B. Labor
B-1 Foreman M/D 1,200.00
B-2 Technician M/D 1,000.00
B-3 Skilled Worker M/D 703.00
B-4 Common Labor M/D 542.00
Note: Foreman & Technician are Manila base and Skilled worker
and Common labor are locally recruited.
E. Equipment/Tool
E-1 Disc Sander 50 210.00
E-2 Concrete Breaker 3,877.00
E-3 Saw Cutter 290.00
E-4 Injection Pump 150.00
E-5 Generator 2KVA 104.00
E-6 Generator 15KVA 113.00
E-7 Air Compressor 0.4KW 125.00
E-8 High Pressure Water Blaster 380.00
E-9 Melting Kettle 400 Lit. 250.00
E-10 Grout Mixer 200lit 374.00
E-11 Vibrator 45mm 101.00
E-12 Welder 300A 74.00
E-13 Concrete Drilling Machine 2,182.00
E-14 Vibration Roller 3,082.00
E-15 Compactor 187.00
E-16 Sand Blast Machine 300.00
E-17 Hydraulic Jack 75 ton 2,666.00
E-18 Dial Gauge 75.00
E-19 Torque Wrench 122.00
E-20 Pile Hammer 4,427.00