STORAGE TANK 57 11-Sep-13 06-Nov-13 06-Nov-13, DIESEL STORAGE TANK
A1250 LAYOUT MARKING 1 11-Sep-13* 11-Sep-13 LAYOUT MARKING
A1260 EXCAVATION 2 12-Sep-13 13-Sep-13 EXCAVATION
A1280 LEVELING & COMPACTION 3 17-Sep-13 19-Sep-13 LEVELING & COMPACTION
A1300 LEAN WORK 1 23-Sep-13 23-Sep-13 LEAN WORK
A1310 RE-BAR WORK 10 24-Sep-13 03-Oct-13 RE-BAR WORK
A1320 FORM WORK 10 29-Sep-13 08-Oct-13 FORM WORK
A1330 PVC CONDUITS INSTALLATION 5 06-Oct-13 10-Oct-13 PVC CONDUITS INSTALLATION
A1350 CONCRETE POURING 1 11-Oct-13 11-Oct-13 CONCRETE POURING
A1360 REMOVAL OF FORM WORK 5 12-Oct-13 16-Oct-13 REMOVAL OF FORM WORK
A6350 INSTALLATION OF GEO-MEMBRANE WALL 5 17-Oct-13 21-Oct-13 INSTALLATION OF GEO-MEMBRANE WALL
A6355 BACK FILLING 15 22-Oct-13 05-Nov-13 BACK FILLING
A6380 CONCRETE WORK OVER GEOMEMBRANE 1 06-Nov-13 06-Nov-13 CONCRETE WORK OVER GEOMEMBRANE
DEMIN STORAGE TANK 54 03-Nov-13 26-Dec-13 26-Dec-13, DEMIN STORAGE TANK
A1490 LAYOUT MARKING 1 03-Nov-13* 04-Nov-13 LAYOUT MARKING
A1500 EXCAVATION 2 04-Nov-13 06-Nov-13 EXCAVATION
A1520 LEVELING & COMPACTION 3 06-Nov-13 09-Nov-13 LEVELING & COMPACTION
A1540 LEAN WORK 1 09-Nov-13 10-Nov-13 LEAN WORK
A1550 RE-BAR WORK 10 10-Nov-13 20-Nov-13 RE-BAR WORK
A1560 FORM WORK 10 20-Nov-13 30-Nov-13 FORM WORK
A1570 PVC CONDUITS INSTALLATION 5 30-Nov-13 05-Dec-13 PVC CONDUITS INSTALLATION
A1590 CONCRETE POURING 1 05-Dec-13 06-Dec-13 CONCRETE POURING
A1600 REMOVAL OF FORM WORK 5 06-Dec-13 11-Dec-13 REMOVAL OF FORM WORK
A6400 BACK FILLING 15 11-Dec-13 26-Dec-13 BACK FILLING
PIPING 88 10-Sep-13 07-Dec-13 07-Dec-13, PIPING
PIPE RACK-B 34 10-Sep-13 13-Oct-13 13-Oct-13, PIPE RACK-B
A3430 LAYOUT MARKING 1 10-Sep-13* 10-Sep-13 LAYOUT MARKING
A3440 EXCAVATION 5 11-Sep-13 15-Sep-13 EXCAVATION
A3450 LEVELING & COMPACTION 4 14-Sep-13 17-Sep-13 LEVELING & COMPACTION
A3460 LEAN WORK 2 18-Sep-13 19-Sep-13 LEAN WORK
A3470 RE-BAR WORK 8 20-Sep-13 27-Sep-13 RE-BAR WORK
A3480 FORM WORK FOR FOOTING 8 28-Sep-13 05-Oct-13 FORM WORK FOR FOOTING
A3490 FOOTING POURING 2 04-Oct-13 06-Oct-13 FOOTING POURING
A3500 FORM WORK FOR PEDESTALS 5 04-Oct-13 09-Oct-13 FORM WORK FOR PEDESTALS

Actual Work Critical Remaining Work Summary Page 1 of 18 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


UCH-II GAS DEVELOPMENT PROJECT ACTIVITY SCHEDULE 23-Sep-13 09:40

Activity ID Activity Name Original Start Finish 2013 2014


Duration
Sep Oct Nov Dec Jan Feb Mar Apr May
A3510 EMBEDDED ITEMS INSTALLATION 2 09-Oct-13 11-Oct-13 EMBEDDED ITEMS INSTALLATION
A3520 PEDESTALS POURING 1 10-Oct-13 11-Oct-13 PEDESTALS POURING
A3530 REMOVAL OF FORM WORK 4 09-Oct-13 13-Oct-13 REMOVAL OF FORM WORK
PIPE RACK-F 33 17-Sep-13 20-Oct-13 20-Oct-13, PIPE RACK-F
A3650 LAYOUT MARKING 2 17-Sep-13* 18-Sep-13 LAYOUT MARKING
A3660 EXCAVATION 2 18-Sep-13 20-Sep-13 EXCAVATION
A3670 LEVELING & COMPACTION 4 20-Sep-13 23-Sep-13 LEVELING & COMPACTION
A3680 LEAN WORK 1 24-Sep-13 24-Sep-13 LEAN WORK
A3690 RE-BAR WORK 6 25-Sep-13 01-Oct-13 RE-BAR WORK
A3700 FORM WORK FOR FOOTING 6 01-Oct-13 07-Oct-13 FORM WORK FOR FOOTING
A3710 FOOTING POURING 3 05-Oct-13 08-Oct-13 FOOTING POURING
A3720 FORM WORK FOR PEDESTALS 5 07-Oct-13 11-Oct-13 FORM WORK FOR PEDESTALS
A3730 EMBEDDED ITEMS INSTALLATION 4 11-Oct-13 14-Oct-13 EMBEDDED ITEMS INSTALLATION
A3740 PEDESTALS POURING 3 14-Oct-13 17-Oct-13 PEDESTALS POURING
A3750 REMOVAL OF FORM WORK 4 16-Oct-13 20-Oct-13 REMOVAL OF FORM WORK
PIPE RACK-C 38 03-Oct-13 09-Nov-13 09-Nov-13, PIPE RACK-C
A3540 LAYOUT MARKING 2 03-Oct-13* 04-Oct-13 LAYOUT MARKING
A3550 EXCAVATION 5 05-Oct-13 09-Oct-13 EXCAVATION
A3560 LEVELING & COMPACTION 6 07-Oct-13 13-Oct-13 LEVELING & COMPACTION
A3570 LEAN WORK 6 11-Oct-13 17-Oct-13 LEAN WORK
A3580 RE-BAR WORK 11 12-Oct-13 23-Oct-13 RE-BAR WORK
A3590 FORM WORK FOR FOOTING 11 15-Oct-13 26-Oct-13 FORM WORK FOR FOOTING
A3600 FOOTING POURING 5 22-Oct-13 27-Oct-13 FOOTING POURING
A3610 FORM WORK FOR PEDESTALS 7 25-Oct-13 01-Nov-13 FORM WORK FOR PEDESTALS
A3620 EMBEDDED ITEMS INSTALLATION 5 27-Oct-13 01-Nov-13 EMBEDDED ITEMS INSTALLATION
A3630 PEDESTALS POURING 4 31-Oct-13 03-Nov-13 PEDESTALS POURING
A3640 REMOVAL OF FORM WORK 6 04-Nov-13 09-Nov-13 REMOVAL OF FORM WORK
PIPE RACK-A 49 08-Oct-13 25-Nov-13 25-Nov-13, PIPE RACK-A
A1610 LAYOUT MARKING 2 08-Oct-13* 09-Oct-13 LAYOUT MARKING
A1620 EXCAVATION 4 09-Oct-13 13-Oct-13 EXCAVATION
A1640 LEVELING & COMPACTION 5 13-Oct-13 18-Oct-13 LEVELING & COMPACTION
A1660 LEAN WORK 4 18-Oct-13 22-Oct-13 LEAN WORK
A1670 RE-BAR WORK 9 22-Oct-13 31-Oct-13 RE-BAR WORK
A1680 FORM WORK FOR FOOTING 9 31-Oct-13 09-Nov-13 FORM WORK FOR FOOTING
A1690 FOOTING POURING 3 09-Nov-13 12-Nov-13 FOOTING POURING
A1700 FORM WORK FOR PEDESTALS 3 12-Nov-13 15-Nov-13 FORM WORK FOR PEDESTALS
A1705 REMOVAL OF FORM WORK 4 14-Nov-13 18-Nov-13 REMOVAL OF FORM WORK
A1710 EMBEDDED ITEMS INSTALLATION 4 18-Nov-13 22-Nov-13 EMBEDDED ITEMS INSTALLATION
A1720 PEDESTALS POURING 3 22-Nov-13 25-Nov-13 PEDESTALS POURING
PIPE RACK-G 44 24-Oct-13 07-Dec-13 07-Dec-13, PIPE RACK-G
A3760 LAYOUT MARKING 2 24-Oct-13 25-Oct-13 LAYOUT MARKING
A3770 EXCAVATION 3 25-Oct-13 28-Oct-13 EXCAVATION
A3780 LEVELING & COMPACTION 4 27-Oct-13 31-Oct-13 LEVELING & COMPACTION
A3790 LEAN WORK 4 31-Oct-13 04-Nov-13 LEAN WORK
A3800 RE-BAR WORK 12 02-Nov-13 14-Nov-13 RE-BAR WORK
A3810 FORM WORK FOR FOOTING 7 14-Nov-13 21-Nov-13 FORM WORK FOR FOOTING
A3820 FOOTING POURING 3 20-Nov-13 24-Nov-13 FOOTING POURING
A3830 FORM WORK FOR PEDESTALS 5 23-Nov-13 28-Nov-13 FORM WORK FOR PEDESTALS
A3840 EMBEDDED ITEMS INSTALLATION 3 26-Nov-13 29-Nov-13 EMBEDDED ITEMS INSTALLATION
A3850 PEDESTALS POURING 3 27-Nov-13 30-Nov-13 PEDESTALS POURING
A3860 REMOVAL OF FORM WORK 8 29-Nov-13 07-Dec-13 REMOVAL OF FORM WORK

Actual Work Critical Remaining Work Summary Page 2 of 18 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


UCH-II GAS DEVELOPMENT PROJECT ACTIVITY SCHEDULE 23-Sep-13 09:40

Activity ID Activity Name Original Start Finish 2013 2014


Duration
Sep Oct Nov Dec Jan Feb Mar Apr May
BUILDINGS 244 28-Aug-13 29-Apr-14 29-Apr-14, BUILDINGS
MCC ROOM 244 28-Aug-13 29-Apr-14 29-Apr-14, MCC ROOM
FOOTINGS 63 28-Aug-13 29-Oct-13 29-Oct-13, FOOTINGS
A5700 LAYOUT MARKING 2 28-Aug-13* 29-Aug-13 LAYOUT MARKING
A5710 EXCAVATION 10 09-Sep-13 18-Sep-13 EXCAVATION
A5720 LEVELING & COMPACTION 10 22-Sep-13 01-Oct-13 LEVELING & COMPACTION
A5725 TERMITE PROFFING 4 01-Oct-13 04-Oct-13 TERMITE PROFFING
A5730 LEAN WORK 6 05-Oct-13 10-Oct-13 LEAN WORK
A5740 RE-BAR WORK 16 07-Oct-13 22-Oct-13 RE-BAR WORK
A5750 FORM WORK FOR FOOTING 16 09-Oct-13 24-Oct-13 FORM WORK FOR FOOTING
A5770 CONCRETE POURING 5 25-Oct-13 29-Oct-13 CONCRETE POURING
STEP COLUMN 19 30-Oct-13 17-Nov-13 17-Nov-13, STEP COLUMN
A5820 RE-BAR WORK 12 30-Oct-13 10-Nov-13 RE-BAR WORK
A5830 FORM WORK FOR COLUMNS UP TO PLINTH LEVELS 12 02-Nov-13 13-Nov-13 FORM WORK FOR COLUMNS UP TO PLINTH LEVELS
A5850 CONCRETE POURING 4 14-Nov-13 17-Nov-13 CONCRETE POURING
PLINTH BEAMS 25 08-Nov-13 02-Dec-13 02-Dec-13, PLINTH BEAMS
A5860 RE-BAR WORK 15 08-Nov-13 22-Nov-13 RE-BAR WORK
A5870 FORM WORK 15 11-Nov-13 25-Nov-13 FORM WORK
A5890 CONCRETE POURING 2 26-Nov-13 27-Nov-13 CONCRETE POURING
A5980 LAYING OF DAMP PROOF COURSE 5 28-Nov-13 02-Dec-13 LAYING OF DAMP PROOF COURSE
COLUMNS UP TO SLAB 36 03-Dec-13 07-Jan-14 07-Jan-14, COLUMNS UP TO SLAB
A5900 RE-BAR WORK 20 03-Dec-13 22-Dec-13 RE-BAR WORK
A5910 FORM WORK FOR COLUMNS UP TO SLAB LEVELS 20 14-Dec-13 02-Jan-14 FORM WORK FOR COLUMNS UP TO SLAB LEVELS
A5930 CONCRETE WORK 5 03-Jan-14 07-Jan-14 CONCRETE WORK
SLAB 55 08-Jan-14 03-Mar-14 03-Mar-14, SLAB
A5940 FORM WORK 30 08-Jan-14 06-Feb-14 FORM WORK
A5950 RE-BAR WORK 15 28-Jan-14 11-Feb-14 RE-BAR WORK
A5955 ELECTRICAL CONDUITS 4 12-Feb-14 15-Feb-14 ELECTRICAL CONDUITS
A5970 CONCRETE WORK 1 16-Feb-14 16-Feb-14 CONCRETE WORK
A6460 REMOVAL OF FORM WORK 15 17-Feb-14 03-Mar-14 REMOVAL OF FORM WORK
CABLE TRENCHES 29 02-Feb-14 02-Mar-14 02-Mar-14, CABLE TRENCHES
A6420 LEAN CONCRETE 2 02-Feb-14 03-Feb-14 LEAN CONCRETE
A6480 RE-BAR WORK 6 04-Feb-14 09-Feb-14 RE-BAR WORK
A6490 FORM WORK 6 10-Feb-14 15-Feb-14 FORM WORK
A6500 CONCRETE WORK 2 16-Feb-14 17-Feb-14 CONCRETE WORK
A6510 PRE-CAST RCC SLAB 7 18-Feb-14 24-Feb-14 PRE-CAST RCC SLAB
A6520 COVERING OF TRENCHES 6 25-Feb-14 02-Mar-14 COVERING OF TRENCHES
BRICK WORKS 40 25-Feb-14 05-Apr-14 05-Apr-14, BRICK WORKS
A5990 LAYING OF BURNT BRICKS 20 25-Feb-14 16-Mar-14 LAYING OF BURNT BRICKS
A6000 LAYING OF FIRST CLASS FACING BRICKS 35 02-Mar-14 05-Apr-14 LAYING OF FIRST CLASS FACING BRICKS
ELECTRICAL WORK 31 28-Feb-14 30-Mar-14 30-Mar-14, ELECTRICAL WORK
A11070 LAYING OF ELECTRICAL CONDUITS & CABLES ETC. 31 28-Feb-14 30-Mar-14 LAYING OF ELECTRICAL CONDUITS & CABLES ET
ROOF TREATMENT 20 02-Mar-14 21-Mar-14 21-Mar-14, ROOF TREATMENT
A6030 LAYING OF BITUMEN & OTHER ITEMS 20 02-Mar-14 21-Mar-14 LAYING OF BITUMEN & OTHER ITEMS
PLASTER WORKS 25 02-Mar-14 26-Mar-14 26-Mar-14, PLASTER WORKS
A6010 PLASTER WORK INTERNAL AT ALL LEVELS 25 02-Mar-14 26-Mar-14 PLASTER WORK INTERNAL AT ALL LEVELS
A6020 PLASTER WORK EXTERNAL AT ALL LEVELS 10 02-Mar-14 11-Mar-14 PLASTER WORK EXTERNAL AT ALL LEVELS
TILES WORK AT ALL LEVELS 15 12-Mar-14 26-Mar-14 26-Mar-14, TILES WORK AT ALL LEVELS
A6060 INSTALLATION OF TILES AT ALL LEVELS 15 12-Mar-14 26-Mar-14 INSTALLATION OF TILES AT ALL LEVELS
A6070 NON-SKID GLAZED CERAMIC TILES AT ALL LEVELS 14 12-Mar-14 25-Mar-14 NON-SKID GLAZED CERAMIC TILES AT ALL LEVELS

