Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
CHAPTER 17
PROJECT MANAGEMENT
Teaching Notes
In managing operations, we are often faced with activities that do not fit into the usual day-to-day
operations of the firm. These non-typical, unusual activities of the firm are called projects. Due to their
unique nature, projects require different management approaches and techniques. A list of project
examples is given below:
1. Installation of a new bar coding system
2. Installation of a new computerized production and inventory control system
3. Design and development of a product prototype
4. Feasibility study to decide whether to buy new machinery
5. Acquisition and installation of new CNC (Computer Numerically Controlled) machinery
6. Conversion of the plant layout from process layout to group technology layout
7. Selection of a new plant site
8. Construction of a new facility
9. Planning, organizing, and managing a professional conference or a trade show
10. Planning, organizing, and managing major sports events such as the Olympics, sports festivals,
the NCAA basketball tournament, etc.
Project management involves planning, controlling, and directing the non-typical activities facing the
firm. In managing projects, project managers are assigned to schedule the work, to adhere to a given
budget, and to monitor the progress of the work through its various stages. For larger projects, project
teams are formed. These project teams may include workers from within the company involved in the
project and from other outside companies (e.g., a consulting firm). Depending on the size and type of the
project, an internal project manager and possibly project team members may receive full or partial release
from their regular duties. This duty release is given because it would be very difficult for an employee to
manage the responsibilities of a time consuming project and to fulfill the responsibilities of normal day-
to-day activities.
Projects are not necessarily single-time events. They can be repeated in similar settings. In managing a
project, the project team is usually responsible for managing and controlling the following four factors:
1. The length of project completion time
2. Resources
3. Quality
4. Cost
Projects progress through a life cycle consisting of five phases:
1. Initiating: Outlining the expected costs, benefits, and risks associate with a project. It also
includes defining major project goals and choosing a project manager.
2. Planning: Providing details on deliverables, the scope of the project, the budget, the schedule and
milestones, performance objectives, resources needed, a quality plan, and a plan for handling
risks.
3. Executing: the actual work of the project is carried out. The project is managed as activities are
completed, resources are consumed, and milestones are reached.
17-1
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
4. Monitoring and Controlling: This phase occurs at the same time as project execution. It involves
comparing actual progress with planned progress, taking corrective action if needed, and
monitoring and corrective action to ensure that it achieves the desired effect.
5. Closing: This phase ends the project and involves handing off the project deliverables, obtaining
customer acceptance, documenting lessons learned, and releasing resources.
However, because project work is unique, one-time operations designed to accomplish a set of
objectives in a limited timeframe, the project manager must exhibit leadership skills. Leadership
skills are less tangible than the skills listed above and may include the following:
a. the ability to deal with change.
b. deciding what changes are needed and when to make the changes.
c. working with the project team to make the necessary changes.
d. the ability to handle undesirable or unexpected consequences of making changes.
e. the ability to manage/motivate people with varying background and skills who may also be
reporting to other managers in their respective functional areas.
f. the ability to persuade and cooperate with others to fulfill project goals given that the project
manager may not have the formal authority to accomplish some of the goals of the project.
2. The project champion is the person within the company who is designated to promote and support
the project. The project champion can be instrumental in facilitating the work of the project
manager by promoting the project to other managers who might be asked to share resources with
the project team. The project champion also promotes the benefits of the project to employees
who may be asked to work on portions of the project. Because the project champion plays a very
important role in facilitating the project, both the project manager and the project team need to
keep the project champion informed about the status of the project. The project manager and team
may inform the project champion through a combination of face-to-face meetings and status
reports.
17-2
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
17-3
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
d. There may be a tendency to focus solely on activities that are on the critical path. As the
project progresses, other paths may become critical. Furthermore, major risk events may not
be on the critical path.
9. A probabilistic estimate of a projects completion time based solely on the variance of the critical
path might be misleading because near-critical paths can have distributions that overlap the
distribution of the critical path time, which may result in a lower probability of timely completion
than that based solely on the time distribution of the critical path. When path time distributions do
not overlap, probabilistic estimates based solely on the critical path are acceptable.
10. a. Expected activity time is a weighted average of optimistic, most-likely, and pessimistic time
t o 4t m t p
for each activity: t e
6
b. Variance of an activity measures the extent of activity variability.
(t p t o )2
Variance
36
c. The standard deviation of a paths time is a measure of the extent of variability of path time.
It is computed by summing the variances of activities that comprise the path and then taking
the square root of that sum.
11. A person might wish to be involved with a critical path activity because the critical path generates
more attention than the other paths do. Hence, those associated with activities that are on the
critical path are often in the spotlight. If they perform well, there is a good possibility for
recognition and reward. On the other hand, there can be an inordinate amount of pressure
associated with the critical path activities, and some would just as soon avoid that pressure.
12. Potential benefits of working on projects include the dynamic environment that surrounds a
project, the challenge of working under pressure and solving new problems, opportunities to meet
new people and to increase future job opportunities, the status among fellow workers from being
associated with the project, and the team spirit to achieve successful project completion.
Some of the risks associated of working on a project include working for two bosses who impose
different demands, the disruption in friendships and daily routines, the risk of being replaced on
the current job, and the fear of being associated with an unsuccessful project because of the
adverse effect it might have on career advancement.
13. Some aspects of the project managers job that make it more demanding than the job of a
manager working in a more routine framework include: Authority may not be commensurate with
responsibility, the environment often is more dynamic than is the case with more routine jobs,
there may be a much wider range of skills among subordinates, conflicts may arise between
project workers and those not involved with the project (e.g., on other projects or non-project
work), and balancing time, cost, and quality objectives can be stressful.
14. The main benefit of the project organization is the focus on project activities that results from
having project team members work full-time only on project activities.
