Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
PROJECT
(Electromechanical)
AMENDMENTS
PROJECT
CONTENTS
1. Activity
2. Introduction
3. Terminology
6. Sequence of Activities
7. Requirements
7.2. Trainings
8. Emergency Procedures
9. References
10. Attachments
Effective Date : Jan-2013
Document No : Mech – MS003
METHOD STATEMENT FOR
Revision No : 0
HVAC SYSTEM SERVICE
AND MAINTENANCE WORKS Page No : Page 3 of 9
Approved By :
PROJECT
1. Activity
This Method statement illustrates all necessary procedure to be adopted during Service and Maintenance works on
HVAC system,
2. Introduction
HVAC System Service and Maintenance works shall be carried out as per below procedure.
3. Terminology
4.1. Hazards
Fall of Materials.
Slip / Trip / Fall – Same level.
Fall of Person from Height.
Tools.
Manual Handling.
High Pressure.
Flying Particles.
Pinch Points.
Electrical Hazard.
Fire Hazard.
Effective Date : Jan-2013
Document No : Mech – MS003
METHOD STATEMENT FOR
Revision No : 0
HVAC SYSTEM SERVICE
AND MAINTENANCE WORKS Page No : Page 4 of 9
Approved By :
PROJECT
4.2. Control Measures
Fall of Materials:-
o Unwanted Materials shall be cleared from roof Area.
o Proper storage of Materials and tools shall be carried out.
Tools:-
o Hand / Portable tools shall be inspected prior to work starts.
o Skilled personnel shall be deployed.
o Correct tools for the job shall be ensured.
o Helmet, Safety Shoes, Hand gloves shall be worn.
PROJECT
o Prior inspection by competent person shall be done.
Pinch Points:-
o Utmost care shall be taken while shifting equipments.
o Hand gloves shall be worn.
o Communication from one person to lead the team.
o Wooden strip shall be provided below the compressor as and when required to avoid pinch point hazard.
Electricity Hazard:-
o Power Supply to be isolated by Competent person
o TBT shall be conducted for all employees involved in the activity.
o All power supply shall be routed through appropriate circuit breakers which shall be ensured
by competent person (LOTO system shall be followed).
o Helmet, hand gloves, safety shoes, coverall and jacket shall be worn
Fire Hazard:-
o Waste that have generated shall be discarded through approved agency.
o Portable Fire Extinguisher to be made available near work spot.
o Slip resistant safety shoes, helmet, jacket, coverall and Hand gloves shall be worn.
Competent Person
o Ensuring the safe work environment to employees.
o Plan the required resources such as Manpower, Material, and Machineries... well in advance
and ensure the same prior to the commencement.
o Ensuring necessary approved documents at site.
o Ensuring by physical verification about the controls at work spots are in place.
o Verifying the percentage compliance as per risk assessment.
o Ensuring the emergency preparedness.
o Ensures availability of the necessary resources
o Internal checks about the acceptable criteria upon completion.
o Getting O/E Witness Inspection Clearance.
Effective Date : Jan-2013
Document No : Mech – MS003
METHOD STATEMENT FOR
Revision No : 0
HVAC SYSTEM SERVICE
AND MAINTENANCE WORKS Page No : Page 6 of 9
Approved By :
PROJECT
o Conducting TBT based on risk assessment.
o Ensuring the proper usage of recourses by direct supervision
o Implementing the control measures as per risk assessment and also as mentioned in the
permit.
o Close monitoring till completion of work.
o Ensuring the acceptable criteria up on completion of each task.
o Closing the work permit after restoration of work spot.
o Ensuring Proper housekeeping
Workmen
o Wearing appropriate PPEs.
o Understanding and following the instructions given by line staff.
o No horseplay and shortcuts.
o Follow safety instruction as stated in the LAP / PTW system.
6. Sequence of activities
PROJECT
o After completion of work area will be cleaned and unwanted materials will be removed from
work side.
Compressor servicing and Reinstallation
o Electrical works related with HVAC System will be carried out by relevant Electrical Engineer /
Supervisor of HVAC Subcontractor.
o Main Power Supply of AHU & Condensing Unit to be Isolated from HVAC Control Panel & CU
Isolator which is Faulty
o LOTO system to be followed and communicated to all parties.
o Disconnect the Suction and Discharge Refrigerant lines from the particular Compressor which
is faulty.
o Existing Faulty Compressor to be disconnected and returned to unit manufacturer for
overhauling.
o New Compressor or overhauled compressor to be installed.
o The refrigerant lines to be flushed with Nitrogen Gas.
o Connect the Suction and Discharge Refrigerant lines to new compressor
o Leak test to be conducted after connecting of New Compressor and Refrigerating pipes.
o New Filter Drier Core to be fixed.
o System to be vacuumed.
o Compressor Oil to be changed.
o Refrigerant to be charged in the system.
o Replace the contactor if defected and fix New Contactor.
o Condensing unit to be put in to service.
o Check the unit parameters
PROJECT
7. Requirements
LAP
Calibration Certificate
HVAC Layout
HVAC Control panel wiring diagram
AHU,CU – Maintenance Manual
7.2 Training
Risk assessment is attached with this and the same shall be reviewed at site specifically
prior to work starts to ensure the existing controls are adequate.
7.4 PPEs
Safety helmets, safety shoe, goggles, gloves and coverall, safety harness
Equipment / tools
Electrical tool box, Fitter/ Duct man tool box , Ratchet spanner set , Torque wrench , A
type ladder , Portable drilling machine , Portable cutoff machine , Vacuum Pump ,
Nitrogen Cylinder.
Interface activities
Electromechanical works
8. Emergency procedures
Effective Date : Jan-2013
Document No : Mech – MS003
METHOD STATEMENT FOR
Revision No : 0
HVAC SYSTEM SERVICE
AND MAINTENANCE WORKS Page No : Page 9 of 9
Approved By :
PROJECT
In case of fire
o Follow Transco’s approved emergency procedure as per HSE Plan.
o Never try to extinguish a fire if you are not a trained fire fighter.
o Sound the alarm and notify the emergency controller at site.
9. References
Transco Specification
ETA HSE Plan
ADEHMS – Rev.2
HVAC Layout
HVAC Control Panel wiring diagram
AHU , CU – Maintenance Manual
10. Attachments