Actual Work Critical Remaining Work Summary Page 3 of 18 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


UCH-II GAS DEVELOPMENT PROJECT ACTIVITY SCHEDULE 23-Sep-13 09:40

Activity ID Activity Name Original Start Finish 2013 2014


Duration
Sep Oct Nov Dec Jan Feb Mar Apr May
A6080 GLAZED CERAMIC TILES ON WALLS AT ALL LEVELS 13 12-Mar-14 24-Mar-14 GLAZED CERAMIC TILES ON WALLS AT ALL LEVELS
A6090 FLOOR TILES SKIRTING 14 12-Mar-14 25-Mar-14 FLOOR TILES SKIRTING
STEEL WORK 15 02-Mar-14 16-Mar-14 16-Mar-14, STEEL WORK
A6100 STEEL DOOR FRAMES INSTALLATION 15 02-Mar-14 16-Mar-14 STEEL DOOR FRAMES INSTALLATION
A6110 STEEL DOOR WITH DOOR FRAMES INSTALLATIONS 15 02-Mar-14 16-Mar-14 STEEL DOOR WITH DOOR FRAMES INSTALLATIONS
A6120 STEEL GRILLS INSTALLATION 10 02-Mar-14 11-Mar-14 STEEL GRILLS INSTALLATION
ALUMINUM WORK 15 02-Mar-14 16-Mar-14 16-Mar-14, ALUMINUM WORK
A6130 ALUMINUM SLIDING WINDOWS INSTALLATION 15 02-Mar-14 16-Mar-14 ALUMINUM SLIDING WINDOWS INSTALLATION
A6140 ALUMINUM GLAZED DOORS AND PANNELS INSTALLATION
15 02-Mar-14 16-Mar-14 ALUMINUM GLAZED DOORS AND PANNELS INSTALLATION
A6150 ALUMINUM SLIDING VENTILATORS INSTALLATION 10 02-Mar-14 11-Mar-14 ALUMINUM SLIDING VENTILATORS INSTALLATION
A6160 ALUMINUM SHEETS INSTALLATION 10 02-Mar-14 11-Mar-14 ALUMINUM SHEETS INSTALLATION
WOOD WORK 13 28-Feb-14 12-Mar-14 12-Mar-14, WOOD WORK
A6170 WOODEN DOORS INSTALLATIONS 10 28-Feb-14 09-Mar-14 WOODEN DOORS INSTALLATIONS
A6180 BEEDINGS 3 10-Mar-14 12-Mar-14 BEEDINGS
A6340 INSTALLATION OF WOODEN CABINETS 3 10-Mar-14 12-Mar-14 INSTALLATION OF WOODEN CABINETS
MISCELLANEOUS 58 02-Mar-14 29-Apr-14 29-Apr-14, MISCELLANEOUS
A6190 INSTALLATION OF UPVC RAIN WATER DISPOSAL PIPES 5 03-Mar-14 07-Mar-14 INSTALLATION OF UPVC RAIN WATER DISPOSAL PIPES
A6200 INSTALLATION OF POLYPROPYLENE RANDOM (PPR) PIPE5AND FITTINGS
03-Mar-14 07-Mar-14 INSTALLATION OF POLYPROPYLENE RANDOM (PPR) PIPE AND F
A6210 INSTALLATION OF UPVC DRAIN PIPE 6 03-Mar-14 08-Mar-14 INSTALLATION OF UPVC DRAIN PIPE
A6220 INSTALLATION OF UPVC VENT PIPE 4 03-Mar-14 06-Mar-14 INSTALLATION OF UPVC VENT PIPE
A6223 PRE CAST RCC SLAB INSTALLATION 3 07-Mar-14 09-Mar-14 PRE CAST RCC SLAB INSTALLATION
A6225 INSTALLATION OF FALSE CEILING 20 02-Mar-14 21-Mar-14 INSTALLATION OF FALSE CEILING
A6230 INSTALLATION OF WASH BASIN 3 07-Mar-14 09-Mar-14 INSTALLATION OF WASH BASIN
A6240 INSTALLATION OF WATER CLOSET (Western) 2 07-Mar-14 08-Mar-14 INSTALLATION OF WATER CLOSET (Western)
A6250 INSTALLATION OF WATER CLOSET (Eastern) 2 07-Mar-14 08-Mar-14 INSTALLATION OF WATER CLOSET (Eastern)
A6260 MIRROR,SOAP DISH,TOWEL RAIL INSTALLATION 2 09-Mar-14 10-Mar-14 MIRROR,SOAP DISH,TOWEL RAIL INSTALLATION
A6270 INSTALLATION OF GATE VALVES 3 09-Mar-14 12-Mar-14 INSTALLATION OF GATE VALVES
A6280 SHOWER,STAINLESS STEEL BOWL INSTALLATION 3 12-Mar-14 15-Mar-14 SHOWER,STAINLESS STEEL BOWL INSTALLATION
A6290 INSTALLATION OF STAINLESS STEEL BOWL,FLOOR TRAP3 12-Mar-14 15-Mar-14 INSTALLATION OF STAINLESS STEEL BOWL,FLOOR TRAP
A6300 INSTALLATION OF FIBRE GLASS OVERHEAD TANK 2 15-Mar-14 17-Mar-14 INSTALLATION OF FIBRE GLASS OVERHEAD TANK
A6310 PVC CONDUITS INSTALLATION 2 15-Mar-14 17-Mar-14 PVC CONDUITS INSTALLATION
A6315 PAINT WORK 30 30-Mar-14 29-Apr-14 PAINT WORK
A6320 PLINTH PROTECTION 15 17-Mar-14 01-Apr-14 PLINTH PROTECTION
DAY RESERVOIR 69 01-Oct-13 08-Dec-13 08-Dec-13, DAY RESERVOIR
A5620 LAYOUT MARKING 3 01-Oct-13* 03-Oct-13 LAYOUT MARKING
A5630 EXCAVATION 15 04-Oct-13 18-Oct-13 EXCAVATION
A5640 EARTH FILLING 10 14-Oct-13 23-Oct-13 EARTH FILLING
A5650 LEVELING & COMPACTION 15 18-Oct-13 01-Nov-13 LEVELING & COMPACTION
A5660 GEOMEMBRANE INSTALLATION 20 28-Oct-13 16-Nov-13 GEOMEMBRANE INSTALLATION
A5670 CONCRETE WORK 25 02-Nov-13 26-Nov-13 CONCRETE WORK
A5680 STONE PITCHING ON SLOPE 22 12-Nov-13 03-Dec-13 STONE PITCHING ON SLOPE
A5690 STONE MASONRY TOE WALL 20 19-Nov-13 08-Dec-13 STONE MASONRY TOE WALL
AMINE UNIT-I 107 02-Oct-13 17-Jan-14 17-Jan-14, AMINE UNIT-I
A5410 LAYOUT MARKING 3 02-Oct-13* 05-Oct-13 LAYOUT MARKING
A5420 EXCAVATION 6 05-Oct-13 11-Oct-13 EXCAVATION
A5430 LEVELING & COMPACTION 18 11-Oct-13 29-Oct-13 LEVELING & COMPACTION
A5440 LEAN WORK 5 29-Oct-13 03-Nov-13 LEAN WORK
A5450 RE-BAR WORK 30 03-Nov-13 03-Dec-13 RE-BAR WORK
A5460 FORM WORK FOR FOOTING 25 18-Nov-13 13-Dec-13 FORM WORK FOR FOOTING
A5470 FOOTING POURING 5 09-Dec-13 14-Dec-13 FOOTING POURING
A5480 FORM WORK FOR PEDESTALS 15 10-Dec-13 25-Dec-13 FORM WORK FOR PEDESTALS

Actual Work Critical Remaining Work Summary Page 4 of 18 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


UCH-II GAS DEVELOPMENT PROJECT ACTIVITY SCHEDULE 23-Sep-13 09:40

Activity ID Activity Name Original Start Finish 2013 2014


Duration
Sep Oct Nov Dec Jan Feb Mar Apr May
A5490 EMBEDDED ITEMS INSTALLATION 10 25-Dec-13 04-Jan-14 EMBEDDED ITEMS INSTALLATION
A5500 PEDESTALS POURING 5 04-Jan-14 09-Jan-14 PEDESTALS POURING
A5510 REMOVAL OF FORM WORK 8 09-Jan-14 17-Jan-14 REMOVAL OF FORM WORK
MISCELLANEOUS 118 03-Sep-13 30-Dec-13 30-Dec-13, MISCELLANEOUS
DIESEL PUMP 19 07-Oct-13 26-Oct-13 26-Oct-13, DIESEL PUMP
A3870 LAYOUT MARKING 1 07-Oct-13* 07-Oct-13 LAYOUT MARKING
A3880 EXCAVATION 1 07-Oct-13 08-Oct-13 EXCAVATION
A3890 LEVELING & COMPACTION 2 08-Oct-13 10-Oct-13 LEVELING & COMPACTION
A3900 LEAN WORK 1 10-Oct-13 11-Oct-13 LEAN WORK
A3910 RE-BAR WORK 4 11-Oct-13 15-Oct-13 RE-BAR WORK
A3920 FORM WORK FOR FOOTING 4 15-Oct-13 19-Oct-13 FORM WORK FOR FOOTING
A3930 FOOTING POURING 1 19-Oct-13 19-Oct-13 FOOTING POURING
A3940 FORM WORK FOR PEDESTALS 2 19-Oct-13 21-Oct-13 FORM WORK FOR PEDESTALS
A3950 EMBEDDED ITEMS INSTALLATION 2 21-Oct-13 23-Oct-13 EMBEDDED ITEMS INSTALLATION
A3960 PEDESTALS POURING 1 23-Oct-13 24-Oct-13 PEDESTALS POURING
A3970 REMOVAL OF FORM WORK 2 24-Oct-13 26-Oct-13 REMOVAL OF FORM WORK
DEMIN SKID 31 10-Oct-13 10-Nov-13 10-Nov-13, DEMIN SKID
A3980 LAYOUT MARKING 1 10-Oct-13* 10-Oct-13 LAYOUT MARKING
A3990 EXCAVATION 1 11-Oct-13 11-Oct-13 EXCAVATION
A4000 LEVELING & COMPACTION 4 12-Oct-13 15-Oct-13 LEVELING & COMPACTION
A4010 LEAN WORK 2 15-Oct-13 18-Oct-13 LEAN WORK
A4020 RE-BAR WORK 6 18-Oct-13 24-Oct-13 RE-BAR WORK
A4030 FORM WORK FOR FOOTING 6 20-Oct-13 26-Oct-13 FORM WORK FOR FOOTING
A4040 FOOTING POURING 3 26-Oct-13 29-Oct-13 FOOTING POURING
A4050 FORM WORK FOR PEDESTALS 4 29-Oct-13 02-Nov-13 FORM WORK FOR PEDESTALS
A4060 EMBEDDED ITEMS INSTALLATION 3 02-Nov-13 05-Nov-13 EMBEDDED ITEMS INSTALLATION
A4070 PEDESTALS POURING 2 05-Nov-13 07-Nov-13 PEDESTALS POURING
A4080 REMOVAL OF FORM WORK 3 07-Nov-13 10-Nov-13 REMOVAL OF FORM WORK
L.P FUEL GAS KO DRUM 33 21-Sep-13 24-Oct-13 24-Oct-13, L.P FUEL GAS KO DRUM
A4090 LAYOUT MARKING 2 21-Sep-13* 22-Sep-13 LAYOUT MARKING
A4100 EXCAVATION 2 22-Sep-13 25-Sep-13 EXCAVATION
A4110 LEVELING & COMPACTION 4 25-Sep-13 29-Sep-13 LEVELING & COMPACTION
A4120 LEAN WORK 2 29-Sep-13 01-Oct-13 LEAN WORK
A4130 RE-BAR WORK 8 01-Oct-13 09-Oct-13 RE-BAR WORK
A4140 FORM WORK FOR FOOTING 8 04-Oct-13 12-Oct-13 FORM WORK FOR FOOTING
A4150 FOOTING POURING 5 10-Oct-13 15-Oct-13 FOOTING POURING
A4160 FORM WORK FOR PEDESTALS 6 12-Oct-13 18-Oct-13 FORM WORK FOR PEDESTALS
A4170 EMBEDDED ITEMS INSTALLATION 4 15-Oct-13 19-Oct-13 EMBEDDED ITEMS INSTALLATION
A4180 PEDESTALS POURING 4 17-Oct-13 21-Oct-13 PEDESTALS POURING
A4190 REMOVAL OF FORM WORK 2 21-Oct-13 24-Oct-13 REMOVAL OF FORM WORK
INSTRUMENT AIR RECEIVER 47 30-Sep-13 16-Nov-13 16-Nov-13, INSTRUMENT AIR RECEIVER
A4200 LAYOUT MARKING 1 30-Sep-13* 01-Oct-13 LAYOUT MARKING
A4210 EXCAVATION 1 01-Oct-13 02-Oct-13 EXCAVATION
A4220 LEVELING & COMPACTION 3 02-Oct-13 05-Oct-13 LEVELING & COMPACTION
A4230 LEAN WORK 2 05-Oct-13 07-Oct-13 LEAN WORK
A4240 RE-BAR WORK 10 07-Oct-13 17-Oct-13 RE-BAR WORK
A4250 FORM WORK FOR FOOTING 10 15-Oct-13 25-Oct-13 FORM WORK FOR FOOTING
A4260 FOOTING POURING 6 23-Oct-13 29-Oct-13 FOOTING POURING
A4270 FORM WORK FOR PEDESTALS 5 27-Oct-13 01-Nov-13 FORM WORK FOR PEDESTALS
A4280 EMBEDDED ITEMS INSTALLATION 8 01-Nov-13 09-Nov-13 EMBEDDED ITEMS INSTALLATION
A4290 PEDESTALS POURING 5 09-Nov-13 14-Nov-13 PEDESTALS POURING

