Activity ID Activity Name Original Early Start Early Finish 2014

Duration May June July August September October


November
25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 05 12 19 26 02
165 25-May-14 05-Nov-14
Interior fit out & MEP works for DIB Baniyas Branch, Abu Dhabi, UAE
2 25-May-14 27-May-14
General
A1000 Work order confirmation 1 25-May-14 25-May-14
25-May-14 25-May-14
A1010 Kick off meeting 1 26-May-14 26-May-14
26-May-14 26-May-14
A1540 Receipt of client documents & drawings 0 27-May-14
78 27-May-14 12-Aug-14
Pre-construction
Shop drawing approval 39 27-May-14 10-Jul-14
A1020 Shop drawing preparation 30 27-May-14 30-Jun-14
27-May-14 30-Jun-14
A1030 Shop drawing submission 25 08-Jun-14 06-Jul-14
08-Jun-14 06-Jul-14
A1040 Shop drawing approval 25 12-Jun-14 10-Jul-14 12-Jun-14 10-Jul-14
A1490 Receipt of Shop drawing approval 0 10-Jul-14
Sample approval 14 27-May-14 11-Jun-14
A1050 Preparation of samples 10 27-May-14 07-Jun-14
27-May-14 07-Jun-14
A1060 Submission of samples 1 08-Jun-14 08-Jun-14
08-Jun-14 08-Jun-14
A1070 Approval of samples 3 09-Jun-14 11-Jun-1409-Jun-14 11-Jun-14
A1500 Receipt of sample approval 0 11-Jun-14
Authority approval 22 27-May-14 17-Jun-14
A1080 Preparation of documents 6 27-May-14 02-Jun-14
27-May-14 02-Jun-14
A1090 Submission of documents 1 03-Jun-14 03-Jun-14
03-Jun-14 03-Jun-14
A1100 Authority approvals 10 04-Jun-14 17-Jun-14
04-Jun-14 17-Jun-14
Procurement & Production 65 09-Jun-14 12-Aug-14
A1110 Procurement of materials 28 09-Jun-14 06-Jul-1409-Jun-14 06-Jul-14
A1120 Joinery production 30 11-Jul-14 09-Aug-14 11-Jul-14 09-Aug-14
A1130 Delivery of materials to site 18 26-Jul-14 12-Aug-14 26-Jul-14 12-Aug-14
141 17-Jun-14 05-Nov-14
Construction
Phase 01 (Men's Retail area) 60 17-Jun-14 16-Aug-14
General 4 17-Jun-14 21-Jun-14
A1140 Access to site 0 17-Jun-14
A1150 Site mobilization 3 17-Jun-14 21-Jun-14 17-Jun-14 21-Jun-14
Civil works 9 21-Jun-14 01-Jul-14
A1770 Demolition works 5 21-Jun-14 26-Jun-14 21-Jun-14 26-Jun-14
A1780 Solid concrete block works 4 26-Jun-14 01-Jul-14 26-Jun-14 01-Jul-14
MEP 1st and 2nd fix 14 01-Jul-14 17-Jul-14
A2030 Conduits & wiring installation 7 01-Jul-14 09-Jul-14 01-Jul-14 09-Jul-14
A2040 A/C ducting and connections 7 01-Jul-14 09-Jul-14 01-Jul-14 09-Jul-14
A2050 FF pipes installation 6 01-Jul-14 08-Jul-14 01-Jul-14 08-Jul-14
A2070 DB installation & connection 2 09-Jul-14 12-Jul-14 09-Jul-14 12-Jul-14
A2060 FF drops installation 2 15-Jul-14 17-Jul-14 15-Jul-14 17-Jul-14
Wall partiton works 8 03-Jul-14 13-Jul-14
A1790 Gypsum board lining & wall partitons 8 03-Jul-14 13-Jul-14 03-Jul-14 13-Jul-14
Steel works 4 01-Jul-14 06-Jul-14
A1810 Metal sheet cladding to block walls 2 01-Jul-14 03-Jul-14 01-Jul-14 03-Jul-14

Project Start: 25-May-14 Actual Work Interior fit out MEP works for DIB Baniyas Date Revision Checked Approved

