Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
0 INTRODUCTION
Liftboats are the preferred vessel for most shallow water jobs in the United
States Gulf of Mexico where there are about 200 such vessels, which highly possible
Carigali Sdn. Bhd. (PCSB) generally to meet the market demand as well as coping up
with the latest technology evolution in marine industry. This study examines how
liftboats can replace workboats and work barges and bringing fortune towards the
company. As for liftboats selection, there are several key elements required which are,
jacking system, working water depths, deck space, crane capacity, personnel
the right one as a potential alternative multi-purpose vessel replacing other boats for
daily use.
As of 27 March 2014, there are total of four workboats and one work barge
operating under PMO projects, whereby eight workboats are under SKO projects, two
workboats for SKO HUC, two workboats are currently working for SBO projects and
one workboat for SBO HUC. In this current situation, workboat/barge could not operate
throughout the year due to harsh weather condition (monsoon). Workboat/barge can
only operates roughly 270 days a year and a further analysis has been done that
shows restrictions at the beginning and end of year. Therefore, liftboat would be the
most suitable vessel to substitute the current workboat/barge mainly because liftboat
can operates 365 days without any limitations. Liftboat can withstand in any condition
especially monsoon which always occurs first quarter and fourth quarter of a year.
Hence, a high technology with latest and modern facilities and accommodation
option to replace the present workboat/barge. Apart from that, liftboat is also a self-
mobilize without any helps from AHT to tow, and this may reduce some cost especially
in fuel consumption and also daily charter rate (DCR). In addition, it has widely been
used internationally and has been triggered us as a solution in easing workload, more
number of working days per year and bringing up PETRONAS to a more advance
Logistics Services, introduction of Liftboats showing that we are ready for a next big
With regards to above, there were five (5) companies invited to share Proof of
i. Teras Offshore
ii. Seacore
iii. GMS
iv. IPS
v. Emas/Larizz
vi. Hercules
vii. Dextral
3.0 OBJECTIVE
To realize this project successfully, several objectives are needed to keep us on track
and work barges under SCM contracts with Liftboat supporting all PCSB
operations.
To come out with full analysis and study regarding suitablity of Liftboat
In the current market, there are two different types of liftboat where one has 3 legs and
another one has 4 legs. Therefore, a comparison has been made between these two
boats.
3 Legs 4 Legs
V. high pre-load stresses, loss of one Lower pre load stress, reduced overall
Punch-through
leg catastrophic leg pressure
of another leg, i.e., the jacking system to support two legs loaded diagonally is greater
and the hull structure is different/heavier. From HSE point of view, the 4 legs liftboat
will have a better penetration into the soil and have stronger and larger area to support
the liftboat. Giving a situation, if there is a case if one of the legs is not functioning, the
3 legged liftboat will definitely become unstable and causes massive accidents for
instance death. If the same situation occurs to 4 legged liftboat, at least, there are still
left with 3 legs to support the liftboat and the activities on board can be done normally.
We also required specifying the length of the legs which includes the soil
penetration, water depth and air gap. As per our studies, the minimum length of the
leg is 130 m.
The jacking system for a liftboat is very different than the jacking system for a jack-up
drilling rig. The two major differences center around speed and cycles.
Speed of the liftboat jacking system is essential. While a typical jack-up drilling rig
elevates at two feet per minute a liftboat could elevate at four to six feet per minute
and lower the legs at 14-18 feet per minute. This gives the liftboat the ability to get on
The jacking system for a liftboat encounters a very different operational cycle. It would
not be uncommon for a liftboat to jack up and down in one year the same number of
times that a jack-up drilling rig would encounter in its entire lifetime. So, the wear
factors, redundancy, material grades and shock loads are different between jack-ups
and liftboats.
