Sei sulla pagina 1di 13

Available online at www.sciencedirect.

com

ScienceDirect
International Journal of Project Management 33 (2015) 985 997
www.elsevier.com/locate/ijproman

Evaluating the level of stakeholder involvement during the


project planning processes of building projects
Amirhossein Heravi a,, Vaughan Coffey a , Bambang Trigunarsyah b
a
Science and Engineering Faculty, Queensland University of Technology, GPO Box 2434, Brisbane, QLD 4001, Australia
b
College of Environmental Design, King Fahd University of Petroleum and Minerals (KFUPM) Dhahran, Saudi Arabia

Received 27 August 2014; received in revised form 11 December 2014; accepted 16 December 2014
Available online 8 January 2015

Abstract

The purpose of this study is to examine the current level of stakeholder involvement during the project's planning process. Stakeholders often
provide the needed resources and have the ability to control the interaction and resource ows in the network. They also ultimately have strong
impact on an organisation's survival, and therefore appropriate management and involvement of key stakeholders should be an important part of
any project management plan.
A series of literature reviews was conducted to identify and categorise signicant phases involved in the planning. For data collection, a
questionnaire survey was designed and distributed amongst nearly 200 companies who were involved in the residential building sector in Australia.
Results of the analysis demonstrate the engagement levels of the four stakeholder groups involved in the planning process and establish a basis for
further stakeholder involvement improvement.
2014 Elsevier Ltd. APM and IPMA. All rights reserved.

Keywords: Stakeholder involvement; Planning process; Building projects

1. Introduction of the decisions that are made during the construction project
lifecycle, project managers need to develop comprehensive
Many stakeholders, individuals and groups are involved in stakeholder involvement plans (Saghatforoush et al., 2010).
the provision and delivery of construction projects and each has Previous research studies in the construction sector (Bal et al.,
their own role, requirements and objectives. So, because 2013; Bosher et al., 2007; Olander and Landin, 2005a)
stakeholders of construction projects are numerous and highlight that stakeholder involvement is important in improv-
different, this introduces a level of complexity to the concept ing the effectiveness of project outcomes (Yang, 2010). The
of stakeholder involvement (SI) within the industry (Bal et al., quality of a construction project is also largely dependent on the
2013). However, depending on the type of the project being appropriate performance management of diverse stakeholders,
undertaken and its specific requirements, only certain groups especially contractors and consultants (Low Sui and Ke-Wei,
may need to get fully involved in all phases of a project. 1996). This means that, if major parties of a contract are not
To meet the differing demands of different stakeholder committed to properly carrying out their responsibilities, it is
groups, and in order to increase the effectiveness and efficiency likely to adversely affect the final project quality level.
Furthermore, the level of ability to impact the final project
Corresponding author. Tel.: + 61 411255411.
characteristics is at its highest at the beginning of the project
E-mail addresses: Amirhossein.heravitorbati@qut.edu.au,
and reduces as the project progresses. It is widely advocated in
Amir.h.heravi@gmail.com (A. Heravi), V.coffey@qut.edu.au (V. Coffey), the project management and infrastructure project literature
Bambangts@kfupm.edu.sa (B. Trigunarsyah). (IFC, 2007) that the project preparation and planning phase is

http://dx.doi.org/10.1016/j.ijproman.2014.12.007
0263-7863/00/ 2014 Elsevier Ltd. APM and IPMA. All rights reserved.
986 A. Heravi et al. / International Journal of Project Management 33 (2015) 985997

the stage where stakeholders with various demands and objectives consist of project's actual benefit in the operation phase as well as
have the highest possibility to affect the project and its outcomes their micro criteria. Baccarini (1999) identifies two components
(Kolltveit and Grnhaug, 2004; Miller and Lessard, 2001). of project success as project management success and product
Improving effective stakeholder involvement, will not only help success. The project management success deals with the project
project stakeholders to efficiently collaborate with each other, it process and primarily the successful achievement of project in
will also facilitate the possibility of a decrease in negative terms of meeting cost, time and quality objectives whereas the
environmental impacts and increase the economic sustainability product success focuses on the impacts of the ultimate product.
and quality of the project. However, no major studies have been The key point is that both of these success components must
undertaken to date to precisely examine how more effective meet stakeholder's satisfaction where there is a link between
stakeholder involvement can be facilitated to contribute to the their interest and these components (Baccarini, 1999). In
ultimate delivery of construction building projects. On the other addition, as stated by Atkin and Skitmore (2008), enhanced
hand, a significant step to be taken to facilitate improved stakeholder involvement can help with managing their needs,
stakeholder involvements to determine the current levels of decreasing unanticipated risk and reducing unconstructive
stakeholder involvement since according to Yin and Heald actions or reactions that have possible impact on project
(1975), it is essential to evaluate an existing provision within the success. According to the comprehensive statement by the
main research area before establishing a framework. This project management body of knowledge (PMBOK) guide
research therefore focuses on assessing and evaluating the extent published by the Project Management Institute (PMI, 2013),
to which key stakeholders are currently involved within the project success criteria consist of the golden triangle (time,
planning processes of residential building projects. cost, quality) and key project stakeholder's satisfaction and
This paper starts with a discussion on the elements of project their incorporation to the project.
success (Section 2) and stakeholder management in the construc- Despite these arguments, the two elements of quality and
tion industry (Section 3). Section 4 evaluates the influences of stakeholder management, in many cases, have been regarded as
project participants on project quality outcomes and clarifies the two major success factors, and therefore are the focus of the
relationship between stakeholder involvement in different phases research.
of the project life cycle (PLC) and project quality. Section 5 then
discusses the significance of the initial and planning stages in the 3. Stakeholders in the construction industry
PLC. Following that, Section 6 describes the methodology and
data collection process. Data analysis and findings are then The stakeholder theory concept was initially developed from
presented in Section 7. Based on the analysis adopted, Section 8 academic research being undertaken in the US in the 1960s that
discusses the findings and clarifies the relationship between the defined stakeholders as those groups having high enough
findings and the research question. Section 9 outlines a summary impact in an organisation to cause it to stop existing without
of the major findings, describes the significance of the research their (the stakeholders) support (Li et al., 2013; Stoney and
and its theoretical and practical implications and makes recom- Winstanley, 2001). Later, Freeman (1984, 52) extended this
mendations for future research projects. definition and described a stakeholder in an organisation as
any group or individual who can affect or is affected by the
2. Project success achievement of the organisation's objectives. A helpful
illustration by Walker (2003) shown in Fig. 1, provides a
Success has always been the ultimate purpose of each activity widely accepted mapping of project's main stakeholders:
of a project including construction and building projects (Yu
et al., 2006). Project success has been extensively discussed in the Amongst the most important aspects of the above map are
construction and project management literature, however it is not the inclusion of community and external independent concerned
easy for a variety of authors to get to a full agreement regarding
project success criteria (LU et al., 2005). Most studies have
focused on the scope of project success which means the way to
Client
measure success of project and factors affecting project success. End Project
Organisaon
Users Sponsor
Westerveld (2003) states that one of the most common ways of
measuring project success is the well-known iron triangle of cost,
time and required quality. Some studies have extended project External Team Project Leader
Members- (PM) Core Community
success criteria into new aspects, such as stakeholder's Suppliers Team Members and External
Independent
participation and satisfaction, customer's benefit and upcoming Concerned
prospective to organisation (Shenhar et al., 2001). Morris and Group
Hough (1986) applied a number of concepts to measure project Invisible Team Members
People whose co-operaon and
success such as: project function, project management, and support are vital for project
contractor's business performance. Other researchers examine
project success by make use of micro and macro criteria (Lim and Source:(Walker 2003)
Mohamed, 1999). In their examination micro criteria encompass
time, cost, quality, performance and safety, and the macro criteria Fig. 1. Stakeholder mapping.
A. Heravi et al. / International Journal of Project Management 33 (2015) 985997 987

