Construction

Surveys
List of Figures

Readings: Chapter 23
Figures used:
23-1 to 23-10.
Material to be considered: 23-7.
Stages and Measurements of CS
Design stages: topographic Surveying, and site
maps
Construction stage:
Setting-out and positioning works. 60% of
surveying hours.
involves establishing lines and grades by means
of stakes and string lines to guide the contractor
During and after construction: as built drawings, a
record and a check.
Measurements involved: Horizontal and vertical
angles, elevations, horizontal distances.
CS Equipment
Laser Instruments:
to create a visible line, or plane of known elevation or
tilt
The line or plane could be horizontal, vertical, or tilted.
Single beam lasers will project visible string lines or
plumb lines
Rotating beam lasers: a rotating single beam to create a
plane.
Examples:
Laser levels, laser theodolite and total stations, hand-
held EDM instruments (Figures 23-1 to 23-4)
Recent technology of prism-less total stations and
EDMs, and HDS High Density Surveys.
Machine Guidance
Laser is used to guide the blade
HDS Surveys
TotalStations: the ones designed for CS are
of lower angular resolution(10 or 20), and
shorter ranges(500 m)
Relative GPS: sub-centimeter accuracy with
real time kinematic GPS in horizontal, few
cm in vertical. Must maintain visibility with
satellites
Levels
Horizontal and Vertical Control
Before Construction: new control points around the site
must be established with high accuracy. Additional points
inside the site are then established. All points must be tied
out for repositioning. These initial points should:
Meet certain accuracy standards
Be clearly marked, referenced, and recorded
Be far enough to be safe during construction.
During Construction: additional control is extended by the
contractor as needed, around or inside the structure. These
additional points should be close enough to the structure so
that workers with simple equipment can use them
Staking out a Pipeline
Sanitary (sewage) sewers and storm sewers which
carry storm runoffs operate under gravity. The
grade in such pipelines is critical. City water, oil,
and natural gas pipes are not as critical.
The location of the line is determined after a
profile leveling is done.
The center line and an offset reference line are
established.
Precise alignment and grade are guided by laser
beams or battered boards.
Pipe Laying Laser system by Apache

Source: laserlevels.net
Staking Pipeline Grades
A- Cut and Fill:
The center line and an offset line are marked and
stationed. The actual profiling and staking are on the
offset line, not the CL.
Using profile leveling method, obtain ground elevation
at each stake, compute the depth of cut or fill to the
invert level.
Mark that depth on the stake side facing the trench, mark
the station on the other side of the stake.
B- Line and grade:
Generally done using laser equipment.
Staking out a Building
First step is to locate the building by boundary surveying.
Stakes are placed temporarily at the corners as a check.
In a small size building, a set of batter boards and reference
stakes are first set. The boards are around the building
corners and nailed at a full number of feet above the
footing base or at first floor elevation.
Nails are driven into the batter board tops so that a string
connecting them will define an outside wall
See fig 23-7, and the example which illustrates staking out
the building in fig 23-8.
In a larger building, radial methods, the one you used to
lay out piles, are used used. Fig 23-9
Additional Control for Buildings
Elevations:
Visible benchmark(s) should be set. Additional control
could be done using marks on nearby buildings, or
marks on interior structure elements (columns, walls).
Horizontal:
temporary batter boards inside the site, marks on nearby
buildings.
Plumbness:
Essential for multistory buildings: columns, elevator shafts,
construction walls, etc.
Checked by a theodolite line of sight rotating in a vertical plane,
or by lasers.
Two instruments, with perpendicular line of sights, could be used
to guide the construction of vertical members in real time.
CS Using Total Stations
We are simply trying to define (X,Y) and maybe (Z) of the
center of the TS. Once stored in memory, the TS can do
further computations onsite.
Horizontal Orientation:
By azimuth: input occupied point coordinates and azimuth to
another point.
By coordinates: input occupied point coordinates and another point
coordinates
By resection: input coordinates of unoccupied points , at least
three, output is occupied point coordinates.
Vertical Orientation: if necessary, output is HI:
By adding the instrument height to occupied point elevation.
By adding the vertical distance to a benchmark elevation and prism
height:
HI = elevB + hp - V
Staking out with a Total Station
First the instrument is oriented, and a file that
contains control points and stake points information
is downloaded into the total station.
For 2-D stakeout, the number of the desired stake
point is entered, the instrument will display
differences of angles and distances to orient the
prism.
For 3-D works, The difference in elevation between
the stake elevation and the required elevation (cut
or fill) is also displayed.