INSTITUTO TECNOLOGICO DE LA LAGUNA

Unidad No.3
Problemas

Alumna: Cristina Guerrero Rojas


#14130989

Materia: Sntesis y optimizacin de procesos


Docente: Ing. Kenia Crispn Garca

Torren, Coahuila a 21 de Noviembre del 2017


Problema #1

En el sistema se bombea agua a 20c a razn de 100 galones por minuto, estima el costo de la bomba si el
rendimiento es del 70%.

Elevacin Z2=12 m (400 ft)

90 m (300
Tubera de acero 3 pies)
in ced.40

Vlvula de retencin de 2.5 con 4 codos estndar de 90,


obturador ascendente y guas de 3 in rosca
laterales, instalada con
reducciones en una tubera de 3
30 m (100
in
pies)

Elevacin Z1= 0
Z

10 m (30 pies) 20 m (70 pies)

q=100 gpm = 6.309x10-3 m3/seg

Di=7.793 cm

a 20c = 998.23 kg/m3

a 20c = 1.005 cp
1
= ( ( ) + )

2 + + + 4
= ( )
2

6.309103
= = 2 = 1.323
0.07793)
( 4 )


= 1 ( ) = 1


= 0.4 (1 ( )) = 0.4

kg
(0.07793 ) ( 998.23 m3) (1.323 )
= = = 1.31106

1.005

0.000045
= = 0.00058 = 0.0043
0.07793

120
4 = 4 (0.0043) ( ) = 33.11
0.07793

Accesorios Kf
Vlvula de compuerta totalmente 0.2
abierta
Codos estndar 90 0.9

Vlvula de retencin con obturador ascendente.

> 1 1 = 600 < 1


K1 = 600 ft = 600(0.018)=10.8
6.271
= =( ) = 0.8047
1.793

1 + ((0.5)(1 2 ) + (1 2 )2 )) 10.8 + 0.8047((0.5)(1 0.80472 ) + (1 0.80472 )2 ))


2 = =
4 0.80474
K2= 26.33

Kf = 4(0.9) + 1(0.2) + 26.33 = 30.13


1.3232 1 + 0.4 + 26.33 + 33.11
= ( ) = 5.77
2(9.8)
1
= ( (120 0) + 5.77 ) = 179.67
0.7
3
3
= = (998.23 ) ( 6.30910 ) = 6.298 /
3
( )
= = 179.67 6.298 = 1131.56

( ) 1 1
= (. )( )( ) = 14.88
( ) 1.0138
75


= = 1714 = 14.88 1714 = 25504.32
1714
Presin de succin, psig= valor mximo 150

Mxima temperatura del sistema = 250F (ya que es agua lo que se bombea)

Factor Fo= 1

Material hierro moldeado Fm = 1

Costo base = $1786


Costo bomba = (1786*1*1)= $1786
Cmd = $1786*3.48 = $6215.28
Cmda =$6215.28+(1786-1786) = $6215.28
Cmda 2017= $6215.28 (566.6/113.7) = $30972.538
Cmda con 15% de contingencia= $35618.42

Se estim el precio de la bomba para el ao 2017 ya que no se especific en el problema.

Problema #2

Se desea estimar la inversin requerida para la siguiente parte de un proceso de desarrollo

Vapor 212F

= 1000 BTU/h Intercambiador de calor


Intercambiador de
T=77F U=200 BTU/ hr* ft2 F
calor
Construido de AC
FA=50 000 lb/h (coraza) y monel
(tubos)
CpA = 1 BTU/lb F
Cabeza flotante
Reactor

Reactor

Dimetro=3 ft
Altura =6 ft
Construido de AC

a) Estime la inversin requerida para cada uno de los equipos usando el mtodo de Guthrie. Base su
estimacin para 1998
b) Calcule el costo anual de vapor para este esquema si su costo unitario es de 1 c/ lb y se trabajan 8500
horas al ao.
c) Si la corriente de salida del reactor se desea vender y se desprecia el precio de la materia prima estime
el precio de venta si se desea una tasa mnima de recuperacin despus de impuestos del 15%..
suponga que la produccin de la mezcla a vender es equivalente a 2 000 000 lb/ao.
a) Costo de intercambiador de calor
Fd = 1
Fp = 0
Fm = 2.3

Q= mA* CpA(T2-T1) = (50000 lb/hr)(1 Btu/lbF)(177-77) = 5x106 BTU/h


(21277)(212177)
= 135 = 74.08F

35


=

5x106 BTU/h
1 = = 337.473 2

(200 2 )( 74.08)