groups, and an identification of invisible team members. It is key project stakeholders, examining their needs and assessing the
advocated that project success can be critically affected by the impact and probable risks that they can impose on the project.
activities of these two recognised groups. The importance of
stakeholders can also be determined by examining the needs of a
business and the degree to which an organisation is in need of a 4. Inuences of stakeholder involvement on construction
particular stakeholder (Leung et al., 2013; Olander, 2007). In projects and their quality
certain instances, some stakeholders can be more important than
others and the project leader should carefully analyse their Brian and Martin (2008) and other scholars (Bosher et al.,
requirements and attributes at different times during the project 2007; Cole, 2005; El-Gohary et al., 2006; Olander and Landin,
life cycle. Phillips (2003) stated that stakeholder theory should 2005b) studying construction sector stakeholder issues, have
focus on the groups who can input into decision-making process realised that the activities and practices undertaken by major
as well as who are affected by the outputs of such decisions. It is parties have undeniable impacts on project outcomes. There-
argued that an organisation's advantages are basically dependant fore, identification of the important roles of key members on
on its capability to adequately manage stakeholders (Verbeke and projects has therefore developed more in recent years. As noted
Tung, 2013). On the other hand, stakeholder management as a by PMI (2013) in order to obtain project success, a project
task is specific to context and therefore any strategies and manager needs to facilitate the contribution of stakeholders in
methods applied should reflect this context (Bourne and Walker, various project phases. However, in the view of Joaquin et al.
2005; Jones and Wicks, 1999). (2008) using the effective interaction mechanism with stake-
In the construction industry, during the different stages of a holders to improve project outcomes and achieve success is not
project from the initial planning through to the final operation particularly evident in the construction industry practices.
and maintenance, specific parties get involved whose expecta- Different stakeholders can be a part of a large project's
tions can affect the outcomes of, or may be affected by, both executive team and depending on how they get involved and what
negatively and positively the implementation of the project their roles are, they might have different interests in, impacts on
(Olander, 2007). These groups include: and ambitions for a project (Kolltveit and Grnhaug, 2004).
Therefore a significant part of the project management process
Client should be to precisely evaluate the importance and influence levels
Project Management team of these groups and their potential orientation towards the project
Consultant and designing team (Olander, 2007; Winch and Bonke, 2002). According to some
Contractor authors (Johnson and Scholes, 1999a) stakeholder analysis can be
Subcontractor categorised into four steps of: (1) identifying key stakeholders
Supplier (2) assessing stakeholder's interests and the potential impacts
Employees of the project on these interests (3) assessing stakeholder
Local communities influence and importance and (4) outlining a participation
Funding Bodies strategy. It is noted that, stakeholders and projects have a
Government authorities bilateral impact function that means while stakeholders can
influence projects; a construction project can sometimes affect
These groups as stated by many scholars (Olander and Landin, stakeholders. For example, providing a higher quality of life by
2005a; Newcombe, 2003; Atkin and Skitmore, 2008; Yang, 2010) increasing the quality of facilities of the final project are the
are the major stakeholders of construction building projects. Atkin advantages of implementing a project. On the other hand,
and Skitmore (2008) signified that successful implementation and destruction of the environment is an example of the negative
completion of the project largely rely on addressing the needs and impacts of a project on some stakeholders (Olander, 2002;
expectations of those who are involved and failure to correctly Olander and Landin, 2005a).
address their requirements can result in many project issues Many factors can influence the quality of a project. Neverthe-
(Bourne and Walker, 2005). This idea is reinforced by Johnson less, the apparent role of key stakeholders as an important factor in
and Scholes (1999b) who state that it is not adequate to simply determining quality levels has not to date been widely examined in
identify stakeholders, rather managers and owners need to the literature (Joaquin et al., 2010; Low Sui and Ke-Wei, 1996;
evaluate each stakeholder's interest in order to articulate their Olander, 2006; Soetanto et al., 2001; Wang and Huang, 2006).
expectations on project decisions. Olander (2007) advocated that it According to Low Sui and Ke-Wei (1996), the quality of a
is the key responsibility of project leaders to respond to the construction project is largely dependent on the attitudes of
requirements and needs raised by their stakeholders and to be able different stakeholders. Hence, if major parties of the contract are
to carry out, control and manage the project decision-making not committed to properly carrying out their responsibilities, this
process. Inappropriate management and supervision of stake- will adversely affect the final project quality level. Deming (1986)
holders can cause problems in the technical and management declares that the customer's (stakeholder's) perspective of quality
mechanisms of a project. In addition, Bourne and Walker (2005) levels is critically important, and therefore inclusion of the main
highlighted that conflicting and unseen stakeholder agendas, if not stakeholders during the important stages of project lifecycle should
well managed, can lead to many project failures. These issues be a key feature of any framework aiming to improve the quality
highlight the need for having a systematic approach to identifying (Joaquin et al., 2010).
988 A. Heravi et al. / International Journal of Project Management 33 (2015) 985997

A project management team can improve its effectiveness

Involvement
and the efficiency of its control and management processes and Planning
The extent of
as a result, improve project quality. This requires that they

Project Quality
implementation of the
possess important information about the project and be capable project in conformity
with:
enough to accurately analyse that information and outline Design

