PRELIMINARY BUILDING COST ESTIMATE : HOSTEL BUILDING (INCLUDING COMMUNITY FACILITY)

Total Area 17985
No. Of Storey G+4 and G+5
Plinth Area on Grd Floor 3297

Plinth  area  rate as on 01‐10‐
Plinth Area Rate for 2010
S. No. Description 2007   Units Quantity Total Cost
(Rates in Rs. / Sq. M) (After 126% Increment)
126
A.1 R.C.C. Framed Structure 1.1 R.C.C. frames structure upto six storey Floor height 3.35 mt. 0 0 Sq. M 0 0
1.20 R.C.C. frames structure upto six storey Floor height 2.95 mt. 9,100 11,466 Sq. M 17,985 20,62,12,708
1.3 Extras for every additional storey over six storeys upto nine storey 310 391 Sq. M 0 0
1.4 Extras for every 0.3 mt. additional height of floor above normal floor height of 3.35 mt./ 2.90 mts.* 150 189 Sq. M 17,985 33,99,111
1.5 Extra for Termite proof treatment (on G.F. area only) 150 189 Sq. M 3,297 6,23,133
1.6 Extras for resisting earthquake forces 630 794 Sq. M 17,985 1,42,76,264
1.7 Extras for Larger modules over 35 sq. m.  990 1,247 Sq. M 0 0
1.8 Basement Floor height 3.35 mt. with normal water proofing treatment with bitumen felt 18,035 22,724 Sq. M 0 0
Sub Total 22,45,11,216

A..2 Fire Fighting 2.1 Fire fighting with wet riser system 300 378 Sq. M 17,985 67,98,221


2.2 Fire Fighting with sprinkler system 450 567 Sq. M 0 0
Sub Total 67,98,221
A.3 Fire Alarm System 3.1 Automatic Fire Alarm System 300 378 Sq. M 17,985 67,98,221
A.4 Mechanical Ventilation 4.1 Pressurized mechanical ventilation system in the basements (with supply of Exhaust blowers) 50 63 Sq. M 0 0

TOTAL 23,81,07,658

B.1 Services 1.1 Internal water supply & sanitary installations 4.0 95,24,306


1.2 External service connections 5.0 1,19,05,383
1.3 Internal electric connections 12.5 2,97,63,457
1.4 Extra for power wiring and plug 4.0 95,24,306
1.5 Extras for lightening conductors upto 4 storey building 0.5 11,90,538
1.5 Extras for telephone conduits 0.5 0 0
1.6 Extras for computer conducting 0.5 0 0
1.7 Extras for quality assurance 1.0 23,81,077

 TOTAL 6,42,89,068

C.1 Lifts 1.1 Phase 1: UG (B)‐ Passenger lift (8 passenger ,1.0m/s, G+4) 13,50,000 17,01,000 nos. 2 34,02,000


1.2 Phase 1: UG (G)‐ Passenger lift (8 passenger ,1.0m/s, G+4) 13,50,000 17,01,000 nos. 2 34,02,000
1.3 Phase 1: PG (B)‐ Passenger lift (8 passenger ,1.0m/s, G+4) 13,50,000 17,01,000 nos. 2 34,02,000
1.4 Phase 1: PG (G)‐ Passenger lift (8 passenger ,1.0m/s, G+4) 13,50,000 17,01,000 nos. 2 34,02,000
1.5 Phase 1: Senior Hostel ‐ Passenger lift (8 passenger ,1.0m/s, G+4) 13,50,000 17,01,000 nos. 1 17,01,000
1.6 Phase 1: Guest Houses ‐ Passenger lift (8 passenger ,1.0m/s, G+4) 13,50,000 17,01,000 nos. 0 0

TOTAL 1,53,09,000

GRAND TOTAL  (A+B+C) 31,77,05,726

NOTES:
*Ground Floor Height is assumed at 3.3 mt.