Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
B. Bowonder
To cite this article: B. Bowonder (1987) An analysis of the Bhopal accident, Project Appraisal, 2:3,
157-168
the occurence of these errors are the corporate level such as the Mexico gas explosion, Bhopal and Chernobyl.
failure of safety management systems and pro- It has become highly inperative to institutionalize
industrial risk management practices..
cedures. If accidents are to be reduced this needs The Bhopal accident was the worst industrial disaster
maximum attention. in terms of fatalities (Bowonder ,Kasperson and Kasper-
son 1985). This paper is an attempt to derive lessons for
industrial risk managment based on the issues brought to
light by Bhopal. It is imperative to analyze the causes of
Key words: Bhopal; hazard management; environmental im- the accident so as to derive lessons for managers and
pact decision makers.
It is essential that decision makers perceive and
estimate the hazards arising out of a project at the project
formulation phase. Hazard management has to start at
the site selection and project feasibility analysis phase
itself such a comprehensive approach is the only way to
have cheaper and safer plants.
Thinking about the hazards after the commissioning of
the project is likely to minimize the extent of hazards
whereas the anticipate-and-prevent approach is likely to
provide minimum cost options, if initiated at the project
formulation phase itself.
Bhopal accident
First a very brief description of the Bhopal accident is
presented. Bhopal accident was the spillage of a very
toxic substance - methyl isocyanate (MIC) - to the
atmosphere in large quantities from a pesticide plant. It
was a result of poor hazard management, poor safety
management practice, poor use of early warning system,
poor perception of the risk involved and so on.
Detailed accounts of Bhopal accident and its consequ-
ences have been published elsewhere (Bowonder 1985,
B Bowonder is at the United Nations Economic and Social Bowonder Kasperson and Kasperson 1985, Degrazia
Commission for Asia and the Pacific [ESCAP], Asian and 1985, Gladwin 1985, Kletz 1985, Morehouse and Sub-
Pacific Centre for Transfer of Technology [APCTT], 49, Palace ramanian 1986, Technica 1985). A lot of new facts have
Road, Bangalore 560 052, INDIA. been brought to light subsequently.
The views and interpretations given in this paper are the
authors and not attributed to the United Nations Organiza- Bhopal is the capital of a state, Madhya Pradesh,
tion with which the author is affiliated. which is essentially underdeveloped. This state provided
The author would like to thank Dr M Nawaz Sharif, a number of incentives to start industries, such as
Director, APCTT for providing the support, and John backward area investment allowance. Union Carbide
Withers, University of Technology, Loughborough, England, India Ltd set up a unit at Bhopal to formulate a range of
for the valuable comments on the draft manuscript. pesticides and herbicides derived from a carbaryl base.
Project Appraisal September I987 0268-8867/87/030157-12 US$03.00 0 Beech Tree Publishing 157
Bhopal accident
isocyanate and alpha naphthol react to produce carbaryl
pesticides. Until 1979, both the major chemicals were
imported. Only in 1979, UCIL started its own manaufac-
turing facility at Bhopal.
The plant was located adjacent to residential areas and
was only twohhree kilometers from the Bhopal Railway
statiodbus stand (Figure 1). When UCIL applied for a
licence to manufacture MIC, the Administrator of the
city suggested that the unit should be shifted outside the
city, but this was not accepted by the Government and
UCIL was given licence to manufacture MIC in the
existing premises.
Bhopal was a city which had expanded at the rate of
75% during the 1971-1981 period and, because of this
mushrooming urban growth, a large number of squatter
settlements had come close to the factory. During the
1983-1984 period, the local government gave these
0
-
;::;:::
IKn 't
a A S AWECTED ARE*
residents legal sanction to stay in their localities.