Stakeholder
relevant project strategies. Contractors, subcontractors and - terms
- duration
suppliers are those who might not get engaged in very early - budget
stages of projects, however, since they provide materials, - appearance
- operation
equipment and on-site labour, they can still greatly impact on Construction
the final asset quality. Low Sui and Ke-Wei (1996) stated that Overall Satisfaction
one essential step in establishing a total quality culture is to
develop a construction team of main contractors and subcontrac- Source: (Adapted from Bubshait 1994)
tors who commit to the quality process and create a productive
quality attitude at the earliest time. Contractors in the competitive Fig. 2. The interaction between project quality and stakeholder involvement.
market with a reputation for producing poor quality constructed
output will not generally be awarded many future projects. Such
contractors should therefore be encouraged to improve the quality design, construction and post construction phases highly depends
of their work in order to increase their chance of winning tenders on the appropriate decisions being made during the earlier
(Arditi and Murat Gunaydin, 1997). On the other hand, planning phase (Abdul-Kadir and Price, 1995; Toakley and
contractors with a good quality reputation are expected to deliver Marosszeky, 2003).
projects within the specified time and budget and to the desired
level of quality (Aje, 2012).
5. The planning phase
In addition, owners (clients) and developers play an important
role in the accomplishment of the desired project outcome quality
The importance of conceptualisation and planning is relatively
levels. These groups are not only accountable for preparing clear
prominent compared to other phases in the project lifecycle and
and complete specifications, but they should also monitor and
they both have remarkable influence on project success (Meyer
control the actual on-site work of both contractors and
and Utterback, 1995; Zwikael, 2009; Globerson and Zwikael,
subcontractors (Jha and Iyer, 2006). In a recent investigation on
2002). While the final aim of a company is to improve the success
the role of quality using the perspective of the iron triangle of
of a project, each process during the planning phase, follows
cost, time and quality Basu (2014) highlighted that there is a
particular objectives. For example, although appropriate cost
strong correlation between organisational quality and criteria
planning will help to achieve success in the project (Belout and
such as stakeholder management, project leadership and top
Gauvreau, 2004; Yu et al., 2006), it is particularly necessary to
management support. However according to Walker(2000)
ensure that a realistic cost limit determined by factors such as
there is a gap in previous studies and he affirms that the
availability of money and market demand is established.
implementation of quality efforts is often hindered by a lack of
According to PMI (2013, p.64), A cost estimate is needed for a
attention to the expectations and views of the stakeholders
contingency plan involves integration of the planning process.
regarding exactly what quality means in the construction
Similarly, quality planning is necessary to ensure that the quality
industry. Yang (2010) emphasised that there are several
objectives that meet the requirements of key stakeholders are
stakeholders whose expectations and influences must be included
achieved.
in the project management process. More importantly, it has been
underlined that if the project's stakeholders are not satisfied with
the quality of the ongoing project management, or project 5.1. Quality planning process
outcomes, the project team will as a result be required to adjust
scope, time and cost in order to meet the stakeholders' According to Applebaum et al. (2004) quality management and
expectations on quality issues. Bubshait (1994) provides a clear improvement should start from the beginning of the planning
interaction between project quality and stakeholder involvement phase, not when the customer receives the project. One advantage
shown in Fig. 2. of beginning quality improvement practices in upfront project
The above figure shows that project quality can be measured phases is that higher quality planned-in early in the project
by determining the degree to which the implementation of the front-end development work will ensure fewer issues are created
project is in conformity with terms (i.e., specifications), duration, in the later stages of the process, hence resulting in better final
budgets, aesthetics, operation, and the stakeholders' overall quality delivery (Leszaka et al., 2002). Many organisations
satisfaction with project quality. It affirms that stakeholder currently concentrate their efforts on quality improvement
integration in different phases of a project lifecycle is in direct and programmes (Senaratne and Jayarathna, 2012), nonetheless, the
mutual relationship with the project quality. However, the current literature shows that these programmes are not always generating
research mainly focuses on examining SI level in the planning the expected quality improvements (Lam, 1997). This is possibly
phase of projects as the majority of the vital decisions are due to a key reason stated by Juran and Blanton Godfery (1999),
completed during this stage and the ultimate success of the that is the absence of an effective quality planning process before
A. Heravi et al. / International Journal of Project Management 33 (2015) 985997 989

implementing quality practices. Hence, repeatedly the extant and planning process is the quality management plan, which defines
current literature highlights that quality planning is the most how the project management team should implement the
important phase in a business quality management process and performing company's quality policy. It (PMI, 2013) also
therefore requires more investigation and consideration (Senaratne stresses that a key consideration to be borne in mind is that
and Jayarathna, 2012). Quality planning is a disciplined process project planning and quality planning should not be treated as
designed to make sure that the structured set of quality assurance separate processes since they include many similar activities
and control activities is complete. These activities will ensure that that interact with each other as well as with other processes of
an organisation can implement a high quality project on time and the planning phase.
to the satisfaction of customers and stakeholder's needs and
specifications (Juran and Blanton Godfery, 1999). Juran and 6. Study method
Blanton Godfery's (1999) grouping of quality planning, which is
used specifically in this research, has been applied to a number of 6.1. Research aim and methodology
fields of study including the construction sector. They (Juran and
Blanton Godfery, 1999) grouped the main steps of quality The main objective drawn this research study is:
planning into five phases that are illustrated below in Fig. 3.
In this planning process, the purpose of the first phase (EP) is to - To evaluate the extent of current stakeholder involvement in
provide clear goals and correct directions of the project. Some of the planning process of construction building projects.
the major tasks of this step include: identify the projects to fulfil
the organisation's strategy, clarify the mission of each project, This study used a questionnaire-based survey to facilitate the
allocate project team members and prepare a complete project achievement of the main research objective. Two main
plan. The next phase (IS) provides a systematic identification and characteristics describe the purposes of a survey. Firstly,
complete understanding of all project stakeholders and their needs, surveys aim to produce some descriptions about the distribution
expectations and requirements. By identifying customers and of phenomena in a population (Ling et al., 2008; Pinsonneault
explicitly assessing their expectations, the understating and and Kraemer, 1993). Therefore, a survey analysis may be
perception gaps can be avoided. concerned with comparing the relationship between variables,
The specific project/product, quality planning tools, tech- or with demonstrating the finding, descriptively (Zikmund
niques and technology for the industry are required to be et al., 2000). Secondly, surveys are used to collect information
applied to produce an effective design, conforming fully to from research population through use of structured questions.
stakeholders needs. Identifying and implementing the activities Additionally, a survey provides a means for collection of a
that result in delivering the final project that conforms to such large amount of data from a substantial population in a highly
requirements and without deficiencies are main purposes of economical way and it also operates on a foundation of
phase 3 (DP1) (Juran and Blanton Godfery, 1999). Phase 4 statistical sampling to protect a particular representative dataset
(DP2) ensures that the whole process and its elements are made (Fellows and Liu, 2008).
capable enough to deliver the project as it was planned and The survey used in this study focuses on the perceptions of
designed. It also monitors that the process is consistent with four key stakeholder groups including:
project strategic objectives. Lastly, the operational gap can be
closed in phase 5 (CO) by developing and efficiently Owner/developer
transferring the plans over to the operational team. According Construction/project management
to PMI (2013), one of the important outputs of the quality Designer
Contractor,

Phase 1: Establish the Project (EP)


who are/have been involved in medium and high-rise residential
building projects. These stakeholder groups as stated by many
scholars have the highest inuence on the project and its nal
Phase 2: Idenfy Stakeholders and outcomes (Hwang and Lim, 2013; Joaquin et al., 2010; Low Sui
Collect their Needs (IS) and Ke-Wei, 1996).