Actual Work Critical Remaining Work Summary Page 5 of 18 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


UCH-II GAS DEVELOPMENT PROJECT ACTIVITY SCHEDULE 23-Sep-13 09:40

Activity ID Activity Name Original Start Finish 2013 2014


Duration
Sep Oct Nov Dec Jan Feb Mar Apr May
A4300 REMOVAL OF FORM WORK 3 13-Nov-13 16-Nov-13 REMOVAL OF FORM WORK
NITROGEN RECEIVER 37 08-Oct-13 14-Nov-13 14-Nov-13, NITROGEN RECEIVER
A4310 LAYOUT MARKING 1 08-Oct-13* 09-Oct-13 LAYOUT MARKING
A4320 EXCAVATION 2 09-Oct-13 11-Oct-13 EXCAVATION
A4330 LEVELING & COMPACTION 3 11-Oct-13 14-Oct-13 LEVELING & COMPACTION
A4340 LEAN WORK 2 14-Oct-13 16-Oct-13 LEAN WORK
A4350 RE-BAR WORK 8 16-Oct-13 24-Oct-13 RE-BAR WORK
A4360 FORM WORK FOR FOOTING 8 22-Oct-13 30-Oct-13 FORM WORK FOR FOOTING
A4370 FOOTING POURING 1 30-Oct-13 31-Oct-13 FOOTING POURING
A4380 FORM WORK FOR PEDESTALS 5 31-Oct-13 05-Nov-13 FORM WORK FOR PEDESTALS
A4390 EMBEDDED ITEMS INSTALLATION 2 04-Nov-13 07-Nov-13 EMBEDDED ITEMS INSTALLATION
A4400 PEDESTALS POURING 1 07-Nov-13 08-Nov-13 PEDESTALS POURING
A4410 REMOVAL OF FORM WORK 6 08-Nov-13 14-Nov-13 REMOVAL OF FORM WORK
BLOW CASE VESSEL 40 25-Sep-13 03-Nov-13 03-Nov-13, BLOW CASE VESSEL
A4420 LAYOUT MARKING 1 25-Sep-13* 25-Sep-13 LAYOUT MARKING
A4430 EXCAVATION 1 25-Sep-13 26-Sep-13 EXCAVATION
A4440 LEVELING & COMPACTION 3 26-Sep-13 29-Sep-13 LEVELING & COMPACTION
A4450 LEAN WORK 1 29-Sep-13 30-Sep-13 LEAN WORK
A4460 RE-BAR WORK 8 30-Sep-13 08-Oct-13 RE-BAR WORK
A4470 FORM WORK FOR FOOTING 8 06-Oct-13 14-Oct-13 FORM WORK FOR FOOTING
A4480 FOOTING POURING 3 14-Oct-13 17-Oct-13 FOOTING POURING
A4490 FORM WORK FOR PEDESTALS 3 17-Oct-13 20-Oct-13 FORM WORK FOR PEDESTALS
A4500 EMBEDDED ITEMS INSTALLATION 6 20-Oct-13 26-Oct-13 EMBEDDED ITEMS INSTALLATION
A4510 PEDESTALS POURING 3 26-Oct-13 29-Oct-13 PEDESTALS POURING
A4520 REMOVAL OF FORM WORK 5 29-Oct-13 03-Nov-13 REMOVAL OF FORM WORK
POWER GENERATION & GAS TURBINE AREA 99 12-Sep-13 20-Dec-13 20-Dec-13, POWER GENERATION & GAS TURBINE AREA
A4530 LAYOUT MARKING 2 12-Sep-13* 14-Sep-13 LAYOUT MARKING
A4540 EXCAVATION 5 14-Sep-13 19-Sep-13 EXCAVATION
A4550 LEVELING & COMPACTION 10 19-Sep-13 29-Sep-13 LEVELING & COMPACTION
A4560 LEAN WORK 4 29-Sep-13 03-Oct-13 LEAN WORK
A4570 RE-BAR WORK 25 03-Oct-13 28-Oct-13 RE-BAR WORK
A4580 FORM WORK FOR FOOTING 25 28-Oct-13 22-Nov-13 FORM WORK FOR FOOTING
A4590 FOOTING POURING 5 22-Nov-13 27-Nov-13 FOOTING POURING
A4600 FORM WORK FOR PEDESTALS 10 27-Nov-13 07-Dec-13 FORM WORK FOR PEDESTALS
A4610 EMBEDDED ITEMS INSTALLATION 6 05-Dec-13 11-Dec-13 EMBEDDED ITEMS INSTALLATION
A4620 PEDESTALS POURING 5 09-Dec-13 14-Dec-13 PEDESTALS POURING
A4630 REMOVAL OF FORM WORK 8 12-Dec-13 20-Dec-13 REMOVAL OF FORM WORK
HOT OIL SYSTEM 59 01-Nov-13 30-Dec-13 30-Dec-13, HOT OIL SYSTEM
A4640 LAYOUT MARKING 2 01-Nov-13 03-Nov-13 LAYOUT MARKING
A4650 EXCAVATION 5 03-Nov-13 08-Nov-13 EXCAVATION
A4660 LEVELING & COMPACTION 8 08-Nov-13 16-Nov-13 LEVELING & COMPACTION
A4670 LEAN WORK 4 16-Nov-13 20-Nov-13 LEAN WORK
A4680 RE-BAR WORK 10 20-Nov-13 30-Nov-13 RE-BAR WORK
A4690 FORM WORK FOR FOOTING 8 26-Nov-13 04-Dec-13 FORM WORK FOR FOOTING
A4700 FOOTING POURING 4 04-Dec-13 08-Dec-13 FOOTING POURING
A4710 FORM WORK FOR PEDESTALS 8 08-Dec-13 16-Dec-13 FORM WORK FOR PEDESTALS
A4720 EMBEDDED ITEMS INSTALLATION 4 16-Dec-13 20-Dec-13 EMBEDDED ITEMS INSTALLATION
A4730 PEDESTALS POURING 3 20-Dec-13 23-Dec-13 PEDESTALS POURING
A4740 REMOVAL OF FORM WORK 4 26-Dec-13 30-Dec-13 REMOVAL OF FORM WORK
SLUG-CATCHER WITH PLATEFORM FOUNDATIONS 39 03-Sep-13 12-Oct-13 12-Oct-13, SLUG-CATCHER WITH PLATEFORM FOUNDATIONS

Actual Work Critical Remaining Work Summary Page 6 of 18 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


UCH-II GAS DEVELOPMENT PROJECT ACTIVITY SCHEDULE 23-Sep-13 09:40

Activity ID Activity Name Original Start Finish 2013 2014


Duration
Sep Oct Nov Dec Jan Feb Mar Apr May
A4750 LAYOUT MARKING 1 03-Sep-13 04-Sep-13 LAYOUT MARKING
A4760 EXCAVATION 3 04-Sep-13 07-Sep-13 EXCAVATION
A4770 LEVELING & COMPACTION 5 07-Sep-13 12-Sep-13 LEVELING & COMPACTION
A4780 LEAN WORK 4 12-Sep-13 16-Sep-13 LEAN WORK
A4790 RE-BAR WORK 2 16-Sep-13 18-Sep-13 RE-BAR WORK
A4800 FORM WORK FOR FOOTING 2 16-Sep-13 18-Sep-13 FORM WORK FOR FOOTING
A4810 FOOTING POURING 1 16-Sep-13 17-Sep-13 FOOTING POURING
A4820 FORM WORK FOR PEDESTALS 8 18-Sep-13 26-Sep-13 FORM WORK FOR PEDESTALS
A4830 EMBEDDED ITEMS INSTALLATION 6 26-Sep-13 02-Oct-13 EMBEDDED ITEMS INSTALLATION
A4840 PEDESTALS POURING 1 02-Oct-13 03-Oct-13 PEDESTALS POURING
A4850 REMOVAL OF FORM WORK 9 03-Oct-13 12-Oct-13 REMOVAL OF FORM WORK
CONDENSATE WATER SEPERATORS 30 08-Oct-13 06-Nov-13 06-Nov-13, CONDENSATE WATER SEPERATORS
A4860 LAYOUT MARKING 1 08-Oct-13 09-Oct-13 LAYOUT MARKING
A4870 EXCAVATION 2 09-Oct-13 11-Oct-13 EXCAVATION
A4880 LEVELING & COMPACTION 3 11-Oct-13 14-Oct-13 LEVELING & COMPACTION
A4890 LEAN WORK 1 14-Oct-13 15-Oct-13 LEAN WORK
A4900 RE-BAR WORK 7 15-Oct-13 22-Oct-13 RE-BAR WORK
A4910 FORM WORK FOR FOOTING 7 20-Oct-13 27-Oct-13 FORM WORK FOR FOOTING
A4920 FOOTING POURING 3 27-Oct-13 30-Oct-13 FOOTING POURING
A4930 FORM WORK FOR PEDESTALS 3 30-Oct-13 02-Nov-13 FORM WORK FOR PEDESTALS
A4940 EMBEDDED ITEMS INSTALLATION 2 02-Nov-13 04-Nov-13 EMBEDDED ITEMS INSTALLATION
A4950 PEDESTALS POURING 1 04-Nov-13 05-Nov-13 PEDESTALS POURING
A4960 REMOVAL OF FORM WORK 1 05-Nov-13 06-Nov-13 REMOVAL OF FORM WORK
CONDENSATE DEGASSING BOOT 31 01-Nov-13 01-Dec-13 01-Dec-13, CONDENSATE DEGASSING BOOT
A4970 LAYOUT MARKING 1 01-Nov-13 02-Nov-13 LAYOUT MARKING
A4980 EXCAVATION 2 02-Nov-13 04-Nov-13 EXCAVATION
A4990 LEVELING & COMPACTION 3 04-Nov-13 07-Nov-13 LEVELING & COMPACTION
A5000 LEAN WORK 1 07-Nov-13 08-Nov-13 LEAN WORK
A5010 RE-BAR WORK 8 08-Nov-13 16-Nov-13 RE-BAR WORK
A5020 FORM WORK FOR FOOTING 8 13-Nov-13 21-Nov-13 FORM WORK FOR FOOTING
A5030 FOOTING POURING 1 21-Nov-13 22-Nov-13 FOOTING POURING
A5040 FORM WORK FOR PEDESTALS 2 22-Nov-13 25-Nov-13 FORM WORK FOR PEDESTALS
A5050 EMBEDDED ITEMS INSTALLATION 3 25-Nov-13 28-Nov-13 EMBEDDED ITEMS INSTALLATION
A5060 PEDESTALS POURING 1 28-Nov-13 29-Nov-13 PEDESTALS POURING
A5070 REMOVAL OF FORM WORK 2 29-Nov-13 01-Dec-13 REMOVAL OF FORM WORK
FLARE KNOCKOUT DRUM 22 11-Oct-13 02-Nov-13 02-Nov-13, FLARE KNOCKOUT DRUM
A5080 LAYOUT MARKING 1 11-Oct-13 11-Oct-13 LAYOUT MARKING
A5090 EXCAVATION 2 11-Oct-13 13-Oct-13 EXCAVATION
A5100 LEVELING & COMPACTION 2 13-Oct-13 15-Oct-13 LEVELING & COMPACTION
A5110 LEAN WORK 1 15-Oct-13 16-Oct-13 LEAN WORK
A5120 RE-BAR WORK 4 16-Oct-13 20-Oct-13 RE-BAR WORK
A5130 FORM WORK FOR FOOTING 4 20-Oct-13 24-Oct-13 FORM WORK FOR FOOTING
A5140 FOOTING POURING 2 24-Oct-13 26-Oct-13 FOOTING POURING
A5150 FORM WORK FOR PEDESTALS 2 26-Oct-13 28-Oct-13 FORM WORK FOR PEDESTALS
A5160 EMBEDDED ITEMS INSTALLATION 2 28-Oct-13 30-Oct-13 EMBEDDED ITEMS INSTALLATION
A5170 PEDESTALS POURING 1 30-Oct-13 31-Oct-13 PEDESTALS POURING
A5180 REMOVAL OF FORM WORK 2 31-Oct-13 02-Nov-13 REMOVAL OF FORM WORK
FIRE WATER DIESEL ENGINE PUMP 18 19-Sep-13 06-Oct-13 06-Oct-13, FIRE WATER DIESEL ENGINE PUMP
A5190 LAYOUT MARKING 1 19-Sep-13 19-Sep-13 LAYOUT MARKING
A5200 EXCAVATION 1 19-Sep-13 20-Sep-13 EXCAVATION
A5210 LEVELING & COMPACTION 2 20-Sep-13 22-Sep-13 LEVELING & COMPACTION

