PERT/CPM

LIST ACTIVITIES PREDECESSOR DURATION ES EF LS LF TF CP


A Clear Lot - 3 0 3 0 3 0
B Strip Topsoil & Stockpile A 1 1 2 1 2 0

C Stake Lot for Excavation A 1 1 2 1 2 0


D Delivery of Materials A 1 1 2 1 2 0
E Excavation C 5 6 11 5 10 -1
Cutting and assembly of
F D 15 16 31 16 31 0
Steel Reinforcements

Forming of Formworks
G D,E 10 16 26 31 41 15
and Scaffoldings
Positioning of steel
H E,F 15 31 46 31 46 0
reinforcement
Plumbing and Water
I D,E 15 30 45 30 45 0
Pipe connections
J Dummy - 0 0 0 0 0 0
Pouring of Footing and
K H,G 5 36 41 36 41 0
Column
L Removal of Forms K 1 37 38 37 38 0
CHB Laying and
M K 15 51 66 51 66 0
Backfilling
Ground Leveling for
N K 10 46 56 46 56 0
Floor Slab
Pouring of concrete for
O N 8 54 62 54 62 0
floor slab
P Dummy - 0 0 0 0 0 0
Positioning of steel
Q reinforcement for 2nd O 20 74 94 74 94 0
floor
Forming of formworks
R and scaffolding for 2nd O 10 64 74 74 84 10
floor
Plumbing and Water
S Pipe connections for 2nd O 15 69 84 84 99 15
floor
Pouring of concrete for
T Q,R 10 84 94 139 149 55
2nd floor flor slab
Pouring of concrete for
U T 10 94 104 94 104 0
2nd floor clolumn
V CHB Laying for 2nd floor U 15 109 124 109 124 0
W Dummy - 0 0 0 0 0 0
Roof framing and Roof
X V,U 9 118 127 119 128 1
sheets
Y Construction of staircase U 3 97 100 97 100 0

Z Plastering and tile works V 15 124 139 124 139 0


Installation of Doors and
AA V 5 114 119 144 149 30
windows
Plumbing and Drainage
BB S,T 5 89 94 144 149 55
System
Installation of Plumbing
CC X 5 123 128 144 149 21
and Electrical Fixtures

DD Painting and Varnishing Z 20 144 164 144 164 0

EE Final work and Cleaning DD, CC, BB, AA 3 147 150 147 150 0

Critical Path:
A-D-F-H-H-K-N-O-Q-T-U-V-Z-DD-EE = 150 days
3+1+15+15+5+10+8+10+10+10+15+15+20+3= 150 days
List of Work
LIST ACTIVITIES PREDECESSOR DURATION
A Clear Lot - 3

B Strip Topsoil & Stockpile A 1

C Stake Lot for Excavation A 1

D Delivery of Materials A 1
E Excavation C 5

Cutting and assembly of Steel


F D 15
Reinforcements

G Forming of Formworks and Scaffoldings D,E 10

H Positioning of steel reinforcement E,F 15


I Plumbing and Water Pipe connections D,E 15
J Dummy - 0
K Pouring of Footing and Column H,G 5
L Removal of Forms K 1
M CHB Laying and Backfilling K 15
N Ground Leveling for Floor Slab K 10
O Pouring of concrete for floor slab N 8
P Dummy - 0
Positioning of steel reinforcement for 2nd
Q O 20
floor
Forming of formworks and scaffolding for
R O 10
2nd floor
Plumbing and Water Pipe connections for
S O 15
2nd floor
T Pouring of concrete for 2nd floor flor slab Q,R 10

U Pouring of concrete for 2nd floor clolumn T 10


V CHB Laying for 2nd floor U 15
W Dummy - 0
X Roof framing and Roof sheets V,U 9
Y Construction of staircase U 3
Z Plastering and tile works V 15
AA Installation of Doors and windows V 5
BB Plumbing and Drainage System S,T 5
Installation of Plumbing and Electrical
CC X 5
Fixtures
DD Painting and Varnishing Z 20
EE Final work and Cleaning DD, CC, BB, AA 3
Gantt Chart

1w 2w 3w 4w 5w 6w 7w 8w 9w 10w 11w 12w 13w 14w 15w 16w 17w


Duration (By Week)