17-4
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Taking Stock
1. The trade-offs associated with time and cost estimates for a proposed project involve the
relationship between spending and time. A project manager could crash (shorten) a project by
spending more on additional resources for critical path activities.
2. When assessing the cost of a project, the project manager, specialized project personnel dedicated
to handling certain project activities, someone from the finance department, and someone from
top management must be involved in assessing the cost of a project.
3. Two ways that technology has had an impact on project management:
a. Project management software: As project management software becomes more sophisticated,
the ability of a project manager to manage, direct, and control different aspects of the project
becomes easier.
b. Internet and e-mail: The ability to obtain quotes and prices on the Internet has provided a
significant convenience and has reduced the negotiation times for various activities, making
the prices of activities more competitive. Both the Internet and e-mail make sharing project
files easier for team members also. Finally, the Internet enables project team members in
remote locations to hold virtual meetings to discuss status reports, issues, etc.
17-5
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Solutions
1. Use the network diagrams given in the text to determine both the critical path and the expected
project duration. The critical path and the expected project duration are indicated below with an
*. Expected duration for each path equals the sum of the activity times on the path.
a.
Path Expected Duration
12471012 4 + 9 + 5 + 2 + 3 = 23
12581012 4 + 8 + 7 + 2 + 3 = 24
13691112 10 + 6 + 4 + 5 + 6 = 31*
d.
17-6
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
2. a. Ch Sh
Lib Sel
Out Inst
Write
Ck
Sub
Note: The answers for this problem assume that Chris will prepare the paper on the new
computer, but will prepare the outline by hand.
c. The paths and their expected duration times are given below. Expected duration for each path
equals the sum of the activity times on the path.
Expected
Path Duration
Ch-Lib-Out-Write-Ck-Sub 6.7 hours
Sh-Sel-Inst-Write-Ck-Sub 7.5 hours*
Conclusion: Critical path is Sh-Sel-Inst-Write-Ck-Sub and the expected duration is 7.5
hours.
d. The project could take longer than the expected duration if any activity on the critical path is
delayed or if the other activities on the parallel path (Ch-Lib-Out) are delayed by more than
0.8 hours (7.5 6.7).
17-7
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
3. a. Bank location.
Weeks after start
Activity 2 4 6 8 10 12 14 16 18 20
1-2
1-3
2-4
2-5
3-5
4-5
5-6
17-8
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
4. a.
A
E
Dummy
Immediate
Activity Predecessor
A
B
C A
E C
F A,B
End E,F
17-9
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
D
2
A 5
E K
B End
F H
1 3 6 8
C I
G
4 7
L 5
M
2 N
J 6 P
End
9
V
K R
1 3 7
Q W
S
4 T
8
17-10
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
A D
Start B E
End
F H
C G I
L M
J
N P
K R
V
Start
S
Q End
T
W
17-11
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
LS LF
21 26 ES EF
5. a. 21 13 5 18 26
13 18
4 7
12 9 2 28
4 20
11 28
4 2 10 21
8
11 2 3 31
7 4 4 7 28 24
0 21
5 8
19 26
12 19 26
19 12
1 12 19
31
0 10 6 31
0
11 25
10
3 6 5 25
10 25
10 4 25
10 9
6 20
16 16 20 20
16 16 20
Summary:
Activity ES EF LS LF Slack
12 0 4 7 11 7
13 0 10 0 10 0
24 4 13 12 21 8
25 4 12 11 19 7
36 10 16 10 16 0
47 13 18 21 26 8
58 12 19 19 26 7
69 16 20 16 20 0
710 18 20 26 28 8
810 19 21 26 28 7
911 20 25 20 25 0
1012 21 24 28 31 7
1112 25 31 25 31 0
Note: Slack = LS ES or LF EF.
17-12
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
5. b.
Summary:
Activity ES EF LS LF Slack
1 0 5 0 5 0
2 5 23 5 23 0
3 5 18 20 33 15
4 23 26 37 40 14
5 23 33 23 33 0
6 33 37 40 44 7
7 33 44 33 44 0
8 44 53 44 53 0
9 53 55 53 55 0
Note: Slack = LS ES or LF EF.
LS LF
ES EF
37 40
23 26
5 23 40 44
5 23 4 33 37
3
2 23 33 6
23 33
18 4
0 5 44 53 53 55
0 5 44 53
5 53 55
10
1
20 33 8 9
5
5 18 33 44
33 44 9 2
3
7
13
11
17-13
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
6. The network diagram is given in Problem 1, Part a. After 12 weeks, activities 1-2, 1-3, and 2-4
have been finished; activity 2-5 is 75% finished; and activity 3-6 is 50% finished. How many
weeks after the original start date time should the project be finished. The original path expected
durations are given below:
One way of solving this problem is to look at the effects on each path:
Path 1-2-4-7-10-12:
Activities 1-2 and 2-4 were estimated to require take 4 + 9 = 13 weeks. They finished in 12
weeks. In other words, Activity 2-4 finished 1 week early. The net effect is to reduce the expected
time of this path by 1 week to 22 weeks.
Path 1-2-5-8-10-12:
Activities 1-2 and 2-5 were estimated to require 4 + 8 = 12 weeks. Activity 2-5 is 75%
completed; therefore, 25% of the activity time (.25 * 8 = 2 weeks) remains. Activity 2-5 should
have been completed at the end of 12 weeks but is running 2 weeks late. The net effect is to
increase the expected time of this path by 2 weeks to 26 weeks.
Path 1-3-6-9-11-12:
Activities 1-3 and 3-6 were estimated to require 10 + 6 = 16 weeks. Activity 3-6 is 50%
completed; therefore, 50% of the activity time (.50 * 6 = 3 weeks) remains. This means that this
activity should be completed 1 week early because it should be completed by the end of week 15.
The net effect is to reduce the expected time of this path by 1 week to 30 weeks.
