REV.0 Date: 09.06.12
GC10109300/MS/001
S No SECTION PAGE
01 Introduction 05
Al Fowriya Trading &
Project Quality Plan Contracting
02 Project Scope 05
03 Project Quality Statement 06
04 Revision Status / Amendments 06
05 Definitions and Terminology 07 08
06 Quality Policy, Quality System & Quality Strategy 09 13
6.1 Quality Policy Concept
6.1.1 Quality Policy
6.1.2 Quality System
6.1.3 Structure of Quality management system
documentation
6.1.4 Hierarchy of the documentation
6.1.5 Quality Management System manual
6.1.6 Quality Process & procedure manual
6.1.7 Project Quality Plan
6.1.8 Other Quality document
6.1.9 Quality Strategy
6.2 Planning
6.3 Control
6.4 Verifications
07 Quality Management in Construction and Reporting. 14 23
7.1 Management Responsibility
7.2 Organization set up for the Project
7.3 Job Responsibility matrix.
7.4 Responsibilities & Authorities
7.5 Functions of QA / QC system
7.6 Quality Management Reports
7.7 Management Reviews
7.8 Monthly Progress Report
08 Progress Control 24 25
8.1 Construction Work Program
8.2 Progress Control
Al Fowriya Trading &
Project Quality Plan Contracting
1.0 Introduction:
and meeting the project schedule through a well designed Quality Management
system. The Quality Management system shall focus on providing improved
control on processes and practices, thus enhancing customer satisfaction
through its effective implementation
Heavy duty pre-cast block paving for new security staff car-park and the
Access to this car-park.
Hard landscaping around the buildings, new traffic islands, new round
about, sidewalks and modifications to existing paved areas.
Soft landscaping, to suit the road modifications, including relocation of
Existing trees.
Paved pedestrian walkway, with protection railing, from the bus bay
Extended beyond the new roundabout within the Refinery fence.
All services works, including tie-ins, pertaining to the above buildings and
Site development, including plumbing, drainage, fire-detection system, fire
Management system and other specialist systems, equipments etc.
Calibration
All the operations for the purpose of determining the values of the errors of
measuring instruments, material measures, and measurement standards.
Controlled Document
An original numbered copy of a document for which amendments will be
Automatically advised.
Corrective Action
An activity the intention of which is to return a non-conforming item or action to a
Stat or conformity. It also covers action taken to prevent further recurrences of
Non-conformity.
Disposition
An action to be taken concerning material, components or products about which a
Decision has been made.
Document
Any written or printed manual, procedure or form that is part of the quality system.
The term includes documents and data that can be read by people or machines.
Inspection
The careful examination, measurement and testing of the characteristics of
Products and services to ensure they meet regulatory and contractual
requirements.
Procedure
A document that specifies, as applicable, the purpose and scope of an activity; what shall
be done and by whom; when, where and how it shall be done; what materials, equipment,
and documentations shall be used; and how it is all controlled.
Product
Material, part, item, component, assembly, sub-assembly structure, plant equipment,
or finished project identified in or described in any standard or specification and
production or obtained as a result of some manufacturing or construction operation
or process.
Quality Assurance
All those planned and systematic actions necessary to provide confidence that
products or services will satisfy given requirements.
Quality Audit
Al Fowriya Trading &
Project Quality Plan Contracting
Remedial Action
An action to be taken concerning material, components or products about which a
decision has been made.
Repair
The process of restoring a non conforming characteristic to a condition such that the
item conforms to the original specified requirements, where such a repair or
restoration is acceptable.
Verification
The Quality Policy is communicated and made understood at all level of the
organization through awareness program an display of the Quality Policy boards at
all the Project sites/departments. The Quality Policy shall be reviewed annually for
continual improvement and suitability to the purpose of the division. Taking Quality
Policy as guide, the quality objectives are established in related functions and
monitored in the monthly steering committee meetings and periodic Management
Review meetings. Management review includes review of Quality objectives and
specific policy statements with the view to achieve Quality objectives and meeting
the requirements of the policy statement.
