Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Preamble: In reference i), Niagara Gas indicates that the proposed new
facilities will fall under land agreement arrangements already in
place and that no new easements will be required. Niagara Gas
goes on to say that temporary work space will be required on
private property on both sides of the crossing. Niagara Gas
states that it “has, or will acquire, all necessary land rights for
construction of the proposed facilities”.
Niagara Gas has not indicated in its application whether its lands
acquisition process for any required lands, including temporary
work space, will comply with the NEB Act.
Request: Please confirm whether the land acquisition process for any
required lands, including temporary workspace, will comply with
sections 86 and 87 of the NEB Act.
RESPONSE
Niagara Gas will comply with section 86 and 87 of the NEB Act with respect to its land
acquisition process for the project.
Filed: 2011-06-09
Niagara Gas Transmission Limited
St. Lawrence River Pipeline Crossing Replacement Project
NEB File No.: OF-Fac-Gas-N213-2011-01 02
Information Request No. 1
Schedule 2
Page 1 of 3
Plus Attachment
Preamble: In reference i), Niagara Gas indicates that no feedback has been
received by the Company in response to published
announcements or information notices mailed to local residents
about the Project, including any potential concerns regarding
noise associated with the proposed horizontal directional drilling
(HDD).
Reference ii) states that within the city of Cornwall “… the nearest
residential area is located … approximately 20 metres from the
temporary work space boundary.” Reference ii) further states
that, on Cornwall Island, “The nearest residences are directly
adjacent to the temporary work space boundary.” Reference iii)
shows buildings in proximity to the HDD site and the temporary
work space.
RESPONSE
b. A copy of the Notice of Public Information Session is attached and can also be found
in the Environmental and Socio-Economic Assessment Report and external website.
Information pertaining to noise can be found on slide 3 of the Public Information
Session panels.
Filed: 2011-06-09
Niagara Gas Transmission Limited
St. Lawrence River Pipeline Crossing Replacement Project
NEB File No.: OF-Fac-Gas-N213-2011-01 02
Information Request No. 1
Schedule 2
Page 3 of 3
Plus Attachment
d. The HDD contractor will be installing a sound panel barrier wall system at both the
Cornwall and Cornwall Island work sites, between the work area and nearby
residents to minimize the propagation of any construction related noise. The sound
panel barrier wall system consists of approximately 25-foot long by 4-foot wide rolls
of 4-inch thick Quilted Fiberglass Absorbers (“QFAs”) affixed from a 3/8” cable line
spanning between support posts either driven into the ground or supported on steel
road plates every 20-feet. The QFAs are manufactured by “Sound Seal” specifically
to absorb noise and are also fire-proof. This system has been successfully used by
the contractor (Michels Directional Crossings / Michels Canada) on many projects in
urban environments. Niagara Gas will also abide by municipal noise bylaws and
conduct work activities only between 7 a.m. and 7 p.m. However, during the critical
pull-back stage of the drilling operation, 24-hour a day work may be required. In
addition, all construction equipment will be properly maintained and equipped with
mufflers.
e. Not applicable.
Niagara Gas Information Request 1.2 - Attachment
FRANZ Environmental Inc. (FRANZ) has been retained to prepare an Environmental Assessment of the proposed
pipeline route. The study area boundary for this project is indicated by the dotted line. At this Public Information
Session, representatives from FRANZ and N G T L will be available to explain the project and answer questions
regarding the route selection process, the alignment, t h e rationale/requirement for the p i p e l i n e c r o s s i n g ,
construction procedures and specific environmental protection and mitigation measures.
Public Information Sessions regarding the proposed project are scheduled at:
Comments and information regarding this project are being collected to assist the project team in meeting the
requirements of the National Energy Board Act. The report will become part of evidence to be filed with the NEB, as part
of the Section 58 application. These comments will be maintained for reference throughout the project and will become
part of the public record. Under the Freedom of Information and Protection of Privacy Act and the Environmental
Assessment Act, unless otherwise stated in the submission, any personal information such as name, address, telephone
number and property location included in a submission will become part of the public record files for this matter and will be
released, if requested, to any person.
1.3 Manuals
Request: Please file 3 hard copies of the latest version of the Emergency
Response Manual with the NEB for review.
RESPONSE
Enbridge Gas Distribution Inc. is in the process of updating the applicable Emergency
Response Manual, and expects to file the updated document with the Board on
June 13, 2011.