Conclusion: The longest path (1-3-6-9-11-12) is estimated to take 30 weeks. Therefore, the
expected project duration is 30 weeks. The original estimated project duration was 31 weeks. We
estimate that the project should be completed 1 week early.
17-14
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
7. a. C
5
2 E
A
F G End
D 3 6
8
Start
1
B I
4 H
7
b. Activity te 2
A 6.00 4/36
B 8.50 9/36
C 8.17 25/36
D 12.00 36/36
E 6.33 16/36
F 6.00 4/36
G 3.50 25/36
H 4.17 1/36
I 6.83 9/36
Path A-C-E:
Expected duration = 6.00 + 8.17 + 6.33 = 20.50
Variance = 4/36 + 25/36 + 16/36 = 45/36
45
Standard deviation = = 1.118
36
Path D-F-G:
Expected duration = 12.00 + 6.00 + 3.50 = 21.50
Variance = 36/36 + 4/36 + 25/36 = 65/36
65
Standard deviation = 36 = 1.344
Path B-H-I:
Expected duration = 8.50 + 4.17 + 6.83 = 19.50
Variance = 9/36 + 1/36 + 9/36 = 19/36
19
Standard deviation = = 0.726
36
17-15
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
24 20.50
= = 3.13
1.118
Path D-F-G:
24 21.50
= = 1.86
1.344
Path B-H-I:
24 19.50
= = 6.20
0.726
21 20.50
= = 0.45
1.118
Path D-F-G:
21 21.50
= = 0.37
1.344
Path B-H-I:
21 19.50
= = 2.07
0.726
17-16
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
c. Assume it is the end of the 7th day. Activities A and B have been completed while
Activity D is 50% completed. Time estimates for the completion time of Activity D are
5, 6, and 7. Activities C and H are ready to begin. We can re-draw the network as shown
below.
Activity te 2
C 8.17 25/36
D 6.00 4/36
E 6.33 16/36
F 6.00 4/36
G 3.50 25/36
H 4.17 1/36
I 6.83 9/36
C (8.17) E (6.33)
Path C-E:
Expected duration from start of project = 7 + (8.17 + 6.33) = 21.50
Variance = 25/36 + 16/36 = 41/36
41
Standard deviation = 36 = 1.067
Path D-F-G:
Expected duration from start of project = 7 + (6.00 + 6.00 + 3.50) = 22.50
Variance = 4/36 + 4/36 + 25/36 = 33/36
33
Standard deviation = 36 = 0.957
17-17
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Path H-I:
Expected duration from start of project = 7 + (4.17 + 6.83) = 18.00
Variance = 1/36 + 9/36 = 10/36
10
Standard deviation = 36 = 0.527
24 21.50
= = 2.34
1.067
Path D-F-G:
24 22.50
= = 1.57
0.957
Path H-I:
24 18.00
= = 11.39
0.527
21 21.50
= = 0.47
1.067
Path D-F-G:
21 22.50
= = 1.57
0.957
17-18
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Path H-I:
21 18.00
= = 5.69
0.527
d. The partners want to shorten the project by 2 days as long as it does not cost more than
$20,000. The cost per day (in thousands) to crash activities is shown below:
Step 1:
The paths and their expected duration are shown below:
Activity F should be shortened 1 day because it has the lowest crashing cost ($7,000).
Path D-F-G now will be 21.50 days as shown below.
17-19
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Step 2:
The paths and their expected duration are shown below:
Conclusion: Total crashing cost is $7,000 + $8,000 + $8,000 = $23,000, which is $3,000
over budget. The partners have to determine whether the benefits of crashing the project
by 1 day or by 2 days are worth the extra cost.
17-20
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
8. Expected
Path Duration Variance Std. Dev.
A 10 1.21 1.100
B 8 2.00 1.414
C 12 1.00 1.000
D 15 2.89 1.700
E 14 1.44 1.200
Path A:
16 10
= = 5.45
1.100
Probability of completion 16 weeks = 1.0000 (z value > +3.00treat probability of completion
as being = 1.0000)
Path B:
16 8
= = 5.66
1.414
Probability of completion 16 weeks = 1.0000 (z value > +3.00treat probability of completion
as being = 1.0000)
Path C:
16 12
= = 4.00
1.000
Probability of completion 16 weeks = 1.0000 (z value > +3.00treat probability of completion
as being = 1.0000)
Path D:
16 15
= = 0.59
1.700
Using Appendix B Table B: Probability of completion 16 weeks = 0.7224
Path E:
16 14
= = 1.67
1.200
Using Appendix B Table B: Probability of completion 16 weeks = 0.9525
17-21
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Path A:
15 10
= = 4.55
1.100
Probability of completion 15 weeks = 1.0000 (z value > +3.00treat probability of completion
as being = 1.0000)
Path B:
15 8
= = 4.95
1.414
Probability of completion 15 weeks = 1.0000 (z value > +3.00treat probability of completion
as being = 1.0000)
Path C:
15 12
= = 3.00
1.000
Using Appendix B Table B: Probability of completion 15 weeks = 0.9987
Path D:
15 15
= = 0.00
1.700
Using Appendix B Table B: Probability of completion 15 weeks = 0.5000
Path E:
15 14
= = 0.83
1.200
Using Appendix B Table B: Probability of completion 15 weeks = 0.7967
17-22
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Path A:
13 10
= = 2.73
1.100
Using Appendix B Table B: Probability of completion 13 weeks = 0.9968
Path B:
13 8
= = 3.54
1.414
Probability of completion 13 weeks = 1.0000 (z value > +3.00treat probability of completion
as being = 1.0000)
Path C:
13 12
= = 1.00
1.000
Using Appendix B Table B: Probability of completion 13 weeks = 0.8413
Path D:
13 15
= = 1.18
1.700
Using Appendix B Table B: Probability of completion 13 weeks = 0.1190
Path E:
13 14
= = 0.83
1.200
Using Appendix B Table B: Probability of completion 13 weeks = 0.2033
17-23
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
9. Given:
Standard
Path Activity Mean Deviation
A C 5 1.3
D 4 1.0
B E 8 1.6
Path A:
Expected duration = 5 + 4 = 9
Standard deviation:
We must find the variance of the path first by squaring the individual standard deviations to find
the variance for each activity, add the variances, and take the square root of the sum.