3 11
B-1 L-1 R-10

1 2 5 8 9 10 13 14 15

A-3 D-1 F-15 H-15 K-5 N-10 O-8 Q-20 T-10

9
4 6 12

C-1 E-5 G-10 M-15 S-15

I-15

Legend:
Predecessor
Dummy
A (Letter)- 1 (Number) Activities- Duration
17w 18w 19w 20w 21w 22w 23w 24w 25w 26w 27w 28w 29w 30w

18
Y-3

16 17 19 20 22 23

T-10 U-10 V-15 Z-15 DD-20 EE-3

16 22
21

X-9 CC-5

22

AA-5

22
BB-5
BAR CHART (MANPOWER)

12

11 10 10 10 10

10

9 E
O
8 7 7

7 N
MANPOWER

6 F 5 5
D K T
5 H Q

4 3 C G R

3 L M

2 A B I S

1w 2w 3w 4w 5w 6w 7w 8w 9w 10w 11w 12w 13w 14w 15w 16w 17w 18w

Duration (By Week)

Legend:
A (letter) : Activities
1 : No. of men
12
11

10 10

9 Z

V X
U
DD

EE

AA
Y
CC
BB

18w 19w 20w 21w 22w 23w 24w 25w 26w 27w 28w 29w 30w
ACTIVITIES WITH MANPOWER LIST

LIST ACTIVITIES PREDECESSOR DURATION MANPOWER


A Clear Lot - 3 3
B Strip Topsoil & Stockpile A 1 3
C Stake Lot for Excavation A 1 4
D Delivery of Materials A 1 6
E Excavation C 5 10
Cutting and assembly of Steel
F D 15 7
Reinforcements
Forming of Formworks and
G D,E 10 4
Scaffoldings
Positioning of steel
H E,F 15 5
reinforcement
Plumbing and Water Pipe
I D,E 15 3
connections
J Dummy - 0 0
K Pouring of Footing and Column H,G 5 10
L Removal of Forms K 1 5
M CHB Laying and Backfilling K 15 6
N Ground Leveling for Floor Slab K 10 7
Pouring of concrete for floor
O N 8 10
slab
P Dummy - 0 0
Positioning of steel
Q O 20 5
reinforcement for 2nd floor
Forming of formworks and
R O 10 4
scaffolding for 2nd floor
Plumbing and Water Pipe
S O 15 3
connections for 2nd floor
Pouring of concrete for 2nd
T Q,R 10 10
floor flor slab
Pouring of concrete for 2nd
U T 10 10
floor clolumn
V CHB Laying for 2nd floor U 15 6
W Dummy - 0 0
X Roof framing and Roof sheets V,U 9 8
Y Construction of staircase U 3 5
Z Plastering and tile works V 15 11
Installation of Doors and
AA V 5 6
windows
BB Plumbing and Drainage System S,T 5 3
Installation of Plumbing and
CC X 5 4
Electrical Fixtures
DD Painting and Varnishing Z 20 12
EE Final work and Cleaning DD, CC, BB, AA 3 8
S-CURVE DIAGRAM FOR LABOR COST

WEEKS COST TCL


1 12,500.00 12,500.00 700,000.00
2 25,000.00 37,500.00
3 23,500.00 61,000.00
4 16,500.00 77,500.00
600,000.00
5 12,500.00 90,000.00
6 12,500.00 102,500.00
7 15,000.00 117,500.00
500,000.00
8 23,500.00 141,000.00
9 17,500.00 158,500.00

COST (500/PERSON)
10 19,000.00 177,500.00
11 25,000.00 202,500.00 400,000.00
12 17,500.00 220,000.00
13 12,500.00 232,500.00
14 12,500.00 245,000.00 300,000.00 TCL
15 12,500.00 257,500.00
16 20,000.00 277,500.00
17 25,000.00 302,500.00 200,000.00
18 25,000.00 327,500.00
19 25,000.00 352,500.00
20 23,500.00 376,000.00 100,000.00
21 22,500.00 398,500.00
22 22,500.00 421,000.00
23 25,500.00 446,500.00 0.00
24 27,500.00 474,000.00 0 5 10 15 20 25 30 35
25 27,500.00 501,500.00
26 29,000.00 530,500.00 DURATION (WEEKS)
27 30,000.00 560,500.00
28 30,000.00 590,500.00
29 30,000.00 620,500.00
30 24,200.00 644,700.00
12000