QUALITY POLICY
6.2 Planning
This Project Quality Manual is the document which details the Quality
System to be planned, established, implemented and maintained as part of the
Al Fowriya Trading &
Project Quality Plan Contracting
contract for the road works for the project The Project Quality Plan consists of the
following:
(i) The Project Quality Statement of the company
(ii) Project Specific Details including Organization and System Element Description.
(iii) Inspection and Test Plans (including Construction Process Flowcharts and
Quality Verification Checklists).
Issuing the Project Quality Plan including System Element Descriptions and
Inspection and Test Plans.
7.4.3 QA & QC Manager
The QA & QC Manager for the project has the following responsibilities.
Responsibilities for the planning, implementation, control and maintenance of
the Project Quality Plan.
Guide and instruct others in the essential aspects of quality management.
Liaise that the quality of manufacture and construction satisfies the standards.
Ensure that suitable measuring and testing equipment is available and
calibration of same is monitored regularly.
Verification of inspection and test activities.
Recommend remedial action and re inspect to close out.
Recommend corrective action in case of recurring non-conformance.
Responsible for preparing Monthly Quality Management Report
Interaction with CLIENTs representative, approval of all materials as per CA
in day to day basis.
7.4.4 Execution Engineer
o Monitor, Inspect and Guide the project team in aspect of Safety, Environmental
Compliance w.r.t Contract agreement.
o Carry out regular inspection in line with the requirement of contract agreement and
recommend corrective action in case of recurring non-conformance.
o Responsible for participating in preparation of Monthly Progress Report.
o Interaction with CLIENT regarding all aspect of Safety and Environmental
Compliance plan.
7.4.6 Planning Engineer & Quantity Surveyor
7.4.8 Surveyor
o Report day to day basis to Construction Manager in all aspects of Survey work.
o Responsible for organizing for detailed survey for the Pavement, checking
alignment, Horizontal and vertical profile, Cross section w.r.t to the designed profile.
Any difference shall be reported to Construction.
o Preparation of Cross-section for execution.
o Checking Lines and levels for the execution of works in accordance with drawing
and Contract Agreement.
7.5 Functions of QA / QC System: i) For each major activity of work, method
statement will be prepared indicating the quality checks for incorporated materials
and stage of construction. Detailed description shall be followed in later part of this
section 10. ii) Ensure that equipment and testing instruments are calibrated properly
and adjusted to maintain their accuracy within acceptable limits. iii) Provide day to
day routine checks on materials and finished products. iv) Identify problems and
initiate action, which results in solution. v) Verify implementation of solutions /
corrections.
vi) Report regularly on effectiveness of the system. vii) Tests to be performed jointly
with Contractor and CLIENT at site before start of any activity and after review /
approval of the same activity have to start. viii) All the test reports have to be certified
by the Contractor and CLIENTs Representative. CLIENT has to nominate his
representatives for joint testing during site working hours. In case of non availability
of CLIENTs Representative, tests will be carried out by Contractors QC Engineer
under information in the interest of work. ix) All records of qualifying and routine tests
/ checks will be jointly maintained at the QA/QC MANAGERs office. x) Monthly
Project QA report will be prepared by project QA/QC MANAGER, summarizing the
activities of QA department which is to be submitted to Management. xi) Head of QA
from H.Q shall deploy his representative to carry out internal quality audit to ensure
compliance of quality measures covered hereunder and to make necessary
improvement, if required in quality system. xii) Project Manager / QA & QC In-charge
through his representative at site will point out the non-conformity of standards if any,
to the contractors authorized representative in writing and a copy of the same to be
sent to the General Manager for getting the work done as per quality standard
Al Fowriya Trading &
Project Quality Plan Contracting
8.0 Progress Control This section of the Manual outlines requirements and
procedures for construction scheduling and control of work progress. 8.1
Construction Work Program The Contractor is required to submit a detailed work
program for execution of the works as per the QMS Process S00/PO/P/03 Project
Planning & Budgeting process site. This program must show the following, as a
minimum:
Itemized work activities to be executed, based on the Contracts Bill of Quantities,
indicating start and finish dates and scheduled achievement (progress) each month;
Sequencing of work and activity interdependence;
Calendar day estimates for submittal approvals; and
Calendar dates for achievement of various milestones, and for completion of works
by section and of the project as a whole, within the time periods provided for in the
Contract.