The new manufacturing facility was sanctioned in
1979, and UCIL was licenced to produce 5000 tonnes of
...... carbaryl based pesticides. The production of MIC
FIG. I . EXTENT OF MIC'DI'SPERSAL achieved in 1981, 1982, 1983 was 2704 tonnes, 2308
tonnes and 1657 tonnes respectively. The demand for the
Downloaded by [113.210.106.241] at 23:24 15 December 2017
Union Carbide India Ltd (UCIL) is a subsidiary of pesticide was reducing because of the import of new
Union Carbide Corporation (UCC), USA which has products like synthetic pyrethroids. The sales of MIC
50.9% of the stock holdings. Whilst in the early years of based pesticides were only 1500 tonnes in 1983 compared
the firm, American management staff occupied key to 2211 tonnes in 1982.
positions, they have been progressively phased out and at The unit was not making a profit and many technical
the time of the Bhopal accident all the management people left to take up new positions elsewhere. One of
positions in the company were held by Indian personnel the major consequences of loss making was assigning less
(until 1981 the Managing Director was a US national). importance to safety and maintenance practices.
This, nowadays, is a common situation for the overseas A brief description of the manufacturing facility will
operations of multinational corporations. UCC has a be given here so that the sequence of events becomes
reputation of having a relatively centralized decision clear. MIC is stored in three underground tanks made of
making style (Morehouse and Subramaniam 1986). stainless steel. The tanks have to be kept refrigerated so
In the manufacturing process at Bhopal, methyl that the temperature of storage is kept close to 0C and
p e r ticido unil
from
I
'1 c
Ir-
I iI
4.
Ouench filter
Phosgene strlpplngstlll
filter pmsure or vmt 8crubb.r
safety vdve liner
(at ground iewl) Concrete cover
KEY: 7. Nitmgm header lsolotion 13.Supturedisk RWH-relief valvr vent hrader
I , Intereconnccth RVVH valw I 4 . PIC lsolatlon valw PVH- proms volve vmt header
isolation volve 8 .RVV isolation valve I 5. PI isolation valve VGS- vent gas scrubber
2. Interconnection PVH isolatron 9 . w Meedrr~ valve I6.RVVHlsolotlon voIW p ~ - f l m e v e nheader
t
Downloaded by [113.210.106.241] at 23:24 15 December 2017
been provided the whole sequence of events leading to 11.50 pm MIC operator sees yellow drip from
entry of water to the MIC tank would not have occurred. RVVH
The investigations conducted in India indicated that 12.00 am Supervisor ordered stopping of
UCC had given permission to UCIL to carry out the washing operations
plant modifications for interconnecting PVH and RVVH 12.15 am Tea break for operator
in May 1984 (Morehouse and Subramanian 1986). 12.20 am Attempt to start the vent gas scrubber
Pump
12.25 am Plant superintendent, on being in-
Description of events formed about the leak, arrives at the
spot
The refrigeration unit was decommissioned in June 1984. 12.30 am Pressure gauge reading over range.
The pressure indicator control and level indicator of the Concrete tanks get very hot
MIC tank and the temperature indicator alarm were all 12.40 am MIC operator reports escape of MIC
faulty for a long time. The operators never gave attention through the vent line at 33 meters
to these instrument readings. 01.00 am Toxic Gas Alarm was alerted, but
On 22 October 1984 the MIC plant was closed for shut switched off. Police official on patrol
down. On 25 November 1984 the flare tower was reports to police control room that
disconnected and the jumper l i e connecting R W H and something had gone wrong at UCIL
PVH was opened. Actual instructions for washing the 01.15 am Police control room informs the city
quench filter and relief valve lines were given on the police chief
morning of 2 December 1984. The sequence of events 01.30 am UCIL staff when telephoned report
that followed are given briefly (Union Carbide Corp, that everything is normal
1985, Technica 1985). 01.45 am Additional District Magistrate informs
Downloaded by [113.210.106.241] at 23:24 15 December 2017
09.15 pm Washing of relief valve lines without the Works Manager of UCIL at his
isolation residence about the leak
09.30 pm 02.00 am to The safety valve reseated, but 40 to 45
Operator notices the lines are blocked
10.00 pm 02.30 am tonnes of MIC escaped before that.
MIC Plant supervisor orders washing
to continue Public siren was restarted at full blast.
