Format for submission of details of reconciliation of length of NHs / DPR packages

Name of project: Kolhapur – Gaganbawda – Talere

Name of DPR Consultant: Aicons Engineering (P) Ltd. Bhopal

A. The length of the above project for DPR preparation as per LOA is 99.00 Km. The length of
the existing alignment connecting NH-66 (at Talere Junction) to NH-166 (at Kolhapur, near CPR
hospital) based on topographic survey is 88.30 Km. But it is decided to end the project section at
the start of the Kolhapur Municipal Corporation limit since the section within the Municipal area
is already 4-lane. Thus the existing length of the project section under scope is 83.950 Km whereas
the design length is 82.440. The Contract price of the DPR package is Rs. 2,28,27,500.

1. The route of the DPR package as per LOA is “Kolhapur – Gaganbawda – Talere” and
which is the final project route.

2. The start and end points of the project along with landmark details of those locations are as
below:
Sl. No. Reference Chainage & name of place Land mark
1. Start point At existing Ch. 53.600 (Design Talere village, Km 287.200 of NH-66
Km 0.000), Talere junction (Mumbai-Goa highway)
2. End point At existing Ch. 138.360 (Design At the start of Kolhapur Municipal
Km 82.440) near Phulewadi Corporation limit (near start of
Kolhapur Ring Road)

B. The particulars of the project stretch as per survey and design along approved alignment
are as follows:
1. The location of major towns / cities/ tourist centres on the project stretch are as follows:
Sl. Name of town / city / tourist centres Existing Ch. (Km)
No.
1 Talere 53.600
2 Vaibhavwadi 67.000
3 Gaganbawda 86.000
4 Salwan 111.300
5 Kale 121.500
6 Balinge 135.100

2. The location of existing major bridges on the project stretch are as follows:
Sl. Existing Ch. (Km) Name of Length of Span Year of
No. location / river bridge (m) arrangement construction
1 134.650 Bhogawati River 120.0 5 x 20.50 -

3. The location of major junctions (With NH / SH) on the project stretch are as follows:
Sl. Details of junction (with NH Type of intersection Existing Ch. (Km)
No. no…/ SH No….)
1 NH-66 (LHS-Mumbai, RHS-Goa) T-Junction 53.600
2 SH (RHS-Phonda) Y - Junction 67.585
Sl. Details of junction (with NH Type of intersection Existing Ch. (Km)
No. no…/ SH No….)
3 SH (LHS-Umbarde) Y - Junction 68.390
4 SH (LHS-Bhui Bawda) T - Junction 86.300
5 MDR (LHS-Kumbharwadi) T - Junction 122.250
6 Kolhapur Ring Road T - Junction 137.500

4. The existing lane widths of the project stretch are as follows:


Existing Ch. (Km) Length C/W Width
Type of Pavement
From To (Km) (m)
53.600 60.200 6.600 7.00 Flexible
60.200 84.750 24.550 5.50 Flexible
84.750 95.900 11.150 5.50 Flexible
95.900 97.900 2.000 7.00 Flexible
97.900 101.600 3.700 5.50 Flexible
101.600 102.000 0.400 7.00 Flexible
102.000 109.300 7.300 5.50 Flexible
109.300 111.300 2.000 7.00 Flexible
111.300 118.380 7.080 7.00 Flexible
118.380 118.640 0.260 7.00 CC
118.640 119.040 0.400 7.00 Flexible
119.040 119.300 0.260 7.00 CC
119.300 137.550 3.400 7.00 Flexible
Total Length 83.950

5. The location of ROBs / RUBs / flyovers and level crossings on the project stretch are as
follows:
Sl. Description (ROB/RUB/Flyover / level Existing Chainage of the ROB/RUB/flyover
No. crossing) & name of place, if any / level crossing
1 LC-21, TVU-186283, DoS: 18.01.16 to 66.320 (Near Kokisare)
24.01.16, Rly Km 287/9

6. The terrain of the project stretch are as follows:


Sl. Nature of terrain based on cross-slope Existing Ch. (km)
No. (Plain / rolling, hilly or mountainous)
1 Plain and Rolling 53.600 to 75.600
2 Steep 75.600 to 86.000
3 Plain and Rolling 86.000 to 138.360

7. The traffic (PCU/day) on the project stretch are as follows:


Sl. Count Location Project section (Name of place Length Traffic in PCU / day
No. (Existing Km) from…..to…..) & Chainage (Km)
from km….to km…..
1 At Km 68 Km 53.600 to Km 86 32.40 AADT (PCU) 3028,
CVPD: 607
2 At Km 112 At Km 86 to Km 122 36.00 AADT (PCU) 4642,
CVPD: 740
3 At Km 125 Km 122 to Km 138.360 16.36 AADT (PCU) 5883,
CVPD: 963
8. The sections that have an overlap with other NHs / In-principle NHs:
Sl. Project section (Name of Overlap with (Reference of Length of overlap (km)
No. place from…..to…..) & NH with chainage / In-
Chainage from km….to principle NHs)
km…..
Nil

9. The existing BOT projects in the project stretch:


Sl. Details of BOT project - Length of project (Km) Name of Concessionaire &
No. Project section (Name of Concession Period (last date
place from…..to…..) & of toll)
Chainage from km….to
km…..
Nil

10. The details of declared length of NH/ yet to be declared length are as follows-

Sl. Description As per Design Total Design NH Design Total NH


No Chainage Length (Km) Chainage Length (Km)
1 DPR length - - - -
Declared as NH
2 DPR length not yet Km 0.000 to Km 82.440 Km - -
declared as NH 82.440

11. The project has these specific features that need special mention……..

*Please furnish above details in respect of entire DPR length assigned.


**Please insert additional rows if required.
***Please mention NA if any of the above tables are not relevant to your project.
**** Please feel free to insert / add any other details that may be important in assigning
chainages & inventorisation, and reconciliation of length of NH / In-principle NHs.