The Quality 6.2. Grouping questions and survey distribution


Planning Process Phase 3: Develop the Project (DP1)
Main Steps
To design and setup the survey questionnaire, enquiry
questions were grouped from the general to the more specific.
Phase 4: Develop the Process (DP2)
The first section of the questionnaire was developed to collect
information about the demographic characteristics of stake-
holders in terms of work experience, roles in their projects and
Phase 5: Control and Operaon
the type of projects they were involved in. Since this study
focuses on residential building projects, it was important that
Fig. 3. The planning process phases to achieve quality requirements. the respondents were/are involved in these types of projects.
990 A. Heravi et al. / International Journal of Project Management 33 (2015) 985997

Table 1
Feedbacks from pilot survey.
Draft Respondents Method Comments and Suggestion
First draft 6 Academics Face to face interview A few of the factors in the planning process and some of the quality issues were
7 Industry practitioners Email found unreasonable or unnecessary
Some factors should be reworded
Add some more information about the purpose of the survey to the cover letter
Include a section where the respondents can add more comments
Second draft 3 Academics Email Rephrase some statements
2 Industry practitioners

Information about their organisational roles is also important consistency of the quantitative data and to make the interpretation
for comparing different levels of stakeholder involvement. In of results more meaningful, several initial processes were
the second section of the survey, questions were designed to undertaken. These processes include categorising data, editing
answer the main research question which is; data, coding data and creating data files. Descriptive statistical
analysis, particularly the measurement of central tendency (mean,
What is the current level of stakeholder involvement in the median), and the measurement of variation (standard deviation)
planning process of construction building projects? was undertaken for the following reasons:

As mentioned in Section 5.1 the quality planning process is To profile the respondents in terms of position, work experience
divided into five phases. Each phase contains a number of and their role in projects in which they were involved.
corresponding factors that constitute the objectives of that To examine the current level of stakeholder involvement in
phase. These factors were derived from the quality planning different phases of the planning process.
process proposed by Juran and Blanton Godfery (1999). In
order to adapt the process with the project management context, The required results to answer the research question were
it was then completed with the concepts of planning and quality achieved through a comprehensive descriptive analysis (shown
planning derived from PMBoK (PMI, 2013). The questionnaire in Section 7.2); however, in order to statistically test whether
was reviewed, revised and validated by adding, removing and organisational roles have an influence on stakeholder involve-
changing some items originally presented in the pilot test. As a ment levels a parametric analysis of variance (ANOVA) test
result 37 questions were presented to evaluate the current level was also conducted.
of stakeholder involvement in the five phases of the planning
process. Respondents were asked to demonstrate the level of 6.4. Pilot study
involvement by answering to the following question; Please
tick the box which best describe your involvement level to the Questionnaires are typically designed to collect data from
following activities of the planning process of the project. A certain groups of respondents. The pilot study is necessary to
five point Likert scale with a range from 1 representing Not improve the validity and efficiency of the experiment before the
Involved/Very Low to 5 Very High measured the respon- actual data collection starts. A pilot study is usually small
dents' perceived levels of involvement. compared to the main data collection process. Although
implementing a pilot study does not assure success in the
main study, it does enhance the probability of success. It is
6.3. Method of analysis suggested that in construction and project management
research, a draft of questionnaire should be tested to ensure
The data collected from questionnaire were analysed using a that all questions are logical and understandable (Yang and
popular statistical analysis software, the Statistical Package for Pheng, 2008). Respondents from both academia and industry
Social Science (SPSS) version 19.0 (2010). To ensure the were selected to participate in the pilot test. Academic experts

Table 3
Table 2 Dispersion of respondents/sampling results.
Reliability test (Cronbach's Alpha).
Types of stakeholders Number Required number in
Alpha Phase Items N each group (stratum)
0.77 Establish the project 5 77 Owner/developer 260 22
0.80 Identify stakeholder/customer 4 77 Construction and project management 290 24
0.90 Develop the project 15 77 Designer 195 16
0.86 Develop the process 8 77 Contractor 205 17
0.85 Control and operation 5 77 Total 970 79
A. Heravi et al. / International Journal of Project Management 33 (2015) 985997 991

Table 4
Stakeholder profile analysis.
Position indicated Percent Organisational role Percent Years of experience Percent
Project manager 24.7 Construction/project management 32.5 610 years 5.2
Job manager 15.6 Owner/ 27.3 1115 years 29.9
developer
Project coordinator/director 23.4 Contractor 22 More than 16 years 64.9
Job manager 11.7 Designer 18.2
Lead architect 6.5
Lead project planner 9
Other 9
Total 100 Total 100 Total 100

from the construction and project management discipline were 6.6. Sampling and response rate
selected to provide their opinion on the theoretical aspects of
the questionnaire. Six academics provided useful feedback and It is often hard economically, and also infeasible and lengthy to
their knowledge and experience assisted to improve the collect the data from every member of the population (Levy and
shortcomings of the initial survey draft. The industry group Lemeshow, 1999), therefore a sample of population has become
were practitioners who were/are involved in the residential practical to survey so that generalisation can be contingent from
sector such as project managers, contractors and designers. the sample to the entire population (Rea and Parker, 2005). It
Seven respondents finally participated and made practical and involves the selection of a small number of people and it is
valuable comments that could help to improve the quality of the important they are adequate representatives of the whole
questionnaire. From the 13 people who agreed to participate in population.
the pilot survey, six people preferred a face-to-face interview To facilitate sampling for this study, the list of stakeholders
and seven people chose to provide their feedback and according to their organisational roles was gathered from reliable
comments by email. The major feedback obtained from the and valid resources such as Brisbane City Council and Master
pilot survey is outlined in Table 1. Builder Associations of Queensland. Around one thousand
companies were found that related to the context of this research
and these were divided into four main groups. Two methods of
6.5. Reliability analysis sampling were applied to determine the required number of
responses, random sampling and stratified sampling. Ran-
A number of methods are available for determining the dom sampling was first used to calculate the required amount of
consistency (reliability) of multiple item scales. To examine the population for the actual data collection stage. Then, using a
reliability of data, Cronbach's alpha was used to consider the stratified random technique, the required number of responses
internal consistency (Bryman and Hardy, 2009). Items with a from each group of participants was determined. The first step to
value equal to or greater than 0.7 were considered reliable. apply this technique is calculating the size of the whole sample
According to Sekaran and Bougie (2009), the value of alpha () through simple random, or systematic sampling techniques and
greater than .80 is considered to be good, between .07 and .08 is then dividing the result by size of the population, and finally
acceptable and below .07 is poor. Table 2 shows that each of multiplying the results by the size of each group (stratum).
the planning items is reliable as the alpha coefficients were all Table 3 shows the final results of sampling.
greater than 0.77. To facilitate the number of responses, approximately 200
questionnaires were distributed during the months of April and

Table 5 Table 6
The level of involvement in the EP phase. The level of involvement in the IS phase.
Groups of stakeholders Value Std. error Groups of stakeholders Value Std. error
Owner/developer Mean 3.5 .093 Owner/developer Mean 3.6 .091
Median 3.25 Median 3.75
SD .43 SD .420
Construction/project Mean 3.5 .124 Construction/ Mean 3.7 .126
management Median 3.5 project management Median 3.75
SD .623 SD .634
Designer Mean 3.1 .149 Designer Mean 3.4 .191
Median 3.25 Median 3.6
SD .56 SD .716
Contractor Mean 2.2 .109 Contractor Mean 2.5 .090
Median 2.25 Median 2.5
SD .45 SD .372
992 A. Heravi et al. / International Journal of Project Management 33 (2015) 985997

Table 7 (27.3%) and 17 respondents (22.%) are contractors, closely


The level of involvement in the DP1 phase. followed by 14 designer respondents, (18.2%). Considering the
Groups of stakeholders Value Std. error number of each group in the sampling list, this percentage
Owner/developer Mean 3.4 .051 confirms that appropriate number of responses was received.
Median 3.4 Results of the work experience indicate that nearly 65% of
SD .234 the participants have been working more than 16 years in the
Construction/project Mean 3.5 .114
construction industry. 29.9% of respondents had 11 to 15 years
management Median 3.5
SD .571 of work experience in the industry and only 5.2% involved less
Designer Mean 3.3 .146 than 10 years in the industry. This profile signifies the high
Median 3.2 level of experience on which the results of this survey were
SD .549 based.
Contractor Mean 2.4 .045
Median 2.4
SD .187 7.2. The analysis of stakeholder involvement level

