Sei sulla pagina 1di 16

Appendix A

H
Likelihood Descriptors
Consequence

Catastrophic Major Moderate Minor Negligible


(5) (4) (3) (2) (1)
Almost Certain 25 20 15 10 5
(5) VERY HIGH VERY HIGH HIGH HIGH MEDIUM
Likelihood

Highly Likely 20 16 12 8 4
(4) VERY HIGH VERY HIGH HIGH MEDIUM LOW
Likely 15 12 9 6 3
(3) HIGH HIGH MEDIUM MEDIUM LOW
Unlikely 10 8 6 4 2
(2) HIGH MEDIUM MEDIUM LOW LOW
Highly Unlikely 5 4 3 2 1
(1) MEDIUM LOW LOW LOW LOW

Risk Level Management Action


VERY HIGH Risks with a rating above 16 are totally unacceptable and the work will not be undertaken until the risk has been
reduced.

HIGH Where the risk rating is between 10 and 15, immediate action must be taken, including a stoppage of work if necessary,
to reduce the risk level.

MEDIUM If the rating is between 5 and 9, the risk is acceptable provided that everything reasonable practicable has been done
to reduce the risk.

LOW With a rating of 4 or less then the risk is acceptable, provided that the assessment is reviewed at regular intervals and
further reduced if possible.
Consequence Health and Safety Environmental Security

Catastrophic Fatality Major environmental damage with potential for litigation, Rioting in labour camp or worksite causing fatality or
media coverage or community outcry multiple major injury
Theft or vandalism causing company loss over QAR
1M
Major Injury or illness with potential for permanent disability Significant environmental damage with one or more Theft or vandalism causing company loss of over QAR
or long-term hospitalization (over 3 months) irreversible impact on the local environment or ecosystem 500,000 but less that QAR 1M
Physical assault causing major injury
Moderate Injury or illness requiring medical treatment but no Environmental impact requiring reasonable mitigation Theft or vandalism causing company loss of over QAR
potential for LTI measures but no adverse effect on the local environment 100,000 but less than QAR 500,000
or ecosystem Physical assault causing injury that would require
medical treatment
Minor Injury or illness requiring first aid Environmental impact requiring minor or no mitigation Theft or vandalism causing company loss of over QAR
measure and no adverse effect on the local environment 10, 000 but less than QAR 100,000
or ecosystem Assault without any injury
Workplace harassment and bullying
Negligible Injury or illness requiring no first aid or medical Negligible or untraceable impact requiring no mitigation Theft or vandalism causing company loss below QAR
treatment (e.g. muscle cramp, minor scratches, 10,000
abrasion, headache etc) Violation of site access and other security rules.

Likelihood Description
Almost Certain Often occurred within the company in similar situation or condition
Highly Likely Often occurred within the industry and sometimes occurred within the company in similar situation or condition

Likely Sometimes occurred within the industry in similar situation or condition


Unlikely Sometimes occurred in other industries but rarely occurred in the construction industry in similar situation or condition
Highly Unlikely Never occurred in the industry or within the company in similar situation or condition

Consequence
The nature and severity of the harm that can be caused by a hazard
Likelihood
The possibility or probability of the hazard to cause the harm
Risk
A combination of the consequence (C) and likelihood (L) (R = C x L)
Existing Control
Any risk control measure already in place at the time of hazard identification and risk
Assessment
Residual Risk
The level of risk exposure after the implementation of risk control measures
(R = C x L)
Health and Safety Risk Assessment Worksheet

DESIGN AND BUILD OF LIGHT INDUSTRIAL & LOGISTICS UNITS LOCATED AT UM ALHOUL SPECIAL ECONOMIC
Project Title
ZONE

Client MANATEQ

Location UM ALHOUL QEZ-3 ECONOMIC ZONES

Scope INSTALLATION OF LIGHTNING PROTECTION SYSTEM

R/A Date 12th December 2017 Review date 12th June 2018

R/A Number EZ03-CW03-QBEC-ELE-RAS-000006-Rev02

R/A Undertaken by Varghese Ninan ( HSE Manager )

