Sei sulla pagina 1di 1

IGNACIO BARZAGA VS CA AND ANGELITO RTC ruled in favor of the petitioner but such was

ALVIAR reversed by the CA.

GR No. 115129 Hence, this petition.

FACTS: ISSUE:

After a prolonged pain and suffering, Barzagas wife WON Alviar incurred delay in the fulfilment of his
succumbed to a debilitating ailment on December 19, obligation and is liable for damages?
1990. Forewarned of her impending death, she
wished to be buried before Christmas. RULING:

In the fulfilment of his wifes dying wish, Petitioner Yes. The Respondent was negligent and incurred
arranged her internment on the 24th of December. On delay in performing his obligations. The law
December 21, 1990 at 3 pm, he went to Angelito expressly provides that those who in the performance
Alviars hardware store to inquire about the of their obligation are guilty of fraud, negligence, or
availability of certain materials for the construction delay and those who in any manner contravene the
of his wifes niche and if it could be delivered at tenor thereof, are liable for damages.
once. Alviars storekeeper replied that if there are
There was actually a specific time agreed upon for
pending deliveries for this afternoon, it would be
the delivery of the materials. It was evident when the
delivered the following day.
petitioner only agreed to buy the materials when he
Petitioner returned the following day at 7 am. He told was assured of the immediate delivery according to
the employees that the materials he was buying his time frame. Time was of the essence in the
would have to be delivered at the cemetery by eight delivery of the materials to the grave site. The niche
in the morning since his hired workers were already had to be constructed on the 22nd considering that it
there and time was of the essence. With the assurance would take about 2 days to finish the job if the
that the materials will be delivered at the designated internment was on the 24th. Respondents delay on
time and place, he paid the full amount of P2, 110.00. the delivery wasted so much time that the
construction could only start on the 23rd.
However, the materials were not delivered on time.
After several follow ups, Alviars employees gave Respondents justification that his truck had a flat tire
him the same answer, assuring him that the materials is unacceptable, for this event was foreseeable and
will be delivered in no time. Due to the delay in the should have been reasonably guarded against.
delivery, the petitioner was forced to dismiss his
This is a clear non-performance of a reciprocal
laborers for the day.
obligation. Petitioner had already complied with his
Petitioner, determined to fulfil his wifes dying wish obligation as a purchaser when he paid the purchase
and distressed that Alviars employees were not the price. It was incumbent upon the respondent to
least concerned, despite his impassioned pleas, he immediately fulfil his obligation to deliver otherwise
decided to cancel the transaction and buy the delay would attach.
materials from another store. Her wife was finally
Petition was granted. The Court ordered private
laid to rest two-and-a-half days behind schedule since
respondent to refund the purchase price of P2, 110.00
the niche was not finished in time.
with interest, pay P20, 000.00 moral damages, P5,
Petitioner sued Alviar for compensation of the 000.00 litigation expenses and P5, 000.00 attorneys
damages caused by the delay. Respondent claims that fee.
the legal delay could not be validly ascribed to him
because no specific time of delivery was agreed upon
and even if there was delay, it was due to a fortuitous
event since the truck suffered a flat tire.

Potrebbero piacerti anche