BORED PILING METHOD STATEMENT


Posted by Categories Date Comments
HANY ISMAEL, MSC, PMP MANAGEMENT TEMPLATE, PLANNING DISCUSSIONS FEBRUARY 7, 2014 0 COMMENT

Offline
https://planningengineer.net/bored-piling-method-statement-2/ 1/8
11/16/2017 BORED PILING METHOD STATEMENT Planning Engineer Est.

BORED PILING METHOD STATEMENT.

WORK PROCEDURE
Sign-up now! get useful contents into your email. Your email address.. SUBSCRIBE

PROJECT: Ref No. FOUN/04

PAGE 1 OF 2

SECTION: DATE OF ISSUE

FOUNDATIONS Dec 2012

SUBJECT: BY:

BORED PILING QA/QC ENGINEER

APPROVED BY:

QEHS MANAGER

ACTION VERIFY

1. SCOPE Project Method

The scope of this procedure covers the control of installation of Bored Cast-in-Situ Manager Statement
Concrete piles executed by a sub-contractor.
Sub-contractor Approved
2. PROCEDURE
Project Construction
.1 Method Statement: Programme
Manager
A method statement shall be submitted by the piling Sub-contractor for approval which Approval
shall include: Subcon/
Field Book
i) Construction procedure. FCC Surveyor

ii) Pile design with calculations.

iii) Testing procedure.

iv) Documentation to be maintained during the execution of work. Offline


https://planningengineer.net/bored-piling-method-statement-2/ 2/8
11/16/2017 BORED PILING METHOD STATEMENT Planning Engineer Est.

v) Mix design for concrete.

vi) Specification for reinforcement steel and bentonite clay.

vii) Any other information required by the specification.

.2 Construction Programme:

The sub-contractor shall submit a programme for approval based on the Contract
Programme. The subcontractor shall also indicate the mobilisation time of plant,
equipment, materials and work force.

.3 Piling Sequence:

Approval of piling sequence will be given prior to commencement of piling by the


Subcontractor.

.4 Setting-Out:

HEE will execute pre-piling setting out and offer for cross-checking by Subcontractors
Surveyor and Consultants Representative.

WORK PROCEDURE

PROJECT: Ref No. FOUN/04

PAGE 2 OF 2

SECTION: DATE OF ISSUE

FOUNDATIONS Dec 2012

SUBJECT: BY:

QA/QC ENGINEER

BORED PILING APPROVED BY:

QHSE MANAGER
Offline
https://planningengineer.net/bored-piling-method-statement-2/ 3/8
11/16/2017 BORED PILING METHOD STATEMENT Planning Engineer Est.

ACTION VERIFY

.5 Source Certificates: Project Engineer Source certificate

Reinforcement steel and Bentonite test certificates if required shall be obtained from the Project Test result,
Subcontractor and, submitted for approval by the Consultant. Engineer/ FOUN/04/A

.6 Concrete Cube Testing: Labtech. Pile testing record

Cube results will be assessed and retained. The cube test reports shall be clearly Subcon. Checksheet
identified with the location of pour by reference to the checksheet.
QA/QC Non-
.7 Testing of Piles:
QA/QC Conformity Report
The Subcontractor shall carry out a load test and integrity test as specified in the Contract.

.8 Inspection of Work/Checksheet:

The work shall be inspected using the attached checksheet as Appendix FOUN/04/A
which shall be completed as verification and record of compliance.

.9 Non-Conformity:

Non-conforming workmanship shall be notified to the Subcontractor as Appendix 7/3/6/A


and corrective action taken in accordance with good working practice and Consultants
approval.

PROJECT: SITE NO.:


CHECK SHEET FOR BORED PILING Sheet No.

SUBCONTRACTOR: FATAYERJI

SECTION OF WORK ____________________________LOCATION _________________

STAGE ITEM Checked

Offline
https://planningengineer.net/bored-piling-method-statement-2/ 4/8
11/16/2017 BORED PILING METHOD STATEMENT Planning Engineer Est.

by
DATE
PREPARATION 1. Subcontractors method statement approved. PE

2. Materials approved by the consultant. PE

3. Cross-check location of Pile. SU

APPROVAL TO PROCEED QA/QC

INSTALLATION 4. Check borehole to be filled with Bentonite GF


slurry at all times.

5. Check cleaning of bottom of borehole. GF

6. Check reinforcement cage. SE

7. Check minimum cover while lowering cage into the borehole. GF

8. Check slump of concrete. Lab

9. Check cut-off level + location. SU

APPROVAL TO PROCEED WITH PILE CAP. CM

CM Construction Manager, QA/QC Quality Assurance/Quality Control, PE Project Engineer, SE Site Engineer, GF General Foreman, SU
Surveyor, Lab Laboratory Technician

DOWNLOAD BORED PILING METHOD STATEMENT WORD TEMPLATE: BORED PILING

Tag: BORED, bored piling, construction programme, METHOD, method statement, PILING, piling method, procedure project, project
engineer, project manager, statement
Share:

Offline
https://planningengineer.net/bored-piling-method-statement-2/ 5/8
11/16/2017 BORED PILING METHOD STATEMENT Planning Engineer Est.

Hany Ismael, Msc, PMP

Hany Ismael is the founder and CEO of Planning Engineer Est. in Egypt. He has started his career back in 2003 as a site engineer,
technical o ce engineer, planning engineer, planning manager, and nally planning department manager where he has been
involved in several mega construction projects in Egypt and Saudi Arabia. In 2016, he established his own company in Egypt
Planning Engineer Est. Hany gained his MSc degree in project management from Liverpool University-UK 2013-2016, PMP
certi ed from PMI-USA 2010, and BSc Civil Engineer Tanta University-Egypt 2003. Hany provided more than 3,500 hours of
planning and project management training on his website planningengineer.net, YouTube channel, and o ine courses since 2011.
He enjoys teaching project management in simple and practical way, and he developed several planning tools, techniques and
courses.

Previous post Next post

Excavation, Earthwork and Filling Method Statement Batching Of Concrete Method Statement
February 7, 2014 February 8, 2014

YOU MAY ALSO LIKE

Offline
https://planningengineer.net/bored-piling-method-statement-2/ 6/8
11/16/2017 BORED PILING METHOD STATEMENT Planning Engineer Est.

Why you should add the advanced payment to your sched Primavera Currency How to Add New Currency or Chang
22 October, 2017 8 October, 2017

LEAVE A REPLY

You must be logged in to post a comment.

SEARCH

Search

PLANNING COURSES

Free Arabic Course How to create time schedule with P6

Free

Professional Planning Engineer (PPE) Online Workshop

$665.00

Offline
https://planningengineer.net/bored-piling-method-statement-2/ 7/8
11/16/2017 BORED PILING METHOD STATEMENT Planning Engineer Est.
Claims Management, Extension of Time (EOT) and Delays Analysis-Online Workshop

$399.00

Online Primavera Course for Engineers & Construction Managers!

$149.00

Advanced Planning With Primavera Course-Downloadable

$150.00

Quantitative Schedule Risk Analysis with Primavera Online Course

$119.00

Planning Engineer Est.


(00) 201277767728

info@planningengineer.net

FOLLOW US:


Offline
https://planningengineer.net/bored-piling-method-statement-2/ 8/8

Potrebbero piacerti anche