Variance = 1.32 + 1.02 = 1.690 + 1.000 = 2.690
Standard deviation = 2.690 = 1.640
10 9
= = 0.61
1.640
Path B:
Expected duration = 8
Standard deviation = 1.600
10 8
= = 1.25
1.600
Using Appendix B Table B: Probability of completion 10 weeks = 0.8944
17-24
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
10. Given:
The project described below is scheduled to be completed in 11 weeks.
Standard
Path Activity Mean Deviation
A C 4 0.70
D 6 0.90
B E 3 0.62
F 9 1.90
a. If you were the manager of this project, would you be concerned? Explain.
Probability (T 11 weeks):
Path A:
Expected duration = 4 + 6 = 10
Standard deviation:
We must find the variance of the path first by squaring the individual standard deviations to
find the variance for each activity, add the variances, and take the square root of the sum.
Variance = 0.702 + 0.902 = 0.490 + 0.810 = 1.300
Standard deviation = 1.300 = 1.140
11 10
= = 0.88
1.140
Using Appendix B Table B: Probability of completion 11 weeks = 0.8106
Path B:
Expected duration = 3 + 9 = 12
Standard deviation:
We must find the variance of the path first by squaring the individual standard deviations to
find the variance for each activity, add the variances, and take the square root of the sum.
Variance = 0.622 + 1.902 = 0.384 + 3.610 = 3.994
Standard deviation = 3.994 = 1.998
11 12
= = 0.50
1.998
Using Appendix B Table B: Probability of completion 11 weeks = 0.3085
17-25
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
b. If there is a penalty of $5,000 a week for each week the project is late, what is the probability
of incurring a penalty of at least $5,000?
This question is asking what the probability will be that the project will take at least 12 weeks
(which would be 1 week late).
Probability (T 12 weeks):
Path A:
12 10
= = 1.75
1.140
Using Appendix B Table B: Probability of completion < 12 weeks = 0.9599
Path B:
12 12
= = 0.00
1.998
Using Appendix B Table B: Probability of completion < 12 weeks = 0.5000
17-26
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
11. Given:
We are given the following times (optimistic, most likely, and pessimistic) for each activity in the
table below.
a. Determine the expected completion time for each path and its variance.
Most
Activity Optimistic Likely Pessimistic Mean Variance
1-2 8 8 8 8.00 0/36
2-3 11 12 13 12.00 4/36
2-4 5 6 7 6.00 4/36
2-5 10 12 14 12.00 16/36
3-8 9 10 12 10.17 9/36
4-6 14 18 26 18.67 144/36
4-7 13 13 13 13.00 0/36
5-9 7 10 12 9.83 25/36
6-11 8 10 14 10.33 36/36
7-11 10.5 13 15.5 13.00 25/36
8-11 5 7 10 7.17 25/36
9-10 10 11 12 11.00 4/36
10-11 6 6 6 6.00 0/36
Path 1-2-3-8-11:
Expected completion time = 8.00 + 12.00 + 10.17 + 7.17 = 37.34
Variance = 0/36 + 4/36 + 9/36 + 25/36 = 38/36
38
Standard deviation = = 1.027
36
Path 1-2-4-6-11:
Expected completion time = 8.00 + 6.00 + 18.67 + 10.33 = 43.00
Variance = 0/36 + 4/36 + 144/36 + 36/36 = 184/36
184
Standard deviation = 36 = 2.261
Path 1-2-4-7-11:
Expected completion time = 8.00 + 6.00 + 13.00 + 13.00 = 40.00
Variance = 0/36 + 4/36 + 0/36 + 25/36 = 29/36
29
Standard deviation =36 = 0.898
17-27
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Path 1-2-5-9-10-11:
Expected completion time = 8.00 + 12.00 + 9.83 + 11.00 + 6.00 = 46.83
Variance = 0/36 + 16/36 + 25/36 + 4/36 + 0/36 = 45/36
45
Standard deviation =36 = 1.118
b. Determine the probability that the project will require more than 49 weeks.
Path 1-2-3-8-11:
49 37.34
= = 11.35
1.027
Probability of completion 49 weeks = 1.0000 (z value > +3.00treat probability of
completion as being = 1.0000)
Path 1-2-4-6-11:
49 43.00
= = 2.65
2.261
Using Appendix B Table B: Probability of completion 49 weeks = 0.9960
Path 1-2-4-7-11:
49 40.00
= = 10.02
0.898
Probability of completion 49 weeks = 1.0000 (z value > +3.00treat probability of
completion as being = 1.0000)
Path 1-2-5-9-10-11:
49 46.83
= = 1.94
1.118
Using Appendix B Table B: Probability of completion 49 weeks = 0.9738
17-28
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
c. Determine the probability that the project will be completed in 46 weeks or less.
Probability (T 46 weeks):
Path 1-2-3-8-11:
46 37.34
= = 8.43
1.027
Probability of completion 46 weeks = 1.0000 (z value > +3.00treat probability of
completion as being = 1.0000)
Path 1-2-4-6-11:
46 43.00
= = 1.33
2.261
Using Appendix B Table B: Probability of completion 46 weeks = 0.9082
Path 1-2-4-7-11:
46 40.00
= = 6.68
0.898
Probability of completion 46 weeks = 1.0000 (z value > +3.00treat probability of
completion as being = 1.0000)
Path 1-2-5-9-10-11:
46 46.83
= = 0.74
1.118
Using Appendix B Table B: Probability of completion 46 weeks = 0.2296
17-29
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
12. Given:
We are given the following times (optimistic, most likely, and pessimistic) for each activity in the
table below.