The primary aim of the analysis in this section is to


May 2012 and 85 responses were returned of which 77 were valid determine the current level of four groups of stakeholder's
for data analysis. This represents a response rate of 31%, which involvement in five phases of the planning process. Each of
according to Yehuda (1999) is a satisfactory number of responses these phases includes items corresponding to the objectives of
from an overall population sector. Eight responses were found to that phase.
be unacceptable because the respondent's current or previous
employment status, based on the criteria of this research, was not 7.2.1. Stakeholder involvement level in five phases of the
suitable or many questions were left unanswered and resulted in planning process
some incomplete sections. It was found that owner/developer (O/D) and construction/
project management (C/PM) groups were highly involved in the
7. Survey analysis project establishment phase. This can be observed from the mean
and median scores shown in Table 5 which are around 4.
7.1. Analysis of stakeholder profile Designers on the other hand, do not contribute so highly in the
activities of this phase. The lowest involvement is found amongst
Investigating the general profile of the research population is the contractor group, where the mean score of the responses is
important to be considered prior to analysing and interpreting around 2.4 representing below average engagement.
the findings (Egemen and Mohamed, 2006). Table 4 summa- Results shown in Table 6 indicate that the level of
rises the respondent's profile in terms of their position, involvement is above average for both O/D and C/PM groups
organisational role in the project and years of experiences. in the IS phase. This can be concluded from the mean score of the
Using an open-ended question format, respondents were responses. Since the important decisions in relation to collecting,
able to identify their position on their projects, or within their assessing and unifying stakeholder's demands are completed by
companies. Results indicate that more than 90% of the these two groups, they need to adopt a common approach to
respondents were from the top and middle management levels. improving their levels of involvement and contribution in this
Since this research focuses on the strategic management level, phase. The mean and median scores are close to the value of 3
the results of this section confirm that appropriate people were representing average involvement of designers. Finally the lowest
approached. It is shown, the highest return rate was from degree of contribution is for contractors with a mean score of 2.2.
construction/project management companies with 25 respon- Results shown in Table 7, demonstrate a fairly similar
dents (32.5%), whereas owner/developers have 21 responses situation for the three groups of O/D, C/PM and designers in

Table 8 Table 9
The level of involvement in the DP2 phase. The level of involvement in the CO phase.
Groups of stakeholders Value Std. error Groups of stakeholders Value Std. error
Owner/developer Mean 3.9 .084 Owner/developer Mean 2.9 .083
Median 3.8 Median 3
SD .387 SD .381
Construction/ Mean 3.9 .12 Construction/ Mean 3 .187
project management Median 4.2 project management Median 2.8
SD .604 SD .936
Designer Mean 3.2 .206 Designer Mean 3 .261
Median 3.2 Median 2.6
SD .773 SD .978
Contractor Mean 2.4 .088 Contractor Mean 2.5 .090
Median 2.4 Median 2.6
SD .364 SD .373
A. Heravi et al. / International Journal of Project Management 33 (2015) 985997 993

the Developing the Project phase. This is perceived from the Table 11
mean score representing an above average (but still less than The results of the KruskalWallis test ranking.
high) degree of involvement in this phase of the planning Ranks
process. Because many important activities such as grouping Organisation role in the project N Mean rank
stakeholder's needs, developing the project schedule, develop Establish the project Owner/developer 21 50.86
project goals and features, and identifying acceptance criteria Construction/project management 25 46.62
for project deliverables are implemented in this phase, a higher Designer 14 39.21
level of contribution of key project members is generally Contractor 17 12.97
Identify customers Owner/developer 21 46.69
expected.
Construction/project management 25 46.60
The mean and median scores shown in Table 8 demonstrate Designer 14 42.21
that C/PM and O/D group levels of involvement are close to Contractor 17 15.68
high in the Developing the process phase. In contrast, the Develop the project Owner/developer 21 46.38
contractor's level of involvement in this phase is below Construction/project management 25 47.64
Designer 14 43.82
average. Compared to the contractors, designers are more
Contractor 17 13.21
involved as their mean score is above the average. Develop the process Owner/developer 21 43.48
It was found that the O/D and C/PM groups, compared to the Construction/project management 25 47.22
other phases, are slightly less involved in the Control and Designer 14 47.25
Operation phase. This can be observed from the mean and Contractor 17 14.59
Control & operation Owner/developer 21 46.14
median scores (presented in Table 9), which are around 3,
Construction/project management 25 40.26
indicating an average involvement level. Even though contrac- Designer 14 39.54
tors are less involved than other groups, the median score of 2.6 Contractor 17 27.88
shows their higher engagement in this phase compared to other
phases of the planning process.
(p b 0.05). This means that SI level is significantly different in
7.3. Comparing levels of stakeholder involvement four of the five phases of the planning process. Findings,
however, do not demonstrate any statistically significant
This section compares the levels of stakeholder involvement difference in the mean ranking of the CO phase.
in the planning process, based on their organisational roles in Table 11 provides a ranking summary of the data. It
the project and using the KruskalWallis and Mann demonstrates the lower scores of mean ranking of contractors
Whitney non-parametric tests. Both methods are designed to compared to the other stakeholders in four phases of EP, IS,
identify whether two or more samples come from the same DP1 and DP2 of the planning process.
underlying population, or to test whether the medians between To follow-up the findings from the KruskalWallis test,
comparison groups are different. However, the main difference the MannWhitney test was conducted to determine where a
between these methods is that while the MannWhitney test significant difference exists amongst stakeholders in the mean
is applied to compare scores between two groups, the ranking of their responses. The MannWhitney test is also
KruskalWallis test (also referred to as the distribution relevant for data-sets at ordinal level. It tests the hypothesis that
free test) can accommodate the comparison between more than the median of the two groups are equal (Ho, 2006). By default,
two groups (Bryman and Cramer, 2009). The KruskalWallis the statistical software used in this research calculates the
test is appropriate for data at ordinal level (Sadiqi et al., 2013) significance of the MannWhitney and KruskalWallis
and is used in this research because the data-sets are ordinal and using the asymptotic method. This method is considered to be
measured using a Likert scale. This test was conducted to more reliable for use with large samples, but less so with
determine if the involvement levels amongst the four stake- smaller samples. However, in both large and small samples, the
holder groups in the planning process were significantly exact test is the most precise way to determine significance
different. Table 10 illustrates the overall results of the and therefore is used in the analysis in this section.
KruskalWallis test. It suggests that a significant difference A Bonferroni Correction is a multiple-comparison correction
exists in mean ranking of ratings in EP, IS, DP1, and DP2 made to P values when some statistical tests are being performed

