Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
In this course work therere fourth questions that available to answer it. The first question
is about preparing the process flow diagram of the acetylene plant and the complete list
of major equipment required for starting up the acetylene production plant to meet the
annual demand. The second question is to estimating of the acetylene plant to find the
{Fixed Capital Investment, Working Capital investment and Total Capital Investment}.
The third question is to estimating the total production cost {TPC} per kg of acetylene.
The last question is about calculating the Rate of Return {ROR} in this project.
Acetylene (C2H2) is the simplest of alkyne compounds, consisting of two hydrogen atoms
and two carbon atoms linked by a triple bond. Acetylene is a colorless, flammable gas
used in welding and in the preparation of other chemical compounds. In addition,
Acetylene gas is toxic if inhaled by one, and it is also an explosive mixture with the air.
2. Based on the purchased equipment cost, prepare a study estimate of the acetylene
plant (with an accuracy of 30 percent).
Equipment cost of acetylene production of 210 ton per annual of acetylene {2009}
No. Quantity Equipments Equipment Equipment Equipment Cost
Cost Ethiopian Cost USD OMR
Birr
1 2 Water tank 44,650 1,629.57 627.037
2 1 Carbide 113,730 4,150.75 1,597.15
feed
mechanism
3 1 Carbide 61,240 2,235.05 860.018
buffer
4 2 Acetylene 91,860 3,352.57 1,290.03
generator
5 2 Pulverize 52,490 1,915.70 737.136
6 1 Scrubber 56,860 2,075.19 798.506
7 1 Purifier 34,990 1,277.01 491.377
8 15 Nitrogen 26,240 957.669 368.430
cylinders
9 3 Pumps 42,900 1,565.70 602.349
To find the slope and the intercept that required from the linear equation (Y=mX+c)
by using Excel Program.
To calculate the cost index for the next year {2017}, draw the graph by using the
relationship between the {year = X} Vs. {Process Industry = Y}
2009 23 1271.83
2017 31 1421.19
Scaling Factor:
By using the scaling factor role of [six tenth] to find the equipments cost of 9800 ton
per annual by using this formula:
Cost of future = [ ] Equipment Cost
Cost in 2017= Original cost in 2009 [Index value in 2017 Index value in 2009]
The table below show the new equipment cost in 2017 {OMR}
Equipment Cost in 20009 Calculation the new cost using Cost in 2017
{OMR} formula {OMR}
Water tank 5605.66 5605.66 [1421.191271.83] 6263.97
Carbide feed 16023.22 16023.22[1421.191271.83] 17904.94
mechanism
Carbide buffer 8628.03 8628.03 [1421.191271.83] 9641.28
Acetylene generator 12942.07 12942.07 [1421.191271.83] 14461.95
Pulverize 7395.23 7395.23 [1421.191271.83] 8263.70
Scrubber 8010.92 8010.92 [1421.191271.83] 8951.69
Purifier 4929.68 4929.68 [1421.191271.83] 5508.61
Nitrogen cylinders 3696.23 3696.23 [1421.191271.83] 4130.30
Pumps 2141.02 2141.02 [1421.191271.83] 2392.45
Indirect Costs
Total 100
3% FCI
Local Taxes = {(3/100) (341492.91)}
= 10244.79 OMR
0.70% FCI
Insurance = {(0.70/100) (342969.69)}
= 2390.45 OMR
5% TCI
Financing/ Interest = {(5/100) (401756.36)}
= 20087.82 OMR
66% TPC
Direct Production = {(66/100) (420185)}
Cost TPC = 277322.1 OMR
9% TPC
Plant overhead cost = {(9/100) (420185)}
= 37816.65 OMR
15% TPC
= {(15/100) (420185)}
= 63027.75 OMR
4. Determine the Rate of Return (ROR) the project. Comment on whether this ROR is
justifiable to undertake the project.
Comment:
A Rate of Rent should not exceed 30 percent of the adjusted income of any
project, so that mean when the Rate of Rent is less than 30% the project will be
successes. This paper develops and estimates the Rate of Rent {ROR} is equal to
27 %, which is an acceptable value in this project.
In this coursework, all the questions have been answered, which applied all the required
conditions. From this coursework has been gained a lot of information which didn't know
about it before. Also, got an experience how to calculate the {Fixed Capital Investment,
Working Capital investment, Total Capital Investment, Total Production Cost and the
RoR}. In this coursework several steps have been taken to obtain solutions to all
requirements. First of all, has been converted the cost to the OMR to stare doing the
calculation. After the calculation the value of {Fixed Capital Investment = 341492.91
OMR}, {Working Capital investment = 60263.45OMR} and the value of {Total Capital
Investment = 401756.36 OMR}. In addition the value of the Total Production Cost has
been calculated which was equal to 420185 OMR. Finally, the RoR has been calculated
which equal 27 % (is an acceptable value in this project).
Books
Peters, M.L. & Timmerhaus, K.D.,1991. Plant Design and Economics for Chemical
Engineers, Fourth Edition, McGraw Hill Inc.
Websites