Sei sulla pagina 1di 10

AUTCON-01470; No of Pages 10

Automation in Construction xxx (2012) xxxxxx

Contents lists available at SciVerse ScienceDirect

Automation in Construction
journal homepage: www.elsevier.com/locate/autcon

Safety risk analysis based on a geotechnical instrumentation data warehouse in metro


tunnel project
Ling Ma a, Hanbin Luo a,, Huarong Chen b
a
Hubei Key Laboratory of Control Structure, Huazhong University of Science & Technology, Wuhan, 430074, China
b
The Administrative Center for China's Agenda21, Beijing, 100038, Beijing, China

a r t i c l e i n f o a b s t r a c t

Article history: Lack of complete information is the major factor causing accidents on metro tunnel projects. Safety risk con-
Accepted 16 October 2012 trol requires a comprehensive analysis of instrumentation data integrated with other safety related data.
Available online xxxx Based on a multidimensional data model, a safety-oriented geotechnical instrumentation data warehouse
is established to integrate all the data from heterogeneous data sources, not only for quick retrieval of infor-
Keywords:
mation on site, but also for further analysis. As one of the most important safety indicators, ground settlement
Data warehouse
Tunneling
is analyzed to take advantage of the data warehouse. A double Gaussian model is proposed to represent the
Safety risk settlement trough over twin tunnels. Moreover, a revised trough width parameter is proposed to represent
Multidimensional data the scope of safety risk areas. The ground loss is found to grow in a pattern that can be represented by a
Ground settlement logistic curve. The rst derivative of ground loss is applied to represent the evolution of safety risk.
Crown Copyright 2012 Published by Elsevier B.V. All rights reserved.

1. Introduction research. Kim et al. [1] have concluded that the instrumentation
data should be the best text book to evaluate the interaction be-
China is now enjoying a boom in metro construction. However, for tween tunneling and ground settlement which is one of the most im-
most of the cities, there is no previous experience in the construction portant safety indicators.
of metro tunnels. Some serious failures in tunnel construction have Suwansawat [12] developed an Earth Pressure Balance (EPB)
resulted in fatalities and major property damage. Most of the failures tunneling database which contained all shield operational records, in-
are attributed to inadequacies in the management of geotechnical strumentation data and geological information. It was used to identify
risks. Consequently, safety management especially for geotechnical factors which had an impact on ground settlement and showed the
risk control has become one of the major issues in the metro tunnel correlations among these factors. The system was established by
projects. implementing an entity-relationship (ER) data model. However,
During a tunnel project, appropriate geotechnical instrumentation Corral et al. proved that the dimensional model, commonly used in
should be installed to monitor the critical parameters required for data warehouse (DW), was much easily understood than the ER
safety risk control. These include ground settlement, convergence model [5]. DW was more exible in information retrieval, and it
of the tunnel, displacements of adjacent facilities caused by the con- could easily integrate various perspectives in data analysis. As a result,
struction works, etc. Such processes generate large amounts of data. one could reduce reliance on IT professionals for data manipulation.
Additionally, in order to make a more comprehensive analysis, safety In this paper, a safety-oriented geotechnical instrumentation data
management decision making should combine the daily data collec- warehouse is built to facilitate the data analysis process for safety
tion with other relevant information that is scattered among multiple, decisions. Some applications of DW in civil engineering are reviewed
dispersed and fragmented data sources. These may include construc- in Section 2. The multidimensional data model of the proposed DW
tion drawings, geological reports, etc. is discussed in Section 3. The benet of implementing the DW is dem-
As a result, it is vital to store all the data in a standard format in onstrated through a multidimensional analysis of ground settlement
order to facilitate the retrieval of valued information on site and pro- in Section 4. Finally, the ndings of this study are summarized in
vide contextual meanings for the instrumentation data. This also Section 5.
helps to avoid data loss and to accumulate experience for further

2. DW in civil engineering

Corresponding author. Tel.: +86 27 87557824; fax: +86 27 87558171. Data warehouse (DW) is a subject-oriented, integrated, nonvola-
E-mail address: lhblhb1963@vip.sina.com (H. Luo). tile, and time-variant collection of data in support of management

0926-5805/$ see front matter. Crown Copyright 2012 Published by Elsevier B.V. All rights reserved.
http://dx.doi.org/10.1016/j.autcon.2012.10.009

Please cite this article as: L. Ma, et al., Safety risk analysis based on a geotechnical instrumentation data warehouse in metro tunnel project,
Automation in Construction (2012), http://dx.doi.org/10.1016/j.autcon.2012.10.009
2 L. Ma et al. / Automation in Construction xxx (2012) xxxxxx