Costo base = $4400


Costo intercambiador (4400*(1+0)*2.3)=$10120
Cmd = $4400*3.39 = $14916
Cmda =$14916+(10120-4400) = $20636
Cmda 1998= $20636 (389.5/113.5) = $70816.9339
Cmda con 15% de contingencia= $81 439.474

Costo de Reactor

Fm = 1

Fp=1

Costo base =$1437.5


Costo reactor = (1437.5*1*1)=$1437.5
Cmd=1437.5*4.34 =$6328.75
Cmda =6328.75+(1437.5-1437.5) =$6328.75
Cmda 1998= $6328.75 * (389.5/113.5) = $21409.631
Cmda con 15% de contingencia = $24621.0757

b)

mA*CpA(T2-T1)=mB* B


(50000 )(1 )(17777)
= =5000 /
1000 /
Vapor

5000 lb 1c 1$ 8500 h =$425000 / ao


hr 1 lb 100 c 1 ao

C)

Inversin de equipos es el 30% del total entonces inversin total = $353535.1657



ROI = 15% =
= = (0.15)($353535.1657) = $53030.2747

Mano de obra es el 5% de la I total =$17676.7583

d=e=10% y t =35%

$442676.7583
= + + + = $425000 + $17676.7583 =

= ( ) $53030.2747 = (0.1353535.1657) 0.35 ( (0.1353535.1657))
$116938.5546
=

$559615.3129
= = + = $116938.5546 + $442676.7583 =

$559615.3129 1
= ( )( ) = $0.2798 /
2000000

Problema #3

Una columna de destilacin procesa 12000 lb/h de una solucin acuosa que contiene 5% de NH3 en peso y
produce un flujo de destilado de 3000 lb/hr con una concentracin de 20% en peso. Estime la inversin total
requerida para los 3 componentes de equipo en 1997. Indique explcitamente cada suposicin que haga.

Datos de la columna.

Dimetro = 3.5 ft; altura = 8 ft, con 5 platos de cachucha (o campanas) cn espaciamiento de 1 ft y de AC

Datos del hervidor.

rea = 200 ft2, tipo kettle, AI (tubos) y AC (coraza)

Datos del condensador

A= 2000 ft2, tubo y coraza, monel (tubos) y AC (coraza)


XD= 20%

D=3000 lb/hr

Condensador
12000 lb

5% NH3

95% H2O

Hervidor

B=9000 lb/hr

Costo de columna de destilacin:

Recipiente vertical

Fm = 1
Fp = 1 (ya que no se especifica , adems que el NH3 no tiene una presin de vapor muy alta)
Costo base = $2000
Costo columna = (2000*1*1)= $2000
Cmd = $2000*4.34 = $8680
Cmda= $8680 + (2000-2000) = $8680
Cmda 1997 = $8680* (386.5/113.7) =$29505.8927
Cmda con 15% de contingencia = $33931.7766

Platos

Fs = 2.2
Ft= 1.8
Fm =0
Costo base = $172.86
Costo platos = [$172.86 (2.2+1.8+0)] =$691.44
Cmd = =$172.86* 4.34 =$750.2124
Cmda = [750.2124 + (691.44-123.86)]=$1286.7924
Cmda para 1997 = $1286.7924 *(386.5/113.5) = $4313.0014
Cmda con 15% de contingencia = $4959.9516
Costo total de columna de destilacin= $4959.9516+$33931.7766= $38891.7282

Costo de condensador:

Fd=1.35
Fp=0
Fm-3.1
Costo base =$13846.1539
Costo condensador = $13846.1539 (1.35+0)*3.1 = $57946.1541
Cmd=$13846.1539*3.39 =$46938.4617
Cmda = $46938.4617+($57946.1541-$13846.1539)=$91038.4619
Cmda1997 =$91038.4619*(386.5/113.7)=$309466.7153
Cmda con 15% de contingencia = $355 886.7226

Hervidor
Fd = 1.35
Fp=0
Fm = 1.78
Costo base = $3000
Costo hervidor = [$3000*(1.35+0)*1.78]=$7209
Cmd=$3000*3.39=$10 170
Cmda = $10170+(7209-3000)=$14379
Cmda 1997 = $14379*(386.5/113.7)=$48878.4829
Cmda con 15% de contingencia =$56210.2553

Inversin de equipos total = $38891.7282 + $355 886.7226 + $56210.2553 = $450988.7061