Risk Assessment Residual Risk Level


S.I Who might be
Activity Task Hazards Identified Proposed Control Measures Action by
harmed and how?
No. Conseq Likeliho Risk Conseq Likelih Risk
uence od Score uence ood Score
Carry out pre task inspection to assess area of
Nearby Vehicular survey works for traffic hazard.
traffic Put adequate caution signs at required
Uneven ground distance and barricades as well as trained flag
surface, Debris on men to caution & direct vehicle drivers.
floors, wet/ muddy
Survey and floor surface.
Personal injury, collision, All persons must wear high visibility vest.
Project Manager
Heat stress, eye irritation,
Marking Sand dust particles respiratory diseases. Site safety inspection prior to start. Eliminate Site Engineer /
1 blown by wind into Surveying crew 3 3 9 or highlight all potential trips/ slip/ fall hazards. 4 1 4 Supervisor
eyes and sand dust and other Avoid any existing edge of potential fall. (before the
inhalation. personnel Barricade around existing pits / trench if any. activity)
Work in open area Tool box awareness on trip/ slip/ fall hazards
under direct sun, in
condition of High Where possible suppress dust by sprinkling of
heat Index water.
Use adequate necessary PPEs such as safety
helmet, dust musk, safety goggles, safety
shoes, hand gloves, Hi-Vi vest,etc
No activity at the time of heavy wind, sand
storm. Use adequate eyes and respiratory
protection
Implement heat stress prevention plan.
Ensure availability of adequate potable
drinking water and resting areas.
Stop work when heat index exceeds safe
exposure limit
Follow summer working hours as per directive
of ministry.
Put adequate caution signs at required
distance and barricades as well as trained flag
men to caution & direct vehicle drivers.
Trained and experienced person shall perform
the task.
Appropriate Documents (RAMS) to be
obtained from concern parties in order to start
Hand Injury,
the activities.
Pinch point Cuts, Project HSE induction should be attended all
Crush injury Crushing injury, the crew.
Personal injury Project Manager
Lack of knowledge
Mobilization of Property Damage Maintain good housekeeping standards. Use Site Engineer /
Absent mindedness
3 men and Operatives and 3 4 12 safe handling techniques for the transportation 3 1 3 Supervisor
Slip, Trip, Fall
materials other site of tools and equipment to the work place. (before the
Manual Handling
personnel / TBT and JHA to be conducted prior to start of activity)
Collision with
Workers the work
pedestrians vehicles
Proper supervision required.
Bobcat shall be used if necessary.
Personnels should keep safe distance from
equipments
Banksman shall be provided for equipment
operation
Use adequate necessary PPEs such as safety
helmet, dust musk, safety goggles, safety
Work crew shall be trained and competent.
All electrical work, including repairs, shall be
made according to program requirements and
approved drawings.
Only qualified personnel utilizing appropriate
electrical safety related work practices and
PPE shall perform work on electrical systems
and equipment.
Ensure that workers know how to use the
electrical equipment safely. Make sure enough
sockets are available.
Check that socket outlets are not overloaded
by using unfused adaptors as this can cause
fires.
Ensure everyone looks for electrical wires,
cables or equipment near where they are
going to work and check for signs warning of
Fire dangers from electricity, or any other hazard.
Burns
Electrical Electrocution Checks should be made around the job, and
Project Manager
Personal injuries remember that electrical cables may be within
Burns/Shock/ Site Engineer /
Operatives and walls, floors and ceilings (especially when
2 Electrical Works Electrocution 4 4 16 4 1 4 Supervisor
other site drilling into these locations) etc.
Trip, Fall (before the