Filed: 2011-06-09
Niagara Gas Transmission Limited
St. Lawrence River Pipeline Crossing Replacement Project
NEB File No.: OF-Fac-Gas-N213-2011-01 02
Information Request No. 1
Schedule 4
Page 1 of 2
Plus Attachment
Engineering Matters
Preamble: In reference i), Table 6.3 shows the stress calculations for a
restrained pipe. It includes the stress resulting from the internal
pressure during the operation at the maximum operating pressure
(MOP), longitudinal stress from the thermal expansion and the
combined stress.
RESPONSE
a. Please see the attached stress analysis of the pipe for the HDD installation based on
design and worst case scenarios. The stress analysis was prepared by J.D. Hair &
Associates (“JDH&A”), HDD consulting engineers for the project.
b. Please see the attached letter from JDH&A describing the stress analysis performed
and the suitability of the proposed line pipe for installation by HDD, including steps
established to ensure the HDD contractor does not exceed the specified minimum
yield strength of the pipe.
Niagara Gas Information Request 1.4 - Attachment
June 9, 2011
Mr. Tozer:
In accordance with your request, we have completed an analysis of installation loads associated
with a 12-inch welded steel pipeline segment proposed for installation beneath the St. Lawrence
River by horizontal directional drilling (HDD). The objectives of this analysis were to confirm
the suitability of the proposed line pipe for installation by HDD, to determine an estimated
pulling load and establishing steps to ensure the HDD contractor will not exceed the specified
minimum yield strength. The results of our analysis are presented in this letter. Output pages
from our pulling load calculation routine are enclosed for your review.
Installation loads and stresses were evaluated using a method developed by J. D. Hair &
Associates, Inc. (JDH&A) for the Pipeline Research Committee at the American Gas
Association. A detailed explanation of this method may be found in Section 5 of Installation of
Pipelines by Horizontal Directional Drilling, An Engineering Design Guide1.
The information that was utilized in our analysis was provided by Enbridge/Niagara Gas and
consisted of the proposed line pipe specification, the pipeline’s maximum allowable operating
pressure and temperature. The proposed line pipe for the HDD crossing is 12.75-inch outside
diameter, 0.375-inch wall thickness, API 5L X-52 while the pipeline’s maximum operating
pressure and temperature are 3,515 kPa and 30°C (510 psi and 86 °F), respectively. Based on
this information, we first performed an operating stress analysis to determine the stresses at the
designed radius of 366 meters (1,200 feet) as it is laid out on the Drawing: “St Lawrence R0
(preliminary)” produced by JDH&A. At the design radius, the maximum shear stress is well
within the criteria outlined in ANSI B31.4 as shown in the attached “St. Lawrence River
(Metric)” spreadsheet. Next, we performed an operating stress analysis to determine the
1
Installation of Pipelines by Horizontal Directional Drilling, An Engineering Design Guide, prepared for the
Offshore and Onshore Design Applications Supervisory Committee of the Pipeline Research Committee at the
American Gas Association, J. D. Hair & Associates, Inc., Louis J. Capozzoli & Associates, Inc., and Stress
Engineering Services, Inc., April 15, 1995.
Niagara Gas Information Request 1.4 - Attachment
minimum allowable radius with regard to operation. As indicated on the attached “St. Lawrence
River (Metric - Worst Case)” spreadsheets, we determined that the drilled radius is limited to a
minimum of 138 meters (454 feet) based on the maximum shear stress criteria outlined in ANSI
B31.4. This radius was then rounded up to 152 meters (500 feet) and used in our analysis of
installation stresses on the worst case design discussed below.
Our analysis of the proposed HDD installation was based on two drilled path models. The first
model conforms to the drilled path design presented on the drawing. It has a horizontal length of
769 meters and penetrates to a depth of approximately 26 meters below the entry point using an
entry angle of 12 degrees, an exit angle of 16 degrees and two sag bend curves with radii of 366
meters (1,200 feet). Based on this model, the anticipated installation load is 190 kN (42,698
pounds) and our calculations indicated no violations of applicable stress criteria.
Due to the fact that most HDD installations are drilled to greater depths and tighter radii than
designed, we also evaluated a “worst-case” model in order to verify that common deviations
from the designed profile would not result in unacceptable stress levels. This model has a
horizontal length of 789 meters and penetrates to a depth of 36.5 meters below the entry point
using an entry of 14 degrees, an exit angle of 18 degrees and two sag bend curves with radii of
152.39 meters (500 feet). Based on this worst-case model, the anticipated installation load is 255
kN (57,252 pounds) and our calculations again indicated no violations of applicable stress
criteria.
In reviewing these calculations, it should be noted that the pulling load determined by this
calculation method represents only the tensile load transmitted to the pull section as a result of
conditions in the hole. Loads resulting from the drill string, the reaming assembly that precedes
the pull section, and the above-ground portion of the pull section (typically supported on rollers)
are not included in the calculation. However, considering that the loads resulting from the drill
string and above-ground pipe approach zero as pullback nears completion, the estimated pulling
load presented herein for an installation along the designed profile should provide a reasonable
indication of the rig capacity required to pull the pipe assuming that pullback operations go well.
