BILL OF QUANTITY FOR THE PROPOSED WASTE PIT BACKFIL AT BAYELSA STATE.

QTY
ITEM DESCRIPTION UNIT RATE (N) AMOUNT (N)

BILL NO.1
PRELIMINARIES

A Allow for mobilization of all plants, PS 80,000.00


equipment and personnel to site.
Allow for Temporary site
B PS 75,000.00
accomodation and office
C Allow for community relation PS N/A
D Allow for Progress photograph PS 5,000.00

E Allow for provision of sign post PS 8,000.00


(1nos)
Allow for complete first aid box
F PS 7,500.00
(2nos)
G Allow for water for the works PS 26,000.00
Allow for Sanitary facilities for
H PS N/A
workmen
Allow for Temporary shed/canteen
J PS N/A
for workmen

K Allow for watching and Lighting PS N/A

L Allow for scaffolding PS 45,000.00

M Allow for temporary access road PS N/A

N Allow for external fencing PS N/A


Allow for the complete setting out
O of the works to the approval of PS 30,000.00
the Engineer
Allow for Consultancy,
P PS N/A
Supervision .
Allow for demobilization and Hand
Q PS N/A
Over
R Allow for site meetings PS N/A
Bill No.1: PRELIMINARIES TO 276,500.00
GENERAL SUMMARY
BILL OF QUANTITY FOR THE PROPOSED WASTE PIT BACKFIL AT BAYELSA STATE.

ITEM DESCRIPTION QTY UNIT RATE (N) AMOUNT (N)

WASTE PIT STRUCTURE

D : GROUNDWORK (ALL
PROVISIONAL)
INFORMATION

Nature and location of the work

The work in this section


comprises:

The work in this section


comprises: Earthworks, concrete
works, block works and other
ancillaries.

ii) The Contractor is however


refered to the Architectural and
Structural Drawings in relation to
this work section for details of
work to be executed.

iii) The Contractor should keep


accurate records authenticated by
the Project Architect/Engineer or
their duly authorized
Representative.

GENERAL CLEARANCE
664.3
Clear site of all bushes,
shrubs,trees and grubing up their
A roots. m2 75 49,822.50

B Topsoil Excavation.
664.3
Excavate top soil average depth
not exceeding 150mm deep and
deposite to a temporary heap
spoil. m2 100.00 66,430.00

Pits Excavation
BILL OF QUANTITY FOR THE PROPOSED WASTE PIT BACKFIL AT BAYELSA STATE.

1328.6
Maximum depth not exceeding
2.00m; commencing surface
150mm below existing ground
C level. m3 400.00 531,440.00

CARRIED TO COLLECTION 647,692.50


ITEM DESCRIPTION QTY UNIT RATE (N) AMOUNT (N)
Brought forward 647,692.50

Disposal of excavated materials

1480
Deposit excavated materials in
temporary spoil heaps average
distance not exceeding 30m from
A excavation for re-use m3 120.00 177,600.00
Filling
Return,fill and ram selected 371
excavated materials around the
B waste pit for consolidation. m3 150.00 55,650.00
Level and Compact bottom of
Surface Treatment
excavation to receive concrete
C casting. 664.30 m2 N/A

664.30
Approved Pesticides; Dieldrex 20'
solution or other equal and
D approved to surfaces m2 N/A

324.54

Earth work support on opposing


faces of trench excavation depth
E not exceeding 2.00m. m2 1000 324,540.00

HDP1(HIGHTECH DENSITY
POLYTHENE LINER)

Apply an approved hightech


density polythene liner(hdp1) : in
floor base and walls of waste pit as
F described in design drawing. 851.04 m2 1100 936,144.00

Allow for keeping surface of site


and excavation free from
G surface/ground water. Sum 50,000.00

GROUND WORK CARRIED TO


SUMMARY 2,191,626.50
BILL OF QUANTITY FOR THE PROPOSED WASTE PIT BACKFIL AT BAYELSA STATE.

ITEM DESCRIPTION QTY UNIT RATE (N) AMOUNT (N)

IN-SITU CONCRETE/LARGE
PRECAST CONCRETE

INFORMATION

Nature and Location of the work


The work in this section
comprises:

i) Reinforced Concrete Columns,


Beams, Suspended floor slab and
the likes.

ii) The Contractor is refered to the


Structural Drawings for details and
scope of work.

Mass In-situ Concrete (1:4:8)


A 20mm aggregates in:
Blinding to base 50mm thick 27
poured on earth surface. m3 10,000.00 274,050.00
Foundations(1:2:4
B Foundations 137.025 m3 11,000.00 1,507,275.00

Reinforced : Grade 25
C walls 225mm thick 51.612 m3 11,000.00 567,732.00
Recast concrete recess on natural
ground level. 57.996 m3 11,000.00 637,956.00

FORMWORK FOR IN-SITU


CONCRETE

FORMWORK : SAWN HARDWOOD


TO SMOOTH FAIR FINISH.
walls of waste pit
289.98
Plain vertical; not exceeding
D 2000mm high m2 850.00 246,483.00
BILL OF QUANTITY FOR THE PROPOSED WASTE PIT BACKFIL AT BAYELSA STATE.

CARRIED TO COLLECTION 3,233,496.00

ITEM DESCRIPTION QTY UNIT RATE (N) AMOUNT (N)


Brought forward 3,233,496.00
REINFOCEMENT FOR IN-SITU
CONCRETE

Bars; deformed high yield;


straight and bent
nominal sizes

Reinforcement : to BS 4449
(Provisional)
8,012
12mm diameter; in base and walls
A of waste pit kg 182.00 1,458,184.00
B 10mm diameter; ditto 2974 kg 180.00 535,320.00

CONCRETE/LARGE PRECAST
CONCRETE CARRIED TO
SUMMARY 5,227,000.00
BILL OF QUANTITY FOR THE PROPOSED WASTE PIT BACKFIL AT BAYELSA STATE.

ITEM DESCRIPTION QTY UNIT RATE (N) AMOUNT (N)

MASONRY

BRICK/BLOCK WALLING

Nature and Location of the work


The work in this section
comprises:

i) The erection of hollow


sandcrete block walls and
associated works

ii) The Contractor is refered to the


Architectural and Structural
drawings for details and scope of
work

Hollow Sandcrete Blocks to B.S.


6073; natural aggregates;

compressive strength 3.5N/mm2;


face size 450 x 255mm;
cement and sand (1:6) mortar
Walls

575
225mm thick hollow blocks;
B externally . m2 1,500.00 862,500.00

MASONNRY CARRIED TO 862,500.00


SUMMARY
BILL OF QUANTITY FOR THE PROPOSED WASTE PIT BACKFIL AT BAYELSA STATE.

ITEM DESCRIPTION QTY UNIT RATE (N) AMOUNT (N)


GENERAL SUMMARY
A PRELIMINARIES 276,500.00
B GROUNDWORK 2,191,626.50
IN-SITU CONCRETE/ LARGE
C 5,227,000.00
PRECAST CONCRETE
D MASONRY 862,500.00

8,557,626.50
ADD VAT 5% 427,881.33

ADD CONTINGENCY 8,557.63

PROPOSED WASTE PIT BACKFILL


CARRIED TO SUMMARY 8,994,065.45