Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
B Revised as comments
A For approval
1.0 SCOPE
This procedure covers the general requirements for boiler refractory dry out.
2.0 PURPOSE
During the installation of refractory, its humidity and size is relevantly larger than the size after it
is dried up. So that it shall be driying up before it is put into high temperature during boiler
normal operation to eliminate natural water and crystal water.The remained water evaporation
will cause cracks, protrusion, displacement or even worse falling off. In order to lengthen
refractory lifespan and prevent boiler part abrasion, the curing process is necessary.
3.0 REFERENCE
3.1 VENDOR REFRACTORY DATA SHEET
Page 2 of 11
Refractory Dry Out Procedures
Page 3 of 11
Refractory Dry Out Procedures
7.4 Complete the installation of boiler expansion indicator and adjust the needle to
zero.
7.5 Complete the installation of fuel oil system. After water pressure test, clean it and put
into pre-commissioning and then supply oil to the boiler formally.
7.6 Install and pre-commission boiler relevant thermal instruments and electrical
instruments. Put into operation after colligation.
7.7 Finish the installation of boiler inside. Drum water level shall be clear and accurate.
Lighting condition shall be good.
7.8 Make sure the availability of woods or other material as fuel media for low
temperature curing program
7.9 Make sure all the supporting system for RDO must be ready, such as : Drain Pump,
Boiler Fans, and Cooling System
7.10 Supply softened water or chemical demineralized water until normal water level.
Water temperature shall follow design requirement. Clean the water level gauge.
7.11 Set a certain amount of bed materials in boiler air distribution grid and open back
opening man hole for the convenience of hot flue gas flowing through air distribution
device evenly.
7.12 Reserve humidity exhausting hole at the proper position of furnace wall to make sure
that the steam can be exhausted freely during curing.
7.13 Install temporary thermocouple for burner area ( burner 1 and 2 )
7.14 Install temporary line from drain wind box to drain seal pot
7.15 Temperature rising rate, insulation temperature and insulation duration shall be in
consistent with possible dehydration and other physical variation and deformation.
Curing process can be divided into the following two classes:
The first stage (Phase 1) : carry out mid-low temperature curing at approximately
150C and 250C stages according to water discharge law. The main purpose of this
stage is to discharge free water in the castables. There is a large amount of free water
in the castables that using cement as combining agent. So that the insulation time for
this stage shall be long enough to eliminate free water completely.
The second stage (phase 2) : high temperature curing combining with boiler pre-
commissioning. The main purpose for this stage is to discharge structural water in
the refractory materials. Structural water refers to H-O-H. Eliminate H- and -O-H to
increase refractory intensity.
Page 4 of 11
Refractory Dry Out Procedures
Cooling Down
Total minimum curing time
After finish, natural cooling down
Page 5 of 11
Refractory Dry Out Procedures
Operation method:
In the initial stage, remove start up oil gun, open ID fan inlet and Outlet dumper. Open
man hole, set the fire wood, cover the primary air nozzle at bed furnace with rockwoll
and Supervise burner wall and wind box temperature during baked period. The
temperature rising rate shall strictly follow the requirement in the curve.
In order to make hot flue gas reach the loop seal connect the temporary thin pipe of
drain wind box to drain of seal pot for flue emission.
When baked for period, then the natural cooling to ambient temperature install the
start up burner back for the high temperature curing period.
Operation method:
In the initial period, bake the furnace from thermal firewood and the temperature
rising rate shall follow the curve. If the firewood heat quantity cannot meet
temperature rising requirement, input burner into service to continue heating up.
Closely supervise wall temperature metering point until the first stage of curing is
finished.
Page 6 of 11
Refractory Dry Out Procedures
9.2 High-temperature Refractory Dry Out (*if wood firing methode not reach temp.)
After the first stage of Refractory Dry Out remove all temporary facilities, recover
formal system and start the second stage of curing, that is, high temperature curing stage.
High-temperature curing stage is boiler formal operation stage. Start up ID fan and
primary fan. Ignite under burner and Control air room temperature rising rate with
primary air flow rate and oil flow rate. At this time all the systems are in normal
operation status. Control Burner and primary air flow rate to meet temperature rising
curve requirement.
As the steam parameter is very high at the later stage of phrase 2 curing, so this time
boiler blow pipe shall be kept on executed through Boiler Blow Pipe Measures. Carry out
the moisture content test of presetting model after its natural cooling.
Page 7 of 11
Refractory Dry Out Procedures
10.5 Steam that produced during the curing process will eject from the exhaust gate. The
temperature tolerance of steam pocket wall shall be no more than 50C during warming
and boosting process. In order to control the temperature, the wall temperature of super
heater shall be closely monitored at the later stage of curing process. The water level
tolerance shall be opened occasionally to feed water for the boiler.
10.6 After low-temperature curing, the moisture content test will be carried out in the related
region of anti-friction and refractory matter; the high-temperature curing will be
conducted once the test is qualified.
10.7 Temperature rising shall be stable during the curing process, and the furnace wall
situation shall be always checked to avoid flow and transformation.
10.8 Open vent properly in order to eject moisture during curing process.
10.9 Flame must be small at the beginning of curing, or else partial temperature rising speed
too fast will cause the negative effects.
10.10 Sewerage under boiler circuit shall be kept totally open to avoid thermal shock and
water attack.
10.11 Set exhausting system shall be connected to keep smooth water in order to avoid the
water attack that caused by water trapped.
10.12 Expansion indicators in all parts of boiler shall be calibrated zero.
10.13 During curing process, blow-off pipe shall be always checked and dealt with the blow
down valve if there has something abnormal.
10.14 All connected drain valve of header can be adjusted according to the curing situation.
Page 8 of 11
Refractory Dry Out Procedures
12.0 APPENDIX
12.1 General Arrangement of High Velocity Gas Flow
12.2 Temperature Rise Curve
Page 9 of 11
Refractory Dry Out Procedures
APPENDIX 1
TO FLUE DUCT
Firewood Combustion
Page 10 of 11
Refractory Dry Out Procedures
APPENDIX 2
Page 11 of 11
FIELD INSPECTION AND TESTING REPORT
CHECK LIST
Parameter
Remarks
No Area Time
Temp Temp Rising
Area :
Temperature Temperature Time Result Remarks
(C) Rising Speed (Duration)
OK NO
(C) hr
1. Low Temperature (at Burner and Windbox)
Normal temperature 150 5 17
150 C maintain 32
150 - 250 C 5 10
250 C maintain 36
3. High Temperature
250 350 15 25 10
350 Maintain temp. 56
Date :
Equipment : Refractory
Condition
No Subject Remarks
Good Bad
1 REFRACTORY FURNACE
2 REFRACTORY WINDBOX
Note :
FURNACE
PICTURE PICTURE
PICTURE PICTURE
Remarks :
WIND BOX
PICTURE PICTURE
PICTURE PICTURE
Remarks :
CYCLONE L/R
PICTURE PICTURE
PICTURE PICTURE
Remarks :