10.20 pm Pressure in the tank 610 is 2 Psi. 610 MIC vapours started affecting people in the vicinity, and
failed to get pressurized a large number of people started running out of the
10.45 pm Shift changed houses. On the morning of 3 December, Hamidia
10.45 pm Water entry from RVVH to PVH and hospital had about 12000 persons. Again on the night of
the tank 3/4 December, MIC from the atmosphere recondensed
11.00 pm Operator logs pressure in tank 610 as and more people were affected. On the 4 December 1984
10 Psi Hamidia Hospital had to handle about 55000 people,
11.30 pm to, First leak of MIC detected. Plant whereas the hospital had capacity for only 750 people
11.45 pm sipervisor notified about the high (Khandekar and Dubey 1984).
pressure and MIC leak People staying in the vicinity of the firm were severely
R VVH
W T A
1 I
n
4
1
3
I
MIC TANK
3.RUPTURE DISC
4.SAFETY VALVE P V H PROCESS VENT HEADER
RVVH RELIEF VALVE VENT HEADER ( Sourco: Foro, 198s)
Monomethylamine was also produced. all levels of management. If such regular practices had
The wide variety of symptoms observed at Bhopal has been in force at Bhopal, many of the consequences of
been due to the exposure of a large number of toxic plant deficiencies and operator inadequacies would have
substances in varying concentrations at different loca- been made. evident and perhaps corrective action may
tions. Even after three days, the air in the vicinity of the have followed.
plant had fairly high levels of cyanide concentration Given below is a detailed analysis of the errors which
(Appen, 1985). On the night of December 3/4 many caused the accident to be so severe, as well as the type of
persons were affected and, on the night of the 4th, the failure (technical, operator, management or governmen-
vapours got recondensed and some more people were tal (regulatory) as the case may be.
seriously affected.
Hardware errors
Prime cause
The prime cause of the accident and poor mitigation Hardware errors are the ones relating to equipment ,
response can be summarised as follows: Flushing out the design materials of construction, levels of instrumenta-
MIC pipeline by washing should be a safe routine tion, defective fabrication, transient conditions, un-
maintenance operation, but it led to the admission of diagnosed hazard conditions and so on. Though some of
water into the MIC tank 610 because of these are human related these are the first order errors: if
uncorrected they can lead to the next order of failures. A
0 partly leaking isolation valves summary of the hardware errors which occurred at
0 omission to insert a slip plate Bhopal and whether each of these is a management, a
0 a remotely operated valve being open when it should technical or operator failure is indicated in Table 1.
have been shut, and 0 The scrubber was insufficient (Morehouse and Sub-
failure
ramaniam 1986) to handle such large scale release of Reduction in operating and maintenance staff (Degra-
MIC. At the design stage the rates of relP case were zia 1985) in the MIC plant, and use of a non trained
underestimated. superintendent (Morehouse and Subramaniam 1986)
Such factors as no automatic sensors, no manual for the MIC plant are operator related errors caused
mechanism for switching on the scrubber, no on line by poor safety concerns at the corporate level.
monitor for MIC tanks are examples of low safety Failure of the shift operator to communicate infor-
levels and low levels of instrumentation (Bowonder mation Qnrapid pressure build up at the MIC facility,
1985). not following the safety precautions while washing the
The water curtain for neutralizing MIC could only MIC pipelines, failure to inform Works Manager as
reach 10 meters height whereas the MIC escaped at 30 soon as the MIC leak started, are errors caused by
meters height indicating design deficiency (Degrazia poor hazard management procedures and absence of
1985). hazard analysis in the facility.
Use of iron for pipelines, plant modification connect- Not confirming the leak when the police officials
ing RVVH and PVH, disconnecting flare tower, not enquired about the MIC leak at about 12.30 am.
keeping the vent gas scrubber in active mode, (when the first effects outside the plant were noticed),
switching off the refrigeration plant for cooling the not operating the warning siren until the MIC release
MIC plant etc are examples of undiagnosed hazard became severe, switching off the safety siren (kept for
conditions. warning the public living in the vicinity) immediately
The pressure indicator and temperature indicator of after starting it and failure to use the third MIC tank
the MIC tank was not working. Normally this can be a to release the pressure were due to lack of formaliza-
technical failure, but in MIC plant most of the tion of safety procedures. In hazardous facilities
instruments were working properly because of poor absence of formalization leads to random or ad hoc
safety concerns of the management (Degrazia 1985). response by operators.