decisions [19]. It supports information processing by providing a solid


platform of consolidated and historical data. Many researchers have
implemented this superior tool in the eld of civil engineering.
Chau et al. [7] developed a Construction Management Decision
Support System (CMDSS) as a prototype DW integrated information
management system. The CMDSS was designed to separate the anal-
ysis database from the operational database, and use conceptual mul-
tidimensional data models for dynamic data presentation. As an
example, a typical material inventory application was proposed to fa-
cilitate inventory decision making.
Ahmad et al. [3] applied DW technology to a prototype decision
support system (DSS) to select an optimal residential housing site.
The methodology and data models of the prototype were illustrated
in detail. It was concluded that DW, if well incorporated with other
systems, could create powerful analytical tools to support decision
making in the selection of construction sites.
Ma et al. [21] explored the utilization of electronic documents
by means of DW. Based on the characteristics of construction docu-
ments, a prototype system called EXPLYZER was developed, which
Fig. 1. Part of the soil proles of Wuhan Metro Tunnel.
could extract useful information from accumulated electronic project
documents. Then, a case study of payment analysis was carried out
for a construction project. Finally, the applicability of EXPLYZER was
discussed. 3.1.1. Data collection
Rujirayanyong and Shi [18] presented a Project-oriented DW The metro project is divided into dozens of construction sections
(PDW) for contractors' company-level data facility, providing a robust and involves a large number of participants including designers, con-
tool for collecting, storing, and utilizing historical construction project tractors, surveyors and resident engineers. They produce large amount
data. The quality data available in the PDW could provide useful in- of fundamental and specic data for metro construction and are autho-
formation for conducting in-depth business analyses or data mining rized to upload the data to the online database in the form of electronic
studies. documents. The documents include drawings and geological reports of
Moon et al. [16] developed a Cost Data Management System the designers, construction schedules from contractors, instrumenta-
(CDMS) in a DW environment to improve the effectiveness of utilizing tion and installation data from surveyors and inspection reports from
historical cost data. A probability model was established to analyze the resident engineers.
DW. The CDMS showed that the DW could help people understand the
uncertainties in construction cost estimation, and provide a method
3.1.2. Data extraction
for more reliable construction cost budget planning.
The construction drawings and some textual reports are classied
Tseng et al. [15] proposed an information model and a system
as unstructured data, which does not have a pre-dened data model.
based on a spatiotemporal DW to help public road authorities lessen
Therefore some implied details are difcult to identify by the comput-
trafc disruptions and increase the pavement lifespan and quality. It
er programs automatically. The valuable information involved in these
showed that the proposed spatiotemporal DW was benecial to facil-
materials must be extracted and represented in a structured form.
itating the utility coordination process between public road authori-
Consider a typical soil prole which was uploaded with the geolog-
ties and utility owners.
ical report, as shown in Fig. 1. The borings (labeled with Jz-5 and K-62)
The above-mentioned practical applications demonstrate the po-
were drilled one by one along the tunnel alignment to explore the
tential of DW to provide exible and efcient analysis on construction
geological conditions in the tunnel route. The most important infor-
projects data. Likewise, safety risk control in metro tunnel project also
mation is the thickness of each soil layer depicted in this drawing.
requires a comprehensive evaluation of data from diverse sources.
However, computers may not be able to recognize these valuable de-
Consequently, a safety-oriented DW was established as a superior
tails. Also electronic drawings increase the difculty of information re-
data analysis platform in a real life tunnel project.
trieval. Consequently, the information involved in the soil proles is
manually extracted and uploaded to the online database. The entity-
3. Instrumentation DW for Wuhan Metro Tunnel Project relationship (ER) model of this part of data is shown in Fig. 2.

Wuhan, the capital city of Hubei Province by the Yangtze River in 3.1.3. Data transformation
China, has approximately 8 million inhabitants. Its metro network Different participants might have different naming conventions
has been scheduled to include 9 urban lines, 3 intercity lines and 309 and measurement units in their reports. Therefore, all data had to be
stations, with a total length of about 540 km and a total construction in-
vestment of about 300 billion Yuan. The rst 28.9 km line (27 stations),
an elevated metro, has been in operation. Now, there are three lines (all
underground) under construction simultaneously. Faced with the great
pressure of safety management in metro construction, Wuhan Metro ProspectingBoreholes SoilProfile
Group Co., Ltd decided to implement the proposed safety-oriented DW. SoilType
ID ID
Name 1:N ProspetingID N:1 ID
3.1. Data acquisition process Chainage SoilID Name
GroundELevation Thinckness Characteristic
The proposed DW executed a recursive collection, extraction and SiteID Elevation
transformation process for data acquisition by applying a web-based
data management system. Fig. 2. ER model for soil proles.

Please cite this article as: L. Ma, et al., Safety risk analysis based on a geotechnical instrumentation data warehouse in metro tunnel project,
Automation in Construction (2012), http://dx.doi.org/10.1016/j.autcon.2012.10.009
L. Ma et al. / Automation in Construction xxx (2012) xxxxxx 3

Fig. 3. Part of the instrumentation scheme in Wuhan Metro Tunnel Project.

