Procedure
Consequences
Emp Can Employ Others To Complete Work - Using Acc, Plant, Mats Etc
Empr May Insist (Except Insolvency) To Take On Assignment Of Subs
All Equip Must = Removed When Ca Instructs
Mc Not = Payment Until Completion
Entitlement = Ct Sum Minus Cost Of Getting Works Complete Inc L&E / Damages, Usually Main Cr
Owes Empr
Jct 98 - By Cr - Clause 28
Consequences
Cr And Subs Must Remove All Equip / Mats (Insurances For Injury / Damage Remain Inforce)
Payment - Mc Entitled To :-
Value Of Work Completed At Time Of Determination
Value Of Work Begun But Not Completed
Mats Ordered (Then Become Property Of Empr)
Costs Of Removal From Site
Outstanding L&E Claims
L&E Caused By Determination
Either Party Can Determine If Works Are Suspended For The Continuous Period, Stated In The
Appx, Due To The Following Events (28a.1)
Force Majeure
Loss Or Damage Due To One Or More Of Spec Perils
Civil Commotion
Ais Issued Due To Negligence Of Stat Auth
Hostilities Involving UK
Terrorist Activity
Must Not Be Caused By Crs Negligence
Notice Given By Either Party, Cr Employt Suspended Within 7 Days, Unless Suspension Is
Terminated Within That Period
Cr Must Remove Temp Bldgs, Tools Etc From Site
Cr Paid One Half Of Any Retention Ddt Prior To Determination
Within Two Mths Cr Must Provide All Info To Empr To Prepare Account
Including Value Of Work Exec
Any Direct Loss & Expense
Reasonable Costs Of Removal
Cost Of Mats / Gds Ordered For Which Cr = Legally Bound To Pay
Gc Works 1
(Empr Determination - Cr As Jct)