The Contractors program should show the critical path activities, and the float
available for activities outside the critical path. It should preferably be prepared
based on a commercially available project scheduling software package, such as
Microsoft Project / Primavera. The Contractor should also furnish a breakdown of his
anticipated monthly earnings for payments in accordance with the terms and
conditions set forth in the Contract. Based on work program, Contractor shall review
and submit it to the CLIENT as stipulated in the Contractor agreement for his review
and approval. Once approved, the program cannot be modified except with the prior
approval of the CLIENTs Representative. The CLIENT approval of the program
does not relieve the Contractor of his obligation to complete the works or sections of
work within the time periods stipulated in the Contract Agreement.
8.2 Progress control
The Contractor is required to undertake its activities in accordance with the approved
work program. Each month the contractor shall indicate the actual work completed
as compared to work scheduled as per the QMS Process S00/PO/P/04 Project
Monitoring Process site. In the event portions of the work are in danger of being
delayed, or actually are delayed, the contractor is to determine a plan for remedial
action. Various circumstances may justify the changing of contract requirements for
completion of the project on a specific date. Among these circumstances are items
not within the control of the Contractor, such as: changes to contract requirements
(modification of Contract); suspensions of work; delays in providing access; force
majure, etc. Generally, such occurrences will justify a delay in completion if they
affect activities on the critical path of the program. However, each instance must be
Al Fowriya Trading &
Project Quality Plan Contracting
carefully evaluated and fully documented before a decision can be made. The
following are guidelines for controlling work progress:
There should always be a baseline program. If changes to the baseline program are
required, an updated baseline program (baseline program no. 2, etc.) should be
created.
Unauthorized changes to completion milestones should not be allowed, unless
authorized by a contract modification.
Contractor shall monitor the progress of works and should update their completion
percentages and report to CLIENT through Monthly Progress Report.
When actual progress falls behind scheduled progress or when it appears that a
milestone will not be completed on time, the Contractor must identify the reasons for
delay and in conjunction with CLIENT the Contractor make recommendations for
remedial actions.
9.0 Design Quality Plan The Contractor shall engage a Design Consultant for the
preparation of detailed designs and drawings as per the QMS Process S00/DE/P/01
Design Consultants Registration and Pre qualification process &
S00/DE/P/02 Design Consultants Final Selection Process. The Contractors
Design Consultant shall submit the designs and drawings to the Contractor and the
Contractors Design Review Team shall review and check these designs and
drawings before they are forwarded to CLIENT for their comments and approval.
9.1 Design Control This section of the PQP outlines the requirements for the control
and management of the designs which are prepared by the Design Consultant as
per QMS process S00/DE/P03 Design Management Process. All designs and
drawings, including design calculations, shall be prepared by the Contractors
Design Consultant, based on the Employers Requirements in the Contract and in
accordance with applicable design standards and criteria, codes, and methodology.
The drawings shall basically show details of the Works and, where applicable, their
sequence of construction. Prior to carrying out any designs, the Contractor and the
Design Consultant shall arrange to procure all the survey and site data such as
pavement evaluation. Data provided by the Employer as part of the Tender
Documents shall be verified through confirmatory survey and investigations. The
Design Consultant shall also prepare a Design Brief listing out all the design criteria
to be adopted for the designs of the Works. This shall be checked by the
Al Fowriya Trading &
Project Quality Plan Contracting
Contractors Design review team and if in order, this shall be submitted to the
Employer for their comments and concurrence. This Design Brief shall then form the
basis of all designs and drawings of the Works. Drawings shall generally be
prepared by computer aided design methods.