transformed to a naming standard and standard measurement units to First, it is obvious that a temporal dimension can be implemented
maintain consistency. to explore the time dependent properties of ground settlement, since
All three data acquisition processes are executed on the ER model, the ground settlement is measured during the construction process.
which lays the foundation for the database management system. It is Second, a spatial dimension can be applied to depict the distribution
a data sharing platform for all participants, and the proposed DW sits of ground settlement. The settlement markers are installed in arrays on
on top of it. The DW design is based on a multidimensional data the ground surface (a typical instrumentation scheme is shown in
model which is superior to an ER model in data analysis. Fig. 3). Each array depicts the settlement prole (often referred to as
the settlement trough) of its located cross section. Consequently, group-
ing the markers by array is adopted as the grouping manner in spatial
3.2. Multidimensional modeling of the DW dimension (i.e.) to evaluate the distribution of ground settlement.
Third and nally, besides the spatio-temporal dimensions, there
A multidimensional data model is specically designed to store remain some context dimensions to evaluate the relevant factors of
data in a way that emphasizes users' understandability and facilitates ground settlement. According to the recent evaluations on the rele-
superior data presentation. It is composed of fact tables and dimen- vant factors of ground settlement (as is shown in Table 1), tunnel ge-
sion tables. ometry and hydro-geological conditions are taken as two context
dimensions in the DW.
Part of the proposed multidimensional data model of ground set-
3.2.1. Fact tables tlement is shown in Fig. 4. The primary difference between ER model
Fact tables store physical information to describe a factual event. in database (as shown in Fig. 2) and multidimensional model in DW
In this metro tunnel project, the instrumentation data is considered is that while the former is designed and optimized to record, the latter
in the safety diagnosis of the site and is a good reference for safety de- has to be designed and optimized to respond to analysis. The table
cisions. Therefore, all the instrumentation data including the ground structures in DW are simpler, standardized, and denormalized to re-
settlement, displacement of the tunnel crown, convergence of the duce the linkages between tables and the corresponding complexity
tunnel, settlement of the adjacent facilities, etc. are stored as factual of queries. Consequently, the DW drastically reduces the cost-per-
data in different fact tables. analysis and is more efcient than application database.

3.2.2. Dimension tables 4. Implementation of the proposed DW


Dimension tables provide context and meanings for the factual data
(i.e. instrumentation data in the proposed model) to facilitate the explo- The most important benet of the proposed DW is that it facili-
ration of data from multiple perspectives. For example, there are at least tates the analysis of safety indicators to extract potential and useful
two important descriptive dimensions for ground settlement which is patterns from large amounts of data. Ground settlement is one of
the most important instrumentation type: the most important safety indicators in the proposed DW, because

Table 1
Relevant factors of ground settlement considered in recent research works.

Resent research Tunnel geometry Hydro-geological conditions

Tunnel depth Tunnel Geology at Geology at Groundwater Ground water


diameter tunnel crown tunnel invert state level (m)

Santos and Celestino [10]


Neaupane and Adhikari [6]
Suwansawat and Einstein [13]
Kim et al. [1]
Shi et al. [4]

Please cite this article as: L. Ma, et al., Safety risk analysis based on a geotechnical instrumentation data warehouse in metro tunnel project,
Automation in Construction (2012), http://dx.doi.org/10.1016/j.autcon.2012.10.009
4 L. Ma et al. / Automation in Construction xxx (2012) xxxxxx

DimCrossSection

PK CrossSectionKey

Mileage
......

S2

FactSettlement
DimMarkerOwner DimGeology S1
PK SettlementKey
PK MarkerOwnerKey PK GeologyKey
Tunnel centerline
DailySettlement
MarkerOwner Groundwater
CumSettlement
...... ......
Level
FK1 DateKey Overall settlement trough
DimMarker FK2 MarkerOwnerKey
FK3 MarkerKey DimDate
PK MarkerKey FK4 SiteKey
FK5 CrossSectionKey PK DateKey
MarkerName FK6 GeologyKey
...... FK7 GeometryKey FullDate
...... Northbound Southbound

Fig. 6. A typical ground settlement trough over twin tunnels.


DimSite DimGeometry

PK SiteKey PK GeometryKey where S is ground settlement, Smax is the maximum settlement above
SiteName TunnelDepth
the tunnel centerline, x is the horizontal distance from the tunnel cen-
...... ...... terline in the transverse direction, and i is the distance from the tun-
nel centerline to the inexion point of the curve, which determines
Fig. 4. Part of the multi-dimensional data model of ground settlement. the shape of the curve, as is shown in Fig. 5.
However, twin tunnels have been used more often than a single tun-
nel, especially in urban metro construction. This requires a redenition
large ground settlement brings great safety risk to both the tunnel of the ground settlement trough over twin tunnels. Suwansawat and
and its adjacent facilities. Einstein [14] used a superposition technique to describe the settlement
The construction of a tunnel inevitably affects existing ground trough over twin tunnels. First, when the preceding tunnel just passed
stresses and hydro-geological conditions, which will induce ground set- through, the ground settlement was tted by a Gaussian function,
tlement. Suwansawat and Einstein [13] pointed out that a major prob- which was referred to as the settlement trough induced by the preced-
lem in evaluating the ground settlement was lack of extensive eld ing tunnel. Then, the additional settlement was obtained by subtracting
instrumentation data and relevant construction information. The pro- this portion of settlement from the nal settlement after the following
posed DW provides an excellent data support to evaluate the ground tunnel passed. Then the additional settlement was tted by another
settlement in multiple dimensions. Gaussian function. Finally, the two curves were superposed to present
the overall ground settlement trough. The hypothesis implies that the
4.1. Revised model of ground settlement trough additional settlement is only induced by the following tunnel but has
nothing to do with the preceding tunnel. Hence, the hypothesis may
The spatial dimension in the DW offers a perspective to evaluate lead to non-optimal tting results.
the spatial characteristics of the instrumentation data. The distribu- In this study, a double Gaussian model is proposed to represent
tion of ground settlement is depicted by the settlement trough. Peck the settlement trough over twin tunnels as follows:
[11] once suggested that the settlement trough above a single tunnel
  h i
could be represented by a Gaussian curve as follows: 2 2
S s1 exp a1 x s2 exp a2 xu 2

