Sei sulla pagina 1di 18

Optimized Post-Tensioning

Anchorage in Prestressed
Concrete 1-Beams
Zhongguo (John) Ma Anchorage zones in prestressed concrete /-beams
Ph.D., S.E. are designed to accommodate a n chorage
Research Assistant Professor
Departm ent of Ci vil Engineering hardware and to provide adequate space for the
University of Nebraska-Lincoln reinforcement needed to distribute the highly
Omaha , Nebraska
concentrated post-tensioning force. Based on
ana l ytica l and fu ll-scale experimental studies,
optimized anchorage zone detai ls have been
developed. The proposed standardized anchorage
zone is suitab le for use with a post-tensioning
tendon size up to 75 - 0.6 in. (7 5 mm) diameter
Mohsen A. Saleh strands. It has a width of 28.5 in. (725 mm), which
Ph.D., P.E. tapers for a distance of 39.4 in . (7 000 mm) to the
Assi stant Professor standard /-beam web width. Standard welded wire
Departm ent of Civi l Engineerin g reinforcement is proposed for post-tensioning of
UAE Un iversity
A l-Ain , United Arab Emirates up to three 75 - 0.6 in. (7 5 mm) diameter strand
tendons. The use of a reduced b lock size can
result in a weight reduction of as much as 80
percent compared to the common l y used
anchorage block. A detailed example is included
to demonstrate app licatio n of the strut-and-tie
model to the design of the anchorage zone.

Maher K. Tadros, Ph.D., P.E.


Cheryl Prew ett Professor
Departm ent of Civil Engineering he span limit of precast, pretensioned 1-beam bridges
University of Nebraska-L inco ln
Omaha, Nebraska T is often controlled by handling and shipping limita-
tions. ' In many regions of the United States, the
maximum span and weight ranges are 120 to 150 ft (36 to
46 m) and 60 to 90 tons (54 to 82 t) , respectively. Post-ten-
sioning is an efficient method of field splicing of precast
concrete 1-beam segments to reach spans up to 300 ft (90
m). This can improve bridge economy by providing a struc-
tural concrete alternative to span levels that have been in
56 PCI JOURNAL
the exclusive domain of structural anchorage locations was not a struc- in Appendix B to illustrate the design
steel plate girders. tural design requirement. In other of the anchorage zone using the strut-
Despite the enormous potential of words , if the post-tensioning anchor- and-tie model. The method can be
post-tensioning in increasing the span age hardware were small enough to be used in applications that are not con-
length of 1-beam bridges, several is- fully housed in the web and flanges of sistent with the assumptions used to
sues need to be resolved before post- the member, the reinforcement could develop the standard details.
tensioning can be implemented more be designed to satisfy the structural
widely. One of these issues is the lack requirements.
FLOW OF FORCES
of guidelines for the design and detail- The reality is that there is no special
ing of the post-tensioning anchorage anchorage hardware and tensioning IN ANCHORAGE ZONE
zones. equipment on the market today that The analysis and design of the an-
The 15th Edition of the AASHTO can fit in the 6.9 in. (175 mm) web of chorage zone in post-tensioned mem-
Standard Specifications2 required that an !-beam. Therefore, it was decided bers have been studied since the early
the width of the anchorage zone be as to develop an anchorage zone with the days of the prestressed concrete indus-
wide as the narrower flanges of the smallest possible size that could allow try. In the 1950s and 1960s, extensive
1-beam and as long as three-quarters housing of commercially available an- research was performed on anchorage
of the member depth. However, in the chorage hardware. zones using a theory of elasticity anal-
current 16th Edition of the AASHTO The most critical stresses in the an- ysis and small-scale anchor zone
Standard Specifications 3 and 2nd Edi- chorage zones occur at the time of ten- tests. 6·7 Later, Gergely and Sozen pre-
tion of the AASHTO LRFD Specifica- don jacking. Optimizing and standard- sented a method of analysis dealing
tions,4 the size of the anchorage zone izing the post-tensioning anchorage with the effect of transverse reinforce-
dimensions is not specified. Instead, a zone was based on this condition. Be- ment based on the equilibrium condi-
somewhat vague statement is given: yond the time of post-tensioning, con- tions of the cracked anchorage zone.'
" ... the transverse dimensions (of the crete continues to gain strength and These studies gave a basic under-
anchorage zone) may be taken as the prestress continues to decrease. The standing of the flow of forces in sim-
depth and width of the section." This study was limited to !-beams with up ple anchorage zone configurations.
gives the designer little guidance in to three tendons consisting of 15 - 0.6 However, engineers have had diffi-
determining the minimum required an- in. (15 mm) strands per tendon . culty in extrapolating these results to
chorage zone dimensions. This is a relatively large level of more complicated anchorage zone
This Jack of guidance has led de- post-tensioning and is not expected to configurations . Therefore, the Na-
signers to over-size the anchorage be exceeded in most practical applica- tional Cooperative Highway Research
zone. It should be emphasized that tions. Based on the analysis and exper- Program (NCHRP) initiated a research
larger concrete dimensions in the an- imental work, standard concrete di- project in which one of the main re-
chorage zone do not necessarily pro- mensions and welded wire rein- search results from that study was the
duce smaller stresses. They should not forcement details are presented in this division of the anchorage zone into a
be viewed as structurally more conser- paper. A detailed example is included local zone and a general zone. 9 It was
vative. In this paper, the proposed an-
chorage zone dimensions are com-
pared to the more specific dimensions l.Oh -1.5 h
given in the 15th Edition of the I'"
AASHTO Standard Specifications.
Anchorage zones that are unneces-
Strut-and-tie model
sarily bulky and over-reinforced are
uneconomical. More importantly, they P/2
Local Zone c ~

may cause the precast, prestressed \ f --~


member to be too heavy to transport, P/2 ~-------"75// -' \---..._
thus defeating one of the primary pur-
a p-,-
2 -•-------'+Ar-/~~-----,_-----~~---~'.::::_--_,_.,_,._-=______:_--
poses of beam splicing by post-ten-
sioning. The authors have had experi-
ence with recently designed bridges
h
J - -8----- _j Bursting stress diagram
P/2
where the anchorage zone weight D
alone was as much as 10 tons (9 t).
When weight is critical, it can be a de- General Zone
termining factor in the feasibility of

Ira/~ ~I
the precast concrete alternate.
In the early stages of this investiga- rc_ -
h/2
tion,5 the finite element analysis indi- r-- - -
cated that increasing the concrete di-
mensions at the post-tensioning Fig. 1. Force flow of a simple anchorage zone .