Fire personnel / Dry powder fire extinguisher shall be provided activity)
Workers at working area. All the crew shall be used
mandatory PPE's.
Put adequate caution signs at required
distance and barricades in near traffic route.
All persons must wear high visibility vest.
Site safety inspection shall be done prior to
start.
Eliminate or highlight all potential trips/ slip/ fall
hazards.
Where possible damp down dust by sprinkling
of water.
Access / Egress should be always kept clear
and free from materials.
TBT and JHA to be conducted prior to start of
the work
All equipments / materials shall be checked
prior to installation.
Use adequate necessary PPEs such as safety
Use right tools for the task.
Check the tools before performing the task.
Dont use damaged tools
Pinch point
Crush injury
Hand Injury,,cuts , Follow the manufacture instruction.
crushing injury Project Manager
Cut injury Operatives and
Defective tools should be identified and
Site Engineer /
Use of Hand Lack of knowledge remove from the site.
4 other site 3 4 12 3 1 3 Supervisor
tools Absent mindedness personnel / TBT and JHA to be conducted prior to start of (before the
Damaged hand tools Workers the work activity)
Flying particles
Keep the cutting tools sharp.
Dont keep sharp hand tools on pockets.
Proper supervision required.
Trained and experienced person shall perform
the task.
Only 110 V power tools to be used
TBT and JHA to be conducted
Cable joints shall be with industrial sockets
Trailing cables should not be in path
Hand Injury,,cuts , Electric tools should be earthed and double
Electricity Entanglement, crushing
insulated
injury, Electrocution Project Manager
Moving parts
Sharp surfaces Operatives and Equipment should be repaired by competent Site Engineer /
5 Use of Power 4 4 16 person 4 1 4 Supervisor
Entanglement other site
tools Provision of RCD (before the
Damaged power personnel /
Workers activity)
tools The power tools should be inspected quarterly
and provided colour coding tag after
inspection.
Equipment should be visually inspected before
use and checked for quarterly inspection
colour coding tag.
Use of task specific / speed rated discs
Clear the area after the completion of the task. Project Manager
Site Engineer /
Dont leave any material on the work area
Supervisor
Major minor injuries, back after performing the task.
(before the
injury, Burns, Supervisor should ensure that every material activity)
Slips, Trips and Falls Operatives and is kept in its designated place.
6 Housekeeping Minor / Major Injuries other site 3 3 9 Access / Egress should be always kept clear 3 1 3
Fire personnel /
and free from materials.
Workers
Proper cable / hose management should be
ensured.
Supervisor shall ensure all the time that the
work area shall be clear.
Proper manual handling technique should be
followed
Sharp edges should be covered
Manual handling hazard awareness training
should be provided.
Fall of material Back pain
Use mechanical aids for transporting the
Damage of material Personal injury material to work place
Project Manager
Manual handling Back pain (strain/Sprain) If more than 20 kg use two person or
Site Engineer /
Muscular disorder Operatives and mechanical means such as wheel barrow or
7 other site 3 3 9 3 1 3 Supervisor
Hernia other mechanical means (As per QCS section
personnel / (before the
Cut injury 11 part 1.2.7.8)
Workers activity)
Fracture Dont carry heavy material too long
TILE ( task, load , individual , environment )
shall be considered before manual handling of
any material
Dont carry overload
Dont twist the body
Use adequate necessary PPEs such as safety
All underground services should be located
and made safe
A careful investigation should be undertaken
to ensure there are no electric cables,
underground water courses, or ground
conditions, which could lead to hazardous
situations.
Workers shall be trained and competent.