The flow of design documents shall generally be as follows:-
a) The Design Consultant shall prepare all designs and documents and have them
internally checked as per their own design quality control plan. All designs and
drawings shall be signed and dated by the Design Consultants draftsman, designer
and the design checker.
b) These documents shall then be submitted to the Contractor. The Contractors
Design Review team shall check the drawings and calculations for completeness,
correctness, legibility and conformance to the contractual requirements.
c) These designs and drawings shall then be submitted to the Employer in such
number and format as stated in the Contract for their review, comment and approval.
d) The Employer or the Employers Representative shall review and comment on the
Contractors designs and drawings. Regular meetings shall be arranged between the
Employers Representative, Contractor and Design Consultant in order to expedite
the process of review and concurrence of the designs and drawings.
e) The Employers Representative shall signify no comment or comments made
or resubmit and return one copy of the designs and drawings to the Contractor.
f) The notes no comment or comments made will enable the Contractor to
proceed with the construction of the relevant works. The Contractor shall issue these
drawings to the sub-contractor for construction.
g) Where the designs and drawings are marked resubmit, then such documents
shall be amended, modified or prepared again and resubmitted to the Employer. The
process as mentioned above shall be repeated until the Employers Representative
signifies no comment or comments made on these documents.
h) The Contractor shall maintain a detailed register of all designs and drawings and
the status of their submissions and review by the Employer.
9.2 Control of Design Changes This section of the PQP outlines the requirements
for the control and management of the designs Changes as per QMS process
S00/DE/P03 Design Change Management Process.
The Contractor may initiate design changes due to site conditions being different
from that envisaged during preparation of the initial designs, or for other reasons.
The Employers Representative may also order changes as provided for under the
Al Fowriya Trading &
Project Quality Plan Contracting
Contract. The Contractor shall provide Design Consultant with all the necessary
instructions and site information, and the Design Consultant shall prepare the design
changes, together with the design change report, where applicable. The process for
submission, checking and concurrence the design changes by the Design
Consultant, the Contractors Design Review team and the Employers
Representative shall be the same as set out for designs and drawings under item 9.1
above. The Contractor shall keep the sub-contractors informed of any imminent
design changes and shall issue the revised drawings to the sub-contractor for
construction for construction soon after the drawings are concurred by the
Employers Representative. The Contractor shall update the design and drawing
register for the design changes made.
9.3 As-Built Drawings The Contractor is responsible for the preparation and
submission of as-built drawings once the Works are constructed and completed.
During the course of the construction works, the Contractor shall maintain a
complete set of the latest construction drawings marked up with the as-built details.
The as-built details shall be updated on a regular basis until the whole of the Works
are completed. Where revised drawings have been issued to incorporate design
changes, the as-built details shall be transferred and marked up on the revised
drawings. Upon completion of the Works, the Contractor shall prepare as-built
drawings incorporating all the as-built data collected and submit the as-built drawings
to the Employers Representative in the format and number as specified in the
Contract and as required by the Employers Representative. The Employers
Representative shall review these as-built drawings and after reviewing, shall
endorse them as reflecting the as-built details of the Works.
10.0 Quality Control and Assurance in Construction 10.1 Quality Control of
Pavement Works: QA/QC Performing required Mix designing Reject the Source Mix
design approved by Client Getting approval For Mix Design from Client Flow Chart
for Quality Control At Site Responsibility Identification of Source for material RFI for
Sampling and testing Joint Sampling and testing with Client Source approved by
Client N Y N Registering and Use for Construction Y RFI for Work to be excuted
Al Fowriya Trading &
Project Quality Plan Contracting
Joint Inspection with Client Conducting necessary field and laboratory testing Work
Approved by Client Start next stage of work Y Non Conformance by Client N Repair /
Removal / Demolish as per instruction by Client Rework
10.0 Quality Control and Assurance in Construction 10.1 Quality Control of
Pavement Works: QA/QC Performing required Mix designing Reject the Source Mix
design approved by Client Getting approval For Mix Design from Client Flow Chart
for Quality Control At Site Responsibility Identification of Source for material RFI for
Sampling and testing Joint Sampling and testing with Client Source approved by
Client N Y N Registering and Use for Construction Y RFI for Work to be excuted
Joint Inspection with Client Conducting necessary field and laboratory testing Work
Approved by Client Start next stage of work Y Non Conformance by Client N Repair /
Removal / Demolish as per instruction by Client Rework
CONSTRUCTION QUALITY CONTROL:
General: Quality control of materials forms an integral part of the overall construction
and supervision function. Taken properly into account, it provides the link between
the design and the finished works. Testing of construction materials is carried out for
a variety of reasons and purposes including:
Screening Tests (e.g. choosing a borrow source, an aggregate supplier, a
manufacturer / supplier of cement etc.)