March-April 1999 57
1250

175

500
1100

I• 450 •I
1000

1.. 450 •I envelope Section A-A


1000

(All dimensions in mm)

Fig. 2. Detail 1 -Optimized rectangular anchorage zone.

also concluded from that study that the compressive strut in the local zone and limited number of practical configura-
design of the general zone can be member "CD" represents the tension tions of the local zone. Their behavior
based on a strut-and-tie model. tie to resist the bursting force in the and design can be handled by a stan-
The strut-and-tie model is a gen- general zone. By using the simple dard acceptance test procedure. 9 In de-
eral term used to represent the truss strut-and-tie model , considerable in- sign practice, an engineer who uses an
model , which was introduced by sight into the flow of forces in the an- anchorage device type that has passed
Ritter in 1899. 10 The model has been chorage zones can be gained. How- the acceptance test does not need to
used as a conceptual tool in the de- ever, the following points need to be check the bearing capacity, node com-
sign of reinforced concrete struc- emphasized when applying this model pression capacity, and the node-strut
tures for the last 100 years. Over the to the design of the anchorage zones: interface capacity in the local zone.
years, the model has been modified First, it is apparent that if the loca- This separation makes it acceptable to
by several investigators. ''·'• tion of the tension tie member is apply the strut-and-tie model only to
It has been well understood that changed, the bursting force in the tie the design of the general zone.
cracked reinforced concrete carries will be changed. Therefore, one of the Finally, the strut-and-tie model is an
load mainly by developing a truss sys- keys in using the strut-and-tie model is equilibrium-based model. It does not
tem represented by compressive to locate the tension tie member. Stud- accurately model the forces that are
stresses in the concrete and tensile ies6·9 have shown that a reasonable lo- needed to satisfy compatibility condi-
stresses in the reinforcement. Further- cation of the tension tie is about half tions. Thus , although the strut-and-tie
more, upon the occurrence of signifi- of the member height away from the method does not give a unique solution,
cant cracking, the originally curved anchorage face for simple rectangular its use generally produces conservative
principal stress trajectories in concrete anchorage configurations. results. A detailed numerical example
tend toward straight lines. It is then For complex I-beams with flanges , is given in Appendix B to demonstrate
appropriate to regard the resulting however, a greater degree of disper- the design of the anchorage zone using
compressive forces as being carried by sion is required because a large per- the strut-and-tie model.
straight compressive struts. Therefore, centage of the compressive force must
the strut-and-tie model is capable of find its way into the top and bottom
OPTIMIZING THE
representing such stress flows after the flanges . It is considered conservative
concrete has cracked, and hence indi- to take the bursting distance as half of ANCHORAGE ZONE
cates a plausible force path for the the member height minus the eccen- During the early stages of this inves-
concentrated post-tensioning force to tricity of the tendon group for this type tigation, the study focused on the pos-
flow from the anchorage hardware of anchorage zone. sibility of completely eliminating the
into the member. Secondly , the complicated local increase of the web width at the post-
Fig. 1 shows a simple strut-and-tie zone behavior, such as the compres- tensioning anchorage locations. Based
model that represents the force flow in sive stress check of member "AB" in on a finite element analysis and simple
a simple anchorage zone. In the figure, Fig. 1, can be separated from the gen- rectangular anchorage zone testing, it
the truss member "AB" represents the eral zone. In general, there are only a was concluded that increasing the con-

58 PCI JOURNAL
500.0
1- .. ,
---1---l.-150.0
,---
...- ------------------------------- - 2996 kN - +58.0
144.8
2996 kN -+r,----·-------------· A 743 kN 209.8
267.0 : -- ------------------------------- ..,__2531 kN
2531 kN --.J,---------------------
225.9 1 1784 kN 548.9

283.0
2148 kN -+r-t-----------------
! ·s- ------------------------------ -2148 kN

168.5
3710 kN -+~------- 684 kN
179.3
L -~ ---------------- -------------------------------- 3710 kN

+
114.8

Jacking end

(All dimensions except as shown in mm)

Fig. 3. Strut-and-tie model in beam height direction.

crete dimensions at the post-tensioning don was then used to estimate the sultants at the other end (bound ary
anchorage locations was not a struc- boundaries of the anchorage zone. The section) of the anchorage zone. It
tural design requirement 5 resulting anchorage zone has a width should be noted that the stress distri-
The problem, however, is that there of 17.7 in. (450 mm) that is uniform bution at the boundary section follows
is no special anchorage hardware in the for a distance of 19.7 in. (500 mm) the conventional beam theory.
market today that can fit in a 6.9 in. and then tapers for a distance of 11.8 in. The length of the general zone was
(175 mm) web of an 1-beam. Also the (300 mm) to the standard NU 1-beam taken as one times the depth of the
production of new anchorage hardware, web thickness of 6.9 in. (175 mm), as loaded beam, i.e., 3.6 ft (1100 mm).
which can fit in the thin web, will re- shown in Fig. 2. The eccentricity of the three tendons
quire producing special jacking equip- The height of the anchorage zone can was found to be 2 in. (50 mm). There-
ment to be used with it This will add vary with the height of the NU 1-beam. fore, the location of the bursting ten-
an initial cost to the system that might As an example, the Detail 1 anchorage sion tie was chosen as half of the
make it an unfavorable alternative. zone for the NU 2000 1-beam weighs beam depth minus the eccentricity,
Therefore, it was considered a better al- about 2 tons (1.8 t). If this anchorage i.e., 19.7 in. (500 mm) away from the
ternative to develop an anchorage zone zone was designed according to the 15th jacking end.
with the smallest possible size that Edition of the AASHTO Specifications/ From Fig. 3, the maximum bursting
would allow housing of commercially it would weigh about 10 tons (9 t). By force was calculated to be equal to 401
available anchorage hardware. comparison, the proposed Detail 1 an- kips (1784 kN) from Node A and
chorage zone can reduce the weight of 400.9 kips (1782 kN) from Node B.
the conventional anchorage zone by as The required area of reinforcement for
Detail 1 - Optimized Rectangular much as 80 percent the bursting force had been calculated
Anchorage Zone With the chose n co ncrete dimen- as 6.68 sq in. (4312 mm 2). This rein-
In developing the Detail 1 anchor- sions of the Detail 1 anchorage zone, forcement was then distributed over a
age zone, optimization was focused on reinforcement for the general zone length of approximately 3.6 ft (1100
minimizing the weight of the anchor- under the three concentrated post-ten- mm). The actual reinforcement pro-
age zone. Therefore, the minimum di- sioning forces was designed using the vided in the anchorage zone was 0.5
mensions that can enc lo se all the strut-and-tie model. The web of the 1- in. (12.7 mm) diameter (#4) reinforc-
available anchorage hardware in the beam provides for the vertical distri- ing bar at a spacing of 2.0 in. (50
market pi us a reasonable concrete bution of the three concentrated jack- mm). The resulting area of reinforce-
cover were chosen. ing forces. The factored app lied ment was 8.0 sq in. (5162 mm 2) .
The 6.9 in. (175 mm) Nebraska Uni- jacking forces were divided into four Then, the reinforcement in the top
versity !-beam ' s web can accommo- concentrated forces in the model with flange, bottom flange, and web was
date a duct with a maximum diameter two forces flowing into flanges and designed to allow for the transverse
of 3.5 in. (88 mm). The duct can hold two into the web, as shown in Fig. 3. distribution of the three concentrated
a 15 - 0.6 in. (15 mm) strand tendon. These four forces at the jacking end tendon forces. Strut-and-tie models are
The anchorage hardware with this ten- balance the resulting elastic force re- shown for the top flange, bottom
March-April 1999 59
500 b/2 = 625
I• 500 • 11:12 = 5~?