Operator should be in possession to all valid
documents. (Valid Qatar License and (TPC).
Equipment must have valid documents.
(Istimara and TPC).
Daily equipment inspection by operator prior to
start work.
Damage of
Ensure appropriate barricade and sign board
underground utilities.
Toppling of placed around equipment operating area.
equipment Person Major Injuries Equipment must be placed in a firm level
Preparation of struck with Fatality base.
Pit using Drilling equipment. Property Damage Ensure the rig and mud plant are bonded and Project Manager
by Truck Contact with grounded/earth to protect the equipment from Site Engineer /
Operatives and
8 Mounted contaminated risings 4 4 16 electric cable strikes. 4 1 4 Supervisor
other site
Hydraulic Drilling or groundwater. (before the
personnel / The stability of the surrounding structures is a
Rig (TMHDR) Ground water activity)
Workers prime consideration. Workers shall be wear
equipment. accumulation.
gumboot to avoid direct contact with ground
Noise, Vibration.
water.
Collapse of
excavations, nearby Ground water shall be drained from the area
structures etc to avoid water accumulation at site.
Noise and vibration are particular hazards and
all persons associated with the operation
should wear the appropriate protective
clothing and equipment such as hard hats, eye
and hearing protection.
Ensure ABC fire extinguisher is available at
site.
Assign competent foreman/supervisor to
monitor activity.
TBT and JHA shall be conducted before start
of the task.
Use appropriate PPEs(such as safety helmet ,
earplug, face shield, dust mask , safety
goggles, safety shoe , hand gloves, hi-vi vest)
Work at height permit shall be obtained from
the HSE department before performing the
task.
Working area shall be barricaded and
signages shall be posted
Ensure that the operatives are medically and
physically fit for the task
Work at height procedure shall be followed
Proper tagging of the scaffolds shall be done.
A competent scaffolding supervisor /
scaffolding inspector with valid third party
certification shall ensure inspection and
tagging of the scaffolds
Three point contact shall be maintained while
accessing and descending from ladder
Ensure that the foot of the ladder is free from
slip
Fall of person
Fall of material from Major injuries, Ladders should be set, as near as possible, at
height Fracture an angle of 75 (a ratio of 1 unit of length out
Operatives and to 4 units of length up) As per QCS section 11 Project Manager
Working at Slippage of foot
other site part 1.3.2.8) Site Engineer /
height Physically unfit
10 personnel / 4 4 16 4 1 4 Supervisor
(scaffolding, Slippery foot while Ladders must extend at least 1 metre (before the
ladders) climbing Workers (approximately 5 rungs) above the landing activity)
Absent mindedness place, unless an alternative, secure handhold
Heavy wind is available. As per QCS section 11 part
1.3.2.8)
Ladders must extend at least 1 metre
(approximately 5 rungs) above the landing
place, unless an alternative, secure handhold
is available. (As per QCS section 11 part
1.3.2.8)
TBT and JHA to be conducted prior to start of
work.
Proper supervision required
Trained and experienced person shall perform
the task
Full body harness shall worn while performing
the task with 100% tie off
Monitor windspeed and suspend activity
during heavy wind.
Use adequate necessary PPEs such as safety
helmet, dust musk, safety goggles, safety
shoes, leather hand gloves, Hi-Vi vest,etc
MSDS AND COSHH assessment shall be
followed
Manufacturer instruction shall be followed
COSHH material shall be stored in COSHH
room
Required quantity of material only shall be
used or kept in the work area
Waste material shall be dumped in hazardous
waste storage area.
Put adequate caution signs at required
Overuse of Major injuries, distance and barricade.
gunpowder headache, fatigue and