!
x2 where S is the overall ground settlement. s1 and s2 can be considered as
S Smax exp 2 1
2i the maximum ground disturbance induced by the northbound tunnel

Inflexion point of the curve


Tunnel centerline
Settlement trough

Fig. 5. Ground settlement trough induced by a single tunnel. Fig. 7. Histogram of correlation coefcient from 3638 trials.

Please cite this article as: L. Ma, et al., Safety risk analysis based on a geotechnical instrumentation data warehouse in metro tunnel project,
Automation in Construction (2012), http://dx.doi.org/10.1016/j.autcon.2012.10.009
L. Ma et al. / Automation in Construction xxx (2012) xxxxxx 5

Fig. 10. A typical settlement trough located in DK26 + 970.

Fig. 8. Box-plot with R of good tting results. and r is the residual vector of m settlement markers in each ground
array. The LevenbergMarquardt (LM) method [9] uses a search direc-
tion pk to iteratively minimize F and to nd an optimum estimation of
and the southbound tunnel respectively. x is the horizontal distance
the unknown parameters (i.e. s1, a1, s2 and a2) in Eq. (2). pk is a solu-
from the northbound tunnel centerline in the transverse direction. a1
tion of the linear set of equations as follows:
and a2, as replacements of the original parameter (i.e. i) in Eq. (1), are
the shape parameters of the settlement trough. u, which is already  
T T
recorded in the DW, is the distance between the two tunnels. A typical Jk Jk k I pk Jk Rk 6
ground settlement trough over twin tunnels is shown in Fig. 6.
While the non-linear single Gaussian model (i.e. Eq. (1)) could be where k is the iteration step and J is the Jacobian matrix of r as follows:
easily transformed to a linear one by log transformation, the proposed h  2 i
ea2 xj u s2 xj u ea2 xj u
2 2 2 2
double Gaussian model (i.e. Eq. (2)) could not. Consequently, in order J ea1 xj s1 xj 2 ea1 xj : 7
j1;2;m
to t the proposed model to the instrumentation data in the DW, a
non-linear least-squares based optimization method (i.e. Levenberg
Marquardt method) is implemented to solve this problem. The scalar k, i.e. damping factor, controls both the magnitude and
According to Eq. (2), the objective function F will be direction of pk at each major iteration. If the reduction of F is rapid, a
smaller k can be used, but if an iteration gives insufcient reduction
m h
X i2 of F, k can be increased and pk tends to move towards a more steep
F r j s1 ; a1 ; s2 ; a2 3 descent direction. In this work the initial damping factor 0 is given as
j1 0.001.

where 4.2. Results from spatial analysis

    2 
2
r j s1 ; a1 ; s2 ; a2 s1 exp a1 xj s2 exp a2 xj u Sj 4 3638 groups of samples are tted by LM method in the analysis.
The root-mean-square error (RMSE) and correlation coefcient (R) are
used to validate the tting results. Fig. 7 shows the histogram of R.
Sj is the observed ground settlement at jth settlement marker. Conse- 83% of the cases show good tting results with R > 0.8. The RMSE and
quently, rj(s1,a1,s2,a2) is the deviation of jth data point from the tted R of these cases are shown in Figs. 8 and 9. As a result, the proposed dou-
curve. ble Gaussian model t the settlement data well.
DK26 + 970 is a typical settlement array, as shown in Fig. 3. Actually,
T due to the interference of the site conditions, only 5 settlement markers
r r1 r2 rm  5
were put into use in this ground array, so marker 6 was excluded. The
instrumentation data, however, could still be fully represented by the

Settlement Marker

Northbound Northbound

Moment 1 Moment 2

Southbound Southbound

Tunnel face
Settlement Array

Fig. 9. Box-plot with RMSE of good tting results. Fig. 11. Two moments depicted in Fig. 10.

Please cite this article as: L. Ma, et al., Safety risk analysis based on a geotechnical instrumentation data warehouse in metro tunnel project,
Automation in Construction (2012), http://dx.doi.org/10.1016/j.autcon.2012.10.009
6 L. Ma et al. / Automation in Construction xxx (2012) xxxxxx

Table 2
Description of each curve.