1855 ~---------------~---------------1--- 1855 kN


1498 kN__ ...--------- .-----]·················1-- 1498 kN
1 479kN ..l.._ 510 kN
1855 kN ·------------ -----------------1--- 1855 kN
.0 1498 ;·-----------------.
·- ·················1-1498 kN

(b) Bottom Flange


(a) Top Flange

150
:-:+1 1-
2340 kN~ 2340 kN
~ r
0
T
- - ·r··cr··---------..... -
-·- lTJl ------------
_1; L_ 2340 kN ° -· 2340 kN

Tl=ll70 kN

(c) Web

(All dimensions except as shown in mm)

Fig. 4. Strut-and-tie models in transverse direction (Deta ill ).

flange, and web in Figs. 4a, 4b, and Detail 2 -Optimized Tapered between the Detail 2 anchorage zone
4c, respectively. Anchorage Zone and Detail 1 anchorage zone.
The required steel in the top flange
During the optimization process of The slope of the tapered anchorage
was found to be 0.5 in. (12.7 mm) di-
the Detail 2 anchorage zone, several zone was calculated based on the fol-
ameter (#4) reinforcing bar at a spac-
other factors were considered besides lowing conditions: (1) the width at the
ing of 6.1 in. (156 mm), which was
the minimum weight requirement. section 19.7 in. (500 mm) away from
smaller than the steel provided to resist
First, the tapered part of the Detail 1 the jacking end was at least 17.7 in.
the loading during deck placement.
anchorage zone was extended to the (450 mm) to accommodate the avail-
The steel required in the bottom flange end of the beam to allow for more able anchorage hardware; and (2) the
was 0.5 in. (12.7 mm) diameter rein-
space for the concrete consolidation in chosen slope would result in minimum
forcing bar at a spacing of 4.3 in. (110
this area. Fig. 6 shows the comparison weight of the anchorage zone.
mm), which was more than that nor-
mally provided for strand confinement.
The actual steel provided for the top Fig. 5.
and bottom flange was the same, i.e., The general zone
0.5 in. (12.7 mm) diameter reinforcing reinforcing cage
bar at a spacing of 2.0 in. (50 mm). (Deta ill ).
Based on calculations, the required
steel in the web was equal to 0.63 in.
(16 mm) diameter (#5) reinforcing bar
at a spacing of 2.5 in. (64 mm). Be-
cause there was not enough length in
this direction to develop the 0.63 in.
(16 mm) diameter reinforcement,
threaded rods of 0.63 in. (16 mm) di-
ameter with anchoring plates at the
ends were used. The actual spacing of
the rod was 2.0 in. (50 mm). Fig. 5
shows the completed general zone re-
inforcing cage.

60 PCI JOURNAL
steel forms. One of the objectives of
,--- this testing program was to explore
how to minimize modifying the cur-
rent constant section steel forms. Con-
sidering the fac t that the current pris-
m ati c stee l fo rm s have a stand ard
length of about 40 ft (12 m), there are
§
- two poss ible alternatives to produce
post-tensioned concrete I-beams.
The first alternative is to cast both
anchorage zones simultaneously with
a prismatic 1-beam piece. In this case,
producers need not only to add steel

L,.__500
I.
.. !.. 300 .. 1 _j forms for anchorage zones, but also to
cut the standard 40ft (12m) long pris-
matic fo rm to fit the designed length
1000 of the precast beams.
The other alternative is to cast one
(All dimensions in mm) anchorage zone with the pri smatic
beam component. In this second alter-
Fig. 6. Comparison between two details in transverse direction. native, producers only need to add a
small stee l form for the anchorage
zone to the avail able standard pris-
As a result, the Detail 2 anchorage fabricated reinforcing bar welded cage
matic steel forms. The other anchor-
zone has a width of 28.5 in. (725 rnm) to save production time. This cage has
age zone can be cast separately or
that tapers for a di stance of 39.4 in. the same shape as the tapered anchorage
using a longer beam segment with an
(1 000 mm) to the standard NU beam zone in the transverse direction for easy
anchorage seg ment cast integrally
web thickness of 6.9 in. (175 mm ). placement, as shown in Fig. 7. The final
with it. The se parately -cast prec ast
The height of the anchorage zone can design results are shown in Fig. 8.
components can th en be po st-ten -
vary with the height of the I-beam.
sioned together by match-casting or by
Once the concrete dimensions of the
Detail 2 anchorage zone were chosen,
INTEGRAL VS. SEPARATE a wet joint.
reinforcement was designed based on ANCHORAGE ZONE
the strut-and-tie model similar to the de- In applying the post-te ns ioning FULL-SCALE TEST
sign of the Detail 1 anchorage zone. splicing technique, producers might be In contrast to the conventional labo-
However, the decision was made to concerned about the poss ible modifi- ratory testing in which specimens are
change the threaded rod details to a pre- cation of available standard prismatic loaded proportionally until failure, the

r- - /
/ First two vertical wires of the WWF

§ V"l
N
r--
r
13 X 2
Plate
g (weld
\0 to the
I
---------~R
25
::::-----....__
~ V"l
____t_S
-~~
l
1 25 mrn

__....----- ' 45CLR


#5- A706 (Typ.)
Weld Detail A #5 - A706

J 17 SPA@ 50= 850


welded cage
.I _._
I
25
~
\W -~ E70
8 25

Weld Detail A

Fig. 7. Welded bar cage deta il.

March-April 1999 61
12.7 mm dia. bar @ 50 mm spacing
• - -,
R
I
=
=
12. 1 mm Dia. bar
···-
@ 50 mm spacing
(1600 mm long)
!"" !"" !"" !"" '/
- ./

welded bar cage


-······ ..
I §
(see Fig. 7) :····· ---· .. .. 8
....;
---~--.......... ....;

... . . . ....

~~
!-- 1--
~ lr- F
If' ~
1=- = "=
· -1 -L
12.7 mm Dia. bar @ 50 mm spacing
( 1600 mm long)

Fig. 8. Reinforcement details (Detail 2).

full-scale experimental program 15 in was first ordered. This form has the reduce poss ible local stress concen-
this research project was designed to same length as the anchorage zone, tration. This procedure proved to be
simulate the field post-tensioning pro- i.e., 2.6 ft (0.8 m) . Then , it was at- satisfactory.
cess. Before the full-scale specimens tached to the standard NUll 00 pris- To account for the load factor of
were produced , anchorage hardware matic steel form to make one end of 1.2 in the actual post-tensioning
available in the market was installed the anchorage zone plus the 14.8 ft stage, it was found that the tendon
in the specimens. The post-tensioning (4.5 m) prismatic 1-beam segment. Fi- with 19 - 0.6 in. (15 mm) low-relax-
technicians from that particular hard- nally , the other end of the 2.6 ft (0.8 ation strands should be used . These
ware supplier were invited to do the m) anchorage zone was match-cast, as tendon s can give a load factor of
actual post-tensioning work. shown in Fig. 9. 19/15 = 1.27 for the tendon with 15-
The main objectives of the program Once the two pieces of the same 0.6 in. (15 mm) strands used in the
were to study the behavior of the pro- specimen were ready to receive the design of the optimized anchorage
posed anchorage zones under factored post-tensioning force , the match-cast zone dimen sion s base d on the
post-tensioning forces, to verify the faces were lubricated with epoxy to AASHTO LRFD Specifications.'
adequacy of the design based on the
strut-and-tie model and the overall
performance of the local zone as well
as the general zone, and to investigate
casting the anchorage zone separately
from the prismatic beam.

First Test Series


The first series of tests consists of
two Detail 1 specimens (B l and B2).
Each specimen is 20 ft (6.1 m) long
with two Detail 1 anchorage zones at
the ends. Of the 20 ft (6.1 m) long
specimen, each anchorage zone is 2.6
ft (0.8 m) in length and the remainder
is 14.8 ft (4.5 m) long standard pris-
matic NUIIOO 1-beam segment. The
anchorage hardware was provided by
Dywidag Systems International.
The special steel form to produce
the Detail 1 anchorage zone shape Fig. 9. Match-cast joint surface.

62 PCI JOURNAL
strength testing. For ultimate strength
te sting , only minor hairline cracks
were found in the anchorage zone, as
shown in Fig. 11. No signs of other
distress were noticed . According to
the s train gauge readings after the
three tendons had been post-tensioned,
all the reinforcement stress in the pre-
dicted bursting zone reached about the
yield stress level. The performance
of the specimens was believed to be
satisfactory.