Based on our experience, a rig capacity of roughly twice this estimated load provides a sufficient
factor of safety in the event that reasonably foreseeable problems should occur.
Based on the calculations, we believe that the proposed line pipe is suitable for installation by
HDD beneath the St. Lawrence River and can be done while ensuring that longitudinal stresses
during the installation will not exceed the SMYS of the pipe. Our opinion is rooted in three
assumptions: 1) that the actual drilled path will not exceed the length or depth of the worst-case
model described in the following paragraphs; 2) that the HDD contractor will not employ any
improper construction procedures; and 3) that problematic subsurface conditions will not be
encountered.
Niagara Gas Information Request 1.4 - Attachment
If you have any questions concerning this analysis, please don't hesitate to contact me.
Sincerely,
Dylan Bruntzel
Project Engineer
Enclosures
Niagara Gas Information Request 1.4 - Attachment
PRCI Method, St. Lawrence River (Metric).xls
J:\Niagara Gas\1109-St. Lawrence River\Working\Stress Analysis\
Comments
Pulling load analysis based on the JDH&A design for the St. Lawrence River.
Station Elevation Angle Radius Length Inclination Assumed Average Total Pull
Submerged Ballasted
(m) (m) (⁰) (m) (m) (⁰) Tension (kN) Tension (kN) (kN)
Entry Point 0.0 54.5 12.0 78.0 190
Entry Tangent 79.4 yes no 1 Not Used
PC 77.7 38.0 78.0 174
Entry Sag
PI 115.3 30.0 12.0 366 76.6 yes no 158 158
Bend
PT 153.7 30.0 90.0 0 142
Bottom Tangent 0.0 427.3 yes no 1 Not Used
PC 581.0 30.0 90.0 35
Exit Sag
PI 632.4 30.0 16.0 366 102.1 yes no 18 18
Bend
PT 681.8 44.2 106.0 0 1
Exit Tangent 90.8 no no 1 Not Used
Exit Point 769.1 69.2 16.0 106.0 Above Ground Load 0
True Length 776.3
Drilling Mud 54.5
Ballast
Niagara Gas Information Request 1.4 - Attachment
Weight &
Weight Bending External Hoop Tensile,
Tensile &
Point Fluidic Drag Friction Friction Total Pull Tensile Stress Bending Stress Stress Bending & Ext.
Bending Stress
Hoop Stress
(kN) (kN) (kN) (kN) (kg/cm 2) (kg/cm 2) (kg/cm 2)
Entry Point 120 35 34 190 206 ok 0 ok 0 ok 0.06 ok 0.00 ok
189 ok 0 ok 34 ok 0.06 ok 0.01 ok
PC 106 34 34 174
189 ok 903 ok 34 ok 0.39 ok 0.14 ok
154 ok 903 ok 50 ok 0.38 ok 0.14 ok
PT 93 36 13 142
154 ok 0 ok 50 ok 0.05 ok 0.01 ok
38 ok 0 ok 50 ok 0.01 ok 0.00 ok
PC 18 4 13 35
38 ok 903 ok 50 ok 0.35 ok 0.11 ok
1 ok 903 ok 21 ok 0.34 ok 0.10 ok
PT 0 1 0 1
1 ok 0 ok 21 ok 0.00 ok 0.00 ok
0 ok 0 ok 0 ok 0.00 ok 0.00 ok
Exit Point 0 0 0 0
Comments
Pulling load analysis based on the JDH&A worst case design for the St. Lawrence River. The design incorporates an entry angle of 14
degrees, an exit angle of 18 degrees, radii of 152.39 meters (500 feet), while being 10 meters deeper and 20 meters longer than original
design.
Station Elevation Angle Radius Length Inclination Assumed Average Total Pull
Submerged Ballasted
(m) (m) (⁰) (m) (m) (⁰) Tension (kN) Tension (kN) (kN)
Entry Point 0.0 54.5 14.0 76.0 255
Entry Tangent 127.5 yes no 1 Not Used
PC 123.7 23.7 76.0 231
Entry Sag
PI 141.9 19.1 14.0 152 37.2 yes no 210 210
Bend
PT 160.6 19.1 90.0 0 189
Bottom Tangent 0.0 449.3 yes no 1 Not Used
PC 609.9 19.1 90.0 77
Exit Sag
PI 634.1 19.1 18.0 152 47.9 yes no 61 61
Bend
PT 657.0 26.6 108.0 0 45
Exit Tangent 138.9 yes no 1 Not Used
Exit Point 789.1 69.5 18.0 108.0 Above Ground Load 0
True Length 800.8
Drilling Mud 54.5
Ballast
Niagara Gas Information Request 1.4 - Attachment
Weight &
Weight Bending External Hoop Tensile,
Tensile &
Point Fluidic Drag Friction Friction Total Pull Tensile Stress Bending Stress Stress Bending & Ext.
