Demanda 1 2 3 4 5

4321 4630 4939 5248 5557

Precio 380
CV
Goma 62.8
Fibra 85.2
MOD 25
173
Costo F
G. Adm 96000
G. Gene 36000

Activos V. Salvamento Depreciacion


L. Produccion 210000 84000 25200
Obras Fisicas 650000 390000 52000
Terreno 100000
Monto
1 458,753.30
Capital de trabajo Inversione total 2 389,351.47
747533 L. P 210000 3 310,233.39
62294.416667 O. fisicas 650000 4 220,038.78
186883.25 Terreno 100000 5 117,216.92
C. de trabajo 186883.25
Inv. Total 1146883.25

Prestamo 458753.3
Prestamo 14%
WACC 14.40%
Imp 15%

Pago S/.133,627.29
Amort. Interes Pago Saldo
69,401.83 64,225.46 133,627.29 389,351.47
79,118.08 54,509.21 133,627.29 310,233.39
90,194.61 43,432.67 133,627.29 220,038.78
102,821.86 30,805.43 133,627.29 117,216.92
117,216.92 16,410.37 133,627.29 0.00