Table 10
The results of the KruskalWallis test statistics.
Test statistics a,b
Planning phases Establish the project (EP) Identify stakeholder (IS) Develop the project (DP1) Develop the process (DP2) Control and operation (CO)
Chi-Square 32.319 24.371 29.364 26.515 6.520
df 3 3 3 3 3
Asymp. Sig. .000 .000 .000 .000 .089
a
KruskalWallis test.
b
Grouping variable: what is your organisation role in the project?
994 A. Heravi et al. / International Journal of Project Management 33 (2015) 985997

Table 12
The results of the MannWhitney test.
Stakeholders Establish the Identify Develop the Develop the Control and
project (EP) stakeholder (IS) project (DP1) process (DP2) operation (CO)
Owner-contractor MannWhitney U 5.000 19.000 5.500 25.500 73.000
Exact Sig. [2*(1-tailed Sig.)] .000 .000 .000 .000 .001
Project manager- contractor MannWhitney U 34.000 60.500 60.500 40.500 154.500
Exact Sig. [2*(1-tailed Sig.)] .000 .000 .000 .000 .139
Designer-contractor MannWhitney U 28.500 34.000 5.500 29.000 93.500
Exact Sig. [2*(1-tailed Sig.)] .000 .000 .000 .000 .316
Owner-designer MannWhitney U 91.500 129.500 125.500 115.500 141.500
Exact Sig. [2*(1-tailed Sig.)] .061 .561 .474 .293 .855
Owner-project management MannWhitney U 242.500 247.000 223.000 235.000 223.500
Exact Sig. [2*(1-tailed Sig.)] .659 .741 .387 .548 .391
Project manager-designer MannWhitney U 143.000 152.500 150.500 169.000 162.500
Exact Sig. [2*(1-tailed Sig.)] .361 .515 .478 .874 .718

concurrently on a single data set. To apply this method, the P process. It indicates that the C/PM group, compared to others, has
value () is divided by the number of comparisons being made. A the most efficient levels of incorporation, especially in the EP
Bonferroni Correction was applied (6 comparisons were made phase where the median score is above 4. Although involvement
between four stakeholder groups) and all effects are reported as levels of the O/D and C/PM groups are nearly the same, the boxes
being at a 0.008 (0.05/6 = 0.008) level of significance. Results show a wider dispersion of data amongst the C/PM group,
shown in Table 12, suggest that there is a significant difference in especially in the DP1 and DP2 phases. Compared to the O/D and
the mean rankings between contractors and other stakeholders in C/PM groups, designers are generally less involved. However,
four phases of EP, IS, DP1 and DP2. However, no significant this discrepancy is very low in the DP2 and CO phases. While the
difference was found between O/D, CP/M and designers' level of figure illustrates that there is no significant difference amongst
involvement. the first three groups of respondents, contractors are demonstrat-
Fig. 4 provides a visual summary of the involvement level of ing a considerably lower level of involvement in all phases of the
different stakeholder groups in five phases of the planning planning process.

Fig 4. Compare stakeholder involvements in planning process phases.


A. Heravi et al. / International Journal of Project Management 33 (2015) 985997 995

8. Discussion Once the project has been developed, it is essential to


determine and establish the processes by which the project will
This study culminates a comprehensive evaluation of current then be developed and delivered. The level of team involvement
level of stakeholder involvement in project planning phases. It in developing the process (DP2) was found to be less than high,
was determined that designers and contractors are not highly but still above average and this can be related to many factors.
involved in establishing the project where the key objectives Sometimes, a project has varying degrees of complexity and it
are normally to identify the projects, determine the scope, goals was determined that establishing and monitoring the various
and objectives and establishing a mechanism to achieve the processes for complex projects requires a substantially higher
identified objectives, selecting the project team and defining level of competency. Aje (2012) confirms that in the construction
project resources and their limitations. This can be attributed to industry, where many companies are involved, the process of
the lack of attention paid by these groups to the importance of determining participants must place an emphasis on their
understanding the role of key stakeholders and the significance of technical, practical and managerial skills. But finding a stake-
their inputs into the decision-making (DM) process. Arditi and holder, especially a contractor with a high enough level of
Murat Gunaydin (1997); Marosszeky et al. (2002) reinforced this proficiency is not always easy. In addition, deciding on the most
view, stating that even though project performance depends on accurate methods to implement the processes needs a perfect
creating a team relationship between contractors, designer and the understating of the project and its specific features. Indeed when
owner in the project initial phases, it has not been evidenced much participants do not possess adequate and correct information, or
in the residential building sector. Additionally, the type of project are not expert enough, implementing such processes cannot be
delivery adopted by project owners, in many cases, determines the fully facilitated.
stages where both designers and contractors can get engaged in Analysis of the survey data revealed that the contractors'
project planning. Therefore, they (the owners and developers) involvement in the planning phase of projects was considerably
need to carefully select the right contract type to improve the lower compared to other stakeholders. In many cases, contractors
effective involvement of these former stakeholder groups. are attributed simply as builders and they are assigned only for
In spite of the fact that correctly identifying key stakeholders the execution of the project. Therefore they get engaged when the
and analysing their needs and requirements, is a necessary part planning and design is almost complete, the scope, objectives and
of the planning phase, and that the ability to correctly identify stakeholders are identified, the acceptance criteria are determined
and manage stakeholders can mean the difference between and the project process is established. However, depending on the
success and failure (PMI, 2013). This study determined that type of the contract, they may get involved prior to the design
owners and developers are not highly engaged in a systematic phase, but after the planning is mainly completed. It was found
identification process. This issue may be the result of certain that in such situations, the contractor involvement level is low
causes; for instance, lack of knowledge and information about and that can negatively impact on subsequent project quality.
the project and its features can be a major barrier to effective Low Sui and Ke-Wei (1996) confirm that the quality of the
interaction between the owner and the project. Olander (2007) construction project is largely dependent on the attitudes of
suggested that poor client knowledge can negatively influence contractors. Sometimes the contractor's objectives do not align
both the project and its stakeholders. The quality planning of with the strategic project objectives, which might result in
most projects will be challenged by the large number of conflict amongst different parties and affect the final quality
stakeholder needs, and therefore the project team should outcomes. However, interacting with contractors in the early
classify and assess those needs and demands properly. phases of a project can help prevent such conflict. Contractors are
The project development (DP1) phase is where the project is sometimes assigned to carry out the project from beginning to the
actually operationalized. Activities such as grouping of related end. In that case they will get engaged in the conceptual and
stakeholders' needs, determining the method of identifying project planning phases but they are more a developer in this instance,
features, identifying the quality expectations, are all completed in rather than a contractor. Another reason for the low level of
this phase. In spite of the significance of this phase, it was found contractors' contributions could be the issue of competitiveness.
that owners/developers and designers do not contribute greatly to Involving contractors in the very initial stages might result in the
the successful achievement of the phase objectives. One of the project losing the competitive edge during the tendering process.
reasons for this may be due to the lack of full commitment of these Such early involvement can also create a misconception amongst
two groups to accurately implement the activities related to this contractors that they have already been pre-selected to be the
phase. This lack of full commitment can be the result of poor company finally undertaking the construction phase.
awareness of both the significance, and the advantages, of
applying these activities towards achieving success in a project. 9. Conclusions
As discussed in the literature review section, appropriate
management and involvement of stakeholders as well as meeting This study has evaluated the current level of SI during
quality requirements (that are included as major activities in this different phases of the planning process. It highlights the
phase) are two main project success factors. If, therefore, key weaknesses and strengths of the four stakeholder groups in
project members can expand their awareness and contribute to the different phases of the process. It was found that the O/D group
achievement of objectives of this phase, this could help to attain and C/PM groups were more involved than the designer group.
project success. Results revealed that contractors have the lowest level of
996 A. Heravi et al. / International Journal of Project Management 33 (2015) 985997