4.3 Working Water Depth
The expected wind, wave and current (environmental conditions) in the maximum
working water depth need to be determined. Although, other variables will go into the
liftboat design, such as, net deck load, the starting point is still working water depth.
will be a significantly different liftboat design in all aspects, i.e., legs, jacking system
and hull. As a general rule, as working water depths and severity of environmental
conditions increase, then, costs of the vessel rise exponentially. Therefore, we did
some analysis regarding water depths in Malaysia especially PMO, SKO and SBO
regions. We found out that liftboats are suitable to be used in our regions to replace
the existing workboat/barge. The figure below shows the average water depth for our
regions. For more specific water depths data for each platforms, please refer to
Appendix 1.
The deck area is the unobstructed, open area. The liftboat crane is used to move
equipment and materials around and on to and off the platform/offshore location.
There is a relationship among these variables open deck area, net deck load and
crane capacity. Further, you need a crane capacity that is commensurate with the
The net deck load for a liftboat is what you have on your deck in transit and can then
jack up with on the deck. Consumables (such as water, fuel, hydraulic fluid, etc.) are
in addition to the net deck load. Liftboat operators are concerned with what they can
There is a definite relationship among deck area, deck load and crane capacity.
Also, one needs to consider the type of equipment and components that will be on the
deck, so that, various areas can be designed to accommodate the various loadings,
i.e., an area near the bow may have higher point loading than other areas.
4.6 Crane Capacity
The value of open deck space, deck load and crane capacity is what makes a
liftboat a liftboat.
There are a variety of cranes for liftboats. However, there is one caveat cranes
for liftboats are designed by crane manufacturers specifically for liftboats. Weight is a
key consideration in liftboat design, so, every consideration needs to be made in the
overall design including the crane. Therefore, cranes for liftboats are typically
Regarding types of liftboat cranes, there are lattice boom, box boom, telescopic
boom, pedestal mounted, and leg encircling cranes. The main things to consider in
crane selection are reach, load capacities and effect on deck area.
PCSB also has made their requirements which a liftboat must have minimum 2
4.7 Accommodations
accommodations are generally divided into two areas navigation crew and
capacities, so, has the requirement for more personnel. For example, a 100-man
accommodation block would typically have about 20 navigation crew and the
requirement, i.e., an offshore construction job would generally require more personnel
than a well intervention job. The construction job may even require additional modular
living quarters on the deck. Additionally, one needs to consider the area of operation
in accommodation design.
4.8 Propulsion
the need for tugs to move the liftboat or to set up on location. This results in a
significant cost advantage in that the liftboat can move to a new location without having
to wait on tugs to move them. The liftboat can wait for a weather window and move.
Remember the liftboat captain is lowering the legs and station keeping all at the
same time an operation that takes very little time compared to the jack-up drilling rig.
Power design is all important when one in positioning near the platform.
5.0 COMPARISON OF SERVICES
PERFORMED OF VESSELS
Service performed
Construction, Workboat Jackup Construction
maintenance and Liftboats Floatel
/barge drilling rigs vessels
decommissioning
support
Remove/install/
decommissioning of / X X / X
modules
Construction support / / X / X
Maintenance support / / X / X
Diving support X X X / X
Accommodation Depend
(Limitations) on water Limited Limited / /
depth
Well servicing
Conventional drilling X X / X X
Coiled tubing / X / X X
Wireline / X / X X
Well workover / X / X X
Well testing/early
/ X / X X
production
Cost effective
Daily charter rate (DCR) Relatively Relatively Very very Relatively
Very High
High Low High Low
Maintenance/service Relatively Very very Very very Relatively
High
High High High Low
Stable to work at
/ X / X X
platform
Need tugs assistance X / X / /
6.0 REQUIRED SPECIFICATIONS
Therefore, there are several required specifications that has been mentioned by our
Well Specialist, Mr. Lawrence Sim regarding of using Liftboat in our platforms. As from
our studies, we found out that every platform has different water depths and different
well activities.