Curve Description

A Ground disturbance induced by the following tunnel when the preceding


tunnel passed beneath
B Ground disturbance induced by the preceding tunnel when the preceding
tunnel passed beneath
C Ground settlement trough over twin tunnels when the preceding tunnel
passed beneath (i.e. A+ B)
D Ground disturbance induced by the preceding tunnel when both tunnels
passed through
E Ground disturbance induced by the following tunnel when both tunnels
passed through
F Ground settlement trough over twin tunnels when both tunnels passed
through (i.e. D + E)

proposed double Gaussian model, as shown in Fig. 10. Settlement data


of the array at 2 moments (as shown in Fig. 11) was plotted with dif-
ferent symbols. Round points indicate the ground settlement records
at moment 1 when the northbound tunnel (i.e. the preceding tunnel)
passed beneath the array whereas square points indicate the ground
Fig. 13. Trough width parameters of DK25 + 325.
settlement records at moment 2 when both tunnels passed through
the array and the ground stabilized. Each group of data was tted by
the proposed double Gaussian model (i.e. C and F). According to
Eq. (2), both the two curves C and F could be decomposed into two were divided into several parts by tunnel shafts along the tunnel align-
parts to represent the ground disturbance by each tunnel (i.e. C = ment. Independent construction procedures were progressed for
A + B, F = D + E). Descriptions of each curve are illustrated in Table 2. each part. DK25 + 067, DK25 + 092 and DK26 + 940 were located at
As shown in Fig. 10, the northbound tunnel (i.e. the preceding tun- a part where the southbound tunnel was the preceding tunnel, where-
nel) passed under the ground array rst, while the southbound tunnel as DK25 + 142 was located, like DK26 + 970, at a part where the
(i.e. the following tunnel) was far away the array. However, the exca- northbound tunnel was the preceding tunnel.
vation of southbound tunnel had still made a small disturbance to the It can be concluded that although there is a signicant enlargement
ground (i.e. A). When the southbound tunnel also passed through the of ground settlement when the tunnel is passing beneath (i.e. B and E
ground array and the ground became stabilized, the ground distur- A), both the pre-settlement (i.e. A) and the post-settlement (i.e. DB)
bance induced by the southbound tunnel had sharply increased from still exist, deserving due attention. This nding can be regarded as
A to E. Moreover, at this moment, although the northbound tunnel the main difference between Suwansawat and Einstein' work [14]
had passed through for a time, it still enlarged the ground disturbance and this study. Their simplied method implied that they omitted
from B to D. Finally, D and E made up the overall ground settlement the pre-settlement of the following tunnel, i.e. A, and used B directly
trough over twin tunnels (i.e. F). to represent C. Moreover, they considered that the overall additional
Some other results are shown in Fig. 12. In the Wuhan Metro Pro- settlement was only induced by the following tunnel. As a result, the
ject, in order to speed up the construction progress, the twin tunnels settlement of the preceding tunnel, i.e. (DB), was also omitted. This

Fig. 12. Part of the settlement troughs derived from the proposed DW.

Please cite this article as: L. Ma, et al., Safety risk analysis based on a geotechnical instrumentation data warehouse in metro tunnel project,
Automation in Construction (2012), http://dx.doi.org/10.1016/j.autcon.2012.10.009
L. Ma et al. / Automation in Construction xxx (2012) xxxxxx 7

may lead to a narrower ground settlement trough and underestima- derived from Eq. (2) as follows:
tion of the amount of ground settlement.
p p
i1 1= 2a1 and i2 1= 2a2 : 8
4.3. Scoping of the safety risk areas
With a view to the overlap of ground disturbance of the twin tun-
By directly tting the data with the proposed double peak Gaussian nels (as shown in Fig. 13), a more comprehensive trough width pa-
model, the ground disturbance induced by each tunnel could be more rameter (i.e. ) for twin tunnels is proposed as follows:
exactly represented. Recalling Eq. (1) the characteristics of Gaussian
curve, i is a vital parameter which determines the atness of the i i i u=2: 9
1 2
curve. The larger the value of i, the wider the settlement trough on
the ground. Therefore, the former is also dened as a trough width pa- The proposed is considered to be a measurement of the scope of
rameter. Considering the twin tunnels, i for each tunnel could also be safety risk areas, since most of the ground settlement happened

Fig. 14. Time variations of trough with parameters.

Please cite this article as: L. Ma, et al., Safety risk analysis based on a geotechnical instrumentation data warehouse in metro tunnel project,
Automation in Construction (2012), http://dx.doi.org/10.1016/j.autcon.2012.10.009
8 L. Ma et al. / Automation in Construction xxx (2012) xxxxxx

within the distance of 3 on each cross-section above the twin tun-


nels. And the area within the distance of deserves the most safety at-
tention. Consequently, the derived factor from the DW was
implemented in the safety decisions on the Wuhan Metro Project.
By combining the spatial analysis with temporal dimension, the
proposed safety-oriented DW facilitates the evaluation of the evolv-
ing scope of risk. As shown in Fig. 14, the time variations of all the
trough width parameters (i.e. i1, i2 and ) are investigated. All the
parameters are listed by normalized time t (a value from 0 through
1). Different symbols stand for different ground arrays. Because differ-
ent ground arrays are not in use or are not monitored at the same time,
the normalized time makes the comparison more convenient. In addi-
tion, since the ground array is put into service before the preceding
tunnel passes beneath it and goes out of monitoring after both tunnels
pass under the array and the ground has stabilized, the normalized Fig. 15. A typical soil prole in Wuhan Metro Project.