Actual Work Critical Remaining Work Summary Page 7 of 18 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


UCH-II GAS DEVELOPMENT PROJECT ACTIVITY SCHEDULE 23-Sep-13 09:40

Activity ID Activity Name Original Start Finish 2013 2014


Duration
Sep Oct Nov Dec Jan Feb Mar Apr May
A5220 LEAN WORK 2 22-Sep-13 23-Sep-13 LEAN WORK
A5230 RE-BAR WORK 3 23-Sep-13 26-Sep-13 RE-BAR WORK
A5240 FORM WORK FOR FOOTING 3 26-Sep-13 29-Sep-13 FORM WORK FOR FOOTING
A5250 FOOTING POURING 1 29-Sep-13 30-Sep-13 FOOTING POURING
A5260 FORM WORK FOR PEDESTALS 2 30-Sep-13 03-Oct-13 FORM WORK FOR PEDESTALS
A5270 EMBEDDED ITEMS INSTALLATION 2 03-Oct-13 04-Oct-13 EMBEDDED ITEMS INSTALLATION
A5280 PEDESTALS POURING 1 04-Oct-13 05-Oct-13 PEDESTALS POURING
A5290 REMOVAL OF FORM WORK 1 05-Oct-13 06-Oct-13 REMOVAL OF FORM WORK
FIRE WATER ELECTRIC DRIVEN PUMP 18 19-Sep-13 07-Oct-13 07-Oct-13, FIRE WATER ELECTRIC DRIVEN PUMP
A5300 LAYOUT MARKING 1 19-Sep-13 19-Sep-13 LAYOUT MARKING
A5310 EXCAVATION 1 19-Sep-13 20-Sep-13 EXCAVATION
A5320 LEVELING & COMPACTION 2 20-Sep-13 22-Sep-13 LEVELING & COMPACTION
A5330 LEAN WORK 1 22-Sep-13 23-Sep-13 LEAN WORK
A5340 RE-BAR WORK 3 23-Sep-13 26-Sep-13 RE-BAR WORK
A5350 FORM WORK FOR FOOTING 3 26-Sep-13 29-Sep-13 FORM WORK FOR FOOTING
A5360 FOOTING POURING 1 29-Sep-13 30-Sep-13 FOOTING POURING
A5370 FORM WORK FOR PEDESTALS 2 30-Sep-13 02-Oct-13 FORM WORK FOR PEDESTALS
A5380 EMBEDDED ITEMS INSTALLATION 2 02-Oct-13 05-Oct-13 EMBEDDED ITEMS INSTALLATION
A5390 PEDESTALS POURING 1 05-Oct-13 06-Oct-13 PEDESTALS POURING
A5400 REMOVAL OF FORM WORK 1 06-Oct-13 07-Oct-13 REMOVAL OF FORM WORK
CIVIL WORK FOR TIE-IN AT UCH-I 0
CIVIL WORK FOR TIE-IN AT UPL 0
MECHANICAL 180 22-Oct-13 20-Apr-14 20-Apr-14, MECHANICAL

TANKS 141 22-Oct-13 11-Mar-14 11-Mar-14, TANKS


RAW WATER TANK 97 22-Oct-13 26-Jan-14 26-Jan-14, RAW WATER TANK
FABRICATION 24 22-Oct-13 14-Nov-13 14-Nov-13, FABRICATION
BOTTOM 8 22-Oct-13 29-Oct-13 29-Oct-13, BOTTOM
A6770 MARKING OF BOTTOM & SUMP PLATES 1 22-Oct-13* 22-Oct-13 MARKING OF BOTTOM & SUMP PLATES
A6780 CUTTING OF BOTTOM & SUMP PLATES 2 23-Oct-13 24-Oct-13 CUTTING OF BOTTOM & SUMP PLATES
A6790 SAND BLASTING & PAINTING 5 25-Oct-13 29-Oct-13 SAND BLASTING & PAINTING
SHELL 11 23-Oct-13 02-Nov-13 02-Nov-13, SHELL
A6840 STRAIGHTEING & MARKING 3 23-Oct-13 25-Oct-13 STRAIGHTEING & MARKING
A6850 CUTTING & BEVELING 7 26-Oct-13 01-Nov-13 CUTTING & BEVELING
A6860 ROLLING 10 23-Oct-13 01-Nov-13 ROLLING
A6865 SAND BLASTING & PAINTING 6 28-Oct-13 02-Nov-13 SAND BLASTING & PAINTING
ROOF 12 03-Nov-13 14-Nov-13 14-Nov-13, ROOF
A6900 MARKING 2 03-Nov-13 04-Nov-13 MARKING
A6910 CUTTING 5 05-Nov-13 09-Nov-13 CUTTING
A6920 SAND BLASTING & PAINTING 5 10-Nov-13 14-Nov-13 SAND BLASTING & PAINTING
ERECTION 85 03-Nov-13 26-Jan-14 26-Jan-14, ERECTION
A6930 ERECTION OF BOTTOM PLATES & SUMP 2 03-Nov-13 04-Nov-13 ERECTION OF BOTTOM PLATES & SUMP
A6940 WELDING OF BOTTOM PLATES & SUMP 2 05-Nov-13 06-Nov-13 WELDING OF BOTTOM PLATES & SUMP
A6950 VACUUM BOX TEST 1 07-Nov-13 07-Nov-13 VACUUM BOX TEST
A6960 ERECTION OF 1st SHELL 1 08-Nov-13 08-Nov-13 ERECTION OF 1st SHELL
A6970 WELDING OF 1st SHELL 3 09-Nov-13 11-Nov-13 WELDING OF 1st SHELL
A6980 OIL PENETRANT TEST(OPT) 1 12-Nov-13 12-Nov-13 OIL PENETRANT TEST(OPT)
A6990 2ND SHELL INSTALLATION 4 13-Nov-13 16-Nov-13 2ND SHELL INSTALLATION
A7000 3RD SHELL INSTALLATION 4 17-Nov-13 20-Nov-13 3RD SHELL INSTALLATION
A7010 DYE PENETRANT TEST 25 21-Nov-13 15-Dec-13 DYE PENETRANT TEST
A7020 4TH SHELL INSTALLATION 5 21-Nov-13 25-Nov-13 4TH SHELL INSTALLATION

Actual Work Critical Remaining Work Summary Page 8 of 18 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


UCH-II GAS DEVELOPMENT PROJECT ACTIVITY SCHEDULE 23-Sep-13 09:40

Activity ID Activity Name Original Start Finish 2013 2014


Duration
Sep Oct Nov Dec Jan Feb Mar Apr May
A7030 RADIOGRAPHIC TESTING (RT) 25 21-Nov-13 15-Dec-13 RADIOGRAPHIC TESTING (RT)
A7040 5TH SHELL INSTALLATION 6 21-Nov-13 26-Nov-13 5TH SHELL INSTALLATION
A7050 6YH SHELL INSTALLATION 6 27-Nov-13 02-Dec-13 6YH SHELL INSTALLATION
A7055 CURB ANGLE INSTALLATION & WELDING 2 03-Dec-13 04-Dec-13 CURB ANGLE INSTALLATION & WELDING
A7060 CENTRAL COLUMN ERECTION FOR ROOF 1 05-Dec-13 05-Dec-13 CENTRAL COLUMN ERECTION FOR ROOF
A7070 BRACKETS INSTALLATION(FOR RAFTER) 2 06-Dec-13 07-Dec-13 BRACKETS INSTALLATION(FOR RAFTER)
A7080 RAFTERS INSTALLATION 2 08-Dec-13 09-Dec-13 RAFTERS INSTALLATION
A7090 NOZZLE MARKING & CUTTING FOR SHELLS 1 10-Dec-13 10-Dec-13 NOZZLE MARKING & CUTTING FOR SHELLS
A7100 NOZZLE INSTALLATION FOR SHELLS 5 11-Dec-13 15-Dec-13 NOZZLE INSTALLATION FOR SHELLS
A7105 NOZZLE WELDING FOR SHELLS 6 16-Dec-13 21-Dec-13 NOZZLE WELDING FOR SHELLS
A7110 MANHOLE MARKING & CUTTING 1 22-Dec-13 22-Dec-13 MANHOLE MARKING & CUTTING
A7120 MANHOLE FIT UP 1 23-Dec-13 23-Dec-13 MANHOLE FIT UP
A7130 MANHOLE WELDING 1 24-Dec-13 24-Dec-13 MANHOLE WELDING
A7135 PNEUMATIC TEST OF MANHOLES 1 25-Dec-13 25-Dec-13 PNEUMATIC TEST OF MANHOLES
A7150 ROOF PLATES INSTALLATION 2 26-Dec-13 27-Dec-13 ROOF PLATES INSTALLATION
A7160 ROOF PLATES WELDING 3 28-Dec-13 30-Dec-13 ROOF PLATES WELDING
A7170 NOZZLE MARKING & CUTTING FOR ROOF 2 31-Dec-13 01-Jan-14 NOZZLE MARKING & CUTTING FOR ROOF
A7180 NOZZLE FITUP FOR ROOF 2 02-Jan-14 03-Jan-14 NOZZLE FITUP FOR ROOF
A7190 NOZZLE WELDING FOR ROOF 2 04-Jan-14 05-Jan-14 NOZZLE WELDING FOR ROOF
A7210 VACUUM BOX TEST FOR ROOF 1 06-Jan-14 06-Jan-14 VACUUM BOX TEST FOR ROOF
A7220 INSTALLATION OF PLATEFORM,STAIRCASE & ROOF HANDRAIL
4 07-Jan-14 10-Jan-14 INSTALLATION OF PLATEFORM,STAIRCASE & ROOF HANDRAIL
A7230 PUNCH LIST 1 11-Jan-14 11-Jan-14 PUNCH LIST
A7240 HYDROTESTING 10 12-Jan-14 21-Jan-14 HYDROTESTING
A7250 PAINTING 5 22-Jan-14 26-Jan-14 PAINTING
DIESEL STORAGE TANK 93 07-Nov-13 07-Feb-14 07-Feb-14, DIESEL STORAGE TANK
FABRICATION 17 07-Nov-13 23-Nov-13 23-Nov-13, FABRICATION
BOTTOM 6 07-Nov-13 12-Nov-13 12-Nov-13, BOTTOM
A10210 MARKING OF BOTTOM & SUMP PLATES 1 07-Nov-13 07-Nov-13 MARKING OF BOTTOM & SUMP PLATES
A10220 CUTTING OF BOTTOM & SUMP PLATES 2 08-Nov-13 09-Nov-13 CUTTING OF BOTTOM & SUMP PLATES
A10230 SAND BLASTING & PAINTING 3 10-Nov-13 12-Nov-13 SAND BLASTING & PAINTING
SHELL 8 08-Nov-13 15-Nov-13 15-Nov-13, SHELL
A10240 STRAIGHTEING & MARKING 2 08-Nov-13 09-Nov-13 STRAIGHTEING & MARKING
A10250 CUTTING & BEVELING 3 10-Nov-13 12-Nov-13 CUTTING & BEVELING
A10260 ROLLING 3 13-Nov-13 15-Nov-13 ROLLING
ROOF 8 16-Nov-13 23-Nov-13 23-Nov-13, ROOF
A10270 MARKING 2 16-Nov-13 17-Nov-13 MARKING
A10280 CUTTING 3 18-Nov-13 20-Nov-13 CUTTING
A10290 SAND BLASTING & PAINTING 3 21-Nov-13 23-Nov-13 SAND BLASTING & PAINTING
ERECTION 84 16-Nov-13 07-Feb-14 07-Feb-14, ERECTION
A10300 ERECTION OF BOTTOM PLATES & SUMP 1 16-Nov-13 16-Nov-13 ERECTION OF BOTTOM PLATES & SUMP
A10310 WELDING OF BOTTOM PLATES & SUMP 2 17-Nov-13 18-Nov-13 WELDING OF BOTTOM PLATES & SUMP
A10320 VACUUM BOX TEST 1 19-Nov-13 19-Nov-13 VACUUM BOX TEST
A10330 ERECTION OF 1st SHELL 2 20-Nov-13 21-Nov-13 ERECTION OF 1st SHELL
A10340 WELDING OF 1st SHELL 2 22-Nov-13 23-Nov-13 WELDING OF 1st SHELL
A10350 OIL PENETRANT TEST(OPT) 1 24-Nov-13 24-Nov-13 OIL PENETRANT TEST(OPT)
A10360 2ND SHELL INSTALLATION 4 25-Nov-13 28-Nov-13 2ND SHELL INSTALLATION
A10370 3RD SHELL INSTALLATION 4 29-Nov-13 02-Dec-13 3RD SHELL INSTALLATION
A10380 DYE PENETRANT TEST 30 03-Dec-13 01-Jan-14 DYE PENETRANT TEST
A10390 4TH SHELL INSTALLATION 4 03-Dec-13 06-Dec-13 4TH SHELL INSTALLATION
A10400 RADIOGRAPHIC TESTING (RT) 30 07-Dec-13 05-Jan-14 RADIOGRAPHIC TESTING (RT)
A10410 5TH SHELL INSTALLATION 4 07-Dec-13 10-Dec-13 5TH SHELL INSTALLATION

