This document provides a calibration procedure for temperature transmitters on cooling water systems including water tanks at a facility. It lists the necessary safety equipment including PPE for H2S gas protection. References such as P&IDs, manuals and datasheets are required. The procedure involves isolating equipment, inspecting and calibrating temperature transmitters using tools like an HHC communicator, calibrator, multi-meter and wrenches. It requires an instrument technician, senior technician and CCR operator and applies to specific transmitter tags. Steps include inspection, simulation, functionality checks and verification upon completion.
This document provides a calibration procedure for temperature transmitters on cooling water systems including water tanks at a facility. It lists the necessary safety equipment including PPE for H2S gas protection. References such as P&IDs, manuals and datasheets are required. The procedure involves isolating equipment, inspecting and calibrating temperature transmitters using tools like an HHC communicator, calibrator, multi-meter and wrenches. It requires an instrument technician, senior technician and CCR operator and applies to specific transmitter tags. Steps include inspection, simulation, functionality checks and verification upon completion.
This document provides a calibration procedure for temperature transmitters on cooling water systems including water tanks at a facility. It lists the necessary safety equipment including PPE for H2S gas protection. References such as P&IDs, manuals and datasheets are required. The procedure involves isolating equipment, inspecting and calibrating temperature transmitters using tools like an HHC communicator, calibrator, multi-meter and wrenches. It requires an instrument technician, senior technician and CCR operator and applies to specific transmitter tags. Steps include inspection, simulation, functionality checks and verification upon completion.
Job Plan Target Cooling Water System (Trains 1-3) including Water Tank
Purpose Calibration Procedure for Temperature Transmitters (FOUNDATION FieldBus Application)
Safety and Standard PPE is required that includes protection against H2S Gas. Environmental Requirements References ILD, P&ID, Operation/maintenance manual, and instrument datasheet.
Job Prerequisites 1. Obtain work permits and authorizations
2. Ensure that work permit / JSA is read and understood in toolbox talk with all involved personal 3. Ensure all PPE requirements are met as listed in work permit / JSA before conducting the work. 4. Ensure the online equipments/instruments are isolated / removed from the system, as per P&ID given by operations and as per ESD C&E Matrices (if applicable).
Tools and Equipment 1. Handheld Communicator HHC475
2. Temperature Calibrator/Signal Generator (Resistance, mV, direct temperature) 3. Pair of Screw Drivers (+/-) 4. Digital Multi-meter 5. Adjustable Wrench and set of spanners 6. Rags and cleaning agent (if applicable) 7. Teflon tape or liquid sealant 8. 2 2-Way Radios (1 for CCR Operator and 1 for Field Technicians)
Check element condition, installation, connection leads [ ] Check transmitter voltage [ ] Check sensor condition by measuring output mV or Ω [ ] Inspect for any water ingress [ ] Do temperature simulation while instrument in OOS mode [ ] Check indicator functionality [ ] Check inspect instrument cable condition [ ] Check transmitter overall functionality [ ]
Work Completion Task
Ensure all procedures were done and executed as per PM checklist [ ]
Clear and do area housekeeping [ ] Put transmitter online and inspect for any leaks [ ] Verify all mechanical isolations are back to operating condition [ ] Clean the instrument from any dirt and check readability [ ] Close and complete work permit after task completion [ ] Inform all personnel regarding work completion [ ]