Non availability of sufficient number of gas masks, is a
hardware error caused by poor safety concerns at the If the errors are analyzed, it can be seen that the only
corporate level. pure operator failure is the failure of the MIC plant
operator to recognize the seriousness of the leak. This
The basic causes for these errors are analyzed in a again was due to poor awareness, lack of openness in
subsequent section. matters regarding safety and hazards, and absence of
emergency response procedures for operators.
concerns are: 0 the line of treatment for MIC exDosure was ..__ ~ not
disclosed. Most of the informatio; on MIC was
no emergency plan at the plant; proprietary and open literature gave very little toxico-
ad hoc response by operators because of no specific logical information on MIC (Dagani 1985, Ten Berge
instructions on how to handle emergency; 1985).
no hazard analysis before plant modification;
in the West Virginia plant of Union Carbide Corpora- Communication related errors can be severe in hazardous
tion, USA a safety audit conducted in July 1984 chemical plants because firms dealing with such facilities
indicated that a runaway reaction can occur in the are generally very secretive and not open in approach.
MIC tank. (This information was not communicated The causes of such errors are discussed subsequently.
to UCIL, though UCC took corrective action by
September 1984 and informed USEPA (US Congress System related errors
1985) about the implementation of corrective
measures; System related errors are the next level of errors such as
information on differential sensitivity of MIC towards poor siting procedures, absence of risk assessment, poor
children and elderly people compared to the rest of the implementation of safety audit, large scale storage of
population, was not communicated to public health or toxics, p y r emergency evacuation procedures and lack
civil authorities to hasten emergency evacuation. of coordination of emergency, and mecdical care. The
UCC considered phosgene as more toxic and did not major system related errors at Bhopal are listed in Table
inform public about the precautions. MIC is five times 4.
more toxic than phosgene: the threshold limit value of At the corporate level, the major errors (management
phosgene is 0.1 ppm whereas that of MIC is 0.02. This failure) were:
was known in toxicological literature well before the
0 Not evaluating the safety levels needed for a toxic
accident (Bowonder, Kasperson and Kasperson
1985). There was one publication on toxicity of MIC
facility close to human settlements;
0 Not improving safety systems even after the audits
published in German: though this was known to UCC,
regulatory agencies in India did not have this infor- (Bhushan and Subramaniam 1985) indicating poor
mation (US Congress 1985). safety;
0 Poor emphasis of systems safety and safety pro-
precautions to be taken for minimizing the effect of
MIC were not dsiclosed; cedures. Emphasis was on component safety;
0 Decision to store MIC in large scale, while laree scale
v
Even after six accidents (three were toxic spills) safety Not having an emergency plan for the city;
was not improved (Bowonder 1985). In hazardous Information on wind movement was not disseminated
facilities near misses or minor accidents should be and this caused some people to move in the direction
thoroughly investigated (Kletz 1985a, Lees 1982, of the MIC cloud movement;
Lees 1985); Toxicity of MIC was not independently assessed at the
Carrying out plant modifications (Technica 1985) in project approval phase: only the information provided
hazardous facilities without hazard and operability by the firm was used;
studies; Delay in providing correct toxicological information
Decision to reduce operating and maintenance staff in on line of treatment for MIC exposed people;
the MIC plant and control room; No action was initiated on press reports which
Neglecting the warning of the factory inspector in indicated (in 1982 and in 1984) that safety was poor at
1981 that washing MIC lines without slip blinds can the UCIL plant. These provided sufficient early
cause serious accidents; warnings or near misses of a catastrophe. Nothing
Reliance on inexperienced operators; substantial was done to improve safety either by
Transfer of the specially trained person to a non MIC government or by corporate management (Kletz
facility; 1985);
Though the UCC Headquarters had earlier sent a telex Similarly no action was taken on the enquiry report of
(Ramaseshan 1984, 1985) to Bhopal asking for a the earlier accident;
cyanide antidote to be given, when the seriousness of Large scale storage of MIC is not permitted in a
the situation was known, they retracted from this number of countries and this itself is a good indication
position; by the regulatory agencies to monitor the safety
There was serious confusion about the nature of the systems involved in storage.
