Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Abstract This paper presents research on adaptive load. It also considers a few of the fault resistances. Baran, et.
overcurrent protection by considering critical clearing time al. [2] demonstrated how to set an overcurrent relay connected
(CCT) for a microgrid system (MGS). The studied case is to one grid. However, this scheme will not be able to solve the
located in Mae-Sariang district, Chiang Mai province which is a problems of electric systems consisting of many DGs.
remote area. It is composed of many kinds of user loads, an Brahma, et. al. [3] proposed a method to adjust overcurrent
energy storage system and distributed generations (DGs). When relay in cases where there are very large DGs connected to an
faults occur while MGS is performing in the grid-connected electrical-radiance system. Nevertheless, this strategy cannot
mode or island mode, very different fault current level (FCL) be used for an overcurrent relay in an electrical-loop system.
values occur. According to this event, the overcurrent relay
While, Schaefer, et. al. [4] improved the time setting of the
might malfunction and the generators might become unstable.
The FCL change depends on the grids while the system is in the
overcurrent relay in the MGS that performs in the grid-
grid-connected mode. On the other hand, the FCL depends on connected and island modes. This system was also operated by
DGs while the system is in the island mode or stand-alone mode. hardware and software. If the collection of fault current
Our research was carried out in the 22kV distribution system of information is not complete in all cases, the overcurrent relay
the Provincial Electricity Authority of Thailand (PEA). System might malfunction.
analysis used the DigSILENT Power Factory software and the This paper presents how to set the time dial (TD) and pick-
Real Time Digital Simulation (RTDS). Test results show the
up current value (Ipick-up) of an overcurrent relay. It also
fault current, CCT and overcurrent relay setting.
includes the critical clearing time (CCT) for the stability of
Index Termsadaptive overcurrent relay, microgrid system, generators when the MGS operates in the grid-connected and
distributed generations, DigSILENT Power Factory, Real Time island modes. There were two utility grids connected to the
Digital Simulation. MGS. The fault level (FCL) and the CCT were collected for
different DGs sizes, load sizes and fault resistances that
covered all cases. Our research particularly analyzed the three
I. INTRODUCTION phase fault at the end of feeder lines in the MGS because it is
A microgrid system (MGS) is defined as a cluster of the maximum fault current that may affect users of electricity
distributed generations (DGs), a storage system, loads and and damage the system.
control systems. MGS involve multiple energy sources as a
way of incorporating renewable power. Other purposes of MGS in the Mae Sariang district, Mae Hong Son, north of
their use include cost reduction and reliability enhancement. Thailand operated by PEA was studied. This research used the
Microgrids can operate either in the grid-connected mode or in DigSILENT Power Factory, RTDS hardware and RSCAD
the island mode. Previous studies [1] [4] have shown that simulator software to study the adaptive operation of
microgrid protection can be significantly affected by the type overcurrent relay.
of DGs and operation mode of the microgrid. Therefore,
protection systems must be adaptive and continuously tuned to II. PROTECTION IN A MICROGRID SYSTEM
the rapidly changing operating conditions of the microgrid. A. Important characteristics of the protective relay in MGS
Adaptive overcurrent relaying scheme is based on the Reliability, Selectivity, Sensitivity, Simplicity, and Fast.
development of overcurrent relay settings. Buque, et. al. [1] First, reliability is a main characteristic of protection systems
presented a model of the MGS and fault current analysis. It and consists of two critical factors, dependability and security.
operated in parallel connecting with a grid-connected and These two factors indicate whether the protection system is
island operation system. However, this method is only suitable reliable or not. Dependability indicates that the system trips
for one grid-connected with a microgrid. It considers the only when it is expected to trip. It is the amount of certainty
length of the transmission line between the grid and the short- that the overcurrent relay will operate correctly. Security is the
Authors would like to thank the Faculty of Engineering and Graduate
School, Chiang Mai University for partial financial support.
N. Tummasit (e-mail: nopthna@gmail.com) and S.
Premrudeepreechacharn (e-mail: suttic@eng.cmu.ac.th) are with the
Department of Electrical Engineering, Faculty of Engineering, Chiang Mai
University, Chiang Mai Thailand 50200.
