Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
P.K.PATTANAIK
ASST. MANAGER (ELECT.)
GRID CORPORATION OF ORISSA LTD. BURLA
Grid sub-stations are the Interlocks are generally of power supply to the
powers from different regions in the system. For the stations, these equipments are
Isolator and Switch Gears are series to the breaker in the Some cases like automatic
the two important equipments system, then this isolator and SCADA controlled sub-
in the grid sub-station, which must not be operated when stations these are
play the important role for circuit breaker is in closed operated/controlled at the
correct and smooth operation condition i.e. the power Central Control Stations
avoid improper switching should not be done through In this article various
operations, inter locks are isolator. Because this interlock schemes with
among the isolators and switch, that operated in air supervision of the schemes
breakers that are involved medium. Switching action in have been discussed. Study to
Arrangements have also been to clear the fault through operated in parallel unless
dealt with relevant circuit breaker. their tap changer settings are
breaker / contact switch etc., 6. A circuit breaker Main and Transfer Bus
Isolator) can be operated, adjacent breaker in series to it most common used system
only when 52L (Line remains in OFF condition. for 33KV, 66 KV and 132
This scheme is very the Circuit breakers, present operation with ease
simple and easily understood. on either side of the isolator, maintenance without
Basically these isolators are feeding the power flow. The interruption and
interlocks are not provided in included to the scheme if Bus coupler. But in this
.2.Ring and mesh system: Example: 1. B1, B2, can be always used as loading
- (Fig. B) operated only when '52B1, bus. The total shut down
understood.
4
For interlock
Line isolator (29L) 1.Line breaker (52L) Applicable when earth switch is present
2. E/switch (29E)
Transfer isolator (29T) 1.B/C breaker (52B 1. To use only one feeder through bus
isolator of Transformer/Main 3.Double Bus bar system: event of fault on any bus. The
transfer bus isolator of any problem of continuous use of work of circuit breaker. The
distributing feeder, and then one bus as the main bus and bus-coupler scheme is also
power flow will result other as the reserve bus. The available for the system,
directly without involvement system offers two which introduces the transfer
of any breaker or any proper independent main buses in of system load of any feeder
protection in the system. So, the service, which becomes for the case of fault on any
For interlock
2. E/switch (29E)
Line isolator (29L2) 1.Line breaker (52L) Applicable when earth switch is
By pass Isolator (29B) 1.B/C breaker (52B 1. To use only one feeder through
feeder.
feeder.
** Detail logic from the bus system. Because system, the required bus
The Main Bus power flow will occur from isolator remains in closed
Isolator (29M1) & (29M2) either of the bus system condition. The three
for this system become the So, during the power important equipments (line
common path of power flow flow according to the bus breaker 52L, B/C breaker
6
52B and own by-pass isolator the usual circuits has been
29B) play the vital role for explained for the interlock
(a) Path
29B 52B
52B
Note: - N/O Contact of the Equipment
interlock scheme for 29M2 replacing the 29M2 by 29M1 above for 29M1.
7
L1
B1 52B1 B2 52B2
29M
52L
29L
Fig. A Fig. B
29M 29M1
29L
29T 29M2
Fig.C Fig. D
29L1
29B 52L
29A 29TBC-A
52B
29B 29TBC-B
52L
52TBC
29TBC-C
29D 29C
Fig. E
8
For this system an quite advantageous for using through transfer bus system.
additional bus is used, with two different sources Similarly the bus shut down
two main buses. In similar (systems), simultaneously in can also be availed for
manner Bus coupler is also two buses. For the event of emergency requirement.
For interlock
Main Bus Isolator (29A) 52L, 29B, 52B To allow the specific Bus
Main Bus Isolator (29B) 52L, 29A, 52B To allow the specific Bus
Transfer Bus Isolator 29A, 29B, 29C, 29D, 29TBC-A, 1. To use only one feeder
of power flow
Line isolator (29D) 52L, 29E, 29C, 29TBC-A, 29TBC-B, To maintain all possible path
29A- Main Bus Isolator-I, 29TBC-A Transfer B/C Main Transfer Bus Isolator
29C-Transfer Bus Isolator 29TBC-B Transfer B/C Main 52L – Line Breaker
9 2
9 1
2 10
1 10
Interlock for 29C
4 9 2 7 11 8 12
1 6
5 11 9 3
Interlock for 29D
5 9 3
3 8 6
7
Number Notation in the circuit
1. Such schemes involve the 3. The cable connections and 5. The auxiliary contacts do
hardware concepts of the contact multiplication of the not work properly after few
contacts and cables etc. equipments become very days of the operations.