time can also illustrate the whole tunneling process around each
array. Consequently, the results can also reect the relationship be- Based on the results of back-analysis by using the monitoring data
tween trough width parameters and the tunneling process. of the Taipei Rapid Transit System, Chi, S.Y et al. [17] reported the fact
As shown in Fig. 14, during the tunneling process, there is little that = 45 for tunneling in clay, while ranges between 30 and 45
change in the width of overall settlement trough and that of each tun- for sandy layers. Moreover, E.J. Cording and W.H. Hansmire [2]
nel, but the settlement trough has been enlarged indeed, as shown suggested that = 11 for rock and hard clays. Consequently,
in Figs. 10 and 12. Therefore, the width of settlement trough may be according to Eq. (12), we can get some useful suggestions about the
mainly determined by some time-invariant factors like the geological value of k, as shown in Table 3.
conditions (i.e. soil condition, ground water table, etc.). Also, the However, in a real tunnel project, the soil layers in the prole may
tunneling process of each tunnel only deepens the settlement trough, not be uniform. The geological conditions in Wuhan Metro Project are
but does not widen it notably. more complex. The context dimensions in the DW facilitate the com-
This nding also implies that can only be regarded as a measure- bination of spatial analysis results with the structured description of
ment of static risk. Although a good control of tunneling process may geological information. According to the extracted data from geolog-
be helpful in reducing the ground settlement in a certain area, the ical reports, the overburden of the tunnel can be mainly divided
scope of the inuenced area may be predetermined by the geological into 3 layers, i.e. ll, clay and rock, as is shown in Fig. 15.
conditions or some other objective conditions. When looking at the soil layers above the tunnel centerline, the
Some researchers discussed the factors affecting the width of set- thicknesses of soil layers vary from one another at different cross-
tlement trough. Based on detailed instrumentation data, Mahmutoglu, sections of the tunnel along the tunnel alignment. Apart from this,
Y [20] reported that the variations in the settlement trough are related the inuences of these different soil types on the trough width pa-
to the soil type and the thickness of the tunnel's overburden. Ac- rameter vary signicantly (as shown in Table 3). Consequently, the
cording to the Gaussian model of a single tunnel, O'Reilly and New conventional tunnel depth z, i.e. the vertical distance from ground
[8] made an analysis of case history data and proposed the formula surface to the tunnel centerline, is redened as z, which reects the
comprehensive inuence of the overburden of different soil layers
i kz 10 on the trough width. The formula can be expressed as follows:

where i is the trough width parameter, k is an empirical constant relat- z kj j 13


ed to the soil type, and z is tunnel depth, i.e. the vertical distance from
ground surface to the tunnel centerline. where j is the thickness of the jth soil layer and kj is the empirical
Considering the twin tunnels, Suwansawat and Einstein [14] constant related to this soil type. In this study, 0.3, 0.5 and 0.1 are cho-
found that the trough width parameter i, which is obtained from sen as the values of kj for ll, clay and rock respectively.
the additional settlement trough over the following tunnel, was in Trough width parameter derived from 24 stabilized troughs are
agreement with O'Reilly and New's work [8]. It found that the empir- shown in Fig. 16 to represent the relationship between and z.
ical constant k falls within the bound of 0.4 and 0.5, which was similar Round points indicate that there is no conned water around the
to most cases of tunneling projects in clay layers.
Chi, S.Y et al. [17] also summarized the relationship between
trough width i and tunnel depth z by using the angle of the inuence
zone of ground settlement (i.e. ) as follows:

tan 2i=z: 11

By combining Eq. (10) with Eq. (11), we can easily derive the
following:

k tan=2: 12

Table 3
Suggested value of k.

Type of soil k

Sandy layers 0.30.5


Clayey soils 0.5
Rock and hard clays 0.1
Fig. 16. Relationship between and z.

Please cite this article as: L. Ma, et al., Safety risk analysis based on a geotechnical instrumentation data warehouse in metro tunnel project,
Automation in Construction (2012), http://dx.doi.org/10.1016/j.autcon.2012.10.009
L. Ma et al. / Automation in Construction xxx (2012) xxxxxx 9