N. Tantichayakorn (e-mail: narong.tan@pea.co.th) is with the Substation
and Power System Maintenance Department Provincial Electricity Authority
(PEA) 200 Ngamwongwan,Rd, Jatujak, Bangkok, Thailand 10900.
property which prevents false tripping. The overcurrent relay operating point shifts to E and swing takes a place along EF.
is called to be secure if it does not trip when it is not expected In Figure 1 area1 is the accelerating area and area2 is the
to trip. It is the amount of certainty that the overcurrent relay possible decelerating area. If area1 is larger than area2, the
will not operate incorrectly. Second, selectivity is the ability to system is unstable. But if the area1 is smaller than area2, the
correctly locate and classify the fault. The overcurrent relay system is stable.
should be able to distinguish whether the fault is in its area or Mechanical
not. Third, sensitivity, the overcurrent relays must be able to Power
detect abnormalities which may occur in the system. Fourth,
Pmax
simplicity, the overcurrent relays must be easy to install and E
maintain. Fifth, fast, a fault should be cleared as quickly as
possible in order to maximize safety, minimize equipment Area2
damage and system instability. The overcurrent relay should
quickly arrive at a decision and circuit breakers should Pm A D F
Extremely Inverse (EI) 28.2 0.1217 2 D. Adaptive overcurrent relay considering the CCT scheme
For this paper, the inverse time overcurrent relay To date, there has been much research [1]-[4] on adaptive
characteristic is used in protection the MGS because it has a protection of MGS that are in the island and grid-connected
function that can detect all of faults within CCT for stability of modes. However, this scheme pertains to the improvement of
generation. adaptive overcurrent relays. The overcurrent relay should be
operated properly when the MGS changes, including
C. Crtical clearing time configuration changes, equipment outages, and transient
A power angle diagram is illustrated in Figure 1. The instability. These network changes cause the fault current
initial operating point is A. At the instant the fault is initiated value to change which necessitates adaptation of the operating
the bus voltage collapses. The output power to the infinite bus time of the overcurrent relay to maintain the stability of the
is zero and output power curve is along the x-axis. The generators. This step-wise phenomenon is presented in Figure
operating point shifts to B and the rotor angle continues to 2. The first step defines the operation mode of the MGS. The
increase along the x-axis. At C ( G G cr ) the overcurrent relay second step defines the fault location of the MGS. The third
step varies system configuration such as magnitude of DGs,
clears fault. The pre-fault power angle curve is stored. The magnitude of loads, the magnitude of battery storage and fault
resistance. The fourth step sets the overcurrent relay. The fifth TABLE II. LOAD DETAILS
step takes the operation time of overcurrent relay from the Load1 Load2 Load3 Load4 Load5
fourth step and then checks with the CCT. If the operation Load (MW) 1 0.9 0.9 1 1.3
time of the overcurrent relay is more than the CCT, the system Distance from bus (km) 5 4.2 5.8 5 6
loops back to the fourth step. Connected to Bus1 Bus2 Bus2 Bus2 Bus1
Start
TABLE III. DISTRIBUTED GENERATORS AND BATTERY STORAGE
Define Mode Operation of DETAILS
Microgrid system
Hydro Solar Diesel Battery
Define fault location Source
generator system generator storage
Vary magnitude of DGs Install rated
1.5 MVA 4 MW 7.5 MVA 3 MW
Vary magnitude of Loads capacity
Vary magnitude of Battery
Vary fault resistance 3.3kV/22kV 0.4V/22kV 0.4kV/22kV 0.4V/22kV
Transformer
In step of 25% 2.5 MVA 5 MVA 8MVA 4 MVA
Run initial Distance
Run load flow 1.2 km 4 km 0.2 km 0.2 km
condition from Bus
Run fault Run simulation
Recorded
fault current
Recorded CCT Utility Grids: PEA Grid HOA08 contributes electricity
through AVR1 and AVR2 to bus1. It supplies load 1 and load
No
All case? All case?