Remaining Work
Branch, Abu Dhabi, UAE
Date: 19-May-14 Critical Remaining Work
Page 1 of 5
Activity ID Activity Name Original Early Start Early Finish 2014
Duration May June July August September October
November
25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 05 12 19 26 02
A1820 Galvanized sheet cladding to ATM walls 2 03-Jul-14 06-Jul-14 03-Jul-14 06-Jul-14
Floor finishes 21 09-Jul-14 03-Aug-14
A1870 laying of cement sand screed 4 09-Jul-14 14-Jul-14 09-Jul-14 14-Jul-14
A1880 Crema marfil floor tiles installation 3 26-Jul-14 29-Jul-14 26-Jul-14 29-Jul-14
A1890 Non-slip ceramic floor tiles installation 2 26-Jul-14 28-Jul-14 26-Jul-14 28-Jul-14
A1910 Raised access flooring with vinyl and marble finish 4 26-Jul-14 30-Jul-14 26-Jul-14 30-Jul-14
A1900 Vinyl flooring installation 2 29-Jul-14 31-Jul-14 29-Jul-14 31-Jul-14
A1920 Skirting installation 2 31-Jul-14 03-Aug-14 31-Jul-14 03-Aug-14
Wall finishes 19 13-Jul-14 04-Aug-14
A1980 Glass fixing on partitions 3 13-Jul-14 16-Jul-14 13-Jul-14 16-Jul-14
A1960 Polished ceramic wall tiling 2 20-Jul-14 22-Jul-14 20-Jul-14 22-Jul-14
A1970 Wall covering installation 2 26-Jul-14 28-Jul-14 26-Jul-14 28-Jul-14
A1940 Painting 1st and 2nd coat on walls & ceiling 2 29-Jul-14 31-Jul-14 29-Jul-14 31-Jul-14
A1950 Painting final coat on walls & ceiling 3 31-Jul-14 04-Aug-14 31-Jul-14 04-Aug-14
Ceiling finishes 17 09-Jul-14 29-Jul-14
A1990 Framework for ceiling 5 09-Jul-14 15-Jul-14 09-Jul-14 15-Jul-14
A2000 Inspection before ceiling closure 1 15-Jul-14 16-Jul-14 15-Jul-14 16-Jul-14
A2010 Boarding, taping & jointing 3 16-Jul-14 20-Jul-14 16-Jul-14 20-Jul-14
A1930 Primer and stucco on walls and ceiling 5 20-Jul-14 26-Jul-14 20-Jul-14 26-Jul-14
A2020 Fixing light boxes 3 26-Jul-14 29-Jul-14 26-Jul-14 29-Jul-14
Joinery items 18 26-Jul-14 16-Aug-14
A1850 Door frames installation 3 26-Jul-14 29-Jul-14 26-Jul-14 29-Jul-14
A1860 Door panels & ironmongaries installaiton 3 29-Jul-14 02-Aug-14 29-Jul-14 02-Aug-14
A1840 Dry pantry cabinets installation 3 13-Aug-14 16-Aug-14 13-Aug-14 16-Aug-14
MEP final fixing 3 26-Jul-14 29-Jul-14
A2080 Switches, sockets & lights installation 3 26-Jul-14 29-Jul-14 26-Jul-14 29-Jul-14
A2090 AC grills and diffusers installation 3 26-Jul-14 29-Jul-14 26-Jul-14 29-Jul-14
A2100 FF & FA devices installation 3 26-Jul-14 29-Jul-14 26-Jul-14 29-Jul-14
Snagging & Handover 8 29-Jul-14 07-Aug-14
A1760 Snagging works 4 29-Jul-14 03-Aug-14 29-Jul-14 03-Aug-14
A1670 Getting permanent power supply 3 29-Jul-14 02-Aug-14 29-Jul-14 02-Aug-14
A1600 Fire alarm testing & commissioning & panel programming 2 30-Jul-14 02-Aug-14 30-Jul-14 02-Aug-14
A1680 Electrical testing & commissioning 2 31-Jul-14 03-Aug-14 31-Jul-14 03-Aug-14
A1690 A/C air balancing & commissioning 2 02-Aug-14 04-Aug-14 02-Aug-14 04-Aug-14
A1710 Final inspection by client 2 04-Aug-14 06-Aug-14 04-Aug-14 06-Aug-14
A1720 Client possession 1 06-Aug-14 07-Aug-14 06-Aug-14 07-Aug-14
Phase 02 (Ladies banking area) 45 07-Aug-14 21-Sep-14
General 0 07-Aug-14 07-Aug-14
A2110 Access to site 0 07-Aug-14
Civil works 7 07-Aug-14 16-Aug-14
A2330 Demolition works 4 07-Aug-14 12-Aug-14 07-Aug-14 12-Aug-14
A2320 Solid concrete block works 3 12-Aug-14 16-Aug-14 12-Aug-14 16-Aug-14
MEP 1st and 2nd fix 14 16-Aug-14 01-Sep-14