Most
Activity Optimistic Likely Pessimistic Mean Variance
A 2 4 6 4.00 16/36
D 6 8 10 8.00 16/36
E 7 9 12 9.17 25/36
H 2 3 5 3.17 9/36
F 3 4 8 4.50 25/36
G 5 7 9 7.00 16/36
B 2 2 3 2.17 1/36
I 2 3 6 3.33 16/36
J 3 4 5 4.00 4/36
K 4 5 8 5.33 16/36
C 5 8 12 8.17 49/36
M 1 1 1 1.00 0/36
N 6 7 11 7.50 25/36
O 8 9 13 9.50 25/36
End
M N
4 8 1
1
17-30
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
b. The project manager will receive a bonus of $1,000 if the project is finished within 26 weeks.
P (T 26):
Path A-D-E-H:
Expected completion time = 4.00 + 8.00 + 9.17 + 3.17 = 24.34
Variance = 16/36 + 16/36 + 25/36 + 9/36 = 66/36
66
Standard deviation =36 = 1.354
26 24.34
= = 1.23
1.354
Using Appendix B Table B: Probability of completion 26 weeks = 0.8907
Path A-F-G:
Expected completion time = 4.00 + 4.50 + 7.00 = 15.50
Variance = 16/36 + 25/36 + 16/36 = 57/36
57
Standard deviation =36 = 1.258
26 15.50
= = 8.35
1.258
Probability of completion 26 weeks = 1.0000 (z value > +3.00treat probability of
completion as being = 1.0000)
Path B-I-J-K:
Expected completion time = 2.17 + 3.33 + 4.00 + 5.33 = 14.83
Variance = 1/36 + 16/36 + 4/36 + 16/36 = 37/36
37
Standard deviation =36 = 1.014
26 14.83
= = 11.02
1.014
Probability of completion 26 weeks = 1.0000 (z value > +3.00treat probability of
completion as being = 1.0000)
Path C-M-N-O:
Expected completion time = 8.17 + 1.00 + 7.50 + 9.50 = 26.17
Variance = 49/36 + 0/36 + 25/36 + 25/36 = 99/36
99
Standard deviation =36 = 1.658
26 26.17
= = 0.10
1.658
Using Appendix B Table B: Probability of completion 26 weeks = 0.4602
Conclusion: The probability of receiving a bonus of $1,000 = Probability (T 26 weeks) =
0.8907 x 1.0000 x 1.0000 x 0.4602 = 0.4099
17-31
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
The project manager will receive a bonus of $500 if the project is finished within 27 weeks.
P (T 27):
Path A-D-E-H:
27 24.34
= = 1.96
1.354
Using Appendix B Table B: Probability of completion 27 weeks = 0.9750
Path A-F-G:
27 15.50
= = 9.14
1.258
Probability of completion 27 weeks = 1.0000 (z value > +3.00treat probability of
completion as being = 1.0000)
Path B-I-J-K:
27 14.83
= = 12.00
1.014
Probability of completion 27 weeks = 1.0000 (z value > +3.00treat probability of
completion as being = 1.0000)
Path C-M-N-O:
27 26.17
= = 0.50
1.658
Using Appendix B Table B: Probability of completion 27 weeks = 0.6915
17-32
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
13. Given:
We have the following list of activities for a project and crashing costs:
Middle D 3 $9 $11
E 7 $8 $9
C 3 $14 $15
Determine which activities should be crashed to shorten the project by 3 weeks as cheaply as
possible. Draw the precedence diagram first.
B
2
4
C
A E
7
D
3
1
H
6
F
G
5
17-33
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Step 1:
The paths and their expected duration are shown below:
Activity F should be shortened 1 week because it has the lowest crashing cost ($10). Path
F-G-H now will be 14 weeks as shown below.
Activities crashed to this point: Step 1: F (first crash).
Step 2:
The paths and their expected duration are shown below:
17-34
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Step 3:
The paths and their expected duration are shown below:
17-35
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Conclusion: Expected project duration = 12 weeks. Total crashing cost = $10 + $18 + $26 = $54.
17-36
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
14. Given:
We have the activities and crashing costs shown below:
A K
Start
End
C M
G
D N
P
E
H
F
J
I
17-37
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Determine a minimum-cost crashing schedule that will shave five weeks off the project length:
Step 1:
The paths and their expected duration are shown below:
Path Expected Duration
A-B-K 35
C-D-G-M 45
C-E-H-N 47
C-E-H-P 44
C-F-I-J-P 49
Critical path is C-F-I-J-P.
Rank critical activities according to crash costs:
Cost per Week
Activity to Crash
C $5
F $12
P $20
J $25
I $30
Activity C should be shortened 1 week because it has the lowest crashing cost ($5).
Paths C-D-G-M, C-E-H-N, C-E-H-P, and C-F-I-J-P all will decrease 1 week as shown below.
Activities crashed to this point: Step 1: C (first week).
Step 2:
The paths and their expected duration are shown below:
Path Expected Duration
A-B-K 35
C-D-G-M 44
C-E-H-N 46
C-E-H-P 43
C-F-I-J-P 48
Critical path is C-F-I-J-P.
Rank critical activities according to crash costs:
Cost per Week
Activity to Crash
C $5
F $12
P $20
J $25
I $30
Activity C should be shortened 1 week because it has the lowest crashing cost ($5).
Paths C-D-G-M, C-E-H-N, C-E-H-P, and C-F-I-J-P all will decrease 1 week.
Activities crashed to this point: Step 1: C (first week). Step 2: C (second week).