Control Tests (e.g. sampling and testing of cement material delivered to site to
confirm adherence to project specifications and to confirm manufacturers Test
Certificate)
Audit Tests to verify independently the reported properties of materials
Trial Mixes (selection of appropriate concrete mix designs, design of bituminous
mixtures etc.)
Acceptance Tests (e.g. testing of cubes cast of produced concrete to confirm that
required strength is achieved and is consistent)
Special testing as may be deemed necessary and prudent
Test shall be carried out quality controls on the materials and work to the frequency
described in subsequent paragraphs. In the absence of clear indications about
method and or frequency of tests for any item, the direction of the CLIENT shall be
followed.
For satisfying himself about the quality of the materials and work, quality control tests
will also be conducted by the Contractor / CLIENT, generally to the frequency set
forth herein under. Additional tests may also be conducted where in the opinion of
the CLIENT need for
such tests exist.
Defective / Inferior quality of work shall be modified in the procedure of work, if found
necessary, as directed by the CLIENT during inspection.
The Contract rate quoted for various items of works by the contractor in the Bill of
Quantities or the lump sum amount tendered will be deemed to be inclusive of all
costs of the quality control test and operations necessary for ensuring quality of the
material and work so as to be in conformity with specification requirement.
All the tests to be conducted at laboratory and at site shall be documented as per the
format specified in the later part of the section. Usually the documentation shall be
maintained in such a fashion that it shall be very easy traceable with a specific RFI
No. mentioned with date in layer chart for Pavement and in turn this shall be filed
with bituminous and Non-bituminous in a separate file / volume as a lot with several
sub lot. For all routine test for Pavements and other works, Borrow areas result,
Bought out items shall be maintained in a separate lot irrespective of section.
10.1.1 Methodology:
SURVEY WORKS
1. Topographical Surveying
The Surveying actively is undertaken for the determination of control points and to
afford sufficient data for the designing of engineering work such as site preparation
and pavements. In the beginning of commencing works on any project, the following
data shall be collected from Customer (Engineer / employer) or prepared by the
Contractor.
1.1.1 Vertical Control Points (VCP) The records of all GPS Points carrying details
shall be obtained from Customer (Engineer / employer). The data shall also include
the Reduced Levels (RLs) of all TBMs fixed with location sketch and adjustment
details from GPS to GPS.
1.1.2. Horizontal Control Points (HCP) The records of all GPS Points (X, Y)
position and intermediate traverse points with location sketches shall be received
from Customer (Engineer / employer). The data shall also include traverse carrying
data and adjustment details from GPS to GPS Point.
1.1.1.3 Proposed Centerline Coordinates The co-ordinates (X, Y) for proposed
centerline of the pavement. at a regular interval as specified by Customer (Engineer /
employer) shall be obtained.
1.2. Survey works Survey actually in any project involves three stages of surveying
necessary to be carried out at project sites. The survey work shall include
Before starting the construction activity, Temporary Bench Marks (TBM), shall be
established on the ground at specified interval. The control pillars shall be
constructed before start of conformation survey for VCPs & HCPs. The pillars shall
be constructed in staggered position within the project premises. The visibility
between proceeding pillar to succeeding pillar shall be maintained. The control pillars
are fixed at regular intervals of 250 or 200 meters.
The TBMs shall be used as reference points for executing the works in the particular
reach. The TBMs shall contain Reduced Levels of the ground and changing of that
location. These shall be
Checked periodically once in 3 months to ascertain the sanctity of levels. The levels
shall be entered as per Rise & Fall for TBM Verification. The data shall be used for
preparing site leveling & earthwork excavation plan, cross-section of the Pavement
and working drawings. The centerline is also fixed for reference and execution.