Second Test Series


The second series consists of two
Detail 2 anchorage zone specimens
(B3 and B4). Each specimen is again
about 20 ft (6.1 m) long with two opti-
mized tapered anchorage zones at the
ends . The anchorage hardware was
Fig. 10. Middle tendon during post-tensioning. provided by CCS Special Structures.
The special stee l form of 3 .3 ft
(1.0 m) in length to produce the Detail
A specified concrete strength of 6000 tensioned after the deck was cast, was 2 anchorage zone shape was ordered.
psi (41.4 MPa) at the stage of post-ten- post-tensioned to the same force level. Fig. 12 shows the form and its attach-
sioning and a 28-day strength of 8000 To keep the testing simple, the last ment to the standard NUllOO pri s-
psi (55 .2 MPa) were chosen for design tendon was post-tensioned on the non- matic steel form to make half of the
calculations. The actual cylinder composite specimen. This procedure 20 ft (6.1 m) long specimen. Once the
strength at the time of the post-tension- was believed to be on the safe side, as other half was produced , the two
ing , which was applied about two compared to the procedure in which pieces were connected together by a
months after the specimens were pro- the third tendon was post-tensioned wet joint about 4 in. (102 mm) long at
duced, was 9600 psi (66.2 MPa) for after the deck was cast. the middle of the specimen instead
Specimen B 1 and 10,500 psi (72.4 According to this testing procedure, of the match-cast joint in the Detail 1
MPa) for Specimen B2, respectively. the non-composite specimen had actu- anchorage zone.
The reinforcement of the web, top ally received 1.33 times the designed Thi s change was made based on the
flange and bottom flange in the center maximum jacking force. This was be- fact that some producers may prefer
of the predicted bursting zone was in- lieved to be s imilar to ultimate the wet joint option. To make the wet
strumented to evaluate the behavior of
the design model.
During the post-tensioning process,
the actual post-tensioning sequence in
the field was followed:
Step 1 - The middle tendon of the
three designed tendons was post-ten-
sioned to 0.85Aps/pu = 946.2 kip s
(4205 kN). This was equivalent to
(0.85/0.81) (1.27) = 1.33 times the de-
signed post-tensioning force level.
Then , the possible concrete cracking
in the anchorage zone was observed
and marked. Fig. 10 shows the middle
tendon during post-tensioning. No
cracking was found.
Step 2 - The bottom tendon was
post-tensioned to the same force level
as the middle tendon.
Step 3 - The last top tendon close
to the centroid of the composite sec-
tion , which was designed to be post- Fig. 1 1. Hai rlin e cracks after post-tension ing (Detail 1).

March-April 1999 63
Fig. 12. Steel form for tapered anchorage zone.

joint, the following procedure was beam together. Care has to be taken to mixer with rotating blades was used.
used: make the two pieces straight. The gap Up to 45 percent of washed pea
1. Prepare a rough joint surface. In between the two pieces is recom- gravel in a maximum size of 3/s in .
the testing program, the "panel pad" mended to be about 4.0 in. (102 mm). (9.5 mm) was added to the grout mix.
(see Fig. 13A) was attached to the 3. Use a non-shrink high perfor- Testing has shown that this procedure
steel end plate to make the rough sur- mance grout to pour the wet joint. works well.
face. Fig. 13B shows the roughened The "Sure-Grip High Performance For the transverse bursting force, ta-
joint surface using the "panel pad." Grout" from the market was used in pered welded bar cages were used and
2. Align two pieces of the same the testing program. A mechanical produced by welding the bars to flat

Fig. 13. The " panel pad" used to roughen the joint surface. Fig. 14. Anchorage zone reinforcement details (Deta il 2).
(A) The " panel pad"; (B) Roughened wet joint surface . (A) Tapered welded bar cage; (B) Reinforcement detail.

64 PCI JOURNAL
plates (see Fig. 14A). Two such cages
were used in the anchorage zone, as
shown in Fig. 14B.
To account for the load factor of 1.2
in the actual post-tensioning stage, the
tendon with 19 - 0 .6 in. (15 mm)
low-relaxation strands was again used,
as in the first series.
A specified concrete strength of
6000 psi (41.4 MPa) at the stage of
post-tensioning and a 28-day strength
of 8000 psi (55 .2 MPa) were again
chosen for the design calculations .
However, the actual cylinder strength
at the time of the post-tensioning was
10,170 psi (70.1 MPa) for Specimen
B3 and 10,050 psi (69.3 MPa) for
Specimen B4, respectively. Again,
Fi g. 15. Hairline cracks for Spec imen B4 .
the reinforcement of the web , top
flange and bottom flange in the cen-
ter of the predicted bursting zone cracking is not necessarily critical, and 1. Minor cracks were limited to a
was instrumented. there often is significant strength be- smaller range in Detail 2 than in Detail
As in the first test series, the actual yond the first appearance of cracks. 1 during the full-scale tests .
post-tensioning sequence in the field According to the strain gauge read- 2. It is easier to consolidate the con-
was followed . However, the following ings, after the three tendons were post- crete near the anchorage hardware in
changes were made as compared to tensioned, the maximum reinforcement Detail 2 than in Detail 1.
the first series: stress in the predicted bursting zone 3. The smooth transition shape of
1. The tendon was only post-ten- had reached about 35 ksi (241.3 MPa), Detail 2 makes the placement of trans-
sioned to 0.81APJP" = 901.7 kips which is smaller than the stress level in verse bursting reinforcement more
(4010 kN). This is equivalent to 1.27 the first test series. Based on the test convenient.
times the designed post-tensioning results of this test series, the concrete 4. Detail 2 is slightly more aestheti-
force level, which is smaller than the dimensions of the Detail 2 anchorage cally pleasing than Detail 1.
load level used in the first series but zone, the reinforcing details used, the In the design, attention was focused
still larger than the ultimate load fac- wet joint detail, and the local zone per- on adopting standard anchorage de-
tor specified in the AASHTO LRFD formance all proved to be adequate. tails for different I-beam sections
Specifications. 4 varying from NU1100 to NU2000. To
2. After the middle tendon, the top this end, three 15 - 0.6 in. (15 mm) di-
tendon was post-tensioned before the
STANDARD AN CHORAGE
ameter low-relaxation strand tendons
bottom tendon. This sequence was dif- ZONE DETAILS were chosen for all the sections. The
ferent from the first test series. Based on the full-scale NU1100 spec- different force flow at the anchorage
Not even minor cracks were found imen test results, the two optimized an- zone due to the changing of the sec-
after the middle tendon was tensioned chorage zones have been proven to per- tion height was adjusted by extending
to the maximum load level in this test form well. It is important to point out the vertical bursting reinforcement.
series. After the top tendon was post- that the test results were based on speci- Table 1 summarizes the bursting re-
tensioned to the load level, small mens with a limited height of 43 .3 in. inforcement required in the anchorage
minor cracks were found and no fur- (1100 mm). It is impractical to test all zone for different NU I-beam sections.
ther cracking was found at the post- the specimens with different sizes . Based on the strut-and-tie model de-
tensioning of the third tendon . As However , the tests on the NU 1100 sign, the following conclusions can be
shown in Fig. 15 , the minor cracks specimens have shown that the strut- made:
were limited within a much smaller and-tie model can give a good predic- 1. The standard tapered anchorage
range than the crack found in the first tion on the bursting reinforcement re- zone (Detail 2) with the same concrete
test series. No signs of other distress quirement. Therefore, it was used as a dimensions can be used for all the
were observed. design tool for the other I-beam sizes. !-beam sections, as shown in Fig. 16.
It should be emphasized that minor Although both Detail 1 and Detail 2 2. As shown in Fig. 17, the same re-
cracking in the anchorage zone is performed well in the full-scale tests , inforcement details in the top flange,
quite normal and to be expected.' 6 It the optimized Detail 2 anchorage web, and bottom flange with the ex-
has nothing to do with the onset of an- zone design was chosen as the stan- ception of the vertical web reinforce-
chorage zone failure. In adequately re- dard concrete dimensions based on ment can be used for all sizes of
inforced tendon anchorage zones, such the following: !-beams.
March-April 1999 65
3. In the vertical direction, the rein-
forcement size, D18, and spacing of 2 0 0 ~ 0 0 0 0 0 0 0 0 0 0 0 0 ~ ~ ~ ~ 0
in. (50 mm) can be used for all beam E gg8 g ~ gggg6 . . . . . 8 8 8 8 6
E ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~
sizes in the NU 1-beam series, which
1;l
ranges from 43.3 to 78.7 in. (1100 to
s ~+-----------~----------r---------~~--------~
2000 mm) deep . However, the extent "-
Q
of this reinforcement size and spacing
into the beam depends on the beam
depth, as shown in Table 1.