17-38
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Step 3:
The paths and their expected duration are shown below:
Path Expected Duration
A-B-K 35
C-D-G-M 43
C-E-H-N 45
C-E-H-P 42
C-F-I-J-P 47
Critical path is C-F-I-J-P.
Step 4:
The paths and their expected duration are shown below:
Path Expected Duration
A-B-K 35
C-D-G-M 43
C-E-H-N 45
C-E-H-P 42
C-F-I-J-P 46
Critical path is C-F-I-J-P.
17-39
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Step 5:
The paths and their expected duration are shown below:
Path Expected Duration
A-B-K 35
C-D-G-M 43
C-E-H-N 45
C-E-H-P 42
C-F-I-J-P 45
Critical paths are C-E-H-N and C-F-I-J-P.
17-40
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Length after Length after Length after Length after Length after
Path Initial crashing 1 crashing 2 crashing 3 crashing 4 crashing 5
time week weeks weeks weeks weeks
A-B-K 35 wk. 35 wk. 35 wk. 35 wk. 35 wk. 35 wk.
C-D-G-M 45 wk. 44 wk. 43 wk. 43 wk. 43 wk. 43 wk.
C-E-H-N 47 wk. 46 wk. 45 wk. 45 wk. 45 wk. 44 wk.
C-E-H-P 44 wk. 43 wk. 42 wk. 42 wk. 42 wk. 40 wk.
C-F-I-J-P 49 wk. 48 wk. 47 wk. 46 wk. 45 wk. 44 wk.
Step 1 Crashing Step 2 Crashing Step 3 Crashing Step 4 Crashing Step 5 Crashing
Activity Cost Activity Cost Activity Cost Activity Cost Activity Cost
C $5 C $5 F $12 F $15 E $16
P 20
$36
Conclusion: Expected project duration = 44 weeks. Total crashing cost = $5 + $5 + $12 + $15 + $36 =
$73(000) = $73,000.
17-41
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
15. Given:
We have the following activities and crashing costs ($000):
Crashing Costs ($000)
First Second Third
Activity Week Week Week
17-42
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Step 2:
The paths and their expected duration are shown below:
Path Expected Duration
1-2-5-7-11-13 34
1-3-8-11-13 32
1-3-9-12-13 20
1-4-6-10-12-13 33
Critical path is 1-2-5-7-11-13.
Rank critical activities according to crash costs:
Cost per Week
Activity to Crash
1-2 $18
7-11 $20
2-5 $24
5-7 $30
11-13 $30
Activity 1-2 should be shortened 1 week because it has the lowest crashing cost ($18) and
this cost is $40. Path 1-2-5-7-11-13 will decrease 1 week as shown below.
Activities crashed to this point: Step 1: 7-11 (first week). Step 2: 1-2 (first week).
17-43
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Step 3:
The paths and their expected duration are shown below:
Path Expected Duration
1-2-5-7-11-13 33
1-3-8-11-13 32
1-3-9-12-13 20
1-4-6-10-12-13 33
Critical paths are 1-2-5-7-11-13 & 1-4-6-10-12-13.
Rank critical activities according to crash costs:
Cost per Week
Path Activity to Crash
1-2-5-7-11-13 7-11 $20
1-2 $22
2-5 $24
5-7 $30
11-13 $30
1-4-6-10-12-13 6-10 $5
4-6 $8
1-4 $10
10-12 $14
12-13 $26
Activity 7-11 should be shortened 1 week because it has the lowest crashing cost ($20) on
Path 1-2-5-7-11-13, which will decrease 1 week as shown below.
Activity 6-10 should be shortened 1 week because it has the lowest crashing cost ($5) on
Path 1-4-6-10-12-13, which will decrease 1 week as shown below.
The combined crashing cost = $25 and is $40.
Activities crashed to this point: Step 1: 7-11 (first week). Step 2: 1-2 (first week). Step 3: 7-
11 (second week) & 6-10 (first week).
17-44
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Step 4:
The paths and their expected duration are shown below:
Path Expected Duration
1-2-5-7-11-13 32
1-3-8-11-13 32
1-3-9-12-13 20
1-4-6-10-12-13 32
Critical paths are 1-2-5-7-11-13, 1-3-8-11-13, & 1-4-6-10-12-13.
Rank critical activities according to crash costs:
Cost per Week
Path Activity to Crash
1-2-5-7-11-13 1-2 $22
2-5 $24
5-7 $30
11-13 $30
1-3-8-11-13 1-3 $12
11-13 $30
8-11 $40
1-4-6-10-12-13 4-6 $8
1-4 $10
6-10 $12
10-12 $14
12-13 $26
Activity 11-13 should be shortened 1 week on Paths 1-2-5-7-11-13 & 1-3-8-11-13 because it
has the lowest crashing cost ($30) to shorten both paths. Both paths will decrease 1 week as
shown below.
Activity 4-6 should be shortened 1 week because it has the lowest crashing cost ($8) on Path
1-4-6-10-12-13, which will decrease 1 week as shown below.
The combined crashing cost = $38 and is $40.
Activities crashed to this point: Step 1: 7-11 (first week). Step 2: 1-2 (first week). Step 3: 7-
11 (second week) & 6-10 (first week). Step 4: Activity 11-13 (first week) & Activity 4-6
(first week).
17-45
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Step 5:
The paths and their expected duration are shown below:
Path Expected Duration
1-2-5-7-11-13 31
1-3-8-11-13 31
1-3-9-12-13 20
1-4-6-10-12-13 31
Critical paths are 1-2-5-7-11-13, 1-3-8-11-13, & 1-4-6-10-12-13.
