Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Afstudeerrapport aan de
Technische Universiteit Delft
Faculteit der Civiele Techniek
Vakgroep: Waterbouwkunde
student: S.Mann
student number: 542709
date: March 1999
Supervisors TU Delft:
prof. drs. ir. J.K. Vrijling
ir. W.H. Tutuarima
ir. T.H.W. Horstmeier Delft
Technische Universiteit Delft
S.Mann
Preface
Preface
This report has been prepared for the department of Civil Engineering of the Technical University of
Delft and contains the thesis: 'A floating factory for the Maasvlakte 2 caisson breakwater, 'The design
and construction method of reusable caissons for the Maasvlakte 2 breakwater', which analyses the
feasibility to construct the Maasvlakte 2 breakwater by means of reusable caissons. A floating
construction method for these caissons has been analysed as well.
The thesis has been written under the supervision of prof. drs. ir. J.K. Vrijling, ir. W.H. Tutuarima and
ir. T.H. Horstmeier from the Technical University of Delft, and from the Ministry of Transport, Public
Works and Watermanagement under the supervision ofir. H.A. Lavooij head of the Department of
Hydraulic Engineering and ing. R. Camerik of the Dry Infrastructure department.
I would like to express my gratitude to all these people for their time and assistance in the preparation
of this thesis. Also I would like to thank the Ministry of Transport, Public Works and
Watermanagement for their facilities which were made available to me.
S.Mann
Abstract
Abstract
Due to its excellent geographical location and its modem facilities, the Port of Rotterdam has a leading
position in the world trade. In order to maintain this position, the port must compete with the rapid
development of other European ports, and investments on the harbour facilities must constantly be
made. A problem the harbour will face during the next decades, will be the lack of area to expand.
A typical Dutch solution to create the necessary area for harbour and industrial terrain, is reclamation of
land from the sea. This can be achieved by expanding Maasvlakte 1 with Maasvlakte 2. The exact
amount of required terrain is subject to many elements which are continuously changing such as
political, economical, environmental and social views, and therefore is very difficult to predict
accurately. A solution to meet this uncertainty, is to create the Maasvlakte 2 in several phases. By
maintaining a flexible planning of the reclamation, the expansion works can be adapted to changed
views ifnecessary.
The construction works ofthe Maasvlakte 2 are very extensive, and consist of3 main elements, the
terrain itself which is to be created, sea-defence works which must protect the terrain against inundation
and erosion, and a breakwater, which must reduce the height of the incoming waves from the North sea
to an acceptable level in order to give access for shipping to the harbour under storm conditions and
limit downtime of the harbour activities.
For the phased execution ofMaasvlakte 2, sections of the newly gained terrain must be protected
against the sea by a breakwater during each phase. As breakwaters are very expensive structures, a
flexible breakwater, a breakwater which can be reused several times, might be economical. Caissons are
an ideal alternative for such a breakwater as these can be brought afloat again and repositioned at a new
location.
The caisson dimensions have been determined using the Goda design formulas to calculate the wave
forces on vertical walls and the wave transmission over the caisson, and the formulas of Brinch-
Hanssen to calculate the bearing capacity of the soil layers. These formulas have been implemented in
the computer program 'Outer Caisson Dimensions', (O.C.D.) written in this study. This program
indicates that for the conditions of the future Maasvlakte 2 breakwater site, slip of the subsoil is the
decisive failure mode. In order to prevent the occurrence of this failure mode, the caisson must have a
width of at least 21.1 m. In order to sufficiently reduce the wave transmission of the crest the
construction height of the caisson must be 23,5 m.
The outer walls have a construction thickness of0.70 m and are prestressed to absorb the outward
ground pressure on the shaft. The inner walls have a construction thickness of0.50 m, and are not
prestressed. The caisson consists of 4 cells in width direction and 15 cells in length direction. These
cells will have an internal length and width of 4.55 m.
Construction of the caissons will be on a floating construction yard moored in the Europe Harbour of
the Maasvlakte 1 equipped with slip formwork. The main advantage of the floating caisson construction
method is that there is no need of an expensive construction dock or specialised lifting equipment.
When the caisson is completed, it is moored at a temporary location where it is trimmed for stability
and prepared for transport to the breakwater site. The caissons are towed to the breakwater construction
site by tugs, and are lowered onto the foundation by flooding the cells.
Finally the cells are filled with sand, concrete capping plates are placed, and the rocks of the rubble
mound bottom protection are placed. The caissons can be considered as building blocks, easily reusable
components of the Maasvlakte 2 breakwater.
For caisson reuse, the capping plates must be removed and the sand content of the cells replaced with
ballast water. When the caisson is ready to be transported, the water is pumped from the cells and the
caissons become buoyant. They can now be transported to their new destination. The costs to reuse the
S.Mann ii
Abstract
caisson are relatively low, and therefore the costs of the breakwater for construction phase 2 of
Maasvlakte 2 are also relatively low.
Total costs/m 1 of this reusable caisson breakwater are (based on a 4.0 km long section):
By construction of only a section of the Maasvlakte 2 terrain (approximately 50%) the investment in the
year 20 I 0 would be 3023 million, approximately Nlg. 1200 million less than required for the
construction of the complete MV2. This money can be spent on other (money generating) projects and
may lead to a lower threshold for the decision makers of the MV2 to invest on this project.
The investment which can be saved by a breakwater construction of reusable caissons opposed to
construction of a new breakwater is Nlg. 160 million (based on the reuse of a 4 km breakwater section).
Another important advantage of a phased execution concerns the flexibility. If there is no need for
enlargement of MV2 in 2030, this will not be done. If a terrain which is twice as large as predicted is
required, this is also possible. In this manner the chance that money will be invested in a wrong project
is limited.
1
It must be noted that the accuracy of the values in this table serves to find back the essence of the value in the
rest of the text. The costs are not as accurate as might be suggested by the values presented in this table.
S.Mann iii
Table ofcontents
Preface
Abstract ii
Table of contents
2. Introduction 2.1
2.I General 2.I
2.2 Problem definition: 2.2
2.3 Aim ofthesis: 2.3
S.Mann
Table ofcontents
7.3.1 Schematised design forces on the caisson during construction phase 7.3
7.3.2 Schematised design forces on the caisson during transport phase 7.4
7.3.3 Schematised design forces on the caisson during placement phase 7.4
7.3.4 Schematised design forces on the caisson during operational phase 7.5
7.3.5 Schematised design forces on the caisson during reuse phase 7.8
7.3.6 Conclusion design forces 7.8
7.4 Calculation of the bending moments in the plates 7.8
7.5 Calculation of the concrete and steel dimensions 7.9
7.5.1 Computer program RCA 7.9
7.6 Technical drawings 7. IO
7.6.1 Outer wall 7.IO
7 .6.2 Inner wall and base slab 7. II
7.7 Conclusions 7.13
S.Mann 2