IMPACT OF SHEAR
One important issue may be that the
anchorage zone might need more rein-
forcement to resist the high shear
~ ~,-----------t-----------t---------~~----------1
force at the member ends. Considering <
the possible reinforcement congestion
in this zone, it is very important to in-
vestigate the impact the high shear
force would have on this region . Be-
cause the NU2000 1-beam section has
the longest anchorage zone, the impact
of shear was studied for this section
using the following two examples. 1;l
c
~ ~+-----------t-----------T---------~~----------1

Example 1 "'
Q
The first example is a single span of .E
= ~
0
g
0
~
0
g
0 0 0 0 0 0
~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~
~ ~ ~ 0 0 0 0 0
ggggg
0 0 0

155 ft (47.2 m). NU2000 1-beams are ~


spaced at 8.0 ft (2.4 m) . Concrete cE
c
·~ r-+-~----------+-----------+-----------r-----------1
strength is 8000 psi (55.2 MPa) at ser-
vice and 6000 psi (41.4 MPa) at the ~
time of post-tensioning. HS-25 truck ·=
..
<:1'

loading is used. Deck thjckness is 7.5 1:1:

in. (191 mm) with a concrete strength


~ ~+-----------~----------~----------~--------~
of 5000 psi (34.5 MPa). Based on the <
AASHTO Standard Specifications /
the required shear reinforcement at the
critical section is 0.42 sq in./ft (0.89
mm 2/mm).
From Table 1, the required trans-
verse reinforcement at the section to
resist the bursting post-tensioning
force is 11.48 sq in. (7406.4 mm 2)/72
in. (1828 .8 mm) = 1.91 sq in./ft (4.05
mm 2/mm) . If the prestress loss of the
post-tensioning tendons is assumed to
be 20 percent, then the actual required
bursting reinforcement at service is
1.91 sq in./ft (4.05 mm 2/mm) (1 - 0.2)
= 1.53 sq in./ft (3.24 mm 2/mm).
The actual reinforcement provided
at this section is 14.17 sq in./ft (9141.9
mm 2/mm)/78.7 in. (2000.0 mm) =
2.16 sq in./ft (4.57 mm 2/mm), which is
greater than 0.42 sq in./ft (0.89
mm 2 /mm) + 1.53 sq in./ft (3.24
mm 2/mm) = 1.95 sq in./ft (4.13
mm 2/mm). Therefore, the reinforce-
ment provided at the anchorage zone
66 PCI JOURNAL
1000
§
N

--
8
, .. 725 ..,
1000

envelope Section A-A

(All dimensions in mm)

Fi g. 16. Standard NU 1-beam post-tensioning anchorage (concrete dimension).

B WWF6

r
A WWFI
(Plus 20-G401 @ Ea. End)
rl-----~-600_·_2_000
_ _ _ _ _..,

-------------
----------------------------------
./
Welded Bar Cage -- ........ --------------------
(WBC) (see Fig. 7) ---------------------------

------------- --------------
l_l.!._______ j _..!..!

A B
Beam Elevation

A-A B-B

__ ws (Typ.) 020 ® 150


!.(1 50 .~1 50 I... .
. 510_,r1 50* 150)1
' -'1 ~ m ---'----''----"1""1 . ws (Typ.)

WWF6 r-43~430 1
- 018 @ 50 ~.J. :!
#4 ~
nmm\p;::@50 ~
I -r
~>J&.~m
#3
G301
J--- - - -1175 ------1 t -370 -1-330 -1..290 ..\-330 ..1.- 370 ~
G401 1690 WWFI
WBFI

Fig. 17. Stand ard NU 1-beam post-tensioning anc horage (reinforcement).

March-April 1999 67
is sufficient to resist the bursting force force due to post-tensioning in combi- 5. Design of the anchorage zone
due to post-tensioning as well as the nation with vertical shear. based on the strut-and-tie model is
shear force at ultimate. conservative. It gave reasonable rein-
forcement quantities for the I-beams
CONCLUSIONS
Example 2 considered in this study.
1. Although it would be theoreti-
The second example is a two-span cally possible to eliminate the change
bridge of 165 ft (50.3 m) spans. in concrete dimensions at the anchor- ACKNOWLEDGMENTS
NU2000 I-beams are spaced at 8.0 ft age zone and to use a constant I-beam This project was sponsored by the
(2.4 m). Concrete strength is 8000 psi cross section, there is no anchorage Nebraska Department of Roads
(55.2 MPa) at service and 6000 psi hardware on the market today that (NDOR) and the University of Ne-
(41.4 MPa) at the time of post-tension- would fit into a 7 to 8 in. ( 178 to 203 braska Center for Infrastructure Re-
ing. HS-25 truck loading is used. Deck mm) web of anI-beam. search (CIR). The support of all NDOR
thickness is 7.5 in. (191 mm) with a 2. For the currently available post- personnel is gratefully acknowledged.
concrete strength of 5000 psi (34.5 tensioning hardware systems, an opti- Specimens for the experimental pro-
MPa). Again, based on the AASHTO mized tapered anchorage zone detail gram and technical assistance were
Specifications, 3 the required shear re- was developed. Based on the full-scale provided by Concrete Industries, Lin-
inforcement at the critical section is specimen testing, it was found to per- coln, Nebraska, and Wilson Concrete
0.55 sq in./ft (1.16 mm2/mm). form well for a maximum of three ten- Co., Omaha, Nebraska.
From Table 1, the required trans- dons, each consisting of 15 - 0.6 in. The generous contributions by two
verse reinforcement at the section to (15 mm) diameter low-relaxation post-tensioning companies are grate-
resist the bursting post-tensioning strands. The optimized tapered an- fully acknowledged. Both firms do-
force is 11.48 sq in. (7406.4 mm 2)/72 chorage zone dimensions are applica- nated technician support and all the
in. (1828.8 mm) = 1.91 sq in./ft (4.05 ble for all currently existing I-beam necessary hardware. In particular, the
mm2/mm). If the prestress loss of the shapes and sizes. authors wish to express their sincere
post-tensioning tendons is assumed to 3. All reinforcement details in the appreciation to Ronald Bonomo, Kent
be 20 percent, then the actual required top flange, web, and bottom flange Speheger and Clarence Nash of Dy-
bursting reinforcement at service is with the exception of the vertical web widag Systems International (DSI),
1.91 sq in./ft (4.05 mm 2/mm) (1 - 0.2) reinforcement can be used for all sizes and Andrew Micklus, Jr. and George
= 1.53 sq in./ft (3.24 mm 2/mm). of I-beams. In the vertical direction, Hare of CCS Special Structures, Inc.
The actual provided reinforcement the reinforcement size, Dl8, and spac- (CCS).
at this section is 14.17 sq in./ft (9141.9 ing of 2 in. (50 mm) can be used for Last but not least, the authors ac-
mm 2/mm)/78. 7 in. (2000.0 mm) = all beam sizes in the NU I-beam se- knowledge the work of Dr. Gregor
2.16 sq in./ft (4.57 mm 2/mm). It is ries, which ranges from 43 .3 to 78.7 Wollmann of VSL Corporation who
greater than 0. 55 sq in ./ft ( 1.16 in. (1100 to 2000 mm) deep. However, independently checked the anchorage
mm 2/mm) + 1.53 sq in ./ft (3.24 the distance over which this reinforce- zone reinforcement and verified the
mm 2/mm) = 2.08 sq in./ft (4.40 ment is used in the beam ends depends necessary spiral sizes. The following
mm 2/mm), which is required at the on the beam depth, as illustrated in research assistants and staff also
section. this paper. helped with the project: Mantu
Based on the two examples dis- 4. Reinforcement in the anchorage Baishya, Sherif Yehia, Zak Metry and
cussed, it is concluded that the rein- zone was designed to satisfy both Jim Peoples. Karen Bexten of Tadros
forcement provided at the anchorage post-tensioning and vertical shear Associates LLC reviewed the example
zone is enough to resist the bursting requirements. in Appendix B.