Actual Work Critical Remaining Work Summary Page 9 of 18 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


UCH-II GAS DEVELOPMENT PROJECT ACTIVITY SCHEDULE 23-Sep-13 09:40

Activity ID Activity Name Original Start Finish 2013 2014


Duration
Sep Oct Nov Dec Jan Feb Mar Apr May
A10420 6YH SHELL INSTALLATION 4 11-Dec-13 14-Dec-13 6YH SHELL INSTALLATION
A10430 CURB ANGLE INSTALLATION & WELDING 1 15-Dec-13 15-Dec-13 CURB ANGLE INSTALLATION & WELDING
A10440 CENTRAL COLUMN ERECTION FOR ROOF 1 16-Dec-13 16-Dec-13 CENTRAL COLUMN ERECTION FOR ROOF
A10450 BRACKETS INSTALLATION(FOR RAFTER) 2 17-Dec-13 18-Dec-13 BRACKETS INSTALLATION(FOR RAFTER)
A10460 RAFTERS INSTALLATION 3 19-Dec-13 21-Dec-13 RAFTERS INSTALLATION
A10470 NOZZLE MARKING & CUTTING FOR SHELLS 3 22-Dec-13 24-Dec-13 NOZZLE MARKING & CUTTING FOR SHELLS
A10480 NOZZLE INSTALLATION FOR SHELLS 5 25-Dec-13 29-Dec-13 NOZZLE INSTALLATION FOR SHELLS
A10490 NOZZLE WELDING FOR SHELLS 3 30-Dec-13 01-Jan-14 NOZZLE WELDING FOR SHELLS
A10500 MANHOLE MARKING & CUTTING 1 02-Jan-14 02-Jan-14 MANHOLE MARKING & CUTTING
A10510 MANHOLE FIT UP 1 03-Jan-14 03-Jan-14 MANHOLE FIT UP
A10520 MANHOLE WELDING 1 04-Jan-14 04-Jan-14 MANHOLE WELDING
A10530 PNEUMATIC TEST OF MANHOLES 1 05-Jan-14 05-Jan-14 PNEUMATIC TEST OF MANHOLES
A10540 ROOF PLATES INSTALLATION 3 06-Jan-14 08-Jan-14 ROOF PLATES INSTALLATION
A10550 ROOF PLATES WELDING 2 09-Jan-14 10-Jan-14 ROOF PLATES WELDING
A10560 NOZZLE MARKING & CUTTING FOR ROOF 2 11-Jan-14 12-Jan-14 NOZZLE MARKING & CUTTING FOR ROOF
A10570 NOZZLE FITUP FOR ROOF 2 13-Jan-14 14-Jan-14 NOZZLE FITUP FOR ROOF
A10580 NOZZLE WELDING FOR ROOF 2 15-Jan-14 16-Jan-14 NOZZLE WELDING FOR ROOF
A10590 VACUUM BOX TEST FOR ROOF 1 17-Jan-14 17-Jan-14 VACUUM BOX TEST FOR ROOF
A10600 INSTALLATION OF PLATEFORM,STAIRCASE & ROOF HANDRAIL
4 18-Jan-14 21-Jan-14 INSTALLATION OF PLATEFORM,STAIRCASE & ROOF HANDRAIL
A10610 PUNCH LIST 1 22-Jan-14 22-Jan-14 PUNCH LIST
A10620 HYDROTESTING 10 23-Jan-14 01-Feb-14 HYDROTESTING
A10630 PAINTING 6 02-Feb-14 07-Feb-14 PAINTING
DEMIN STORAGE TANK 100 02-Dec-13 11-Mar-14 11-Mar-14, DEMIN STORAGE TANK
FABRICATION 12 02-Dec-13 13-Dec-13 13-Dec-13, FABRICATION
BOTTOM 6 02-Dec-13 07-Dec-13 07-Dec-13, BOTTOM
A10980 MARKING OF BOTTOM & SUMP PLATES 1 02-Dec-13* 02-Dec-13 MARKING OF BOTTOM & SUMP PLATES
A10990 CUTTING OF BOTTOM & SUMP PLATES 2 03-Dec-13 04-Dec-13 CUTTING OF BOTTOM & SUMP PLATES
A11000 SAND BLASTING & PAINTING 3 05-Dec-13 07-Dec-13 SAND BLASTING & PAINTING
SHELL 5 03-Dec-13 07-Dec-13 07-Dec-13, SHELL
A11010 STRAIGHTEING & MARKING 3 03-Dec-13 05-Dec-13 STRAIGHTEING & MARKING
A11020 CUTTING & BEVELING 4 04-Dec-13 07-Dec-13 CUTTING & BEVELING
A11030 ROLLING 4 03-Dec-13 06-Dec-13 ROLLING
ROOF 7 07-Dec-13 13-Dec-13 13-Dec-13, ROOF
A11040 MARKING 2 07-Dec-13 08-Dec-13 MARKING
A11050 CUTTING 2 09-Dec-13 10-Dec-13 CUTTING
A11060 SAND BLASTING & PAINTING 3 11-Dec-13 13-Dec-13 SAND BLASTING & PAINTING
ERECTION 75 26-Dec-13 11-Mar-14 11-Mar-14, ERECTION
A10640 ERECTION OF BOTTOM PLATES & SUMP 2 26-Dec-13 28-Dec-13 ERECTION OF BOTTOM PLATES & SUMP
A10650 WELDING OF BOTTOM PLATES & SUMP 2 28-Dec-13 30-Dec-13 WELDING OF BOTTOM PLATES & SUMP
A10660 VACUUM BOX TEST 1 30-Dec-13 31-Dec-13 VACUUM BOX TEST
A10670 ERECTION OF 1st SHELL 2 31-Dec-13 02-Jan-14 ERECTION OF 1st SHELL
A10680 WELDING OF 1st SHELL 3 02-Jan-14 05-Jan-14 WELDING OF 1st SHELL
A10690 OIL PENETRANT TEST(OPT) 1 05-Jan-14 06-Jan-14 OIL PENETRANT TEST(OPT)
A10700 2ND SHELL INSTALLATION 4 06-Jan-14 10-Jan-14 2ND SHELL INSTALLATION
A10710 3RD SHELL INSTALLATION 4 10-Jan-14 14-Jan-14 3RD SHELL INSTALLATION
A10720 DYE PENETRANT TEST 25 14-Jan-14 08-Feb-14 DYE PENETRANT TEST
A10730 4TH SHELL INSTALLATION 4 14-Jan-14 18-Jan-14 4TH SHELL INSTALLATION
A10740 RADIOGRAPHIC TESTING (RT) 25 18-Jan-14 12-Feb-14 RADIOGRAPHIC TESTING (RT)
A10750 5TH SHELL INSTALLATION 4 18-Jan-14 22-Jan-14 5TH SHELL INSTALLATION
A10760 6YH SHELL INSTALLATION 4 22-Jan-14 26-Jan-14 6YH SHELL INSTALLATION
A10770 CURB ANGLE INSTALLATION & WELDING 2 26-Jan-14 28-Jan-14 CURB ANGLE INSTALLATION & WELDING

Actual Work Critical Remaining Work Summary Page 10 of 18 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


UCH-II GAS DEVELOPMENT PROJECT ACTIVITY SCHEDULE 23-Sep-13 09:40

Activity ID Activity Name Original Start Finish 2013 2014


Duration
Sep Oct Nov Dec Jan Feb Mar Apr May
A10780 CENTRAL COLUMN ERECTION FOR ROOF 1 28-Jan-14 29-Jan-14 CENTRAL COLUMN ERECTION FOR ROOF
A10790 BRACKETS INSTALLATION(FOR RAFTER) 2 29-Jan-14 31-Jan-14 BRACKETS INSTALLATION(FOR RAFTER)
A10800 RAFTERS INSTALLATION 2 31-Jan-14 02-Feb-14 RAFTERS INSTALLATION
A10810 NOZZLE MARKING & CUTTING FOR SHELLS 1 02-Feb-14 03-Feb-14 NOZZLE MARKING & CUTTING FOR SHELLS
A10820 NOZZLE INSTALLATION FOR SHELLS 3 03-Feb-14 06-Feb-14 NOZZLE INSTALLATION FOR SHELLS
A10830 NOZZLE WELDING FOR SHELLS 4 06-Feb-14 10-Feb-14 NOZZLE WELDING FOR SHELLS
A10840 MANHOLE MARKING & CUTTING 1 10-Feb-14 11-Feb-14 MANHOLE MARKING & CUTTING
A10850 MANHOLE FIT UP 1 11-Feb-14 12-Feb-14 MANHOLE FIT UP
A10860 MANHOLE WELDING 1 12-Feb-14 13-Feb-14 MANHOLE WELDING
A10870 PNEUMATIC TEST OF MANHOLES 1 13-Feb-14 14-Feb-14 PNEUMATIC TEST OF MANHOLES
A10880 ROOF PLATES INSTALLATION 3 14-Feb-14 17-Feb-14 ROOF PLATES INSTALLATION
A10890 ROOF PLATES WELDING 3 17-Feb-14 20-Feb-14 ROOF PLATES WELDING
A10900 NOZZLE MARKING & CUTTING FOR ROOF 1 20-Feb-14 21-Feb-14 NOZZLE MARKING & CUTTING FOR ROOF
A10910 NOZZLE FITUP FOR ROOF 1 21-Feb-14 22-Feb-14 NOZZLE FITUP FOR ROOF
A10920 NOZZLE WELDING FOR ROOF 1 22-Feb-14 23-Feb-14 NOZZLE WELDING FOR ROOF
A10930 VACUUM BOX TEST FOR ROOF 1 22-Feb-14 23-Feb-14 VACUUM BOX TEST FOR ROOF
A10940 INSTALLATION OF PLATEFORM,STAIRCASE & ROOF HANDRAIL
5 23-Feb-14 28-Feb-14 INSTALLATION OF PLATEFORM,STAIRCASE & ROOF HANDRAIL
A10950 PUNCH LIST 3 28-Feb-14 03-Mar-14 PUNCH LIST
A10960 HYDROTESTING 4 03-Mar-14 07-Mar-14 HYDROTESTING
A10970 PAINTING 4 07-Mar-14 11-Mar-14 PAINTING
STEEL STRUCTURE 98 25-Oct-13 30-Jan-14 30-Jan-14, STEEL STRUCTURE
PIPE RACK-B 79 25-Oct-13 11-Jan-14 11-Jan-14, PIPE RACK-B
FABRICATION 29 25-Oct-13 22-Nov-13 22-Nov-13, FABRICATION
A7260 MARKING 5 25-Oct-13* 29-Oct-13 MARKING
A7270 CUTTING 9 26-Oct-13 03-Nov-13 CUTTING
A7280 FITUP 26 27-Oct-13 21-Nov-13 FITUP
A7290 WELDING 26 28-Oct-13 22-Nov-13 WELDING
A7300 DYE PENETRANT TEST (DPT) 25 28-Oct-13 21-Nov-13 DYE PENETRANT TEST (DPT)
A7310 SAND BLASTING & PAINTING 25 28-Oct-13 21-Nov-13 SAND BLASTING & PAINTING
ERECTION 51 22-Nov-13 11-Jan-14 11-Jan-14, ERECTION
A7320 SHIFTING 4 22-Nov-13 25-Nov-13 SHIFTING
A7330 PLACING ON FOUNDATION 20 26-Nov-13 15-Dec-13 PLACING ON FOUNDATION
A7340 LEVELING & ALLIGNMENT 15 11-Dec-13 25-Dec-13 LEVELING & ALLIGNMENT
A7360 BOLTING/WELDING 25 18-Dec-13 11-Jan-14 BOLTING/WELDING
PIPE RACK-F 72 28-Oct-13 07-Jan-14 07-Jan-14, PIPE RACK-F
FABRICATION 45 28-Oct-13 11-Dec-13 11-Dec-13, FABRICATION
A7470 MARKING 6 28-Oct-13* 02-Nov-13 MARKING
A7480 CUTTING 12 29-Oct-13 09-Nov-13 CUTTING
A7490 FITUP 30 04-Nov-13 03-Dec-13 FITUP
A7500 WELDING 26 09-Nov-13 04-Dec-13 WELDING
A7510 DYE PENETRANT TEST (DPT) 25 16-Nov-13 10-Dec-13 DYE PENETRANT TEST (DPT)
A7520 SAND BLASTING & PAINTING 20 22-Nov-13 11-Dec-13 SAND BLASTING & PAINTING
ERECTION 27 12-Dec-13 07-Jan-14 07-Jan-14, ERECTION
A7710 SHIFTING 2 12-Dec-13 13-Dec-13 SHIFTING
A7720 PLACING ON FOUNDATION 12 14-Dec-13 25-Dec-13 PLACING ON FOUNDATION
A7730 LEVELING & ALLIGNMENT 14 19-Dec-13 01-Jan-14 LEVELING & ALLIGNMENT
A7750 BOLTING/WELDING 14 25-Dec-13 07-Jan-14 BOLTING/WELDING
PIPE RACK-C 90 31-Oct-13 28-Jan-14 28-Jan-14, PIPE RACK-C
FABRICATION 41 31-Oct-13 10-Dec-13 10-Dec-13, FABRICATION
A7530 MARKING 8 31-Oct-13* 07-Nov-13 MARKING
A7540 CUTTING 14 01-Nov-13 14-Nov-13 CUTTING

Actual Work Critical Remaining Work Summary Page 11 of 18 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