nausea, Molds shall be inspected prior to start of work
Improper / metal fume fever, and replace if damaged. Project Manager
Unauthorized use Burns,
Exothermic Inhalation
The work area shall be cleared from Site Engineer /
11 Operatives and 3 4 12 flammable/combustible materials. 3 1 3 Supervisor
welding Ingestion
other site Chemicals containers shall be labelled (before the
Contact with Skin
activity)
Contact with Eyes personnel / TBT and JHA shall be conducted before start
Fire Workers of the task.
Damaged Molds Proper supervision required.
Trained and experienced person shall perform
the task
Fire extinguisher shall be made available in
work area and storage area.
Medical Surveillance / medical fitness of
workers shall be checked periodically.
Firewatcher and First Aider shall be provided
for the activity
Use appropriate PPEs(such as safety helmet,
dust mask, safety goggles, safety shoe,
Put adequate caution signs at required
distance and barricades in near traffic route.
Nearby Vehicular
All persons must wear high visibility vest.
traffic
Uneven ground Site safety inspection shall be done prior to
surface, start. Eliminate or highlight all potential trips/
Personal injury, collision,
Electricity Heat stress, eye irritation, slip/ fall hazards.
Debris on floors, respiratory diseases. LOTO procedure shall be followed while Project Manager
Testing wet/ muddy floor Electrocution testing is carried out. Site Engineer /
12 (Earth Megger surface. Operatives and 4 3 12 4 1 4 Supervisor
Where possible damp down dust by sprinkling
and Continuity) Sand dust particles other site of water. (before the
blown by wind into personnel / activity)
eyes and sand dust Workers TBT and JHA to be conducted prior to start of
inhalation. the work
Slips, trip, falls All equipments / materials shall be checked
Damaged materials / prior to installation.
equipments Use adequate necessary PPEs such as safety
helmet, dust musk, safety goggles, safety
shoes, insulated hand gloves, Hi-Vi vest,etc
13
Work Activities All work shall be stopped during the extreme
with exposure to Illness ,skin burns, weather condition
high temperature/ vomiting, head ache,
high humidity collapse, blood Regular interval to be provided for workers in
pressure, irritation hot session
conditions (Heat High heat stress
Stress) Index Operatives and Heat stress Index/ emergency plan to be
other site monitored and implemented during working in
personnel / extreme weather condition
Workers Drink water more frequently and add ORS for
lost minerals and salt. Project
4 3 12
Supervisor need to Keep a sharp eye on heat 4 1 4 Manager/
related illness on fellow workers. Construction
Proper meal and take proper rest during break Manager
time. Summer factor awareness training shall
be conducted.
First Aid responders should be available, and
an emergency response plan should be in
place.
Trainings related to heat stress to make
awareness among workers.
Provide adequate medical attention to anyone
reporting symptoms or uneasiness.
To provide the lighting meeting the QCS- 14,
Section 11, 1.5.3
Recommended levels for site lighting which
are given below
Security 5/30Lux
Movement and handling of peoples,
Machine and vehicles, Handling of
Supervisor, materials 20 LUX
Foreman and site Store & stockyard 30 Lux Project Manager
14 Night shift work Vehicle movement 4 4 16 4 1 4 / Site Engineer/
workers Site entrance General access, vehicle and Supervision Team
pedestrian 30 LUX
General work area 50LUX
Reinforcing concreting, shattering erecting
100 LUX
Fine craft work all work with Power tools
Painting Electrical 300 LUX
Site hunts Rest room, Toilet 150 LUX
Site office 500 LUX
Supervisor, To check the illumination level as per
Project Manager
Low visibility Foreman and site requirement by Lux meter from competent
4 4 16 4 1 4 / Site Engineer/
workers person Supervision Team