Bending Stress
Hoop Stress
(kN) (kN) (kN) (kN) (kg/cm 2) (kg/cm 2) (kg/cm 2)
Entry Point 140 55 59 255 276 ok 0 ok 0 ok 0.08 ok 0.01 ok
250 ok 0 ok 63 ok 0.08 ok 0.01 ok
PC 118 54 59 231
250 ok 2,166 ok 63 ok 0.88 ok 0.70 ok
205 ok 2,166 ok 72 ok 0.87 ok 0.68 ok
PT 112 55 23 189
205 ok 0 ok 72 ok 0.06 ok 0.01 ok
84 ok 0 ok 72 ok 0.03 ok 0.01 ok
PC 33 22 23 77
84 ok 2,166 ok 72 ok 0.83 ok 0.61 ok
48 ok 2,166 ok 57 ok 0.82 ok 0.59 ok
PT 24 20 0 45
48 ok 0 ok 57 ok 0.01 ok 0.00 ok
0 ok 0 ok -31 ok 0.00 ok 0.00 ok
Exit Point 0 0 0 0
Security Matters
1.5 Manuals
Preamble: PRC 2010-01 sets out the NEB’s requirement for a company to
have a security program that is in accordance with
CSA Z246.1-09. Specifically PRC 2010-01 states:
RESPONSE
a. Niagara Gas is aware of the proposed regulatory change (PRC 2010-01) and will
follow the provisions of Section 9.2 Facility Design and Construction as per CSA
Z246.1-09 Security Management for the Petroleum and Natural Gas Industry
Systems.
b. An on-site security assessment will be conducted no later than June 30, 2011.
Filed: 2011-06-09
Niagara Gas Transmission Limited
St. Lawrence River Pipeline Crossing Replacement Project
NEB File No.: OF-Fac-Gas-N213-2011-01 02
Information Request No. 1
Schedule 5
Page 2 of 2
Plus Attachment
c. A security management plan framework for the project has been developed and is
attached. The framework identifies the elements of the security management plan to
be developed for the project after the security assessment is conducted.
Niagara Gas Information Request 1.5 - Attachment
Cornwall Bridge Relocation Project Security Management Plan Framework
SECURITY
MANAGEMENT PLAN
FRAMEWORK
2011 Cornwall Bridge Relocation Project
1
Niagara Gas Information Request 1.5 - Attachment
Cornwall Bridge Relocation Project Security Management Plan Framework
1.0 PURPOSE
Security Governance
2.0 SCOPE
3.0 RESPONSIBILITIES
2
Niagara Gas Information Request 1.5 - Attachment
Cornwall Bridge Relocation Project Security Management Plan Framework
5.1 General
The security risk management process provides the flexibility needed for
proactive decision making to address the security risks to the project. The
Prime Contractor identifies and classifies security risks in order to develop
3
Niagara Gas Information Request 1.5 - Attachment
Cornwall Bridge Relocation Project Security Management Plan Framework
6.1 General
6.2 Process
6.2 Planning
4
Niagara Gas Information Request 1.5 - Attachment
Cornwall Bridge Relocation Project Security Management Plan Framework
The Prime Contractor shall include procedures to direct people away from
the construction site, including provisions to account for people that have
been evacuated from the construction site.
6.9 Investigations
The Prime Contractor with support from the EGD Corporate Security
department shall develop and implement a process to conduct security-
related investigations.
5
Niagara Gas Information Request 1.5 - Attachment
Cornwall Bridge Relocation Project Security Management Plan Framework
On-site security measures must reflect the size, location, risk, and
criticality of the assets that require protection. Security risks to people, the
environment, assets, or economic stability to the project shall be taken into
account when determining the degree of physical security that is required.
Physical security measures shall consider:
The Prime Contractor shall conduct project specific security training and
awareness sessions to all on-site personnel which outlines the provisions
of the Security Management Plan.
6
Niagara Gas Information Request 1.5 - Attachment
Cornwall Bridge Relocation Project Security Management Plan Framework
11 REFERENCES
The Prime Contractor shall consider the elements contained within the
Canadian Standards Association Z246.1, Security management for
petroleum and natural gas industry systems when developing and
implementing the Security Management Plan.