UCH-II GAS DEVELOPMENT PROJECT ACTIVITY SCHEDULE 23-Sep-13 09:40

Activity ID Activity Name Original Start Finish 2013 2014


Duration
Sep Oct Nov Dec Jan Feb Mar Apr May
A7550 FITUP 30 04-Nov-13 03-Dec-13 FITUP
A7560 WELDING 35 04-Nov-13 08-Dec-13 WELDING
A7570 DYE PENETRANT TEST (DPT) 30 09-Nov-13 08-Dec-13 DYE PENETRANT TEST (DPT)
A7580 SAND BLASTING & PAINTING 22 19-Nov-13 10-Dec-13 SAND BLASTING & PAINTING
ERECTION 49 11-Dec-13 28-Jan-14 28-Jan-14, ERECTION
A7760 SHIFTING 4 11-Dec-13 14-Dec-13 SHIFTING
A7770 PLACING ON FOUNDATION 20 15-Dec-13 03-Jan-14 PLACING ON FOUNDATION
A7780 LEVELING & ALLIGNMENT 30 15-Dec-13 13-Jan-14 LEVELING & ALLIGNMENT
A7800 BOLTING/WELDING 25 04-Jan-14 28-Jan-14 BOLTING/WELDING
PIPE RACK-A 72 05-Nov-13 15-Jan-14 15-Jan-14, PIPE RACK-A
FABRICATION 35 05-Nov-13 09-Dec-13 09-Dec-13, FABRICATION
A7590 MARKING 5 05-Nov-13* 09-Nov-13 MARKING
A7600 CUTTING 10 06-Nov-13 15-Nov-13 CUTTING
A7610 FITUP 30 08-Nov-13 07-Dec-13 FITUP
A7620 WELDING 30 08-Nov-13 07-Dec-13 WELDING
A7630 DYE PENETRANT TEST (DPT) 25 12-Nov-13 06-Dec-13 DYE PENETRANT TEST (DPT)
A7640 SAND BLASTING & PAINTING 15 25-Nov-13 09-Dec-13 SAND BLASTING & PAINTING
ERECTION 37 10-Dec-13 15-Jan-14 15-Jan-14, ERECTION
A7810 SHIFTING 3 10-Dec-13 12-Dec-13 SHIFTING
A7820 PLACING ON FOUNDATION 15 13-Dec-13 27-Dec-13 PLACING ON FOUNDATION
A7830 LEVELING & ALLIGNMENT 10 25-Dec-13 03-Jan-14 LEVELING & ALLIGNMENT
A7850 BOLTING/WELDING 18 29-Dec-13 15-Jan-14 BOLTING/WELDING
PIPE RACK-G 87 05-Nov-13 30-Jan-14 30-Jan-14, PIPE RACK-G
FABRICATION 36 05-Nov-13 10-Dec-13 10-Dec-13, FABRICATION
A7650 MARKING 4 05-Nov-13* 08-Nov-13 MARKING
A7660 CUTTING 10 06-Nov-13 15-Nov-13 CUTTING
A7670 FITUP 30 08-Nov-13 07-Dec-13 FITUP
A7680 WELDING 30 11-Nov-13 10-Dec-13 WELDING
A7690 DYE PENETRANT TEST (DPT) 30 11-Nov-13 10-Dec-13 DYE PENETRANT TEST (DPT)
A7700 SAND BLASTING & PAINTING 25 15-Nov-13 09-Dec-13 SAND BLASTING & PAINTING
ERECTION 52 10-Dec-13 30-Jan-14 30-Jan-14, ERECTION
A7860 SHIFTING 3 10-Dec-13 12-Dec-13 SHIFTING
A7870 PLACING ON FOUNDATION 25 13-Dec-13 06-Jan-14 PLACING ON FOUNDATION
A7880 LEVELING & ALLIGNMENT 15 28-Dec-13 11-Jan-14 LEVELING & ALLIGNMENT
A7900 BOLTING/WELDING 25 06-Jan-14 30-Jan-14 BOLTING/WELDING
AMINE UNIT-I 100 10-Jan-14 20-Apr-14 20-Apr-14, AMINE UNIT-I
AMINE CONTACTOR 13 10-Jan-14 23-Jan-14 23-Jan-14, AMINE CONTACTOR
A7370 SHIFTING 1 10-Jan-14 11-Jan-14 SHIFTING
A7380 PLACING ON FOUNDATION 1 11-Jan-14 12-Jan-14 PLACING ON FOUNDATION
A7390 LEVELING & ALLIGNMENT 4 12-Jan-14 16-Jan-14 LEVELING & ALLIGNMENT
A7400 GROUTING 1 16-Jan-14 17-Jan-14 GROUTING
A7410 BOLTING/WELDING 6 17-Jan-14 23-Jan-14 BOLTING/WELDING
AMINE REGENERATOR 18 11-Jan-14 29-Jan-14 29-Jan-14, AMINE REGENERATOR
A7910 SHIFTING 1 11-Jan-14 12-Jan-14 SHIFTING
A7920 PLACING ON FOUNDATION 2 12-Jan-14 14-Jan-14 PLACING ON FOUNDATION
A7930 LEVELING & ALLIGNMENT 5 14-Jan-14 19-Jan-14 LEVELING & ALLIGNMENT
A7940 GROUTING 1 19-Jan-14 20-Jan-14 GROUTING
A7950 BOLTING/WELDING 9 20-Jan-14 29-Jan-14 BOLTING/WELDING
FEED GAS K.O DRUM 15 11-Jan-14 26-Jan-14 26-Jan-14, FEED GAS K.O DRUM
A7960 SHIFTING 1 11-Jan-14 12-Jan-14 SHIFTING

Actual Work Critical Remaining Work Summary Page 12 of 18 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


UCH-II GAS DEVELOPMENT PROJECT ACTIVITY SCHEDULE 23-Sep-13 09:40

Activity ID Activity Name Original Start Finish 2013 2014


Duration
Sep Oct Nov Dec Jan Feb Mar Apr May
A7970 PLACING ON FOUNDATION 3 12-Jan-14 15-Jan-14 PLACING ON FOUNDATION
A7980 LEVELING & ALLIGNMENT 4 15-Jan-14 19-Jan-14 LEVELING & ALLIGNMENT
A7990 GROUTING 1 19-Jan-14 20-Jan-14 GROUTING
A8000 BOLTING/WELDING 6 20-Jan-14 26-Jan-14 BOLTING/WELDING
FEED GAS FILTER COALESCER 16 11-Jan-14 27-Jan-14 27-Jan-14, FEED GAS FILTER COALESCER
A8010 SHIFTING 1 11-Jan-14 12-Jan-14 SHIFTING
A8020 PLACING ON FOUNDATION 3 12-Jan-14 15-Jan-14 PLACING ON FOUNDATION
A8030 LEVELING & ALLIGNMENT 4 15-Jan-14 19-Jan-14 LEVELING & ALLIGNMENT
A8040 GROUTING 2 19-Jan-14 21-Jan-14 GROUTING
A8050 BOLTING/WELDING 6 21-Jan-14 27-Jan-14 BOLTING/WELDING
TREATED GAS LO DRUM 18 11-Jan-14 29-Jan-14 29-Jan-14, TREATED GAS LO DRUM
A8060 SHIFTING 1 11-Jan-14 12-Jan-14 SHIFTING
A8070 PLACING ON FOUNDATION 2 12-Jan-14 14-Jan-14 PLACING ON FOUNDATION
A8080 LEVELING & ALLIGNMENT 6 14-Jan-14 20-Jan-14 LEVELING & ALLIGNMENT
A8090 GROUTING 2 20-Jan-14 22-Jan-14 GROUTING
A8100 BOLTING/WELDING 7 22-Jan-14 29-Jan-14 BOLTING/WELDING
RICH AMINE FLASH DRUM 11 29-Jan-14 09-Feb-14 09-Feb-14, RICH AMINE FLASH DRUM
A8110 SHIFTING 1 29-Jan-14 30-Jan-14 SHIFTING
A8120 PLACING ON FOUNDATION 2 30-Jan-14 01-Feb-14 PLACING ON FOUNDATION
A8130 LEVELING & ALLIGNMENT 2 01-Feb-14 03-Feb-14 LEVELING & ALLIGNMENT
A8140 GROUTING 2 03-Feb-14 05-Feb-14 GROUTING
A8150 BOLTING/WELDING 4 05-Feb-14 09-Feb-14 BOLTING/WELDING
AMINE SURGE VESSEL 13 30-Jan-14 12-Feb-14 12-Feb-14, AMINE SURGE VESSEL
A8160 SHIFTING 1 30-Jan-14 31-Jan-14 SHIFTING
A8170 PLACING ON FOUNDATION 2 31-Jan-14 02-Feb-14 PLACING ON FOUNDATION
A8180 LEVELING & ALLIGNMENT 3 02-Feb-14 05-Feb-14 LEVELING & ALLIGNMENT
A8190 GROUTING 2 05-Feb-14 07-Feb-14 GROUTING
A8200 BOLTING/WELDING 5 07-Feb-14 12-Feb-14 BOLTING/WELDING
REGENERATOR REFLUX DRUM 12 31-Jan-14 12-Feb-14 12-Feb-14, REGENERATOR REFLUX DRUM
A8210 SHIFTING 1 31-Jan-14 01-Feb-14 SHIFTING
A8220 PLACING ON FOUNDATION 2 01-Feb-14 03-Feb-14 PLACING ON FOUNDATION
A8230 LEVELING & ALLIGNMENT 3 03-Feb-14 06-Feb-14 LEVELING & ALLIGNMENT
A8240 GROUTING 2 06-Feb-14 08-Feb-14 GROUTING
A8250 BOLTING/WELDING 4 08-Feb-14 12-Feb-14 BOLTING/WELDING
AMIN SUMP DRUM 11 01-Feb-14 12-Feb-14 12-Feb-14, AMIN SUMP DRUM
A8260 SHIFTING 1 01-Feb-14 02-Feb-14 SHIFTING
A8270 PLACING ON FOUNDATION 2 02-Feb-14 04-Feb-14 PLACING ON FOUNDATION
A8280 LEVELING & ALLIGNMENT 3 04-Feb-14 07-Feb-14 LEVELING & ALLIGNMENT
A8290 GROUTING 1 07-Feb-14 08-Feb-14 GROUTING
A8300 BOLTING/WELDING 4 08-Feb-14 12-Feb-14 BOLTING/WELDING
AMINE STORAGE TANK 10 12-Feb-14 22-Feb-14 22-Feb-14, AMINE STORAGE TANK
A8310 SHIFTING 1 12-Feb-14 13-Feb-14 SHIFTING
A8320 PLACING ON FOUNDATION 1 13-Feb-14 14-Feb-14 PLACING ON FOUNDATION
A8330 LEVELING & ALLIGNMENT 3 14-Feb-14 17-Feb-14 LEVELING & ALLIGNMENT
A8340 GROUTING 2 17-Feb-14 19-Feb-14 GROUTING
A8350 BOLTING/WELDING 3 19-Feb-14 22-Feb-14 BOLTING/WELDING
LEAN AMINE STRAINERS 11 22-Feb-14 05-Mar-14 05-Mar-14, LEAN AMINE STRAINERS
A8360 SHIFTING 1 22-Feb-14 23-Feb-14 SHIFTING
A8370 PLACING ON FOUNDATION 1 23-Feb-14 24-Feb-14 PLACING ON FOUNDATION
A8380 LEVELING & ALLIGNMENT 3 24-Feb-14 27-Feb-14 LEVELING & ALLIGNMENT
A8390 GROUTING 2 27-Feb-14 01-Mar-14 GROUTING

Actual Work Critical Remaining Work Summary Page 13 of 18 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