contribution within early project stages. The low level of Baccarini, Danial, 1999. The logical framework method for defining project
contractor involvement suggests the need to engage them as success. Proj. Manag. J. 30 (4), 2532.
Bal, Menoka, Bryde, David, Fearon, Damian, Ochieng, Edward, 2013.
early as possible through, for example, use of an integrated Stakeholder engagement: achieving sustainability in the construction sector.
project delivery method. Sustain. J. 6, 695710.
Results of this study could provide project managers and Basu, Ron, 2014. Managing quality in projects: an empirical study. Int. J. Proj.
owners with the required information and a direction as to Manag. Elsevier 32, 178187.
Belout, Adnane, Gauvreau, Clothilde, 2004. Factors influencing project success:
where SI improvement plans should begin. Although the
the impact of human resource management. Int. J. Proj. Manag. 22 (111).
important activities of the planning process require effective Bosher, L., Dainty, A., Carrillo, P., Glass, J., Price, A., 2007. Integrating
engagement and great contribution of major parties involved in disaster risk management into construction: a UK perspective. J. Build. Res.
the project, according to the outcomes of this research, such Inf. 35 (2), 163177.
engagement is not fully evident in the residential building Bourne, L., Walker, D.T.H., 2005. Visualising and mapping stakeholder
sector. Findings from this research affirm that project leaders influence. Manag. Decis. 43 (5), 649660.
Brian, Aktin, Martin, Skitmore, 2008. Stakeholder management in construction.
and owners should adopt improved decision-making strategies Constr. Manag. Econ. 26 (6), 549552.
and design a plan to enhance the effectiveness of SI from the Bryman, Alan, Cramer, Duncan, 2009. Quantitative data analysis with spss
beginning of the project to its completion stages. 14,15 and 16: a guide for social scientists. Sussex 408 1 edition (December
The survey conducted in this research used only the perceptions 3, 2008).
of four stakeholder groups including owner, developer, con- Bryman, A., Hardy, M.A., 2009. Hand book of Data Analysis: Sage Publication.
Bubshait, Abdulaziz A., 1994. Owner involvement in project quality. Int.
struction/project management, designers and contractors. J. Proj. Manag. 12 (2), 115117.
Taking into account the perspectives of other project members Cole, R.J., 2005. Building environmental assessment methods: redefining
such as, subcontractors, suppliers and surrounding social environ- intentions and roles. J. Build. Res. Inf. 33 (5), 455467.
ment could provide a more complete picture of involvement level Deming, W.E., 1986. Out of the Crisis. Massachusetts Institute of Technology,
in the whole community of stakeholders. This research provided Center for Advanced Engineering Study.
Egemen, M., Mohamed, A.N., 2006. Client's need, wants and expectations
some valuable understanding about the issue of poor stakeholder from contractors and approach to the concept of repetitive works in the
involvement during the decision-making process, and as a result Northern Cyprus construction market.J. Bus. Ind. Mark. 17, 107118.
low level of contribution in other phases of the PLC. However, El-Gohary, N.M., Osman, H., Ei-Diraby, T.E., 2006. Stakeholder management
further investigations are still required to improve the solutions to for public private partnerships. Int. J. Proj. Manag. 24 (7), 595604.
these complex problems. Furthermore, outcomes of this research Fellows, Richard, Liu, Anita, 2008. Research Methods for Construction. Third
ed. Wiley-Blackwell, Oxford.
provide a basis for further development of a framework which Freeman, R.E., 1984. Strategic Management: a Stakeholder Approach.
aims to improve and enhance the involvement of stakeholders in Globerson, S., Zwikael, O., 2002. Impact of the project manager on project
the project. It has been revealed from this research that serious management planning processes. Proj. Manag. J. 33 (3), 5864.
consideration should be given to facilitating the more effective Ho, Robert, 2006. Handbook of Univariate and Multivariate Data Analysis and
Interpretation with SPSS. Chapman & Hall/CRC.
incorporation of different project members during the project life
Hwang, Bon-Gang, Lim, E-Sin Janicia, 2013. Critical success factors for key
cycle. poject players and objectives: case study of Singapore. J. Constr. Eng. Manag.
The main focus of this research was on high-rise and ASCE 139, 204215.
medium-rise residential building projects. It is suggested that IFC, 2007. Stakeholder Engagement: A Good Practice Handbook for Companies
further research is undertaken using the outputs of this study, to Doing Business in Emerging Market (Washington).
incorporate results from an examination that includes other types Jha, K.N., Iyer, K.C., 2006. Critical factors affecting quality performance in
construction projects. Total Qual. Manag. 17 (9), 11551170.
of building projects. This study also collected data from projects Joaquin, David, Hernandez, Delgado, Aspinwall, Elaine, 2008. A framework
in Brisbane, Australia. Further studies may be undertaken to test for building quality into construction projectspart I. Total Qual. Manag.
the findings in other locations in Australia, or globally. 19 (10), 10131028.
Joaquin, David, Hernandez, Delgado, Aspinwall, Elaine, 2010. A framework
for building quality into construction projectspart II. Total Qual. Manag.
Conict of interest 21 (7), 725736.
Johnson, G., Scholes, K., 1999a. Exploring Corporate Strategy. Prentice Hall
Europe.
The authors declare they have no conflicts of interest. Johnson, G., Scholes, K., 1999b. Exploring Corporate Strategy (London).
Jones, Thomas, Wicks, Andrew, 1999. Convergent stakeholder theory. Acad.
Manag. Rev. 24 (2), 206221.
References Juran, Joseph M., Blanton Godfery, A., 1999. Juran's Quality Handbook Vol. 5.
McGraw-Hill, New York.
Abdul-Kadir, M.R., Price, A.D.F., 1995. Conceptual phase of construction Kolltveit, Bjrn Johs, Grnhaug, Kjell, 2004. The importance of the early
projects. Int. J. Proj. Manag. 13 (6), 387393. phase: the case of construction and building projects. Int. J. Proj. Manag.
Aje, Isaac, 2012. The impact of contractors' prequalification on construction Elsevier 22, 545551.
project delivery in Nigeria. Eng. Constr. Archit. Manag. 19 (2), 159172. Lam, S.S.K., 1997. Quality planning performance: the relationship between
Applebaum, Robert, Schneider, Barbara, Kunkel, Suzanne, Davis, Shawn, 2004. objectives and process. Int. J. Qual. Reliab. Manag. 14 (1), 1023.
A Guide to Quality in Consumer Directed Services. Miami University. Leszaka, Marek, Perryb, Dewayne E., Stoll, Dieter, 2002. Classification and
Arditi, David, Murat Gunaydin, H., 1997. Total quality management in the evaluation of defects in a project retrospective. J. Sys. Softw. 61, 173187.
construction process. Int. J. Proj. Manag. 15 (4), 235243. Leung, Mei-yung, Yu, Jingyu, Liang, Qi, 2013. Improving public engagement
Atkin, B., Skitmore, M., 2008. Stakeholder management in construction. in construction development projects from a stakeholder perspective.
Constr. Manag. Econ. 26 (6), 549552. J. Constr. Eng. Manag. 139, 04013019.
A. Heravi et al. / International Journal of Project Management 33 (2015) 985997 997

