This report is used to find out whether a component exists in the BOM's. With this
report, you can find out the parent material in which a component is used as BOM
item.
It is basically reverse BOM explosion which means through component child code,
you can find out the parent material code. For example Component like Tread is
used as an item in BOM of Tyres.
1. Input single material code for which you want to see the parent material.
3. Flag "Material BOM" as you are looking the component up in material BOM.
3. Flag "Multi-level" which means you want to see all upper BOM levels for the
component.
Press execute button on top or press F8 from the keyboard to move to next screen.
Step 3)In this screen,
1. You can see the different levels of BOM in which this component exists
2. You can see the parent material in which the component exists.
Basic scheduling :
1.Exact to second
2.ie production start date /time and finish date and time
are calculated.
3. cap reqmts are generated.
4. uses times from routing.
5. carried out only if the scheduling mode in MD02 screen
is kept with indicator 2.
From the order finish date the system subtracts the float
after production to calculate the production finish date.
From the production finish date the individual operations in
the routing are scheduled backwards to calculate
production start date.
From the production start date the system subtracts the
float before production to calculate order start date.
In house production time in MRP2 view, specifies the time
in workdays needed to produce the material in-house. In-
house production time is independent of the order
quantity.
So when you do the basic scheduling system take the
timing from the material master to calculate the scheduling
date.While "Basic Scheduling" in MRP... Scheduling
margin key is not considered. It takes the "In house
production" days for fixing up the start date. This is only
exact to "days".
Lead Time scheduling is carried out on request from the
scope of MRP. Target dates are calculated from routing
and Capacity requirement calculations are also done. The
calculations are exact to the seconds (time).
In routing you enter the setup, teardown, processing, and
interoperation times it is utilize to calculate scheduling
date.
you have to mention on md02 screen that you want lead-
time scheduling.
1. Basic dates scheduling. Basic dates scheduling is
calculated by considering the values like goods receipt
(GR) processing time, in-house production time and
planned delivery time from material master (MRP 2
view). It calculates basic start date and basic finish date
for an order.
..
What are the difference between basic scheduling and lead time scheduling?
Basic Scheduling
When do planning in MRP with single–item, multi-level planning in the initial screen
and in that if you go to MRP Control Parameters and then to scheduling if you
Select = 1 (basic dates will be determined for Planned Orders)
Select = 2 (lead time scheduling and Capacity Planning)
Please note when you do lead time scheduling you need to maintain:
1. Queue time
2. Wait time
3. Setup time
4. Operation time
5. Teardown time
and also you need to maintain in-house production time in material master.