ID Task Name Duration

Predecessors Start Finish Resource Names


SatMon
02
Wed
Sep
04 06
SepSep
000000
1 SP#2 SD Sinter machine discharge plan 36 hrs Mon 04-09-17 08:00 Tue 05-09-17 20:00

2 Power cutting of sinter machine and 2 hrs Mon 04-09-17 08:00 Mon 04-09-17 10:00
breaker

3 clearance received 0.5 hrs 2 Mon 04-09-17 10:00 Mon 04-09-17 10:30

4 breaker changing 33 hrs Mon 04-09-17 10:30 Tue 05-09-17 19:30

5 discharge door opening 1 hr 3 Mon 04-09-17 10:30 Mon 04-09-17 11:30

6 inspection of sinter machine 1 hr 5 Mon 04-09-17 11:30 Mon 04-09-17 12:30


breaker

7 small hood removal 3 hrs 24,20 Mon 04-09-17 20:30 Mon 04-09-17 23:30

8 large hood removal 4 hrs 7 Mon 04-09-17 23:30 Tue 05-09-17 03:30

9 haflex gearbox holding 3 hrs 6 Mon 04-09-17 12:30 Mon 04-09-17 15:30

10 coupling bolt opening 3 hrs 9 Mon 04-09-17 15:30 Mon 04-09-17 18:30

11 breaker removal 3 hrs 8,10 Tue 05-09-17 03:30 Tue 05-09-17 06:30

12 base cleaning 1 hr 11 Tue 05-09-17 06:30 Tue 05-09-17 07:30

13 new breaker positioning 3 hrs 12 Tue 05-09-17 07:30 Tue 05-09-17 10:30

14 breaker base bolt fixing 2 hrs 13 Tue 05-09-17 10:30 Tue 05-09-17 12:30

15 coupling bolt fixing 2 hrs 14 Tue 05-09-17 12:30 Tue 05-09-17 14:30

16 large hood plaxement 4 hrs 14 Tue 05-09-17 12:30 Tue 05-09-17 16:30

17 small hood placement 3 hrs 16 Tue 05-09-17 16:30 Tue 05-09-17 19:30

18 knife bar changing 29 hrs Mon 04-09-17 12:30 Tue 05-09-17 17:30

19 grizzly removal outside 2 hrs 6 Mon 04-09-17 12:30 Mon 04-09-17 14:30

20 knife bar changing 6 hrs 19 Mon 04-09-17 14:30 Mon 04-09-17 20:30

21 grizzly fixing inside 2 hrs 20 Mon 04-09-17 20:30 Mon 04-09-17 22:30

22 door closing 1 hr 16 Tue 05-09-17 16:30 Tue 05-09-17 17:30

23 permit return 0.5 hrs 22,17 Tue 05-09-17 19:30 Tue 05-09-17 20:00

24 Strengthening of small hood 8 hrs 6 Mon 04-09-17 12:30 Mon 04-09-17 20:30

Task Inactive Task


Critical Task Inactive Milestone
Milestone Inactive Summary
Summary Manual Task
Rolled Up Task Duration-only

Project: MSProj11 Rolled Up Critical Task Manual Summary Rollup


Date: Mon 27-11-17 09:31 Rolled Up Milestone Manual Summary
Rolled Up Progress Start-only
Split Finish-only
External Tasks Progress
Project Summary Deadline
Group By Summary

Page 1

Potrebbero piacerti anche