Project Start: 25-May-14 Actual Work Interior fit out MEP works for DIB Baniyas Date Revision Checked Approved

Remaining Work
Branch, Abu Dhabi, UAE
Date: 19-May-14 Critical Remaining Work
Page 2 of 5
Activity ID Activity Name Original Early Start Early Finish 2014
Duration May June July August September October
November
25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 05 12 19 26 02
A2440 Conduits & wiring installation 7 16-Aug-14 24-Aug-14 16-Aug-14 24-Aug-14
A2450 A/C ducting and connections 7 16-Aug-14 24-Aug-14 16-Aug-14 24-Aug-14
A2460 FF pipes installation 6 16-Aug-14 23-Aug-14 16-Aug-14 23-Aug-14
A2480 DB installation & connection 2 24-Aug-14 26-Aug-14 24-Aug-14 26-Aug-14
A2470 FF drops installation 2 30-Aug-14 01-Sep-14 30-Aug-14 01-Sep-14
Wall partiton works 8 18-Aug-14 27-Aug-14
A2150 Gypsum board lining & wall partitons 8 18-Aug-14 27-Aug-14 18-Aug-14 27-Aug-14
Steel works 4 16-Aug-14 20-Aug-14
A2130 Metal sheet cladding to block walls 2 16-Aug-14 18-Aug-14 16-Aug-14 18-Aug-14
A2140 Galvanized sheet cladding to ATM walls 2 18-Aug-14 20-Aug-14 18-Aug-14 20-Aug-14
Floor finishes 20 24-Aug-14 16-Sep-14
A2190 laying of cement sand screed 4 24-Aug-14 28-Aug-14 24-Aug-14 28-Aug-14
A2200 Crema marfil floor tiles installation 3 08-Sep-14 11-Sep-14 08-Sep-14 11-Sep-14
A2210 Non-slip ceramic floor tiles installation 2 08-Sep-14 10-Sep-14 08-Sep-14 10-Sep-14
A2230 Raised access flooring with vinyl and marble finish 4 08-Sep-14 13-Sep-14 08-Sep-14 13-Sep-14
A2220 Vinyl flooring installation 2 11-Sep-14 14-Sep-14 11-Sep-14 14-Sep-14
A2240 Skirting installation 2 14-Sep-14 16-Sep-14 14-Sep-14 16-Sep-14
Wall finishes 18 27-Aug-14 17-Sep-14
A2380 Glass fixing on partitions 3 27-Aug-14 31-Aug-14 27-Aug-14 31-Aug-14
A2360 Polished ceramic wall tiling 2 03-Sep-14 06-Sep-14 03-Sep-14 06-Sep-14
A2370 Wall covering installation 2 08-Sep-14 10-Sep-14 08-Sep-14 10-Sep-14
A2340 Painting 1st and 2nd coat on walls & ceiling 2 11-Sep-14 14-Sep-14 11-Sep-14 14-Sep-14
A2350 Painting final coat on walls & ceiling 3 14-Sep-14 17-Sep-14 14-Sep-14 17-Sep-14
Ceiling finishes 16 24-Aug-14 11-Sep-14
A2400 Framework for ceiling 5 24-Aug-14 30-Aug-14 24-Aug-14 30-Aug-14
A2410 Inspection before ceiling closure 1 30-Aug-14 31-Aug-14 30-Aug-14 31-Aug-14
A2420 Boarding, taping & jointing 3 31-Aug-14 03-Sep-14 31-Aug-14 03-Sep-14
A2390 Primer and stucco on walls and ceiling 4 03-Sep-14 08-Sep-14 03-Sep-14 08-Sep-14
A2430 Fixing light boxes 3 08-Sep-14 11-Sep-14 08-Sep-14 11-Sep-14
Joinery items 6 08-Sep-14 15-Sep-14
A2160 Dry pantry cabinets installation 3 08-Sep-14 11-Sep-14 08-Sep-14 11-Sep-14
A2170 Door frames installation 3 08-Sep-14 11-Sep-14 08-Sep-14 11-Sep-14
A2180 Door panels & ironmongaries installaiton 3 11-Sep-14 15-Sep-14 11-Sep-14 15-Sep-14
MEP final fixing 3 08-Sep-14 11-Sep-14
A2490 Switches, sockets & lights installation 3 08-Sep-14 11-Sep-14 08-Sep-14 11-Sep-14
A2500 AC grills and diffusers installation 3 08-Sep-14 11-Sep-14 08-Sep-14 11-Sep-14
A2510 FF & FA devices installation 3 08-Sep-14 11-Sep-14 08-Sep-14 11-Sep-14
Snagging & Handover 8 11-Sep-14 21-Sep-14
A2270 Snagging works 4 11-Sep-14 16-Sep-14 11-Sep-14 16-Sep-14
A2290 Getting permanent power supply 3 11-Sep-14 15-Sep-14 11-Sep-14 15-Sep-14
A2280 Fire alarm testing & commissioning & panel programming 2 13-Sep-14 15-Sep-14 13-Sep-14 15-Sep-14
A2300 Electrical testing & commissioning 2 14-Sep-14 16-Sep-14 14-Sep-14 16-Sep-14
A2310 A/C air balancing & commissioning 2 15-Sep-14 17-Sep-14 15-Sep-14 17-Sep-14