UCH-II GAS DEVELOPMENT PROJECT ACTIVITY SCHEDULE 23-Sep-13 09:40

Activity ID Activity Name Original Start Finish 2013 2014


Duration
Sep Oct Nov Dec Jan Feb Mar Apr May
A8400 BOLTING/WELDING 4 01-Mar-14 05-Mar-14 BOLTING/WELDING
CARBON BED FILTER 8 23-Feb-14 03-Mar-14 03-Mar-14, CARBON BED FILTER
A8410 SHIFTING 1 23-Feb-14 24-Feb-14 SHIFTING
A8420 PLACING ON FOUNDATION 1 24-Feb-14 25-Feb-14 PLACING ON FOUNDATION
A8430 LEVELING & ALLIGNMENT 2 25-Feb-14 27-Feb-14 LEVELING & ALLIGNMENT
A8440 GROUTING 1 27-Feb-14 28-Feb-14 GROUTING
A8450 BOLTING/WELDING 3 28-Feb-14 03-Mar-14 BOLTING/WELDING
LEAN AMINE CARTRIDGE FILTER 6 24-Feb-14 02-Mar-14 02-Mar-14, LEAN AMINE CARTRIDGE FILTER
A8460 SHIFTING 1 24-Feb-14 25-Feb-14 SHIFTING
A8470 PLACING ON FOUNDATION 1 25-Feb-14 26-Feb-14 PLACING ON FOUNDATION
A8480 LEVELING & ALLIGNMENT 1 26-Feb-14 27-Feb-14 LEVELING & ALLIGNMENT
A8490 GROUTING 1 27-Feb-14 28-Feb-14 GROUTING
A8500 BOLTING/WELDING 2 28-Feb-14 02-Mar-14 BOLTING/WELDING
AMINE FILTER 5 02-Mar-14 07-Mar-14 07-Mar-14, AMINE FILTER
A8510 SHIFTING 1 02-Mar-14 03-Mar-14 SHIFTING
A8520 PLACING ON FOUNDATION 1 03-Mar-14 04-Mar-14 PLACING ON FOUNDATION
A8530 LEVELING & ALLIGNMENT 1 04-Mar-14 05-Mar-14 LEVELING & ALLIGNMENT
A8540 GROUTING 1 05-Mar-14 06-Mar-14 GROUTING
A8550 BOLTING/WELDING 1 06-Mar-14 07-Mar-14 BOLTING/WELDING
RICH AMINE STRAINERS 10 03-Mar-14 13-Mar-14 13-Mar-14, RICH AMINE STRAINERS
A8560 SHIFTING 1 03-Mar-14 04-Mar-14 SHIFTING
A8570 PLACING ON FOUNDATION 2 04-Mar-14 06-Mar-14 PLACING ON FOUNDATION
A8580 LEVELING & ALLIGNMENT 3 06-Mar-14 09-Mar-14 LEVELING & ALLIGNMENT
A8590 GROUTING 1 09-Mar-14 10-Mar-14 GROUTING
A8600 BOLTING/WELDING 3 10-Mar-14 13-Mar-14 BOLTING/WELDING
COOLING WATER SIDE FILTER 5 03-Mar-14 08-Mar-14 08-Mar-14, COOLING WATER SIDE FILTER
A8610 SHIFTING 1 03-Mar-14 04-Mar-14 SHIFTING
A8620 PLACING ON FOUNDATION 1 04-Mar-14 05-Mar-14 PLACING ON FOUNDATION
A8630 LEVELING & ALLIGNMENT 1 05-Mar-14 06-Mar-14 LEVELING & ALLIGNMENT
A8640 GROUTING 1 06-Mar-14 07-Mar-14 GROUTING
A8650 BOLTING/WELDING 1 07-Mar-14 08-Mar-14 BOLTING/WELDING
COOLING TOWERS 9 03-Mar-14 12-Mar-14 12-Mar-14, COOLING TOWERS
A8660 SHIFTING 1 03-Mar-14 04-Mar-14 SHIFTING
A8670 PLACING ON FOUNDATION 2 04-Mar-14 06-Mar-14 PLACING ON FOUNDATION
A8680 LEVELING & ALLIGNMENT 2 06-Mar-14 08-Mar-14 LEVELING & ALLIGNMENT
A8690 GROUTING 1 08-Mar-14 09-Mar-14 GROUTING
A8700 BOLTING/WELDING 3 09-Mar-14 12-Mar-14 BOLTING/WELDING
FEED GAS HEATER 7 12-Mar-14 19-Mar-14 19-Mar-14, FEED GAS HEATER
A8710 SHIFTING 1 12-Mar-14 13-Mar-14 SHIFTING
A8720 PLACING ON FOUNDATION 1 13-Mar-14 14-Mar-14 PLACING ON FOUNDATION
A8730 LEVELING & ALLIGNMENT 2 14-Mar-14 16-Mar-14 LEVELING & ALLIGNMENT
A8740 GROUTING 1 16-Mar-14 17-Mar-14 GROUTING
A8750 BOLTING/WELDING 2 17-Mar-14 19-Mar-14 BOLTING/WELDING
LEAN / RICH AMIN EXCHANGER 9 19-Mar-14 28-Mar-14 28-Mar-14, LEAN / RICH AMIN EXCHANGER
A8760 SHIFTING 1 19-Mar-14 20-Mar-14 SHIFTING
A8770 PLACING ON FOUNDATION 1 20-Mar-14 21-Mar-14 PLACING ON FOUNDATION
A8780 LEVELING & ALLIGNMENT 3 21-Mar-14 24-Mar-14 LEVELING & ALLIGNMENT
A8790 GROUTING 1 24-Mar-14 25-Mar-14 GROUTING
A8800 BOLTING/WELDING 3 25-Mar-14 28-Mar-14 BOLTING/WELDING
REGERATOR REBOILERS 12 19-Mar-14 31-Mar-14 31-Mar-14, REGERATOR REBOILERS
A8810 SHIFTING 1 19-Mar-14 20-Mar-14 SHIFTING

Actual Work Critical Remaining Work Summary Page 14 of 18 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


UCH-II GAS DEVELOPMENT PROJECT ACTIVITY SCHEDULE 23-Sep-13 09:40

Activity ID Activity Name Original Start Finish 2013 2014


Duration
Sep Oct Nov Dec Jan Feb Mar Apr May
A8820 PLACING ON FOUNDATION 2 20-Mar-14 22-Mar-14 PLACING ON FOUNDATION
A8830 LEVELING & ALLIGNMENT 3 22-Mar-14 25-Mar-14 LEVELING & ALLIGNMENT
A8840 GROUTING 2 25-Mar-14 27-Mar-14 GROUTING
A8850 BOLTING/WELDING 4 27-Mar-14 31-Mar-14 BOLTING/WELDING
FEED GAS COOLER 8 19-Mar-14 27-Mar-14 27-Mar-14, FEED GAS COOLER
A8860 SHIFTING 1 19-Mar-14 20-Mar-14 SHIFTING
A8870 PLACING ON FOUNDATION 1 20-Mar-14 21-Mar-14 PLACING ON FOUNDATION
A8880 LEVELING & ALLIGNMENT 2 21-Mar-14 23-Mar-14 LEVELING & ALLIGNMENT
A8890 GROUTING 1 23-Mar-14 24-Mar-14 GROUTING
A8900 BOLTING/WELDING 3 24-Mar-14 27-Mar-14 BOLTING/WELDING
TREATED GAS COOLER 8 20-Mar-14 28-Mar-14 28-Mar-14, TREATED GAS COOLER
A8910 SHIFTING 1 20-Mar-14 21-Mar-14 SHIFTING
A8920 PLACING ON FOUNDATION 2 21-Mar-14 23-Mar-14 PLACING ON FOUNDATION
A8930 LEVELING & ALLIGNMENT 1 23-Mar-14 24-Mar-14 LEVELING & ALLIGNMENT
A8940 GROUTING 1 24-Mar-14 25-Mar-14 GROUTING
A8950 BOLTING/WELDING 3 25-Mar-14 28-Mar-14 BOLTING/WELDING
LEAN AMINE TRIM COOLER 9 21-Mar-14 30-Mar-14 30-Mar-14, LEAN AMINE TRIM COOLER
A8960 SHIFTING 1 21-Mar-14 22-Mar-14 SHIFTING
A8970 PLACING ON FOUNDATION 2 22-Mar-14 24-Mar-14 PLACING ON FOUNDATION
A8980 LEVELING & ALLIGNMENT 2 24-Mar-14 26-Mar-14 LEVELING & ALLIGNMENT
A8990 GROUTING 1 26-Mar-14 27-Mar-14 GROUTING
A9000 BOLTING/WELDING 3 27-Mar-14 30-Mar-14 BOLTING/WELDING
REGENERATOR CONDENSER 10 30-Mar-14 09-Apr-14 09-Apr-14, REGENERATOR CONDENSER
A9010 SHIFTING 1 30-Mar-14 31-Mar-14 SHIFTING
A9020 PLACING ON FOUNDATION 2 31-Mar-14 02-Apr-14 PLACING ON FOUNDATION
A9030 LEVELING & ALLIGNMENT 2 02-Apr-14 04-Apr-14 LEVELING & ALLIGNMENT
A9040 GROUTING 1 04-Apr-14 05-Apr-14 GROUTING
A9050 BOLTING/WELDING 4 05-Apr-14 09-Apr-14 BOLTING/WELDING
LEAN AMINE COOLER 5 31-Mar-14 05-Apr-14 05-Apr-14, LEAN AMINE COOLER
A9060 SHIFTING 1 31-Mar-14 01-Apr-14 SHIFTING
A9070 PLACING ON FOUNDATION 1 01-Apr-14 02-Apr-14 PLACING ON FOUNDATION
A9080 LEVELING & ALLIGNMENT 1 02-Apr-14 03-Apr-14 LEVELING & ALLIGNMENT
A9090 GROUTING 1 03-Apr-14 04-Apr-14 GROUTING
A9100 BOLTING/WELDING 1 04-Apr-14 05-Apr-14 BOLTING/WELDING
LEAN AMINE BOOSTER PUMPS 6 31-Mar-14 06-Apr-14 06-Apr-14, LEAN AMINE BOOSTER PUMPS
A9110 SHIFTING 1 31-Mar-14 01-Apr-14 SHIFTING
A9120 PLACING ON FOUNDATION 1 01-Apr-14 02-Apr-14 PLACING ON FOUNDATION
A9130 LEVELING & ALLIGNMENT 2 02-Apr-14 04-Apr-14 LEVELING & ALLIGNMENT
A9140 GROUTING 1 04-Apr-14 05-Apr-14 GROUTING
A9150 BOLTING/WELDING 1 05-Apr-14 06-Apr-14 BOLTING/WELDING
LEAN AMINE CIRCULATION PUMPS 6 31-Mar-14 06-Apr-14 06-Apr-14, LEAN AMINE CIRCULATION PUMPS
A9160 SHIFTING 1 31-Mar-14 01-Apr-14 SHIFTING
A9170 PLACING ON FOUNDATION 1 01-Apr-14 02-Apr-14 PLACING ON FOUNDATION
A9180 LEVELING & ALLIGNMENT 2 02-Apr-14 04-Apr-14 LEVELING & ALLIGNMENT
A9190 GROUTING 1 04-Apr-14 05-Apr-14 GROUTING
A9200 BOLTING/WELDING 1 05-Apr-14 06-Apr-14 BOLTING/WELDING
REGENERATOR REFLUX PUMPS 6 31-Mar-14 06-Apr-14 06-Apr-14, REGENERATOR REFLUX PUMPS
A9210 SHIFTING 1 31-Mar-14 01-Apr-14 SHIFTING
A9220 PLACING ON FOUNDATION 1 01-Apr-14 02-Apr-14 PLACING ON FOUNDATION
A9230 LEVELING & ALLIGNMENT 2 02-Apr-14 04-Apr-14 LEVELING & ALLIGNMENT
A9240 GROUTING 1 04-Apr-14 05-Apr-14 GROUTING

Actual Work Critical Remaining Work Summary Page 15 of 18 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


UCH-II GAS DEVELOPMENT PROJECT ACTIVITY SCHEDULE 23-Sep-13 09:40

Activity ID Activity Name Original Start Finish 2013 2014


Duration
Sep Oct Nov Dec Jan Feb Mar Apr May
A9250 BOLTING/WELDING 1 05-Apr-14 06-Apr-14 BOLTING/WELDING
FRESH AMINE TRANSFER PUMPS 6 31-Mar-14 06-Apr-14 06-Apr-14, FRESH AMINE TRANSFER PUMPS
A9260 SHIFTING 1 31-Mar-14 01-Apr-14 SHIFTING
A9270 PLACING ON FOUNDATION 1 01-Apr-14 02-Apr-14 PLACING ON FOUNDATION
A9280 LEVELING & ALLIGNMENT 2 02-Apr-14 04-Apr-14 LEVELING & ALLIGNMENT
A9290 GROUTING 1 04-Apr-14 05-Apr-14 GROUTING
A9300 BOLTING/WELDING 1 05-Apr-14 06-Apr-14 BOLTING/WELDING
PORTABLE AMINE DRUM PUMP 6 06-Apr-14 12-Apr-14 12-Apr-14, PORTABLE AMINE DRUM PUMP
A9310 SHIFTING 1 06-Apr-14 07-Apr-14 SHIFTING
A9320 PLACING ON FOUNDATION 1 07-Apr-14 08-Apr-14 PLACING ON FOUNDATION
A9330 LEVELING & ALLIGNMENT 2 08-Apr-14 10-Apr-14 LEVELING & ALLIGNMENT
A9340 GROUTING 1 10-Apr-14 11-Apr-14 GROUTING
A9350 BOLTING/WELDING 1 11-Apr-14 12-Apr-14 BOLTING/WELDING
AMINE SUMP PUMP 7 06-Apr-14 13-Apr-14 13-Apr-14, AMINE SUMP PUMP
A9360 SHIFTING 1 06-Apr-14 07-Apr-14 SHIFTING
A9370 PLACING ON FOUNDATION 1 07-Apr-14 08-Apr-14 PLACING ON FOUNDATION
A9380 LEVELING & ALLIGNMENT 2 08-Apr-14 10-Apr-14 LEVELING & ALLIGNMENT
A9390 GROUTING 1 10-Apr-14 11-Apr-14 GROUTING
A9400 BOLTING/WELDING 2 11-Apr-14 13-Apr-14 BOLTING/WELDING
COOLING TOWERS PUMPS 5 13-Apr-14 18-Apr-14 18-Apr-14, COOLING TOWERS PUMPS
A9410 SHIFTING 1 13-Apr-14 14-Apr-14 SHIFTING
A9420 PLACING ON FOUNDATION 1 14-Apr-14 15-Apr-14 PLACING ON FOUNDATION
A9430 LEVELING & ALLIGNMENT 1 15-Apr-14 16-Apr-14 LEVELING & ALLIGNMENT
A9440 GROUTING 1 16-Apr-14 17-Apr-14 GROUTING
A9450 BOLTING/WELDING 1 17-Apr-14 18-Apr-14 BOLTING/WELDING
HSS REMOVAL PACKAGE 7 13-Apr-14 20-Apr-14 20-Apr-14, HSS REMOVAL PACKAGE
A9460 SHIFTING 1 13-Apr-14 14-Apr-14 SHIFTING
A9470 PLACING ON FOUNDATION 1 14-Apr-14 15-Apr-14 PLACING ON FOUNDATION
A9480 LEVELING & ALLIGNMENT 2 15-Apr-14 17-Apr-14 LEVELING & ALLIGNMENT
A9490 GROUTING 1 17-Apr-14 18-Apr-14 GROUTING
A9500 BOLTING/WELDING 2 18-Apr-14 20-Apr-14 BOLTING/WELDING
ANTIFOAM INJECTION PACKAGE 5 13-Apr-14 18-Apr-14 18-Apr-14, ANTIFOAM INJECTION PAC
A9510 SHIFTING 1 13-Apr-14 14-Apr-14 SHIFTING
A9520 PLACING ON FOUNDATION 1 14-Apr-14 15-Apr-14 PLACING ON FOUNDATION
A9530 LEVELING & ALLIGNMENT 1 15-Apr-14 16-Apr-14 LEVELING & ALLIGNMENT
A9540 GROUTING 1 16-Apr-14 17-Apr-14 GROUTING
A9550 BOLTING/WELDING 1 17-Apr-14 18-Apr-14 BOLTING/WELDING
MISCELLANEOUS 177 25-Oct-13 20-Apr-14 20-Apr-14, MISCELLANEOUS
DIESEL PUMP 12 07-Nov-13 19-Nov-13 19-Nov-13, DIESEL PUMP
A7420 SHIFTING 1 07-Nov-13 08-Nov-13 SHIFTING
A7430 PLACING ON FOUNDATION 2 08-Nov-13 10-Nov-13 PLACING ON FOUNDATION
A7440 LEVELING & ALLIGNMENT 3 10-Nov-13 13-Nov-13 LEVELING & ALLIGNMENT
A7450 GROUTING 2 13-Nov-13 15-Nov-13 GROUTING
A7460 BOLTING/WELDING 4 15-Nov-13 19-Nov-13 BOLTING/WELDING
DEMIN SKID 12 27-Nov-13 09-Dec-13 09-Dec-13, DEMIN SKID
A9560 SHIFTING 1 27-Nov-13 28-Nov-13 SHIFTING
A9570 PLACING ON FOUNDATION 2 28-Nov-13 30-Nov-13 PLACING ON FOUNDATION
A9580 LEVELING & ALLIGNMENT 3 30-Nov-13 03-Dec-13 LEVELING & ALLIGNMENT
A9590 GROUTING 2 03-Dec-13 05-Dec-13 GROUTING
A9600 BOLTING/WELDING 4 05-Dec-13 09-Dec-13 BOLTING/WELDING
L.P FUEL GAS KO DRUM 18 07-Nov-13 25-Nov-13 25-Nov-13, L.P FUEL GAS KO DRUM