Rank critical activities according to crash costs:
Cost per Week
Path Activity to Crash
1-2-5-7-11-13 1-2 $22
2-5 $24
5-7 $30
11-13 $33
1-3-8-11-13 1-3 $12
11-13 $33
8-11 $40
1-4-6-10-12-13 1-4 $10
6-10 $12
4-6 $13
10-12 $14
12-13 $26
Activity 11-13 could be shortened 1 week on Paths 1-2-5-7-11-13 & 1-3-8-11-13 because it
has the lowest crashing cost ($33) to shorten both paths. Both paths would decrease 1 week.
Activity 1-4 could be shortened 1 week because it has the lowest crashing cost ($10) on Path
1-4-6-10-12-13, which would decrease 1 week.
The combined crashing cost = $43 and is > $40. Stop.
The marginal cost of crashing > marginal benefit of crashing. We stop crashing after Step 4.
17-46
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
b. Plot the total-cost curve that describes the least expensive crashing schedule that will reduce
the project length by 6 weeks:
In Part a of this problem, we reduced the project length by 4 weeks. We must decrease the
project length by 2 more weeks. We will start with Step 5 from Part a above.
17-47
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Step 5:
The paths and their expected duration are shown below:
Path Expected Duration
1-2-5-7-11-13 31
1-3-8-11-13 31
1-3-9-12-13 20
1-4-6-10-12-13 31
Critical paths are 1-2-5-7-11-13, 1-3-8-11-13, & 1-4-6-10-12-13.
17-48
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Step 6:
The paths and their expected duration are shown below:
Path Expected Duration
1-2-5-7-11-13 30
1-3-8-11-13 30
1-3-9-12-13 20
1-4-6-10-12-13 30
Critical paths are 1-2-5-7-11-13, 1-3-8-11-13, & 1-4-6-10-12-13.
17-49
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
The table below summarizes the cumulative crashing cost, indirect cost, and total cost for
project lengths of 35, 34, 33, 32, 31, 30, and 29 weeks:
Cumulative Cumulative
Project Weeks Crash Cost Indirect Cost Total Cost
Length Shortened ($000) ($000) ($000)
35 0 0 35(40) = 1,400 1,400
34 1 15 34(40) = 1,360 1,375
33 2 15 + 18 = 33 33(40) = 1,320 1,353
32 3 33 + 25 = 58 32(40) = 1,280 1,338
31 4 58 + 38 = 96 31(40) = 1,240 1,336
30 5 96 + 43 = 139 30(40) = 1,200 1,339
29 6 139 + 46 = 185 29(40) = 1,160 1,345
17-50
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
1,400
Total
Cost
($000)
1,300
0 29 30 31 32 33 34 35
Project Length
(weeks)
17-51
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
16. Given:
We have the following crashing costs for activities:
M
L P Z
Start K Q Y End
N J
Develop a crashing schedule given that Mr. T wants delivery in 32 weeks or he will impose a
penalty of $375 for each week his yacht is late:
We will crash as long as the crash cost at a step $375.
17-52
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Step 1:
The paths and their expected duration are shown below:
Activity Z should be shortened 1 week because it has the lowest crashing cost ($90) to crash
both critical paths, which both will decrease by 1 week as shown below. This cost is $375.
Activities crashed to this point: Step 1: Activity Z (1st week).
17-53
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Step 2:
The paths and their expected duration are shown below:
Activity L should be shortened 1 week because it has the lowest crashing cost ($125) on Path
K-L-M-Q-P-Z, which will decrease Paths K-L-M-Q-P-Z & K-L-M-Q-Y 1 week as shown
below.
Activity N should be shortened 1 week because it has the lowest crashing cost ($45) on Path
K-N-J-Q-P-Z, which will decrease Paths K-N-J-Q-P-Z & K-N-J-Q-Y 1 week as shown
below.
Combined crashing cost = $170. This cost is $375.
Activities crashed to this point: Step 1: Activity Z (1st week). Step 2: Activity L (1st week) &
Activity N (1st week).
17-54
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Step 3:
The paths and their expected duration are shown below:
Activity Q should be shortened 1 week because it has the lowest crashing cost ($200) to
crash both critical paths. This cost is $375. All four paths will decrease by 1 week as shown
below.
Activities crashed to this point: Step 1: Activity Z (1st week). Step 2: Activity L (1st week) &
Activity N (1st week). Step 3: Activity Q (1st week).
17-55
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Step 4:
The paths and their expected duration are shown below:
Activity Q should be shortened 1 week because it has the lowest crashing cost ($225) to
crash both critical paths. This cost is $375. All four paths will decrease by 1 week as shown
below.
Activities crashed to this point: Step 1: Activity Z (1st week). Step 2: Activity L (1st week) &
Activity N (1st week). Step 3: Activity Q (1st week). Step 4: Activity Q (2nd week).
17-56
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Step 5:
The paths and their expected duration are shown below:
Activity M should be shortened 1 week because it has the lowest crashing cost ($300) on
Path K-L-M-Q-P-Z, which will decrease Paths K-L-M-Q-P-Z & K-L-M-Q-Y 1 week as
shown below.
Activity N should be shortened 1 week because it has the lowest crashing cost ($45) on Path
K-N-J-Q-P-Z, which will decrease Paths K-N-J-Q-P-Z & K-N-J-Q-Y 1 week as shown
below.
Combined crashing cost = $345. This cost is $375.
Activities crashed to this point: Step 1: Activity Z (1st week). Step 2: Activity L (1st week) &
Activity N (1st week). Step 3: Activity Q (1st week). Step 4: Activity Q (2nd week). Step 5:
Activity M (1st week) & Activity N (2nd week).
17-57
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Step 6:
The paths and their expected duration are shown below:
Activity M could be shortened 1 week because it has the lowest crashing cost ($350) on Path
K-L-M-Q-P-Z, which would decrease Paths K-L-M-Q-P-Z & K-L-M-Q-Y 1 week.
