BACK SUPPORT ASSEMBLING AND LIFTING PLAN

3nos of 10T lifting


2nos of 10T lifting
belts + 3 nos of 35T 2nos of 10T lifting belts + 2 nos of 35T
Shackles belts + 2 nos of 35T Shackles
Shackles

1T
22T
3T

1. Unload left and right part of back 2. Unload Middle Support by using 65T 3. Unload bottom Support by using 65T
support by using 65T gantry crane and gantry crane and place on surface for gantry crane and place on surface for
place on surface for assembling work assembling work assembling work

2nos of 35T Wire


Slings + 2 nos of
35T Shackles
2nos of 35T Wire 2nos of 35T Wire
Slings + 2 nos of Slings + 2 nos of
35T Shackles 35T Shackles

48T
48T

48T

4. Assemble all parts together and lift up 5. Lift up back support until it reaches 6. Once reaches vertical position, lower
using 2nos of 35T wire sling and 2nos of vertical position down back support into launching shaft
35T shackles