Features Description
Helideck
Main Propulsion
Bow Thruster
Electric Power
Generators
Emergency Generator
Jacking System
Jacking Speed
Steering System
Deck Space
Windlass
Cranes
Peninsular Malaysia, Sabah and Sarawak. This weather pattern will determine
whether liftboat vessel is fit in condition for any operations. In this weather pattern, we
need to consider several aspects such as water level, climate, wind conditions, rain
weather changes for instance tropical storm or typhoon. All of these must be taken
into consideration to avoid any mishap during operation. Malaysia is separated by the
South China Sea into two similarly sized regions, Peninsular Malaysia and Malaysian
Borneo. Land borders are shared with Thailand, Indonesia, and Brunei, and maritime
The wind over the country is generally light and variable. There are, however,
some uniform periodic changes in the wind flow patterns. Based on these changes,
four (4) seasons can be distinguished, namely, the southwest monsoon, northeast
half of May or early June and ends in September. The prevailing wind flow is generally
southwesterly and light, below 15 knots. The northeast monsoon season usually
commences in early November and ends in March. During this season, steady easterly
or northeasterly winds of 10 to 20 knots prevail. The winds over the east coast states
of Peninsular Malaysia may reach 30 knots or more during periods of strong surges of
Based on data taken from Umbrella 2014 Strategy, analysis had been done to
determine the total number of pax and total number of workboat/barge throughout the
year of 2014. For example, in August (peak month) the total number of pax are 5600
and 28 workboats are required for the operation, whereas only 23 liftboats are needed
for the same number of pax. Based on the results and analysis, we can conclude that
the total number of vessels can be reduced by 5 if we are using liftboats. The base
line in the graph below reflects the minimum number of vessels required for each
operation
Therefore, a further analysis has been done based on projection for the next upcoming
years, 2015 until 2018, which shows that the pattern of the graph is the same as 2014.
However, the number of pax reduces as after 2014 due to several possibilities such
As shown in the graph above, the total cost for lift boat is higher than total cost of
Workboat/barge. The total cost for lift boat is calculated based on the DCR and fuel
consumption of 365 days per year as it can operates the whole year regardless
weather adverse. On the other hand, Workboat/barge is contracted only for 270 days
per year and the total cost is calculated based on the contracted year. A further
calculation will be done to show that upcoming years, the total cost of liftboat will be
cheaper and able to operate like workboat/barges and also jack-up accommodation.
Liftboat is ahead of all other vessels by referring to the blue stars and we can see that
Liftboat gained all the stars for all the features involved.
Since liftboats are using almost the same concept of jack up rigs, we need to do
several soil tests to check the availability of a sea bed type to support the weight of
the jack-up rig depends on the soils profile to a considerable depth. (Refer to the table
in literature review)
1. Moisture Content
Method: Weigh a sample of wet material, bake for 24 hours at 105 degree
Method: Weigh a known volume of wet soil, dry at 105 degree Celsius for 24
3. Torvane Test
Method: A special bladed disc is rotated against a calibrated torsion spring. The
disc being presses flat against the soil. The soil enclosed within the vanes is
sheared off the sample. The effort required can be measured on the calibrated
spring.
4. Pocket Penetrometer
spring attached to the rod is compressed and the amount of compression can
5. Fallcone test
of soil. Penetration of the cone is measured and a factor applied which results
Particle size affects soil behavior. A sample is hand sieved to determine the
Purpose: To determine the liquid and plastic limits and the plasticity index of a
9. Density Determination
Determines angle of shearing resistance of a sample. The result gives a graph of shear
The following list shows the risks associated with placing any particular jack-up barge
on the sea bed and elevating it. The site investigation should take into consideration
these hazards and determine their relevance to the site under construction and the
Wind/wave/current data.
Current data.
Soil samplers
Historical data
Historical data
Charts/field data
Chart data
There are three types of feasibility that will be discussed herein: required design,
economic and schedule. Required design is needed as such the liftboat will meet all
the requirements of all the platforms and able to perform all the activities. The
economical feasibility will review the expected costs to see if they are in-line with the
projected budget or if the project has an acceptable return on investment. At this point,
the projected costs will only be a rough estimate. The exact costs are not required to
project costs will fall within the target budget or return on investment. Similar to
order to assess the feasibility of a project, information has to be obtained from the
research, presentations and interviews. A review from articles and reports may also
be appropriate.