Activity J could be shortened 1 week because it has the lowest crashing cost ($50) on Path
K-N-J-Q-P-Z, which would decrease Paths K-N-J-Q-P-Z & K-N-J-Q-Y 1 week.
However, combined crashing cost = $400. This cost is > $375. Stop.
17-58
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
17-59
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
17. Given:
We have the following activities and time estimates:
Bottom D 7 8 11
E 2 3 4
F 1 4 6
B 4
2
A C
Start 6 End
1
F
D
3 E 5
Standard
Path Activity Optimistic Most Likely Pessimistic Mean Deviation
Top A 4 5 6 5.00 4/36
B 7 8 10 8.17 9/36
C 3 5 9 5.33 36/36
Path A-B-C:
Expected completion time = 5.00 + 8.17 + 5.33 = 18.50
Variance = 4/36 + 9/36 + 36/36 = 49/36
Path D-E-F:
Expected completion time = 8.33 + 3.00 + 3.83 = 15.16
Variance = 16/36 + 4/36 + 25/36 = 45/36
17-60
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
b. Determine the probability that the project will take at least 18 days.
Probability (T 18):
Path A-B-C:
49
Standard deviation =36 = 1.167
18 18.50
= = 0.43
1.167
Using Appendix B Table B: Probability of completion < 18 days = 0.3336
Path D-E-F:
45
Standard deviation = = 1.118
36
18 15.16
= = 2.54
1.118
Using Appendix B Table B: Probability of completion < 18 days = 0.9945
17-61
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
18. Given:
We are given the events, probabilities, and costs in the table below:
Create a risk matrix for this project. Use a vertical scale of $0 to $80.
$80 5
$60
3 6
Cost 7
$40
$20 2
1
4
Conclusion: The manager should be most concerned about Event #7, which has a greater than
50% probability of occurring and a relatively high cost.
17-62
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
19. Given:
We are given the events, probabilities, and costs in the table below:
$200 2
$150
3
Cost $100
$50 5
1
6
4
0 .25 .50 .75 1.00
Probability of Occurring
The weather problems (4) and funding delays (5) are placed using the highest probabilities
because we are conservative (i.e., we will assume the worst case).
Conclusion: The manager should be most concerned about Event 2 (vendor is late with key
segment) due to its greater than 50% probability and its high cost.
17-63
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
17-64
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Expected Standard
Path Duration (weeks) Deviation
A 10 4
B 14 2
C 13 2
Project duration for Smitty to include in the proposal for a 5% risk of not delivering the project on
time:
This means we would like a 0.9500 probability of completion within the specified time. When we take the
probability of completion within the specified time for each path and multiply these probabilities, we need
to obtain a joint probability of at least 0.9500.
Next, we can analyze the length of each path if we use this corresponding z value (1.645):
We know that we need all three probabilities to be > 0.9500; therefore we can start by focusing on the
longest path (Path B) and specify the project completion time as 17.29 days as a starting point.
17-65
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
We can set up a spreadsheet in Excel to automate our calculations. To find a probability for a z value
using Excel, we enter the following formula: =NORMSDIST(z), where z = the cell where we have
calculated z.
Column
Row A B C D E
1 Path Mean Sigma z value Prob.
2 A 10 4 1.8225 0.9658
3 B 14 2 1.645 0.9500
4 C 13 2 2.145 0.9840
5 Completion = 17.29
6 Prob. of Completion = 0.9028
As shown above, the probability of completing the project within 17.29 days is 0.9028, which is less than
0.9500.
From here, we can experiment by entering project completion times greater than 17.29 days until the
value in Cell E6 is close to 0.9500. An alternate approach would be to create a simple Excel Solver model
to solve this. Note: We will carry the project completion time to two decimals.
After experimentation, a project completion time of 18.02 days gives us a probability of project
completion of 0.9501 as shown in the table below.
Column
Row A B C D E
1 Path Mean Sigma z value Prob.
2 A 10 4 2.005 0.9775
3 B 14 2 2.01 0.9778
4 C 13 2 2.51 0.9940
5 Completion = 18.02
6 Prob. of Completion = 0.9501
17-66
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Project duration for Smitty to include in the proposal for a 10% risk of not delivering the project
on time:
This means we would like a 0.9000 probability of completion within the specified time.
We know that when we started with a project completion of 17.29 days above, the probability of
completion was 0.9028 (just above 0.9000).
We can lower the project completion time from 17.29 until the value in Cell E6 is close to 0.9000. As
shown in the table below, a project completion time of 17.26 days provides a probability of completion of
0.9002.
Column
Row A B C D E
1 Path Mean Sigma z value Prob.
2 A 10 4 1.815 0.9652
3 B 14 2 1.63 0.9484
4 C 13 2 2.13 0.9834
5 Completion = 17.26
6 Prob. of Completion = 0.9002
Project duration for Smitty to include in the proposal for a 15% risk of not delivering the project
on time:
This means we would like a 0.8500 probability of completion within the specified time.
We know that when we used a project completion of 17.26 days above, the probability of completion was
0.9002.
We can lower the project completion time from 17.26 until the value in Cell E6 is close to 0.8500. As
shown in the table below, a project completion time of 16.78 days provides a probability of completion of
0.8506.
Column
Row A B C D E
1 Path Mean Sigma z value Prob.
2 A 10 4 1.695 0.9550
3 B 14 2 1.39 0.9177
4 C 13 2 1.89 0.9706
5 Completion = 16.78
6 Prob. of Completion = 0.8506
The pros of quoting project times aggressively are the ability to secure new business or to win project
approval.
The cons of quoting project times aggressively are the increased probability of missing the deadline,
which could lead to severe consequences for the project manager.
The pros of quoting project times conservatively are the increased probability of meeting the deadline.
The cons of quoting project times conservatively are the reduced likelihood of being able to secure new
business or to gain project approval.
17-67
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.