1.3 Survey work while execution
Based on the reference of TBM along with reduced levels and centerline, each
activity of the work during execution shall be carried out.
1.4 Survey work on completion of job After completion of work, Reduced Levels
shall be taken up on the works, so as to ascertain the true levels as mentioned in the
drawing are transferred to site. In case of any deviation, such changes shall be
recorded and as built up drawing shall be prepared.
1.5 Confirmation of Survey works Immediately after receiving the survey data
from the Customer (Engineer / employer), the Contractor shall confirm the survey
data of the entire project. The confirmation process shall include the following
aspects
1.5.1 Confirmation of Vertical Control Points The confirmation of Vertical Control
Points (VCP) shall be undertaken by surveying from GPS to GPS points. The Rise
and Fall method shall be adopted for TBM Confirmation Survey. The control pillars
established shall be connected by this survey work. The TBM level after the survey
work is recorded.
1.5.2 Confirmation of Horizontal Control Points The confirmation of Horizontal
Control Points (HCP) shall be undertaken by surveying from a pair of GPS points to
another pair of GPS Points. These values shall be checked with the values given by
the Customer (Engineer / employer). The traverse points established shall be
identified with nail punched on top of Pavement to get the exact point and shall be
encircled with paint of golden yellow color.
1.6 Transferring Survey Data to Control Pillars
1.6.1 HCPs to Pillars Once survey data of HCP is confirmed and control pillars are
constructed, the coordinates (X, Y) shall be transferred from nails to control pillars by
the Total Station. The transferring of levels and coordinates from nails to pillars shall
be prepared.
1.6.2 VCPs to Pillars Once levels of TBM are confirmed and control pillars are
constructed, the levels (Z Co-ordinates are transferred from permanent benchmark
to pillar. The transferring of levels from permanent benchmark to Pillars shall be
prepared.
1.7 Detailed Survey work for runways and Taxiways
Al Fowriya Trading &
Project Quality Plan Contracting
1.9 Instrument The work shall be carried out with Auto level instrument and Total
Station. The recent calibration report of the instruments shall be submitted and
approval shall be sought from the Customer (Engineer / employer) prior to the start
of levelling work in the field. The MS Plate shall be used for every change point to
support levelling staff, depending on the condition of the ground.
CLEARING, GRUBBING AND DISMANTLING STRUCTURES (Acceptance
Criteria: Ref. Section 200 of MORT&H)
1. General This work shall consists of cutting, removing and disposing of all
materials such as trees, bushes, shrubs, roots, grass, weeds, top organic soil not
exceeding 150mm. Dismantling of structures acquired within ROW in brick work,
stone masonry, plain/ reinforced concrete, timber structures, removing tiles, GCI
sheets, etc., and sorting out dismantled materials, disposal of unserviceable
materials and utilizing the serviceable materials at free of cost.
2. Procedure for clearing and grubbing:
Original ground levels shall be recorded jointly before commencing C&G activities.
Before starting the Clearing and grubbing activity, information to the Client / Clients
Representative given.
Top-soil and deleterious material will be dozed and removed up-to 150mm
thickness .All the dozed top soil will be removed from toe line and stacked /displayed
away from the area of work.
Al Fowriya Trading &
Project Quality Plan Contracting
All the trees, shrubs and roots will be removed from the stretch with the help of
manpower / machineries.
Backfilling of the pits will be carried out if required with sand, saturated fully with
water.
The structure shall be carefully dismantled and the resulting materials so removed
shall not cause any damage to the serviceable materials and the structures nearby.
The connecting edges shall be cut, chipped and trimmed to the required lines and
grades without weakening or damaging any part of the structure. Due care shall be
taken to ensure that the reinforcement bars which are to be left in place so as to
project into the new work as dowels or ties are not injured during removal of concrete
while extending the existing culverts/ bridges.
Equipment / Machinery Requirement:
1. Dozer
2. Excavator
3. Tippers
In dismantling pavements, MS pipes, guard rails, kerbs, gutter, and fencing, where
portions of existing construction are to be left in the finished work, the same shall be
removed to an existing joint or cut/chipped true to the lines with face perpendicular to
the existing structure.