settlement trough whereas square points indicate that there is con- stabilized after both tunnels have passed through, V is the increased
ned water. It can be concluded that when the revised tunnel depth ground loss from the initial time to the nal stablizaed stabilized
z tends to be deeper, the trough width parameter, namely, the radius time, p is a parameter that determines the shape of the curve and is
of the risk scope, tends to be wider. Moreover, conned water seems relevant to the geological conditions along with the construction
to centralize the safety risk scope around its location by decreasing conditions.
the trough width parameter. Consequently, the conned water is con- The selected settlement array shown in Fig. 17 was located at
sidered as an unfavorable geological condition in Wuhan Metro Pro- chainage DK25 + 192. It was put into use from January 31st, 2009
ject. However, this nding was not considered in former research (when the tunnel face of the preceding tunnel was 28 m before the
works. array) to May 19th, 2009 (when the tunnel face of the preceding tun-
Furthermore, the proposed trough width parameter (i.e. ) cannot nel was 75.2 m after the array). These 109 days are mapped to a nor-
comprehensively reect the degree of safety risk as it can only repre- malized time scale, which also indicates the 104.2 m advancement of
sent the inuenced scope of the ground. Because the settlement the preceding tunnel face.
trough could still be very shallow sometimes when tends to be a larg- It could be concluded that the value of Vl at a certain area will in-
er value, the degree of safety risk tends to be minor. Consequently, a crease sharply while the tunnel face is approaching and passing
more comprehensive parameter should be introduced to represent through, whereas the growth rate of Vl will decrease after the tunnel
both the depth and width of the settlement trough. passes through. Finally, the value of Vl stops increasing when it
reaches a certain value. As shown in Fig. 18(a), the rst derivative
4.4. Evolution of safety risk degree of Vl at DK25 + 192 reects the growing rate of Vl, which also reects
the evolution of safety risk. The moment with the highest growing
In the proposed DW, ground loss Vl was introduced to solve the rate of Vl which indicates the highest safety risk, can be easily xed
above-mentioned problem. It is dened as the integral of the ground by the second derivative of Vl (as shown in Fig. 18(b)). By combining
settlement trough. this nding with the records of construction progress in the DW, it
can be concluded that the moment subjected to the highest safety
risk is the moment when the preceding tunnel is just arriving beneath
x   the settlement array. These revealed evolution laws of safety risk are
2 2
V l s1 exp a1 x s2 expa2 xu
14 considered to be valuable references for safety management in future
p
x
Wuhan Metro construction project.
2i1 s1 i2 s2
Additionally, by dividing the Vl of stabilized ground settlement
troughs by the excavation area of twin tunnels, the ration of ground
loss can be derived. Most of the ground loss rations from different
where, i1 and i2 arepthe
trough width
pparameters of the two tunnels re- areas in this project fall between 0.5% and 1%, as is shown in Fig. 19.
spectively (i1 1= 2a1 ,i2 1= 2a2 ). It's worth noting that meter (m)
This may be a reference for further work.
is used as the unit of i1 and i2, and millimeter (mm) for s1 and s2. There-
fore, the integral results should be divided by 1000 to get the unit of m2.
Vl is considered as an important safety indicator in spatial dimen-
sion. By combining the spatial analysis with temporal dimension, the a First derivative of Ground loss
proposed safety-oriented DW facilitates the evaluating the evolution
of Vl. It is found that the derived ground loss Vl is growing in a pattern 0.8
that can be well represented by the logistic growth curve (Eq. (15)),
as is shown in Fig. 17.
0.6

  p 
t 0.4
V l V max V 1 15
t0

0.2
where Vl is the ground loss at the normalized time t (a value from
0 through 1), Vmax is the maximum ground loss when the ground is
0.0
0.0 0.2 0.4 0.6 0.8 1.0

b Second derivative of Ground loss

Highest growing rate

0.0 0.2 0.4 0.6 0.8 1.0

Fig. 17. Time variation of ground loss measured at DK25 + 192. Fig. 18. First and second derivatives of ground loss at DK25 + 192.

Please cite this article as: L. Ma, et al., Safety risk analysis based on a geotechnical instrumentation data warehouse in metro tunnel project,
Automation in Construction (2012), http://dx.doi.org/10.1016/j.autcon.2012.10.009
10 L. Ma et al. / Automation in Construction xxx (2012) xxxxxx

risk. It is found that the moment the tunnel reaches beneath a cer-
1.4 tain point deserves the greatest attention to safety in the nearby
area, which accords with our common knowledge. Additionally,
we may also regard the second derivative of ground loss as a safe-
1.2
ty warning index when it fails to reach 0 after the tunnel passes
through.
1.0
The spatio distribution and time-dependent characteristic of ground
Ratio of ground loss

settlement are investigated in this study. Future work will focus on eval-
0.8 uation and exploration of the impact of construction and geological con-
ditions on the changing regularity of ground settlement, since this study
has demonstrated that soil properties have some impact on the trough
0.6
width parameter.