Not having emergency rehearsals to cheik safety Permitting settlements to come close to the firm and
inadequacies. regularizing these settlements;
At the government level (regulatory and administration Decisions not to shift the factory when it applied for a
problems) some of the major errors were: license for manufacturing MIC based pesticides.
Management HI, H4, H5, H6, H7, H9, H11, 01, 1 Poor safety concerns at the corporate level
failure 06, 114, S1, S2, S3, S4, S7, S17,
(65) S20, S21, S24
H2, 110, 02, 03, 04, 05, 06, 07, 08, 2 .Nan specification of procedures/lack of
013, S24,27 formalization
H7, H8, 115, 116, S5, S6, S7, S12 3 Poor risk assessment practices
S15, S16
14, S13, S16, S21, S22, S26 4 Similar procedures/methods for hazardous
and non hazardous facilities
15, 16, K7, 19, 111, 113, S19, 118 5, Failure to be open i n approach
H3, H12, H13, S15, H16, S23, S27 6 Failure to equip the plant for required safety
11, S6, S23, H I 5 7 Failure to anticipate the catastrophic
potential
company. In the Bhopal case the UCC Headquarters did are due to human error. The analysis of the Bhopal
not exercise this extra responsibility towards the hazard- accident, presented here corroborates the conclusion of
ous facility and treated it as if it were a genial Batston (1986) that organizational or corporate level
non-hazardous facility. failures are the most critical ones that need attention if
accidents are to be avoided.
The most important prerequisite for accident preven-
Analysis of failure tion is the top manangement commitment to safety.
Accident prevention needs not to be treated as an
The four levels of errors given in Tables 1,2,3 and 4 are expensive add-on facility but it has to be an integral part
reclassified in terms of the four causes of these errors of management and organizational objectives (Batstone
namely technical failure, operator failure, management 1987). Regulatory agencies and insurance agencies can
(corporate) failure and government failure. Table 5 provide a basic framework for the safety and support
presents the analysis. Technical failures, accounted for systems needed, but the basic institutionalization of
21 errors, 12 were caused by operator failures, 65 were safety procedures should be at the corporate level.
the result of management failures and 28 were due to Another major implication of the Bhopal accident is
government failures (regulatory failure). that, at the project formulation phase itself, hazard
This clearly supports the view that all human initiated assessment has to be carried out. The safety levels that
disasters ultimately can be traced back to deficiencies in are to be adopted in any hazardous facility have to be
the management of the systems at the corporate level. determined in terms of population at risk.
Yet in major accident assessment and prevention, these When hazardous facilities are to be built in developing
deficiencies are often overlooked or very inadequately countries, the levels of safety to be achieved must be
addressed (Batstone, 1986). higher and not lower than that planned for developed
The basic causes of these errors are given in Table 5 , countries, since, in developing countries,
Downloaded by [113.210.106.241] at 23:24 15 December 2017
of them may be considered to be unnecessary by the operability studies normally take place late in design
operator has to be made statutory. The Bhopal (Kletz 1985a). If we are to build simpler, cheaper and
accident would have been completely averted, if the' safer plants, then we need to allow time in the early
reasons for non-pressurization of the MIC tanks that stages of design for a critical review and evaluation of
occurred five days before the accident were thorough-r alternatives before the detailed engineering design starts
ly investigated before attempting repressurization (Kletz 1985a).
again. It is difficult to deal with inconceivable events because
starting from the project formulation stage itself the they usually depend by inference on some factors which
project proposers have to be open in approach are not readily included in the models and systems used
(Kunreuther and Linneroth 1984) with respect to the for design of industrial products with respect to normal
nature of hazards and precautions. In low probability performance (Ostberg 1982). Perceiving inconceivable
accident systems sharing of information will have a events is a very difficult and complex problem.