Actual Work Critical Remaining Work Summary Page 16 of 18 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


UCH-II GAS DEVELOPMENT PROJECT ACTIVITY SCHEDULE 23-Sep-13 09:40

Activity ID Activity Name Original Start Finish 2013 2014


Duration
Sep Oct Nov Dec Jan Feb Mar Apr May
A9610 SHIFTING 1 07-Nov-13 08-Nov-13 SHIFTING
A9620 PLACING ON FOUNDATION 3 08-Nov-13 11-Nov-13 PLACING ON FOUNDATION
A9630 LEVELING & ALLIGNMENT 5 11-Nov-13 16-Nov-13 LEVELING & ALLIGNMENT
A9640 GROUTING 2 16-Nov-13 18-Nov-13 GROUTING
A9650 BOLTING/WELDING 7 18-Nov-13 25-Nov-13 BOLTING/WELDING
INSTRUMENT AIR RECEIVER 24 21-Dec-13 14-Jan-14 14-Jan-14, INSTRUMENT AIR RECEIVER
A9660 SHIFTING 1 21-Dec-13 22-Dec-13 SHIFTING
A9670 PLACING ON FOUNDATION 3 22-Dec-13 25-Dec-13 PLACING ON FOUNDATION
A9680 LEVELING & ALLIGNMENT 10 25-Dec-13 04-Jan-14 LEVELING & ALLIGNMENT
A9690 GROUTING 2 04-Jan-14 06-Jan-14 GROUTING
A9700 BOLTING/WELDING 8 06-Jan-14 14-Jan-14 BOLTING/WELDING
NITROGEN RECEIVER 20 29-Nov-13 19-Dec-13 19-Dec-13, NITROGEN RECEIVER
A9710 SHIFTING 2 29-Nov-13 01-Dec-13 SHIFTING
A9720 PLACING ON FOUNDATION 2 01-Dec-13 03-Dec-13 PLACING ON FOUNDATION
A9730 LEVELING & ALLIGNMENT 6 03-Dec-13 09-Dec-13 LEVELING & ALLIGNMENT
A9740 GROUTING 2 09-Dec-13 11-Dec-13 GROUTING
A9750 BOLTING/WELDING 8 11-Dec-13 19-Dec-13 BOLTING/WELDING
BLOW CASE VESSEL 19 18-Nov-13 07-Dec-13 07-Dec-13, BLOW CASE VESSEL
A9760 SHIFTING 1 18-Nov-13 19-Nov-13 SHIFTING
A9770 PLACING ON FOUNDATION 4 19-Nov-13 23-Nov-13 PLACING ON FOUNDATION
A9780 LEVELING & ALLIGNMENT 6 23-Nov-13 29-Nov-13 LEVELING & ALLIGNMENT
A9790 GROUTING 2 29-Nov-13 01-Dec-13 GROUTING
A9800 BOLTING/WELDING 6 01-Dec-13 07-Dec-13 BOLTING/WELDING
POWER GENERATION & GAS TURBINE AREA 101 20-Dec-13 31-Mar-14 31-Mar-14, POWER GENERATION & GAS TURBIN
A9810 SHIFTING 4 20-Dec-13 24-Dec-13 SHIFTING
A9820 PLACING ON FOUNDATION 10 24-Dec-13 03-Jan-14 PLACING ON FOUNDATION
A9830 LEVELING & ALLIGNMENT 40 03-Jan-14 12-Feb-14 LEVELING & ALLIGNMENT
A9840 GROUTING 12 12-Feb-14 24-Feb-14 GROUTING
A9850 BOLTING/WELDING 35 24-Feb-14 31-Mar-14 BOLTING/WELDING
HOT OIL SYSTEM 66 13-Feb-14 20-Apr-14 20-Apr-14, HOT OIL SYSTEM
A9860 SHIFTING 5 13-Feb-14 18-Feb-14 SHIFTING
A9870 PLACING ON FOUNDATION 10 18-Feb-14 28-Feb-14 PLACING ON FOUNDATION
A9880 LEVELING & ALLIGNMENT 20 28-Feb-14 20-Mar-14 LEVELING & ALLIGNMENT
A9890 GROUTING 6 20-Mar-14 26-Mar-14 GROUTING
A9900 BOLTING/WELDING 25 26-Mar-14 20-Apr-14 BOLTING/WELDING
SLUG-CATCHER WITH PLATEFORM FOUNDATIONS 35 25-Oct-13 29-Nov-13 29-Nov-13, SLUG-CATCHER WITH PLATEFORM FOUNDATIONS
A9910 SHIFTING 2 25-Oct-13 27-Oct-13 SHIFTING
A9920 PLACING ON FOUNDATION 6 27-Oct-13 02-Nov-13 PLACING ON FOUNDATION
A9930 LEVELING & ALLIGNMENT 10 02-Nov-13 12-Nov-13 LEVELING & ALLIGNMENT
A9940 GROUTING 5 12-Nov-13 17-Nov-13 GROUTING
A9950 BOLTING/WELDING 12 17-Nov-13 29-Nov-13 BOLTING/WELDING
CONDENSATE WATER SEPERATORS 37 16-Nov-13 23-Dec-13 23-Dec-13, CONDENSATE WATER SEPERATORS
A9960 SHIFTING 3 16-Nov-13 19-Nov-13 SHIFTING
A9970 PLACING ON FOUNDATION 5 19-Nov-13 24-Nov-13 PLACING ON FOUNDATION
A9980 LEVELING & ALLIGNMENT 15 24-Nov-13 09-Dec-13 LEVELING & ALLIGNMENT
A9990 GROUTING 2 09-Dec-13 11-Dec-13 GROUTING
A9995 BOLTING/WELDING 12 11-Dec-13 23-Dec-13 BOLTING/WELDING
CONDENSATE DEGASSING BOOT 18 02-Jan-14 20-Jan-14 20-Jan-14, CONDENSATE DEGASSING BOOT
A10010 SHIFTING 2 02-Jan-14 04-Jan-14 SHIFTING
A10020 PLACING ON FOUNDATION 3 04-Jan-14 07-Jan-14 PLACING ON FOUNDATION
A10030 LEVELING & ALLIGNMENT 6 07-Jan-14 13-Jan-14 LEVELING & ALLIGNMENT

Actual Work Critical Remaining Work Summary Page 17 of 18 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


UCH-II GAS DEVELOPMENT PROJECT ACTIVITY SCHEDULE 23-Sep-13 09:40

Activity ID Activity Name Original Start Finish 2013 2014


Duration
Sep Oct Nov Dec Jan Feb Mar Apr May
A10040 GROUTING 2 13-Jan-14 15-Jan-14 GROUTING
A10050 BOLTING/WELDING 5 15-Jan-14 20-Jan-14 BOLTING/WELDING
FLARE KNOCKOUT DRUM 36 22-Dec-13 27-Jan-14 27-Jan-14, FLARE KNOCKOUT DRUM
A10060 SHIFTING 2 22-Dec-13 24-Dec-13 SHIFTING
A10070 PLACING ON FOUNDATION 6 24-Dec-13 30-Dec-13 PLACING ON FOUNDATION
A10080 LEVELING & ALLIGNMENT 15 30-Dec-13 14-Jan-14 LEVELING & ALLIGNMENT
A10090 GROUTING 3 14-Jan-14 17-Jan-14 GROUTING
A10100 BOLTING/WELDING 10 17-Jan-14 27-Jan-14 BOLTING/WELDING
FIRE WATER DIESEL ENGINE PUMP 20 10-Nov-13 30-Nov-13 30-Nov-13, FIRE WATER DIESEL ENGINE PUMP
A10110 SHIFTING 1 10-Nov-13 11-Nov-13 SHIFTING
A10120 PLACING ON FOUNDATION 3 11-Nov-13 14-Nov-13 PLACING ON FOUNDATION
A10130 LEVELING & ALLIGNMENT 7 14-Nov-13 21-Nov-13 LEVELING & ALLIGNMENT
A10140 GROUTING 2 21-Nov-13 23-Nov-13 GROUTING
A10150 BOLTING/WELDING 7 23-Nov-13 30-Nov-13 BOLTING/WELDING
FIRE WATER ELECTRIC DRIVEN PUMP 20 21-Nov-13 11-Dec-13 11-Dec-13, FIRE WATER ELECTRIC DRIVEN PUMP
A10160 SHIFTING 1 21-Nov-13 22-Nov-13 SHIFTING
A10170 PLACING ON FOUNDATION 3 22-Nov-13 25-Nov-13 PLACING ON FOUNDATION
A10180 LEVELING & ALLIGNMENT 8 25-Nov-13 03-Dec-13 LEVELING & ALLIGNMENT
A10190 GROUTING 2 03-Dec-13 05-Dec-13 GROUTING
A10200 BOLTING/WELDING 6 05-Dec-13 11-Dec-13 BOLTING/WELDING
ELECTRICAL 118 01-Jan-14 28-Apr-14 28-Apr-14, ELECTRICAL

INSTRUMENTATION & CONTROL 94 25-Jan-14 28-Apr-14 28-Apr-14, INSTRUMENTATION


A6530 INSTRUMENT CABLE LAYING & TERMINATION 40 25-Jan-14* 05-Mar-14 INSTRUMENT CABLE LAYING & TERMINATION
A6540 CABLE TRAY INSTALLATION & ACCESSORIES 35 30-Jan-14* 05-Mar-14 CABLE TRAY INSTALLATION & ACCESSORIES
A6550 INSTALLATION OF FIRES,GAS POLES & DETECTORS 45 05-Feb-14* 21-Mar-14 INSTALLATION OF FIRES,GAS POLES & DETECTORS
A6560 INSTALLATION OF INSTRUMENT HOOK UPS 35 11-Feb-14* 17-Mar-14 INSTALLATION OF INSTRUMENT HOOK UPS
A6570 INSTALLATION OF RTU PANNEL 45 25-Feb-14* 10-Apr-14 INSTALLATION OF RTU PANNEL
A6580 INSTALLATION OF INSTRUMENT JUNCTION BOXES 50 06-Mar-14* 24-Apr-14 INSTALLATION OF INSTRUMENT
A6590 INSTALLATION OF ESD PUSH BOTTONS 40 20-Mar-14* 28-Apr-14 INSTALLATION OF ESD PUSH B
ELECTRICAL SYSTEM 110 01-Jan-14 20-Apr-14 20-Apr-14, ELECTRICAL SYSTEM
A6650 CABLE TRAY & ACCESSORIES INSTALLATION 50 01-Jan-14* 19-Feb-14 CABLE TRAY & ACCESSORIES INSTALLATION
A6660 POWER CABLE LAYING & TERMINATION 40 10-Jan-14* 18-Feb-14 POWER CABLE LAYING & TERMINATION
A6670 INSTALLATION OF DB'S 35 25-Feb-14* 31-Mar-14 INSTALLATION OF DB'S
A6680 INSTALLATION OF LIGHTING SYSTEM 40 10-Mar-14* 18-Apr-14 INSTALLATION OF LIGHTING SYSTEM
A6690 INSTALLATION OF SOLAR ARRAY SYSTEM 30 15-Mar-14* 13-Apr-14 INSTALLATION OF SOLAR ARRAY SYSTE
A6700 INSTALLATION OF HEAT TRACING 40 12-Mar-14* 20-Apr-14 INSTALLATION OF HEAT TRACING
A6710 INSTALLATION OF JN'S 45 02-Mar-14* 15-Apr-14 INSTALLATION OF JN'S
TELECOMMUNICATION 46 14-Mar-14 28-Apr-14 28-Apr-14, TELECOMMUNICAT
A6600 FIBER OPTIC CABLE LAYING & TERMINATION 35 14-Mar-14* 17-Apr-14 FIBER OPTIC CABLE LAYING & TERMI
A6610 INSTALLATION OF CCTV'S 30 25-Mar-14* 23-Apr-14 INSTALLATION OF CCTV'S
A6620 INSTALLATION OF SWITCHES 35 20-Mar-14* 23-Apr-14 INSTALLATION OF SWITCHES
A6630 INSTALLATION OF TELEPHONES 30 30-Mar-14* 28-Apr-14 INSTALLATION OF TELEPHONE
A6640 INSTALLATION OF FOC PATCH PANELS 45 15-Mar-14* 28-Apr-14 INSTALLATION OF FOC PATCH

Actual Work Critical Remaining Work Summary Page 18 of 18 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.