Project Start: 25-May-14 Actual Work Interior fit out MEP works for DIB Baniyas Date Revision Checked Approved

Remaining Work
Branch, Abu Dhabi, UAE
Date: 19-May-14 Critical Remaining Work
Page 3 of 5
Activity ID Activity Name Original Early Start Early Finish 2014
Duration May June July August September October
November
25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 05 12 19 26 02
A2250 Final inspection by client 2 17-Sep-14 20-Sep-14 17-Sep-14 20-Sep-14
A2260 Client possession 1 20-Sep-14 21-Sep-14 20-Sep-14 21-Sep-14
Phase 03 (Customer Service area) 45 21-Sep-14 05-Nov-14
General 0 21-Sep-14 21-Sep-14
A2520 Access to site 0 21-Sep-14
Civil works 8 21-Sep-14 30-Sep-14
A2740 Demolition works 4 21-Sep-14 25-Sep-14 21-Sep-14 25-Sep-14
A2730 Solid concrete block works 4 25-Sep-14 30-Sep-14 25-Sep-14 30-Sep-14
MEP 1st and 2nd fix 14 30-Sep-14 16-Oct-14
A2850 Conduits & wiring installation 7 30-Sep-14 08-Oct-14 30-Sep-14 08-Oct-14
A2860 A/C ducting and connections 7 30-Sep-14 08-Oct-14 30-Sep-14 08-Oct-14
A2870 FF pipes installation 6 30-Sep-14 07-Oct-14 30-Sep-14 07-Oct-14
A2890 DB installation & connection 2 08-Oct-14 11-Oct-14 08-Oct-14 11-Oct-14
A2880 FF drops installation 2 14-Oct-14 16-Oct-14 14-Oct-14 16-Oct-14
Wall partiton works 8 02-Oct-14 12-Oct-14
A2560 Gypsum board lining & wall partitons 8 02-Oct-14 12-Oct-14 02-Oct-14 12-Oct-14
Steel works 4 30-Sep-14 05-Oct-14
A2540 Metal sheet cladding to block walls 2 30-Sep-14 02-Oct-14 30-Sep-14 02-Oct-14
A2550 Galvanized sheet cladding to ATM walls 2 02-Oct-14 05-Oct-14 02-Oct-14 05-Oct-14
Floor finishes 20 08-Oct-14 01-Nov-14
A2600 laying of cement sand screed 4 08-Oct-14 13-Oct-14 08-Oct-14 13-Oct-14
A2610 Crema marfil floor tiles installation 3 23-Oct-14 27-Oct-14 23-Oct-14 27-Oct-14
A2620 Non-slip ceramic floor tiles installation 2 23-Oct-14 26-Oct-14 23-Oct-14 26-Oct-14
A2640 Raised access flooring with vinyl and marble finish 4 23-Oct-14 28-Oct-14 23-Oct-14 28-Oct-14
A2630 Vinyl flooring installation 2 27-Oct-14 29-Oct-14 27-Oct-14 29-Oct-14
A2650 Skirting installation 2 29-Oct-14 01-Nov-14 29-Oct-14 01-Nov-14
Wall finishes 18 12-Oct-14 02-Nov-14
A2790 Glass fixing on partitions 3 12-Oct-14 15-Oct-14 12-Oct-14 15-Oct-14
A2770 Polished ceramic wall tiling 2 19-Oct-14 21-Oct-14 19-Oct-14 21-Oct-14
A2780 Wall covering installation 2 23-Oct-14 26-Oct-14 23-Oct-14 26-Oct-14
A2750 Painting 1st and 2nd coat on walls & ceiling 2 27-Oct-14 29-Oct-14 27-Oct-14 29-Oct-14
A2760 Painting final coat on walls & ceiling 3 29-Oct-14 02-Nov-14 29-Oct-14 02-Nov-14
Ceiling finishes 16 08-Oct-14 27-Oct-14
A2810 Framework for ceiling 5 08-Oct-14 14-Oct-14 08-Oct-14 14-Oct-14
A2820 Inspection before ceiling closure 1 14-Oct-14 15-Oct-14 14-Oct-14 15-Oct-14
A2830 Boarding, taping & jointing 3 15-Oct-14 19-Oct-14 15-Oct-14 19-Oct-14
A2800 Primer and stucco on walls and ceiling 4 19-Oct-14 23-Oct-14 19-Oct-14 23-Oct-14
A2840 Fixing light boxes 3 23-Oct-14 27-Oct-14 23-Oct-14 27-Oct-14
Joinery items 6 23-Oct-14 30-Oct-14
A2570 Dry pantry cabinets installation 3 23-Oct-14 27-Oct-14 23-Oct-14 27-Oct-14
A2580 Door frames installation 3 23-Oct-14 27-Oct-14 23-Oct-14 27-Oct-14
A2590 Door panels & ironmongaries installaiton 3 27-Oct-14 30-Oct-14 27-Oct-14 30-Oct-14
MEP final fixing 3 23-Oct-14 27-Oct-14