positive effect on hazard reduction. At Bhopal if the The probabilities of many unlikely events are hard to
corporation had been open about the hazardous nature assess accurately even for experts who devote their lives
of MIC to the government workers, public in the to the task (Fischhoff 1980). Once people's minds are
vicinity and public health authorities, the number of made up, it is hard to change them since experts tend to
people affected by the accident would have been much overvalue their knowledge component (Fischhoff 1980).
lower. Hazard assessments have to be done by a team of experts
carrying out detailed rehearsal of emergency on the outside the project proposing agency, that is by accept-
hazardous facilities with the active involvement of all able third parties well versed in this task.
levels of management, at regular intervals must be In order to stimulate preparedness for possibly surpris-
made statutory. Inadequacies of systems should be ing alternatives in the development of technology, the
evaluated during such rehearsals and corrective action proper thing to do should be to encourage open
Downloaded by [113.210.106.241] at 23:24 15 December 2017
ing Future Bhopals", Environment, 27, (71, pages 6-16, gineering, 10, pages 65-81, 1985.
1985. W Morehouse and A Subramaniam, The Bhopal Tragedy
R Dagani, "Date on MIC's toxicity are scant: leave much Council on International and Public Affairs, (New York,
to be learned", Chemical & Engineering News, 63, (6). 1986).
pages 37-40, 1985. G Ostberg, "Evaluation of a design for inconceivable
A Degrazia, A Cloud Over Bhopal, (Popular Prakashan, event occurence," Materials and Design, 5, pages
Bombay 1985). 88-93, 1982.
Delhi Science Forum, "Bhopal gas tragedy", Social D H Ott, "Bhopal and the Law," Third World Quarterly, 7,
Scientist, 13, (140), pages 1-36, 1985. pages 648-660, 1985.
I Fera, "Not sabotage", Illustrated Weekly of India. 104, H J Otway and R Misenta, "Some human performance
(17). pages 27-33, 1985. paradoxes of nuclear operations", futures, 18, pages
B Fischhoff, Approaches to Acceptable Risk, NUREGICR- 340-357, 1980.
1614,ORNL/SUB-7656/1 (Oak Ridge National Lab, Oak C E Perrow, Normal Accidents, (Basic Books, New York,
Ridge, 1985). 1984).
T N Gladwin, "The Bhopal tragedy", NYU Business, 5, R Ramaseshan, "Government responsibility for Bhopal
(I), pages 17-21, 1985. gas tragedy", Economics and Political Weekly, 19,
S Khandekar and S Dubey, "City of death", India Today, pages 2109-21 11, 1984.
9, (241, pages 4-24, 1984. R Ramaseshan, "Bhopal gas tragedy", Economics and
P Kleindorfer and H Kunreuther, Insuring and Managing Political Weekly, 20, pages 56-57, 1985.
Hazardous Risks (IIASA Laxenburg, 1986). Technica, Bhopal: An Analysis of the Contributory
T A Kletz, "Inherently safer plants", Plant Operations Causes, (Technica, London, 1985).
Progress, 4, pages 164-167, 1985. W F Ten Berge, "The toxicity of methylisocyanate for
T A Kletz, What Went Wrong (Gulf Publishing, Houston, rats", Journal of Hazardous Materials, 12, pages
1985). 309-31 1, 1985.
H Kunreuther and J Linnerooth, "Low probability acci-, Union Carbide Corporation, Bhopal Methyl Isocyanate
Downloaded by [113.210.106.241] at 23:24 15 December 2017
dents", Risk Analysis, 4, pages 143-152, 1984. Incident: Investigation Report, (UCC, Danburg, March
P Lagadec, Major Technological Risk (Pergamon Press, 1985).
New York, 1982). US Congress, House Committee o n Energy and Com-
F P Lees, "The hazard warning structure of major merce, Subcommittee on Health and Environment
hazards", Transactions of the Institute of Chemical Hazardous Air Pollutants, December 14, 1984, 98th
Engineering, 60, pages 21 1-221, 1982. Congress, 2nd Session USG PO, Washington DC, No
F P Lees, "Hazard warning structure", Reliability En- 192, 1985.