68 PCI JOURNAL
REFERENCES
I. Seguirant, S. J., "New Deep WSDOT Standard Sections Ex- 9. Breen, J. E., et a!, "Anchorage Zone Reinforcement for Post-
tend Spans of Prestressed Concrete Girders," PCI JOURNAL, Tensioned Concrete Girders," Transportation Research Board,
V. 43, No. 4, July-August 1998, pp. 92-11 9. NCHRP Report 356, National Academy Press, Washington,
2. AASHTO , Standard Specification s f or Highway Bridges, D.C., 1994, 203 pp.
Fifteenth Edition , American Association of State High- 10. Ritter, W., "Die Bauweise Hennebique ," Schweizerische
way and Transportation Officials, Wa shington , D.C. , Bauzeitung (Zurich), V. 17, 1899, pp. 41-43 , 49-52, and 59-61.
1992. 11. Morsch, E., Reinforced Concrete Construction - Theory and
3. AASHTO, Standard Specifications for Highway Bridges, Application (Der Eisenbetonbau -Seine Theorie und Anwen-
Sixteenth Edition , American Association of State High- dund) , 5th Edition, K . Witter, Stuttgart, V . 1, Part 1, 1920, 112
way and Transportation Official s, Wa shington , D.C ., pp., and Part 2, 1922, 112 pp.
1996. 12. Marti, P., "Basic Tools of Reinforced Concrete Beam Design,"
4. AASHTO LRFD, Bridge Design Specifications, Second Edi- ACI Journal, V. 82, No. 1, January-February 1985, pp. 46-56.
tion, American Association of State Highway and Transporta- 13. Schlaich, J., Schafer, K., and Jennewein, M. , "Toward a Con-
tion Officials, Washington, D.C., 1998. sistent Design of Reinforced and Prestressed Concrete Struc-
5. Hamad, H. H., "Anchorage Zone in Post-Tensioned Concrete tures," PCI JOURNAL, V. 32, No.3, May-June 1987, pp. 74-
Bridge 1-Beams," M.S. Thesis, University of Nebraska-Lin- 151.
coln, Omaha, NE, 1996, 106 pp. 14. Ramirez, J. A., "Strut-Tie Design of Pretensioned Concrete
6. Guyon, Y., Prestressed Concrete, John Wiley and Sons, Inc., Members," AC! Structural Journal, V. 91 , No. 4, September-
New York, NY, 1953. October 1994, pp. 572-578.
7. Huang, T., "Stresses in End Zones of a Post-Tensioned Pre- 15. Ma, Z., "Shear and Disturbed Regions in High Performance
stressed Beam," AC! Journal , V. 61, No. 5, May 1964, pp. Concrete Bridges," Ph.D. Dissertation, University of Ne-
589-601. braska-Lincoln, Omaha, NE, 1998, 329 pp.
8. Gergely , P., and Sozen, M. A., "Design of Anchorage- 16. Wollmann, G. P., and Breen, J. E., Discussion of "Stress Dis-
Zone Reinforcement in Prestressed Concrete Members," tribution and Cracking Behavior at Anchorage Zones in Pre-
PCI JOURNAL, V. 12, No. 2, March-April 1967 , pp. stressed Concrete Members," AC! Structural Journal, V. 95 ,
63-75. No. 4, July-August 1998, pp. 458-459.

APPENDIX A- NOTATION

a = width of anchorage plate Sb =noncomposite section modulus for extreme fiber of


A = area of noncomposite gross section section where tensile stress is caused by externally
Aps = total area of strands per tendon applied loads
b = width of transverse direction S1 = noncomposite section modulus for extreme fiber of
F; = node force in ith node section where compressive stress is caused by ex-
fci =specified concrete strength at time of post-tension- ternally applied loads
ing V =shear force
/pu= specified tensile strength of prestressing strands w 1 = beam self-weight
h = overall depth of beam w 2 = deck weight
hb = equivalent bottom flange height Yb = distance from neutral axis to extreme tension fiber
h 1 = equivalent top flange height Ybottom = location of resultant tendon force in bottom flange
hw = equivalent web height y 1 = distance from neutral axis to extreme compression
I = moment of inertia of noncomposite gross section fiber
P = maximum jacking force per tendon Yrop =location of resultant tendon force in top flange
PT = total factored tendon force in horizontal direction Y web = location of resultant tendon force in web
Pu = factored tendon force per tendon a= angle of tendon relative to longitudinal axis
R = reaction force ¢ = resistance factor

March-April 1999 69
APPENDIX B - DESIGN OF POST-TENSIONED ANCHORAGE ZONE
Design of the po st-ten sioned an- gross section properties at Section B-B sioning anchorage zones is taken as
chorage zone based on the AASHTO in Fig. Blare as follows: 1.2 times the maximum jacking force.
LRFD Specifications• by the strut- A = 789 sq in. (0.509 m2) The resistance factor ¢is taken as 0.80
and-tie model is illustrated using the for compression in anchorage zones
Yb = 24.73 in. (0.63 m)
following example. The example is and 1.00 for tension in steel in anchor-
Y1 = 29.27 in. (0.74 m)
for a two-span continuous bridge con- age zones (AA SHTO LRFD Article
l = 260,741 in. 4 (0.109 m 4 )
structed with AASHTO Type IV 1- 5.5.4. 2. 1). Hence, the tendon force
beam s. The spans are each 122 ft sb = 10,543 cu in. (0.173 m 3) used in design is P u = 1.2P = 854 kips
(37.2 m) long. The beams are spaced sf= 8908 cu in. (0.146 m3) (3 797 kN). The uniform dead load
at 10.7 ft (3.25 m) and have 28 - 1/2 in. In this example, the DSI Multiplane from the deck and the beam bearing
(12.7 mm) low-relaxation pretension- Anchorage (MA) is used. The anchor- reaction tend to reduce the bursting
ing strands and three post-tensioning age size is 15 - 0.6 in. (15 mm) which force. For this reason, a load factor of
tendon s of 12 - 0 .6 in. (15 mm ) can accommodate 15 - 0.6 in. (15 mm) 1.0 is used for these loads.
strands. GR 270 strands. The maximum jack- The anchor plate size is taken ap-
In this example, the anchorage zone ing force is P = 0.9 APJPY = 0.81Aps/pu proximately as the spiral size plus the
will be designed to resist three post- = 712 kip s (3164 kN ) (AA SHTO concrete cover. According to the hard-
tensioning tendons of 15 - 0.6 in. ( 15 LRFD Article 5.9.3), where Aps is the ware supplier (DSI), the outside diam-
mm) strands. The effect of the preten- total area of strands per tendon, /py is eter of the spiral is 12.5 in. (318 mm).
sioning strand s is ignored . Fig. B 1 the yield strength of pre s tre ss ing Since the spiral is round, it is easier to
shows the beam details near the an- strands, and fru is the specified tensile convert the spiral into an equivalent
c horage zo ne . All po st-ten sioning strength of prestressing strands. square to compare it with rectangular
forces are assumed to be applied to the According to AASHTO LRFD Arti- struts. Therefore, the width of plate
non-compo site precast beam s. The cle 3.4.3, the design force for post-ten- can be taken as a = 12.0 in. (305 mm).

