Sei sulla pagina 1di 10

MEASUREMENTS FOR STP TANK

SUMMARY SHEET

TANK SIZE = 15.68 X 4.93 X

S.No. PARTICULARS Nos. L B H/D QTY.


1 EXCAVATION 1 X 18.88 X 5.5 X 4.5 467.28

2 PCC
RAFT Bottom 1 X 16.68 X 5.43 X 0.1 9.057
-1 X 1.1 X 0.9 X 0.1 -0.099
SUMP Bottom 1 X 1.97 X 1.93 X 0.1 0.380
TOTAL (Cum) 9.338
KOTA STONE
3 WATERPROOFING
BELOW RAFT 1 X 16.62 X 5.4 X - 89.748
SIDE OF RAFT 1 X 16.62 X - X 0.4 6.648
2 X 5.07 X - X 0.4 4.056
EXTERIOR WALLS 2 X 4.93 X - X 4.1 40.426
SUMP Bottom 1 X 1.845 X 1.47 X - 2.712
SUMP Walls 2 X 1.56 X - X 0.83 2.590
1 X 1.36 X - X 0.83 1.129
TOTAL (Sqm) 147.309

4 BRICK WORK

SUMP WALL 2 X 1.815 X - X 0.83 3.013


2 X 0.9 X - X 0.83 1.494
STAIRS 1 X 1.5 X 0.3 X 0.15 0.068
1 X 1.5 X 0.6 X 0.15 0.135
1 X 1.5 X 0.9 X 0.15 0.203
1 X 1.5 X 1.2 X 0.15 0.270

TOTAL (Cum) 5.182


5 RCC WORK

RAFT 1 X 16.48 X 5.33 X 0.4 35.135


OUTER WALL 2 X 15.68 X 0.33 X 4.1 42.430
2 X 4.27 X 0.33 X 4.1 11.555
TWT TANK WALL 1 X 4.27 X 3.65 X 0.23 3.585
SUMP WALL 2 X 1.56 X 0.23 X 0.83 0.596
1 X 0.9 X 0.23 X 0.83 0.172
SUMP BASE 1 X 1.11 X 0.9 X 0.23 0.230

INNER PARTITION WALL 4 X 1.8 X 0.23 X 2.5 4.140

OUTER PARTITION 1 X 13.87 X 0.23 X 2.5 7.975


WALL

OVER FLOW LAUNDER 1 X 1.8 X 0.4 X 0.1 0.072

OVER FLOW LAUNDER 1 X 1.8 X 0.3 X 0.1 0.054


TOW WALL

BAFFLE WALL 1 X 1.8 X 0.1 X 1.65 0.297

BSC CHAMBER WALL 1 X 1 X 0.23 X 2.5 0.575

1 X 0.6 X 0.23 X 1.9 0.2622

OGT TANK WALL 1 X 2.9 X 0.23 X 2.5 1.668

OGT TANK BAFFLE WALL 1 X 1.2 X 0.1 X 0.8 0.096

OPERATING PLATFORM 1 X 14.46 X 0.8 X 0.15 1.735

ROOF SLAB 1 X 15.68 X 4.93 X 0.2 15.460

PLATFORM OVER SUMP 1 X 1.5 X 1.5 X 0.15 0.3375

X X TOTAL (Cum) 126.374


6 SHUTTERING WORK

RAFT 1 X 16.48 X - X 0.4 6.592


OUTER WALL 1 X 15.68 X - X 4.1 64.288

1 X 15.02 X - X 4.1 61.582

-1 X 1.2 X - X 2.1 -2.52


2 X 4.93 X - X 4.1 40.426
2 X 4.27 X - X 4.1 35.014
TWT TANK WALL 2 X 4.27 X - X 3.6 30.744
SUMP WALL 2 X 1.1 X - X 0.6 1.32
2 X 0.9 X - X 0.6 1.08

INNER PARTITION WALL 8 X 1.8 X - X 2.5 36.00

OUTER PARTITION 1 X 27.31 X - X 2.5 68.275


WALL

OVER FLOW LAUNDER 1 X 1.8 X 0.4 X - 0.72

OVER FLOW LAUNDER 1 X 1.8 X - X 0.4 0.72


TOW WALL

1 1.8 - 0.3 0.54

BAFFLE WALL 2 X 1.8 X - X 1.6 5.76


1 X 1.8 X 0.1 X - 0.18
BSC CHAMBER WALL 2 X 1 X - X 2.5 5
2 X 0.3 X - X 1.9 1.14
OGT TANK WALL 2 X 2.9 X - X 2.5 14.50
OGT TANK BAFFLE WALL 2 X 1.2 X - X 0.8 1.92
1 X 1.2 X 0.1 X - 0.12

OPERATING PLATFORM 1 X 14.46 X 0.8 X - 11.568

1 X 14.46 X - X 0.1 1.446

ROOF SLAB 1 X 15.02 X 4.27 X - 64.1354

1 X 25.54 X - X 0.2 5.108

PLATFORM OVER SUMP 1 X 1.5 X 1.5 X - 2.25

1 X 6 X - X 0.15 0.9

TOTAL (Sqm) 458.808


INTERNAL WALL
PLASTER
Except TWT & Pump 1 X 31.31 X - X 2.5 78.275
Room
1 X 15.21 X - X 4.1 62.361

TOTAL (Sqm) 140.636

TILE WORK IN TWT


TANK AND PUMP
ROOM

1 X 4.27 X - X 3.6 15.372


1 X 8.67 X - X 4.1 35.547
1 X 2.24 X - X 2.5 5.600
1 X 2.24 X - X 3.5 7.840
1 X 9.96 X - X 2.5 24.900
1 X 9.6 X - X 2.5 24.00
1 X 11.26 X 1 X - 11.26
1 X 9.1 X 1.65 X - 15.015
1 X 0.3 X 1.14 X - 0.342
TOTAL (Sqm) 139.876

LEAN CONCRETE IN
PUMP ROOM

1 X 9.96 X 2.24 X 0.2 4.462


-1 X 1.1 X 0.9 X 0.2 -0.198
TOTAL (Sqm) 4.264

6 PUDDLE FLANGES

Dia 80 mm 5 X - X - X -
Dia 100 mm 5 X - X - X -
Dia 50 mm 5 X - X - X -
Dia 150 mm 1 X - X - X -

TOTAL (Nos.) 16

6 MAN HOLE COVERS

Dia 560 mm 2 X - X - X -

TOTAL (Nos.) 2
6 INJECTION GROUTING
Outer Walls 1 X 38.58 X - X 4.1 158.178
TWT Tank Wall 1 X 4.27 X - X 2.6 11.102
INNER PARTITION WALL 8 X 1.8 X - X 2.5 36.00

OUTER PARTITION 1 X 27.31 X - X 2.5 68.275


WALL
BAFFLE WALL 2 X 1.8 X - X 1.6 5.76
BSC CHAMBER WALL 2 X 1 X - X 2.5 5
2 X 0.3 X - X 1.9 1.14
OGT TANK WALL 2 X 2.9 X - X 2.5 14.50
OGT TANK BAFFLE WALL 2 X 1.2 X - X 0.8 1.92
TOTAL (Sqm.) 301.88
6 RCC Cutting
1 X 1.2 X - X 2.1 2.52
TOTAL (Sqm.) 2.52
MEASUREMENTS FOR STP TANK

TANK SIZE = 15.68 X 4.93 X 4.1

REMARKS

SUMP