No
5. The distance from PEA Grid HOA08 to bus1 is 106km.
Yes Yes
PEA Grid HOA09 contributes electricity through AVR3 and
AVR4 to bus2. It supplies load 2-4. The distance from PEA
Yes
Setting Relay Tripping Time <
CCT ?
Stop Grid HOA09 to bus2 is 106km.
No Switches: Switch1 (SW1) is the main switch used for
connecting bus1 and bus2 when the connection is required
Figure 2. Flow chart of the adaptive overcurrent relay. such as in the island mode or during one of two grid outages.
Switch2 (SW2) and Switch3 (SW3) are used for transferring
The simulation was executed by using DigSILENT electric power. When the system operates normally the
Programming Language (DPL). The calculation of load flow, switches do not function.
short circuit and transient stability were performed.
Relay: Feeders are protected by the overcurrent relays
III. MAE-SARIANG MICROGRID TEST SYSTEM which use the inverse time characteristics. The overcurrent
relays operate according to the fault current.
The MGS (Figure 3) was in the Mae-Sariang area. It is a
22kV distribution system which supplies electric power to the IV. CASE STUDY AND RESULTS
remote area of Mae-Sariang city. The Mae-Sariang Microgrid
System (MSG) was imported from Geographic Information A. Grid-connected mode
System (GIS) to DIgSILENT Power Factory software. It has In grid-connected mode, the system can be divided into
more than 3,800buses and more than 8,000 line sections. It two study cases. In the first case, the system operates
was reduced by a tool function of DIgSILENT Power Factory normally. SW1 is opened, then PEA Grid HOA08 supplies
software, Network Reduction, and then modeled with RTDS the left side of the loads and PEA Grid HOA09 supplies the
to show the stability graph of the generators. right side of the loads. Load 1 and 5 shared electric power
PEA Grid
HOA08
PEA Grid
HOA09
from PEA Grid HOA08. Load 2-4 shared electric power from
DGs and PEA Grid HOA09 (Figure 4).
AVR1 AVR3
51 51 51 51 51 CB CB CB CB
Load1 Load5 Load2 Load3 Load4 Relay Relay Relay Relay Relay
1 MW 1.3 MW 0.9 MW 0.9 MW 1 MW + -
SW2
SW3 AC AC
7.5MVA 4MW 3MW DC
Feeder1 Feeder5 Feeder2 Feeder3 Feeder4 DC
Diesel Gen Solar Battery
which is contributed from only PEA Grid HOA08. These AVR1 AVR3
faults do not affect the CCT because the SW1 is opened. The AVR4
AVR2
fault occurs at the end of the feeder 2-4. The fault current is CB
IV). 51
Relay
51
Relay
51
Relay
51
Relay
51 CB CB
Relay
CB CB
Figure 5 (a) and (b) shows the RTDS capture for a 220ms Feeder1 Feeder5
SW3
Feeder2 Feeder3 Feeder4
AC
DC
AC
DC
(a) 330
In the island mode, if PEA Grid HOA08 and PEA Grid 310
Speed
Speed of
of diesel
diesel generator
generator (rad/sec)
HOA09 are in outage from the system then SW1 must be 360 (rad/sec)
closed and battery storage must be operated (Figure 11). (b) 330
310
According to the island mode, load 1-5 shared electric power 1.0
Fault duration
Figure 13. RTDS event capture for a 250ms three phase fault (a) speed of
AVR4
AVR2
hydro generator (rad/sec) (b) speed of diesel generator (rad/sec)
CB
SW1 2x750 kVA
(c) fault duration.
CB
CB
Hydro Gen
bus1 bus2 CB
51 51 51 51 51 CB CB CB CB
Relay Relay Relay Relay Relay
TABLE IV. FAULT CURRENT AND CCT
SW3
AC AC
Feeder1 Feeder5 Feeder2 Feeder3 Feeder4 DC DC
TD=0.2s
Ipick-up=0.17A 0.053 [s]
0.023 [s]
TD=0.1s
Ipick-up=0.048A
Fault
0.01 current [A]
10 100 1000 10000