The Object of area lighting should be to


produce and overall level illumination,
Supervisor, Sufficient for workmen and vehicle to move
safely. Every part of the area should receive Project Manager
Man Machine interface Foreman and site
4 4 16 light from the least two directions to avoid 4 1 4 / Site Engineer/
workers Supervision Team
dangerous, dense shadows
Pedestrian walkways should be kept clear
and illumination. High visibility
Excavation to be barricaded off with warning
signs and lighting to be arranged.
Tower light to be increased and regular
Supervisor, maintenance to be ensured.
Open excavated area Project Manager
Foreman and site Continuous adequate solid barriers will be
/edge 4 4 16 4 1 6 / Site Engineer/
workers placed around all excavations over 1.2m Supervision Team
deep at a distance at least of 1.2m.
All solid barriers shall be fitted with warning
lights.

Supervisor, HSE
Workers New to Night Foreman and site Site induction/ TBT to be performed regarding
4 4 16 4 1 4 Represent
works workers lighting and night works
ative/ Site
Supervisor
Project Manager
Supervisor, All moving parts of machinery need to be / Site
Pinch points Foreman and site 4 4 16 covered as per required guard 4 1 4 Engineer/
workers Supervision
Team

Unwanted projected objects must be Project Manager


Supervisor, removed from the site or separated from the
Foreman and site / Site
Protruding nails 4 4 16 movement area. 4 1 4 Engineer/
workers Denailing to be done for all used and Supervision
waste plywood materials Team

Work area to be fenced off and secured Project Manager


/ Site
Continues supervision to be done by security Engineer/
Supervisor, personal and supervisor Supervision
Movement of operatives Use emergency contact number in case of an Team
Foreman and site
outside the work area in 4 4 16 4 1 4
workers emergency (55219535)
dark
Appropriate welfare facilities shall be provided
together with frequent breaks to allow the
operatives to rest, refresh themselves and
regain alertness.
Always keep workplace and premise neat,
clean and tidy
Arrange all materials in a proper manner Project Manager
Materials should be stored in a proper manner / Site
Engineer /
Inspection prior to commence of the activity to Supervision
be conduct by respective supervisor Team
Notifying supervisor if there are dangerous
animals sighting.
Contamination of soil
Evacuate the area immediately without
causing Panic
that will harm
Supervisor. Never work alone
environment if the
15 Environment. Foreman and 3 3 9 3 1 3
spillage is in big
workers Ensure there is enough supervision to
amounts facilitate communication between workers and
promote appropriate behavior and rational
decision making.
Provision of Spill kits
Adequate lighting should be install in the area
of work
Avoid threatening the animals or insects as
these may aggravate the situation
Provision of secondary containment
MSDS shall be made available in site and
shall be communicated to the operatives.

Name: Amal Sarath Reviewed by: Name: Varghese Ninan Approved by: Name: Samer Housni
Prepared By: HSE Engineer HSE Manager Project Manager
Sign/ Date: Sign/ Date: Sign/ Date:

Fire and Emergency Evacuation Plan (FEEP)


During the activity all staff must be aware of the FEEP for that activity. In the event of an injury during this task the HSE Officer shall ensure
that first aid treatment is available for the activity. The casualty shall be treated at the scene in the first instance. Should further treatment be required the
closest vehicle to the scene of the incident shall be deemed the FEEP vehicle to take the injured to the QBEC clinic for further treatment.
In the unlikely event that somebody is struck by debris or the trencher itself the casualty shall not be moved at all unless there is an immediate threat
to life by the location they are in or by the nature of the injuries sustained. QBEC emergency no: 55219535 ambulance shall immediately be called to the
scene; in the meantime the Primary First Aider 33658361 shall ensure the stability of the casualty.
In the event of a fire during the activity then the fire extinguishers at the scene should be used to tackle the blaze if possible, all un required staff
should be evacuated from the location to a pre agreed location at the start of the activity.
Civil Defense fire service should be called immediately to assist. All engines and electrical sources should be switched off and isolated.
During in any FEEP all other activities in the area shall immediately be stopped until advised otherwise by the Senior Staff at the scene.
Once the FEEP has been activated and the immediate threat is controlled the Project Management must be informed of the incident or accident.
The scene should be sealed, either by staff or barriers if possible to ensure that his area remains the same for photographs and other investigation
steps that may be required. Depending on the nature and severity of the incident the Police may be required to attend the scene and to carry out their own
investigation.
For investigation purposes all people who were involved in the activity are to identify themselves to the HSE Officer to assist in the investigation.
All staff involved in the activity must be aware of this FEEP prior to the start of work.

Potrebbero piacerti anche