Date Activities Remarks

13/3/2015 Student learn to use strain gage and other equipment for Will be discuss for the indicator
preparation before testing at factory ( held at UITMPP) equipment for sagging (made by plywood)
20/3/2015 Factory will casting the precast concrete pile and student Factory cast 3 type of concrete pile and
will observe on the casting process. The strain gage will be each type need 3 sample to be tested.
put on the pile before concreting process.
21/3/2015 To see the de molding of the precast concrete pile and will The concrete cube test result will be help
be connecting data logger to be take the reading while in de monitored by the factory on the day 2, 3,
molding stages. 5, 7 and the following week is taken by
The concrete cube test result will be taken at day 1, 2, 3, 5, student.
7, 14, 21, 28, 35, 42, 49, 56, 63. This activities date is not confirm yet due
to depends on the factory de mold the
precast concrete pile take how many days
from the casting process. (TBD)
27/3/2015 Student will take the reading result on day 7 of the stress Student check and take the result being
development stages. taken by the factory on the past week.
(TBD)
03/4/2015 Student checking the result for week 2 (TBD)
10/4/2015 Student checking the result for week 3 (TBD)
17/4/2015 Student checking the result for week 4 (TBD)
24/4/2015 Student checking the result for week 5 (TBD)
01/5/2015 Student checking the result for week 6 (TBD)
08/5/2015 Student checking the result for week 7 (TBD)
15/5/2015 Student checking the result for week 8 (TBD)

TYPE OF PRECAST CONCRETE PILE

1. Pile size 200mm X 200mm X 9 m with reinforcement bar type 4T10 and with concrete grade 50.
This type need to be cast by the factory 3 sample.
2. Pile size 200mm X 200mm X 9 m with reinforcement bar type 4T10 and with concrete grade 60.
This type need to be cast by the factory 3 sample.
3. Pile size 200mm X 200mm X 9 m with reinforcement bar type 4T10 plus NTcrack bar and with
concrete grade 50. The NT crack bar type is T9 X 2.95m.This type need to be cast by the factory
3 sample.

CALIBRATION STAGES

 The factory will be prepared for student 3 type of the precast concrete pile with each type
consist 3 sample for student to be tested out in lab UITMPP. The precast concrete pile size is
(200mm X 200mm X 3m). (TBD)