Levy, Paul S., Lemeshow, Stanley, 1999. Sampling of Populations: Methods Saghatforoush, Ehsan, Trigunarsyah, Bambang, Too, Eric, HeraviTorbati,
and Applications. John Wiley and Sons, New York. AmiHossein, 2010. Effectiveness of constructability concept in the provision
Li, Terry, Ng, Thomas, Skitmore, Martin, 2013. Evaluating stakeholder of infrastructure assets. Paper presented at the eddBE 2011 Conference.
satisfaction during public participation in major infrastructure and construction Queensland University of Technology, Brisbane, Australia (April 2011).
projects: a fuzzy approach. Autom. Constr. Elsevier 29, 123135. Sekaran, U., Bougie, R., 2009. Research Methods for Business: A Skill-Building
Lim, C.S., Mohamed, Z.M., 1999. Criteria of project success: an exploratory Approach, edited by. Fifth ed. Wiley, Chichester-UK.
reexamination. Int. J. Proj. Manag. 17 (4), 243248. Senaratne, Sepani, Jayarathna, Thushangi, 2012. Quality planning process of
Ling, F., Low, S., Wang, S., Egbelakin, T., 2008. Models for predicting project construction contractors: case studies in Sri Lanka. J. Constr. Dev. Countries
performance in China using project management practices adopted by 17 (1), 101114.
foreign AEC firms. J. Constr. Eng. Manag. 134 (12), 983990. Shenhar, A.J., Dvir, D., Levy, O., Maltz, A.C., 2001. Project success: a
Low Sui, Pheng, Ke-Wei, Phe, 1996. A framework for implementing TQM in multidimensional strategic concept. 34 (6), 699725.
construction. TQM. Soetanto, Robby, Proverbs, David G., Holt, Gary D., 2001. Achieving quality
LU, A.G., Flett, P.D., Bowers, J.A., 2005. Developing a value-centred proposal construction projects based on harmonious working relationships.Int.
for assessing project success. Int. J. Proj. Manag. 23 (6), 428436. J. Qual. Reliab. Manag. 18 (5), 528548.
Marosszeky, R. Thomas, Marton, Khalid Karim, David, S., McGeorge, D., SPSS, 2010. SPSS Inc. (http://www.spss.com/).
2002. The importance of project culture in achieving quality outcomes in Stoney, C., Winstanley, D., 2001. Stakeholding: confusion or utopia? Mapping
construction. Paper presented at the IGLC, Brazil. the conceptual terrain. J. Manag. Stud. 35 (5), 603626.
Meyer, Marc H., Utterback, James M., 1995. Product development cycle time Toakley, A.R., Marosszeky, M., 2003. Towards total project qualitya review
and commercial success. IEEE Trans. Eng. Manag. 42 (4), 297304. of research needs. J. Eng. Archit. Manag. 10 (3), 219228.
Miller, R., Lessard, D., 2001. Understanding and managing risks in large Verbeke, Alain, Tung, Vincent, 2013. The future of stakeholder management
engineering projects. Int. J. Proj. Manag. 19, 437443. theory: a temporal perspective. J. Bus. Ethics 112 (3), 529543.
Morris, P.W.G., Hough, G.H., 1986. The preconditions of success and failure in Walker, D.H.T., 2000. Client/customer or stakeholder focus? ISO 14000 EMS
major projects. Oxf. Major Proj. Assoc. (3). as a construction industry case study. Total Qual. Manag. 12 (1), 1825.
Newcombe, R., 2003. From client to project stakeholders: a stakeholder Walker, D.H.T., 2003. Procurement Strategies: A Relationship-based Approach.
mapping approach. Constr. Manag. Econ. 21 (841848). Blackwell Publishing, Oxford.
Olander, Stefan, 2002. Consensual approaches to siting controversy. Constr. Wang, Xiaojin, Huang, Jing, 2006. The relationships between key stakeholder's
Innov. Glob. Compet. 2, 909920. project performance and project success: perceptions of Chinese construc-
Olander, S., 2006. External stakeholder analysis in construction project tion supervising engineers. Int. J. Proj. Manag. 24, 253260.
management. (PhD Thesis). Lund University. Westerveld, E., 2003. The project excellence model: linking success criteria and
Olander, S., 2007. Stakeholder impact analysis in construction project critical success factors. international. J. Proj. Manag. 21 (6), 411418.
management. Constr. Manag. Econ. 25 (3), 277287. Winch, G., Bonke, S., 2002. Project stakeholder mapping: analysing the
Olander, S., Landin, A., 2005a. Evaluation of stakeholder influence in the interests of project stakeholders. Project Management Institute, Manchester,
implementation of construction projects. Elsevier Int. J. Proj. Manag. 23 (4), pp. 385403.
321328. Yang, Jing, 2010. Stakeholder management in construction: an empirical study
Olander, S., Landin, A., 2005b. Evaluation of stakeholder influence in the to address research gaps in previous studies. Elsevier, International Journal
implementation of construction projects. Int. J. Proj. Manag. 23 (4), 21. of Project Management.
Phillips, R., 2003. Stakeholder Theory and Organisational Ethics. Berrett- Yang, J.B., Pheng, S.C., 2008. Development of customer satisfaction evaluation
Koehler Publishers Inc., San Francisco. model for construction project management. Build. Environ. 43 (4), 458468.
Pinsonneault, Alain, Kraemer, Kenneth L., 1993. Survey research methodology Yehuda, Baruch, 1999. Response Rate in Academic Studiesa Comparative
in management information systems: an assessment. J. Manag. Inf. Syst. 10 Analysis. SAGE Publ. 52 (4).
(2), 75105. Yin, Robert K., Heald, Karen A., 1975. Using the case survey method to
PMI, 2013. A Guide to the Project Management Body of Knowledge (PMBOK). analyze policy studies. Adm. Sci. Q. 20 (3), 371381.
Fifth ed. Project Management Institute (PMI). Yu, Ann T.W., Shen, Qiping, Kelly, John, Hunter, Kirsty, 2006. Investigation
Rea, Louis M., Parker, Richard A., 2005. Designing and Conducting Survey of critical success factors in construction project briefing by way of content
Research. Jossey-Bass, San Francisco. analysis. J. Constr. Eng. Manag. ASCE 132 (11), 11781186.
Sadiqi, Zabihullah, Coffey, Vaughan, Trigunarsiyah, Bambang, 2013. Post- Zikmund, William G., Babin, Barry J., Carr, Jon C., Griffin, Mitch, 2000.
Disaster Reconstruction: A Statistical Overview of the Barriers for Business research methods. vol. 6. Dryden Press Fort Worth.
Community Participation in Afghanistan. Paper presented at the Interna- Zwikael, Ofer, 2009. Critical planning processes in construction projects.
tional Institute for Infrastructure Renewal and Reconstruction, Queensland Constr. Innov. 9 (4), 372387.
University of Technology.

Potrebbero piacerti anche