Sei sulla pagina 1di 1

BLCP OUTAGE 2017 UNIT#1 PROJECT

PLAN SCHEDULE OF WORK & PROGRESS OF WORK


Project name : BLCP OUTAGE 2017 UNIT#1 PROJECT
Update : 12/11/2017 Time : 8:30:00 PM Rev.2
THAI JURONG ENGINEERING LIMITED
Work Nov-17 Dec-17
S/N DESCRIPTION Total joint Remarks
Balance Finish RT Start Finish 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

1 1ry RH Tube Replacement 1174 981 193 170 4-Nov-17 10-Dec-17

2 RH Tube Cutting (Furnace inside) 4-Nov-17 13-Nov-17

- Left side -145 joint 145 0 145 4-Nov-17 5-Nov-17

- Right side -145 joint 145 0 145 4-Nov-17 8-Nov-17

- Front Left side -149 joint 147 0 147 6-Nov-17 10-Nov-17

- Front Right side -150 joint 150 0 150 9-Nov-17 13-Nov-17

3 RH Tube Fit up &Weld ( Top) 4-Nov-17 27-Nov-17

- Left side -145 joint 80 4-Nov-17 15-Nov-17

Team A 70 16 54 4-Nov-17 14-Nov-17

Team B 75 42 33 6-Nov-17 15-Nov-17

- Right side -145 joint 79 9-Nov-17 23-Nov-17

Team C 70 7 63 9-Nov-17 18-Nov-17

Team D 75 50 25 13-Nov-17 23-Nov-17

- Front side -297 joint 11 9-Nov-17 27-Nov-17

Team E 100 84 16 9-Nov-17 23-Nov-17

Team F 100 100 0 11-Nov-17 25-Nov-17

Team G 97 97 0 13-Nov-17 27-Nov-17

4 RH Tube Fit up &Weld ( Bottom) 0 15-Nov-17 10-Dec-17

- Team C+D Left side - 145 joint 145 143 2 15-Nov-17 25-Nov-17

- Team C+D Right side - 145 joint 145 145 0 20-Nov-17 5-Dec-17

- Team E+F+G Front side - 297 joint 297 297 0 15-Nov-17 10-Dec-17

Prepared By : Nathaporn.W

THAI JURONG ENGINEERING LIMITED

Potrebbero piacerti anche