Fig. Bl .
Example anchorage
zo ne.
r A f 78.7 : 62 1 B~
-r----- -~r--------------------,------------~i
l
-~ ---r===~~====================================~~
- -------------- 1~ :

----------------------------~~~~~-;~~~~~~~~~~~~~~ "' ·I ~]
-:---- ---
-:--- --

.L I _ _ _ _ _98.5 _ _ _ _ _ _ _..., i .,JI


A
..j~61~ ____________
General Zone
146.5 - - - - - - - - - --+
B

12 x 12 anchor
plate (Typ.)
+
·t-
t-
(All dimensions in inch)
26
.. j

Fig. B I. Example anchorage zone.

70 PC I JOURNAL
Determine Extent not more than one and one-half times Determine Stress Distribution
of General Zone that dimension. at End of General Zone
In this example, the height of the
There are two types of discontinu- noncomposite beam is 54 in. (1.4 m). The locations of the three tendons
ities in the end region of the beam, Therefore, the length of the general are shown in Fig. B 1. From this fig-
which disturb the stress distribution zone is not to exceed 1.5 x 54 in. (1.5 ure, the calculated angles of the three
based on the beam theory : (1) loading x 1.4 m) = 81 in. (2.1 m) . However, tendons relative to the longitudinal
discontinuities, such as post-tension- considering the geometrical disconti- axis are a 1 = 3.94°, a 2 = 3.19°, and a 3
ing force and reaction force; and (2) nuity , the boundary of the general = 2.44°. At the end of the general
geometric discontinuity. zone will be assumed to be located zone, the center of gravity of the three
According to AASHTO LRFD Ar- one web width ahead of the end of the tendons is 22.5 in. (572 mm), and the
ticle 5 .10.9.1 , the longitudinal extent change in web geometry. As a result, eccentricity is 2.23 in. (56.6 mm).
of the anchorage zone in the direc - the extent of the general zone is taken The total factored design tendon
tion of the tendon is to be not less as 11.8 in. (0.3 m) + 78.7 in. (2.0 m) + force in the horizontal direction is
than the greater of the transverse di- 8.0 in. (0.2 m) = 98.5 in. (2.5 m) as PT = Pu (cosa 1 + cosa2 + cosa3) =
mensions of the anchorage zone and shown in Fig. B 1. 2559 kips (11372 kN) . Thus, the bot-

Fig. B2.
Strut-and-tie model.
(a) Stress
3.525 ksi distribution and
- 763.8k resultant forces at
3.419 ksi boundary;
(b) Strut-and-tie
model .
- 798.4k

3.125 ksi
- - - 996.0k
3.004 ksi

(a) Stress distribution and resultant forces at the boundary

..
1.822 k/ft

'''' ' ''''' '' ' ..


-. - 765.6 k
r-
a I
. A.----· ·2
1..:
______ _BI. -----r· · -~

15
:14
15.0 k

I
----------- -4 --------------- ~63 . 8 k
I
i
--r
1 II i
~I
799.6 k
. 5 fr;····-·6 -- E -
7
--------------------A=~ 798.4 k f ~
..,.1
~I
a3 12 16 158.6 k
1
=
I 00
996.9 k I

I
i ·s·t---- - ·9 ·---- iI I ;::"'
:G H
/ 13 -- --------- ---------w -- - ----------------- ~ 996.0 k a, II I
.I__ ' I --- ~ L _L_i
I "-1- 95.9 k
I
:
I,.

f _ 31.5" - _ __.;_

--------------------
' 98.5"

General Zone
~

(b) Strut-and-tie model

March-April 1999 71
tom fiber and top fiber stresses at the Table Bl. Member forces in the strut-and-tie model.
end of the general zone due to this ten- Member Force, kips (kN) By which node balance?
don force are 3. 784 and 2. 602 ksi l 765.6 (3403) Known
(26 .1 and 17.9 MPa) respectively.
2 788.6 (3505) Node 8
After calculating the stresses due to
beam self-weight (w 1 = 0.822 kip/ft or 3 763.9 (3395) NodeC
12.0 kN/m) and deck weight (w 2 = 4 763 .8 (3395) Known
1.000 kip/ft or 14.6 kN/m) , the total 5 799.6 (3554) Known
bottom fiber and top fiber stresses at
6 800.8 (3559) NodeD
the end of the general zone are 3.004
and 3.525 ksi (20.7 and 24.30 MPa) 7 800.5 (3558) NodeF
respectively , as shown in Fig. B2 (a). 8 996.9 (443 1) Known
The reaction force at the support 9 1040.5 (4624) Node H
near the jacking end is 50.1 kips (222.8
10 996.0 (4427) Known
kN) due to beam self-weight. The reac-
tion force due to deck weight on the II 248.7 (1105) Node A
two-span continuous beams is 45.8 12 354.7 (1576) NodeG
kips (203 .3 kN). Thus, the total reac- 13 95.9 (426) Known
tion force at the support near the jack-
14 15.0 (67) Known
ing end is R = 95.9 kips (426.1 kN).
15 -181.1 (-805)(Tension) Node B
16 -301.2 (-1339)(Tension) NodeH
Draw Strut-and-Tie Model and
Determine Member Forces
Step 1 - Calculate force resultant At web= 0.5 (3.419 + 3.125) (30.5) The middle tendon force:
at end of general zone (8) = 798.4 kips (3548 kN)
pZ = Force in web = 798.4
When considering possible strut- At bottom flange= 0.5 (3.125 + 3.004) u cosa 2 cos 3.19°
and-tie model of the general zone, it is (12.5) (26) = 996.0 kips (4427 kN)
= 799.6 kips (3554 kN)
easier to start at the end of the general The location of the resultant forces
zone. The top and bottom flanges of are as following: The bottom tendon force:
the beam are transferred into equiva-
Ywp = 12.5 + 30.5 + 5.53 p 3 = Force in bottom flange = 996.0
lent rectangular shapes:
= 48.53 in. (1233 mrn) " cosa 3 cos2.44°
Equivalent top flange height:
Yweb = 12.5 + 15.48 = 27.98 in. (711 mrn) = 996.0 kips (4431 kN)
h = + 2x(0.5x6x6)
8 = 6.29 in. (160 mm)
Ybotrom
t 20-8 Resultant shear force could be as-
The calculated resultant forces are signed based on the shear stress distri-
= 11.0 in. (279.4 mm)
shown in Fig. B2(a). Once all the re- bution , but it is simp ler and suffi-
Equivalent bottom flange height: sultants and their locations on the ciently accurate to assign all of the
boundary of the general zone are de- shear force to the web. That is:
h = + 2x(0.5x9x9)
8 termined, the final "desti nations" of Shear force:
b 26-8
the post-tensioning force paths are
12.5 in. (317 .5 mrn) PuI sma
· p2 ·
V 1 + u sma 2 +
= =
determined. The force resultants in
The height of the web: · the top flange, web, and bottom (98.5 I 12)(w1 + w2 ) - R
flange are balanced by the top ten- = 58.6 kips (260.0 kN)
hw = 54.0- h1 - hb = 30.5 in. (774.7 mrn)
don, middle tendon, and the bottom
The stress at the bottom of the tendon, respectively. where, w 1 and w2 are beam self-weight
equivalent top flange is: and deck weight, respectively.
If the compressive stress directly
3.004 + (3.525- 3.004)(12.5 + 30.5)/54 under the anchor plate, whose size is
= 3.419 ksi (23.57 MPa) the diameter of the spiral plus the Step 2 - Select location of
The stress at the top of the equiva- cover in this example, is assumed to local zone node
lent bottom flange is: be uniformly distributed, the three ten- As discussed earlier, the width of
don forces can be re-calculated to the anchor plate a = 12.0 in. (305
3.004 + (3.525- 3.004)(12.5)/54
maintain equilibrium. mm). The closer to the anchors the
= 3.125 ksi (21.55 MPa)
The top tendon force: local zone nodes are located, the
Resultant forces at the end of the smaller the bursting force. In this ex-
general zone are as follows: P' = Force in top flange = 763 ample, the local zone nodes are se-
At top flange= 0.5 (3.525 + 3.419) " cosa 1 cos3.94a lected at: (a/2) = 6.0 in. (152 mm)
(11) (20) = 763.8 kips (3395 kN) = 765.6 kips (3403 kN) ahead of the anchor bearing plates.