0.4 References
[1] C.Y. Kim, G.J. Bae, S.W. Hong, C.H. Park, H.K. Moon, H.S. Shin, Neural network
0.2 based prediction of ground surface settlements due to tunnelling, Computers
and Geotechnics 28 (67) (2001) 517547.
[2] E.J. Cording, W.H. Hansmire, Displacement around soft ground tunnels, General
Report: Session IV, Tunnels in soil, Proceedings of 5th Pan American Conference
0.0
on Soil Mechanics and Foundation Engineering, 1975.
[3] I. Ahmad, S. Azhar, P. Lukauskis, Development of a decision support system using
Fig. 19. Ratio of ground loss in Wuhan Metro Project.
data warehousing to assist builders/developers in site selection, Automation in
Construction 13 (4) (2004) 525542.
5. Conclusion [4] J.S. Shi, J. Ortigao, J.L. Bai, Modular neural networks for predicting settlements dur-
ing tunneling, Journal of Geotechnical and Geoenvironmental Engineering 124 (5)
(1998) 389395.
The difculties in safety risk control for metro tunnel construction [5] K. Corral, D. Schuff, R. Louis, The impact of alternative diagrams on the accuracy of
projects fall mainly into two categories: recall: a comparison of starschema diagrams and entityrelationship diagrams,
Decision Support Systems 42 (1) (2006) 450468.
1) Lack of construction experience [6] K.M. Neaupane, N.R. Adhikari, Prediction of tunneling-induced ground movement
2) Lack of complete information of the site with the multi-layer perceptron, Tunnelling and Underground Space Technology
2 (2006) 151159.
A multidimensional data model, which includes spatio-temporal di- [7] K.W. Chau, Y. Cao, M. Anson, J.P. Zhang, Application of data warehouse and Deci-
sion Support System in construction management, Automation in Construction
mensions and context dimensions, is proposed to establish a safety- 12 (2) (2003) 213224.
oriented DW. The DW facilitates the information retrieval and safety de- [8] M.P. O'Reilly, B.M. New, Settlements above tunnels in the United Kingdom, their
cisions on the basis of large amounts of data. Since large scale metro magnitude and prediction, in: Proc. Tunnelling '82, Inst of Mining & Metallurgy,
Brighton, 1982, pp. 173181.
tunnel construction will continue for a long time in China, the valuable [9] N. Jorge, S.J. Wright, Numerical Optimization, second ed. Springer Verlag, Berlin,
knowledge derived from the DW will be good references for the future Heidelberg, New York, 2006.
construction projects. The benets of the proposed DW are demonstrat- [10] O.J. Santos, T.B. Celestino, Articial neural networks analysis of Sao Paulo subway
tunnel settlement data, Tunnelling and Underground Space Technology 23 (5)
ed through a multidimensional analysis of ground settlement. Some
(2008) 481491.
other interesting ndings are drawn from this study: [11] R.B. Peck, Deep excavations and tunnelling in soft ground, in: Proc.7th Interna-
tional Conference on Soil Mechanics and Foundation Engineering, Mexico City,
1) The proposed double Gaussian model well represents the ground 1969, pp. 225290.
settlement trough over twin tunnels. 83% of the cases show good [12] S. Suwansawat, Shield tunneling database management for ground movement eval-
tting results with R > 0.8. uation, Tunnelling and Underground Space Technology 19 (45) (2004) 376377.
[13] S. Suwansawat, H.H. Einstein, Articial neural networks for predicting the maxi-
2) The redened trough width parameter, which is derived from the mum surface settlement caused by EPB shield tunneling, Tunnelling and Under-
proposed double Gaussian model, can be considered as a measure- ground Space Technology 21 (2) (2006) 133150.
ment of static risk. Since the trough width parameter is almost [14] S. Suwansawat, H.H. Einstein, Describing settlement troughs over twin tunnels
using a superposition technique, Journal of Geotechnical and Geoenvironmental
time-invariant, it was discovered that the tunneling process of Engineering 133 (4) (2007) 445468.
each tunnel mainly deepens, but does not signicantly widen the [15] S. Tseng, C. Chou, T. Ho, C. Lin, T. Chen, A spatiotemporal database approach to the
settlement trough. The relationship between the trough width management of utility work schedules in transportation projects, Automation in
Construction 20 (6) (2011) 729739.
and geological conditions is also discussed in this paper. The nd- [16] S.W. Moon, J.S. Kim, K.N. Kwon, Effectiveness of OLAP-based cost data management
ing can be of great help in estimating the scope of safety risk. More- in construction cost estimate, Automation in Construction 16 (3) (2007) 336344.
over, since it exerts a negative centralized impact on ground [17] S.Y. Chi, J.C. Chern, C.C. Lin, Optimized back-analysis for tunneling-induced
ground movement using equivalent ground loss model, Tunnelling and Under-
settlement, conned water is considered to be an unfavorable geo- ground Space Technology 16 (3) (2001) 159165.
logical condition. [18] T. Rujirayanyong, J.J. Shi, A project-oriented data warehouse for construction,
3) As a more comprehensive parameter that reects the safety risk, Automation in Construction 15 (6) (2006) 800807.
[19] W.H. Inmon, Building the Data Warehouse, in: Wiley, New York, 1992.
the derived ground loss was used to represent both the depth
[20] Y. Mahmutoglu, Surface subsidence induced by twin subway tunnelling in soft
and width of the settlement trough over twin tunnels. The logistic ground conditions in Istanbul, Bulletin of Engineering Geology and the Environ-
growth curve can be applied to well represent the growth of ment 70 (1) (2011) 115131.
ground loss over time. The rst derivative of ground loss shows [21] Z.L. Ma, K.D. Wong, L. Heng, Y. Jun, Utilizing exchanged documents in construc-
tion projects for decision support based on data warehousing technique, Automa-
the evolution laws of safety risk while the second derivative of tion in Construction 14 (3Sp. Iss. SI) (2005) 405412.
ground loss helps identify the moment with the highest safety

Please cite this article as: L. Ma, et al., Safety risk analysis based on a geotechnical instrumentation data warehouse in metro tunnel project,
Automation in Construction (2012), http://dx.doi.org/10.1016/j.autcon.2012.10.009

Potrebbero piacerti anche