Project Start: 25-May-14 Actual Work Interior fit out MEP works for DIB Baniyas Date Revision Checked Approved

Remaining Work
Branch, Abu Dhabi, UAE
Date: 19-May-14 Critical Remaining Work
Page 4 of 5
Activity ID Activity Name Original Early Start Early Finish 2014
Duration May June July August September OctoberNovember
25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 05 12 19 26 02
A2900 Switches, sockets & lights installation 3 23-Oct-14 27-Oct-14 23-Oct-14 27-Oct-14
A2910 AC grills and diffusers installation 3 23-Oct-14 27-Oct-14 23-Oct-14 27-Oct-14
A2920 FF & FA devices installation 3 23-Oct-14 27-Oct-14 23-Oct-14 27-Oct-14
Snagging & Handover 8 27-Oct-14 05-Nov-14
A2680 Snagging works 4 27-Oct-14 01-Nov-14 27-Oct-14 01-Nov-14
A2700 Getting permanent power supply 3 27-Oct-14 30-Oct-14 27-Oct-14 30-Oct-14
A2690 Fire alarm testing & commissioning & panel programming 2 28-Oct-14 30-Oct-14 28-Oct-14 30-Oct-14
A2710 Electrical testing & commissioning 2 29-Oct-14 01-Nov-14 29-Oct-14 01-Nov-14
A2720 A/C air balancing & commissioning 2 30-Oct-14 02-Nov-14 30-Oct-14 02-Nov-14
A2660 Final inspection by client 2 02-Nov-14 04-Nov-14 02-Nov-14 04-Nov-14
A2670 Client possession 1 04-Nov-14 05-Nov-14 04-Nov-14 05-Nov-14

Project Start: 25-May-14 Actual Work Interior fit out MEP works for DIB Baniyas Date Revision Checked Approved

Remaining Work
Branch, Abu Dhabi, UAE
Date: 19-May-14 Critical Remaining Work