72 PCI JOURNAL
Step 3 - Select location of forces except Node E. Therefore, this longitudin al, then the width of the
bursting tie node can be checked to verify the bearing area at the local zone - gen-
For the bursting reinforcement, a model accuracy. eral zone interface is:
uniform arrangement in the general LFx = F6x -F7x = 0 14 75
zone is envisioned. To be on the con- (ok) 12 + 2 · = 21.8 in.> 19.55 in.
l_Fy = F6y +F7y +Fj 6 = 0 3 (554 mm > 497 mm)
servative side, however, the calc ul a-
tion will be based on the uniformly Similar steps can be used to draw a
Therefore, the width of the bearing
distributed reinforcement for a dis- strut-and-tie model in the transverse
area at the interface is 19.55 in. (497
tance of beam height. direction. Then the transverse bursting
mm).
Assume the right edge of the bearing forces can also be calculated.
The height of the bearing area as-
plate to the end face of the beam is 9 in.
suming one to three distribution is:
(229 mm). The beam height is
Check Compression Stresses
54 in. (1372 mrn). Then, the location of 14 75
Compression stresses may be criti- (6 + 2 X 14 + 6) + 2 ·
the bursting tie is taken as 9 + (54- 9)/2 3
= 31.5 in. (800 mrn) away from the end cal immediately ahead of the anchor
= 49.83 in. (1266 mm)
face of the beam. The final calculated plates (bearing pressure), immediately
reinforcement spacing within the range outside the locally confined region The bearing stress at the local zone -
of (54- 9) = 45 in. (1143 mrn) will be (i .e., local zone - general zone inter- general zone interface is, therefore:
used for the entire general zone. face), and the node compression strut
capacity perpendicular to the tendon Pr 2.627 ksi (18 .11 MPa)
path. However, the bearing pressure 19.55x49.83
Step 4 - Draw strut-and-tie model and node compression strut capacity which should be less than (AASHTO
and calculate member force are considered the local zone check. LRFD Article 5.10.9.3.1):
Based on the above steps, the strut- They are guaranteed by the anchorage
0.6¢/,; and¢= 0.8
and-tie model can be built as shown in device supplier through standard ac-
Fig. B2(b). As shown in Fig. B2(b) , ceptance test procedures. Thus, the required concrete strength
there are eight named nodes (i.e. , A From Fig. B2, the maximum com- at the time of post-tensioning/;; :
through H) and sixteen members (i.e., pression stress at the boundary is
2.627 = 5. 47 3 ks1. (3 7.7 MPa)
1 through 16) in the strut-and-tie 3.525 ksi (24.30 MPa). Therefore, the f ci ~ 0.6x0.8
l

model. The forces in members 1, 4, 5, minimum required concrete strength at


8, 10, 13, and 14 can be observed from the time of post-tensioning is In conclusion, the concrete strength
the model directly. The other member (AASHTO LRFD Article 5.10.9.3.1): u:i) at time of post-tensioning must
forces can be calculated from node be greater than 6.295 ksi (43.4 MPa).
3 525
force equilibrium condition. J;; = · = 6.295 ksi (43.4 MPa)
IfF; is the force in the ith member, 0.7¢
Select Bursting Reinforcement
then for example: F 1 = 766 kips For the local zone - general zone in- Table B2 lists the tensile bursting
(3403 kN). terface capacity, the following simpli- forces in the anchorage zone, the corre-
From Node C equilibrium condition: fied method is used. From Fig. B1 , the sponding reinforcement requirements,
115 kips (67 kN) .Y anchor plate size is 12 x 12 in. (305 x
305 mm). From hardware supplier
and the reinforcing bars selected.
When selecting the reinforcement
T C 763.8 kips l___!. (DSI), the depth of the local zone is required, the following data were
/~ (3395kN) 14.75 in. (375 mrn) . The physical width used: the yield strength = 60 ksi (414
F3 at the end of the local zone is therefore: MPa); the strength reduction factor ¢
8 + (20 - 8) 78.7- (14.75 -11.8) = 1.0; transverse bursting length =
F3x = 763.8 kips (3395 kN)
78.7 2(31.5) = 63 .0 in . (1600 mm) ; web
F 3y = 15.0 kips (67 kN) bursting length in thin direction =
= 19.55 in. (497 mm)
2(10) = 20 in. (508 mm); flange burst-
F3 = ~( F3: + F3~ ) = 764 kips (3395 kN) S"uppose the slope of the compres- ing length in thin direction = 2(13) =
sive strut is one transverse to three 26 in. (660 mrn).
Note that at Node C, the 15 kips (67
kN) load represents the beam self-
weight and deck weight for the gen- Table B2. Genera l zon e reinforcement.
eral zone. The slope of the Member 3 Force Reinforcement, sq in. (mm 2)
can also be determined from Node C's f-----
Action kips (kN) Required Selected
force equi librium condition. [- - +--
Transverse bursting 30 1.2 ( 1339) 5.02 (3239) 9.30 (6000)(#5@ 4 in. )
Similarly, all member forces can be
determined as shown in Table B 1. Burst ing in thin 214.8 (9~ 3.58 (23 10) 1 3.72 (2400)(#5@ 4 in. )
direction of web
From Table B 1, it can be found that
Flange bursting 11 2.2 (499) 1.87 ( 1206) 1 2. 17 ( 1400)(#5 @ 4 in.)
all nodes are used to calculate member I

March-April 1999 73

Potrebbero piacerti anche