To avoid the above difficulty designed to study the status supervises the system and
Relay (ISR) of considering the status of the signals for correct and
microprocessor based being interlocks and the status logic smooth operation of the
Basic design
of any interlock schemes. contacts of those equipments. are brought to the relay and
The following factors are to 3. Requirement of power simulated for the software
for the condition of power 4. Feasibility of the system. From every involved
of the interlocking scheme, provided for the software about the interlocking
only one pair of N/O Contact design. For any operation of problems in the circuits if
and N/C Contact is brought the equipment, the relay occurs during the operation
for the relay design instead of studies the logic of the of any equipments in the
the multi number of contacts operation circuit and extends system. The interlocking
as described in the above the permissive out put contact problems are displayed in the
schemes. The logic equations for the operation. This design screen of the ISR.
Conclusion: -
Interlock Scheme is adopt this scheme for its operation can be avoided.
considered as a safety tool for system. Because of the Moreover operators become
every power flow system. So, Interlock Scheme the human conscious for doing the
Grid sub-stations are the in the system. For the Some cases like automatic
powers from different regions series to the breaker in the operated/controlled at the
are controlled to maintain system, then this isolator Central Control Stations
Isolator and Switch Gears are circuit breaker is in closed In this article various
the two important equipments condition i.e. the power interlock schemes with
play the important role for should not be done through supervision of the schemes
correct and smooth operation isolator. Because this have been discussed. Study to
avoid improper switching switch, that operated in air arrangements have also been
operations, inter locks are medium. Switching action in dealt with relevant
provided in the system, air medium may result severe advantages and
circuit. consumers.
article has mentioned But focus has been given used for the Common Bus
From
P.K.PATTANAIK Contacts
Asst. Manager (Elect.) Ph. (0663)-2430514,2430512(O)
E&MR Divn. BURLA - 2431232 (R )
GRIDCO, Sambalpur-768017 FAX- (0663)- 2430160 (O )
Email ppk110 @ rediffmail.com
prasanta_ pattanaik@yahoo.com
To,
Sir,
Please find enclosed here with the a article titled “ELECTRICAL INTERLOCK
DESIGNS FOR SUB-STATION OPERATION” for publication of the same in IEEMA
Journal with other relevant documents.
Receipt of the letter with enclosures may kindly be acknowledged on the Fax- (0663)-
2430160 or e-mail to the above address.
Thanking You
Yours faithfully
Enclosures: -
1. 2 (Two) hard copies of the article P. K. Pattanaik
2. A floppy with contents of the article
3. Two copies of the photographs
4. Declaration in respect of the Article.
15
From
P.K.PATTANAIK Contacts
Asst. Manager (Elect.) Ph. (0663)-2430514,2430512(O)
E&MR Divn. BURLA - 2431232 (R )
GRIDCO, Sambalpur-768017 FAX- (0663)- 2430160 (O )
Email ppk110 @ rediffmail.com
prasanta_ pattanaik@yahoo.com
To,
Sir,
1. I confirm that this article is original and has not been earlier published in any
journal/magazine or any other publication in India. The article has also not been
presented in any seminar/ conference held in India.
2. I confirm that this article has not been sent by me to any other
journal/magazine/publication for publishing the same.
3. I am aware, that IEEMA pays honorarium to every published article. On payment of such
honorarium, the copyright of the article rests with IEEMA Journal. Therefore, the same
cannot be published elsewhere without express permission from IEEMA Journal.
4. I confirm that I am responsible for Correctness of data/experimental results presented,
Opinions expressed in the article, and Infringement, if any, of copyrights/ ownership
rights.
5. I am aware, that IEEMA journal publishes articles on “ good faith basis”. Hence I will be
solely responsible for contents, violation of any law in the contents or actions arising
from contents or illustrations.
Thanking You.
Yours faithfully
P. K.PATTANAIK.
16